Automatic Bus Transfer Scheme
Automatic Bus Transfer Scheme
Abstract—Automatic bus transfer scheme (ABTS) is the practice financial incentives to defer this investment is significant, there-
of transferring a load bus to an alternate source when the normal fore to meet these emerging loads the modern distribution net-
power supply fails or is tripped thus ensuring continuity of supply. work operator will often seek to increase the capacity of existing
This paper comprehensively reviews existing schemes and imple-
mentations of ABTS especially for motor bus. To limit the fault substations by installing additional transformers. However it is
levels, during certain situations, the transformers supplying a pri- likely that for existing local primary substation this can result
mary distribution substation can be run in split instead of parallel in raising the fault levels beyond design limits when operated in
operation. This is because during outages if one transformer is lost, parallel with the existing transformers.
overloading of remaining transformers, if it occurs, can be man- A high impedance primary transformer can be used to limit
aged. This paper proposes an ABTS for a primary distribution
substation for a utility facing such a situation and present details fault levels. However these assets are non-standard equipment,
of its implementation. In the proposed scheme which is enabled by meaning that spares would not be readily available in the event
digital communications, if a transformer is lost, the bus section cir- of its failure. Additionally sub-optimal load sharing will occur
cuit breaker (CB) will be closed automatically after the incomer CB between the transformers during normal operation. This effec-
trips. The proposed ABTS has been implemented in the bus section tively reduces the useful rating of the new transformer when
relay for a new 11 kV switchboard where inter-relay communica-
tion is based on the IEC 61850 suites of standard. The contribu- operated in parallel with the other existing units.
tion of this paper is that it shows how to use a standard automation Other primary equipments such as series reactors and neutral
scheme smartly to defer network reinforcements and manage fault earthing resistors can be used to restrict fault levels but these
levels in primary distribution substation. would incur additional cost and have similar disadvantages like
Index Terms—Automatic bus transfer scheme, IEC 61850, intel- the high impedance transformer solution with regards to main-
ligent electronics devices (IEDs), substation automation. taining of spares. Series reactors can also potentially result into
other issues such as the production of electromagnetic radiation
that are difficult to be kept within the regulatory limits.
I. INTRODUCTION One novel approach proposed in this paper is to restrict the
network configuration so that the substation busbar is run spilt
under normal operation. The obvious disadvantage of this tech-
I N MODERN distribution network operations, increases
in substation loadings requires to be managed smartly. To
meet emerging loads it is likely that some substation might
nique however is that if a transformer trips then feeder outages
or overloading of the remaining transformer may occur. Clearly
if there is a method of quickly and automatically closing the nor-
require housing additional transformers but due to increased
mally open bus section circuit breaker following such an event
fault levels they cannot always operate in parallel with the other
is available then these shortcomings can be minimized. The de-
existing transformers. Implementing smarter and cost-effec-
velopments and investments in smart grid by distribution utili-
tive bus transfer schemes to manage the operation of parallel
ties provide opportunities in this direction.
transformers is one option.
The concept and development of the term and definition of
New planned subdivision and relocation of large industrial
smart grid is arriving towards a consensus both amongst policy
customers to the suburb necessitates increased local distribu-
makers and grid owners [1], [2]. The difficulty of interoper-
tion network capacity. The traditional approach to addressing
ability amongst legacy power network controls and emerging
this is often to construct a new primary substation. While this
intelligent electronic devices (IEDs) is also a significant chal-
will certainly address the immediate need and provide excellent
lenge that needs to be addressed [2], [3]. Towards the end of
network security, it usually comes at a considerable cost. The
2009, National Institute of Standards & Technology (NIST)
published an initial suite of smart grid standards. One of the
Manuscript received November 28, 2010; revised June 20, 2011; accepted
standard included in it, that addresses substation automation
October 08, 2013. Date of publication November 04, 2013; date of current ver-
sion November 25, 2013. This work has been supported in part by The Univer- and the communication aspect is IEC 61850 [1]. IEC 61850 is
sity of Auckland FRDF grant # 362665/9573. Paper no. TSG-00351-2010. a universal communication standard for Substation Automation
N.-K. C. Nair is with the Department of Electrical and Computer Engineering,
System (SAS) which has the ability to offer interoperability
University of Auckland, Auckland 1142, New Zealand (e-mail: n.nair@auck-
land.ac.nz). amongst IEDs from different vendors [2], [3]. In the context
D. L. P. Jenkins is with the Centre of Excellence, Alstom Grid, Stafford ST17 of IEC 61850, the functions that are required to be performed
4LX, U.K. (e-mail: [email protected]).
