(E Billing) R.a.bill 1 Kalkeri (SC) Mdrs 23-05-2018
(E Billing) R.a.bill 1 Kalkeri (SC) Mdrs 23-05-2018
(E Billing) R.a.bill 1 Kalkeri (SC) Mdrs 23-05-2018
EXECUTIVE DIRECTOR
KARNATAKA RESIDENTIAL EDUCATIONAL
INSTITUTIONAL SOCIETY
8, MSB – 1, 6TH & 7TH FLOOR,
CUNNINGHAM ROAD,
BANGALORE – 560 052.
AT KALKERI
TALUK : HANGAL DISTRICT: HAVERI
Work Order No. : KREIS/PROJECT (2) /CR (2)-357/2016-17/ Work Indent-1604_Dated : 26-03-2018
CERTIFICATE ###
1) This work has been executed as per Work Order No. : KREIS/PROJECT (2) /CR (2)-357/2016-17/ Work Indent-1604_Dated : 26-03-2018 ###
2) This work has been executed during April to May - 2018. ###
3) I have taken the measurements along with agency & recorded in the M.B. book details mentioned in the abstract. ###
4) This work has been executed as per specifications, tender conditions and our supervision. ###
5) The work has been carried out satisfactorily.
6) Necessary material test certificates, photographs, work execution certificates are enclosed with this bill.
7) Necessary statutory deductions can be effected from your end.
8) Hence, the Bill is recommended for Rs. 24,499,930.32
WORK :- Constuction of MDRS Complex
AGENCY :- R. RAMA REDDY Engineer & Contractor
:- Kalkeri Village
:- Hanagal Taluk,
:- Haveri Dist
R. A. BILL - 01
ABSTRACT SUMMERY
Sl Previous
Description BOQ Amount Present Amount Upto Date
No Amount
1 Main Building Civil works Ground Floor 139,506,418.32 - 19,884,593.65 19,884,593.65
CERTIFICATE
1 This work has been executed as per WORK Order No - KREIS/Project (2)/CR (2)-357/2016-17
2 This work has been executed as per - MARCH 2018 to APRIL 2018
3 I have taken the measurements along with Agency and recorded the measurements in the MB No. 01
4 This work has been executed as per specifications, tender conditions and our supervision.
5 The relevant details, Drawings, BOQ's, Specification and Technical instructions at site are issued to contractor in time.
6 The work has been carried out satisfactorily.
7 Necessary statutory deductions can be effected from your end.
Hence, the Bill is recommended for
8 24,478,971.78
Rs.
Page 4
CONSTRUCTION OF ( SC ) MDRS COMPLEX AT KALKERI IN HANGAL TALUK OF HAVERI DISTRICT
Name of Work : Construction of ( SC ) MDRS Complex at Kalkeri in Hangal Taluk of Haveri District
Work Order No. : KREIS/PROJECT (2) /CR (2)-357/2016-17/ Work Indent-1604_Dated : 26-03-2018
Client : Karnataka Residential Educational Institutions Society, Bangalore
Name of Contractor : Sri. R. Ramareddy, Engineer & Contractor, Bangalore.
Bill No. : R.A.Bill No. 1
Agreement amount : 1867.55 Lakhs NIT Published : 09-06-2017
Date of commencement : 28-03-2018 Technical Bid Opening 28-06-2017
Date of completion : 27-08-2019 Contract Period : = 18 Months
Time of Extention :
Whole Sale Price Index Numbers
Labour Cement Steel All Commodities
Particulars Qtr/month
Index Average Index Average Index Average Index Average
March/17 295.00 106.70 89.40 113.20
Base index April/17 294.00 295.00 110.50 110.30 90.80 90.17 113.20 113.10
May/17 296.00 113.70 90.30 112.90
April/18 311.00 111.90 106.90 116.80
Months under
consideration 311.00 111.90 106.90 116.80
Page 7
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
KSRB 2-2.4 : Excavation by manual means for foundation of buildings, water supply &
sanitary lines and electrical conduits etc., either in pits or in trenches 1.50m and above
in width, in soft rock without blasting 1.50mtrs in depth including stacking the
excavated stuff clear from edges of excavation with lead upto 50mt including cost of
explosives,
5 2.6 labour, HOM of equipment complete as per specifications. specification. No. KBS
2.1C/2.9.4/2.18/2.19
Page 8
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 with
OPC cement @ 220kgs, with 40mm and down size graded granite metal coarse
aggregates @0.892cum and fine aggregates @ 0.465cum machine mixed, machine
mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in
foundation including cost
8 4.2 of all materials, labour, HOM of machinery, curing complete as per specifications.
Specification No. KBS 4.1, 4.2
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining
Principal Quarters 22.52
Teaching Staff Quarters-1 46.24
Teaching Staff Quarters-2 46.24
Non-Teaching Staff Quarters 40.10
Total Quantity 155.09 cum 556 4900 2724400 155.09 4900 759,956.21 155.09
KSRB 5.3-3 : Providing and constructing granite / trap / basalt size stone masonry in
basement with cement mortar 1:6, edges of stones chistle dressed in courses not less
than 15 cms high, bond stones at two m. apart in each course including cost of
materials, labour, curing complete as per specifications. KBS 5.1.13
10 5.9
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining
Principal Quarters 5.73
Teaching Staff Quarters-1 31.92
Teaching Staff Quarters-2 36.09
Non-Teaching Staff Quarters 12.46
Total Quantity 86.20 cum 581 5880 3416280 86.20 5880 506,842.71 86.20
Page 9
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
KSRB 2.3 : Filling available excavated earth ( excluding rock ) in sides of foundations
upto plinth in layers not exceeding 20 cms. in depth, compacting each deposited layer
by ramming after watering with lead upto 50 m. and lift upto 1.5 m. including cost of all
labour complete as per specifications. Specification. No. KBS 2.9
12 2.10
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining 522.69
Principal Quarters 113.92
Teaching Staff Quarters-1 328.29
Teaching Staff Quarters-2 350.20
Non-Teaching Staff Quarters 261.28
Total Quantity 1576.38 cum 1923 314 603822 1,576.38 314 494,983.15 1,576.38
KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of Design
mix M20 with OPC cement @ 320kgs, with 20mm and down size graded granite metal
coarse aggregates @0.69cum and fine aggregtes @ 0.460 cum, with super plasticisers
@ 3 liters confirming to IS 9103-1999 reafirmed-2008, machine mixed, concrete laid in
14 4.11 layers not exceeding 15 cms thick, vibrated for all works in foundation for footings,
pedastals, retaining walls, return walls, walls (any thickness) including attached
pilasters, columnspillars, posts, struts, buttresses, bed blocks, anchor blocks &
plinths etc., including cost of all materials, labour, HOM of machinery, curing,
complete but excluding cost of reinforcement as per specifications. Specification No.
