DOCUMENT TITLE: ISOLATION VALVES REPLACEMENT – NR NGL ORIGINATOR : Vitalii Zhmudenko / Ananda Kumar
DOCUMENT TITLE: ISOLATION VALVES REPLACEMENT – NR NGL ORIGINATOR : Vitalii Zhmudenko / Ananda Kumar
E-mail Attachment.pdf
As no modifications are required in the JB and
relay panel wiring, Loops drawings are not
Loop drawings, JB's wiring and Relay panel wiring are
Scope of applicable. However, to aid loop checks during
Work
missing. These are important documents and required Maksim Usov
commissioning, JB and relay panel terminal
Closed
to be in place,
details against each valve is tabulated and
included with the Construction work pack
Given constructability review will be discussed in-
country for above CWPs, I would Suggest verifying
the following items at site:
During installation of Isolation valves, if any
• Existing small-bore valves in bypass lines where
bypass small bore valves need to be removed,
construction sequence of the ESDVs will be require
General
de-install them then re-install them after install the
Wajdi Alsaleh then small bore valves, spacers, spec. blind Closed
need to be reused, while gasket and bolt need
new ESDVs, MOVs…. the concern is the erection
to be used from stock items.
materials (Gaskets, bolt sets) and confirmation that
these small-bore valves will be re-used (all where
applicable). The same for spacers and spectecal
blinds also.
DOCUMENT TITLE: ISOLATION VALVES REPLACEMENT – NR NGL ORIGINATOR : Vitalii Zhmudenko / Ananda Kumar
• Confirmation whether vendor support will be required Vendor support is not included into Wood PO.
General during SD. I.e. ESDVs actuators rotating degree Wajdi Alsaleh Actuators rotating degree is designed as per Closed
adjusting (Where applicable). approved site survey.
• Confirmation whether various valves have been Confirmed. Various valves have been ordered
General
ordered with tag-in (Valve ID per P&ID), if any.
Wajdi Alsaleh
with tag-in Valve ID per P&ID
Closed
• Insulation removal and earthing installation, (Where Insulation removal added.
General
applicable).
Wajdi Alsaleh
Existing earthing arrangement shall be reused.
Closed
Constructability Review Comments
For 85-6 we have done clash checks for the
valves at NR NGL and all compressor
Has Clash checks between new valve/actuators and
Constructability stations. No issues have been identified
CR-1 existing facility (piping, structure, instruments, etc)
Review Comments except for three valves where we requested
Closed
been carried out ?
the vendor to shift the filter assembly to the
other side of the actuator.
Megger testing of existing cables should be
carried out pre-shutdown to confirm if existing
cable can be re-used, if cable cannot be re-
Megger testing of existing cables - when will this Constructability
CR-2
activity be carried out? Review Comments
used then new cable is to be laid pre- Closed
shutdown - BGC construction to liase with
BGC operations / maintenance to plan
activities
DOCUMENT TITLE: ISOLATION VALVES REPLACEMENT – NR NGL ORIGINATOR : Vitalii Zhmudenko / Ananda Kumar
DOCUMENT TITLE: ISOLATION VALVES REPLACEMENT – NR NGL ORIGINATOR : Vitalii Zhmudenko / Ananda Kumar
From: [email protected]
Sent: Saturday, May 04, 2019 10:24 PM
To: KUMAR, Ananda
Cc: [email protected]; NEJAD, Moe; ROSSI, Andrea
Subject: JB`s - WG 85-6
Attachments: JB List.xlsx
Hi Ananda,
- The current design on WG 85-6 is based on reuse of existing JB`s and cables.
- The concern around condition of existing JB`s was being discussed. The design and work packs shall continue
accordingly on the basis of re-use of existing JB`s.
- To ensure we are not caught in trouble in a shutdown due to an existing JB that cannot be re-used, please
find attached a list of JB`s to be procured. These will be an insurance/back up stock and hence shall not be
captured in the design documents or BOQ`s in the work packs.
- Take note of the yellow highlighted rows in the attachment that mention the number of terminals, the Ex
rating required, material of construction etc.
- I assume all the cable entry points to the JB`s come fitted with blind Ex plugs such that any entry point not
being used remains plugged. Correct? Please confirm.
- Please consider the other bulk accessories for these JB`s such as cable glands as part of the MTO to be
procured.
Thanks.
Regards,
Peter.
1
BGC - Construction Workpack
CONTRACT : UI76316
SITE : NR NGL
CLIENT No. :
REVISION RECORD
CHECKED APPROVED
REV DESCRIPTION DATE ORIG.
CONST.