by the IEDs are decomposed into subparts which are known
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org. as logical nodes (LNs), and each LN usually has a list of
Digital Object Identifier 10.1109/TSG.2013.2285557 data with their attributes [3]. The data and their attributes
TABLE I
COMPARATIVE ASSESSMENT OF BUS TRANSFER SCHEMES
attached to that transformer’s bus bar. Bus section relay 2–3 will
check parameters and if it is safe to do so will automatically
close its circuit breaker.
Once both T1 and T2 are operational again the control room
operator should ideally open either bus section before the in-
comer CB is closed. This is to prevent paralleling of all three
transformers.
C. Special Considerations
For both situations listed in the previous subsections the fol-
lowing considerations are required to be satisfied to ensure that
the overall scheme operates safely and reliably:
1) Safety: The scheme must only operate for the two cases
described in the previous subsection. A dangerous situation can Fig. 4. Case 1, T3 Trip.
occur if the bus-section were to automatically close on to a fault
following a bus-bar or downstream uncleared feeder fault. This messages can be sent over a substation’s LAN. Normal Ethernet
has the potential to cause a cascading outage that could affect communication uses acknowledgement messages which ensure
the whole primary substation. that all messages sent reach their destination, but this is done
If all three transformers are paralleled then there is also a at the expense of transmission speed. GOOSE messages do not
safety hazard due to fault levels rising above design limits. The use acknowledgements; instead the message is resent multiple
scheme needs to be designed so that this risk is avoided. times at increasing intervals once an event occurs to ensure that
2) Self Monitoring: The scheme should have the ability to there is a very high probability of the message getting through
monitor its own integrity, especially with regards to the automa- to its destination. One of the features of GOOSE is the facility
tion scheme, to ensure its availability at all times and also to to interrogate the status of each transferred message. While the
minimize re-testing requirement after commissioning. interruption of a connection cannot be detected with conven-
3) Control: Control to turn the automation scheme on and off tional wiring, the signal transmission with IEC 61850 has an
should be provided both locally for technicians and remotely for integrated continuous monitoring which indicates failure of the
control room operators. connection or the transmitter. Since modern IEDs also have in-
4) Speed: The scheme should operate as fast as possible built device health monitoring this effectively makes the entire
to minimize disruption and potential overloading of remaining control scheme maintenance free.
transformers. Special consideration however should be made if
downstream distributed generation exists so that the bus section C. Improved Testing
circuit breaker does not automatically close onto an island that
has formed following an outage of the third transformer (like in Tools exist which enable the simulation of GOOSE messages.
Case 1 in Section III-A). This greatly assists in testing of the scheme compared to the
hard-wired approach.
IV. IEC 61850 FOR AUTOMATIC BUS TRANSFER SCHEME
D. Interoperability
The IEDs involved in the ABTS need to exchange informa-
Unlike some other peer-to-peer relay communication tech-
tion to determine when a transformer unit trip has occurred and
nologies IEC 61850 GOOSE is vendor independent. Different
to determine the position of all relevant circuit breakers so that
relay types can be integrated into the scheme.
the risk of paralleling is minimised. As such it is preferred that
Fig. 6 proposes an ABTS system that can be developed for
peer-to-peer relay communications is used to avoid the need for
the system of Fig. 3 using GOOSE enabled communication fea-
hard wiring.
tures of the IEDs associated with the secondary systems in the
IEC 61850 GOOSE messaging provides this peer-to-peer
primary distribution substation. Such a scheme has been imple-
communications capability. There are several advantages in
mented for an actual distribution substation of Fig. 7. The details
using this technology for the ABTS which are:
of the implementation with the design features are elaborated in
A. Installation Cost Savings the next section.
gration of IEDs into the substation automation projects. It is and proposes to extend it to primary distribution substation.
