Exam Prep For Students
Exam Prep For Students
ut
ib
tr
is
D
or
e
at
lic
Student Edition
up
D
ot
N
o
D
e
DISCLAIMER
ut
While Project Management Institute, Inc. takes care to ensure the accuracy and quality of these materials, we cannot guarantee
their accuracy, and all materials are provided without any warranty whatsoever, including, but not limited to, the implied warranties
of merchantability or fitness for a particular purpose. Any name used in the data files for this course is that of a fictitious company.
Any resemblance to current or future companies is purely coincidental. We do not believe we have used anyone’s name in creating
ib
this course, but if we have, please notify us and we will change the name in the next revision of the course. The use of screenshots,
photographs of another entity’s products, or another entity’s product name or service in this book is for editorial purposes only.
No such use should be construed to imply sponsorship or endorsement of the book by nor any affiliation of such entity with Project
tr
Management Institute, Inc. This courseware may contain links to sites on the Internet that are owned and operated by third parties
(the "External Sites"). Project Management Institute, Inc. is not responsible for the availability of, or the content located on or
through, any External Site. Please contact Project Management Institute, Inc. if you have any concerns regarding such links or
is
External Sites.
TRADEMARK NOTICES
D
Logical Operations, the Logical Operations logo, and CHOICE LMS are registered trademarks of Logical Operations, Inc. and its
affiliates.
PMBOK®, Project Management Institute (PMI)®, Project Management Professional (PMP)®, and Certified Associate in
or
Project Management (CAPM)® are registered trademarks of Project Management Institute, Inc. in the U.S. and other
countries. The PMI TALENT TRIANGLE and the PMI Talent Triangle logo are registered marks of Project
Management Institute, Inc. The other products and services discussed or described may be trademarks or
registered trademarks of Project Management Institute, Inc. Allother product and service names used may be
common law or registered trademarks of their respective proprietors.
e
Materials in this class are based on the A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
– Sixth Edition,Project Management Institute, Inc., © 2017.
at
Glossary definitions for terms indicated in blue italic text with an asterisk are taken from A Guide to the Project
Management Body ofKnowledge (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., © 2017 and
lic
or transmitted in any form or by any means, electronic ormechanical, including photocopying, recording, storage
in an information retrieval system, or otherwise, without express written permission of Project Management
Institute, Inc.
This book conveys no rights in the software or other products about which it was written; all use or licensing of
such software or other products is the responsibility of the user according to terms and conditions of the owner.
D
Do not make illegal copies of books or software. If you believe that this book, related materials, or any other
Project Management Institute, Inc. materials are being reproduced or transmitted without permission, please
email [email protected].
ot
N
o
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Using the PMI® Authorized PMP® Exam Prep
Student Guide
e
Welcome!
ut
Thank you for choosing the PMI® Authorized PMP® Exam Prep
course.
ib
To make the best use of the PMI® Authorized PMP® Exam Prep
tr
course materials, be sure to review all of the components of
the PMI CHOICE platform. The PMI CHOICE platform is developed
is
and hosted by Logical Operations (CHOICE LMS®) and has been
customized specifically for PMI Authorized content.
D
Preparing for Class
This document follows the course slide by slide. You can take
or
notes in this file and highlight concepts you want to revisit
or you can refer to the "Notes Handouts" documents and take
notes there.
e
at
Estimated Learning Time
The lesson durations given in the course content are estimates
based on a typical class experience. The five lessons in this
lic
• Introduction: 30 minutes
• Lesson 1 (7 topics): 8 hours
D
Hardware
3
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
• 1 gigahertz (GHz) 64-bit (x64) processor.
• 2 gigabytes (GB) of Random Access Memory (RAM).
• 32 GB available storage space.
• Monitor capable of a screen resolution of at least 1,024
× 768 pixels, at least a 256-color display, and a video
e
adapter with at least 4 MB of memory.
• Keyboard and mouse or a compatible pointing device.
ut
• Internet access (contact your local network
administrator).
ib
Software
tr
• Microsoft® Office 365™ license (which provides the
is
Microsoft Office apps)
• Microsoft® Windows® 10 Professional or Mac OS
D
Setting Up the Course
or
For each student and the instructor:
• Provide a system with Internet access and the given
hardware requirements.
e
• Install Microsoft Windows 10.
• Log in to https://login.microsoftonline.com then on the
at
Office 365 home page, select Install Office > Office 365
apps.
lic
ATPPMP1Files<ver> folder.
3. Open the ATPPMP1Files<ver> folder. It contains separate
N
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
About This Course
Course Description
e
The course enables candidates to develop professionally,
increase their project management skills, apply a formalized
ut
and standards-based approach to project management, and seek
career advancement by moving into a formal project manager job
ib
role, as well as to apply for the Project Management
Institute, Inc. (PMI)® Project Management Professional (PMP)®
certification.
tr
is
Student Profile
This course is for individuals, who have on-the-job project
D
management experience regardless of whether their formal job
role is project manager, who are not certified project
management professionals, and who might or might not have
or
received formal project management training.
Course Objectives
D
In this course, you will learn how to build and manage a team
that will plan, execute, and complete a project that is
aligned with the business environment. You will explore the
ot
following topics:
5
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
5 Environment in Mind with business strategy and its
ecosystem
e
Login and access information for your CHOICE environment will
ut
be provided with your class experience. The CHOICE platform is
your entry point to the CHOICE learning experience, of which
this course manual is only one part.
ib
On the CHOICE Home screen, you can access the CHOICE Course
tr
screens for your specific courses. Visit the CHOICE Course
screen both during and after class to make use of the world of
is
support and instructional resources that make up the CHOICE
experience.
D
Each CHOICE Course screen will give you access to the
following resources:
or
• Classroom: A link to your training provider’s classroom
environment.
• eBook: An interactive electronic version of the printed
book for your course.
e
• Files: Any course files available to download.
at
• Checklists: Step-by-step procedures and general
guidelines you can use as a reference during and after
class.
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Course Iconography
• Notes to help you contextualize the material are in
purple.
e
Notes indicate extra
ut
information that can
help you.
ib
Examples are given in
boxes cued with this
tr
icon.
is
These icons indicate
D
ideas for further
thinking or exploration
of a topic. These are
or
optional. e
at
lic
up
D
ot
N
o
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Introduction
Duration: 30 minutes
e
ut
ib
tr
is
Welcome and thank you for joining the course!
D
Let’s get to know a little about each other’s
background.
or
e
Meet your Instructor! This slide should be
at
customized with their professional
information.
lic
up
certification.
o
Course Introduction 8
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
‘The Project Economy’ is a term PMI coined
during the 50th anniversary Transformation—it
describes the work that we do and is a good
introduction to the organization.
e
ut
• PMI had its 50th anniversary in 2019.
• Earning your PMP essentially means
ib
becoming a part of the PMI community.
• Globally recognized and demanded, the
PMP demonstrates that those with this
tr
designation have the experience,
education, and competency to lead and
is
direct projects. Once you pass the exam,
you maintain the credential by obtaining
D
Professional Development Units (PDUs).
This is similar to the Certified Public
Accountant (CPA) exam and professional
or
development requirements.
https://www.pmi.org/The-
Project-Economy
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
organization that support strategic
goals and business health.
e
ECO by number. As it would be impossible to
ut
cover the entire breadth of the document in a
week, we recommend that you use it as a
checklist against your knowledge base and as
ib
guidance for what you need to learn as you
prepare to take the exam.
tr
The exam content was revised by a global
is
committee of PMPs. They devised the topics on
the new Exam Content Outline, or the ECO. The
D
ECO is a detailed list of all the domains and
tasks relevant to project management work.
You should be familiar with this document as
or
a study aid. Use it to check what you know
and what you still need to know.
e
• Domains are defined as the high-level
knowledge areas that are essential to
at
the practice of project management.
• Tasks are the underlying
lic
management.
to the course.
D
10
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
This slide introduces the format of the new
exam.
e
questions, it now features new question
formats.
ut
We’ll explore the ECO over five (5) lessons.
ib
1. Creating a High-Performing Team: We
tr
begin with the people, or leadership,
element—specifically how we create a
is
high-performing team.
2. Starting the Project: Then we begin
D
looking at “process”, and what’s
involved in starting a project.
3. Doing the Work: A further development of
or
the “process” element with a closer look
at how we do the actual work of the
project.
4. Keeping the Team on Track: A return to
e
the “people” element with how to keep
at
the team on track.
5. Keeping the Business in Mind: And
lic
11
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Glossary of Terms
80/20 rule
A general guideline with many applications; in terms of
e
controlling processes, it contends that a relatively
ut
large number of problems or defects, typically 80%,
are commonly due to a relatively small number of
causes, typically 20%.
ib
AB testing
tr
A marketing approach used to determine user preferences
by showing different sets of users similar services
is
with one independent variable.
D
AC (Actual Cost)
The realized cost incurred for the work performed on an
activity during a specific time.
accept
or
A strategy for managing negative risks or opportunities
e
that involves acknowledging a risk and not taking any
action until the risk occurs.
at
acceptance criteria
lic
active listening
A communication technique that involves acknowledging
what you hear and clarifying the message to confirm
D
activity attributes
Multiple attributes associated with each schedule
activity that can be included within the activity
N
list.
o
activity dependency
A logical relationship that exists between two project
D
12
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
activity list
A documented tabulation of schedule activities that
shows the activity description, activity identifier,
and a sufficiently detailed scope-of-work description
so project team members understand what work is to be
performed.
e
ut
activity
A distinct, scheduled portion of work performed during
the course of a project.
ib
administrative closure
tr
Involves verifying and documenting project results to
formalize project or phase completion.
is
Affinity diagram
D
A technique that allows large numbers of ideas to be
classified into groups for review and analysis.
or
agile life cycles
A project life cycle that is iterative or incremental.
Also referred to as change- driven or adaptive, they
e
work well in environments with high levels of change
and ongoing stakeholder involvement in a project.
at
agreements
Any documents or communication that defines the initial
o
analogous estimating
A technique for estimating the duration or cost of an
activity on a project using historical data from a
similar activity or project.
13
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
approved change requests
Change requests that have been reviewed and approved by
the change control board (CCB) and are ready to be
scheduled for implementation.
e
assumption and constraintanalysis
ut
A process that explores the validity of the project
assumptions within the constraints and identifies risks
from any incompleteness or inaccuracy of these project
ib
assumptions.
tr
attribute sampling data
Data that is counted such as the number of product
is
defects or customer complaints.
D
auditing
An examination of a project’s goals and achievements,
including adequacy, accuracy, efficiency,
or
effectiveness, and the project’s compliance with
applicable methodologies and regulations. It tends to
be a formal, one-sided process that can be extremely
e
demoralizing to team members.
at
autocratic
Using this group decision-making method,
lic
avoid
D
BAC
(Budget at Completion) The sum of all budgets established
for the work to be performed.
o
D
bar chart
A graphic display of schedule-related information. In the
typical bar chart, schedule activities or WBS components
are listed down the left side of the chart, dates are
shown across the top, and activity durations are shown as
date-placed horizontal bars. See also “Gantt chart”.
14
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
benchmarking
The comparison of actual or planned products,
processes, and practices to those of comparable
organizations to identify best practices, generate
ideas for improvement, and provide a basis for
measuring performance.
e
ut
benefit cost analysis
A financial analysis tool used to determine the
benefits provided by a project against its costs.
ib
benefits management plan
tr
The documented explanation defining the processes for
creating, maximizing, and sustaining the benefits
is
provided by a project or program.
D
bidder conferences
The meetings with prospective sellers prior to the
preparation of a bid or proposal to ensure all
or
prospective vendors have a clear and common
understanding of the procurement. Also called vendor
conferences, pre-bid conferences, or contractor
e
conferences.
at
bottom-up estimating
A method of estimating project duration or cost by
lic
brainstorming
A technique that involves a facilitator to help a group
identify project risks in a free-form session where
ideas are generated, built on, and recorded.
D
breach of contract
ot
burndown chart
A tool that is used to track the progress of the
o
business case
A documented economic feasibility study used to
establish the validity of the benefits of a selected
component lacking sufficient definition and that is
used as a basis for the authorization of further
project management activities.
15
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
business risk
The inherent risk in any business endeavor that carries
the potential for either profit or loss. Types of
business risks are competitive, legislative, monetary,
and operational.
e
business value
ut
The net quantifiable benefit derived from a business
endeavor. The benefit may be tangible, intangible, or
both.
ib
CCB
tr
(Change Control Board) A formally chartered group
responsible for reviewing, evaluating, approving,
is
delaying, or rejecting changes to the project, and for
recording and communicating such decisions.
D
cease and desist letter
A document sent to an individual or a business to stop
or
(cease) allegedly illegal activities and to not
undertake them again (desist).
e
change control form
A document used to request a project change. They can
at
also be recommendations for taking corrective or
preventive actions. See also “change request”.
lic
change management
The process of managing project changes in a structured
and standardized manner.
ot
change request
Request for change sent to the upper management or the
Change Control Board (CCB) for its evaluation and
approval. See also “change control form”.
checklist analysis
A technique for systematically reviewing materials
using a list for accuracy and completeness.
16
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
CI
(Continuous Improvement) The ongoing effort to improve
products, services, or processes.
e
project, phase, or contract.
ut
close-out meetings
Sessions held at the end of a project or phase; they
ib
involve discussing the work and capturing lessons
learned.
tr
co-location
is
An organizational placement strategy where the project
team members are physically located close to one
D
another in order to improve communication, working
relationships, and productivity.
or
coaching
The act of giving guidance and direction to another
person so that they can make better decisions.
e
code of accounts
at
A numbering system used to uniquely identify each
component of the WBS.
lic
communication methods
A systematic procedure, technique, or process used to
transfer information among project stakeholders.
ot
communication models
A description, analogy, or schematic used to represent
N
17
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
planned communication activities.
communication technology
Specific tools, systems, computer programs, etc., used
to transfer information among project stakeholders.
e
communications management plan
ut
A component of the project, program, or portfolio
management plan that describes how, when, and by whom
information about the project will be administered and
ib
disseminated.
tr
completion contract
A type of contract that is completed when the vendor
is
delivers the product to the buyer and the buyer
accepts the product.
D
configuration management
A tool used to manage changes to a product or service
or
being produced as well as changes to any of the
project documents such as schedule updates.
e
configuration management plan
A component of the project management plan that
at
conflict management
The application of one or more strategies for dealing
ot
context diagram
A visual depiction of the product scope showing a
o
contingency plan
A risk response strategy developed in advance, before
risks occur; it is meant to be used if and when
identified risks become reality.
18
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
contingency reserves
Time or money allocated in the schedule or cost
baseline for known risks with active response
strategies.
e
contract change control system
The system used to collect, track, adjudicate, and
ut
communicate changes to a contract.
ib
contract
A mutually binding agreement that obligates the seller
to provide the specified project or service or result
tr
and obligates the buyer to pay for it.
is
control account
A management control point where scope, budget, actual
D
cost, and schedule are integrated and compared to
earned value for performance measurement.
or
Control Procurements process
The process of managing procurement relationships,
monitoring contract performance, making changes and
e
corrections as appropriate, and closing out contracts.
at
controlling PMO
A type of PMO that provides support and requires
lic
CoQ
D
cost aggregation
Summing the lower-level cost estimates associated with
o
cost baseline
The approved version of the time-phased project
budget, excluding any management reserves, which can
be changed only through formal change control
procedures and is used as a basis for comparison to
actual results.
19
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
cost management plan
A component of a project or program management plan
that describes how costs will be planned, structured,
and controlled.
e
cost of conformance
The money spent during a project to avoid failures.
ut
This includes prevention costs that build a quality
product and appraisal costs that assess the quality.
ib
cost of non-conformance
The money spent after a project is complete because of
tr
failures. This includes internal and external failure
costs.
is
cost-reimbursable contract
D
A type of contract involving payment to the seller for
the seller’s actual costs, plus a fee typically
representing the seller’s profit.
CPAF contract
or
(Cost Plus Award Fee contract) A category of contract
e
that involves payments to the seller for all
legitimate actual costs incurred for completed work,
at
plus an award fee representing seller profit.
lic
CPFF contract
(Cost Plus Fixed Fee contract) A type of cost-
reimbursable contract where the buyer reimburses the
up
CPI
(Cost Performance Index) A measure of the cost
ot
CPIF contract
(Cost Plus Incentive Fee contract) A type of cost-
o
20
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
critical path
The sequence of activities that represents the longest
path through a project, which determines the shortest
possible duration.
e
cultural awareness
Understanding the cultural differences of the
ut
individuals, groups, and organizations in the project
stakeholder community so you can adapt communication
strategies to avoid or reduce miscommunication and
ib
misunderstandings.
CV
tr
(Cost Variance) The amount of budget deficit or surplus
at a given point in time, expressed as the difference
is
between the earned value and the actual cost.
D
daily standup
A short, 15-minute meeting in which the complete team
gets together for a quick status update while standing
or
in a circle. Also referred to as a daily scrum.
de facto regulations
e
Regulations that are widely accepted and adopted
at
through use.
de jure regulations
lic
debriefing
A less formal, more cooperative means of discussing the
positives and the negatives of the project, what
D
culture.
N
decision making
The process of selecting a course of action from among
multiple options.
o
D
decomposition
A technique used for dividing and subdividing the
project scope and project deliverables into smaller,
more manageable parts.
21
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
deliverable
Any unique and verifiable product, result, or
capability to perform a service that is required to be
produced to complete a process, phase, or projects.
e
directions of influence
ut
A classification model that groups stakeholders based
on how they influence the project: upwards (senior
management), downwards (team or specialists), outwards
ib
(external), sidewards (project manager’s peers), and
prioritization.
tr
directive PMO
is
A type of PMO that takes control of projects by
directly managing the projects.
D
discretionary dependency
A relationship that is established based on knowledge
or
of best practices within a particular application area
or an aspect of the project where a specific sequence
is desired.
e
at
document analysis
A technique used to gain project requirements from
current documentation evaluation.
lic
DoD
(Definition of Done) A team’s checklist of all the
up
DoR
(Definition of Ready) A team’s checklist for a user-
centric requirement that has all the information the
ot
EAC
(Estimate at Completion) The expected total cost of
completing all work expressed as the sum of the actual
o
EEF
(Enterprise Environmental Factors) Conditions that are
not under the immediate control of the team, and that
influence, constrain, or direct the project, program,
or portfolio.
22
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
These major risks include time, cost, quality, and
scope.
effort
The number of labor units required to complete a
scheduled activity or WBS component, often expressed
e
in hours, days, or weeks. Contrast with duration.
ut
EI
(emotional intelligence) The ability to identify,
ib
assess, and manage the personal emotions of oneself
and other people, as well as the collective emotions
tr
of groups of people. EQ is also a commonly used
abbreviation.
is
elapsed time
D
The actual calendar time required for an activity from
start to finish.
or
EMV
(Expected Monetary Value) A method of calculating the
average outcome when the future is uncertain.
e
enhance
at
A strategy for managing positive risks or
opportunities that involves increasing the probability
that the opportunity will happen, or the impact it
lic
escalate
The strategy in which you determine that a threat is
outside the scope of the project or beyond the project
D
ETC
(Estimate to Complete) The expected cost of finishing
N
EV
o
EVM
(Earned Value Management) A methodology that combines
scope, schedule, and resource measurements to assess
project performance and progress.
expert judgment
Judgment provided based upon expertise in an
23
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
application area, knowledge area, discipline,
industry, etc., as appropriate for the activity being
performed. Such expertise may be provided by any group
or person with specialized education, knowledge,
skill, experience, or training.
e
explicit knowledge
ut
Knowledge that can be codified using symbols such as
words, numbers, and pictures. This type of knowledge
can be documented and shared with others.
ib
exploit
tr
A strategy for managing positive risks or
opportunities that involves attempting to make sure
is
that the opportunity happens.
D
external dependency
Types of activity dependencies that exist between
project activities and non-project activities and can
or
be out of the project’s control.
facilitated workshops
e
Organized working sessions held by project managers to
determine a project’s requirements and to get all
at
stakeholders together to agree on the project’s
outcomes.
lic
facilitation
A skill used to lead or guide an assembled group toward
up
FF
(Finish-to-Finish) A logical relationship in which a
successor activity cannot finish until a predecessor
ot
FFP contract
(Firm Fixed Price contract) A type of fixed price
contract where the buyer pays the seller a set amount
o
24
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
float
Also called slack. See also “total float” and “free
float”.
focus groups
An elicitation technique that brings together pre-
e
qualified stakeholders and subject matter experts to
learn about their expectations and attitudes about a
ut
proposed product, service, or result.
ib
FPEPA contract
(Fixed Price with Economic Price Adjustment contract)
A fixed-price contract, but with a special provision
tr
allowing for pre-defined final adjustments to the
contract price due to changed conditions, such as
is
inflation changes, or cost increases (or decreases)
for specific commodities.
D
FPIF contract
or
(Fixed Price Incentive Fee contract) A type of
contract where the buyer pays the seller a set amount
(as defined by the contract), and the seller can earn
an additional amount if the seller meets defined
e
performance criteria.
at
free float
The amount of time that a schedule activity can be
lic
FS
(Finish-to-Start) A logical relationship in which a
successor activity cannot start until a predecessor
D
functional organization
An organizational structure in which staff is grouped
by areas of specialization and the project manager has
N
Gantt chart
A bar chart of schedule information where activities
are listed on the vertical axis, dates are shown on the
horizontal axis, and the activity durations are shown
as horizontal bars placed according to start and finish
25
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
dates.
IFB
(Invitation for Bid) Generally, this term is equivalent to
request for proposal. However, in some application areas,
it may be a narrower or more specific meaning. A type of
e
procurement document that is most commonly used when
deliverables are commodities for which there are clear
ut
specifications and when the quantities are very large. The
invitation is usually advertised, and any seller may
ib
submit a bid. Negotiation is typically not anticipated.
These are sometimes used interchangeably with RFPs.
tr
impediment
An obstacle that prevents the team from achieving its
is
objectives.
D
increment
A functional, tested, and accepted deliverable that is
or
a subset of the overall project outcome.
Influence/impact grid
up
influencing
The act of presenting a good case to explain why an
ot
information radiator
The generic term for visual displays placed in a
o
insurable risk
A risk that has only the potential for loss and no
potential for profit or gain. An insurable risk is one
for which insurance may be purchased to reduce or
offset the possible loss. Types of insurable risks are
direct property, indirect property, liability, and
26
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
personnel- related.
interactive communication
An exchange of information between two or more people
that ensures common understanding for everyone
participating in that exchange.
e
ut
internal dependency
A type of activity dependency that exists between
project activities and is usually under the project’s
ib
control.
tr
interpersonal skills
Skills used to establish and maintain relationships
is
with other people.
D
interview
A formal or informal approach to elicit information
from stakeholders by talking with them directly.
IRR
or
(Internal Rate of Return) The interest rate that makes
the net present value of all cash flow equal to zero.
e
at
issue
A current condition or situation that may have an
impact on the project objectives.
lic
issue log
A document where information about issues is recorded
up
and monitored.
iteration
D
27
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
job shadowing
See “observations”.