KBS 4.1, 4.6
Academic Block 144.45
Dormitory Block-1 108.31
Dormitory Block-2 108.31
Kitchen & Dining 84.23
Principal Quarters 20.05
Teaching Staff Quarters-1 53.15
Teaching Staff Quarters-2 53.40
Non-Teaching Staff Quarters 48.89
Total Quantity 620.79 cum 799 7860 6280140 620.79 7860 4,879,436.21 620.79
Page 10
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
KSRB 4.2.4 : Providing and laying in position reinforced cement concrete of mix M10
with OPC cement @ 220kgs, with 20mm and down size graded granite metal coarse
aggregates @0.792cum and fine aggregtes @ 0.465cum, machine mixed, concrete laid
in layers not exceeding 15 cms thick, vibrated for all works in foundation plinth and
ground floor level for roof slabs, staircase, lintles, retaining walls, return walls, walls
15 4.13 ( any thickness ) including attached plasters, columns, piers, abutments, pillars, posts,
struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks,
plain window cills, fillets etc., including cost of all materials, labour, HOM of
machinery, curing, complete as per specifications. Specification No. KBS 4.1, 4.6
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining 16.57
Principal Quarters 5.36
Teaching Staff Quarters-1 11.91
Teaching Staff Quarters-2
Non-Teaching Staff Quarters
Total Quantity 33.84 cum 906 8348 7563288 33.84 8348 282,489.42 33.84
KSRB 4.2.10 : Providing and laying in position reinforced cement concrete of design
mix M20 with OPC cement @ 24kgs, with 12mm and down size graded granite metal
coarse aggregates @0.05175cum and fine aggregtes @ 0.0345cum, with superplastisiser
16 4.19 @0.225lts, machine mixed, well compacted for plain chajja of 7.5 cms. average
thickness, upto ground floor level, including cost of all materials, labour, HOM of
machinery, finishing, curing, complete but excluding cost of
reinforcement as per specifications. Specification No. KBS 4.1, 4.6
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining 24.02
Principal Quarters 6.48
Teaching Staff Quarters-1 12.24
Teaching Staff Quarters-2
Non-Teaching Staff Quarters
Total Quantity 42.74 Sqm 373 735 274155 42.74 735 31,416.84 42.74
KSRB 4-1.6 ; Providing and laying in position plain cement concrete of mix 1:2:4 with
cement @ 240kgs, with 20mm and down size graded granite metal coarse aggregates @
0.878 cum and fine aggregtes @ 0.53cum, machine mixed, concrete laid in layers not
exceeding 15 cms. thick, well compacted, in foundation, plinth and cills, ncluding cost
of all materials, labour, HOM of machinery, curing complete as per specifications.
18 4.6
Specification No. KBS 4.1, 4.2
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining 3.84
Principal Quarters 2.56
Teaching Staff Quarters-1 5.97
Teaching Staff Quarters-2 3.97
Non-Teaching Staff Quarters 2.39
Total Quantity 18.73 cum 219 6860 1502340 18.73 6860 128,483.46 18.73
Page 11
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc.,
and removal of form work for foundations, footings, bases of columns for mass
concrete including cost of all materials, labour complete as per specificaitons.
Specification No. KBS 4.6.2
19 4.28
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining 226.15
Principal Quarters 80.09
Teaching Staff Quarters-1 173.85
Teaching Staff Quarters-2 79.19
Non-Teaching Staff Quarters 64.01
Total Quantity 623.29 Sqm 2654 490 1300460 623.29 490 305,409.94 623.29
KSRB 4-6.6 : Providing and removing centering, shuttering, strutting, propping etc.,
and removal of form work for columns, pillars,post and struts, circular or curved in plan
including cost of all materials, labour complete as per specifications. Specification No.