ENG LEAD
WG
Vitalii Ananda Ian Harrop Moe
Zhmudenko Kumar Nejad
01R Issued for Review 12.09.19 Construction Senior PACO Construction Lead
Workpack Engineer Manager Project Engineer
Lead
Vitalii Nakkeeran Vitalii Alex
Approved for Zhmudenko Sivalingam Zhmudenko Herrera
02C 07.04.21
Construction Construction Lead PACO Construction Project
Lead Engineer Lead Manager
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it Page 1 of 27
Rev/Date: 3 14 November 2019 was printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
CONTENTS
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 2 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
SCAFFOLDING YES
LOLER YES
INSULATORS NO
PAINTERS YES
WELDING YES
NDT YES
HYDROTIGHT YES
HYDROTEST NO
OPERATIONS (ISOLATIONS)
YES
STROKE TEST
YES
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 3 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
Workpack Engi.
Tech. Safety
Certification
Workpack
Originator
WORKPACK CONTENTS CHECK
Discipline
Engineer
Engineer
Engineer
HSE
checker
Quality
Project
1 1a Overview of Scope - Completed as latest SOW.
Inputs to include bullet points, screen shots of 3D N/A
model, marked up drawings for information only,
isometrics and P&IDs where applicable.
Drawings, Documents and Drawing Register
2a - Drawings included as per Drawing Register N/A
2 2b - All Drawings are signed by Originators,
Checkers and Approvers
(at appropriate revision)
2c - All Drawings have been approved AFC
NOTE:
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 4 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
1.1.1 Definition
Means all temporary facilities, buildings and contents thereof and temporary
TEMPORARY WORKS works of every kind required for, or/in, or about the execution or
maintenance of the WORKS.
Mean any place (except the SITE) where CONTRACTOR conducts aspects
WORKSITE
of the WORKS required in order to comply with its obligations.
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 5 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
1.1.2 Abbreviations
TBA To Be Advised
TBC To Be Confirm
The project scope is to complete the engineering and procurement services for the replacement of train isolation
valves in the following assets
a) NR NGL,
b) North Rumaila Compressor stations (CS-1 to CS-5),
c) South Rumaila Compressor stations (Janubiya, Qurainat, Markaziya and Shamiya) and
d) Zubair Hammar Mishrif Compressor station.
Existing Train Isolation valves are either old, motor operated, not fail safe and / or having functional issues.
The rating of solenoid in the existing valves are 110 VDC for Compressor stations and 110VAC for NR NGL.
Therefore, for each valve being replaced as part of this project scope, two numbers of solenoid valves are
included in vendors scope (1 number rated for 24 VDC and 1 number rated for 110 VDC for Compressor stations
/ 110 VAC for NR NGL). In order to implement the FRR project, valves shall be hooked up to the existing control
panels which are based on 110 VAC / 110 VDC solenoid designs in the interim phase. 24 VDC solenoid shall
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 6 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
be delivered as loose supply item which can be field replaced when the plant control system upgrade (i.e, new
ICSS) is sanctioned.
98 No’s of valves will be replaced in a phased manner and will be captured through 11 No’s of Work-packs. Each
work-pack will have Scope of Work for each station with tag number details, Drawings, Documents as applicable,
Materials (BOMs / MTOs), Completions & Certification, Close-out / As-building, TQ(s), Site Construction
Completion Check List as required for the work pack.
Work-pack will consist of Pre-shutdown and shutdown activities.
Pre-shutdown will include all works to be done by installation contractor in advance in order to be ready for
shutdown, for example – foundations for JBs, JBs installation, cabling and termination where possible, etc.
Shutdown activities will include the works to be done during shutdown, like valve dismantling, valve installation,
final hook-ups etc. The sequence and priority should be as per shutdown schedule/request.
For Constructability, Safety and Effective execution of the above project scope all the works have been broke
down onto 11 different work-packs which are as following:
Total 27 number of valves were identified during FRR at NR NGL which will be replaced by new valve in this
Work-pack.
Additionally, 7 No’s of valves were procured and handed over to BGC Maintenance but shall not be replaced
within scope of this workpack as per BGC instruction.
To have clear scope of execution, installation contractor shall refer Table 1 below for the details like valve tag
number, P&ID number, line number and location of valves to be replaced under scope of this Work-pack.
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 7 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
In the Table 2 below the details like tag number, P&ID number, line number and location of valves to be procured
and handed over to BGC Maintenance.
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 8 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
Table 2: List of valves to be procured for NR NGL and handed over to BGC Maintenance. Replacement of
these valves is not part of the Construction Work Pack.
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 9 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
Table 3: List of ESDV valves already delivered to site which require Actuator Rotation to be done by
CONTRACTOR before installation.