Kanban board
A visualization tool that enables improvements to the
e
flow of work by making bottlenecks and work quantities
ut
visible.
knowledge management
ib
Connecting individuals, in person or virtually, to
share knowledge and collaborate together.
tr
KPI
(Key Performance Indicator) A set metric used to
is
evaluate a team’s performance against the project
vision and objectives.
D
lag
The amount of time whereby a successor activity will be
or
delayed with respect to a preceding activity.
lead
e
The amount of time whereby a successor activity can be
at
advanced with respect to predecessor activity.
leadership
lic
initiatives.
lean
D
lessons-learned register
A project document used to record knowledge gained
N
lessons-learned repository
A store of historical information about lessons learned
in projects.
majority
A group decision-making method in which a majority of
group members agree on the course of action to take.
28
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
make-or-buy analysis
The process of gathering and organizing data about
product requirements and analyzing them against
available alternatives including the purchase or
internal manufacture of the project.
e
make-or-buy decisions
ut
Decisions made regarding the external purchase or
internal manufacture of a product.
ib
management reserves
An amount of the project budget or project schedule
tr
held outside of the performance measurement baseline
(PMB) for management control purposes, that is
is
reserved for unforeseen work that is within the scope
of the project.
D
mandatory dependency
A relationship that is contractually required or
or
inherent in the nature of the work.
matrix organization
e
An organizational structure in which the project
manager shares responsibility with the functional
at
managers for assigning priorities and for directing the
work of persons assigned to the project.
lic
MBI
(Minimum Business Increment) The smallest amount of
up
milestone
A significant point or event in a project, program, or
portfolio.
ot
milestone charts
A type of project schedule bar chart that only includes
N
milestone list
A document that contains the significant points or
D
events in a project.
mind mapping
A technique used to consolidate ideas created through
individual brainstorming sessions into a single map to
reflect commonality and differences in understanding
and to generate new ideas.
29
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
mitigate
A strategy for managing negative risks or threats that
involves taking action to reduce the probability of
occurrence or the impact of a risk.
e
Monte Carlo simulation
An analysis technique where a computer model is
ut
iterated many times, with the input values chosen at
random for each iteration driven by the input data,
including probability distributions and probabilistic
ib
branches. Outputs are generated to represent the range
of possible outcomes for the project.
tr
motivation
is
The inner drive that keeps people involved and wanting
to complete work of high quality in a timely fashion.
D
multi-criteria decision analysis
This technique utilizes a decision matrix to provide a
or
systematic analytical approach for establishing
criteria, such as risk levels, uncertainty, and
valuation, to evaluate and rank many ideas.
e
MVP
at
(Minimum Viable Product) The smallest collection of
features that can be included in a product for
lic
negotiated settlements
Are undertaken to arrive at a final equitable
settlement of all outstanding issues, claims, and
D
disputes by negotiation.
ot
negotiation
An approach used by more than one individual to come to
an agreement or resolution.
N
NPS
(Net Promoter Score) Measures a customer’s willingness
to recommend a provider’s products or services to
another on a scale of -100 to 100.
30
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
NPV
(Net Present Value) The present value of all cash
outflows minus the present value of all cash inflows.
observations
The techniques used to gain knowledge of a specific
e
job role, task, or function in order to understand and
ut
determine project requirements. This is also known as
job shadowing.
ib
OPA
(organizational process assets) Plans, processes,
tr
policies, procedures, and knowledge bases that are
specific to and used by the performing organization.
is
opportunity
D
A risk that would have a positive effect on one or more
project objectives.
or
organizational theory
The study of how people, teams, and organizations
behave to look for common themes for the purpose of
e
maximizing efficiency and productivity, problem
solving, and meeting the stakeholder requirements of a
at
project.
lic
outsourcing
Moving beyond the organization to secure services and
expertise from an outside source on a contract or
up
short-term basis.
overlapping relationships
A type of phase-to-phase relationship that contains
D
parametric estimating
An estimating technique in which an algorithm is used to
calculate cost or duration based on historical data and
N
project parameters.
o
Pareto chart
A histogram that is used to rank causes of problems in
D
a hierarchical format.
PDM
(Precedence Diagramming Method) A technique used for
constructing a schedule model in which activities are
represented by nodes and are graphically linked by one
or more logical relationships to show the sequence in
which the activities are to be performed.
31
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
phase gate
A point review at the end of a phase in which a
decision is made to continue to the next phase, to
continue with modification, or to end a project or
program.
e
planning package
ut
A WBS component below the control account with known work
content but without detailed schedule activities.
ib
plurality
Decisions made by the largest block in a group, even if
tr
a majority is not achieved.
is
PMIS
(Project Management Information System) An information
system consisting of the tools and techniques used to
D
gather, integrate, and disseminate the outputs of
project management processes.
PMO
or
(Project Management Office) A management structure that
standardizes the project-related governance processes
e
and facilitates the sharing of resources,
at
methodologies, tools, and techniques. PMOs are more
common in larger organizations because of the number
of projects that can be in process all at the same
lic
time.
political awareness
up
portfolio management
The centralized management of one or more portfolios to
ot
portfolio
Projects, programs, subsidiary portfolios, and operations
managed as a group to achieve strategic objectives.
o
D
Power/influence grid
A classification model that groups stakeholders on the
basis of their levels of authority and involvement in the
project.
Power/interest grid
A classification model that groups stakeholders on the
basis of their levels of authority and interest in the
project.
32
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
precedence relationship
A logical dependency used in the precedence diagramming
methods.
e
predictive life cycle
A form of project life cycle in which the project
ut
scope, time, and cost are determined in the early
phases of the life cycle.
ib
probability and impact matrix
A grid for mapping the probability of occurrence of each
tr
risk and its impact on project objectives if that risk
occurs.
is
probability distribution
D
The scattering of values assigned to likelihood in a
sample population. It can be visually depicted in the
form of a probability density function (PDF).
procurement
or
The acquisition of goods and services from an external
e
organization, vendor, or supplier to enable the
deliverables of the project.
at
procurement audit
lic
procurement documents
The documents utilized in bid and proposal activities,
which include the buyer’s invitation for bid, invitation
D
procurement SOW
D
product analysis
For projects that have a product as the deliverable, it
is a tool to define scope that generally means asking
questions about a product and forming answers to describe
33
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
the use, characteristics, and other relevant aspects of
what is going to be manufactured.
product backlog
A prioritized list of customer requirements and the
first step of Scrum in which priority is based on the
e
riskiness and business value of the user story.
ut
product box exercise
A technique used to explain an overarching solution
ib
wherein stakeholders try to describe aspects of a
solution in the same way a marketer might describe
tr
product features and benefits on a box.
is
product owner
An individual or an organization who is responsible for
D
gathering inputs about a product from the customer and
translating the requirements into the product vision for
the team and stakeholders.
product roadmap
or
A high-level visual summary of the product or products of
e
the project that includes goals, milestones, and potential
deliverables.
at
program management
lic
components individually.
program
D
progressive elaboration
The iterative process of increasing the level of detail
o
available.
project artifact
Any document related to the management of a project.
project charter
A document issued by the project initiator or sponsor
that formally authorizes the existence of a project and
34
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
provides the project manager with the authority to apply
organizational resources to project activities.
e
ut
ib
tr
is
D
or
e
at
lic
up
D
ot
N
o
D
35
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
project governance
The framework, functions, and processes that guide
project management activities to create a unique product,
service, or result to meet organizational, strategic, and
operational goals.
e
ut
project life cycle
A series of phases that a project passes through from
its start to its completion.
ib
project management plan
tr
The document that describes how the project will be
executed, monitored and controlled, and closed.
is
project management software
D
A computer application that helps plan, organize, and
manage project resources and develop resource estimates
for activities.
project management
or
The application of knowledge, skills, tools, and
e
techniques to project activities to meet the project
requirements.
at
project manager
lic
project phase
A collection of logically related project activities
D
project requirements
For a project, these are the agreed-upon conditions or
N
36
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
project scope
The features and functions that characterize a product,
service, or result.
e
project team
A set of individuals who support the project manager in
ut
performing the work of the project to achieve its
objectives.
ib
project
A temporary endeavor undertaken to create a unique
tr
product, service, or result.
is
projectized organization
A structure where a project manager and a core project
D
team operate as a separate organizational unit within the
parent organization.
prototypes
or
A method of obtaining early feedback on requirements by
providing a working model of the expected product before
e
actually building it.
at
pull communications
Messages that require the interested people to access the
lic
push communications
up
PV
(Present Value) The current value of a future sum of
money or stream of cash flows given a specific rate of
ot
return.
PV
N
QFD
D
qualified vendors
The vendors who are approved to deliver the products,
services, or results based on the procurement requirements
identified for a project.
37
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
qualified vendors list
Contains details regarding vendors who meet the
organization’s requirements and to whom requests can be
sent.
e
qualitative risk analysis
ut
A technique used to determine the probability of
occurrence and the impact of identified risk.
ib
quality audit
A structured, independent process to determine if project
tr
activities comply with organizational and project
policies, processes, and procedures.
is
quality gate
D
A special type of gate located before a phase that is
strongly dependent upon the outcome of a previous
phase. The quality gate process is a formal way of
or
specifying and recording the transition between stages
in the project life cycle.
e
quality management plan
A component of the project or program management plan that
at
objectives.
quality metric
up
quality
The degree to which a set of inherent characteristics
fulfills requirements.
ot
questionnaires
D
RACI chart
(Responsible, Accountable, Consulted, and Informed) A
common type of Responsibility Assignment Matrix (RAM)
that uses responsible, accountable, consult, and inform
statuses to define the involvement of stakeholders in
38
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
project activities.
RAM
(Responsibility Assignment Matrix) A grid that shows
the project resources assigned to each work package.
RBS
e
(risk breakdown structure) A hierarchical
ut
representation of potential sources of risk.
ib
recognition
A more personalized, intangible, and experiential event
that focuses on behavior rather than outcome.
tr
regulations
is
Requirements imposed by a governmental body. These
requirements can establish product, process, or service
D
characteristics, including applicable administrative
provisions that have government-mandated compliance.
or
relative authority
The project manager’s authority relative to the functional
manager’s authority over the project and the project team.
e
requirements documentation
at
A description of how individual requirements meet the
business need for the project.
lic
resource calendar
A calendar that identifies the working days and shifts
N
resource levelling
A resource optimization technique in which adjustments
D
39
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
resource requirements
The types and quantities of resources required for each
activity in a work package.
e
reward
A tangible, consumable item that is given to a person
ut
based on a specific outcome or an achievement.
ib
reward and recognition plan
A formalized way to reinforce performance or behavior.
tr
RFI
(Request for Information) A type of procurement document
is
whereby the buyer requests a potential seller to provide
various pieces of information related to a product or
service or seller capability.
D
RFP
or
(Request for Proposal) A type of procurement document
used to request proposals from prospective sellers of
products or services. In some application areas, it may
have a narrower or more specific meaning.
e
at
RFQ
(Request for Quotation) A type of procurement document
used to request price quotations from prospective
lic
specific meaning.
risk appetite
D
risk categorization
Organization by sources of risk (e.g., using the RBS),
N
effects of uncertainty.
D
risk impact
The likely effect on project objectives if a risk event
occurs.
40
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
risk probability
The likelihood that a risk event will occur or prove
true during the project.
e
risk register
A repository in which outputs of risk management
ut
processes are recorded.
ib
risk threshold
The level of risk exposure above which risks are addressed
and below which risks may be accepted.
tr
risk tolerance
is
The maximum amount of risk, and the potential impact of
that risk occurring, that a project manager or key
D
stakeholder is willing to accept.
risk workshop
or
A technique that uses a special meeting conducted for the
purpose of identifying project risks. In addition to the
project team members, this workshop might also include
e
the project sponsor, SMEs, customer representatives, and
other stakeholders, depending on the size of the project.
at
risk
lic
ROI
(Return on Investment) A financial metric of
profitability that measures the gain or loss from an
D
SAFe
D
salience model
A classification model that groups stakeholders on the
basis of their level of authority, their immediate
needs, and how appropriate their involvement is in
terms of the project.
41
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
schedule management plan
A component of the project or program management plan that
establishes the criteria and the activities for
developing, monitoring, and controlling the schedule.
e
scope baseline
ut
The approved version of a scope statement, WBS, and its
associated WBS dictionary, that can be changed using
formal change control procedures and is used as a basis
ib
for comparison to actual results.
tr
scope creep
The uncontrolled expansion to product or project scope
is
without adjustments to time, cost, and resources.
D
scope management plan
A component of the project management plan or program
management plan that describes how the scope will be
or
defined, developed, monitored, controlled, and validated.
Scrum master
e
The coach of the development team and process owner in
the Scrum framework. Removes obstacles, facilitates
at
Scrum team
Dedicated, self-managing, cross-functional, fully
up
Scrum
An agile framework for developing and sustaining complex
products, with specific roles, events, and artifacts.
ot
sequential relationships
A type of phase-to-phase relationship that contains
N
servant leadership
D
42
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
activity has started.
share
A strategy for managing positive risks or opportunities
that involves allocating some or all of the ownership
of the opportunity to a third party.
e
ut
simulation
An analytical technique that models the combined effect
of uncertainties to evaluate their potential impact on
ib
objectives.
tr
SLA
(Service Level Agreement) A contract between a service
is
provider (either internal or external) and the end
user that defines the level of service expected from
D
the service provider.
SoS
or
(Scrum of Scrums) A technique to operate Scrum at scale
for multiple teams working on the same product,
coordinating discussions of progress on their
e
interdependencies, and focusing on how to integrate
the delivery of software, especially in areas of
at
overlap.
lic
SPI
(Schedule Performance Index) A measure of schedule
ot
Sprint backlog
A list of work items identified by the Scrum team to be
o
Sprint planning
A collaborative event in Scrum in which the Scrum team
plans the work for the current sprint.
Sprint retrospective
This critical part of the Scrum process is attended by the
Product Owner, Scrum Master, and the Scrum team to analyze
from a process perspective what is working well and what
43
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
is not and to agree upon changes to implement.
Sprint review
A review at the end of each iteration with the Product
Owner and other customer stakeholders to review the
progress of the product, get early feedback, and review an
e
acceptance from Product Owner of the stories delivered in
ut
the iteration. Also referred to as a Demo.
ib
Sprint
A timeboxed iteration in Scrum.
tr
SS
(Start-to-Start) A logical relationship in which a
is
successor activity cannot start until a predecessor
activity has started.
D
stakeholder analysis
A technique of systematically gathering and analyzing
or
quantitative and qualitative information to determine
whose interests should be taken into account
throughout the project.
e
at
stakeholder cube
A three-dimensional classification model that builds
on the previous two-dimensional grids to group
lic
stakeholders.
stakeholder register
A project document including the identification,
o
stakeholder
An individual, group, or organization that may affect,
be affected by, or perceive itself to be affected by a
decision, activity, or outcome of a project, program,
or portfolio.
standard
A document established by an authority, custom, or
44
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
general consent as a model for example.
e
actions are taken in response to analysis of statistical
ut
sampling and other quality control activities, and as
trend analysis is performed, defects and process
variability should be reduced.
ib
statistical sampling
tr
Choosing part of a population of interest for
inspection.
is
storyboarding
D
The prototyping method that uses visuals or images to
illustrate a process or represent a project outcome.
Storyboards are useful to illustrate how a product,
or
service, or application will function or operate when it
is complete.
e
supportive PMO
The type of PMO that provides a consultative role to
at
projects by supplying templates, best practices,
training, access to information, and lessons learned
lic
SV
up
SWOT analysis
An analysis of strengths, weaknesses, opportunities,
ot
T&M contract
(Time and Material contract) A type of contract that is
a hybrid contractual arrangement containing aspects of
o
T-shaped
Refers to a person with one deep area of specialization
and broad ability in the rest of the skills required by
the team.
tacit knowledge
Personal knowledge that can be difficult to articulate
and share such as beliefs, experience, and insights.
45
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
task board
Used to visualize the work and enable the team and
stakeholders to track their progress as work is
performed during an iteration. Examples of task boards
include Kanban boards, to-do lists, procedure
e
checklists, and Scrum boards.
ut
team building
The process of continually supporting and working
ib
collaboratively with team members in order to enable a
team to work together to solve problems, diffuse
tr
interpersonal issues, share information, and tackle
project objectives as a unified force.
is
team charter
D
A document that records the team values, agreements,
and operating guidelines as well as establishing clear
expectations regarding acceptable behavior by project
or
team members.
team-building activities
The specific functions or actions taken to help the team
to develop into a mature, productive team. They can be
ot
teaming agreement
A legal contractual agreement between two or more
o
term contract
A type of contract that engages the vendor to deliver a
set amount of service—measured in staff-hours or a
similar unit—over a set period of time.
46
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
threat
A risk that would have a negative effect on one or more
project objectives.
e
three-point estimating
A technique used to estimate cost or duration by
ut
applying an average or weighted average of optimistic,
pessimistic, and most likely estimates when there is
uncertainty with the individual activity estimates.
ib
timebox
tr
A fixed period of time; for example, 1 week, 2 weeks, 3
weeks, or 1 month.
is
tolerance
D
The quantified description of acceptable variation for
a quality requirement.
total float
or
The amount of time that a schedule activity can be
delayed or extended from its early start date without
e
delaying the project finish date or violating a
schedule constraint.
at
TQM
lic
training
An activity in which team members acquire new or
D
transfer
A strategy for managing negative risks or threats that
involves shifting the impact and ownership of the risk to
N
trend analysis
D
trigger condition
An event or situation that indicates that a risk is
about to occur.
47
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
unanimity
Agreement by everyone in the group on a single course
of action.
e
assigns a particular alphanumeric sequence of characters
ut
to each element of a WBS.
ib
user story
A brief description of deliverable value for a specific
user. It is a promise for a conversation to clarify
tr
details.
is
Validate Scope
The process of formalizing acceptance of the completed
D
project deliverables.
or
A lean enterprise technique used to document, analyze,
and improve the flow of information or materials
required to produce a product or service for a
e
customer.
at
value stream
An organizational construct that focuses on the flow of
lic
variance
A quantifiable deviation, departure, or divergence away
ot
variance analysis
A technique for determining the cause and degree of
difference between the baseline and the actual
o
performance.
D
version control
A system that records changes to a file, in a way that
allows you to retrieve previous changes made to it.
virtual team
A group of people with a shared goal who fulfill their
roles with little or no time spent meeting face-to-
face.
48
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
waiver
The giving up of a contract right, even inadvertently.
warranty
A promise, explicit or implied, that goods or services
e
will meet a predetermined standard.
ut
WBS dictionary
A document that provides detailed deliverable,
ib
activity, and scheduling information about each
component in the work breakdown structure.
tr
WBS
is
(work breakdown structure) A hierarchical decomposition of
the total scope of work to be carried out by the project
team to accomplish the project objectives and create the
D
required deliverables.
or
work package
The work defined at the lowest level of the work breakdown
structure for which cost, and duration are estimated and
managed.
e
at
work performance data
The raw observations and measurements identified during
activities being performed to carry out the project
lic
work shadowing
D
49
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
e
ut
ib
tr
is
D
or
e
at
lic
up
D
ot
N
o
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
e
Student Edition
ut
ib
tr
is
D
or
e
at
lic
up
D
ot
N
o
D
Lesson 1
Create a High-Performing Team
PMI® Authorized PMP® Exam Prep
Lesson 1: Creating a High-Performing Team 1
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Creating a High-Performing Team
Lesson Time: 8 hours
e
Lesson Introduction
ut
The success of your project depends on the people involved. The project team
members are vital to doing the work of the project efficiently and effectively. The
stakeholders connected to the project have the ability to help or hinder a project’s
ib
success and therefore need to be kept engaged along the way. A key role of a
project manager is the assembling and managing of the project team and any
tr
additional stakeholders. High-performing teams have a shared understanding of and
commitment to the project and possess the appropriate training that empowers them
is
to do the work.
D
In this lesson, you learn what’s involved in creating a high-performing project team.
This lesson addresses tasks from the People domain of the PMP® Exam Content
Outline.
Lesson Objectives or
e
In this lesson, you will learn how project managers and teams:
at
Lesson Topics
Title Slides
N
e
You need talent, skill, and people who can get the project going. Let’s take a look at
ut
what it takes to build a team!
ib
tr
is
D
Build a Team
or
Finding the talent, giving the motivation and inspiration to
do their best—this is your first and foremost
e
responsibility.
at
Building a Team
ot
e
ut
Roles on the project team can include:
✓ Project management staff members who perform
activities such as budgeting, scheduling, reporting
ib
and control, risk management, and project
communications. This role may be supported by a
tr
PMO.
✓ Project staff members who perform the work to
is
create the project deliverables.
✓ Supporting experts who perform work to develop
D
the project management plan. These roles can
include legal, logistics, engineering, testing, and so
on.
or
✓ Business partner members that support the
business partnership.
e
at
Project Teams
lic
e
need to identify the other physical supports that the
ut
team members will require to be able to perform—
equipment, access rights, etc.).
• The Plan Resource Management process
ib
encompasses both planning for the team members
and for the physical resources those team members
tr
will require to perform.
is
Stakeholder (Definition)
D
A stakeholder is an individual, group, or organization that
may affect, be affected by, or perceive itself to be
or
affected by a decision, activity, or outcome of a project,
program, or portfolio.
Project Stakeholders
o
•
D
e
project team, which are not?
ut
Which are typically active in
project work?
ib
Stakeholder Identification
tr
•
is
Identify internal and external stakeholders of a project
as early as possible, learn what their needs are, and
secure their participation in defining the project's
D
parameters and success criteria.
• Although it may be difficult to negotiate a consensus
or
early in the project, it is far less painful and costly
than getting to the end of the project only to learn that
someone's needs were not met or were
misunderstood.
e
• Stakeholders are the people best able to help the
at
project succeed, as they have a specific interest in
the project objectives and its success.
•
lic
model.
Stakeholder Identification – Tools & Techniques
D
e
completion of the project and whose needs or
ut
expectations need to be considered.
ib
Management Plan should provide the names of the
stakeholders.
tr
is
Stakeholder Register
D
individuals or entities.
• Project Role – Position on the project or job title in
or
the organization.
• Major Requirements – Which of the project
requirements are they concerned with?
• Expectations – Take note of their expectations of the
e
project. You will have learned this during an interview,
at
for example.
• Influence – What degree of impact can this
lic
or not?
• Supporter? – Note this stakeholder’s view of the
project. Is it supportive, tolerant, resistant, critical, and
ot
e
A use case about circuit board production is given on the
ut
next slide.
RACI Chart Example
ib
The RACI matrix helps identify who is responsible for
making decisions and how the people responsible are
tr
supported. RACI is generally used to provide clarity on
is
the roles and responsibilities assigned to each project
team member.
D
Team Skills Appraisal
or
The project leader needs to perform an assessment of
team members for skills, aptitude, attitude, work style,
and other characteristics.
e
Assessments of the team members and the team
at
holistically enable the team to:
• Identify its strengths and weaknesses
lic
• Aspirations
• Information processing and organization
• Decision-making processes
ot
Pre-Assignment Tools
e
Diversity, Equity, and Inclusion (DEI)
ut
Diversity, Equity, and Inclusion, or DEI, is an established
human resource component or initiative in most global
ib
workplaces.
tr
has diversity. People come from different
backgrounds of gender, language, ability or disability,
is
nationality, and so on.
