DBR For Peb
DBR For Peb
TABLE OF CONTENTS
b) The PEB VENDOR shall design the building as per the technical requirements
furnished by . Fabrication & erection will be started only after getting approval
on general arrangement drawings from the .
ISSUE
R3
Confidential - External
c) shall review staad file & calculations for correctness as per this Design Basis
Report. The foundation forces furnished by PEB VENDOR shall be used as
it is for design of the foundations. It’s PEB VENDOR’s responsibility to furnish
correct load data to for foundation design. DOR to be agreed between PEB/
. shall review model for clash check.
e) Any approval from will not relieve the PEB VENDOR of his contractual
obligations and his responsibilities for correctness of structural design,
dimensions, materials of construction, weight, quantities, design details,
assembly fits, performance requirements and conformity of the supplies with
the Indian Statutory Laws as may be applicable, nor does it limit the
purchaser’s rights under the contract.
h) It will be PEB VENDOR’s responsibility to give safe and robust design. PEB
VENDOR shall indemnify from all the responsibilities as far as stability and
performance of the PEB structures are concerned.
i) The PEB VENDOR shall issue stability certificate and provide performance
guarantee of all the structures designed, fabricated & erected by them
alongwith 10 years of leak-proof guarantee.
j) Engineering data i.e. Staad file, connections, Base plate designs, Tekla model
and drawings shall be submitted by the PEB VENDOR during the progress of
the work. During erection work, Necessary provision for drinking water and
potable water for the labourers at site to be arranged by the PEB VENDOR.
k) PEB VENDOR should maintain safety, security, and clean-up of the site.
ISSUE
R3
c) Roof shall be standing seam & non-piercing type to support solar panels and
maintenance platform.
d) Roof slope shall be 1:33.33 to horizontal for process block building. For
warehouse and other buildings, slope shall be 1:20 to horizontal.
e) Nylon safety net shall be provided below roof sheeting in all buildings for
construction.
h) One cage ladder & one permanent staircase shall be provided to access the
roof for all buildings (unless noted otherwise in Architectural drawings or as
per Client requirement). Staircase shall be located such that all the roof
elevations are accessed from that staircase. Numbers and location of cage
ladders shall be indicated by in Architectural drawings. Length shall be from
FGL for roof access. The bottom of cage ladder shall be covered with suitable
hinged grill and locking arrangement to avoid direct access to roof. Top of cage
ladder shall have spring shutter with standing platform at junction of roof and
cage ladder.
i) Minimum width of the cage ladder provided shall be 750 mm and the ladder
to be designed for a load of 100 kg. Same paint specification as that of PEB
primary members shall be followed.
j) The colour shade of the cage ladder shall match the sheeting colour shade
and patterns.
m) 4 Nos. of MS templates 6mm thick for each type of column along with
foundation bolts shall be provided by the PEB VENDOR. All primary fasteners
must be fully tightened using torque wrench to specified torque values.
Torquing shall be done as per IS 1367.
n) The supporting frame arrangement for all rolling shutters, doors, windows,
ventilators, exhaust fans etc., including chajja projection (if any) shall be
provided by the PEB VENDOR with necessary fixtures and details as required.
PEB VENDOR shall also provide frame arrangement for automated doors as
required and mentioned in Architectural drawings.
o) For fixing the rolling shutters and doors, the Jamb headers shall be clamped
to plinth beams below using mechanical fasteners. The same shall be in the
scope of PEB VENDOR.
2.2.1. Roofing:
Roofing shall be provided as indicated in the Architectural drawings and as per following
details:
b) Steel solid web portal frame with Single skin roofing, with the insulation,
composed of 0.60 mm Total Coated Thickness (TCT) Plain (Bare) Pre-coated
Galvalume sheeting of min. 345 MPA yield strength, seating above the purlin
members. The sheeting shall be fixed to purlin with “Standing Seam” system.