Sr. Actuator Rotation
Tag no Input for Rotation
no requirement
1 41-7-ESDV-11 Yes HVRF
11 41-7-ILSA-46V Yes HVRF
14 41-8-ILDSA-63V Yes HVRF
BGC Construction / Projects team will update Site Construction Contractor with the shutdown window (Duration)
to replace the ESDV as soon as such info is received from BGC asset.
Installation contractor shall test (megger) the existing cables (Secondary Cable - Valve to Junction Box and
Primary Cable - Junction Box to Relay Panels) in order to identify suitability of re-using these cables and produce
appropriate test reports to allow BGC make decision on the way forward. COMPANY to advise additional scope
of work (if any) for ENGINEER, based on provided test report. Megger test ITR’s to be signed of by PACO TA3.
For the terminal details in the existing Junction box and control panels CONTRACTOR shall refer
Attachment-01 “NR NGL Valve List with termination details” included in Section 2 of the Workpack.
Installation contractor to fill and sign ITRs for cable testing as listed in section 6.0 of the work-pack.
Installation contractor shall prepare detail method of statement for replacement of ESDV from the existing pipe,
for cables testing and new ESDV installation.
Installation contractor shall collect the weight of the valve from the name plate detail and arrange pulley/crane
for lifting the existing ESDV. Before starting ESDV Valve removal/demolition, installation contractor shall prepare
barricaded laydown area for the collection of the demolished material.
The Installation Contractor shall note that the work involves removal/demolition of ESDV, in hazardous area,
near the live and operating equipment and certain works are required to be carried out under shut down/ PTW
system.
Installation contractor shall ensure that the shutdown for the power supply from the respective system is already
in place as per permit to work system. Workshop activities shall be done before pre-shutdown such as functional
test, valve stroke test, Limit switch (Open/Close) etc.
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 10 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
Fabricate structural stand where required with related concrete foundations for JBs as per Instrument
Installation Details – NOT APPLICABLE as the existing Junction boxes shall be re-used.
Installation of Junction Boxes – Current philosophy is to re-use the existing junction boxes in order to
complete this FRR project scope, as complete re-instrumentation and new JB for NR NGL plant is
being addressed through separate FRR work order (WG0085A-7). However, as per the steer from
BGC, Junction Boxes are procured as standby spare in case if it’s found during the construction that
the existing Junction boxes are not suitable for re-use also contingency in earthing cable is provided
in case new junction box is used.
Cable trenches, Routing and Cable Installation – NOT APPLICABLE “if test result is accepted and
signed by TA3” as existing cables shall be re-used.
Cable laying and pulling – NOT APPLICABLE “if test result is accepted and signed by TA3” as existing
cables shall be re-used.
Termination of cables in Junction Box at field end – NOT APPLICABLE “if test result is accepted and
signed by TA3” as existing cables & Junction boxes shall be re-used.
Instrument Air tubing and arrangements as per Instrument Air Hook-up Drawing (Doc 9500-WGEL-
N001-ISGP-G00000-IN-2335-06119)
Provision of pneumatic arrangements as per Instrument Air Hook-up Drawing (Doc 9500-WGEL-
N001-ISGP-G00000-IN-2335-06119)
To provide lifting/rigging and scaffolding in advance where required and applicable.
SITE PHOTOS – Refer Site Survey report for Site Photos (Doc 9500-WGEL-N001-ISGP-G00000-IN-8417-
06013)
All isolation required to complete the scope of work within this work pack are to be in place prior to work
commencing as per permit to work. If any isolations are required / found later, work must stop until isolations are
in place.
The contractor shall take all reasonable precautions to identify and ensure the safety of personnel and equipment
on site. The contractor is responsible to get Permit to Work to perform the work at site. During shutdown,
Installation Contractor shall perform the below works but not limited to following:
Dismantling existing cable termination, disconnecting and demolition related Valve instrumentation
tubing, air tank etc.;
Insulation removal & reinstatement after completion of ESDV replacement wherever applicable.
Unbolting and removing Valves;
Installation of new valves. Site installation contractor would provide a temporary support to adjacent
ESDV’s piping systems avoiding drops or mismatches in piping alignment during limited SD time
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 11 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
(where applicable and required – this item can be done as a pre-shut down activity). Site contractor
to do steel structural modification where cannot be done before shutting down.
Cable terminations to new Solenoid Valve;
Connection of Instrument Air tubing at valve side as per Instrument Air Hook-up Drawing (Doc 9500-
WGEL-N001-ISGP-G00000-IN-2335-06119)
Testing of valves through Existing panel as per GOC ITRs A and B.
The sequence and priority should be as per shutdown schedule/request.
