Integration of Planning Analysis Design
Integration of Planning Analysis Design
Integration of Planning Analysis Design
Building Information Modeling (BIM) is a powerful digital The primary objective of this study is to assess the
tool that has revolutionized the construction industry. BIM application of BIM technology in the design and construction
enables the integration of planning, analysis, design, of a multispeciality hospital. We aim to demonstrate how the
estimation, and scheduling processes into a unified digital use of BIM tools can enable accurate planning, analysis, and
model, resulting in improved collaboration and estimation of quantities and scheduling of construction
communication among stakeholders. In this study, we activities.
explore the application of BIM technology in the design and
construction of a multispeciality hospital project. This
2. LITERATURE REVIEW
project utilized a combination of software technologies, V. J. Saran and S. S. Pimplikar examined BIM technology has
including AutoCAD, Revit, STAAD.Pro, RCDC, and MS Project, the potential to revolutionize the healthcare infrastructure
to enable accurate project planning and analysis. planning process, including design, construction, and facilities
management. The authors hypothesize that BIM can facilitate
1.1 Problem Statement:
accurate planning, analysis, and estimation of quantities and
Healthcare facilities are critical for providing medical scheduling of construction activities, leading to improved
services to the community, but the design and construction of collaboration among project stakeholders and more efficient
such facilities often face challenges related to accuracy, project management, as well as reducing the risk of time and
collaboration, and efficiency.
© 2023, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1126
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 04 | Apr 2023 www.irjet.net p-ISSN: 2395-0072
cost overruns through accurate estimation of quantities and g) Floor space Hospital beds (General) = 15 to 18 sq. m
scheduling of construction activities. per bed
S. Alomari and M. Al-Qawasmi., in his study, observed the h) Beds space = 7 sq. m per bed
implementation of BIM technology in hospital design and i) Minimum distance between centers of two beds = 2.5 m
construction can bring significant benefits, including (minimum)
improved project efficiency and productivity, better
collaboration among project stakeholders, and enhanced j) Clearance at foot end of each bed = 1.2 m (minimum)
decision-making. The authors also aim to explore the 2) Tamil Nadu Combined Development and Building Rules
challenges and limitations of BIM technology in this context,
and provide insights on how to overcome them a) The height of room in a structure other than domestic
residency should not be lower than3.00 m handed, in the case
Sankar F. Alarcon etal., deals with BIM adoption in healthcare of air- conditioned apartments it shall not be lower than 2.5
construction can result in improved project management, m.
design quality, and cost and time performance. The article b) The height of restroom or potty shall be not lower
also suggests that there are several challenges to BIM than2.20 m.
implementation in healthcare, such as stakeholder
engagement, data management, and standardization, which c) Any structure having further than four bottoms
need to be addressed to achieve successful BIM adoption including basement or sunken bottoms, shall have at least
two staircases, one of which may be an external stairway
A. Srikanth et al in his studies, main purpose of our design is
d) The minimal range of stair shall be not lower than1.20
satisfying the medical requirements of people. In this design
m
we concerned about the plan, analysis and design of
Multispeciality institutional structure. The plan of the e) The minimal range of tread shall be 30 cm.
institutional structure is done by using AUTO CADD software.
f) The height of platform shall not exceed 15 cm.
The analysis of structures was done by using E-tabs as well as
IS 456 (2000). The design of RCC element is grounded on g) The height of rail shall be not lower than 90 cm
limit state system as per IS 456 (2000).
h) The range of fire escape staircase shall be not lower
3. DATA COLLECTION than 75 cm.
i) The range of fire escape stair tread shall be not lower
1) Compendium of Norms for Designing of Hospitals & than 15 cm.
Medical Institutions – CPWD
j) The height of the fire escape stair platform shall not
a) Land Area exceed 19 cm.