The roof shall be totally non-pierced type.
c) Performance stimulated test like water leakage test to be done for all
structures by the PEB VENDOR at site after laying the roofing sheet. Water to
be poured on top of sheet through hose pipe to prove that there is no water
leakage.
e) PEB vendor shall furnish cleaning philosophy and methods to ensure safe
cleaning during operation to be in place to ensure no operation gets affected
during cleaning.
a) Vertical cladding / side sheeting to be considered from top of Brick masonry wall (if
provided by others) level up to bottom of gutter at the locations shown
ISSUE
R3
Confidential - External
in the bid drawings. At the brick wall to cladding junction drip/masonry trim or
flashing supplied by the PEB vendor, where the interface between brick wall
and panel is such a way that extended overlapping with brick wall to drain out
water without leakage. This trim will be connected to the brick wall and
sheeting when the gap between them is minimum like below 100mm. Without
any gap it will act as dust proof. If gap is like 200mm or more than that soffit
sheeting to be provided by PEB vendor.
e) Extra 20% framed opening area over and above to that indicated in
Architectural drawings.
a) On grids having rolling shutters (or access location), portal bracings up to rolling
shutter level to be provided and above cross angle bracings can be provided.
c) The vertical bracings shall be of angle, channel members, RHS/ CHS/ SHS only.
d) Wall bracing connections shall be designed for 1.25 times the maximum compression
force in the connecting member.
e) All bracings shall be X type bracings. The use of K bracing shall not be permitted.
f) Angle bracing shall be provided for the roof, wherever required as per design. Rod
bracing shall not be permitted for wall bracing.
h) PEB VENDOR shall plan the bracing bays and shall take approval from on patterns
and location before going for detailed engineering.
ISSUE
R3
Confidential - External
i) At bracing crossing location, the connection shall be such that the slenderness
requirements/ compression capacity and out of plane buckling strength shall
be equivalent/ same as main bracing element.
c) Rainwater down-take pipes, header pipe and Gutter design shall be as per
PEB VENDOR’s standard design. The supporting calculations for the same
shall be submitted during drawing approval to . Galvalume gutters &
Galvalume down take pipes shall be designed and provided for rainfall
intensity of 100mm/hr as per data received from client.
a) Primary built-up & hot-rolled main members: Surface cleaning: Grit blasting to
SA2.5.
Copper slag abrasive shall not be used.
Primer: Zinc rich EPOXY primer (1 x 75 to 100 DFT micron) at SHOP
Intermediate paint: High Build MIO Epoxy intermediate (1 x 175 to 200 DFT micron)
at SHOP
Finish Paint: Aliphatic Acrylic Urethane Finish (1 x 50 to 65 DFT microns) either
at SHOP or SITE.
There shall not be any time lag between shot blasting and application of primer
due to corrosion possibilities. Member shall be immediately painted upon shot
blasting.
c) Secondary members:
Surface cleaning: Mechanical wire brush cleaning. Rust, grease, dust shall be completely
removed. Grit blasting to SA2.5.
Copper slag abrasive shall not be used.
Zinc rich EPOXY primer (1 x 75 to 100 DFT microns) at SHOP
ISSUE
R3
Confidential - External
Intermediate paint: High Build MIO Epoxy intermediate (1 x 175 to 200 DFT micron)
at SHOP
Aliphatic Acrylic Urethane Finish (1 x 50 to 65 DFT microns) either at SHOP or
SITE
Standard Specification for Protective Coatings (Field and Shop Painting) shall be
followed in conjunction with this specification.
d) External finish for roof to have high solar reflecting Index value or white colour.
2.7. Lifeline and its bracket arrangement for all canopy structures shall be provided
by PEB VENDOR. For safety line, PEB VENDOR shall propose the standard
arrangement for approval.
2.8. Permanent handrail shall be considered along the periphery of roof in all
buildings. External staircase shall be provided for each building as shown in
Architectural drawings.
2.9. All monorail beams shall have butt welded splice joints for smooth movement of
wheels from one end to other. Plates and bolts shall not be used for splice
joints for Monorail beams. Location & Load details of EOT cranes/monorails
shall be provided in bid-purpose drawings.
Sr.
Code No. Title
No.
2 IS:1893-2016
(Part-I) Criteria for Earthquake resistant Design of Structures.
IS:1893-2024
Seismic Provisions for Structural Steel Buildings
(Part-IV)
IS800:2007Section
12
Code of Practice for design loads (other than
3 IS: 875-Part-I Earthquake) for buildings and structures - Unit weights
of Building materials and stored materials.