Installation Contractor to verify alignment of all flange faces at site. In case of existing flange faces
differ from new valves flange faces then Installation Contractor shall adjust misalignment by cutting
of existing Flanges or Pipe spool, adjusting orientation, welding, Hydro Test and Radiography Test
to match with new ESDV.
Piping modification work next to the below new ESDV valves, which has end to end dimension
mismatch with the existing space available. The gap shall be fitted / replaced by the adjacent pipe
spools for
- 41-7-ILSA-46V - New valve dimension is nearly 63 mm bigger than existing one. Need Piping
modification to match as per isometric drawing 9500-WGEL-N001-ISGP-U14000-MP-2343-
00002.
- 41-7-ILDSA-71V - New valve dimension is 109 mm bigger than existing one. Spool towards
break up flange need to be modified as per isometric drawing 9500-WGEL-N001-ISGP-U14000-
MP-2343-00001.
- All other new valves are slightly 2 mm to 14 mm bigger than existing valves. Piping adjustment
is required at site, as and where necessary.
Site construction team shall refer for the below table for recommendations on supports (concrete
blocks) for the listed ESDV valves. New support where needed in the table shall be constructed as
per Support Sketch included below in the Workpack.
No additional support
41-7- required. Temporary
1 24 5806546.001 No action for civil team
ESDV-11 support is required at
the time of installation.
41-1- No additional support
2 22 5806546.002 No action for civil team
ESDV-4 required
41-17- NO ADDITIONAL Cracks found in pedestal, Pedestal to
3 6 5806546.003
ESDV-53A SUPPORT REQUIRED be repaired.
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 12 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 13 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 14 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
Support Sketch
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 15 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
Refer any site queries with this workpack by utilising the Site Technical Query Process Map (referring doc. no.
CON-PCM-1048) provided within Section 6 of this workpack.
Refer any site queries with this work-pack to Project Manager by e-mail [email protected], with a copy
being cc’d to DCC on [email protected].
All TQs are to be accompanied by a standard Site Technical Query Form (referring doc. no. CON-FOR-1121)
provided within Section 6 of this workpack.
Any deviations to the design requirements / Work-pack instructions to be authorised by the relevant query
procedure.
Upon scope completion, the Workpack close-out checklist will be completed and signed-off to confirm Workpack
completion and closure.
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 16 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Workpack Tool Box Talk Checklist
Is the Work-party familiar with the area and equipment to be If confined space entry, work from scaffold or work of an
employed in the task? exceptional nature involved, are all the procedures and
Discuss objectives of the job. precautions fully understood?
Are the job steps understood by all? Ensure personnel are familiar with the work area,
telephones, GPA’s, escape routes, fire-fighting equipment,
Have the likely job hazards been identified?
PPE requirements, or any special precautions due to the
Legislation Etc type of area and / or work.
Name:
Name:
Name:
Name:
Name:
Comments / Actions:
Name:
Name:
Name:
Name:
Name:
Name:
Name:
Name:
Name:
Name:
Name:
Name:
Name:
Name:
Name:
As-built
Document Number Document Title Rev
Required
0085-9500-WGEL-N001-ISGP- NR NGL P&ID – Stripper O.V.H.D
02C Yes
G00000-PX-2365-00001-001 Compressor
0085-9500-WGEL-N001-ISGP- NR NGL P&ID – Booster Compressor – 1st
02C Yes
G00000-PX-2365-00002-001 Stage Gas (Train A)
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Hot Oil Furnace 02C Yes
G00000-PX-2365-00003-001
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Acid Gas Removal Unit 02C Yes
G00000-PX-2365-00004-001
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Acid Gas Removal Unit 02C Yes
G00000-PX-2365-00005-001
0085-9500-WGEL-N001-ISGP- NR NGL P&ID – Stripper O.V.H.D
02C Yes
G00000-PX-2365-00006-001 Compressor
0085-9500-WGEL-N001-ISGP- NR NGL P&ID – Stripper O.V.H.D
02C Yes
G00000-PX-2365-00006-002 Compressor
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Liquid Separation 02C Yes
G00000-PX-2365-00007-001
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Liquid Separation 02C Yes
G00000-PX-2365-00008-001
0085-9500-WGEL-N001-ISGP- NR NGL P&ID – Gas and Liquid Dehydration
02C Yes
G00000-PX-2365-00009-001 Unit
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Acid Gas Removal Unit 02C Yes
G00000-PX-2365-00010-001
0085-9500-WGEL-N001-ISGP- NR NGL P&ID – Gas and Liquid Dehydration
02C Yes
G00000-PX-2365-00011-001 Unit
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Acid Gas Incinerator 02C Yes
