Supervisory Control & Data Acquisition System (Scada)
Supervisory Control & Data Acquisition System (Scada)
SYSTEM (SCADA)
History
In 1993 it was determined that a Supervisory Control & Data Acquisition System (SCADA) system was
needed to monitor the campus electrical supply and distribution system. A study was conducted to
determine which SCADA system would be most appropriate for Stanford University Power Systems.
We reviewed other utilities' SCADA and wall Map systems such as PG&E, Palo Alto, Santa Clara and
Berkeley. In addition, we contacted numerous vendors in order to better understand the different
technologies available. Most of the packaged systems involved the purchase of a complete SCADA
system as opposed to the method of using single meters as the basic component. We were aware that
strategically placing these meters both in switch gear at the substations and building switchgear; an
effective instant evaluation could be made regarding the status of the electrical power distribution
system.
In 1994 the Utilities Division started installation of the campus SCADA system using Intelligent
Electronic Devices (IEDs) and a DOS based SCADA software package. The Energy Management
Control Systems (EMCS) group, which is a department in the Utilities Division, also needs data from
building meters. The IEDs provide communications to the SCADA software as well as an analog output
signal (proportional to kW) which is read by the building EMCS. The building EMCS (a Rosemont
system) records this signal to track electrical energy demand and Kilo Watt Hours (KWH).
The SCADA software is a graphical package using a Window NT Operation System. The system,
manufactured by Power Measurement Ltd (PML), provides the programming necessary to incorporate
actual AutoCAD campus maps and diagrams, and to display real time information on top of the graphic
background. Items such as: power system parameters, breakers and switches status, alarms, event logs
& historical data logs; can be overlaid on the AutoCAD Single-Line Diagram.
Additionally, this system allows the Facilities Operations - High Volt Technicians to view the big picture
(a section of campus), and then tunnel down to a detailed view ( a single-line) as needed. SCADA
automatically generates alarms and monthly energy reports and is easily expandable as the needs grow.
The new system is extremely flexible and is completely expandable as IED meters are added.
Benefits
Present Benefits
The University needs have grown and the demands for reliable and accurate performance and trend data
have increased. High Volt Technicians need to be able to remotely and instantaneously, identify
electrical power loop feeder sections that are affected, and respond accordingly. As discussed, when a
particular section of the distribution system goes down, the operators are provided with instant
information. This enables the system operators to provide individual building managers, researchers,
department chairs and others, information on the problem. In addition, the engineers are able to
examine historical data for load trending, planning and improving system performance.
In addition, the following functions are being utilized more and more as the SCADA system is expanded
across campus.
Stanford has already been experimenting with the web based metering and plans to incorporate, and
design custom features with off the shelf web based tools. This will allow users within the university
community to access specific information by using a web browser instead of expensive third party
software (e.g., energy consumption report, performance data, etc...).
Summary
It is considered imperative that Stanford University become fully aware of the disposition of the
Electrical System at all times in order to serve the academic mission with the least amount of
disruptions. Stanford requires accurate real-time alarming and historical information to continually meet
the needs of a diverse community of energy users. We need to prevent outages and other power
problems proactively. We have acquired a solid communications and highly reliable SCADA system.
Fault Location
Prior to 1993, the method used to determine the magnitude of a campus power failure such as which
buildings were affected and what should be first priority to restore power to were determined by a
combination of waiting, hoping, guessing, triangulation and luck.
A triangulation scenario:
A power failure on the campus would usually start with a call being received from Maintenance
Customer Service (MCS) or a building manager stating that a building, ( in some cases a number of
buildings) had lost its electrical power. Not knowing which branch of the circuit had failed; High-Volt
Electricians would wait for a second call identifying another building power outage. Eventually, when a
number of buildings without power were identified, by using a simple method of triangulation could be
used to determine which area of the distributions system had failed. This would be an elaborate
procedure, sometimes taking several hours. High-Volt crews would be dispatched along the route of the
distribution (all of which is underground at Stanford) and would selectively remove vault and manhole
covers, observing the fault indicators on the distribution cables. In time, the cause of these multiple
building power failures were becoming more difficult to locate, consequently, fault location time, and
subsequent restoration time could be several hours. With the installation of SCADA technology, the
excessive time spent investigating faults and problems is reduce substantially.