Code of Practice for design loads (other than
4 IS: 875-Part-II Earthquake) for buildings and structures- Imposed
Loads
Code of Practice for design loads (other than
5 IS: 875-Part-III
Earthquake) for buildings and structures- Wind Load.
ISSUE
R3
Confidential - External
Sr.
Code No. Title
No.
Code of Practice for design loads (other than
6 IS: 875- Part-V Earthquake) for buildings and structures P5- Special
Loads and Combination.
Code of Practice for Design and Construction of
7 IS: 1904 Foundations in Soils- General Requirement.
8 SP: 38 Handbook – Typified Designs for Structural Steel Roof
Handbook on Structures with Steel Portal Frames
9 SP: 40 (without Cranes)
Applicable codes and Standards for materials
3.2.1. Structural designs for the steel members shall be based on Limit state method as
per IS:800-2007. The PEB Contractor may adopt working stress method for
ISSUE
R3
Confidential - External
3.2.2. The structural members shall be either classified as compact, plastic or semi
compact as per IS: 800-2007, in no case “Slender members” shall be
permitted for any primary or secondary members. Only Purlin and cladding
runners will be of cold formed “slender” sections.
3.2.3. Chapter 12 of IS: 800-2007 shall be followed without any deviation for design and
detailing for earthquake loads.
3.2.4. Design of cold form section shall confirm to IS: 801 unless noted.
3.3. LOADS
Solar panel Load: Solar Panel load of 20 kg/m2 shall be considered for
C design of total roof area as per standard practice. The solar panel load
is considered as part of live load as per standard practice.
ISSUE
R3
Confidential - External
PEB VENDOR shall consider Fire hydrant pipe supports along the
peripheral columns for all buildings. Bracket projections from column,
bracings as well as supporting member between two brackets
throughout length shall be considered.
Live load shall be the maximum load expected by the intended use or occupancy
and consists of the following loads:
• Persons, portable machinery and tools
• Materials temporarily stored during maintenance such as moulds, finished goods, raw
material, and scrap material.
• Materials normally stored during operation.
• Moving or standby vehicles.
Live loads shall be uniformly distributed/ concentrically applied over the
horizontal projection of the specified area. Distributed live load is applied to all
areas except directly under equipment. Collateral load accounts for piping and
miscellaneous utilities and is applied to all the areas.
Following live loads shall be the minimum considered in structural design as specified
in IS: 875 (Part 2) unless noted otherwise.
Note 1: Loading to be considered for arrangement for maintenance (cleaning +safety
measures).
Note 2: Manual/Guideline for maintenance shall be specified by PEB vendor and
approved by consultant.
Table-6:
Loading Area
Minimum Load Intensity (kN/m2)
For Sloping Roof with slope For roof membrane sheets or purlins-
greater than 10 degrees 0.75 kN/m2 less 0.02 kN/m2 for every
ISSUE
R3
Confidential - External
Loading Area
Minimum Load Intensity (kN/m2)
Staircase 4.0
Maintenance Bays, Compressor
House 7.5
ISSUE
R3
Confidential - External
Table-7:
Vb = 39 m/sec -
Basic Wind speed at 10m
height for Ahmedabad
Vz = k1*k2*k3*k4*Vb m/sec Clause 6.3
Design Wind Speed at any
height:
Table 1
Where; k1 = Probability factor = 1.00 (Mean probable life of
structure 50 years)
Terrain category:
All the structures fall under category – 2 type of terrain (Open terrain with well
scattered obstructions having heights generally between 1.5 to 10m).
To calculate the value of k2, table – 2 of IS: 875 Part 3 shall be referred
considering terrain category – 2.
Note – As per IS:875 (Part 3), pressure for buildings less than 10m high shall
be reduced by 20% for evaluation stability and design of the framing.
Design Wind Pressure at any Maximum of, N/m2 Clause 7.2
height
1. pd=
Kd.Ka.Kc.pz,
2. pd= 0.70
pz
Where; Kd = Wind Directionality factor Clause 7.2.1
ISSUE
R3
Confidential - External
SEISMIC PARAMETERS:
Seismic design forces shall be determined based upon the following parameters.