G00000-PX-2365-00012-001
0085-9500-WGEL-N001-ISGP-
Pneumatic Hook-up drawing NR NGL 03C Yes
G00000-IN-2335-06119-001
0085-9500-WGEL-N001-ISGP-
Instrument Cable Block Diagram NR NGL 03A Yes
G00000-IN-0980-06080
0085-9500-WGEL-N001-ISGP-
Data sheet for actuated ON-OFF valves 01I Yes
G00000-IN-2105-06026
0085-9500-WGEL-N001-ISGP-
Instrument and JB location layout 02C Yes
G00000-IN-4024-06145-001
0085-9500-WGEL-N001-ISGP-
Instrument and JB location layout 02C Yes
G00000-IN-4024-06145-002
0085-9500-WGEL-N001-ISGP-
Instrument and JB location layout 02C Yes
G00000-IN-4024-06145-003
0085-9500-WGEL-N001-ISGP-
Instrument Index 02I Yes
G00000-IN-6612-06013
0085-9500-WGEL-N001-ISGP-
Site Survey Report NR NGL 03I No
G00000-IN-8417-06013
9500-WGEL-N001-ISGP-U14000-
Piping Isometric – Line 1”-41-P314-15C 01C Yes
MP-2343-00001
9500-WGEL-N001-ISGP-U14000-
Piping Isometric – Line 6”-41-P124-15C 01C Yes
MP-2343-00002
9500-WGEL-N001-ISGP-G00000-
Site Survey Report 03A No
MP-8417-00003
Attachment 01 NR NGL Valve List with termination details - No
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 17 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
A Task Based Risk Assessment for the workscopes documented within this workpack will be undertaken by
the site nominated contractor.
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 18 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
API STD 607 Fire test for quarter-turn valves and valves equipped with non-metallic seats
API STD 608 Metal Ball Valves – Flanged, threaded and Welding end
ASME B16.5 Pipe Flanges and Flanged Fittings NPS 1/2 through NPS 24 Metric/ Inch
Standard
ASME B16.10 Face to Face and End to End dimensions of valves
BS EN 12266 Part-1 Industrial valves Testing of valves Part 1: Pressure tests, test procedures
and acceptance criteria Mandatory requirements
BS EN 12266 Part-2 Industrial Valves - Testing of Valves Part 2: Tests, Test Procedures and
Acceptance Criteria Supplementary Requirements
CEN EN 15714-3 Industrial valves - Actuators - Part 3: Pneumatic part-turn actuators for
industrial valves - Basic requirements
IEC 60079-0 Electrical Apparatus for Explosive Gas Atmospheres - Part 0: General
Requirements
IEC 60079-11 Explosive atmospheres – Part 11: Equipment protection by intrinsic safety
“I” - Edition 6.0
IEC 60079-14 Explosive atmospheres – Part 14: Electrical installations design, selection
and erection
ISO 12490 Petroleum and natural gas industries - Mechanical integrity and sizing of
actuators and mounting kits for pipeline valves
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 19 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
MSS SP-06 Standard Finishes for Contact Faces for Pipe Flanges and Connecting End
Flanges of Valves and Fittings
MSS SP-25 Standard Marking System for Valves, Flanges, Fittings and Unions
MSS SP-55 Quality Standard for Steel Casting for Valves, Flanges and Fittings and
Other Piping Components- Visual Method for Evaluation of Surface
Irregularities
NACE MR 0175 / ISO 15156-1 Petroleum and natural gas industries—Materials for use in H2S containing
Environments in oil and gas production—Part-1
General principles for selection of cracking-resistant materials
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 20 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
For other Installation Bulk Materials Installation Contractor shall refer to below Material Take-Off.
Installation Contractor shall ensure that the above stated materials are procured and ready at site before
commencement of work in order to avoid any impact on the approved construction schedule.
Installation Contractor must arrange the following material required for installation, testing & commissioning but
not limited to Crane / Pulley, Tools, Cable lugs and ferrules, Cable ties, Strain relief clamps, insulating
consumables, painting consumables etc.
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 21 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
N/A
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 22 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
Scope of work is not complete until all Construction and Completions check / test sheets are signed-off and
approved by the worksite management.
All certification will be uploaded to the GoCompletions Database, from which a full list of certifications will be
produced.
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 23 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
The installation contractor shall submit the mark-up drawings / documents for final record and reference along
with hand over dossier.
Installation contractor shall prepare mark-up drawings/ documents register and shall obtain approval from the
Company.
After that WG shall update drawings to “as-built” in accordance with the red-line mark-ups completed and
returned to WG by BGC.
