Resume Sameh Kamel-2018 - 30jun2018
Resume Sameh Kamel-2018 - 30jun2018
Resume Sameh Kamel-2018 - 30jun2018
ENG, PMP
656 Gervais Terrace, Milton, ON, L9T 7R7
Tel. (cell): +1 (416)-890-0542
E-mail: [email protected]
EXECUTIVE SUMMARY
Twenty (20)+ years of experience working in all aspects of municipal infrastructure projects, from
design, through ground-breaking, to commissioning, including:
• Wastewater treatment plants (max $200M upgrade);
• Water treatment plants;
• WW and W pumping stations and reservoirs (max $40M upgrade);
• International projects founded by USAID and World Bank (WB) such as Secondary Cities
Water and Wastewater Projects and Second Integrated Sanitation and Sewerage
Infrastructure (ISSIP2) Project;
• Forcemains and gravity sewers;
• Airport upgrades and new commercial facilities.
EMPLOYMENT HISTORY:
2017-Present Black & Veatch Special Project (SPC), Senior Program Manager/Deputy
Team Leader
2011-17 Black & Veatch Program Management and Construction Management
(PMCM), Project Manager
2006-11 AECOM, Resident Engineer
City of Toronto - Canada | Ashbridges Bay Treatment Plant – Truck Loading Facility
Project Manager-Construction, Program Management and Construction Management
Led contract administration and construction team on the $CAD43M truck loading facility
upgrade. Project entails the upgrade to the Solids facility and expansion of the existing Biofilters.
Responsibilities included management and coordination of all on-site construction activities for
contract agreement compliance (scope, schedule, budget), and report on construction productivity
and schedule performance through monthly project progress reports.
City of Toronto – Canada | Ashbridges Bay Treatment Plant – Critical Repair Contract No.1
Project Manager-Construction, Program Management and Construction Management
Led contract administration team to undertake execution phase of $6.2M project. The objective of
the project was to maintain functional components of the plant Pumping stations until further
extensive upgrades are completed. The major responsibility of this project was to coordinate with
plant operations so as to execute construction while maintaining plant functionality.
Region of Peel - Canada | G.E. Booth WWTP –Mercury Reduction Media Remedy Project
Project Manager-Construction, Program Management and Construction Management
Led contract administration and construction team to undertake execution phase of $4.7M project.
The objective of the project is installation of caustic system that would be fed to the effluent water
tray scrubbers, so as to increase the scrubber water pH that will encourage the SO2 to remain in
solution. The major responsibilities in this project was acting as liaison and maintain a close and
effective working relationship between contractors, client, suppliers and inspectors with respect to
all site construction and design issues.
Region of Peel - Canada | Bolton Chemical Corrosion Control System, and Bolton PS
Design and Contract Administration
Responsible for leading the project team for a $CAD1.5M design and construct project for a
temporary pilot plant, including chemical supply, and pilot plant operation, sampling, monitoring,
and testing to perform a 12-month full scale pilot testing program for corrosion control on the
Brampton East Sub-Trunk system. Upgrades to the Bolton PS facility were also included.
Region of Peel - Canada | G.E. Booth WWTP - Site Preparation and Demolition Project
Resident Engineer & Contract Administration
Design and contract administration of $CAD4.1M project consisting of significant demolition of
structures, process mechanical, and associated electrical and SCADA removals located in nine
buildings, along with upgrades to the existing odour control system for the facility while
maintaining full plant operations.