Item Value Reference
ANNEX – E
Seismic Zone
Zone – III (IS 1893-Part 1)
Zone Factor Table – 13
(Z) 0.16 (IS 1893-Part 1)
Table 3
Importance 1.50 for structures in category 2 (IS 1893-Part
Factor “I”
1.20 for structures in category 3 42024)
5% Damping shall be considered for Reinforced
Concrete Structures and 2% Damping shall be Table 2
considered for Steel structure, irrespective of (IS 1893–Part
Method of Analysis (i.e. Equivalent Static Method or 42024)
Dynamic Analysis Method)
Damping
Response 5 - Steel structures with special moment resisting Table 4
reduction frame (SMRF) (IS 1893-Part
factor (R) 42024)
ISSUE
R3
Confidential - External
ISSUE
R3
Confidential - External
(Part 1) shall be considered while calculating nodal masses. Imposed load on the
roof shall not be accounted in the calculation of nodal masses.
Resulting torsion effect due to eccentricity between centre of mass and centre of
rigidity will be considered in design as per IS 1893, clause no 7.8.
Structures / equipment’s shall be classified into the four categories as per clause 8.1,
IS 1893 (Part-4):2024.
Typical categorization of industrial structure for the project is as given below,
for other structures refer table-6 of IS 1893 (Part-4):2024 Category- 2:
• FG Warehouse,
• Block 1
• Raw Material Warehouse
• Block 2
• Utility Building
Category- 3:
• Parking shed (2-wheeler and 4-wheeler)
Horizontal acceleration values of the spectra are obtained from IS: 1893 Part
4:2024.
The horizontal seismic co-efficient Ah = (Z/2) *(I/R) *(Sa/g)
Seismic parameters Z, I, R and Sa/g are obtained as per table below.
Vertical acceleration values are to be taken as 2/3 of the corresponding horizontal
acceleration values (Clause 6.4.6 of IS: 1893 Part-1).
The seismic weight of building includes all permanent and rigidly attached
structural and non-structural components of a building, such as walls, floors,
roofs, cladding, piping, duct load, cable tray load, total weight of permanent
equipment, utility weight of permanent equipment, normal operating weight of
contents in vessels and pipe etc.
The contribution of live load to be considered in the seismic weight calculation
shall be taken as per the Clause 7.3.1 and as specified in Table – 10 of IS
1893 (Part 1).
Imposed Uniformly Distributed Floor loads
Percentage of Imposed load
(kN/m2)
ISSUE
R3
Confidential - External
Response spectrum method shall be applied for seismic analysis. Following are
the steps involved in Response Spectrum Method:
Number of modes to be used in the analysis for the earthquake shaking along
a considered direction, shall be such that the sum total of modal masses of
these modes considered is at least 90% of the total seismic mass.
The peak response quantities shall be combined as per Complete Quadratic Combination
(CQC) method.
Since lateral load resisting elements are oriented along two mutually
orthogonal horizontal directions, the structures shall be designed for two
component earthquakes (One horizontal and vertical). For Horizontal
earthquake load, structure shall be designed for the effects due to full design
earthquake load in one horizontal direction at a time, and not in both directions
simultaneously. When lateral load resisting elements are not oriented along
mutually orthogonal horizontal directions, Structure shall be designed as per
Clause No.6.3.2.2. IS 1893 Part.1.
Effect due to vertical earthquake shaking shall be considered as per clause
No. 6.3.3.1 IS 1893 (Part 1); the design vertical force shall be calculated for
vertical ground motion as detailed in clause No. 6.4.6 IS 1893 (Part 1).
When both horizontal and vertical seismic forces are considered, load combination
specified in Clause No.6.3.4 IS 1893 (Part 1) shall be considered.
When response from the three earthquake components are to be considered
(three directional earthquake ground shaking), the response due to each
component may be combined using the assumption that when maximum
response from one component occurs, the responses from other two
components are 30% each of their maximum. All possible combinations of
three components including variations in sign shall be considered. Refer
clause no. 6.3.4.1 IS 1893 (Part 1) for set of combinations of earthquake load
effect.
ISSUE
R3
Confidential - External
The storey drifts in any storey due to the minimum specified design lateral
force, with partial load factor of 1.0 shall not exceed 0.004 times the storey
height as per IS 1893 (Part 1), clause no. 7.11.1.