As-
Document Number Document Title Rev build
Req.
Technical Query
CON-FRM-1121 Site Technical Query Form C1 NO
CON-PCM-1048 Site Technical Query Process Map 0 NO
As Building
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Stripper O.V.H.D Compressor 02C Yes
G00000-PX-2365-00001-001
0085-9500-WGEL-N001-ISGP- NR NGL P&ID – Booster Compressor – 1st
02C Yes
G00000-PX-2365-00002-001 Stage Gas (Train A)
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Hot Oil Furnace 02C Yes
G00000-PX-2365-00003-001
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Acid Gas Removal Unit 02C Yes
G00000-PX-2365-00004-001
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Acid Gas Removal Unit 02C Yes
G00000-PX-2365-00005-001
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Stripper O.V.H.D Compressor 02C Yes
G00000-PX-2365-00006-001
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Stripper O.V.H.D Compressor 02C Yes
G00000-PX-2365-00006-002
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Liquid Separation 02C Yes
G00000-PX-2365-00007-001
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Liquid Separation 02C Yes
G00000-PX-2365-00008-001
0085-9500-WGEL-N001-ISGP- NR NGL P&ID – Gas and Liquid Dehydration
02C Yes
G00000-PX-2365-00009-001 Unit
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Acid Gas Removal Unit 02C Yes
G00000-PX-2365-00010-001
0085-9500-WGEL-N001-ISGP- NR NGL P&ID – Gas and Liquid Dehydration
02C Yes
G00000-PX-2365-00011-001 Unit
0085-9500-WGEL-N001-ISGP-
NR NGL P&ID – Acid Gas Incinerator 02C Yes
G00000-PX-2365-00012-001
0085-9500-WGEL-N001-ISGP-
Instrument Cable Block Diagram NR NGL 03A Yes
G00000-IN-0980-06080
0085-9500-WGEL-N001-ISGP-
Pneumatic Hook-up drawing NR NGL 03C Yes
G00000-IN-2335-06119-001
0085-9500-WGEL-N001-ISGP-
Instrument Cable Block Diagram 02A Yes
G00000-IN-0980-06080
0085-9500-WGEL-N001-ISGP-
Data sheet for actuated ON-OFF valves 01I Yes
G00000-IN-2105-06026
0085-9500-WGEL-N001-ISGP-
Instrument and JB location layout 02C Yes
G00000-IN-4024-06145-001
0085-9500-WGEL-N001-ISGP-
Instrument and JB location layout 02C Yes
G00000-IN-4024-06145-002
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 24 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
0085-9500-WGEL-N001-ISGP-
Instrument and JB location layout 02C Yes
G00000-IN-4024-06145-003
0085-9500-WGEL-N001-ISGP-
Instrument Index 02I Yes
G00000-IN-6612-06013
0085-9500-WGEL-N001-ISGP-
Site Survey Report NR NGL 03I Yes
G00000-IN-8417-06013
9500-WGEL-N001-ISGP-
Piping Isometric – Line 1”-41-P314-15C 01C Yes
U14000-MP-2343-00001
9500-WGEL-N001-ISGP-
Piping Isometric – Line 6”-41-P124-15C 01C Yes
U14000-MP-2343-00002
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 25 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 26 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
Wood Group Document No.: 9500-WGEL-N001-ISGP-G00000-BA-5794-85611
Workpack for Isolation Valves Replacement – NR NGL Revision: 02C
Form No: CON-FRM-1196 Content property of Wood. Paper copies are uncontrolled. This copy was valid at the time it was Page 27 of 27
Rev/Date: 3 14 November 2019 printed. For an up-to-date copy, please visit Wood Management System.
List of Actions
List of Actions
Action Number Att. Parent Project Name Review Name Status Action Action Response Approval Comments Owner Owner Discipline Final Approver Date Completed
0001 WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 1. Dummy Action: Action 1 only applies to Zubair. - No Comment Nancy Anis (AA) Safety Engineering Nancy Anis (AA) 09/01/2020
0002 WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 2. HAZOP review will be required (only when manual valve is substituted with ESDV) with Not applicable as MOV valves are being changed to ESDV , as per discussion /Agreement No Comment FRR Project-Engineer Project Engineering Clarissa Munoz Escanilla 19/02/2020
proper process safety information (i.e. P&ID, C&E, safeguarding, ESD logic). HAZOP is only required when Manual valve is being changed to ESDV
0003 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 3. Verify with the equipment supplier for consideration of wet service in the material selection Refer to attached Signed off close out sheet. Nancy Anis (AA) Safety Engineering Nancy Anis (AA) 23/01/2020
process.