Minimum Land area requirement are as follows: k) The height of rail of a fire escape staircase shall not be
Up to 100 beds = 0.25 to 0.5 hectare lower than 100cms
500 beds and above= 6.5 hectare (4.5 hectare for hospital Nursing area 19 – 25 m2
and 2 hectares for residential) Intensive therapy 30 – 50 m2
b) Size of hospital as per number of Beds Surgical area 130 – 160 m2
General Hospital – 80 to 85 sq. M per bed to calculate total X- ray 60 – 70 m2
plinth area
Recovery area 25 – 30 m2
Teaching Hospital - 100 to 110 sq. M per bed to calculate
total plinth Patient room minimum 10 m2 for single bed and 16 m2
for double bed
c) ICU beds = 5 to 10 % of total beds
Doctor’s station 16 – 20 m2
d) Floor space for each ICU bed = 25 to 30 sq. m (this
includes support 4 services) Eye treatment minimum 25 m2
e) Floor space for Pediatric ICU beds = 10 to 12 sq. m per Ear Nose and Throat (ENT) 25 – 30 m2
bed
f) Floor space for High Dependency Unit (HDU) = 20 to 24
sq. m per bed
© 2023, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1127
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1128
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
Table -1: Site and Building Specification Building dimension across wind direction (b) = 65.00 m
Height of the building above ground (h) = 16.5m
Total site area 11,400m2
a/b = 1.78
Total plinth area 5,600m2
h/b = 0.25
Total build up area 11,303m2
Wind Load in X-Direction
No. of storyes G+3
Cf = 1.15
No. of typical floor 2
Wind Speed, Vz = Vb x k1 x k2 x k3 x k4 = 45.7639 m/s
Floor height 3.6meter
Wind Pressure, Pz = 0.6Vz2 = 1.257(KN/m2)
Main corridor spacing 3.5meter
Secondary corridor spacing 2.5meter Wind Load in Z-Direction
Cf = 1.30
5. STRUCTURAL ANALYSIS Wind Speed, Vz = Vb x k1 x k2 x k3 x k4 = 45.7639m/s
Wind Load
Wind load was determined by using code for design
loads (IS 875:2000 Part 2) for various height of the
building
Vb = 47 m/s, K1 = 1.07, K3 = 1, K4 = 1, Kd = 0.9, Ka = 0.9,
Kc = 0.9 and Terrain Category = 3
Building dimension along wind direction (a) = 116.00 m Fig -5: Shear Force Along Y-Axis
(Beam No. 1921)
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1129
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
Element Specification
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1130
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1131
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
General Data
Wall No. : C83
Level : 0m to 3.3m
Grade of Concrete = M25
Grade of Steel = Fe550
Wall B = 200 mm
Wall D = 3600 mm Fig -11: Shear Wall Cross Section (C83)
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1132
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
Design Data
Footing No : FC128
Concrete Grade : M25
Steel Grade : Fe550
Clear Cover : 50 mm
Column No : C128 (600mm x 300mm)
Footing size (L x B x D) : 1850 X 1550 X 550 (mm)
Bottom @ L : T12@145
Bottom @ B : T10@100 Fig -14: footing Qty. take off
7. ESTIMATION
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1133
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
Table -3 Site Summary of Estimation results of a scheduling performed using Microsoft (MS)
Project, one of the most widely used tools in the construction
Name of Work: Civil works for Proposed Development of industry.
Multispeciality Hospital at Thanjavur
Table -4 Scheduling of work
SUMMARY
S.No. Description Cost in Rs. S.No Task Name Duration
01 General Conditions 17 days
A SOR ITEMS
02 Long Lead Procurement 70 days
1 Civil Works 104658235 03 Mobilize on Site 10 days
04 Site Grading and Utilities 35 days
2 Plumbing 05 Foundations 33 days
Water supply system + Sewer 06 Steel Erection 45 days
a) 10465823.50 07 Form and Pour Concrete - Floors and
system (10%) 85 days
Roof
b) Medical gas pipe line (20%) 20931647.00 08 Carpentry Work 15 days
Sub total for Plumbing system 31397470.50 09 Masonry Work 110 days
10 Roofing 31 days
3 Electrical work (10%) 10465823.50 11 Window wall and store front closures 60 days
Sub total for SOR Items 177918999.50 12 Building Finishes 80 days
13 Elevators 40 days
B Non -SOR ITEMS 14 Plumbing 90 days
15 Electrical 139 days
4 HVAC System (15%) 15698735.25
16 Heating and Ventilating - AC 180 days
5 Fire Fighting System (5%) 5232911.75 17 Final Clean-up and Occupancy 60 days
18 Complete Final Inspections 6 days
6 Escalators (6 x Rs.1804000) 10824000.00
19 Complete punch list items from all
2 wks.