KBS 4.6.2
22 4.33
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining 14.37
Principal Quarters 11.09
Teaching Staff Quarters-1
Teaching Staff Quarters-2
Non-Teaching Staff Quarters
Total Quantity 25.46 Sqm 71 931 66101 25.46 931 23,702.44 25.46
Page 12
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
KSRB 4-6.7 :Providing and removing centering, shuttering, strutting, propping etc., and
removal of form work for sides and soffits of beams, beam haunchings, cantilever
girders, bressumers and lintels not exceeding 1m in depth including cost of all
materials, labour complete as per specificaitons. Specification No. KBS 4.6.2
23 4.34
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining 49.90
Principal Quarters 22.38
Teaching Staff Quarters-1 42.74
Teaching Staff Quarters-2
Non-Teaching Staff Quarters
Total Quantity 115.02 Sqm 3351 314 1052214 115.02 314 36,117.03 115.02
KSRB 4-6.4 : Providing and removing centering, shuttering, strutting, propping etc.,
and removal of form work for vertical surface such as walls at any thickness, including
attached pilasters, buttresses, plinth cills and string courses cost of all materials, labour
complete as per specifications. Specification No. KBS 4.6.2
25 4.31
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining 324.98
Principal Quarters 73.95
Teaching Staff Quarters-1 175.05
Teaching Staff Quarters-2 157.51
Non-Teaching Staff Quarters 101.13
Total Quantity 832.62 Sqm 1829 392 716968 832.62 392 326,386.48 832.62
KSRB 4-6.10 :Providing and removing centering, shuttering, strutting, propping etc.,
for chajjas, corbels etc., including edges including cost of all materials, labour complete
as per specifications. Specification No. KBS 4.6.2
26 4.37
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining 25.94
Principal Quarters 8.68
Teaching Staff Quarters-1 13.68
Teaching Staff Quarters-2
Non-Teaching Staff Quarters
Total Quantity 48.30 Sqm 276 343 94668 48.30 343 16,568.27 48.30
Page 13
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including
straightening, cutting, bending, hooking, placing in position, lapping and / or welding
wherever required, tying with binding wire and anchoring to the adjoining members
wherever necessary complete as per design (laps, hooks and wastage shall not be
measured and paid) cost of materials, labour, HOM of machinery complete as per
specifications. Specification No. KBS 4.6.3 - TMT bars Fe 500
28 4.46.2
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining 83.08
Principal Quarters 24.09
Teaching Staff Quarters-1 59.17
Teaching Staff Quarters-2
Non-Teaching Staff Quarters
Total Quantity 166.34 Cum 1126 7365 8292990 166.34 7365 1,225,112.62 166.34
Providing RCC loft (atta) 7.5cms thick with cement concrete design mix M20 using
clean granite or trap jelly of 20mm and down size with necessary reinforcements at
20cms centre to centre as per design including form work, centring, curing, etc.,
60 4.54 complete (exclusive of cost of steel and fabrication charges).
Academic Block
Dormitory Block-1
Dormitory Block-2
Kitchen & Dining 21.76
Principal Quarters 2.28
Teaching Staff Quarters-1 7.48
Teaching Staff Quarters-2
Non-Teaching Staff Quarters
Total Quantity 31.51 Sqm 36 490 17640 31.51 490 15,440.88 31.51
59,156,425.00 19,884,593.65
Page 14
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
Page 15
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc.,
and removal of form work for foundations, footings, bases of columns for mass
concrete including cost of all materials, labour complete as per specificaitons.
7 4.28
Specification No. KBS 4.6.2
Sump Tank 72
Total Quantity 72 Sqm 175 25 4375.0 72.00 25 1800 72.00
Page 16
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
Providing & fixing 60mm x 60cm MS inspection door with necessary MS frame made
15 DR out of MS angle of 50mm x 50mm x 6mm & MS shutter of 3 mm thickness with hinges
on top & locking arrangements, painting, etc complete
Sump Tank 1
Total Quantity 1 No 2 1470 2940.0 1.00 1470 1470 1.00
890,974.50 378,919.58
Bore well 12
Total Quanttity 12 Mtr 12 343 4116.0 12.00 343 4116 12
Supplying and fixing L.T. cast Iron pot heads suitable for 1.1 KV class UG cable filled
with necessary bitumen/insulating compound complete with terminals, clamps, bolts,
nuts and washers etc. - 25Sqmm
5 7.13.3
Bore well 2
Total Quanttity 2 Each 2 392 784.0 2.00 392 784 2
Supplying tinned copper lugs and crimping and wiring to terminal point for wire of the
6 7.21.7 following sizes. - 25 sqmm Long Barrel
Bore well 16
Total Quanttity 16 Each 16 20 320.0 16.00 20 320 16
Page 17
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
Fixing a shunt capacitor of … KVAR capacity with necessary clamps, bolts, and nuts
on existing wooden or metal board including banking of more than one capacitor. - Up
to 5 KVAR
7 17.15.1
Bore well 4
Total Quanttity 4 Each 4 206 824.0 4.00 206 824 4
Supplying of 1.1 KV LT UG cable having aluminum conductor PVC insulated,
extruded inner sheathed, galvanized, steel strip (except 2CX10Sq.mm wire armoured)
8 7.4.5 confirming to IS-3975:1990 (No. of Strip indicated in GTP) & extruded PVC outer
sheathed armoured cable with specified IS-1554 Part-1:1988 & confirming to GTP of
GROUP-A. - 3.5 core 25 sqmm
Bore well 120
Total Quanttity 120 Mtr 120 167 20040.0 120.00 167 20040 120
Labour charges for laying of 1.1 KV class UG cable in existing trench GI pipe /