• DEI initiatives work towards establishing equitable
D
and “psychologically safe” workplaces, which is a
practice element in Disciplined Agile.
•
or
You should seek to create an environment that takes
advantage of this diversity and builds a team climate
of mutual trust.
• Team DEI development objectives might include:
e
• Improving team knowledge and skills to reduce
at
cost and time and improve quality.
• Improving trust to raise team morale, reduce
conflict, and improve teamwork.
lic
controlled.
o
• Identification of resources
• Acquisition of resources
• Roles and responsibilities
• Roles—The function of the person in the project.
e
• Project Organization Chart—Defines the project team
ut
members and their reporting relationships.
• Team resource management—Guidance on the
lifecycle of the team resources, how they are defined,
ib
staffed, managed, and eventually released.
• Training strategies and requirements.
tr
• Team development methods to be used.
• Resource controls for the management of physical
is
resources to support the team.
• Recognition Plan—How team members are rewarded
D
and recognized.
or
resources, they will produce a resource calendar that
identifies the following:
• Working days, shifts, hours, weekends, and holidays
• Physical resource availability
e
• When and for how long resources will be available
at
during the project
• Attributes such as skills, experience levels, and
lic
geographies
Virtual Teams
up
Virtual teams:
• Are defined as a group of people with a shared goal
ot
e
electronic collaboration so that everyone on the
ut
team can reliably transmit and access information
from one another can be challenging.
o Because roles, reporting, and performance can be
ib
harder to track on a dispersed team, individual
contributions may be overlooked.
tr
Virtual Team Considerations
is
Let’s follow and fill in this flow chart about virtual team
work.
D
• Top row – Considerations or benefits of virtual teams
• Middle row – Challenges associated with virtual
•
teams
or
Bottom row – Solutions to the challenges
e
Idea: We’ve proposed two
at
possible solutions to the
challenges of “managing
communications” and “Enabling
lic
e
implementations, and the nuances of this project?
ut
• Skills: Does the team member have the relevant
skills?
• Attitude: Does the team member have the ability to
ib
collaborate with the other team members?
• International factors: Consider team member
tr
location, time zone, and communications needs.
Rates
is
Each resource has a cost factor. This explains how you
D
work with the cost factor of resources.
or
The project manager is responsible for project budget
and disbursements. Resource requirements should be
met using the most cost-effective resource given the
needs of the project, resource availability, and other
e
factors.
at
Resource Assignment
lic
Project schedules
e
this stage.
ut
Knowledge Transfer in and Between Teams
ib
Make a plan for how you will capture and share
tr
knowledge within your team and then make it available
for concurrent or future teams. Let’s take a look at how
is
project managers set up teams for successful knowledge
sharing and transfer.
D
Facilitate collaboration and promote visibility of work.
Manage knowledge sharing among team members,
or
especially on virtual teams.
Check the team charter for knowledge sharing
methods, including:
o Frequency of updates
e
o Version control
at
o Supporting tools and agreed approach to their
use
lic
e
ground rules based on context, such as organizational rules and team dynamics.
ut
ib
Define Team Ground Rules
tr
working ground rules.
is
D
Deliverables and Tools
This is a list of the deliverables and tools associated
or
with this topic. These slides are provided to help you
match up project tools and deliverables with tasks.
e
at
Teams Norms
lic
e
ut
Team Charter (Definition)
ib
to establish its values, agreements, and practices as it
performs its work together
tr
is
Team Charter
D
A good team charter should include:
tools.
or
• Guidelines for team communications and the use of
improvement activities).
management context.
• Ground rules are included in the project charter.
D
Ground Rules
e
deciding how violations will be dealt with, the team
sets expectations for itself, and provides itself a tool
ut
to maintain and norm its performance.
• The project manager seeks to create an environment
ib
where the teams can perform effectively and build
trust.
• Ground rules contribute to these ends by enabling
tr
the team to take ownership of its rules, set
expectations for itself around how the team will
is
operate together, and establish effective
mechanisms to handle conflicts that will inevitably
D
occur.
• Key objectives include:
• Facilitating effective team collaboration
or
• Promoting visibility of work and progress
• Enabling the team to self-organize and self-
manage as much as practicable
e
at
Negotiation Skills
lic
e
The team should focus on its core values when
addressing “serious” violations. Accountability, shared
ut
expectations, and transparency are paramount.
ib
Idea: Have you been on a project
in which clear ground rules would
tr
have prevented conflict?
is
GUIDELINES: Manage and Rectify Ground
Rule Violations
D
• When the team establishes its charter, it sets
expectations for the ground rules about how the
• or
team is to operate, and what methods will be used
to handle conflicts that occur.
For violations of the team’s ground rules, the team
e
and the project manager should assess
at
opportunities for remediation
• If the violation is serious—and it’s a good idea to
define levels of violations—the team may need to
lic
e
reach an agreement about the project objectives.
ut
ib
Negotiate Project Agreements
tr
This is the third topic in Lesson 1. We explain a few
concepts and artifacts in the first few slides before
is
discussing the negotiations process.
D
Deliverables and Tools
This is a list of the deliverables and tools associated with
or
this topic. These slides are provided to help you match
up project tools and deliverables with tasks.
e
at
Project Agreement Objectives
This is an overview of how you’ll be able to monitor the
lic
Agreements:
e
(functional performance) and service warranty
(including availability, speed, security, continuity, and
ut
other usability expectations).
• Can take the form of contracts, MOUs, SLAs, letters,
ib
verbal, or email correspondence.
tr
define the expected level of performance. Ideally,
effective SLAs should reflect business-driven metrics,
is
including such things as transaction processing,
customer satisfaction, etc.
D
Reaching Agreements in Negotiations
or
As we learned in the first topic, negotiations are
discussions that are aimed at reaching an agreement.
e
As part of an external procurement, the agreement may
specify the rights, obligations, and terms of a purchase in
at
order to facilitate a mutual agreement prior to signing a
contract.
lic
Negotiation Strategy
needed.
e
Idea: Can you differentiate
ut
between the items in this list?
Which are used in reaching an
ib
agreement and which are the
produced because of an
tr
agreement?
Prioritization Techniques
is
When thinking about what work needs to be done to
D
produce project deliverables or outcomes, you have to
prioritize.
or
Project managers may be asked to help the customer
prioritize the list of work. In this case, you can use a
prioritization technique.
e
Prioritization techniques include:
at
Product (MVP).
• Paired Comparison Analysis - Looking at each pair
of stories and prioritizing one over the others.
• 100 Points Method - Each stakeholder is given 100
points and can multi-vote their points across all the
stories, which then give a weighted priority when
combined.
e
Example metrics might include:
ut
• Percentage of work completed
• Quality and technical
ib
performance metrics
• Start and finish of scheduled
tr
activities
• Change requests
• Defects
is
• Actual costs and durations
D
Work performance data is defined as the raw
observations and measurements identified during
or
activities that are part of project work.
management processes.
N
Experts
o
e
ut
Resource Calendars
ib
Use a calendar to determine resource availability during
a planned activity period. Then take this into account
tr
when estimating project activities.
is
The calendar may also identify key resource attributes
such as skills and experience levels to ascertain if the
D
resources with the proper skills to carry out certain types
of work will be available during different aspects of the
project.
or
Review Team Performance and Identify Lessons
Learned Regularly
e
You may not think this is a task to complete before
at
project kickoff, but it is.
Lessons Learned
We’re using the term “lessons learned” here, but these
ideas are similar in agile project retrospectives.
e
at the end of each iteration to identify potential issues,
solutions, and improve the processes the team uses to
ut
improve its overall performance.
Special Intervals
ib
Down time during work often causes disruption and
tr
distress, so be sure to identify and include reasons for
down time in your negotiations and agreements for
is
project work.
D
“Blackout” or “Go Live” times are often necessary during
production of work.
or
e
at
lic
up
D
ot
N
o
D
e
team strengths, and set up systems to ensure the teams are accountable for their
ut
tasks.
ib
Empower Team Members and Stakeholders
tr
Welcome to the fourth topic in this lesson! Let’s discuss
is
why empowering team members and stakeholders is an
essential part of building a high-performing project team.
D
Deliverables and Tools
or
This is a list of the deliverables and tools associated with
this topic. These slides are provided to help you match
up project tools and deliverables with tasks.
e
at
Team Strengths
lic
e
seek consensus, but the team may want
to identify how they will respond when
ut
consensus can't be reached; for example,
by deciding in advance to take the highest
ib
estimate in case of persistent
disagreements.
tr
Brainstorming
is
Brainstorming is an ideation technique. It empowers team
D
members and stakeholders by enabling everyone to
become involved in generating the ideas that lead to
solutions and decisions.
or
In brainstorming, a facilitator works with the team to
identify a series of potential solutions to a given problem
e
and then performs various types of analyses to assist the
team in selecting the most appropriate alternatives.
at
Estimates
lic
•
ot
e
ut
Team Task Accountability
ib
responsibility for work. Effective project managers
generally encourage the team members themselves to
tr
"self-organize" for them to determine the work that must
be done in order to meet an objective, to identify how to
is
perform that work and who should perform it.
D
Focus on visibility and collaboration by using Gantt charts
or Kanban boards.
or
It is critical to have visibility on who is performing which
tasks and when to ensure effective collaboration and use
of team resources. This may be tracked and managed as
e
part of a large project schedule or more simply on team
task boards that facilitate collaboration and promote
at
visibility across the team.
lic
Retrospective
up
together.
D
e
• Set the Stage - Do some kind of check-in activities
ut
to engage the team.
• Gather and Share Data - Team Performance
ib
metrics, Earned Value Analysis, etc.
• Generate Insights - What’s working? Where are
tr
challenges? Problem Analysis.
• Make Decisions - Agree on 1-2
is
improvements/changes to try in the subsequent
iteration.
• Close - New Information, Appreciation, and Thank-
D
Yous.
or
GUIDELINES: Evaluate Demonstration of Task
Accountability
e
The project manager should determine how task
at
accountability will be tracked and managed.
e
managers should defer appropriate decisions to the
ut
team, while maintaining control and visibility into the
overall plan and progress.
ib
• Enable team members to identify, plan, and manage
tasks as much as possible by the team members
tr
themselves. They are the ones closest to the work
and will have the best visibility into what needs to be
is
done to perform the work and deliver the needed
results.
• Teams performing the work also should estimate the
D
work. Especially in teams where a number of
different people are sharing the overall workload, not
or
every team member can perform a certain amount of
work in the same time. Using relative estimates helps
the team focus on the rough overall level of work
without getting too precise on the exact number of
e
hours it will take; hour estimates may differ widely
at
based on risk, the level of innovation required, and
who will actually be performing that work and their
lic
e
stakeholders are adequately trained.
ut
ib
Train Team Members and Stakeholders
tr
This is the fifth topic in this lesson.
is
D
Deliverables and Tools
This is a list of the deliverables and tools associated with
or
this topic. These slides are provided to help you match up
project tools and deliverables with tasks.
e
at
Training and Coaching Plan
lic
e
Here are some guidelines:
• When – Timing is important. Skill training for a
ut
deliverable (product or service) should happen close
to the time of delivery or implementation to avoid
ib
delays and to ensure the customer accepts the
product or service successfully.
• Which – How do you decide which training, coaching,
tr
and mentoring activities you need to have for your
is
high-performing team? A gap analysis is a great
method.
• Formalization through certification – Consider
D
whether the team, the project, or the organization
would benefit from pursuing specialized certifications.
or
They can be a valuable investment.
• Scope – In addition to technical and practical skills,
also consider soft skill training, or knowledge or
experience sharing.
e
T-Shaped Skills
at
as “T-shaped”.
Required Competencies
ot
needed.
D
e
Consider from the many forms of training available:
ut
• Instructor-led, classroom – physically present or co-
located
ib
• Virtual classroom, instructor-led
• Self-paced eLearning
• Document review
tr
• Interactive simulations
• On-the-job training
is
Training Options
D
This table describes some of the training methods we just
listed. Let’s explore them a bit more.
or
This course is delivered as either a live (in-person) or
online, instructor-led training through a virtual
e
environment. Simulated, hands-on labs are often made
available this way as well.
at
e
Some trainings end with a training credential, or topical
ut
certification: a certificate or badge are examples.
ib
Beyond that are professional certifications. An industry
certification demonstrates credibility of expertise or skill.
tr
Industry credentials are portable and may be a desirable
reward for the certification holder, as this demonstrates
is
their knowledge and skills to a wider audience for
advancement or employment opportunities. Investing in
certification for your team shows them that you and/or the
D
organization are helping them improve their skill set.
or
The PMP®, for example, is an industry-
recognized and premier professional
certification.
e
at
Baseline and Post-Training Assessments
e
up and help your virtual team become effective and high- performing, and to
ut
continually evaluate the effectiveness of virtual team member engagement.
ib
Engage and Support Virtual Teams
tr
This is the sixth lesson in this topic. We mentioned virtual
teams earlier, noting especially the challenges. Now, it’s
is
time to delve a bit deeper in this topic.
D
Deliverables and Tools
or
This is a list of the deliverables and tools associated with
this topic. These slides are provided to help you match up
project tools and deliverables with tasks.
e
at
Collaboration Technology
lic
e
Any combination of these types of tools can be useful, if
ut
your team has decided how to use the tools to help the
team promote visibility and enable collaboration.
ib
Virtual Team Member Needs
tr
Let’s shift now to what a virtual team needs to thrive.
is
The list begins with the basics:
D
• A shared goal
• A clear purpose
• Clarity on their role and what is expected of them.
or
Because the team is not co-located, project managers of
virtual teams will spend a substantial amount of their time
e
"knocking down virtual walls" to ensure the teams are
able to effectively collaborate and operate as a team, and
at
not just a series of isolated individuals.
lic
to solve problems.
e
Note: While these technologies can
ut
certainly support your team’s endeavors,
how the team uses the tools and how
ib
well the tools' use reflects the team’s
values and priorities is critical.
tr
is
For example: If the team doesn't keep
the information on a task board current,
it's always out of date, and people can't
D
make decisions or pull work based on
what the board says, thus defeating a lot
or
of the purpose.
Communication
e
While it's trite to say that communication is key, it clearly
is. Successful teams get to be successful by working
at
on getting results.
e
achieve the team’s objectives. While all teams need
people with certain subject matter expertise and
ut
capabilities, effective teamwork, collaboration, and
communications are especially important in whether the
ib
virtual team will be able to perform effectively.
tr
This is especially important in virtual teams.
is
As new members may join the team over time, the team
itself will need to go through the process of re-forming,
storming as necessary to produce a new set of team
D
norms, and then begin the process of continual
improvement as the team strives for greater efficiency and
or
effectiveness.
Communications Plan
up
e
Team Member Engagement
ut
Key guidelines for implementing effective virtual teams
ib
include:
• Focus on collaboration and team norms before
focusing too much on tools. Allow team members to
tr
figure out how and why they need to communicate
and collaborate with one other, then look at how
is
technologies and tools can help.
• Recognize that team formation in a virtual
D
environment is difficult, so it's critical to reinforce the
teams' mutual commitments, achievements, and
opportunities.
or
• Virtual teams will require a significant amount of
feedback and reinforcement of the team goals and
objectives, or collaboration will quickly devolve to
e
individual behavior and performance instead of the
team’s shared goals.
at
Calendar Tools
status.
• In general, timeboxing meetings is a good idea. It:
o Improves focus,
N
e
The project manager may produce variance analysis of
ut
different kinds as the team carries out its work. Variance is
defined as a quantifiable deviation, departure, or
ib
divergence away from a known baseline or expected
value. Variance analysis may include:
• Accuracy of team estimates
tr
• Delivery in a sprint or by an established milestone
• Team performance against targets—perhaps
is
measured by story points completed or successful
burndown during an iteration.
D
Results of a variance analysis may be shared with the
or
team as part of a retrospective and may serve as the
basis for problem solving, identification of lessons learned,
and proposed experiments to improve team performance
in subsequent iterations.
e
at
Use the results to motivate and challenge team members
in positive ways.
lic
e
consensus and support the outcome of the parties' agreement.
ut
ib
Build a Shared Understanding About a Project
tr
A shared understanding is more than scope, schedule,
is
and objectives. It’s enabling our team to understand the
importance of the project to the organization’s strategic
D
objectives.
Deliverables and Tools
or
This is a list of the deliverables and tools associated with
this topic. These slides are provided to help you match
up project tools and deliverables with tasks.
e
at
Project Vision
lic
be reasonably consistent.
e
authority to apply organizational resources to project
activities.
ut
The project initiator or sponsor is a person who provides
ib
resources and support for the project and is accountable
for enabling the project's success. An effective project
tr
charter conveys why the project is being initiated and
what the project's outcomes will be, ensures that you
is
have support for the project, and gives you the authority
to apply resources to project activities.
D
Project Charter Contents
or
The project charter contains much of the information that
a team member needs to understand the value, content,
and importance of a project.
e
Idea: Brainstorm exactly how
at
understanding of a project.
Project Overview Statement
up
It should:
• Be brief and clear.
ot
Once you have all of these elements in place, it’s time for
kickoff.
e
This is the moment in the project where the planning
leads to action. It’s usually a meeting in which a few
ut
things need to happen:
• Establish the project context
ib
• Assist in team formation
• Ensure that the team is aligned to the overall project
tr
vision
is
Activities during kickoff may include:
• Define the vision statement
• Define the team charter
D
• Facilitate creation of the following with your customer
or product owner:
or
o User story writing
o Estimation of effort
o Prioritization planning
o Initial product backlog
e
Iteration Planning
at
e
objectives for the iteration, identify potential blockers,
and coordinate the day’s work.
ut
In a Sprint Review at the end of each iteration, the
Product Owner and other customer stakeholders
ib
review progress and receive feedback for that
iteration.
tr
A Scrum Master facilitates a Sprint Retrospective
for the team to identify improvements. They review
the team’s processes and practices and identify ways
is
to improve performance and collaboration.
D
Task Boards
or
understanding. By making data visible, everyone has
access to it. This creates an atmosphere of transparency
and information-sharing.
e
at
Consensus (Definition)
lic
Reach Consensus
Estimation Techniques
D
e
ut
Product Box – Collaboration Game
ib
Another technique of explaining a solution is “product
box”. It can work like an “elevator pitch”. Basically, we are
tr
encouraging the explanation of a complex idea in parts so
that everyone can understand.
is
GUIDELINES: Reach Consensus and Support the
D
Outcome of the Parties’ Agreement
or
it, even if they have a different, personal point of view.
team.
lic
End of Lesson 1
This is the end of the first lesson. The next lesson takes
up
or
e
at
lic
up
D
ot
N
o
D
Lesson 2
Starting the Project
PMI® Authorized PMP® Exam Prep
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Starting The Project
Duration: 10 hours
Lesson Introduction
e
Now that you've assembled a high-performing, engaged, and empowered project
ut
team, you are ready to plan and start the project.
ib
Planning includes all aspects of a project, including budget, schedule, scope, quality,
project activities, procurement, and closure. You also need to determine the
tr
appropriate project methodology or method.
is
Learning Objectives
D
In this lesson, you will learn how project managers and teams:
or
• Assess project needs, complexity, and magnitude to determine the appropriate
project methodology/methods and practices.
• Plan and manage the scope.
e
• Plan, prepare, modify, and manage the project schedule based on methodology.
• Plan and manage the budget and resources.
at
Lesson Topics
D
Title Slides
ot
Topic A
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Determine Appropriate
Project Methodology/Methods and Practices
Every project is unique, even if it’s been done before. You need to understand which
e
methods suit the type of work and outcomes. There is no one way to manage every
ut
project. Knowing and understanding project management best practices is one part
of the equation. Determining and applying the most appropriate methodology and
practices to your project is another part.
ib
tr
Here’s what we’ll cover in this lesson. Let’s learn about
how to start project work!
is
D
or
Determine Appropriate
Project Methodology/Methods and Practices
e
This is the first topic in our learning about how to start a
at
project. We’ll learn about project management methods
and practices.
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
The business needs document expresses the goal—what
needs to be created or what needs to be performed.
e
goal.
ut
Project Implementation Plan
ib
The goal of any project is to deliver some product or
service for a customer, whether internal or external to the
tr
organization.
is
Depending on what the product or service is, the team
should select the methodology that fits. Usually, this
D
means which method delivers value to the organization
most quickly. Additionally, project planning should ensure
minimal negative disruption to the business and address
or
concerns relative to the project and business
environment.
e
Project Implementation Plans should consider all
stakeholders, schedules, risks, budgets, and quality
at
standards.
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
have a full picture or all of the details
• It’s a form of progressive elaboration (we’ll define
that in the next slide), that you apply to work
packages, planning packages, or release planning.
e
Rolling wave planning works in this way: teams
decompose work down to level of known detail during
ut
strategic planning. And as work progresses, they continue
decomposing work packages into activities.
ib
We will ensure you understand each of these terms later in
this lesson.
tr
Progressive Elaboration (Definition)
is
Progressive elaboration is the iterative process of
D
increasing the level of detail in a project management plan
as greater amounts of information and more accurate
estimates become available.
or
Overview: Project Management Methodologies,
Methods, and Practices
e
at
There may not be an ideal approach to manage your
project, but experienced project managers can choose the
lic
and Hybrid.
much as needed.
o The aim is to deliver value early by regularly
confirming and incorporating input.
o The team’s work, together with the
customer’s input, drives the project forward.
• Predictive / Plan Driven - A more traditional
approach wherein, as much as possible, the project
needs, requirements, and constraints are
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
understood at the beginning of the project, and
plans are developed accordingly.
o Those plans drive the project forward.
o The more well planned out, the more
predictive and controlled the project is.
e
• Hybrid – A third option is to incorporate components
of both approaches.
ut
Examples are:
ib
• Using a particular strategy or
technique from one methodology
tr
for a certain need.
• Blending the various approaches
is
concurrently on the project.
• Switching approaches based on
D
need, changing work
requirements, or circumstances.
Types of Life Cycles
or
A life cycle is a way of describing the nature and trajectory
of a project.
e
•
at
There are two major types of project life cycles:
predictive and adaptive.
• ‘Hybrid’ is exactly that, a blend of the two.
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Predictive Life Cycle
e
element of control—and, thus, predictability—in projects
which follow a predictive life cycle.
ut
Adaptive and Hybrid Life Cycles
ib
There may be fewer and fewer cases of projects that can
adopt purely predictive life cycles. That’s because we are
tr
living in an age of high complexity and change, where
predicting outcomes is fraught with difficulty, and business
is
needs and conditions, as well as external environmental
factors change rapidly and without notice.
D
The adaptive life cycle enables projects to operate with
flexibility so that plans can respond effectively to change.
Hybrid Methods
or
e
A balance of the two life cycles is often the necessary
compromise. Teams can combine predictive and adaptive
at
approaches to adopt a hybrid method of working and to
balance the business’s need for predictable outcomes
lic
undefined environments.