usually recommended that whenever a new IEC 61850 based The possibility to enhance ABTS enabled through IEC 61850
control scheme is designed it be bench tested exhaustively. IEDs has been established. A scheme for ABTS in an existing
Constructing a suitable test rig, developing a testing method- substation while adding a third transformer in parallel to ex-
ology [6] and comprehensively test the scheme to uncover isting transformers has been developed. The novelty comes
any potential issues are important aspect that needs practical from being able to use an automation scheme based on IEC
considerations before actual implementation. For the IEC 61850 standards to defer network reinforcements and manage
61850 enabled ABTS implemented using the practical case fault levels in primary distribution substation. The proposed
study, thirty-two different tests were required to pass before scheme has been implemented, tested and made operational
acceptance was completed. This approach is applicable for fac- in one of the 11 kV primary distribution substations. Future
tory acceptance test (FAT) of control scheme but is particularly implementation pathways, following inter-substation commu-
important when using GOOSE to ensure that interoperability nication, have been briefly discussed.
between IEDs is achieved and that GOOSE transmission speeds
are acceptable.
Pre-installation testing uncovered a number of issues. How- ACKNOWLEDGMENT
ever these were relatively easy to diagnose and correct on the
The authors thank the entire Otara Third Transformer Re-
test-rig when compared to what would have been required
placement Team, from within Electrix, Tesla Consultants, HV
during on-site commissioning. The final test requirements after
Power, and Vector for their input and support to implement the
the installation of T3 transformer of Fig. 7 were minimal as a
ABTS.
result. The scheme has been tested and is fully operational.
The economic advantage of using an ABTS is the avoided
cost of having to build a separate primary distribution substation REFERENCES
to house the new transformer bay. For cities where land cost is
[1] NIST. (Report to NIST on the Smart Grid Interoperability Standards
a premium this can translate into millions of dollars. Roadmap-Post Comment Period Version Aug. 2009 [Online]. Avail-
able: http://www.nist.gov/smartgrid/upload/Report_to_NIST_Au-
VII. FUTURE EXTENSIONS ENABLED THROUGH IEC 61850 gust10_2.pdf
INTER-SUBSTATION COMMUNICATION [2] R. Hledik, “How green is the smart grid?,” The Electr. J., vol. 22, pp.
29–41, 2009.
IEC 61850 is currently undergoing revision around inter-sub- [3] Communication Networks and Systems in Substation-Part 5: Com-
station communication and associated architectures. Edition 2 munication Requirements for Functions and Device Models, IEC
61850–5, 2003.
and part 5 of the standards lays out requirements for commu- [4] Communication Networks and Systems in Substation-part-7–1: Basic
nication between substation automation systems to utility au- Communcation Structure for Substation and Feeder Equipment-Prin-
tomation systems. Maturity and acceptance of these practices ciples and Models, IEC 61850–7-1, 2003.
[5] Communication Networks and Systems in Substation-Part-7–2: Basic
will offer opportunities for extending ABTS schemes to be inte- Communcation Structure for Substation and Feeder Equipment-Ab-
grated with other control and protection schemes requiring inter- stract Communcation Serivce Interface (ACSI), IEC 61850–7-2, 2003.
action amongst more than one primary distribution substations. [6] L. Zhang and N.-K. C. Nair, “Testing protective relays in IEC 61850
framework,” in Proc. Aust. Universities Power Eng. Conf. (AUPEC),
The next immediate opportunity for ABTS, described in this Dec. 14–17, 2008.
paper, is towards extending it for inter-substation schemes. This [7] S. Mohagheghi et al., “Modeling distribution automation system com-
will involve developing distributed logic across one or more ponents using IEC 61850,” in Proc. IEEE Power Energy Soc. Gen.
Meet. 2009 (PES ’09), pp. 1–6.
primary distribution substations. Considering the scheme dis- [8] T. A. Higgins, P. L. Young, W. L. Snider, and J. H. Holley, “Report on
cussed in Section IV, for a fault in one transformer the bus-sec- bus transfer, part I—assessment and application,” IEEE Trans. Energy
tion would close and inter-substation communication can then Convers., vol. 5, no. 3, Sep. 1990.
