How To Scope and Plan A Project
How To Scope and Plan A Project
This booklet is a companion to the Project Managers Manual and to the Project Plan Template. It describes a five step approach to scoping and planning a project. If you follow these five steps they will generate a viable plan for the project and the information you need to complete the Project Plan Template included in the e-learning support tool How to Manage a Project.
Introduction
A Project Scoping Study gives the project manager the opportunity to look at and assess the project before it becomes formally "live". Not so much to query whether the project should go ahead but to establish how it needs to be organised and managed, specifically: what the project aims and objectives should be what the risks and possible difficulties are, how the project should be organised and tackled.
Such a study may take only a week or may take several months depending on the size of the project. Usually it is based around discussions with key stakeholders (those with a vested interest in the project) and potential team members and contributors. The findings and conclusions are summarised in a Project Plan. If a team is involved in the project, it is invariably best to scope a project as a team. This booklet describes a five step approach to scoping and planning a project. If you follow these five steps they will generate a viable plan for the project and the information you need to complete the Project Plan Template included in the e-learning support tool How to Manage a Project.
Contents
Introduction The Five Step Approach to Scoping Step 1: Step 2: Step 3: Step 4: Step 5: Project Objectives and Terms of Reference Project Benefits & Costs Top-Level Plan Project Organisation Implementation Issues & Risks
Page
2 3 4 5 7 10 11
Page 2 of 10
Page 3 of 10
This provides an overall description of the project, often with some background and reference to time and cost constraints, together with a statement for each of the key stakeholders summarising what the project will aim to deliver to each of them. We suggest the following two-stage process: 1. Stakeholder Analysis Carry out a review of the various stakeholders of the project (those with a vested interest in the project and its outcomes) and establish the criteria (four or five) by which they will assess the success of the project. We have provided a worked example of such an analysis overleaf. Develop Project Terms of Reference The development of terms of reference to satisfy those criteria. Best with an overall definition and description of the project and its aims (possibly including cost, time and quality) supported by project objective for each of the major stakeholders. When agreed with the Sponsor, this then forms the terms of reference.
2.
Page 4 of 10
Project Management skills Personal & Career Development Interesting, Practical, Relevant Training Confidence
IT Unit
Projects easier to start-up & establish Better Project Delivery House Style & clarity of roles Project Sponsors
Good Training Course Coherence with other training Contributes to Leading Edge Portfolio
H.R. Unit
Better management of Projects Satisfy Modernising Government House Style for Project Mgt.
Top Management
Note:
The above analysis provided the information we needed to create the example terms of reference shown on the previous page. We find this approach provides the best balance between on the one hand taking account of conflicting requirements and on the other having a clear project focus. It needs to be done during the initial scoping study (perhaps updated later) and is best done with the project team, possibly supplemented by key stakeholder representatives. This not only creates better terms of reference but is also excellent team-building. The resulting terms of reference then provide an excellent basis for the project plan and for discussions/negotiations with the Project Sponsor and possibly certain key stakeholders.
Page 5 of 10
Main Costs
Page 6 of 10
Each technique has its strengths and weaknesses and you need to select the technique most suited to your particular project. Each is illustrated on the following pages.
Planning Sheet
Activity Date Activity can Start Date Activity must Finish by Estimated Duration People and Resources involved Estimated cost in time or resources
Page 7 of 10
Stages Plan
2 wks 1 wk 3 wks 2 wks 10 wks
Initial Survey
Outline Design
Detailed Design
Pilots
Outline Proposal
Programme Delivered
Cook Spaghetti 5 0 5 5 4 15 9
Drain Spaghetti 15 18 18 3 21
Get Ingredients 0 5
Complete Sauce 15 18
Page 8 of 10
Gantt Chart
May June July Aug Sep Oct Nov Dec Jan
Senior Mgt Preparation Train Steering Group Visit other organisations Staff Climate Survey Train other Managers Awareness Training for all Staff Train Facilitators First 10 QATs Customer Surveys
Holidays
April
May
June
July
Aug
Sep
Oct
Nov
Dec
Jan
Page 9 of 10
Sponsor
User(s)
Project Manage
Team
Critical Contributors
Key Points
Of these roles, the key ones are clearly those of Sponsor and Project Manager. Each project should have a named Project Manager who is the focal point of the project, and a named Project Sponsor who sponsors the project on behalf of the organisation. The sponsor may be an individual or a group perhaps a steering group or a project board. Functions of the Project Sponsor include: To support the Project Manager when needed (resources, blockages, etc) To try protect the project from undue extraneous influences To forewarn the Project Manager on relevant changes elsewhere in the organisation or other projects To sell the project into the strategic arena and the rest of the organisation To take key information about the project into the rest of the organisation
Page 10 of 10
Hi-Lo Diagram
High
Watch these
Impact On Project
?
Priority items How can we reduce the likelihood of them happening, or lessen their impact if they do happen?
Watch these
High
Page 11 of 10