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
changing objective and scope or when partial delivery of
the objectives provides value.
e
deliverable. Most often, deliverables from one phase are
approved before work begins on the next phase.
ut
For example: Design specifications are
ib
approved and handed off before the
design phase begins. However, a
subsequent phase may begin before
tr
approval is gained on the deliverables of
a previous phase, if the risks are
is
considered acceptable. It helps the
project management team plan work to a
D
greater level of detail as the project
progresses.
or
This cycle is like an extension or corollary of the
overlapping relationship, but in this case the same phase
repeats itself multiple times—once in every iteration.
e
•
at
In an iterative life cycle, the project scope is
generally determined early in the project life cycle,
but time and cost estimates are routinely modified
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
successively add functionality within a
predetermined time frame. The deliverable contains
the necessary and sufficient capability to be
considered complete only after the final iteration.
e
Both types of life cycles include project phases that are
intentionally placed and repeated as the team's
ut
understanding of the deliverables is developed and
understood. In most cases, the team will work with a high-
ib
level vision because the deliverables will be defined up
front and developed with more detail and characteristics as
the project moves through each phase.
tr
is
Adaptive Life Cycles
D
Moving on from iterative and incremental, we have the
world of ‘agile’, which has become a catch-all for non-
predictive approaches. But let’s try to understand what
or
they really are.
project.
• This is similar to iterative and incremental life
cycles, but they move at a much more rapid pace.
up
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Typical Use Cases
e
the expectations of stakeholders.
ut
Idea: Look at the examples on the first
two rows. Can you think of examples for
ib
the last three rows?
tr
is
D
or
e
at
lic
up
D
ot
N
o
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Topic B: Plan and Manage Scope
The project team must complete work in order to achieve project outcomes.
e
What that work is, what must be done, guiding that work, ensuring the work is done,
and setting criteria as to what “done” is, so it can be properly validated are all
ut
elements the project team must plan for and manage throughout the project.
ib
Plan and Manage Scope
tr
In the second (and longest) topic of this lesson, we look
at how to plan for the project’s scope. As we’ll see,
is
there is a lot of work involved in managing the effort and
the scope of the project.
D
Deliverables and Tools
This is a list of the deliverables and tools associated
or
with this topic. These slides are provided to help you
match up project tools and deliverables with tasks.
e
at
11
Lesson 2: Starting the Project | Topic B
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Scope Management Tools and Techniques
e
• Use internal and external experts that have
ut
experience in similar projects to apply expert
judgment. These individuals can be consulted
when you are ready to put the plan together.
ib
• Alternatives analysis is a technique used to
identify different ways of collecting requirements,
tr
elaborating the project and product scope,
creating the product, and validating and
is
controlling the scope. This analysis can have an
influence on the scope management plan.
•
D
Hold meetings with any team member who will
be involved with the creation of the scope
management plan.
or
Project Requirements (Definition)
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
For example: Some of the
requirements for a new house might
include the square footage of each
room; the type of counter tops needed
in the kitchen and each bathroom; a
e
central vacuuming system; and the
size and materials used for a deck.
ut
Any project will have many requirements, and it is
ib
important to determine the requirements early in the
project.
tr
Throughout the life of the project, the requirements may
change. Stakeholders might add new requirements
is
during the project—sometimes even during project
execution—as well as changing others.
D
Project Scope (Definition)
or
This is the work performed to deliver a product, service,
or result with the specified features and functions.
“Project scope” may include “product scope.”
e
at
Tolerances
o
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
For example: Project A has set a
tolerance so that the project manager
can control issues with a budget or
time variance of less than 5% but be
e
required to escalate any variances that
exceed that threshold.
ut
Enterprise Environmental Factors (EEFs) –
(Definition)
ib
EEFs are things outside out the project team’s control.
tr
These are internal or external conditions that influence,
constrain, or direct the project at organizational,
is
portfolio, program, or project level.
D
Organizational Process Assets (OPAs) –
or
(Definition)
influences.
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Document Analysis (Definition)
e
ut
Document Analysis
ib
The document analysis method can be used to derive
new project requirements from existing documentation
tr
such as business plans, service agreements, marketing
materials, current process diagrams, application
is
software documentation, and more.
D
Focus Groups (Definition)
or
Focus groups are an elicitation technique that brings
together pre-qualified stakeholders and subject matter
experts to learn about their expectations and attitudes
about a proposed product, service, or result.
e
at
Focus Groups
lic
people.
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Questionnaires and Surveys (Definition)
e
subject.
ut
Questionnaires and Surveys
ib
This technique is useful when the group is varied and
located in multiple locations.
tr
The results of the questionnaires and surveys can be
is
sent out and returned quickly and the results can be
analyzed in a timely manner.
D
In most cases, the results will be used to conduct a
statistical analysis and used by decision makers to
or
prioritize, categorize, and determine requirements.
Benchmarking (Definition)
measuring performance.
Benchmarking
ot
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Interviews (Definition)
e
ut
Interviews
ib
Through discussion, you can record any pertinent
information you need for your project requirements.
tr
With this information, you can further identify and define
is
specific project outcome features and functions.
D
For example: An interview might
be helpful when you need to get
specific feedback from an end
or
user of a product or service to
find out what is useful and what is
not.
e
Group Decision-Making Techniques
at
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
in views about a subject.
• Plurality - Decisions made by the largest block
in group, even if a majority is not achieved.
• Autocratic - Using this method, one person
makes the decision. In most cases, this person
e
will consider the larger group's ideas and
decisions and will then make his or her decision
ut
based on the best decision.
• Agile methods – Fist of five, thumbs
ib
up/down/sideways, planning poker, and so on
Data Representation
tr
Visual representations of data are powerful tools for
is
showing data so that you can then make a decision.
Mind mapping and affinity diagrams are two such ways.
D
We explore a few of these methods later in this lesson.
Observations (Definition)
or
Observations, also referred to as job shadowing, is a
technique used to gain knowledge of a specific job role,
e
task, or function in order to understand and determine
at
project requirements.
project requirements.
Facilitated Workshops (Definition)
N
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Context Diagrams (Definition)
e
systems (actors) interact with it.
ut
Context Diagrams
ib
The diagram includes the business process, equipment,
or computer system and what roles interact with those
tr
systems.
is
The diagram depicts specific business and actor inputs
to the business system, as well as the business and
D
actor outputs of the system.
or
Storyboarding (Definition)
Prototyping (Definition)
N
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
revisions until the project requirements are determined.
Requirements Documentation
e
project.
ut
The documentation is composed of all the individual
requirements needed for a project to meet the business’
ib
and stakeholders’ needs.
tr
The composition of the documents will vary depending
on the specific needs of a project. For example, very
is
detailed and categorized, to a simple list of high-level
requirements.
D
Requirements documentation can include any or all of
the following components:
•
• or
Business requirements
Stakeholder requirements
e
• Solution requirements
• Transition and readiness requirements
at
• Support and training requirements
• Project requirements
lic
• Quality requirements
Types of Requirements
up
Nonfunctional Requirements
They include:
D
• Availability
• Capacity
• Continuity
• Security
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Requirements Management Plan (Definition)
e
managed.
ut
Requirements Management Plan
ib
This plan provides guidance on how the process of
collecting requirements will be managed.
tr
Components of the requirements management plan
is
require project managers to choose the most effective
relationships to aid in the project's success and
D
document this approach in the plan.
or
• How requirements activities will be planned,
tracked, and reported.
• Configuration management activities
e
• Requirements prioritization process
• Metrics used and the rationale for using them.
at
• Traceability structure
lic
project objectives.
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
proposed changes to the scope.
e
objectives.
• Project objectives.
ut
• Project scope and WBS deliverables.
• Product design.
ib
• Product development.
• Test strategy and test scenarios.
tr
• High-level requirements to more detailed
requirements.
is
• Work package mapping.
• Stakeholder reference, so you can track each
D
individual requirement to a stakeholder.
GUIDELINES: Collecting Project Requirements
Review:
or
• the scope management plan for clarity as to
how project teams will determine which type of
e
requirements need to be collected for the
at
project.
• the requirements management plan for the
lic
requirements.
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Project Scope Statement (Definition)
e
ut
Project Scope Statement
ib
Stakeholders and other project members can refer to
the scope statement when scope development needs to
tr
be verified against the scope baseline, updated, or
changed during the course of a project.
is
A project scope statement will be different for every
D
project, it may include any, or all, of the following
components:
• Project scope description
or
• Acceptance criteria
• Deliverable
• Project exclusion
e
• Constraints
• Assumption
at
the project.
• Multi-criteria decision analysis - A decision-
o
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
tool that generally means asking questions about
a product and forming answers to describe the
use, characteristics, and other relevant aspects
of what is going to be manufactured.
Product Analysis (Definition)
e
ut
Product analysis is a tool to define scope that generally
means asking questions about a product and forming
answers to describe the use, characteristics, and other
ib
relevant aspects of what is going to be manufactured.
tr
Product Analysis
is
Depending on the product the project is delivering, you
can use a number of analysis methods to create a
D
working understanding of it and to develop the scope.
These methods include product breakdown, systems
or
analysis, requirements analysis, systems engineering,
value engineering, and value analysis.
GUIDELINES: Develop a Project Scope
e
Statement
at
the project.
• Review the OPAs such as policies, procedures,
N
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Work Breakdown Structure (Definition)
e
objectives and create the required deliverables.
ut
Work Breakdown Structure (Definition)
ib
A WBS defines the total scope of work required to
complete the project.
tr
The deliverables and their component sub-deliverables
is
are represented on the WBS in levels of descending
order.
D
The WBS shown in the figure is a specialized approach
known as DMAIC (Define, Measure, Analyze, Improve,
or
and Control). This approach is commonly used in Six
Sigma types of projects.
e
Code of Accounts (Definition)
at
structure.
o
WBS Dictionary
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
• Responsible organization
• Schedule milestones
• Associated schedule activities
• Resources required to complete the work
• Cost estimations
e
• Quality requirements
•
ut
Acceptance criteria
• Technical references
• Agreement information
ib
Decomposition (Definition)
tr
Decomposition is a technique used for dividing and
is
subdividing the project scope and project deliverables
into smaller, more manageable parts.
D
Decomposition - Example
or
The work package is the smallest chunk from the WBS,
which includes the to-do activities, so you can ascribe
e
duration and estimated cost.
at
The level of decomposition is based on specific project
needs and the level of granularity needed to manage
lic
decomposition process:
• Identify the deliverables and the work tasks
necessary to accomplish the deliverable.
• Structure and organize the WBS.
D
Planning Packages
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Control Account (Definition)
e
measurement.
ut
Control points are tracked by finance to verify that costs
are within budget.
ib
These accounts associated with different work
tr
packages within the WBS can be tracked and verified
against the earned value of a project to check
is
performance.
D
and the work will be managed within that account
throughout the project.
or
Control accounts may contain more than one work
package, but each work package should be assigned to
only one control account.
e
Planning Package (Definition)
at
applied.
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Planning Work Using a WBS
e
An important distinction to be made here is that the
ut
"work" referred to in a WBS is actually the products or
deliverables that are a result of an individual work
ib
package, not necessarily the work itself.
tr
Each level of the WBS breaks down the work into more
and more layers until the work package is at a level that
is
can be assigned, estimated for cost and duration, and
tracked individually.
D
The goal is to eventually roll up each work package into
the level above within the WBS hierarchy to gain the
or
overall time and budget requirements.
Scope Baseline (Definition)
e
The scope baseline is the approved version of a scope
statement, WBS, and its associated WBS dictionary,
at
actual results.
Scope Baseline
up
on the variance.
components:
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
GUIDELINES: Create a WBS
e
WBS will be maintained and approved.
•
ut
Review the project scope statement for a
description of the requirements that need to be
satisfied and the work that will be excluded from
ib
the scope. Include a list and description of the
specific internal or external restrictions or
tr
limitations that may affect the execution of the
project.
is
• Review the requirements documentation to
understand what needs to be produced as the
D
result of the project and what needs to be done
to deliver the project and its final products.
• Review the Enterprise Environmental Factors
or
(EEFs) such as industry-specific WBS standards
(such as ISO) that are relevant to the nature of
the project and that may serve as external
e
reference sources for creating the WBS.
• Review Organizational Process Assets (OPAs)
at
such as policies, procedures, template for the
WBS, project files from previous projects, and
lic
delivered incrementally.
• Document the scope baseline and update any
project documents, as needed.
N
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
completed. PBIs are edited and clarified as more is
known or as product requirements may change.
e
product backlog is an ongoing exercise, typically
scheduled in weekly or monthly intervals.
ut
The product backlog grooming also orders the items
ib
based on priority and other criteria.
tr
completed, teams set up iterations with its own backlog
based on items from the product backlog.
is
In an Iteration Backlog, the team determines what items
D
from the product backlog can conceivably be completed
within that time period based on the team’s capacity.
or
Hence, teams must estimate the effort size of the work
and understand the priorities of the business.
e
User Stories (Definition)
at
Short descriptions of required functionality; told from the
user’s point of view.
lic
up
User Stories
stories.
N
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
to focus more on what the user actually values over
simply delivering to a specification.
Tools and Techniques for Verifying Scope
e
used to verify the scope.
ut
Definition of Done (DoD) - A team's checklist of all the
criteria required to be met so that a deliverable can be
ib
considered ready for customer use.
tr
Definition of Ready (DoR) - A team's checklist for a
user-centric requirement that has all the information the
is
team needs to be able to begin working on it.
D
Acceptance Criteria - A set of conditions that is
required to be met before deliverables are accepted.
or
Validate Scope - The process of formalizing
acceptance of the completed project deliverables. This
usually involves reviewing the deliverables with the
e
project customer or sponsor to ensure that they are
satisfied with the final deliverable and securing their
at
formal acceptance for the completeness of the
deliverable.
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Topic C: Plan and Manage Schedule
The project schedule in its most basic form is simply a representation of how long a
project takes to complete.
e
It includes a number of components, including the activities that will be performed to
ut
execute the project scope, the duration of each activity, and how the activities are
related to each other.
ib
Plan and Manage Schedule
tr
We have just learned about how you plan and manage
is
scope. The next step is the schedule.
D
Deliverables and Tools (1 of 2)
or
This is a list of the deliverables and tools associated with
this topic. These slides are provided to help you match
up project tools and deliverables with tasks.
e
This list is continued on the next slide.
at
Project Schedule
ot
32
Lesson 2: Starting the Project | Topic C
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
project objectives on time.
e
Benchmarks and Historical Data
ut
Benchmarking in the context of scheduling is the
comparison of a project schedule to a schedule for a
ib
similar product or service produced elsewhere.
tr
For example: If a widget can be
designed in six months by other
is
companies, your design for a comparable
widget should not take a year.
D
Benchmarks can be useful in the initial stage of
scheduling, to help assess the feasibility of a project.
or
Historical data, on the other hand, can come from other
projects completed within an organization for which
e
detailed information is available.
at
project.
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Components of the Schedule Management Plan
e
project schedule describes how to update the status
ut
and record the progress of the project during the
project execution.
• Accuracy - Level of accuracy is the acceptable
ib
range used to determine realistic activity duration
estimates and may include an amount for risk
tr
contingency.
• Units - Units of measure are defined for each
is
resource such as staff hours, days, and weeks.
• Organizational links - The WBS is used as the
D
framework for the schedule management plan so
that there is consistency with the estimates and
resulting schedules.
or
• Control thresholds - Control thresholds are the
defined variance thresholds for monitoring schedule
performance before action is taken. Expressed as
e
percentage deviations from the baseline plan; for
example, 10% behind schedule or 15% ahead of
at
schedule.
• Rules - This includes the rules of performance
lic
are documented.
Schedule Management Considerations for Agile/
ot
Adaptive Environments
demand scheduling.
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
on-demand pull-based scheduling.
e
• Define Activities
• Sequence Activities
ut
• Estimate Activity Durations
• Develop Schedule
ib
• Control Schedule
Iterative Scheduling with Backlog
tr
This method uses progressive elaboration (rolling wave)
is
techniques to develop and schedule activities in a
specified time window, often two weeks, based on
D
requirements defined in user stories.
or
Iterative Scheduling with a Backlog Process
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
GUIDELINES: Develop a Schedule Management
Plan
e
scope baseline and other scheduling-related
ut
information such as risk decisions.
• Review the project charter for a summary, high-
level milestone schedule for the project, and for
ib
who will approve the project schedule.
• Review the EEFs such as organizational culture
tr
and structure, resource availability and skills, use
of project management software, published
is
commercial information, and organizational work
authorization systems.
D
• Review the OPAs such as monitoring and
reporting tools; historical information; lessons
learned; schedule control tools; existing schedule
or
control-related policies, procedures, and
guidelines; templates; project closure guidelines;
change control procedures; and risk control
e
procedures.
• Use tools and techniques such as expert judgment
at
and historical information to give the project team
advice on schedule development and
lic
Project Activities
o
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
accomplished?)
e
Activities do not appear on the WBS. They are
documented separately in an activity list.
ut
Additionally, they may be entered in the project schedule
ib
or documented in an individual's own work plans.
tr
"reserve conference room" might be
broken down into the following activities:
is
• Determine budget
• Determine size requirement
D
• Determine date needed
• Identify possible room
or
alternatives
• Select room
• Call to reserve room
e
Feature (Definition)
at
Epic (Definition)
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Working with Features
e
Estimating features gives a view of when blocks of
functionality can be released to the business and end
ut
users.
ib
Progress can be measured based on the features
accepted by the business compared to the features
tr
remaining.
Milestones (Definition)
is
A milestone is a significant point or event in a project,
D
program, or portfolio.
Milestones
or
e
Milestones have no duration and trigger a reporting
at
requirement or require sponsor or customer approval
before proceeding with the project.
lic
Milestone Chart
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
GUIDELINES: Estimating Project Activities
e
• Review the scope baseline for the WBS, deliverables,
ut
assumptions and constraints.
• Review the EEFs such as organizational culture and
structure, published commercial information, and
ib
project management information systems.
• Review the OPAs such as lessons learned,
tr
standardized processes, templates and organizational
policies, and procedures and guidelines for
is
scheduling.
• Analyze and decompose each work package of the
D
WBS into activities (if desired) that will be required to
produce the deliverable:
o Conduct brainstorming sessions with the project
or
team to ensure that no required activities are
overlooked.
o Consult the scope statement to ensure that
e
activities will enable you to meet the project
objectives.
at
o Consult subject matter experts (SMEs) about
unfamiliar material.
lic
as possible.
ot
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Activity Dependency (Definition)
e
ut
Activity Dependency
ib
The relationship indicates whether the start of an activity
is contingent upon an event or input from outside the
tr
activity.
is
Activity dependencies determine the precedence
relationships.
D
For example: an architect has designed
a residence and has a vision for the room
or
layouts.
sequence.
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
based on knowledge of best practices within a
particular application area or an aspect of the
project where a specific sequence is desired. They
are also called soft logic. They are not necessary
and can be modified as the project progresses,
e
and a better sequence is found or the schedule
needs to be condensed.
ut
• External - A relationship between project
activities and non-project activities.
ib
tr
For example: The delivery of a part
that is needed to build a prototype.
is
•
D
Internal - A dependency between project activities
and is usually under the project's control.
or
For example: The software testing is
dependent on the software being written
by a software development team.
e
at
Precedence Relationships
than successors.
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Types of Precedence Relationships
e
1. Finish-to-Start (FS) - A logical relationship in
ut
which a successor activity cannot start until a
predecessor activity has finished.
ib
For example: The foundation for the
tr
house must be finished (Activity A)
before the framing can start (Activity B).
is
The total time for these two activities is
the sum of A + B.
D
2. Finish-to-Finish (FF) - A logical relationship in
which a successor activity cannot finish until a
or
predecessor activity has finished.
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
GUIDELINES: Sequence Project Activities
e
sequenced.
•
ut
Determine the dependencies among project
activities by using your activity list and product
descriptions.
ib
• Identify predecessor and successor activities by
reviewing the activity attributes for each activity,
tr
including predecessor or successor relationships.
• Review the milestone list for the dates for specific
is
schedule milestone events.
• Review the project scope statement for the scope
D
description, deliverables, constraints, and
assumptions that may affect activity sequencing.
• Review the EEFs such as government or industry
or
standards, Project Management Information
System, scheduling tool, and work authorization
systems.
•
e
Review the OPAs such as activity planning
policies, procedures, guidelines, and templates.
at
• Use tools and techniques such as Precedence
Diagramming Method (PDM), dependency
lic
finish of one activity and the start of the next one. Each
activity will have one duration associated with it, for
example, two days, one week, or one month.
o
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Examples of things that might be
affected are:
• Domestic and international
holidays
• Unit of measurement used for
e
durations
• Other projects and operations
ut
Elapsed time is the actual calendar time required for an
ib
activity's completion. An activity that requires two weeks
to complete would take four calendar weeks of elapsed
tr
time if there's a two- week plant shutdown in the middle.
is
Effort is the number of labor units required to complete a
scheduled activity or WBS component, often expressed
in hours, days, or weeks. Contrast with duration. The
D
estimates of effort provide the basis for cost estimating
and resource allocation.
or
GUIDELINES: Estimate Activity Durations
guidelines:
lic
estimates?
• Are there any relevant commercial duration
estimating databases?
ot
activity durations.
•
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Schedule Presentation Formats
e
Three commonly used schedule formats are:
• Gantt chart
ut
• Milestone chart
• Project schedule network diagram with dates
ib
Gantt Chart (Definition)
tr
Created by Henry Gantt, the Gantt chart is a bar chart of
schedule information where activities are listed on the
is
vertical axis, dates are shown on the horizontal axis, and
the activity durations are shown as horizontal bars placed
D
according to start and finish dates.
Gantt Chart
or
Tasks in the Gantt chart are listed down the left side and
dates are listed across the top or bottom with bars to
e
indicate start and finish dates.
at
Time is represented with horizontal bars that correspond
to the activities.
lic
team.
Project Schedule Network Diagram with Dates
N
and Dependencies
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Critical Path Method (Definition)
e
ut
Critical Path Activity (Definition)
ib
A critical path activity* is any activity on the critical path in
a project schedule.
tr
Generally, for all activities along the critical path, ES = LS
is
and EF = LF. There can be no flexibility in the start time
or the finish time for these activities. Activities that are not
D
on the critical path usually have some flexibility in their
start and finish times. Activities on the critical path have a
total float of zero.
or
Use the Critical Path Method
through a project
• Goal is to determine the shortest possible project
lic
duration.
• Use early start (ES); early finish (EF); late start
(LS); and late finish (LF) dates for all activities.
up
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
If there is a string of activities with float, free float will
be available for the activity only at the end of the
string. Free float on the activity is calculated by
subtracting the EF of an activity from the ES of its
e
successor activity.
ut
Agile Release Planning
ib
product releases, each containing completed features
that are ready for customer use.
tr
Each release consists of iterations, in which a piece of
is
the product is designed, developed, and tested.
