Procedure For Store
Procedure For Store
PURPOSE To Manage Incoming & Outgoing store procedure and inventory control.
Turtle Diagram
INPUTS OUTPUTS
Yes
Start
Import,RM,BOP,Packing,consumble, Service
spare & Job work Item.
Requistion Communication
Reciept from Confirmation
FIFO with supplier by
user Done
QA
department
RISK MATRIX:
RISK IMPACT CONTROL REFERENCE IN PFD
OPPORTUNITY MATRIX:
OPPORTUNITY BENEFIT CONTROL REFERENCE IN PFD
PERFORMANCE INDICATORS :
Category
(Customer, Source
Standards, Legal, References Description of requirements PFD Cell Reference
Internal)
REFERENCE DOCUMENTED INFORMATION:
Verification sheet of
QSD-STR-06 Perishable/Shelf life item
- Store In-charge Manual
Process Name Production Management
No
Document Ref
Rev No./ Date
n Management Page No 4
Documented
Process Description Additional Informations Output Responsibility Method/Criteria
information reference
Start
Receipt of Mateerial on Gate,
Verify with Invoice/Challan as
Approval - Supplier List per Purchase orderceipt of
Mateerial on Gate, Verify with Invoice/Challan as
1 (RM,BOP,CONSUMBLE, SPARE & per Purchase order.
Job work)
NO
PM- QSF-PUR-08
Audit-Audit Sheet ( QSF-QAD-33),
Previous audit observations, current
quality issue list. Cummunicate the SPR Carry out the audit at
6
to supplier supplier end
Documented
Process Description Additional Informations Output Responsibility Method/Criteria
information reference
NA
PM- Every data collecting with different departments PM- Supplier Performance Report SQA Incharge QSF-PUR-08
Quality- RQC & Line (SAP), Customer Dept,Store, PPC,
Purchase. ( through email ) & Monitor as per criteria. Audit-Supplier audit planing sheet.
Audit- Consider and check the all inputs to preparing
the QMS audit plan list on Yearly bases. Concern base audit
Customer specific
Management specific
PM- Entring all different dept. data in spacified PM- Supplier Decission report prepared. QA H.O.D. SPR-QSF-PUR-29
stanadrad check sheet and calculated. SPR details-QSF-PUR-27
Audit- Select the qualified auditors as per list. Audit-Number of Auditors
NA
PM- Make supplier performance rating details and PM- Supplier Decission ( Good or bad) SQA Incharge PM- Documented. SPR-QSF-PUR-29
catogorized as per QSF-PUR-08.
Audit- First schedule plan dicuss with internal team Audit-Final schedule. Audit-Email
and accordingly communicate to supplier and
confirmation.
NA
PM- Through Email Communicate SPR Sheet. PM- Supplier Communication for SPR. SQA Incharge PM- Email QSF-PUR-08
Audit- Following Audit check sheet, verify the
Previous audit observation closers evidance along Audit-Supplier assessment & Obseravation. Audit- Physical/ Vertual QSD-QAD-33
with supplier. NA as per plan.
PM- For the SPR Warrning Letter raising by email & PM- Communication to Supplier. SQA Incharge PM- Email QSF-PUR-08
Un- Satisfactory for Corrective action again
communicate to supplier for fresh corrective action. Audit-Communicate to supplier , Audit Audit- Email. QSD-QAD-33
Audit- On the bases of Standards/ Observation report.
criteria/Specification finding the observation and
accordingly prepared the audit report and released. NA
PM:- Action Closer Report received by mail with PM- Closer Report. SQA Incharge PM- As per Warrning
supporting documents. Letter Criteria.
Audit- Action Closer Report received by mail with Audit-Closer Report.
supporting documents. Audit- Email.
NA
Document Ref
Rev No./Date
Rev No./Date