This shall mean the weight of equipment during erection and exclude the
weight of internal fluids, solids within equipment, platforms, insulation and
piping attached to the equipment. Equipment empty load shall be considered
as per the details provided by the equipment manufacturer.
This shall mean the weight of equipment during normal operating conditions
including the weight of internal fluids, solids within equipment and all materials
permanently attached to the equipment such as platforms, piping and
insulation.
This shall mean the weight of equipment, piping during hydrostatic testing after
erection / installation including the weight of water within the equipment piping
and all materials permanently attached to equipment such as platforms,
insulations and piping. Equipment test load shall be considered as per the
equipment manufacturer’s data.
All equipment foundations & supporting structures shall be designed for
Hydrotest loads. Hydro-test shall be considered for one equipment at a time.
Further, under hydro-test condition the wind force shall be taken as 25% of
normal wind loading. Seismic forces shall not be considered while hydro-
testing.
ISSUE
R3
Confidential - External
Handling device loads shall mean the loads of Cranes, hoists and lifts including the
lifted weight in the normal operation.
Handling device loads shall be increased with the following percentages to include
adequate allowance for the following impact conditions.
Monorails
Transverse Load : 15% of the lifted load.
Longitudinal Load : 7.5% of the lifted load hoist and trolley
i. Lateral Surge: For design of columns and foundations, supporting crane girders, the
following crane combinations shall be considered:
• For single-bay frames: Effect of one crane in the bay giving the worst effect shall be
considered for calculation of surge force; and
• For multi-bay frames: Effect of two cranes working on each in any of two bays in the
cross-section to give the worst effect shall be considered for calculation of surge
force.
• Where one crane is in operation with no provision for future crane, tractive force from
only one crane shall be taken.
ISSUE
R3
Confidential - External
ISSUE
R3
Confidential - External
ISSUE
R3
Confidential - External
4. MATERIAL SPECIFICATIONS
ii) Unbraced length parameters in STAAD Pro (Lz, Ly, Lx, UNT, UNB, UNL)
parameters of members shall be assigned, such that the entire length of
member shall be assigned with maximum unbraced length, between 2
maximum spaced lateral restraints. Same member shall not have
different unbraced length parameters.
iii) Flanges of mezzanine beams, mezzanine joists, main frame side wall
and interior columns and jack beams shall have minimum web thickness
of 6 mm.
iv) Minimum flange width of all columns, interior rafters, jack beams,
mezzanine beams and joists shall be 150mm.
ISSUE
R3
Confidential - External
v) All built up members shall be symmetrical, i.e. top flange width and thickness
shall be equal to bottom flange width and thickness respectively. Different
sizing shall not be used.
vi) Spacing of mezzanine joists shall be maximum 2m. First and last bays of
mezzanine joists shall have maximum 1.8m spacing.
vii) Maximum butt weld joints in built members shall be as follows:
a. Up to 6m length: No butt weld joint permitted. Member shall be single
piece.
b. 6m to 12m length: 1 No. butt weld joint permitted.
c. For additional butt weld joint requirement for any specific reason, PEB
vendor shall seek approval consultant.
d. Flanges to be welded to web with continuous welding (SAW) on both
sides of web and all the joints of seismic resistant frames (Special
concentric braced frames, Special moment frames) shall have CJP
weld. Welding thickness and type shall be as per the welding
specifications given in AWS.
ix) For columns supporting jack beams / jack portals, lateral restraint of girts
shall not be assumed. Such members shall be designed for minimum
unbraced length of 0.5 times total length of member, with appropriate
restraint provision of cross bracing and strut arrangement as per the
unbraced length of member.
ISSUE
R3
Confidential - External
ii. Flange braces minimum thickness shall be 4mm thick for columns and
2.5m thick for rafters.
iii. Flange braces used to stabilize the inner compression flanges of jack
beam shall be minimum 75 x 75 x 6 mm steel angles, conforming to IS
808 (or equivalent) as per Point No. 4 of this document.
iv. For galvanized flange braces minimum Coating of GI shall be 275 GSM.