Architectural Facade work inspections
7 62794941.00 20 Obtain certificate of occupancy 2 days
(6%)
21 Issue final completion documents
Sub total for Non SOR Items 94550588.00 1 day
including warranties
Total Cost (A +B) 272469587.50 22 Issue final request for payment 1 day
23 Multispecialty hospital 17 days
Provision for GST @ 12% 32696350.5 Total Duration 344 days
TOTAL 305165938.00
9. IDENTIFICATION AND RECTIFICATION OF
Provision for Labour welfare
fund TNMWF@1%
3051659.38 ERRORS
Provision for Centage @ 2% 6103318.76 During the planning stage, we discovered that the
Provision for Contingencies initial layout of the hospital had inadequate space for certain
6103318.76
(2%) departments, which would have resulted in operational
issues in the future. Using BIM software like Revit, we were
GRAND TOTAL 320424234.90
able to modify the layout and adjust the spaces to meet the
GRAND TOTAL (Rs in Lakhs) 3204.24 required specifications. We also found errors in the
GRAND TOTAL (Rs in Cr) 32.04
structural design during the analysis phase, which we
rectified using software like STAAD Pro and RCDC. The use
COST per sq.ft 2308 of these software tools allowed us to detect errors in the
structural design, such as weak points in the building
structure, and make necessary corrections to ensure that the
8. SCHEDULING
building was structurally sound. Overall, the use of BIM
technology helped us detect and rectify errors at various
Scheduling is an essential aspect of construction stages of the project, which contributed to the success of the
project management, and plays a critical role in ensuring the project and reduced the likelihood of future issues.
successful completion of construction projects. By providing
a clear and concise overview of the project timeline,
10. RESULT AND DISCUSSION
scheduling helps to coordinate and control the various
activities and tasks involved in a construction project, and
provides a framework for risk management, cost control, and The integration of various software such as AutoCAD, Revit,
quality control and resources allocation. we present the STAAD Pro, RCDC, and MS Project in the design of a
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1134
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
multispeciality hospital using BIM technology has proven to budget, and to the required quality standards. They also help
be highly beneficial for civil engineers. This method allows to reduce the risk of human error, improve the overall
for accurate planning, analysis, design, estimation, and quality of the design, and facilitate the integration of various
scheduling of construction activities, resulting in a more design aspects such as cost estimating, scheduling, and
efficient and cost-effective project. The collaboration of resource allocation.
different software ensures that the project is designed and
executed seamlessly, with no room for errors or It is therefore advisable for civil engineers to continually
discrepancies. BIM technology enables real-time updates and update their knowledge and skills in this area to stay at the
changes to be made, which is crucial in construction projects forefront of their field
where time and accuracy are of utmost importance. Overall,
the integration of various software using BIM technology has ACKNOWLEDGEMENT
proved to be an indispensable tool for civil engineers in the
design and construction of large-scale projects such as We render our sincere thanks and respectful gratitude to our
multispeciality hospitals The integration of planning, Supervisor Dr.V.A.Shanmugavelu, M.E., Ph.D., Associate
analysis, design, estimation, and scheduling through BIM Professor, Department of Civil Engineering for providing
technology can save a lot of time and effort. The use of valuable guidance.
software like AutoCAD, Revit, STAAD Pro, RCDC, and MS
Project can simplify the design process and provide a We would like to extend our special thanks to all the staff
platform for collaboration and communication between members of the Department of Civil Engineering and
different teams involved in the project. With the help of BIM Technicians who are always available when we need
technology, it is easier to detect errors and inconsistencies in technical assistance.
the design, which can be rectified before the construction
process begins, saving time and money. The ability to we deeply thank our parents and family member for their
visualize the project in 3D models allows for better unconditional trust and timely encouragement throughout
communication with clients, stakeholders, and contractors, our study.
reducing the likelihood of misunderstandings and mistakes.
REFERENCES
11. CONCLUSIONS [4] Code of Practice for Design Loads (Other Than
Earthquake) For Buildings and Structures IS-875-1987.
In conclusion, the use of software techniques in civil
engineering design projects is increasingly becoming [5] National Building Code 2005 – 2015
essential in today's rapidly evolving technological landscape.
Software such as STAAD Pro, RCDC, and Revit offer [6] Neufert Architects' Data Fourth Edition - 2014
numerous benefits to civil engineers, including improved
[7] Dr. Ramachandra, Limit State Design of Reinforced
accuracy, efficiency, and consistency in design and analysis.
These tools also allow engineers to perform complex [8] Concrete'.
calculations and simulations, visualize the behavior of
structures under different loading conditions, and [9] B.C. Punmia, Ashok Kumar Jain, Arun Kumar
collaborate more effectively with other stakeholders.
[10] Jain,R.C.C.Design',Lakshmi Publisher, New Delhi.
Furthermore, software techniques provide a more
streamlined and effective approach to project management, [11] N.Krishna raju, Ramaamurtham & N.N.Narayanan,
helping to ensure that projects are completed on time, within Design of R.C.C structures.
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1135
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1136