Outage Record
Post incident analysis is required to prevent reoccurrence of similar outages and power failures.
Power Quality
As needed, generally after an event, or upon query from building users power users power quality
records are requested.
These systems are used for controlling facilities, including regulating valves
to control the supply from a long-haul transmission pipeline to a local
distribution system; starting and stopping compressors along the system; and
controlling valves at major customer installations and city gates. To avoid the
cost of staffing all of these locations, as well as building and maintaining
associated facilities, most organizations rely on automated data gathering and
recording systems.
T/MonXM software on the T/Mon NOC hardware monitors, The T/MonXM interface
mediates, and forwards alarm data in over 25 standard and makes alarm information
proprietary protocols, including legacy equipment no one easy to find and understand.
else can support. View interface screen shots.
• Multiprotocol, multifunction single-platform solution for all remote alarm monitoring applications.
• Collects remote alarm monitoring data from all your equipment, regardless of manufacturer or protocol.
• Supports over 25 protocols: ASCII, DCP, DCPF, DCPX, E2A, SNMP, TABS, TBOS, TL1, and more.
• Supports legacy devices and proprietary protocols from Badger, Cordell, Granger, Larse, NEC, Pulsecom,
and Teltrac.
• Mediate and forward remote alarm monitoring data to different protocols and master of masters.
• Maps remote alarm monitoring data from all your equipment to one consistent interface.
• Plain English alarm descriptions and specific instructions for correcting alarm conditions ensure prompt,
effective response to alarms.
• Displays network status and alarm information to multiple users connected via LAN, dial-up, or serial
connection.
• Automatically sends detailed notifications and instructions to repair technicians by alphanumeric pager, cell
phone, and e-mail.
• Control remote site equipment automatically in response to multiple alarm inputs.
• History, trending, and root cause analysis.
• Centralized database administration for all your remote sites.
Clear
Name:
E-mail:
View past issues
Subscription options
www.dpstele.com | About us | Products | Applications | Services | Support | The Protocol
White Papers | Request Info | Privacy Statement | Site Map | Career Opportunities | Contact us
[ top ]
DPS Telecom · 4955 E. Yale Ave., Fresno, CA 93727-1523
Sales: (800) 693-0351 · Fax: (559) 454-1688 · E-Mail: [email protected]
© Copyright 2004 DPS Telecom. All rights reserved.
Call: 1-800-693-0351
763-424-2613 Forums 800-443-7426
Landfill Remediation Industrial Mining Water & Wastewater Monitoring & Control
is presently in place? How will it change with new
equipment?
13. What are your present costs for inspection,
maintenance and repair? How can it be changed to
be cost-effective? How will it change with a new
SCADA or data acquisition system?
14. If changes are made to the present system, will outside
vendors (telephone company, satellite links, etc.) service change and what are
those changes? (new transmission modes, service charges, etc.)
(Telemetry/Communication Path)
(Protocol-Encoding/Decoding)
1. Will the future system use existing protocol? (If new purchase, do not use
proprietary protocol! You will reduce your options for integrating future
equipment. If possible, use the Modbus protocol.)
2. Is there complete documentation?
3. What existing equipment do you need to connect to?
4. Do you need a multi-vendor software application to communicate with a variety
of manufacturer's equipment?
5. Consider the security issues: What type of protection/safeguards will be needed
and used to keep out hacking, tampering, sabotage and other unauthorized use.
1. Do you need the master station to control local input/output and back up
operations?
2. How many sites and stations does your application require?
3. Will the remote station collect data independent from the master station?
Purchasing Principles