stoneware pipe / on wall / on pole as required.In existing trench/duct. - 25 sqmm to 75
9 7.8.A.2 sqmm
Page 18
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
Sinking of Borewell of 165mm dia clear using super fast hydraulic rig of capacity 250
PSIG & above 900 CMF & above in all strata including over burden upto 20 M. fixing
of casing pipes, collars and cap with necessary cutting, threading and welding including
14 9.1.5 transportation of rig and supporting vehicle, crew charges and cost of consumables etc.,
complete including yield testing at the final depth with a minimum working of
compressor for one hour (excluding cost of casing pipes, collars, cap etc.,) - 200.00 to
250.00 mtrs
Bore well 150
Total Quanttity 150 Rmtr 100 593 59300.0 100.00 593 59300 100
Sinking of Borewell of 165mm dia clear using super fast hydraulic rig of capacity 250
PSIG & above 900 CMF & above in all strata including over burden upto 20 M. fixing
of casing pipes, collars and cap with necessary cutting, threading and welding including
15 9.1.6 transportation of rig and supporting vehicle, crew charges and cost of consumables etc.,
complete including yield testing at the final depth with a minimum working of
compressor for one hour (excluding cost of casing pipes, collars, cap etc.,) - 250.00 to
300.00 mtrs
Bore well 150
Total Quanttity 150 Rmtr 100 593 59300.0 100.00 593 59300 100
Page 19
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
Sinking of Borewell of 165mm dia clear using super fast hydraulic rig of capacity 250
PSIG & above 900 CMF & above in all strata including over burden upto 20 M. fixing
of casing pipes, collars and cap with necessary cutting, threading and welding including
16 9.1.7 transportation of rig and supporting vehicle, crew charges and cost of consumables etc.,
complete including yield testing at the final depth with a minimum working of
compressor for one hour (excluding cost of casing pipes, collars, cap etc.,) - 300.00 to
350.00 mtrs
Bore well 150
Total Quanttity 150 Rmtr 100 613 61300.0 100.00 613 61300 100
Sinking of Borewell of 165mm dia clear using super fast hydraulic rig of capacity 250
PSIG & above 900 CMF & above in all strata including over burden upto 20 M. fixing
of casing pipes, collars and cap with necessary cutting, threading and welding including
17 9.1.8 transportation of rig and supporting vehicle, crew charges and cost of consumables etc.,
complete including yield testing at the final depth with a minimum working of
compressor for one hour (excluding cost of casing pipes, collars, cap etc.,) - Above
350.00 mtrs
Bore well
Total Quanttity Rmtr 100 652 65200.0 - 652 0 0
Geophysical Investigation of site for sinking Borewell for supplying drinking water to
the habitation either through the Hand Pump, MWS or P.W.S.S. by vertical electrical
sounding by adopting venner or Schlumberger's method, including reconnaissance
18 9.4 survey of geological formation, Geophysical investigation of existing Ground water in
the vicinity, its quality, quantity & acceptability of the users indicating the location of
site, recommended depth of casing pipe required to seal the top unconsolidated
formation incluing an extra depth of 1.0 metre in consolidated formation for proper
Bore well 3.00
Total Quanttity 3.00 Each 2 1862 3724.0 2.00 1862 3724 2
Replacement of pump parts - Non return valve (NRV) assembly complete with rubber
19 10.2.14 "O" ring
Page 20
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
Supply of ISI mark 175mm nominal bore,plain end steel casing pipe-grade of stell Fee
410 of wall thickness 5.4mm thick confirming to IS 4270:2001 and latest amendments
elictric risistance welded steel tube material by confirming to IS 1387/1993 and
24 53 manfuctured by basisc earth electric or basic oxygen process in random length of 5 to7
mts. both ends threaded confirming to IS 554/1985,one end fixed with socket
confirmung to IS 4270:2001 and the other end with screwed pipes. all pipes shall be
free from defects.The tube shall be resonably straight shoulde be ISI marking,weighing
Bore well 50.00
Total Quanttity 50.00 Rmtr 60 1380 82800.0 50.00 1380 69000 50
KSRB13-6.3-6 : Providing and fixing in position brass gate valve with C.I wheel of
approved quality ( screwed end ) 50mm nominal bore including cost of all materials,
labour and HOM of equipments with all leads complete as per specifications.
25 13.37 Specification No.KBS 13.2.6 / 13.3
1,301,850.00 1,033,670.00
Page 21
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
COMPOUND WALL
KSRB 2-2.2 : Earthwork excavation by manual means for foundation of buildings,
culverts, water supply and sanitary lines and electrical conduits etc, either in pits or in
trenches 1.5m and above in width, in hard soil not exceeding 1.5 m. in depth including
1 2.4 dressing the bottom and sides of pits and trenches, stacking the excavated soil clear
from edges of excavation with lead upto 50 m. including breaking of clods complete as
per specifications. No. KBS 2.1(a) / 2.3.5
Page 22
BOQ Item Executed As Per BOQ Previous Present Up to Date
Perticulars of Items Unit
Sl No code Qty Qty Rate Amount Qty Amount Qty Rate Amount Qty
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc.,
and removal of form work for foundations, footings, bases of columns for mass
concrete including cost of all materials, labour complete as per specificaitons.