4.7. WALL, ROOF FLASHING & TRIMS, EAVES GUTTERS & DOWNSPOUTS
Made of cold-formed steel matching with wall sheeting (in colour & finish)
including ridge cap. The length of the rainwater down takes, to be provided by
the PEB Contractor shall be up to the storm water chambers as shown in the
drawings.
ii. All portal bracing shall be straight and shall not be tapered.
iii. In case of portal columns supporting mezzanine loads, portal columns shall
be continued up to base plate with full base plates to these columns. At
other locations, portal columns may be stopped above the base plate or
continued up to base plate depending on design requirement.
ISSUE
R3
Confidential - External
vi. Mill certificates for the sections to be used shall be submitted and approved by the
consultant.
5. OTHER CRITERIA
5.3. Sheeting, purlins, sag rods, side girts, etc. shall not to be considered as structural
members for providing any lateral stiffness or stability of the structure.
5.4. Grade slab shall not be considered for resisting horizontal forces.
5.5. Welding shall be one side continuous and stitch welding on the other side for full length
of the member. Continuous welding shall be followed for full length of the splice joints.
5.6. No welding at site shall be allowed.
5.7. No hollow section shall be used unless access is available for maintenance and painting.
5.8. Deflection criteria shall be as per code or maximum permissible from crane loading/
operation whichever is more stringent.
5.11. The roof sheeting shall be provided in a manner, which prevents ingress of rainwater.
BIS norms shall be followed. Generally, two corrugations to be overlapped for sides and
overlap of 200 mm or as per the roofing system requirement, whichever is more, for
longitudinal direction (i.e., along the length). Silicon sealant tape to be provided for all
joints with self-tapping screws/ rivets.
5.12. Unless noted otherwise Translucent sheets of minimum 1.5mm thickness FRP sheet
shall be provided over the area of 10 % of the roof sheeting for each building. The joint
between translucent sheet and Galvalume sheets shall be sealed with sealant properly to
make it watertight. The necessary flashing and other accessories compatible to the
translucent sheet material shall be provided.
ISSUE
R3
Confidential - External
5.13. Provision of flashings, trims, neoprene gaskets, silicone/ butyl sealants, etc. shall
be ensured.
6.1. Primary members: Primary structural framing shall include the transverse rigid
frames, lean-to-rafters and columns, canopy rafters, interior columns (beams and
column frames), bearing frame rafters and corner columns and end-wall wind
columns.
6.2. Secondary members: Secondary structural framing shall include the purlins, girts
eave struts, wind bracing, flange bracing, base angles, clips, and other
miscellaneous structural parts.
6.3. Anchor bolts: All anchor bolts and anchor bolt assemblies shall be designed,
detailed, approvals obtained from CONSULTANT, supplied, and transported to
site (for erection and grouting by others) including threading, provision of nuts,
locknuts, washers, pie sleeves, etc. all as per specifications and approved
fabrication drawings. All anchor bolts and anchor bolt assemblies shall conform
to IS: 2062/ IS: 1367. The grade of reinforced cement concrete for placing the
anchor bolts shall be M30 with 20 mm downgraded aggregates.
6.4. Connections: All field connections shall be bolted (Unless otherwise noted).
Primary bolted connections shall be furnished with high strength bolts confirming
to the physical specifications of ASTM A325 (or equivalent). Secondary bolted
connections shall be furnished with machine bolts conforming to the physical
specifications of ASTM A307 (or equivalent).
6.5. For the auxiliary supports like duct supports, cabling supports, which are not in
the scope of the PEB contractor as explicitly defined, provision of pre-defined
bolted connections and / or site welded end connections shall be made.
7. OTHER ACCESSORIES
7.1. Gutters (min. size of gutter 200m (W) x 250 mm (D)): The eaves and valley
gutters shall be made from 16-gauge plain galvalume sheeting material or
approved equivalent of same colour and shade as the roof and side sheeting
including dead ends, nozzles, clamps, etc. complete as per specifications and
approved drawings.
7.2. Rain Water Down takes: The rain water down takes shall be made from 16 gauge
plain galvalume sheeting material or approved equivalent of same colour and
shade as side sheeting having pressure rating of 4 kg/cm2 with suitable clamps
on outside of the side sheeting with spacers including necessary bends, off sets
and junctions, vents and dome all as per specifications and approved drawings
complete with joints perfectly water tight including necessary scaffolding, etc.
complete as directed.
7.3. Rainwater collector box / spout shall have grating on top to avoid chocking.
ISSUE
R3