D
Release planning focuses on creating the summary
timeline for the project's product release.
or
In the Agile release planning process, you determine the
number of iterations or Sprints that are needed to
complete each release, the features that each iteration
e
will contain, and the target dates of each release.
at
This enables customers to see the dates when the
features that they want are expected to be available.
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
manager how much variance exists between the actual
work completed and the work scheduled.
e
analysis are used to help determine if the schedule
variance is potentially detrimental to the project and if
ut
corrective actions are needed to ensure on-time
deliverables.
ib
By using the approved schedule baseline as the standard
for measuring progress, the project manager collects
tr
reporting information for each activity and uses a bar
chart to summarize the data.
is
If an agile approach is used to manage the project,
D
progress can be evaluated with the following steps:
• Compare the total amount of work delivered and
or
accepted with the estimate of the work to be
completed for the current time period.
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
• Use smoothing and levelling techniques.
Smoothing/Levelling
e
ut
Smoothing –
• Adjusts the activities of a schedule model to keep
ib
resource requirements within predefined resource
limits and within free and total floats.
• Does not change the critical path is not changed
tr
nor delay the completion date.
• This method may not be able to optimize all
is
resources.
D
Levelling –
• Adjusts start and finish dates based on resource
constraints.
or
• Goal is to balance demand for resources with
available supply.
• Use when shared or critically required resources
e
have limited availability or are over- allocated.
• Can change the critical path.
at
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
depends on resource availability and also carries some
negative factors. Fast-tracking can result in:
• Rework
• Increased risk
• Increased cost
e
Coordination with Other Projects
ut
If the project is part of a program or a portfolio, the
ib
schedule status of the project should be evaluated for
any effect it has on the other components of the program
or portfolio.
tr
In some situations, a delay (or acceleration) of a project
is
may not impact other projects.
D
However, if the delay or acceleration is caused by
activities on the project’s critical path and that project is
critical to the schedule of other projects, the overall effect
or
can be significant.
e
at
lic
up
D
ot
N
o
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Topic D: Plan and Manage Budget and Resources
Without proper management of project costs, expenses can get out of control
quickly. You must be prepared to make adjustments and apply the correct costs to
e
resources, activities, and services that align with your budget. The cost management
plan helps you plan, react to, and update project costs when issues or changes arise
ut
throughout the life cycle of a project.
ib
Plan and Manage Budget and Resources
tr
In this topic, we look at how to plan and manage a
project budget and resources. In this case, by
is
‘resources’, we mean all of the tangible and intangible
requirements needed to do project work.
D
Deliverables and Tools
This is a list of the deliverables and tools associated
or
with this topic. These slides are provided to help you
match up project tools and deliverables with tasks.
e
at
Cost Estimates
lic
costs.
• Logical estimates provide a basis for making
sound decisions about projects, and they
ot
Disadvantages
In the graphic - “Thumbs up” indicates a benefit and
“thumbs down” is a drawback.
Analogous estimating
• Uses the cost of a previous project with similar
scope or activities to predict the cost of future
activities.
51
Lesson 2: Starting the Project | Topic D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
• Can ensure no work is inadvertently omitted from
work estimates.
• Can sometimes be difficult for lower- level
managers to apportion cost estimates.
e
Parametric estimating
• Relies on the statistical relationship that exists
ut
between historical information and variables so
as to arrive at an estimate for parameters such
ib
as duration and cost.
• Is not time consuming.
• May be inaccurate, depending on the
tr
• integrity of the historical information used.
is
Bottom-up estimating
• Estimates the cost of individual activities then
D
"rolls up" to higher levels.
• Is accurate and gives lower-level managers more
or
responsibility.
• May be time consuming and can be used only
after the WBS has been well- defined.
e
Three-point estimating (not on this slide, but you
at
should also know it)
Incorporates three types of estimates into a singular
lic
− pessimistic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Allows the use of a less-detailed estimate (perhaps
ROM) for some later parts of the work, whereas work
that must be done earlier in the project life cycle is
estimated more accurately (perhaps at the definitive
level).
e
Project Governance
ut
Governance, as applied to cost estimates, can be
described as managing project phases.
ib
A different type of cost estimate and level of accuracy
tr
may be required for different phases of the project life
cycle.
is
A cost estimating method might be chosen due to:
D
• Software availability
• Team member experience
• Project life cycle phase
or
• Time constraints
• Project definition
• Personal preference
e
Compliance
at
This topic is covered fully in Lesson 5, so this is a quick
note about compliance and how it affects the budget.
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
GUIDELINES: Estimate Costs
e
which will ultimately be used for measuring project cost
performance. Here are some guidelines for estimating
ut
costs:
ib
• When possible, the cost figures that go into the
cost estimates for individual work packages
tr
should be provided by those who will actually
provide the resources. As always, it is the people
is
who will do the work, provide the service, or
supply the material that can best estimate what
the associated costs will be. It is the project
D
manager's responsibility to compile these cost
figures into realistic estimates.
or
• For some projects, though, the project manager
will be solely responsible for generating the cost
estimates.
• Even in such cases, the project manager may
e
want to do a reality check with the resource
at
supplier to make sure no incorrect assumptions
have been made.
•
lic
accounts.
• Make sure your cost estimates include the
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
GUIDELINES: Estimate Budget
e
• Ensure budget contains funding needed to
complete the project as defined in the scope
ut
baseline and the project schedule.
• Measure project cost performance against this
ib
cost baseline
Cost Baseline (Definition)
tr
A cost baseline is the approved version of the time-
is
phased project budget, excluding any management
reserves*, which can be changed only through formal
D
change control procedures and is used as a basis for
comparison to actual results.
or
Cost Baseline
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
accommodate the risk of incurring extra
expenses.
• Avoid adding contingency reserves for work
packages with low-risk values.
• Total the costs for each time period.
e
• Plot the costs for each period on a chart to create
an S-curve of the baseline.
ut
• Publish and distribute the cost baseline to the
appropriate project stakeholders.
ib
Budget Challenges
tr
Ideally, a budget is set during project planning and does
not change. However, most projects do not exist in a
is
perfect world and one of several things can happen to
pose a challenge to the project manager:
D
• New or changed project requirements, which can
be based on data collected by the organization
regarding how the organization intends to use
or
the project's deliverables.
• New risks, or changes to the probabilities or
impacts of existing risks.
e
• Changes to cost estimates resulting from
at
economic factors, procurement contract
modifications, resource costs, etc.
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Funding Limit Reconciliation (Definition)
e
the funding limits and the planned expenditures.
ut
Funding Limit Reconciliation
ib
Most budgets are created on the premise of steady
incoming and outgoing flows.
tr
Large, sporadic expenditures are usually incompatible
is
with organizational operations.
D
Therefore, funding limits are often in place to regulate
the outgoing capital flow and to protect against over-
spending.
or
Budgets must be reconciled with such limits. This will
affect the scheduling of project work and possibly
e
reshuffle WBS work packages entirely.
at
The schedule, in turn, can affect the distribution or
acquisition of resources.
lic
Challenges
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
stakeholders are added to the project.
• Monitor risks frequently to look for new risks and
changes to existing ones.
• Monitor the performance of suppliers and
vendors.
e
• Monitor all changes to the project and follow the
Change Management System to try to keep them
ut
within budget.
GUIDELINES: Determine a Budget
ib
To determine a project budget effectively:
tr
• Review the cost management plan* for
information on how project costs will be managed
is
and controlled, and the method used and level of
accuracy for estimating activity cost.
D
• Review the resource management plan for
staffing attributes, personnel rates, and reward
and recognition information.
or
• Review the scope baseline for the project scope
statement, WBS, and WBS dictionary.
• Check the project schedule for type, quantity,
e
and duration of resources needed for project
at
activities.
• Review the risk register to consider any risks that
may impact cost estimation.
lic
learned.
• Use tools and techniques such as cost
aggregation, reserve analysis, expert judgment,
D
project.
• Document the project budget and create a cost
baseline.
N
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Topic E: Plan and Manage Quality of Outputs and
Deliverables
e
All projects must be of a certain quality. What that level of quality is, the expectations
around the quality, how the project’s quality is to be measured, how it will be aligned
ut
to the project’s objective, and how the quality is to be tracked and reported are a few
important aspects of managing project quality. There is a lot to do and consider
when it comes to assuring and delivering quality deliverables and products.
ib
Plan and Manage Quality of Outputs and
tr
Deliverables
is
This is the fifth topic in lesson 2. We’ve looked at
methods, scope, schedule, and resources. Now it’s time
D
to turn our attention to deliverables.
or
Deliverables and Tools
This is a list of the deliverables and tools associated with
this topic. These slides are provided to help you match up
project tools and deliverables with tasks.
e
at
lic
Quality (Definition)
59
Lesson 2: Starting the Project | Topic E
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Quality Standards and Regulations
e
characteristics that have been approved by a
recognized body of experts such as the International
ut
Organization for Standardization (ISO). In some
cases, the standards body will provide certification
ib
that suppliers conform to the requirements of their
standards. Often, the conformance to standards is a
tr
customer requirement.
• Regulations are requirements imposed by a
is
governmental body. These requirements can establish
product, process, or service characteristics, including
applicable administrative provisions that have
D
government-mandated compliance. Standards often
start out as accepted or de facto best practices
or
describing a preferred approach and may later
become de jure regulations such as using the critical
path method in scheduling major construction
projects.
e
Verified Deliverables
at
accepted deliverables.
• Measure products and outputs against the project’s
quality standards.
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Style and level of detail are determined by project
requirements.
e
improvement products.
ut
Review the quality management plan early in the project.
Benefits:
ib
• Decisions based on accurate information
• Sharper focus on the project’s value proposition
• Cost reductions
tr
• Mitigate schedule overruns from rework
is
Cost of Quality (CoQ)
D
CoQ is all costs incurred over the life of the product by
investment in preventing nonconformance to
requirements, appraisal of the product or service for
or
conformance to requirements, and failure to meet
requirements.
Quality Metrics
e
at
You need to ensure a description of the project or product
that is measurable. Then, the team needs to decide how
that quality will be measured and what kind of tolerances
lic
Quality Audit
N
performance of a project.
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
GUIDELINES: Manage Quality
e
techniques to determine the causes of quality
problems of the project’s product, service, systems, or
ut
processes.
• Identify and implement the appropriate actions to take
ib
to increase the effectiveness and efficiency of the
project team’s work results.
tr
Control Quality Tools
These are presented here as an opportunity for an
is
overview and compare and contrast. They are discussed
at length over the next 6 slides.
D
Let’s take a look at the tools project managers use to
control quality on a project:
or
• Data gathering
• Data analysis
• Data representation
e
Data Gathering
at
Checklists
N
• Check Sheets
• A structured tool, usually component-specific
o
Statistical sampling
• Choosing part of a population of interest for
inspection.
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
• Determine characteristics of an entire population
based on measurement of representative sample.
Data Analysis
Performance Reviews
e
Technique that is used to measure, compare, and
ut
analyze actual performance of work in progress on the
project against the baseline.
• Critical chain method
ib
• Earned value management
• Trend analysis
tr
• Critical path method
is
Root Cause Analysis
Analytical technique used to determine the basic
D
underlying reason that causes a variance, defect, or a
risk.
• Using gathered data, identify the cause of the
or
problem.
• Goal is to pinpoint the exact cause.
• Follow issue back to the initial trigger.
e
• Use RCA tools - Failure Modes and Effects
Analysis (FMEA), a fishbone diagram, a Pareto
at
chart, a scatter diagram
Data Representation
lic
(1 of 4)
up
Data Representation
o
(2 of 4)
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Data Representation
(3 of 4)
e
time.
ut
✓ A graphic display of project data against
established control limits to reflect both the
ib
maximum and minimum values.
✓ Gives visibility to where corrective actions can
tr
prevent further problems.
✓ Ideal for repetitive processes with predictable
is
results.
Data Representation
D
(4 of 4)
or
A Pareto chart is a histogram used to rank causes of
problems in a hierarchical format.
✓ Use to help determine the most frequent defects,
complaints, or other factors that affect quality.
e
✓ Demonstrates the frequency of occurrence
at
✓ Analyzes data sets related to a specific problem or
issue.
✓ Does not define the root cause of a problem.
lic
time.
• Identify ways to eliminate causes of unsatisfactory
N
results.
• Use flowcharts to identify redundancies, missed
steps, or the source of quality performance
o
problems.
• Initiate process adjustments by implementing
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Topic F: Integrate Project Planning Activities
This is where it all starts coming together. Project teams need to merge or integrate
all of the planning activities we’ve been discussing into a cohesive plan.
e
Integrate Project Planning Activities
ut
In the sixth topic, we turn our attention into integrating
ib
planning activities, aligning scope, budget and resources,
timelines along with any other necessary plans.
tr
is
Integration Management
D
In this step, the team assesses and coordinates all plans
and activities that are built, maintained, and executed
throughout a project.
or
A holistic, integrated view ties plans together, aligns
efforts, and highlights how they depend on each other.
e
An integrated view of all plans can identify and correct
at
gaps or conflicts.
lic
65
Lesson 2: Starting the Project | Topic F
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Project Management Information System (PMIS)
e
Microsoft Project is one product that offers the capability
of managing process integration.
ut
Project Management Plan Components
ib
Project management plan components are a combination
of essential and supporting—or subsidiary—processes
tr
used to run a project.
is
Ensure the essential plans and processes are in place.
These are scope, schedule, and cost, which we have
D
already discussed.
or
processes to your project. Consider the needs of the
project to determine which components of the project
management plan are needed.
e
Project Management Plan Tools and Techniques
at
Managing Change
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Configuration Management Plan/ Change
Management Plan
e
•
ut
Configuration management plans identify and
account for project artifacts under configuration
control and how to record and report changes to
ib
them.
• Change management plans provide direction for
tr
managing the change control process and
documents the roles and responsibilities of the
is
change control board (CCB).
Change Management Plan
D
A change management plan answers the following
or
questions:
• Who can propose a change?
• What exactly constitutes a change?
• What is the impact of the change on project
e
objectives?
at
• What are steps to evaluate a change request
before approving or rejecting it?
• When a change request is approved, what project
lic
• Review:
o Project charter - for the high-level
ot
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
managing change:
e
organization.
• Scrum of Scrums - A technique for operation of
ut
Scrum at scale for multiple teams working on the
same product, coordinating discussions of
ib
progress on interdependencies, and focusing on
how to integrate the delivery of software,
tr
especially in areas of overlap.
• Scaled Agile Framework (SAFe®) - A knowledge
is
base of integrated patterns for enterprise-scale,
lean-agile development.
D
or
e
at
lic
up
D
ot
N
o
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Topic G: Plan and Manage Procurement
While procurement is not the primary responsibility of the project manager, we do
need to understand why and how a project manager needs to plan and manage for
e
procurement of goods and services for a project.
ut
Plan and Manage Procurement
ib
Procurement is the process by which organizations
endeavor to contract or outsource products or services.
tr
Though this is not typically the responsibility of the project
manager, we need to cover the points related to
is
procurement planning and management.
D
Deliverables and Tools
This is a list of the deliverables and tools associated with
or
this topic. These slides are provided to help you match up
project tools and deliverables with tasks.
e
at
Procurement Strategy
lic
Delivery Solution
N
requirements
2. Detailed design – Document the solution
3. Implementation/installation – Implement or install
the solution
4. Testing – Test the solution
5. Training – Ensure those who need training to use
the solution have it.
6. Handover – Conduct formal handoff of the product
69
Lesson 2: Starting the Project | Topic G
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
or service from vendor to supplier
7. Support and maintenance – Ensure ongoing
support is ready and available for the solution
Make or Buy?
e
When you consider your team’s requirements against
ut
budget and timeline, you can make choices about how a
required product or service can be procured.
ib
Do we buy it? Or should we try to make it in house?
tr
Other approaches include borrowing a resource from
another team or outsourcing a product or service
is
temporarily, rather than buying.
Statement of Work (SOW) – (Definition)
D
Error in the slides: This should say “to the project by a
vendor”
or
An SOW is a narrative description of products, services,
or results to be delivered to the project by the vendor.
e
Procurement SOW
at
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Source Selection Criteria
e
✓ Overall or life-cycle cost
ut
✓ Understanding of need
✓ Technical capability
ib
✓ Management approach
✓ Technical approach
✓
tr
Warranty
✓ Financial capacity
✓
is
Production capacity and interest
✓ Business size and type
✓ Past performance of sellers
D
✓ References
✓ Intellectual property rights
or
✓ Proprietary rights
Qualified Vendors
e
Most organizations have a working list of qualified
vendors. This does not mean you can’t opt for using
at
someone new, but ensure that any new vendors are fully
vetted and set up with your organization.
lic
Bidder Conferences
up
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Supplier and Contracts
Contract types are explained in a few slides, so just
mention them here!
e
the seller (supplier) to provide the specified project or
service or result and obligates the buyer to pay for it.
ut
Contracts are:
ib
• Customized for each agreement
• Contract types:
o Fixed-price
tr
o Cost-reimbursable
is
o Time-and-material (T&M)
• Agile contract types
o Capped Time and Materials Contracts
D
o Target Cost Contracts
o Incremental Delivery Contracts
or
Communicating with Suppliers and Vendors
Components of Contracts
ot
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Traditional Contract Types
A fixed-price contract:
e
• Is an agreement that sets the fee that will be paid
for a defined scope of work regardless of the cost
ut
or effort to deliver it.
• Is also known as a lump sum contract.
ib
• Provides maximum protection to buyer but
requires a lengthy preparation and bid evaluation.
• Is suited for projects with a high degree of
tr
certainty about their parameters.
is
A cost-reimbursable contract:
• Involves payment to the seller for the seller's
D
actual costs, plus a fee typically representing the
seller's profit.
or
• Includes incentives for meeting certain objectives,
such as costs, schedule, or technical performance
targets.
• Is suited for projects with uncertain parameters.
e
at
A time-and-material (T&M) contract:
• Is a hybrid contractual arrangement containing
aspects of both cost-reimbursable and fixed-price
lic
contracts?
• Combines a negotiated hourly rate and full
reimbursement for materials.
up
may be prevalent:
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
value runs below budget.
• Allow both parties to face additional costs if it
exceeds budget.
e
• Customers review contracts during the contract life
cycle at pre-negotiated designated points of the
ut
contract lifecycle.
• Customers can make required changes, continue,
ib
or terminate the project at these points.
Control Procurements Process (Definition)
tr
The process of managing procurement relationships,
is
monitoring contract performance, making changes and
corrections as appropriate, and closing out contracts
D
Accounts Payable
or
Suppliers and vendors are given instructions on how to
submit invoices for payment—usually in the SOW.
e
However, project managers need to notify the appropriate
at
entity when work has been fulfilled, or, typically, authorize
payment of the invoice.
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
• A supplemental agreement is an addendum to the
contract which is negotiated separately.
• Constructive changes are caused by the buyer
through action or inaction.
• Termination of contract happens when the vendor
e
defaults or for the customer’s convenience.
For example: Defaults are due to either
ut
non-performance, such as late
deliveries and poor quality, or non-
ib
performance of some or all project
requirements.
tr
Legal Concepts when Managing Disputes
is
When a change leads to a dispute, you’ll need to seek
legal advice to ensure the terms of the contract are
D
observed. Remember to use your negotiation skills to
reach a final, equitable settlement of all issues, claims,
and disputes.
or
Briefly, here are the legal concepts you should know, as
they relate to contracts:
e
• Warranty – This is the promise, explicit or implied,
that goods or services will meet a pre-determined
at
standard. The standard may cover reliability,
fitness for use, and safety.
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
for quality or performance.
• Accepting late deliveries.
• Overlooking an aspect of nonconformance to
contractual obligations.
GUIDELINES: Manage Suppliers and Contracts
e
ut
• Index and store all contract correspondence for
ease of retrieval.
• Develop and implement an effective contract
ib
change control system.
• Evaluate the risk of each contract change request.
tr
• Document all contract changes and incorporate
any effects of the changes into the project plan.
is
• Develop and implement an effective performance
reporting system for the seller.
D
• Specify any performance reporting criteria to the
seller.
• Set performance milestones to monitor project
or
progress.
• If work is performed at another site, conduct site
visits to determine how the seller’s work is
e
progressing.
• Submit approved invoices for payment in
at
accordance with the contract and the project’s
payment system.
lic
up
D
ot
N
o
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Topic H: Establish Project Governance Structure
Project governance is the realm of experienced or senior project managers, but it’s
important to know how your projects are supported by the organization.
e
Establish Project Governance Structure
ut
Project governance is mostly likely in place before you
ib
begin work. It’s often a function of the PMO and in the
purview of senior project managers. But let’s make sure
tr
you know how it works.
is
Deliverables and Tools
This is a list of the deliverables and tools associated with
D
this topic. These slides are provided to help you match
up project tools and deliverables with tasks.
or
Project Governance
e
at
Effective project governance helps to ensure that every
project team can function as they are intended to. So,
let’s have a closer look at what underpins successful
lic
Project Governance
N
77
Lesson 2: Starting the Project | Topic H
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
• Process for stage gate or phase reviews
• Process for review and approval of changes above
the project manager's authority
• Process to align internal stakeholders with project
process requirements
e
Project Phases
ut
We just learned that project governance enables the
process for phase reviews. Before we take a look at how
ib
governance is applied to the project life cycle, we need to
understand project phases.
tr
Project phases are a collection of logically related project
is
activities that culminates in the completion of one or more
deliverables.
D
• Produce one of more deliverables in a phase
• A phase can be sequential or overlapping with
or
another
• Outputs from one phase are generally inputs to the
next phase
e
Apply Governance to the Project Life Cycle
at
program.
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
specialized type of phase gate called a
‘quality gate’.
Phase-to-Phase Relationships
e
We just mentioned that phases can be sequential and/or
ut
overlap with one another. Let’s take a closer look at how
that works.
ib
Sequential relationships contain consecutive
phases that start only when the previous phase is
tr
complete. This relationship reduces the level of
uncertainty, which may eliminate the option for
is
shortening a project's schedule.
D
Overlapping relationships contain phases that start
prior to the previous phase ending. This relationship
increases the level of risk and may cause rework if
or
something from the previous phase directly affects the
next phase.
GUIDELINES: Determine Appropriate
e
Governance for a Project
at
senior managers.
• Choose the most appropriate governance goals and
try to keep them simple.
•
up
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Topic I: Plan and Manage Project/Phase Closure
This is about how we wrap it all up and close down a project.
e
Plan and Manage Project/Phase Closure
ut
This is the final topic in this lesson about starting a
project. Closing phases or a project is a set of measured
ib
steps.
tr
Deliverables and Tools
is
This is a list of the deliverables and tools associated with
this topic. These slides are provided to help you match up
D
project tools and deliverables with tasks.
or
Close Project or Phase
e
During project closeout, several important activities
occur:
at
Closure Reasons:
D
objectives.
• Requirements changed during execution and the
project is no longer feasible.
N
80
Lesson 2: Starting the Project | Topic I
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
changes.
Close Procurements
e
• Close procurements when the contract terms of a
ut
procurement have been satisfied by both buyer and
seller.
• This occurs throughout the life of the project, not
ib
during project closure.