7 4.28 Specification No. KBS 4.6.2
121.2
121.2 Sqm 326 274 89324.0 121.20 274 33208.8 121.20
KSRB 4-6.4 : Providing and removing centering, shuttering, strutting, propping etc.,
and removal of form work for vertical surface such as walls at any thickness, including
attached pilasters, buttresses, plinth cills and string courses cost of all materials, labour
8 4.31 complete as per specifications. Specification No. KBS 4.6.2
5,928,211.00 2,152,204.94
Page 23
Up to Date
Remarks
Amount
31,200.00 -
558,660.00 1,039.69
1,310,015.78 -
317,980.38 -
Page 24
Up to Date
Remarks
Amount
2,032,520.00 953.49
994,020.50 -
376,617.88 -
Page 25
Up to Date
Remarks
Amount
1,639,254.75 -
759,956.21 -
506,842.71 -
Page 26
Up to Date
Remarks
Amount
287,550.86 -
494,983.15 -
4,879,436.21 -
Page 27
Up to Date
Remarks
Amount
282,489.42 -
31,416.84 -
128,483.46 -
Page 28
Up to Date
Remarks
Amount
338,394.00 225.30
305,409.94 -
23,702.44 -
Page 29
Up to Date
Remarks
Amount
36,117.03 -
326,386.48 -
16,568.27 -
Page 30
Up to Date
Remarks
Amount
2,966,033.81 -
1,225,112.62 -
15,440.88 -
19,884,593.65
Page 31
Up to Date
Remarks
Amount
12,268.61 -
36,695.12 -
2,878.85 -
27,814.60 -
125,202.37 -
108,932.07 -
Page 32
Up to Date
Remarks
Amount
1,862.00 -
5,994.00 -
23,612.80 -
8,820.00 -
8,100.00 -
12,389.16 -
1,080.00 -
1,800.00 -
Page 33
Up to Date
Remarks
Amount
1,470.00 -
378,919.58
5,488.00 -
11,880.00 210.00
11,880.00 210.00
4,116.00 -
784.00 -
320.00 -
Page 34
Up to Date
Remarks
Amount
824.00 -
20,040.00 -
2,160.00 -
30,400.00 50.00
44,600.00 50.00
47,500.00 50.00
49,500.00 50.00
Page 35
Up to Date
Remarks
Amount
59,300.00 50.00
59,300.00 50.00
Page 36
Up to Date
Remarks
Amount
61,300.00 50.00
- -
3,724.00 1.00
2,744.00 -
43,175.00 -
116,965.00 -
187,500.00 163.00
128,000.00 -
Page 37
Up to Date
Remarks
Amount
69,000.00 -
4,508.00 -
10,290.00 44.00
236.00 2.00
1,372.00 -
1,884.00 -
27,440.00 -
27,440.00 -
1,033,670.00
Page 38
Up to Date
Remarks
Amount
127,542.56 -
146,928.57 -
655,575.90 -
33,965.08 -
436,201.37 -
100,384.63 -
Page 39
Up to Date
Remarks
Amount
33,208.80 -
94,839.26 -
127,354.29 -
396,204.48 -
2,152,204.94
Page 40
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Academic Block
Ground Floor RA BILL NO - 01
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRRB 200-1. Cutting of trees girth from 300mm to 600mm including cutting of trunks, branches and removal of
1 18.1 stumps stacking of serviceable materials earth filling in the depressions / pit, labour charges complete as per
specifications. MORTH specification clause 201/ Chapter 2
Page 41
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Earth work for lowering and levelling the ground other than foundation works by mechanical means upto 3.00
depth, including providing shoring strutting and brasing, removal of stumps and other deleterious matter, dressing of
3 2.24 sides and bottom, filling back the excavated earth to the extent required & utilising/transporting the remaining earth
upto
1.00 km lead. Including the cost of labour & HOM of machineries, as per drawing and technical specification.
Play Area 1 1.0 168.81 173.46 0.40 11712.71
Play Area 1 0.5 57.92 173.46 0.35 1758.19
Kitchen Garden 1 1.0 38.31 50.16 0.35 672.57
Kitchen Garden 1 0.5 66.18 38.16 0.35 441.95
Kitchen Garden 1 1 66.18 13.00 0.35 301.12
Total Qty 14886.54 Cum
KSRB 2-2.2 : Earthwork excavation by manual means for foundation of buildings, culverts, water supply and sanitary
lines and electrical conduits etc, either in pits or in trenches 1.5m and above in width, in hard soil not exceeding 1.5
4 2.4 m. in depth including dressing the bottom and sides of pits and trenches, stacking the excavated soil clear from
edges of excavation with lead upto 50 m. including breaking of clods complete as per specifications. No. KBS 2.1(a) /
2.3.5
Footing Earth work Excavation
Grid A9 (F4) 1 2.60 2.35 0.30 1.83
Grid A12(F4) 1 2.60 2.35 0.35 2.14
Grid B9 (F4) 1 2.60 2.35 0.30 1.83
Grid B12(F4) 1 2.60 2.35 0.40 2.44
Grid C4(F4) 1 2.60 2.35 0.35 2.14
Grid C7 (F4) 1 2.60 2.35 0.25 1.53
Grid C9 (F4) 1 2.60 2.35 0.25 1.53
Grid C12(F4) 1 2.60 2.35 0.35 2.14
Grid D4(F4) 1 2.60 2.35 0.40 2.44
Grid D7(F4) 1 2.60 2.35 0.25 1.53