0004 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 4. To survey all ESDV bypasses to determine whether they are required for black start or not. NR-NGL review carried out as per projects P&IDs provided, see response email attachment. As discussed in the Adam Burnett (BGC) Operations Clarissa Munoz Escanilla 31/03/2020
Including inching facility to open the ESDV gradually to equalize the line which was NR-NGL operational team included in site review and summary. With updated email response meeting 15th March
implemented 2 years ago with previous EPC for compression projects. action to address former email with copy paste error for clarity. 2020 with OR&A, the
bypass valves are
required to (re)start-up
the compressors.
Refer to action 6 for
the requirements for
bypass ESDVs.
0005 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 5. If bypasses are not required remove valves and blind off. This action is not applicable. Bypasses are required around the main ESDV for start-up. Refer This action is not Nancy Anis (AA) Safety Engineering Clarissa Munoz Escanilla 30/03/2020
to actions 4 and 6 applicable. Bypasses
are required around
the main ESDV for
start-up. Refer to
actions 4 and 6.
0006 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 6. If bypasses are required, provide small ESDV (2”-3”) at the bypass line. Bypass valves that are identified are required and will be utilized operationally with the LO-LC The bypasses of Adam Burnett (BGC) Operations Clarissa Munoz Escanilla 14/05/2020
asset register. ESDVs in NR NGL as
Attached: part of this project
1. PIDs for scope identifying bypass valves. scope have existing
2. Valves with valve bypass identified list ESDVs on them. See
3. Email of site review by OR and Asset operational team attached email
ESDV 4 and 11 are supported by 2" ESDV, however if required will be captured within the clarifications dated 14
asset LO-LC register on completion of activity. Close-out of this action should be cross May 2020.
referenced to action 4&5. Updated email response sent for clarity regarding previously
attached copy & paste error reply, all other items now remain as described.
0007 WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 7. Dummy Action: Action 7 only applies to Zubair - Nancy Anis (AA) Safety Engineering Clarissa Munoz Escanilla 16/01/2020
0008 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 8. Ensure the testing for the cables during the commissioning for reliability of the system and Refer to attached signed off Action Close out Sheet. Nancy Anis (AA) Safety Engineering Clarissa Munoz Escanilla 14/01/2020
replace the cables if any defect is found.
0009 WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 9. To survey all ESDV bypasses to determine whether they are required for black start or not. Duplicate action , same as #4 Repeat of action 4 FRR Project-Engineer Project Engineering Clarissa Munoz Escanilla 19/02/2020
Including inching facility to open the ESDV gradually to equalize the line which was
implemented 2 years ago with previous EPC for compression projects.
0010 WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 10. If bypasses are not required remove valves and blind off. Duplicate action ,same as action # 5 Repeat of action 5. FRR Project-Engineer Project Engineering Clarissa Munoz Escanilla 19/02/2020
0011 WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 11. If bypasses are required, provide small ESDV (2”-3”) at the bypass line. Asset team Duplicate action ,same as action # 6 Duplicate action. Refer FRR Project-Engineer Project Engineering Clarissa Munoz Escanilla 12/03/2020
requires the bypass for start-up during the interim stage of installation for inching facilities. to Action 6
Hence, option 3 or bypass may need to be implemented in due course (i.e. FRR 79 project)
0012 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 12. Update the relevant Startup/shutdown procedure/philosophy via document delivery matrix. Refer to attached Signed off (by BGC ORA & Discipline TA2)Action Close out sheet and NGL Refer to attachments. ORA-NR BGC Operations Clarissa Munoz Escanilla 31/03/2020
OR engineer email response complete
0013 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 13. Verify the surge analysis for ESDV in liquid services with risk mitigation measures & Refer to attached signed off close out sheet. No Comment Nancy Anis (AA) Safety Engineering Nancy Anis (AA) 09/01/2020
recommended closure time of ESDV in place If surge is identified.
0014 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 14. Ensure end to end testing of the ESD loop is carried out prior to the start-up. Refer to attached signed off Action Close out Sheet. Nancy Anis (AA) Safety Engineering Clarissa Munoz Escanilla 14/01/2020
0015 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 15. Potential SIMOP scenario will be reviewed to identify risk mitigation measure for reliability Refer to attached signed off Action Close out Sheet. Nancy Anis (AA) Safety Engineering Clarissa Munoz Escanilla 14/01/2020
of ongoing operations (i.e. checking potential neighbouring plant areas for disturbance of the
control system, relay in the panel)
0016 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 16. Raise TQ to ensure new pneumatic hook-up piping requirement is implemented. Refer to attached signed off close out sheet. No Comment Nancy Anis (AA) Safety Engineering Nancy Anis (AA) 09/01/2020
0017 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 17. The initiator in the interim stage is manumatic. Hence, operating procedure and Refer to attached Signed off (by BGC ORA & Discipline TA2) Action Close out sheet and NGL Refer to attachments. ORA-NR BGC Operations Clarissa Munoz Escanilla 31/03/2020
associated training are required for safe operation OR engineer agreement email attached.