• Keep contracts open only for the necessary period,
tr
to avoid erroneous or unintentional charges against
the contract.
is
Acceptance of Project Deliverables
D
• Project deliverables are deemed accepted when
acceptance criteria have been met.
•
or
These criteria generally refer to some or all of the
requirements that were established at the beginning
of the project (and which might have been modified
during the project’s life cycle).
e
• Deliverables that meet these acceptance criteria are
at
formally signed off and approved by the customer or
sponsor.
lic
Payments
Knowledge Management
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Use the Lessons-Learned Register
e
• Sellers
• Customer
ut
• Strategic
• Tactical
ib
• Any other aspects of the project life cycle
Knowledge Management (Definition)
tr
A store of historical information about lessons learned in
is
projects.
D
Knowledge Management
or
During project or phase closure, knowledge management
activities consist of finalizing the lessons-learned register,
e
which is compiled throughout the project life cycle.
at
• Training
• Documentation
• Communication
• Support
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Transition Readiness
e
such as budget and training.
ut
Examine the readiness of all of the following parties and
prepare them for delivery:
ib
• End users
• The business
• The physical resources
tr
• The project team
is
Readiness is most critical in situations where an existing
product or service is getting an upgrade or improvement.
D
Assess the readiness of all parties, implement the
or
transition plans accordingly, and capture lessons learned
for the next release or project.
GUIDELINES: Close Out a Project or Phase
e
• Review the project management plan.
at
requirements.
• Release project resources.
• Update records to ensure that they reflect final
D
specifications.
• Be sure to update the resource pool database to
reflect new skills and increased levels of proficiency.
ot
acceptance.
• Archive a complete set of indexed project records.
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
End of Lesson 2
e
ut
ib
tr
is
D
or
e
at
lic
up
D
ot
N
o
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
e
ut
ib
tr
is
D
or
Student Edition e
at
lic
up
D
ot
N
o
D
Lesson 3
Doing the Work
PMI® Authorized PMP® Exam Prep
Lesson 3: Doing the Work
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Doing the Work
Lesson Time: 8 hours
e
Lesson Introduction
ut
Now that you have a project plan and have determined the requirements for
managing the project from initiation to closure, you are ready to execute the project.
ib
The time and effort spent on planning will come to fruition as the project team starts
doing the work of the project. During project execution, the ultimate goal is to deliver
tr
business value to the customer.
is
This lesson addresses tasks from the Process domain of the PMP® Exam Content
Outline.
D
Lesson Objectives
In this lesson, you will learn how project managers and teams:
•
• or
Assess and manage the risk landscape inherent in every project.
Execute a project to deliver business value.
e
• Manage the communications in a project.
•
at
Engage all project stakeholders.
• Create project artifacts.
• Manage project changes.
lic
Lesson Topics
Title Slides
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Topic A
Assess and Manage Risks
Up to this point, you have laid out all your project activities, developed a schedule,
e
and planned a project budget. Now what will you do when something unforeseen
ut
happens that affects all the plans you have made? How will you react? Risk
management provides you with specific actions to take for responding to project
risks.
ib
tr
is
D
or
Assess and Manage Risks
Risk (Definition)
o
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Risk
e
positive project outcome.
ut
• Negative risks, or threats, have a negative
impact on the project.
ib
Let’s look at a few useful definitions first.
Trigger Condition (Definition)
tr
is
An event or situation that indicates that a risk is about
to occur.
D
or
Project Risk Management (Definition)
need to consider:
• The likelihood that the risk event will occur and
• The potential impact of the risk.
D
e
• Methodology
ut
• Roles and responsibilities
• Funding
• Timing
ib
• Risk categories
• Stakeholder risk appetite
tr
• Definition of risk probability and impact
• Probability and impact matrix
is
• Reporting formats
• Tracking documents
D
Risk Identification Techniques
or
Use the following techniques to identify risks in your
project environment:
• Expert judgment
e
• Data gathering
at
• Data analysis
• Interpersonal and team skills
• Prompt lists
lic
• Meetings
Risk Classification Approaches
up
(Effect-Based)
• Internal
• External
• Technical
• Non-technical
• Industry-specific
e
• Known known - Information that is fully
ut
studied and well understood
• Known unknown - Information that is
ib
understood to exist but is not in the possession
of the person seeking it
• Unknown unknown - Something
tr
unforeseeable
• Unknown known - Information that an
is
individual or organization has in its possession
but whose existence, relevance or value has
D
not been realized
or
Idea: Think of some examples of
project risks and ask you to
classify and discuss them.
e
Here is a list to get you started:
• Covid-19
at
e
ut
GUIDELINES: Iteratively Identify, Assess, and
ib
Prioritize Risks
tr
package before the project begins.
•
is
Perform a structured review with key
stakeholders of documentation from other
planning processes to ensure understanding.
D
• Identify risks and triggers using risk identification
techniques.
•
or
Be consistent with risk approach but be mindful
of emerging special circumstances.
• Consult relevant historical information for
problems and resolutions—e.g., risk response
e
plans, final reports, and lessons learned from
at
previous, similar projects.
• Group identified risks into categories reflecting
common, relevant risks.
lic
e
ut
Probability and Impact Matrix
ib
This text and graphic are taken from the PMBoK
Guide, 6th edition, page 408. The example shows a
possible numeric risk scoring scheme.
tr
• Opportunities and threats are represented in a
is
common probability and impact matrix using
positive definitions of impact for opportunities and
D
negative impact definitions for threats.
• Descriptive terms—such as very high, high,
medium, low, and very low.
or
• Numeric values can be used for probability and
impact. Where numeric values are used, these
can be multiplied to give a probability-impact
e
score for each risk, which allows the relative
priority of individual risks to be evaluated within
at
e
ut
Risk Response
ib
After you’ve identified, classified, qualified, and
possibly quantified risks, you need to take some sort
tr
of action.
is
The following are possible actions you will take to
address a risk:
D
• Assign a person to implement an action.
• Develop options, select strategies, and agree on
actions to address overall risk exposure and
or
response.
• Address risks by priority–greatest to least.
• Add resources and activities to the budget,
e
schedule, and project management plan to
support risk responses.
at
Accept
e
Idea: Each of these action
ut
pathways begin and end with the
same action. Think of a scenario
for each type of risk and then try
ib
to think of what the steps in the
action pathway might look like.
tr
Contingency Response Strategies
is
(Definition)
D
Responses which may be used in the event that a
specific trigger occurs. Also known as “contingency
or
plan” or “fallback plan”.
impact estimates.
GUIDELINES: Determine and Implement Risk
ot
Responses
e
ut
ib
tr
is
D
or
e
at
lic
up
D
ot
N
o
D
e
improvement on a product or service, or otherwise.
ut
Execute Project to Deliver Business Value
ib
Project managers essentially work in a value-based
delivery system. All of the planning and work that we
tr
do in our teams is converted into something of value
is
to the customer or organization.
D
This is a list of the deliverables and tools associated
with this topic. These slides are provided to help you
or
match up project tools and deliverables with tasks.
e
Lead on Value Delivery
at
This is just a brief mention of a leadership element.
Lesson 3 focuses on process elements—lessons 1
lic
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Create a Culture of Urgency for Value
Delivery
e
ongoing task.
ut
There are a few ways to do this. For one, lead by
communicating the project's importance and vision,
ib
as we just discussed. But also represent the voice of
the customer to the team. Show them why the project
tr
matters. This will create relevancy and personalize
the value.
is
Business Value (Definition)
D
The net quantifiable benefit derived from a business
endeavor. The benefit may be tangible, intangible, or
or
both. e
Business Value
at
•
D
Financial gain
• Social
• Improvements
ot
• New customers
• First to market
• Technological improvement
N
e
how else your project imparts value to the business
ut
Let’s look at a few ways of deriving value or showing
how the project delivers value.
ib
Product Roadmap (Definition)
tr
Further information follows on the next slide.
is
A strategic document and plan which guides why the
product will be delivered and how the product will
meet objectives and the product vision.
D
Product Roadmaps
or
This is also a tool of the product manager. In it, we
should see a clear and deliberate value proposition.
e
Product roadmaps:
at
• Vary in appearance and presentation.
• Display the strategy and direction of the product
lic
Incremental Delivery
N
project.
D
e
looks like next.
ut
Untitled Graphic – Figure 6-20 Relationship
between Product Vision, Release Planning,
ib
and Iteration Planning
This is from the PMBoK 6th edition, page 216, “Agile
tr
Release Planning”
is
Idea: Review the relationships in
the graphic.
D
Minimum Viable Product (MVP) (Definition)
or
Further information is on the next slide.
•
D
e
necessary.
ut
Optimize use of MBIs by:
✓ Ensuring the product and functions are
ib
understood.
✓ Pinpointing an incremental value increase.
tr
Advantages of MBIs:
✓ Enable project team to deliver value sooner.
is
✓ Help team validate improvements.
✓ Enable team to incrementally build on success
D
or pivot as needed.
Cycles and Timeboxes
or
Following up with planning the project schedule,
which we did in the last lesson, let’s introduce agile
release planning methods.
e
at
Working this way, we organize work into release
cycles and work in time blocks. Making better use of
the project schedule also is a clear business value or
lic
benefit.
e
ut
ib
tr
is
D
or
e
at
lic
up
D
ot
N
o
D
e
strategy, plan, and management—not to mention skills!—need to be sharp.
ut
Manage Communications
ib
Information, relationships, progress—everything
depends on successful communication. Let’s learn
tr
how to make a successful project communications
is
plan.
D
This is a list of the deliverables and tools associated
with this topic. These slides are provided to help you
or
match up project tools and deliverables with tasks.
e
Communications
at
Project Communications
D
e
ut
Communications Management Plan –
ib
Components
tr
A communications management plan includes:
is
• Stakeholder communications requirements
• Information to be communicated, including language
D
to be used
• Reason
• Time frame and frequency
•
• or
Responsible person – i.e., release of confidential
information
Receivers
e
• Methods or technologies of conveyance
•
at
Time and budget allocation
• Escalation process for issues that need visibility
• Update method for the plan
lic
e
security and encryption matters for communication of
ut
project work.
ib
• Face-to-face meetings
• Email
tr
• Fax
• Instant Messaging – using third-party apps
is
• Text Messaging – direct phone to phone
• Print media and documents
D
• Video and voice conferencing (virtual meetings)
• Social media
• Company website
or
Idea: Can you think of other ways we
communicate on projects?
e
at
project.
Communication Model
D
e
The pull method, on the other hand, puts the onus of
ut
learning information on the recipient.
ib
Examples:
tr
A person giving a presentation is using
the push method because they are giving
is
information.
D
When that person asks questions of
participants, they are employing the pull
method to obtain information.
or
A free discussion period is interactive,
because everyone contributes.
e
Feedback
at
misunderstanding.
• No feedback provides an implicit acceptance of the
message by the receiver.
D
e
• Ensure your communications management plan
ut
includes all key elements.
• Integrate the communications management plan into
the project plan.
ib
• Distribute the plan to project stakeholders.
tr
is
D
or
e
at
lic
up
D
ot
N
o
D
e
project.
ut
Engage Stakeholders
ib
How are the stakeholders performing? From
customers to experts, you need to be able to get the
tr
most from each stakeholder to ensure work stays on
is
track and of high quality. In this topic, we explore how
project managers can encourage stakeholders to stay
focused and give their best effort to a project.
D
Deliverables and Tools
This is a list of the deliverables and tools associated
or
with this topic. These slides are provided to help you
match up project tools and deliverables with tasks.
e
at
Stakeholder Categories
lic
• Sponsors
• Customers and users
• Seller
D
• Functional managers
• Organizational groups
• Business partners
ot
• Other stakeholders
Stakeholder Register
N
e
A strategy drives your connection with the project
ut
stakeholders. Your strategy should do three things:
ib
• Involve each project stakeholder based on needs,
expectations, interests, and potential impact on the
project.
tr
• Enable development of appropriate management
strategies to engage stakeholders.
is
• Create and maintain relationships between the
project team and stakeholders.
D
Stakeholder Engagement Assessment Matrix
(Definition)
or
A matrix that compares current and desired stakeholder
engagement levels.
e
at
Engagement
o
e
take a closer look now at project artifacts.
ut
Create Project Artifacts
ib
Now it’s time to understand what project work looks
like—these are your artifacts. And just like an
tr
archaeologist, they are physical pieces of your project
is
that you produce and then can use to conduct
research or further work, or even on other projects.
D
Deliverables and Tools
This is a list of the deliverables and tools associated
with this topic. These slides are provided to help you
or
match up project tools and deliverables with tasks.
e
Artifacts vs. Deliverables and Project
at
Documents
On slide 82, “Version Control” – the third bullet
lic
Examples:
Spreadsheets, emails, and
meeting minutes are project
ot
management processes.
Examples:
A scope management plan is a
project document.
e
is a deliverable.
ut
Project Artifact
ib
Artifacts are like historical artifacts; in that they can
tr
show us what work was done and how it was done.
It’s a historical repository that can be useful for future
is
projects.
D
these key pieces of work.
Project Artifact Examples
or
This is a list of typical project artifacts used on
projects. Artifacts unique to agile projects are on the
e
next slide.
at
• Acceptance Criteria
• Assumptions
lic
• Business Case
• Change Requests
• Constraints
up
• Lessons learned
• Minutes of status meetings
• Project Charter
D
• Slide decks
• Requirements
• Scope
ot
• Scope Baseline
• Subsidiary project management plans
N
• Product Backlog
• Product Increment
• Product Roadmap
• Product Vision Statement
• Release Plan
• Sprint Backlog
e
ut
This is important to know, as it’s the means by which
we manage and organize project artifacts.
ib
Configuration Management System
(Definition)
tr
A collection of procedures used to track project
is
artifacts and monitor and control changes to these
artifacts.
D
Configuration Management
or
We discussed this briefly in Lesson 2, as a separate
entity from the change management plan. Let’s take a
closer look.
e
at
Configuration management is applied to a product,
not the project.
lic
This process:
• Controls product iterations.
• Controls the steps for reviewing and approving
up
artifacts.
Version Control (Definition)
N
e
• Include a date/time stamp and the name of the
ut
user who made the changes, providing a digital
“paper trail” of the document’s history.
ib
Note: The third bullet on this
slide incorrectly identifies the
tr
project management plan as a
project artifact.
is
• Use version control for important artifacts such
D
as the project management plan, subsidiary
project management plans, the scope and other
documents.
or
Storage and Distribution of Artifacts
documents
• Standardized formats and templates
D
e
veteran project manager. Let’s look at key techniques and leadership attitudes that
ut
will help you manage change effectively.
ib
Manage Project Changes
tr
Change is inevitable, but it is rarely insurmountable.
Let’s look at strategies, tools, and techniques for
is
managing project changes!
D
Deliverables and Tools
or
This is a list of the deliverables and tools associated
with this topic. These slides are provided to help you
match up project tools and deliverables with tasks.
e
at
e
new governmental or industry-specific regulations
ut
may be enacted. This can be especially true for
lengthy projects. If the new regulations are
related to the ongoing project, project change
ib
becomes necessary. Accommodating new
regulations or legislation can also mean revisiting
tr
the planning process to determine the effect the
new regulations will have on resource needs,
is
schedule durations, and quality specifications.
• Missed requirements - Many times the
D
requirements are understood by reviewing the
documentation and interviewing the end users
and policy makers. However, there are times
or
when complete and comprehensive
understanding may not be possible. The
interviewer feels that he/she has understood the
point, and the interviewee feels that he has
e
expressed all that matters. Although a
at
Requirements Traceability Matrix (RTM) is
prepared, the same confusion might arise in a
lic
e
such decisions.
ut
Change Management Process (Flowchart)
ib
Let’s take a look at the process that all project
tr
changes will go through. Every change ends in one of
two ways—either it is rejected, or the project is
is
rebalanced.
D
Requests that have been received and approved in
or
accordance with the integrated change control plan
and are ready to be scheduled for implementation.
e
Change Requests
at
management plan.
• Preventive action – Ensures future
performance of the project work with the
D
e
potential to affect the scope, schedule, or cost if left unattended. Risks in a project
ut
can become issues, which require resolution. This topic addresses how to handle
them.
ib
Manage Project Issues
tr
Risks are not always negative, but if they become
is
project issues, then you need to take action and resolve
them. We learn how in this section.
D
Deliverables and Tools
or
This is a list of the deliverables and tools associated
with this topic. These slides are provided to help you
match up project tools and deliverables with tasks.
e
at
Issues (Definition)
lic
Issues
• Cost control
• Project variance analysis
D
• Quality
• Risk
• Procurement
• Communications
e
and will impact the project.
ut
Example:
ib
Risk Issue
A supplier A supplier has gone
tr
might go on on strike.
strike.
is
Issue Log (Definition)
D
An example follows on the next slide.
or
A document where information about issues is recorded
and monitored.
Issue Log
Issue Resolution
e
escalate an issue to the project sponsor if it begins to
ut
have a major effect on the project.
GUIDELINES: Resolving Issues
ib
• Use your organization’s Issue Log template; in
the absence of one, create an Issue Log.
tr
• Train project team members to promptly report
potential issues.
is
• Enter the issue into the Issue Log and assign an
owner and a due date.
D
• Monitor progress and discuss each open issue at
every project status meeting.
• Develop a response (also known as a
•
• or
workaround) to the issue.
Assess the impact of the response.
Approve the response.
e
• Close the issue.
at
lic
up
D
ot
N
o
D
e
ut
It is important for project team members to obtain the right knowledge at the time
when they need it to do their job. Knowledge is an asset to project teams and this
lesson is about how to optimize it.
ib
tr
Ensure Knowledge Transfer for Project
Continuity
is
You need to know how to collect and manage
D
knowledge so that your team can use it. You should
also know how to transfer this knowledge to other
or
projects, so they can benefit from it.
Knowledge Types
up
pictures.
• Tacit knowledge - Is personal knowledge that
N
e
fully understand and leverage the knowledge.
ut
Knowledge Management
ib
Think of knowledge management as a three-level
system: individual, project, and organization.
tr
• At the individual level, each team member
is
needs to know how to perform their work in
accordance with each assigned task’s scope,
schedule, and cost—all while maintaining an
D
acceptable level of quality. If a person does not
possess the required knowledge for a particular
or
task, they must acquire it by one of three
methods:
o Research the topic to learn what they do not
know.
e
o Collaborate with other team members to fill in
at
the knowledge gap.
o Examine the project’s or organization’s
knowledge repository.
lic
e
ut
It can take the form of both positive and negative
experiences that occur throughout the project life
cycle.
ib
"Reinventing the wheel" is both time-consuming and
tr
costly. The amount of time and effort used to
document what went well and what did not happen as
is
planned can pay big dividends long into the future.
Considerations for Lessons Learned
D
Here are some typical topics covered in lessons
or
learned:
working together.
• Strategic – These typically affect some aspect of
the organization’s project management
methodology or significantly improve a template,
form, or process. These address the questions:
Can we reuse this project's artifact to get more
done with the same resources and deliver work
sooner?
e
reviewing recommendations with other managers
ut
in other departments, developing implementation
plans, and implementing those plans
ib
Lessons Learned Register (Definition)
Since we covered this topic in Lesson 2 also, take
note here about the continued use of the register
tr
during the project and how it helps with ensuring
knowledge continuity.
is
As the project progresses, you will continuously add
D
information to the lessons-learned register to help
identify specific strengths as well as areas of
improvement.
or
At the conclusion of the project, a team member can
edit and compile the information into a cohesive
e
document. It can be discussed in the project closure
at
meeting and archived for future reference, as a
means of ensuring retention and continuity of
knowledge.
lic
e
interpersonal skills to various degrees, as they are
ut
assigned by the project manager to manage tasks,
lead meetings, etc.
ib
All project team members should be skilled at active
listening, to reduce misunderstandings, and improve
tr
communication and knowledge sharing.
Working Environment Expectations
is
The project manager is responsible for the successful
D
sharing and transfer of project knowledge. Early in the
project, the project manager should set expectations
of how this is to occur. The project kickoff meeting is
or
an excellent venue for this to take place, because key
members of the project team will be present—either
in-person or virtually.
e
at
Typical expectations for sharing and transferring
project knowledge at the kickoff meeting include the
following:
lic
discussions
o Telephone
o Email
o Wikis
o Intranet
o Printed documents
e
ut
Knowledge Transfer Techniques
ib
Keep your team invigorated about learning.
Knowledge transfer opportunities can be among the
tr
most exciting moments at work.
is
Try one of these techniques:
• Networking
D
• Facilitating special interest groups
• Meetings, seminars, and various other types of
in-person and virtual events that encourage
or
people to interact and exchange ideas and
knowledge
• Training that involves interaction between
e
attendees
• Work shadowing and reverse shadowing
at
End of Lesson 3
D
ut
ib
tr
is
D
or
e
at
lic
up
D
ot
N
o
D
Lesson 4
Keeping the Team on Track
PMI® Authorized PMP® Exam Prep
Lesson 4: Keeping the Team on Track 1
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Keeping the Team on Track
Lesson Time: 8 hours
e
Lesson Introduction
ut
Now that the project team has been assembled and is doing the work of the project,
you need to ensure that the team stays on track. As the project manager, you need
to demonstrate the type of leadership that facilitates collaboration among the team
ib
and stakeholders, manages conflict, removes obstacles, and supports the team's
performance. In this lesson, you will keep your project team on track.
tr
This lesson addresses tasks from the People domain of the PMP® Exam Content
is
Outline (ECO).
D
Lesson Objectives
In this lesson, you will learn how project managers and teams:
•
•
• or
Inspire, motivate, and influence team members and stakeholders.
Appraise team performance against key performance indicators.
Determine, prioritize, and remove impediments, obstacles, and blockers for
e
the team.
•
at
Investigate and interpret the source and stage of a conflict and recommend
an appropriate conflict resolution solution.
• Evaluate stakeholder engagement needs and influence stakeholders to
lic
Lesson Topics
D
Title Slides
Topic A Lead a Team 2-16
ot
Performance
e
The appropriate leadership style depends on the situation, the project, the
ut
stakeholders, your skills, and many other factors. A project manager must be astute
in various leadership styles to apply the most suitable technique for the moment.
ib
tr
is
D
or
Lead A Team
on the project team. If you are the project lead, then you
also need to lead on leadership!
up
Leadership
N
manager.
e
users’ and customers’ expectations.
ut
Leadership Skills
ib
leadership skills that enable a good working environment
and guide your project team toward accomplishing the
tr
desired result.
is
This requires a balance of ethical, interpersonal, and
conceptual skills that help you analyze situations and
D
interact appropriately. Project managers work with and
communicate with a number of different people
throughout the life cycle of a project, so having strong
or
people and leadership skills is critical.
• Solve problems
• Exhibit integrity, and
• Guide the team toward a successful project close.
up
e
observing and acknowledging different capabilities,
lifestyle and working requirements, cultural norms,
ut
language and translation needs, and so on.
• Understand that motivations and working styles of
ib
individuals and groups vary based on experiences,
age, culture, job roles, and other influences.