Grid D9(F3) 1 2.80 2.50 0.30 2.10
Grid D12(F3) 1 2.80 2.50 0.30 2.10
Grid E10 (F8) 1 1.90 1.90 0.30 1.08
Page 42
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid E11 (F3) 1 2.60 2.35 0.35 2.14
Grid E13 (F3) 1 1.90 1.90 0.25 0.90
Grid F4 (F4) 1 2.80 2.50 0.40 2.80
Grid F7 (F4) 1 2.80 2.50 0.45 3.15
Grid G10 (F8) 1 1.90 1.90 0.35 1.26
Grid G11 (F4) 1 2.00 2.60 0.35 1.82
Grid G13 (F4) 1 2.60 2.35 0.35 2.14
Grid G'4 (CF2) 1 1.90 1.90 0.30 1.08
Grid G'7(F4) 1 2.60 2.35 0.30 1.83
Grid H'6 (F2) 1 2.60 2.35 0.25 1.53
Grid J10 (F3) 1 2.80 2.50 0.25 1.75
Grid J11 (F4) 1 2.60 2.35 0.20 1.22
Grid J13 (F4) 1 2.60 2.35 0.40 2.44
Grid K4 (CF1) 1 5.10 3.10 0.35 5.53
Grid K 6(F1) 1 2.55 2.75 0.40 2.80
Grid K10(F3) 1 2.80 2.50 0.30 2.10
Grid K11(F3) 1 3.05 2.75 0.25 2.10
Grid K13 (F3) 1 2.80 2.50 0.35 2.45
Grid L6 (F3) 1 2.80 2.50 0.35 2.45
Grid L8 (F1) 1 2.60 2.35 0.30 1.83
Grid L11 (F4) 1 2.60 2.35 0.35 2.14
Grid L12 (F4) 1 2.80 2.50 0.25 1.75
Grid L13(F2) 1 3.00 2.60 0.30 2.34
Grid L14(F8) 1 1.90 1.90 0.40 1.44
Grid L15(F8) 1 1.90 1.90 0.45 1.62
Grid M4 (CF1) 1 5.10 3.10 0.40 6.32
Grid M6 (F3) 1 2.80 2.50 0.35 2.45
Grid M8 (F1) 1 3.05 2.75 0.35 2.94
Grid M11 (F4) 1 2.60 2.35 0.30 1.83
Grid M12 (F4) 1 2.30 2.35 0.30 1.62
Page 43
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid M13 (F2) 1 3.00 2.60 0.35 2.73
Grid M14 (F8) 1 1.90 1.90 0.25 0.90
Grid M15 (F8) 1 1.90 1.90 0.30 1.08
Grid N 6(F4) 1 2.60 2.35 0.25 1.53
Grid N 7(F8) 1 1.90 1.90 0.35 1.26
Grid N10(F8) 1 1.90 1.90 0.30 1.08
Grid N 11(F3) 1 2.80 2.50 0.25 1.75
Grid N13(F3) 1 2.80 2.50 0.30 2.10
Grid Q10(F8) 1 4.60 2.60 0.40 4.78
Grid Q11(F4) 1 2.35 2.05 0.40 1.93
Grid Q13(F4) 1 2.80 2.50 0.35 2.45
Grid R4(CF2) 1 1.90 1.90 0.35 1.26
Grid R6(F6) 1 1.90 1.90 0.25 0.90
Grid R''7 (F3) 1 2.60 2.35 0.30 1.83
Grid S10(F8) 1 2.60 2.35 0.25 1.53
Grid S11(F4) 1 2.60 2.35 0.30 1.83
Grid S13(F4) 1 2.60 2.35 0.30 1.83
Grid T 4(F4) 1 2.60 2.35 0.35 2.14
Grid T 7(F4) 1 2.60 2.35 0.35 2.14
Grid U10(F8) 1 1.90 1.90 0.25 0.90
Grid U11(F3) 1 2.80 2.50 0.35 2.45
Grid U13(F3) 1 2.80 2.50 0.30 2.10
Grid V 4(F4) 1 2.60 2.35 0.30 1.83
Grid V 7 (F4) 1 2.80 2.50 0.30 2.10
Grid V 9 (F3) 1 2.80 2.50 0.30 2.10
Grid V12 (F3) 1 2.60 2.35 0.35 2.14
Grid W4(F4) 1 2.60 2.35 0.25 1.53
Grid W7 (F4) 1 2.60 2.35 0.30 1.83
Grid W9 (F4) 1 2.60 2.35 0.30 1.83
Grid W12 (F4) 1 2.60 2.35 0.25 1.53
Page 44
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid X8(F4) 1 2.60 2.35 0.30 1.83
Grid X12 (F4) 1 2.60 2.35 0.30 1.83
Grid Y 8(F4) 1 2.60 2.35 0.30 1.83
Grid Y12 (F4) 1 2.60 2.35 0.25 1.53
Total Qty 155.08 Cum
KSRB 2-2.4 : Excavation by manual means for foundation of buildings, water supply & sanitary lines and electrical
conduits etc., either in pits or in trenches 1.50m and above in width, in soft rock without blasting 1.50mtrs in depth
5 2.6 including stacking the excavated stuff clear from edges of excavation with lead upto 50mt including cost of
explosives,
labour, HOM of equipment complete as per specifications. specification. No. KBS 2.1C/2.9.4/2.18/2.19
Footing Earth work Excavation
Grid A9 (F4) 1 2.60 2.35 1.70 10.39
Grid A12(F4) 1 2.60 2.35 1.65 10.08
Grid B9 (F4) 1 2.60 2.35 1.70 10.39
Grid B12(F4) 1 2.60 2.35 1.60 9.78
Grid C4(F4) 1 2.60 2.35 1.65 10.08
Grid C7 (F4) 1 2.60 2.35 1.75 10.69
Grid C9 (F4) 1 2.60 2.35 1.65 10.08
Grid C12(F4) 1 2.60 2.35 1.60 9.78
Grid D4(F4) 1 2.60 2.35 1.55 9.47
Grid D7(F4) 1 2.60 2.35 1.50 9.17
Grid D9(F3) 1 2.80 2.50 1.50 10.50
Grid D12(F3) 1 2.80 2.50 1.50 10.50
Grid E10 (F8) 1 2.60 2.35 1.45 8.86
Grid E11 (F3) 1 2.60 2.35 1.55 9.47
Grid E13 (F3) 1 1.90 1.90 1.40 5.05
Grid F4 (F4) 1 2.80 2.50 1.35 9.45
Grid F7 (F4) 1 2.80 2.50 1.45 10.15
Grid G10 (F8) 1 4.60 2.60 1.45 17.34
Page 45
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid G11 (F4) 1 3.00 2.60 1.45 11.31
Grid G13 (F4) 1 2.60 2.35 1.50 9.17
Grid G'4 (CF2) 1 1.90 1.90 1.50 5.42
Grid G'7(F4) 1 2.60 2.35 1.65 10.08
Grid H'6 (F2) 1 2.60 2.35 1.65 10.08
Grid J10 (F3) 1 2.80 2.50 1.70 11.90
Grid J11 (F4) 1 2.60 2.35 1.50 9.17
Grid J13 (F4) 1 2.60 2.35 1.55 9.47
Grid K4 (CF1) 1 5.10 3.10 1.50 23.71
Grid K 6(F1) 1 2.55 2.75 1.60 11.22
Grid K10(F3) 1 2.80 2.50 1.65 11.55
Grid K11(F3) 1 3.05 2.75 1.55 13.00