0018 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 18. Conduct a constructability review to ensure potential risks are addressed and mitigated. Constructability review has been conducted along with WOOD Construction team and BGC Refer to attached FRR Project-Engineer Project Engineering Clarissa Munoz Escanilla 24/03/2020
construction Team , Please find the attached Action tracker with close out responses email.
generated as part of the work shop which will be part of all the CWP as reference.
0019 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 19. Conduct a site screening process to identify additional support requirement for new ESDV Refer to attached signed off close out sheet. No Comment Nancy Anis (AA) Safety Engineering Nancy Anis (AA) 09/01/2020
(up to 24” actuator) and temporary support, as required
0020 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 20. Conduct a stress analysis, including surge analysis (for Broadcut, liquid/2-phases service) Refer to attached signed off close out sheet. No Comment Nancy Anis (AA) Safety Engineering Nancy Anis (AA) 09/01/2020
to ensure system support is adequate.
0021 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 21. Final Site survey to confirm the proper design measure to ensure the requirements for Refer to attached Signed off (by BGC ORA & Discipline TA2)Action Close out sheet and NGL Refer to attachments. ORA-NR BGC Operations Clarissa Munoz Escanilla 31/03/2020
human factor aspect and adequate access for operation & maintenance are met OR engineer email agreement.
0022 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 22. Check the presence of asbestos and ensure sufficient PPE with specialist service, Refer to attached Signed off (by BGC ORA & Discipline TA2)Action Close out sheet and NGL Refer to the specific ORA-NR BGC Operations Clarissa Munoz Escanilla 10/05/2020
including safe disposal (considered as hazardous waste), are considered OR engineer email agreement. requirement for
Asbestos for Execute
phase in the attached
HSSE & SP Activity
Plan (aka HSSE & SP
Discipline Delivery
Plan) for the project.
0023 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 23. Ensure Site competency certificate is provided prior to work Refer to attached signed off close out sheet. No Comment Nancy Anis (AA) Safety Engineering Nancy Anis (AA) 09/01/2020
0024 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 24. Verify the existing safeguarding system to ensure the power supply failure scenario is For compressor stations in NR/SR, during power supply failure, compressor will trip and anti- It is noted that the BGC-ENG Process-TA2 Process Engineering Clarissa Munoz Escanilla 11/03/2020
covered for sizing of relief valve capacity. surge valve will open. In case ESDVs are installed to replace compressor suction/discharge scope for 85-6 is like
MOV, gas inventory will settle-out during compressor trip. Relief valve will need to be checked for like (i.e. ESDV to
for these cases where ESDV are replacing MOVs. ESDV). Further, there
There are 34 valves within NR NGL. The scope is like to like (ESDV to ESDV), therefore, this is an ongoing project
action is not relevant to NR NGL WG0085-6 scope. Refer to attached excel spreadsheet for Z152 which is to check
detailed valve list. the PSVs (adequacy)
across NR NGL. Refer
to attached
discussions.
0025 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 25. Confirm with the ESDV supplier to obtain certificate of NACE compliance for all ESDV. ( Refer to attached Signed off close out sheet. Nancy Anis (AA) Safety Engineering Nancy Anis (AA) 23/01/2020
Refer to Corrosion)
0026 Y WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 26. Confirm with the ESDV supplier to obtain certificate of NACE compliance for all ESDV. ( Refer to attached signed of Action close out sheet. Nancy Anis (AA) Safety Engineering Nancy Anis (AA) 23/01/2020
Refer to Material Selection)
0027 WG0085-6 Unit Isolation Valves DSR NR NGL Action Closed Out 27. A. Engage with Operation to ensure all required document are available for the PSSR All project related documentation viz, AFC P&ID, Construction Work packs , Valve specs, No Comment FRR Project-Engineer Project Engineering Clarissa Munoz Escanilla 03/03/2020
B. Ensure that prior to the PSSR, all the process safety information must be ready and up to Testing certificates, Fire certificates, Valve GA, data sheet are submitted to Asset Through
date (e.g. as-built P&IDs, C&E etc.) for further endorsement OR&A CSU During Statement of Fitness (SoF ) sign off .
C. Develop redline mark-up copy of all drawings for changes in order to revise as as-built
drawings (preparation of HAZOP review as well).
Action Summary By Status