• Projects with diverse locations, industries,
tr
stakeholders, and cultures require communication
and openness to build trust
is
Leadership ≠ Management
D
Leadership is not the same as management.
or
Leadership refers to guiding the team by using
discussion and an exchange of ideas, whereas
management refers to directing actions using a
e
prescribed set of behaviors.
at
Not all team members and other stakeholders are
motivated and inspired the same way. Recognize and act
lic
Management Leadership
D
e
Do things right Do the right things
ut
Focus on operational Focus on vision,
issues and problem alignment, motivation, and
solving inspiration
ib
Idea: Think about how leading
tr
and managing are two distinct
actions by comparing and
is
contrasting the examples in the
management and leadership
columns.
D
Leadership Traits
• or
These are the traits that are typical of leaders.
Servant Leadership
N
e
Support the team so they can accomplish objectives in a
conducive environment. Lead with communication by
ut
removing distractions or roadblocks.
ib
You are working for the team; therefore, you must focus
on their needs. Being a servant leader requires skills
such as active listening, coaching, awareness, and
tr
facilitation.
is
Challenge the Status Quo
D
Challenging the status quo can open new ideas and
perspectives. Challenging the way things were done, or
are being done, at the present time assures all involved
or
that this is the best approach and the best product. It also
breaks complacency and blind acceptance.
e
Encouraging healthy skepticism on all aspects of the
project and its vision helps stakeholders not overlook
at
anything and assume too much.
lic
introspection.
• Avoid complacency and blind acceptance.
ot
e
reinforce performance or behavior. Reward and
ut
recognition plans are generally standardized throughout
an organization and approved through corporate
channels. The purpose is to motivate the team to perform
ib
well.
tr
Rewards can include monetary gifts, additional vacation
time or other perks, company plaques or trophies, or
is
small gifts. Although it is common for the terms “reward”
and “recognition” to be used interchangeably, they are
D
different.
or
reward.
• However, you should never reward a person
without recognizing them.
e
Reward - A tangible, consumable item that is given to a
at
person based on a specific outcome or an achievement.
Rewards can also have a defined start and finish, or fixed
lic
e
ut
ib
tr
is
D
or
e
at
lic
up
D
ot
N
o
D
e
You want to get the most from your team. In this topic, we will explore a few
ut
practices to provide support for the team.
ib
Support Team Performance
tr
Supported team members perform better and are
motivated to do their best work. You’ll need strategies to
is
maintain support to individual as well as for the whole
team.
D
Deliverables and Tools
This is a list of the deliverables and tools associated with
or
this topic. These slides are provided to help you match up
project tools and deliverables with tasks.
e
at
Key Performance Indicators (KPIs) (Definition)
lic
The KPI metric uses a few core examples to let the team
and others know that what they are doing is feeding into
N
project success.
o
e
Ensure the target is a realistic one; you need to be able to
achieve it within the size and scope of proposed
ut
improvement.
ib
Relevant - Ensures that the KPI is meaningfully related to
its associated critical success factor(s). The target needs
to be relevant in the context of the larger objectives and
tr
critical success factors.
is
Time-bound - Means the goal is not open-ended but can
be assigned a specific target duration. The timescale
D
used needs to assess whether the improvement has
achieved the desired results.
or
Supporting your Team
e
Setting up the physical environment supports the whole
ut
team engagement. Co-locating all involved in a shared
workspace fosters more informal and immediate
collaboration and exchange of information. Ensure private
ib
spaces for those who need to work in solitude.
tr
Even the passive information that is absorbed from the
surroundings—such as ad hoc discussions, side
is
conversations, whiteboard drawings, physical body
language have value. Being immersed in the team
D
physically and mentally improves the team's ability to
work faster, more collaboratively, and more unified.
or
Virtual Teams
ownership.
the project.
e
Encourage the team to foster team collaboration and
ut
decision making. The team does not depend on heavy-
handed discipline. The team must recognize the power
ib
and influence they possess. As an empowered cohesive
unit, they depend on each other to make decisions and
tr
solve problems to deliver targeted value quickly.
Keep the Tone Positive and Fluid
is
Establishing a culture of fluid communication and
D
engagement in a workspace that promotes those positive
interactions makes leading and managing teams much
easier.
or
Team Building Activities
e
To foster team building within a project team, a project
at
manager might ask each of the veteran employees on the
team to partner with a less experienced team member,
lic
Team Building
group facilitator.
e
performance assessments help to identify the potential of
each team member in order to help improve interaction
ut
between team members, solve issues, and deal with
conflicts.
ib
A team's technical success is measured on the basis of
tr
meeting the project objectives and finishing the project on
time and within the decided budget. Continual formal or
is
informal evaluations of the team's performance is an
effective way to improve the skills and competencies of
project team members and increase team cohesiveness.
D
You can follow these guidelines to assess team
or
performance:
Ask key questions of the team members - Questions
may include their work experience, likes and dislikes
about the projects assigned to them, tasks that they
e
are confident about, and project tasks they will prefer
at
to do.
Speak to team members frequently – Communicate
through one-to-one meetings and regular project
lic
management.
Provide constructive criticism and acclaim to team
members, as necessary - Team successes should be
D
e
• Re-clarifying roles and responsibilities.
• Delivering positive as well as negative feedback.
ut
• Discovering unknown or unresolved issues.
• Creating and monitoring individual training plans.
ib
• Establishing future goals.
Team Development
tr
Commit time and effort to developing your team, as a
is
team. Though people will come and go, having a strong
group identity is essential.
D
Your team will naturally progress and regress. This is
normal. Focus on acknowledging diversity—both cultural
or
and of personal characteristics. Promote trust,
communication, and respect.
Team Development Stages
e
(Tuckman ladder)
at
1. Forming
ot
2. Storming
Team members begin to assert themselves and control
issues as they emerge. Personality differences begin to
arise. Conflicts result as team members differ on the way
3. Norming
The team begins to work productively, without worrying
e
about personal acceptance or control issues. There are
still conflicts; however, they tend to be focused on
ut
process issues rather than personality differences. The
team begins to operate off mutual dependence and trust.
ib
4. Performing
The team is working at optimum productivity. It is
tr
collaborating easily, communicating freely, and solving its
own conflict problems. Team members feel safe in
is
reporting problems, trusting their fellow team members to
help them create the best solution for the team as a
D
whole.
or
5. Adjourning
The team members complete their assigned work and
shift to the next project or assigned work. This phase is
sometimes known as "mourning."
e
at
The process of forming, storming, norming, performing,
and adjourning is not done in a "lock step" fashion by the
team. Team members keep coming in and going out of
lic
e
and receiving. Asking for feedback from your team means
they know you are willing to listen to them.
ut
Performance Tracking Techniques
ib
Tools can track performance and render visualizations.
This is a powerful method of showing work contributions.
tr
Scrum/Agile/Kanban boards - Based on the Kanban
is
management method of using cards, physical or
electronic boards can track work as it progresses across
D
various stages or categories.
or
that has moved from one stage to another stage over a
certain time.
e
Cycle Time - Measurement of work that has progressed
all the way from plan to completed or delivered.
at
e
ut
Earned Value Management (EVM)
ib
You can measure project progress by comparing actual
schedule and cost performance against planned
tr
performance as laid out in the schedule and cost
baselines.
is
Assessing the value of work requires first determining
D
what work has actually been performed and therefore
what value it has contributed to the project. These
performance reviews are usually included in each project
or
status review meeting.
problems.
EVM Variables
o
e
Planned Value
ut
Planned Value (PV) is the authorized budget assigned to
scheduled work. This amount is specified in the project's
cost baseline. In simpler terms, PV indicates the value of
ib
work scheduled to be done during a particular time
period.
tr
Earned Value
is
Earned Value (EV) is the measure of work performed
expressed in terms of the budget authorized for that work.
D
In other words, EV is a composite measurement of both
cost and time performance in relation to scheduled or
planned cost and time performance.
or
EV is calculated by multiplying the percentage of work
completed by the budgeted cost for the activity as laid out
in the cost baseline.
e
Earned Value (EV) = % completed x Planned Value (PV)
at
In order to determine the EV of the project work to date,
you will have to look back at the cost baseline to
lic
Actual Cost
Actual Cost (AC) is the realized cost incurred for the work
ot
money that has been spent for work that has been
completed.
e
performance expressed as the difference between the
earned value and the planned value. (SV = EV – PV)
ut
o A positive SV indicates that the project is ahead
of schedule.
ib
o A zero SV indicates that the project is on
schedule.
tr
o A negative SV indicates that the project is
behind schedule.
is
Schedule Performance Index (SPI) is a measure of
schedule efficiency expressed as the ratio of earned
value to planned value. (SPI = EV / PV)
D
o An SPI number greater than 1.0 indicates that
the project is ahead of schedule.
or
o An SPI of 1.0 means the project is on
schedule.
o An SPI number less than 1.0 indicates that the
project is behind schedule.
e
EVM Measures for Cost Control
at
are:
Cost Variance (CV) is the amount of budget deficit or
surplus at a given point in time, expressed as the
up
e
It is based on the current spending efficiency (the CPI),
and is calculated from the following formula, where
ut
Budget at Completion (BAC) is the sum of all budgets
established for the work to be performed.
ib
tr
is
D
Estimate to Complete Analysis (ETC)
or
more money you will need to complete the project. This
amount is called the Estimate to Complete (ETC).
e
It is based on the current spending efficiency of the
project and is calculated from the following formula.
at
lic
up
e
(not pictured) Velocity chart - Graphs the completion
rate of the team over time and helps predict future
ut
iterations.
ib
(not pictured) Iteration Cumulative Flow Diagram -
Graphs the throughput of work in the various defined
stages during a timeboxed period.
tr
Earned Value Management Reports - Graphs and
is
values based on the earned value management (EVM)
equations.
D
Variance Analysis Reports - Graphs and their analysis
or
comparing actual results to planned or expected results.
e
ut
Value Stream Map
ib
Work must flow and be fluid. Bottlenecks, slowdowns,
delays, or other forms of non-value effort creates waste
tr
and distraction. Anything not delivering or attributing to
value is wasteful.
is
Producing a Value Steam Map can call out how
D
information and materials in the project and between
team members may be diluted, clogged, or otherwise
wasted of its value.
or
The Value Stream Map presents visual representation of
a process and the actions in each step to spot efficiencies
e
as well as wasteful efforts.
at
Value stream is an organizational construct that focuses
on the flow of value to customers through the delivery of
lic
project environment.
N
e
lessons learned and analyze and apply them moving
ut
forward.
ib
involve everyone and respect everyone's input. These
sessions are not blame games; they are learning and
tr
growth opportunities. The output of the retrospective is a
plan on how to make improvement in the ensuing iteration
is
and beyond.
D
You must facilitate the retrospectives to seek
improvements and recognize successes. Often there are
more lessons learned that can be implemented.
or
Stack rank the opportunities by importance and urgency.
Then incorporate tasks to realize these improvements in
the ensuing iterations or apply some of the ideas to the
e
team environment where appropriate.
at
e
ut
Throughout the project, you will encounter impediments, obstacles, or constraints.
These elements will restrain, slow down, or block the team’s progress towards the
project’s objectives. The interference can range from minor to catastrophic. In minor
ib
cases, the team may experience inconvenience, but sometimes a hindrance
threatens to stop work completely.
tr
Address and Remove Impediments, Obstacles,
is
and Blockers
D
In this topic, you learn how to keep the project path clear
of hindrances by employing project management
or
strategies and skills.
important.
D
Impediments (Definition)
e
ut
Blockers (Definition)
ib
Events or conditions that cause stoppages in the work or
advancement.
tr
is
Impediments, Obstacles, and Blockers
D
Let’s consider some examples of impediments,
obstacles, and blockers.
or
Projects can be blocked for many reasons. The type of
hindrances varies greatly based on industry,
e
stakeholders, the project and business environment, and
the project itself.
at
a file-saving solution.
could work.
e
In this case, someone needs to intervene
ut
and get the contract signed, or work will
stop.
ib
The number and weight of impediments may vary
throughout a project. The variation may even fluctuate
tr
throughout the day.
is
As the team identifies an impediment, they need to alert
others on the team. The project manager assists in
D
facilitating the evaluation of the impediments and how
they could or could not impact the team’s ability to work.
or
Based on those judgements, the team figures out how to
address the impediments. Often, the resolution, or
occasionally the research, is performed by the project
manager to enable the team to focus on more
e
meaningful, productive tasks.
at
e
intentions for the current day, and highlights any
obstacles encountered or anticipated.
ut
Daily Standup
ib
One practice to assist with uncovering the impediments
tr
impacting the team in a timely manner is a Daily Standup
meeting.
is
Also known as a Daily Scrum, the Daily Standup is a
D
short, 15-minute meeting in which the complete team
gets together for a quick status update while standing in
a circle. Ideally, the standup meetings should be
or
conducted at the start of working hours, and the
presence of all team members involved in the Sprint is
mandatory.
e
During the meeting, these questions are answered:
at
e
as everyday conversations, are added to the risk list.
ut
A rigorous review of project risks ensures that risks are
identified and documented. Newly identified and existing
ib
risks on the project risk list must be updated based on
the current knowledge and situation.
tr
Handle Impediments as a Servant Leader
is
As a servant leader, a project manager aims to create an
unobstructed path for the project team so they may
D
contribute and deliver.
or
free of obstacles and other impediments. This extends
from the physical team space to shielding the team from
non-value activities.
e
Removing distraction, randomization, and other
at
e
GUIDELINES: Prioritize Critical Impediments,
ut
Obstacles, and Blockers
ib
Define the categories or levels of prioritization
appropriate for your team, project, and/or
organization. Redefine levels as needed.
tr
• Anchor the priority levels with real examples.
• Clarify the new and still open impediments.
is
• Review the impact or potential impact to the team
and to the project objectives.
D
• Assign a priority to each impediment as a team or
a selected sub-group based on connection to the
impediment.
or
• Communicate the priorities levels in an easily
accessible area, such as a software tool,
information radiator posted on a wall, or
e
communal message board.
• Begin creating action plans for the highest priority
at
impediments.
• Reassess continually to ensure impediments,
lic
e
Working as a team and with a variety of stakeholders, there are bound to be
conflicts. Conflict in projects is inevitable. Conflict is natural. Conflict can be a positive
ut
benefit to the project and its outcomes, if managed and cultivated properly.
ib
Manage Conflict
tr
An extremely important part of the role is maintaining a
peaceful, productive working environment. In this section,
is
we learn how to deal with conflicts, so that when they
arise, you can attend to them.
D
Deliverables and Tools
This is a list of the deliverables and tools associated with
or
this topic. These slides are provided to help you match
up project tools and deliverables with tasks.
e
at
Project Manager’s Role
lic
e
• Differences in objectives, values, and perceptions
• Disagreements about role requirements, work
ut
activities, and individual approaches
• Communication breakdowns
ib
You should be aware of certain characteristics of conflict
tr
that will help them effectively handle conflicts when they
arise.
is
Conflict is natural and forces the need for exploring
alternatives. It is a team aspect, and openness about the
D
situation or opinions can resolve conflicts.
or
While resolving conflicts, focus should be on the issues
and not on individuals. Also attend to the present
situation and not on the past.
e
Conflict Management (Definition)
at
Conflict Management
deliverables.
Conflict Management Approaches
o
e
You will need to use leadership skills and your expert
judgment to assess the situation and choose a conflict
ut
resolution method. Let’s explore each of these in greater
depth next.
ib
Conflict Management Approaches (1 of 2)
tr
Smooth/Accommodate
• Emphasize areas of agreement rather than areas of
is
difference.
• Concede your position to the needs of others to
D
maintain harmony and relationships.
Withdraw/Avoid
or
• Retreat from an actual or potential conflict situation.
• Postpone the issue to be better prepared or to be
resolved by others.
e
Compromise/Reconcile
at
• Search for solutions that bring some degree of
satisfaction to all parties.
lic
Force/Direct
• Pursue your viewpoint at the expense of others.
D
Collaborate/Problem Solve
• Incorporate multiple viewpoints and insight from
N
differing perspectives.
• Enable cooperative attitudes and open dialogue to
reach consensus and commitment.
o
D
e
Project success depends on engagement and appropriate collaboration of project
stakeholders. The more collaboration and alignment, the better ability for the project
ut
to deliver value and progress towards those ends. Working collaboratively requires
constant effort and balance. The tighter the collaboration, the more aligned and
accurate the deliverables.
ib
Collaborate with Stakeholders
tr
We’ve already discussed identifying stakeholders and
is
learning how to best communicate with them. Beyond
this is establishing meaningful and collaborative
D
relationships.
or
Deliverables and Tools
This is a list of the deliverables and tools associated
with this topic. These slides are provided to help you
e
match up project tools and deliverables with tasks.
at
lic
Engaging Stakeholders
e
project.
• Identifies the management strategies required to
ut
effectively engage stakeholders.
• Project managers should be aware of the sensitive
ib
nature of the stakeholder engagement plan and
take appropriate precautions when distributing the
plan to other team members.
tr
The stakeholder engagement plan goes further than the
is
stakeholder register, providing additional information
such as:
D
• Desired and current engagement level of key
stakeholders.
• Scope and impact of change to stakeholders.
or
• Identified interrelationships and potential overlap
between stakeholders.
• Stakeholder communication requirements.
e
• Information to be distributed to stakeholders.
• Reason for the distribution of that information and
at
required information.
• Method for updating and refining the stakeholder
engagement plan.
up
Effective Collaboration
D
Collaboration
D
e
set. Engagement also builds appreciation for others’
needs and constraints.
ut
Communication skills, interpersonal skills, feedback,
ib
meeting management, among other management skills,
are leveraged to maximize the feedback loop and
engagement between stakeholders.
tr
Collaboration Activities
is
Stakeholders collaborate every day in a project. Some
D
stakeholders may be engaged less frequently; for
example, a Project Sponsor who gets updates monthly
or a Product Owner who only engages with the
or
development team three or four times during an
iteration.
e
The frequency of engagement is based on mutual
needs and expectations. Nearly constant engagement
at
amongst the core project team is common. Encouraging
that regular collaboration can be supported by daily
lic
e
• Review the lessons-learned database and historical
information, as they provide insight on previous
ut
stakeholder engagement plans and their
effectiveness.
ib
Develop a Stakeholder Engagement Plan –
(Part 2 of 2)
tr
• Use expert judgment to decide upon the level of
is
engagement required at each stage of the project
from each stakeholder.
D
• Hold meetings with experts and the project team to
define the required engagement levels of all
stakeholders.
or
• Use analytical techniques to classify the level of
engagement for stakeholders.
• Document the stakeholder engagement plan.
e
Maximize Meeting Time
at
three strategies:
• Be organized
• Timebox
• Collaborate – Though you might be running the
up
o technology
o urgency
Set and distribute an agenda prior to the meeting
start.
Projects are managed with a sense of urgency.
Meetings should support that sense of urgency by
starting promptly.
Review the agenda set prior to the meeting and
e
another scheduled meeting with appropriate
stakeholders.
ut
Recap the meeting and any action items to follow
the meeting.
ib
Thank everyone for attending.
Adjourn the meeting per the scheduled time or
earlier.
tr
Distribute the meeting notes or recording as agreed.
is
D
or
e
at
lic
up
D
ot
N
o
D
e
Project management is an art and a science. You improve with practice, learning,
and experience. You learn from others every day. You are learning from this
ut
course. Likewise, there are plenty of opportunities for you to share your knowledge
and experience with others.
ib
Mentor Relevant Stakeholders
tr
Project management is constantly growing and refining
is
the best practices that make us all successful. Increasing
the knowledge base and the skill sets of all project
stakeholders sets up for more successful and effectively
D
managed projects.
or
Deliverables and Tools
This is a list of the deliverables and tools associated with
this topic. These slides are provided to help you match
e
up project tools and deliverables with tasks.
at
lic
on best practices.
• When onboarding a new project team member, guide
them on team processes.
ot
e
Begin with mentoring relevant stakeholders associated
with your project and expand from there.
ut
Let’s look at some ways of cleverly working mentoring
ib
and coaching into your schedule.
Individual Mentoring and Coaching
tr
Mentoring and coaching relevant stakeholders can come
is
in many forms. The expansive range of project
management knowledge – in academic, explicit form and
D
in experience based tacit form – can be passed onto
others in various modes.
or
Process/Task One-on-One Mentoring
• Encouraging others to take the lead on activities
• Facilitating meetings and sessions
e
• Practice taking on new roles
• Informal opportunities
at
• Formal opportunities
• Transferring skills
lic
• Modeling behaviors
• Teammates assist each other
up
• Transfer skills
• Demonstrate desired skills and best practices every
day
e
involved in the activity are learning.
ut
Project managers can call out and explain what is
happening and why. Others in the group can contribute
ib
and guide the practice. The entire team learns and grows
as a unit.
tr
Training and Sharing Plans
is
When an environment encourages and values learning
and knowledge sharing, all stakeholders gain. Setting
D
aside time for sharing and learning can increase the
opportunities to capitalize on mentoring.
or
Formal or informal plans can be established for training
and sharing. Setting times during meetings – such as at
the end of a status meeting or project review session –
e
can be ideal times for sharing what has been learned.
at
e
or understanding to another level requires patience and
compassionate mentoring. Making the change to an agile
ut
operating system can be frightening for team members
who are accustomed to a more deliberate style of
ib
planning and delivering.
tr
The most high-performing teams remain adaptable in the
face of dynamic change. Remember, the skill set you and
is
your project team hold, or utilize, today may be obsolete
or limited tomorrow, especially in a digital world.
D
or
e
at
lic
up
D
ot
N
o
D
e
ut
Emotional intelligence is essential in working with teams. The human resource is
sentient and responsive to emotional triggers. Let’s learn about how to use this skill
appropriately.
ib
tr
Apply Emotional Intelligence to Promote Team
Performance
is
The interpersonal skills related to emotional intelligence
D
are the topic of this section. Learning how to motivate
team members, assess tricky situations, and inspire the
or
team begins with your keenest attention to your human
resources.
Deliverables and Tools
e
This is a list of the deliverables and tools associated
with this topic. These slides are provided to help you
at
Emotional Intelligence
up
Emotional Intelligence
o
e
• Motivation describes your intrinsic reasons for
achievement.
ut
• Social skills address how well you build
relationships and rapport with others.
ib
• Empathy is how well you read and understand
the emotions of others.
• Being able to read the emotions and feelings of
tr
others, as well as recognizing how your emotions
and behaviors positively or negatively affect
is
others, is crucial for effective management and
team performance. The following sections
D
describe the elements of the five EI skills.
Self-Awareness Elements
or
Each emotional intelligence skill is made up of, or
influenced by, a number of components. Self-
e
awareness elements include the following.
at
Emotional Awareness
• Knowing which emotions you're feeling and the root
lic
Accurate self-Assessment
ot
reactions.
o
Self-Confidence
• Expressing opinions that may not be popular.
D
e
to practice behavior that will strengthen your
relationship with your associates and your company.
ut
Here are self-regulation elements.
ib
Self-control
Remaining cool, calm, and even-tempered under
tr
pressure
Staying focused and quick-witted in a stressful
is
environment.
Effectively controlling your rash and destructive
emotions.
D
Trustworthiness
or
Acknowledging your own errors, and challenging
immoral conduct in others.