Grid K13 (F3) 1 2.80 2.50 1.60 11.20
Grid L6 (F3) 1 2.80 2.50 1.55 10.85
Grid L8 (F1) 1 2.60 2.35 1.65 10.08
Grid L11 (F4) 1 2.60 2.35 1.60 9.78
Grid L12 (F4) 1 2.80 2.50 1.60 11.20
Grid L13(F2) 1 3.00 2.60 1.40 10.92
Grid L14(F8) 1 1.90 1.90 1.40 5.05
Grid L15(F8) 1 1.90 1.90 1.45 5.23
Grid M4 (CF1) 1 5.10 3.10 1.45 22.92
Grid M6 (F3) 1 2.80 2.50 1.50 10.50
Grid M8 (F1) 1 3.05 2.75 1.50 12.58
Grid M11 (F4) 1 2.60 2.35 1.45 8.86
Grid M12 (F4) 1 2.30 2.35 1.45 7.84
Grid M13 (F2) 1 3.00 2.60 1.55 12.09
Grid M14 (F8) 1 1.90 1.90 1.55 5.60
Grid M15 (F8) 1 1.90 1.90 1.45 5.23
Page 46
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid N 6(F4) 1 2.60 2.35 1.50 9.17
Grid N 7(F8) 1 1.90 1.90 1.55 5.60
Grid N10(F8) 1 1.90 1.90 1.50 5.42
Grid N 11(F3) 1 2.80 2.50 1.40 9.80
Grid N13(F3) 1 2.80 2.50 1.40 9.80
Grid Q10(F8) 1 4.60 2.60 1.45 17.34
Grid Q11(F4) 1 2.35 2.05 0.35 1.69
Grid Q13(F4) 1 2.80 2.50 1.65 11.55
Grid R4(CF2) 1 1.90 1.90 1.60 5.78
Grid R6(F6) 1 1.90 1.90 1.65 5.96
Grid R''7 (F3) 1 2.60 2.35 1.60 9.78
Grid S10(F8) 1 2.60 2.35 1.60 9.78
Grid S11(F4) 1 2.60 2.35 1.55 9.47
Grid S13(F4) 1 2.60 2.35 1.55 9.47
Grid T 4(F4) 1 2.60 2.35 1.65 10.08
Grid T 7(F4) 1 2.60 2.35 1.55 9.47
Grid U10(F8) 1 1.90 1.90 1.60 5.78
Grid U11(F3) 1 2.80 2.50 1.60 11.20
Grid U13(F3) 1 2.80 2.50 1.60 11.20
Grid V 4(F4) 1 2.60 2.35 1.65 10.08
Grid V 7 (F4) 1 2.80 2.50 1.75 12.25
Grid V 9 (F3) 1 2.80 2.50 1.70 11.90
Grid V12 (F3) 1 2.60 2.35 1.75 10.69
Grid W4(F4) 1 2.60 2.35 1.70 10.39
Grid W7 (F4) 1 2.60 2.35 1.70 10.39
Grid W9 (F4) 1 2.60 2.35 1.70 10.39
Grid W12 (F4) 1 2.60 2.35 1.70 10.39
Grid X8(F4) 1 2.60 2.35 1.70 10.39
Page 47
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid X12 (F4) 1 2.60 2.35 1.75 10.69
Grid Y 8(F4) 1 2.60 2.35 1.70 10.39
Grid Y12 (F4) 1 2.60 2.35 1.70 10.39
Total Qty 773.87 Cum
KSRB 2.2.6 : Excavation for foundation of buildings, water supply & sanitary lines & electrical conduits etc., either in
pits or in trenches 1.50m & above in width in hard rock by chiselling and / or wedging where blasting is prohibited,
6 2.8 not excluding 1.50m in depth including stacking the excavated stuff clear from edges of excavation with lead upto
50m
including cost of explosives, labour HOM of equipment complete as per specifications
Hard Rock
Stock Measurment
1 13.50 9.50 2.20 282.15
1 15.55 7.85 1.80 219.72
1 15.55 7.85 1.80 219.72
1 15.55 7.85 1.80 219.72
1 5.50 12.00 1.50 99.00
Total Qty 1,040.31 Cum
Deduction of Voids 35% 364.11
Total Qty 676.20 Cum
KSRB-3.2: Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating
continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of
the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top
7 3.2 surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits, with chloropyriphos
emulsifiable concentrates of 20% concentration, including cost of chemical, diluting in water to one percent
concentration, labour, HOM of equipments, complete as per specifications. (Plinth area of the building at ground floor
only shall be measured ) Specification No. KBS : 3.2.6 / 3.2.7
Anti-Termite Treatment
Page 48
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid C4W4-C9W9 1 40.12 8.69 348.64
Grid A9Y9-A12Y12 1 52.30 6.46 337.86
Grid E12U12-E13U13 1 29.38 3.00 88.14
Grid L13M13-L14M14 1 6.46 3.90 25.19
Grid G'3' R'3'-G'4R'4 1 20.00 2.40 48.00
Deductions 0.00
Left OTS -1 6.00 5.00 -30.00
Right OTS -1 9.46 6.00 -56.76
Court -2 2.00 3.00 -12.00
Court -2 2.00 4.77 -19.08
Total Qty 729.99 Sqm
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 with OPC cement @ 220kgs, with
40mm and down size graded granite metal coarse aggregates @0.892cum and fine aggregates @ 0.465cum machine
8 4.2 mixed, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation including
cost
of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2
Footing PCC
F1 3 2.65 2.35 0.10 1.87
F2 3 2.60 2.20 0.10 1.72
F3 14 2.40 2.10 0.10 7.06
F4 41 2.20 1.95 0.10 17.59
F6 1 1.95 1.65 0.10 0.32
F8 11 1.50 1.50 0.10 2.48
CF1 2 4.70 2.70 0.10 2.54
CF2 2 4.20 2.20 0.10 1.85
Total Qty 35.41 Cum
Page 49
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2.3 : Filling available excavated earth ( excluding rock ) in sides of foundations upto plinth in layers not