[9] T. A. Higgins, P. L. Young, W. L. Snider, and J. H. Holley, “Report
instruct other neighboring substation transformers to parallel on bus transfer, part II—computer modeling for bus transfer studies,”
and relive the overload (if any caused). IEEE Trans. Energy Convers., vol. 5, no. 3, pp. 470–476, Sep. 1990.
Another example following inter-substation communication [10] D. L. Hornak and D. W. Zipse, “Automated bus transfer control for crit-
ical industrial processes,” IEEE Trans. Ind. Appl., vol. 27, pp. 862–871,
can be towards coordinating tap-changing distribution trans- Sep./Oct. 1991.
formers, down-stream voltage regulators and up-stream capac- [11] S. Mazumdur and M. Chiramal, “Bus transfer practices at nuclear
itor banks. Possibilities for developing transfer trip schemes in plants,” IEEE Trans. Power Del., vol. 6, no. 4, pp. 1438–1443, Oct.
1991.
distribution systems with lightly meshed distribution network [12] R. D. Pettigrew and E. L. Johnson, “Automated motor bus transfer
implementation can also be realized. Also smarter back-feed theory and application,” in Proc. 37th Annu. Conf. Texas A&M Uni-
of certain portion of the laterals in a distribution network, fol- versity, Apr. 16, 1984.
[13] R. D. Pettigrew et al., “Motor bus transfer,” IEEE Trans. Power Del.,
lowing upstream fault in a main feeder, can also be potentially vol. 8, no. 4, pp. 1747–1758, Oct. 1993.
implemented. The design, testing, and implementation for all of [14] M. Thakur, B. Kasztenny, and J. Eapen, “Implementation of automatic
the above identified schemes, if realized on distribution network bus transfer scheme on multi-function microprocessor based relays,” in
Proc. 57th Annu. Conf. Protective Relay Eng. Texas A&M Univ, Mar.
will follow on similar lines as described in this paper for ABTS. 1, 2004.
[15] V. Balamourougan, T. S. Sidhu, B. Kasztenny, and M. M. Thakur, “Ro-
VIII. CONCLUSIONS bust technique for fast and safe transfer of power plant auxiliaries,”
IEEE Trans. Energy Convers., vol. 21, no. 2, pp. 541–551, Jun. 2006.
This paper comprehensively reviews different ABTS [16] Standard for Interconnecting Distributed Resources with Electric
methods used for primary auxiliary bus supplying motor loads Power Systems, IEEE 1547, 2003.
1828 IEEE TRANSACTIONS ON SMART GRID, VOL. 4, NO. 4, DECEMBER 2013
Nirmal K. C. Nair (S’01–M’04–SM’10) received Dylan L. P. Jenkins received his B.Eng. degree with
his B.E. degree in electrical engineering from M.S. first class honors from the University of Auckland,
University, Baroda, India, and M.E. degree in high New Zealand.
voltage engineering from Indian Institute of Science, He is currently a Product Manager for Substation
Bangalore, India. He received his Ph.D. degree in Automation Products from Alstom Grid, based at the
electrical engineering from Texas A&M University, Center of Excellence in Stafford, U.K. Previously
College Station, TX, USA. he was an Electrical Protection and Control Systems
Presently, he is a Senior Lecturer at the Department Engineer at Vector, New Zealand’s largest electricity
of Electrical & Computer Engineering in University distribution company. Prior to this he held a number
of Auckland, New Zealand. His current interest in- of roles within Vector’s Asset Management, Project
clude analysis, operation, protective relaying and op- Engineering, and Capital Delivery teams as a Grad-
timization in the context of smart grid, electricity markets, and integration of uate Engineer.
DG/renewable.
Dr. Nair volunteers as the Chair of PES/PELS Chapter of NZ North Sec-
tion. He is Chair of PES Life Long Learning Subcommittee (2012–13) and also
the Constitution and Bylaws Committee member in the PES Governing Board
(2011–). He is currently an Executive committee member for CIGRE NZ Na-
tional Committee and is 2010–14 Observer Member for CIGRE B5 (Protection
and Automation) from NZ.