Establishing confidence through your reputation
for honesty and credibility.
e
Standing by your principles, even if others don't
at
share your beliefs.
Behaving in a morally correct way, above
suspicion.
lic
Conscientiousness
Having a well-ordered, meticulous approach to
up
work
Being accountable for fulfilling your goals.
Satisfying obligations and delivering on promises.
D
Adaptability
Adjusting your strategies and responses to adapt
ot
to changing events.
Interpreting events in a flexible way.
N
• Active listening
• Communications styles assessment
• Emotional intelligence
• Influencing
e
ut
Motivation is the EI skill associated with your personal,
internal abilities. It's about raising your ambition to attain
peak performance. Let’s review this while thinking about
ib
how to nurture and grow these factors in yourself and
the team.
tr
Achievement drive
is
• Setting tough goals and taking chances.
• Driving hard to get results and satisfy, or exceed,
D
aspirations and ideals.
• Discovering how to upgrade your capabilities.
• Striving to minimize uncertainty and discovering
or
ways to improve.
Commitment
e
• Relying on your team's core principles to make
decisions.
at
• Realizing a benefit in a comprehensive quest.
• Gladly sacrificing to fulfill a substantial company
lic
goal.
• Enthusiastically searching for opportunities to help
achieve the team's mission.
up
Initiative
• Working toward goals beyond what's essential or
D
anticipated.
• Inspiring others through extraordinary, resourceful
feats.
ot
Optimism
o
e
making beyond the immediate circumstance and your
individual priority.
ut
Empathy – Looking Inward
ib
Let’s consider some empathetic traits that make
individuals more able to contribute to collaborative,
tr
high-performing teams:
is
Understanding others
Being of service to others based on their particular
D
needs and emotions.
Readily observing emotional cues and listening
carefully.
or
Displaying tact and appreciating, or sharing, others'
points of view.
e
Service orientation
Happily providing proper help.
at
to products or services.
Empathy – Looking Outward
D
development needs.
D
Leveraging diversity
Appreciating various life philosophies and being
conscious of group contrasts without judging.
Viewing variety as favorable circumstances,
e
Political awareness
ut
Understanding the political truths and realities of
companies.
ib
Grasping the influences that determine opinions
and behaviors of clients, consumers, or rivals.
Recognizing critical social systems.
tr
Correctly interpreting crucial power connections.
is
Social Skills - Elements
D
Social skills draw on other emotional intelligence skill
sets to build strong relationships with people and affect
change in the organization.
or
Here are some critical social skills for high-performing
teams:
e
Communication
Building Bonds
at
Collaboration/Cooperation
Change Catalyst
lic
Conflict Management
Influence
Leadership
up
Team Capabilities
Communication
Managing tough problems directly.
N
perceiving.
Cultivating clear communication and being open
D
Building bonds
Building and maintaining friendly connections
e
Social Skills Elements
ut
(Part 2 of 4)
ib
Collaboration and Cooperation
Fostering an amiable, collaborative environment.
Recognizing and cultivating options for
tr
cooperation.
Balancing job duties and professional
is
relationships.
Working together and sharing strategies,
D
knowledge, and assets.
Change catalyst
or
Challenging the current situation to appeal to the
need for change.
Advocating for change and recruiting others to
e
strive for the transformation.
Appreciating the importance of change and doing
at
Conflict management
Detecting possible clashes, moving disputes into
D
Influence
o
Leadership
Expressing and stimulating interest for a
e
collective vision and goal.
ut
Modeling effective leadership.
Taking on a leadership role based on necessity,
regardless of official title.
ib
Directing others' performance while maintaining
their accountability.
tr
Team capabilities
is
Building team character, camaraderie, and
dedication.
D
Attracting group members into committed and
passionate involvement.
Displaying team characteristics such as civility,
or
supportiveness, and collaboration.
Safeguarding the team and its good name.
Organizational Theory
D
Motivating people
Meeting the stakeholder requirements of a
o
project.
D
e
McGregor's Theory X and Theory Y apply to the
management of labor. Theory X states that people
ut
generally do not like to work and are not motivated to
work. Management feels the need to supervise labor to
ib
maintain productivity. Theory Y is essentially the
opposite: people want to work and enjoy it, and
tr
management does not need to "hover" and constantly
supervise. Sometimes, Theory X is called the "old-
is
school" approach, and Theory Y is a more modern
approach.
D
McClelland's Achievement Theory has three
components: achievement, power, and affiliation.
or
Achievement relates to success, power to influence
other people, and affiliation to belonging to a team.
Active Listening
D
stakeholders.
Reflecting: Most people are aware of the reflecting
D
e
thoughts.
ut
GUIDELINES: Building Emotional Intelligence
with Key Stakeholders
ib
Recognize your own emotions and behaviors.
Assess how your emotions, attitudes, actions,
tr
behaviors control you.
Observe how your emotions affect those around
is
you.
Take note of physical nonverbal cues of others,
D
such as a shrug or smile.
Interpret those cues against the context,
situation, and your emotions.
or
Remain mindful of the emotions of others.
Mirror the behaviors of others when suitable to
become better connected.
e
Practice controlling or changing your emotions to
better suit the situation.
at
End of Lesson 4
lic
Lesson 5
Keeping the Business in Mind
PMI® Authorized PMP® Exam Prep
Lesson 5: Keeping the Business in Mind | Topic B 1
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM
Keeping the Team on Track
Lesson Time: 6 hours
e
Lesson Introduction
ut
Projects don't exist in a vacuum. Internal and external
business environments can influence and affect the work of a
project. As the project manager, you need to manage compliance
ib
requirements and ensure that the project is delivering
benefits and value. Keeping a handle on the changes in both
tr
the internal and external business environments are the
project manager's responsibility. Employing a continuous
is
process improvement plan will ensure that the project's
success can be consistently repeated within your organization.
D
In this lesson, you will learn how to keep the business in
mind during the life of the project.
Lesson Objectives
or
e
In this lesson, you will learn how project managers and teams:
at
Determine necessary approach and action to address
compliance needs.
lic
Lesson Topics
ot
Title Slides
Topic A Manage Compliance Requirements 2-23
N
Changes
Topic D Support Organizational Change 61-73
Topic E Employ Continuous Process 74-85
Improvement
e
political, business, and industry contexts of your project’s
ut
product or service. Whatever they are, you are in charge of
ensuring that your project activity and outcomes are aligned
with legal or regulatory standards, as necessary.
ib
tr
is
D
Manage Compliance Requirements
or
Let’s look at how project managers meet
and maintain these requirements throughout
e
a project.
at
Compliance Requirements
ot
e
ut
During the project, you have tracked and
managed risks using a risk register. Some
ib
of these risks will relate to compliance
with legal and regulatory requirements.
tr
Non-compliance itself is a risk—Waiting
until delivery time to ensure compliance
is
or perform a summary check of compliance
is a risk. If the team identifies
D
disparities late, you will likely trigger
project time and cost overruns.
or
Compliance management includes creating
suitable testing and validation plans
during development to ensure that the
e
project's deliverables meet compliance
requirements.
at
Compliance-related Risks
lic
compliance checklist:
Risk owner
Impact if the risk is realized
Risk responses (potentially
ot
e
deliverables and will continue to be
tracked in the customer’s configuration
ut
management system.
ib
One of the key attributes you will want to
track is compliance information, including
tr
proof of validation for each deliverable
that it meets the identified compliance
is
requirements.
D
demonstrate to the customer that the
deliverable meets the relevant compliance
or
requirements.
Compliance Categories Classification
e
Let’s take a moment to explore compliance
categories. If you are new to a company,
at
country/region, or industry, you will need
to do some research to understand the
lic
Environmental Risk
ot
Quality
Process Risks
o
classifications related to
quality and social
responsibility would include
“b-corp” or “vegan”
certifications.
e
ut
Regular work performance reports –
these will provide details of workplace
standards and practices
ib
Checklists with:
o Project activities and changes
tr
o Team improvements
o Deliverable status
is
o Overall progress
o Risk status
Information about compliance-related
D
risks, such as:
o Risk management actions
or
o Testing and validation activities
o Audits
o Other actions to verify deliverable
compliance
e
Variance Analysis
at
things on track.
e
requirements.
ut
Hopefully, if you have put the recommended
plans in place, the last threat can be
ib
avoided. For the rest of the list, you
handle them just as you would handle a
tr
risk.
Signoffs and Approvals
is
A designated stakeholder should be
D
accountable for each compliance
requirement in your project. This
stakeholder is authorized to sign off and
or
approve compliance. Depending on the
requirement and the project, this may be a
list of stakeholders who need to approve
e
and sign off.
at
While many of these approvals may not be
possible until shortly before project
lic
e
Track and manage the review and
approval activities related to
ut
compliance requirements.
Track and manage the risks and risk
ib
responses related to compliance
requirements.
tr
Next Section: Deliver Benefits and
Value
is
Now let’s discuss how projects deliver
D
benefits and value. Your role as project
manager in value delivery is to ensure
good results for the business. This takes
or
a combination of the technical and soft
skills we just learned.
e
You also should identify how the project
aligns with the business’s overall
at
Compliance
A proven method of aiding compliance
D
subject of quality.
D
e
quality objectives and is an appropriate
ut
place to set expectations for the
project's quality requirements. Quality
requirements might include:
ib
Quality standards to be used.
Quality objectives of the project.
tr
Quality roles and responsibilities.
Project deliverables and processes
is
subject to Quality review.
Quality Control and Quality Management
D
activities planned for the project.
Quality tools to use.
Major procedures relevant for dealing
or
with nonconformance, corrective action
procedures, and continuous improvement
procedures.
e
Control Quality Process Outputs
at
improvements.
e
handle it, or will it need to be
ut
escalated?
ib
project manager’s purview, identify the
stakeholders who are authorized to review
tr
it and assign it to them to manage.
is
This procedure should be defined during
project and risk planning.
D
Quality Audits (Definition)
A process conducted by an external team
or
that confirms the implementation of
approved change requests including
updates, corrective actions, defect
e
repairs, and preventive actions.
at
Audits
lic
practices.
Identify any nonconformity, gaps, and
shortcomings.
o
e
defect repairs, or preventive actions.
ut
Sampling
ib
Another process that can help ensure
compliance is sampling. Because it may not
be viable for quality assurance to inspect
tr
every single product or deliverable, the
sampling method assists in quality review.
is
An appropriate sampling approach can
D
provide similar results in identifying
quality issues and reducing the costs of
quality, thus helping to better align the
or
quality assurance costs with the overall
value to the project.
GUIDELINES: Measure Project
e
Compliance
at
early as possible.
Establish where external audit teams
N
e
Project Benefits and Value
ut
A project is undertaken to meet the objectives and
requirements of its stakeholders, and the project manager is
ib
responsible for delivering what these stakeholders expect.
tr
Evaluate and Deliver Project Benefits
and Value
is
Great project managers think
D
strategically. They have their eye on a
project’s benefit and value to the
or
organization. So, remember to look up from
your schedules and data and ensure you
understand your project’s relationship to
the business.
e
at
First, we will look at methods of
accelerating value delivery in a project
and then some ways of measuring it.
lic
e
Benefits Management Plan
ut
(Definition)
ib
A document that describes how and when the
benefits of a project will be derived and
measured.
tr
is
Benefits Management Plan
D
A benefits management plan typically
includes the following components:
Target benefits—the expected tangible
or
and intangible business value to be
realized from the project.
Strategic alignment—how the benefits
e
align with the business strategies of
the organization.
at
Timeframe—when the benefits (short-term
and long-term) will be realized,
lic
benefits.
Metrics—the direct and indirect
measurements of the realized benefits.
Risks—the risks associated with
D
Sprint Reviews/Demos
D
e
acceptance of the story from the product
owner because it should meet all of the
ut
defined acceptance criteria and to get
early feedback from other stakeholders,
ib
which may unearth changes or additional
undefined requirements.
tr
The sprint review then is used to review
is
progress on the overall product, and to
get feedback early while it’s still
relevant if certain aspects of the
D
solution need to be changed or enhanced in
certain ways to optimize business value.
or
Release Management
e
One of the fundamental benefits of agile
projects is the ability to convert high
at
value capabilities into delivered
solutions early.
lic
“done”.
D
e
business increment (MBI) that defines
ut
work requirements to deliver the stated
value.
o The MBI creates value quickly and
ib
incrementally, so the business can
start using and benefitting from
tr
it.
is
Advantages:
Feature or capability assessment
Improve organizational tolerance for
D
change
A time cadence for subsequent releases
or
Benefit Cost Analysis (Definition)
Further information on the next slide.
e
A systematic approach to estimating the
strengths and weaknesses of alternatives
at
e
ut
Present Value (PV) Calculation
ib
Although you might not need to memorize
how present value is calculated for the
tr
exam, seeing the formula will help you put
the concept into perspective. “PV” is
is
present value, “FV” is future value, “r”
is interest rate, and “n” is number of
D
periods.
or
e
For example, if you need
at
$3,000 in three years and can
invest your money at 8 percent
lic
e
(Definition)
ut
The interest rate that makes the net
present value of all cash flow equal to
ib
zero. IRR is also a financial tool often
used in capital budgeting. IRR is the
discount rate at which the NPV of the
tr
project is zero. It is calculated
iteratively, by setting up the NPV
is
calculation in a spreadsheet or other
software and changing the discount rate
D
until the NPV equals zero.
Return on Investment (Definition)
or
A financial metric of profitability that
measures the gain or loss from an
investment relative to the amount of money
e
invested.
at
It is sometimes called the “rate of
return” and is usually expressed as a
lic
Detractors (0-6)
Would be very willing to work with another
provider, as some aspect of the solution
e
left them less than satisfied.
ut
Passives (7-8)
Somewhat satisfied, but may be willing to
ib
try competitive offerings.
tr
Promoters (9-10)
Very satisfied, and would choose to work
is
with the provider again. May choose to
evangelize the solution to other people.
D
A/B Testing
or
Another way of deriving benefit and value
information from the customer or end-user
is A/B testing. Feedback from real users
e
before final delivery is extremely
valuable during development.
at
e
“bigger picture” to peruse options?
ut
A Monte Carlo simulation generates outputs
to represent the range of possible
ib
outcomes for a project. Monte Carlo refers
to not one single analysis method but to a
wide class of techniques, mostly making
tr
use of sophisticated computers and inputs
of random numbers, probabilities, and
is
algorithms.
D
It has a wide range of applications in
many fields, including finance and
engineering because it works effectively
or
with large inputs of numbers.
Using Simulations
ot
e
A diagramming and calculation technique
ut
for evaluating the implications of a chain
of multiple options in the presence of
ib
uncertainty.
Use Decision Trees to Find Benefit
tr
and Value
is
Decision trees allow decision makers to
evaluate both the probability and impact
D
for each branch of every decision under
consideration, making it a useful tool for
risk analysis.
or
Solving the decision tree indicates the
decision that will provide the greatest
expected value when all the uncertain
e
implications, costs, rewards, and
at
subsequent decisions are quantified.
lic
e
ut
Effective project managers continually assess and evaluate
changes in their organization’s business environment as well
ib
as changes in the industry. Be ready to respond to change to
keep your project aligned with the business’s strategic
direction.
tr
is
Evaluate and Address Internal and
External Business Environment
D
Changes
Projects operate in highly dynamic
or
environments while generating change for
that environment. Highly skilled project
managers embrace the qualities of
e
adaptability and resilience to navigate
these environments and optimize outcomes
at
for their projects and the organizations
in which they operate. Let’s take a closer
lic
look.
Deliverables and Tools
This is a list of the deliverables and
up
e
Here is a quick overview of some helpful
ut
ones.
ib
business environment factors that can
affect the value and desired outcomes of a
tr
project. PESTLE considers political,
economic, social, technical, legal, and
is
environmental factors as causes or agents
of external change.
D
Others are:
✓ TECOP (technical, environmental,
or
commercial, operational, political)
✓ VUCA (volatility, uncertainty,
complexity, ambiguity)
e
These frameworks can help you to better
at
understand external factors that can
introduce risk, uncertainty, or provide
lic
opportunities.
Update Baselines
up
requirements.
e
ut
Business value—what will derive more value
and do so most quickly—determines the
priority of the changes.
ib
Recommended Options for Changes
tr
When change is proposed, the product
owner should focus on the intended
is
business value of the change.
Give the project team discretion to
D
consider the change and identify
potential solution options.
or
Clear Governance Structure
We explored project governance earlier.
This was the external context of your
e
project—where it lives, so to speak.
at
A senior user
PMO resources
D
e
ut
ib
tr
is
D
or
e
at
lic
up
D
ot
N
o
D
e
culture, style, and structure. Understanding this broader
ut
context helps ensure that work is carried out in alignment
with the organization’s goals and managed in accordance with
the organization’s established practices.
ib
In turn, projects can influence the strategic direction of
tr
organizations. And enterprise-level change projects—or
organizational transformations—are instrumental in
is
orchestrating change.
D
Support Organizational Change
Envisioning your project as part of the
or
organization in which it “lives” means
being part of any change initiative that
the organization takes. This will mean
e
adapting your project as well as
realigning it with the changing business
at
objectives.
lic
e
procedures
Motivation and reward systems
ut
Risk tolerance
View of leadership, hierarchy, and
ib
authority relationships
Code of conduct, work ethic, and work
tr
hours
Operating environments
is
As project manager, you should understand
that cultures have a strong influence on a
D
project's ability to meet its objectives.
or
For example, a company that
allows employees to work
flexible hours versus an 8-to-5
workday can directly affect how
e
a project manager schedules
at
resources, general morale, and
how the team interacts.
lic
Organizational Structures
An organizational structure dictates how
up
implementations:
e
core project team operate
ut
as a completely separate
organizational unit within
the parent organization.
ib
Core team members are
responsible for the work
tr
of extended team members
in their functional area.
is
Team members are often co-
located.
The project manager
D
reports to a program
manager and has a
or
significant amount of
authority and
independence.
Some projectized
e
organizations may contain
at
their own support systems
such as a separate
procurement or personnel
lic
department or share
support systems with the
parent organization.
up
characterized as weak,
balanced, or strong,
D
e
It is a combination of all
ut
the other types of
organizations.
ib
The structural model used by an
organization will have a huge impact on
tr
how project managers interact with team
members and stakeholders. In many cases, a
is
project manager will interact with various
levels in an organization such as middle
management, operations, strategic
D
functions, and senior management. Knowing
which individuals in the organization are
or
decision-makers or influencers and working
with them increases the probability of
project success.
e
Relative Authority in Organizational
Structures
at
e
There are several types of PMO structures,
each varying in the degree of control and
ut
influence they have on projects within the
organization:
ib
Supportive PMOs provide a
tr
consultative role to projects by
supplying templates, best practices,
is
training, access to information, and
lessons learned from other projects.
Controlling PMOs provide support and
D
require compliance through various
means. Compliance may involve
or
adopting project management
frameworks or methodologies; using
specific templates, forms, and tools;
or conforming to governance.
e
Directive PMOs take control of
at
projects by directly managing the
projects. A relatively small number
of PMOs fall into this category.
lic
e
include changes in scope, timelines, work
ut
packages, and even individual team member
assignments.
ib
If the project is agile, the impact may be
limited to lower-value deliverables being
tr
moved out of scope to make room for the
change.
is
Training Plan
D
Changes to the project plan likely will
impact the training plan. The changes may
include changes in the scope of the
or
training and knowledge transfer required,
changes in roles and responsibilities of
the stakeholders, and changes in the
e
timeline for when training will be
provided to the relevant stakeholders.
at
Training Artifacts
lic
made.
Demos
Changes to software solutions may
require demonstration of changed
configurations, processes, workflows,
and roles and responsibilities.
Key customer and user stakeholders
e
while the feedback is immediately
relevant and should improve the
ut
quality of the change while reducing
overall cost and risk.
ib
GUIDELINES: Recommend, Plan, and
Facilitate Change
tr
(Part 1 of 2)
is
Establish a single change request
method which includes:
D
o A description of the proposed
change
or
o The business value of the change
o Any risk and risk mitigation
recommendations
o Likely cost of the change
e
Ensure that a CCB can assess the
at
change cost, risk, and value, other
potential impacts to the project, and
make recommendations.
lic
Facilitate Change
(Part 2 of 2)
ot
stakeholders
o Communicate the change vision
D
e
competition. In your role as project manager, you can make a
ut
substantial contribution to this effort by espousing an
ongoing, positive attitude towards changing and improving
work.
ib
Employ Continuous Process Improvements
tr
Continuous process improvements are, quite
is
simply, a characteristic of organizations
that indicates an ongoing, vigilant, and
D
positive response to change. As a project
manager, you need to participate in these
efforts, as they are a very visible
or
vehicle of strategic organizational
change.
Deliverables and Tools
e
This is a list of the deliverables and
at
tools associated with this topic. These
slides are provided to help you match up
project tools and deliverables with tasks.
lic
up
services, or processes.
e
Continuous improvement has been used in
ut
business for nearly three-quarters of a
century. W. Edwards Deming was an early
ib
leader in the field of process
improvement, beginning with his work in
post-World War II Japan. He taught four
tr
concepts that have been the foundation of
the continuous process improvement
is
movement:
Better design of products to improve
D
service
Higher level of uniform product
quality
or
Improvement of product testing in the
workplace and in research centers
Greater sales through global markets
e
Deming’s philosophy was about improving
at
quality to reduce expenses, increase
productivity, and thus increase market
lic
Methods
ot
e
theories attempt to improve business
ut
results through an emphasis on customer
satisfaction, employee development, and
processes rather than functions.
ib
Do any of these inform your current
tr
approach to quality? Which resonate with
you?
is
Continuous Improvement Approaches
D
Agile is itself a means or process of
continuous improvement. Let’s look at two
other approaches:
or
Kaizen – A second idea emerging from
Japanese business (ca. 1980s). Its key
e
features include:
Improvements based on many small
at
changes.
Small changes less likely to require
lic
or product.
D
e
proceed.
ut
Note: PDSA is also known as the
Deming Cycle, or PDCA (Plan,
ib
Do, Check, Act) depending on
your region.
tr
Continuous Improvement Tools
is
Once you’ve decided on your approach to
quality and continuous improvement, you’ll
D
need to look into how to implement it.
Let’s consider a few appropriate tools:
or
Lessons Learned Register – This
important component of each project
can be a source of improving the
e
processes in other projects. Avoid
filing it away at the end of a
at
project and not referring to it.
Retrospectives – These are common in
lic
they’re working.
Update to Process and Standards
o
e
Develop a continuous improvement
ut
approach for your project, keeping in
mind the project goals and the
expectations of the stakeholders.
ib
Use lessons learned from your project
and other projects—as sources of
tr
continuous improvement.
For agile projects, use
is
retrospectives to improve the next
iteration.
D
Use lessons learned at the project
level to improve the organization’s
continuous improvement process.
End of Lesson 5
or
This is the end of the course. Thank you
e
for your participation and best of luck to
at
you as you continue your preparations to
take the PMP® Certification exam!
lic
up
D
ot
N
o
D
Licensed For Use Only By: Eduardo Recondo 6573471 Mar 31 2022 3:48PM