12 2.10 exceeding 20 cms. in depth, compacting each deposited layer by ramming after watering with lead upto 50 m. and
lift upto 1.5 m. including cost of all labour complete as per specifications. Specification. No. KBS 2.9
KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of Design mix M20 with OPC cement @
320kgs, with 20mm and down size graded granite metal coarse aggregates @0.69cum and fine aggregtes @ 0.460
cum, with super plasticisers @ 3 liters confirming to IS 9103-1999 reafirmed-2008, machine mixed, concrete laid in
14 4.11 layers not exceeding 15 cms thick, vibrated for all works in foundation for footings, pedastals, retaining walls, return
walls, walls (any thickness) including attached pilasters, columnspillars, posts, struts, buttresses, bed blocks, anchor
blocks & plinths etc., including cost of all materials, labour, HOM of machinery, curing, complete but
excluding cost of reinforcement as per specifications. Specification No. KBS 4.1, 4.6
Footing Concrete
F1 3 2.45 2.15 0.60 9.48
F2 3 2.40 2.00 0.55 7.92
F3 14 2.20 1.90 0.50 29.26
F4 41 2.00 1.75 0.45 64.58
F6 1 1.75 1.45 0.40 1.02
F8 11 1.30 1.30 0.30 5.58
CF1 2 4.50 2.50 0.65 14.63
CF2 2 4.00 2.00 0.75 12.00
Total Qty 144.45 Cum
Page 50
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
19 4.28 foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per
specificaitons. Specification No. KBS 4.6.2
Footing PCC Shuttering
F1 3 2 2.65 0.10 1.59
3 2 2.35 0.10 1.41
F2 3 2 2.60 0.10 1.56
3 2 2.20 0.10 1.32
F3 14 2 2.40 0.10 6.72
14 2 2.10 0.10 5.88
F4 41 2 2.20 0.10 18.04
41 2 1.95 0.10 15.99
F6 1 2 1.95 0.10 0.39
1 2 1.65 0.10 0.33
F8 11 2 1.50 0.10 3.30
11 2 1.50 0.10 3.30
CF1 2 2 4.70 0.10 1.88
2 2 2.70 0.10 1.08
CF2 2 2 4.20 0.10 1.68
2 2 2.20 0.10 0.88
Footing Concrete Shuttering
F1 3 2 2.45 0.60 8.82
3 2 2.15 0.60 7.74
F2 3 2 2.40 0.55 7.92
3 2 2.00 0.55 6.60
F3 14 2 2.20 0.50 30.80
14 2 1.90 0.50 26.60
F4 41 2 2.00 0.45 73.80
41 2 1.75 0.45 64.58
Page 51
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
F6 1 2 1.75 0.40 1.40
1 2 1.45 0.40 1.16
F8 11 2 1.30 0.30 8.58
11 2 1.30 0.30 8.58
CF1 2 2 4.50 0.65 11.70
2 2 2.50 0.65 6.50
CF2 2 2 4.00 0.75 12.00
2 2 2.00 0.75 6.00
Total Qty 348.12 Sqm
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking,
placing in position, lapping and / or welding wherever required, tying with binding wire and anchoring to the adjoining
28 4.46.2
members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost
of materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3 - TMT bars Fe 500
Footing Steel 9.80
Total Qty 9.80 Tonne
Page 52
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Academic Block GF Steel
Ground Floor Steel Fabrication RA BILL NO - 01
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Acadamic Block
Footing Mats Steel
F1 - - - - - -
A-Bars 12 19 1 3 2.95 - - 168.15 - - -
B-Bars 12 20 1 3 2.65 - - 159.00 - - -
F2 - - - - - -
A-Bars 12 17 1 3 2.85 - - 145.35 - - -
B-Bars 12 21 1 3 2.45 - - 154.35 - - -
F3 - - - - - -
A-Bars 10 20 1 14 2.6 - 728.00 - - - -
B-Bars 10 23 1 14 2.3 - 740.60 - - - -
F4 - - - - - -
A-Bars 10 15 1 41 2.35 - 1,445.25 - - - -
B-Bars 10 17 1 41 2.1 - 1,463.70 - - - -
F6 - - - - - -
A-Bars 10 13 1 1 2.05 - 26.65 - - - -
B-Bars 10 15 1 1 1.75 - 26.25 - - - -
F8 - - - - - -
A-Bars 10 10 1 11 1.5 - 165.00 - - - -
B-Bars 10 10 1 11 1.5 - 165.00 - - - -
CF1 - - - - - -
A-Bars 12 21 2 2 5.05 - - 424.20 - - -
B-Bars 12 37 2 2 3.05 - - 451.40 - - -
CF2 - - - - - -
A-Bars 12 17 2 2 4.65 - - 316.20 - - -
B-Bars 12 33 2 2 2.65 - - 349.80 - - -
Column Steel Upto Plinth Top - - - - - - GL
Page 53
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid A9-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid A12-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid B9-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid B12-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid C4-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid C7-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid C9-C4 - - - - - - ###
Main Bars-1 16 4 1 1 2.65 - - - 10.60 - -
Main Bars-2 12 4 1 1 2.65 - - 10.60 - - -
Rectangle Stirrups 8 14 1 1 1.19 16.66 - - - - -
Dimond Stirrups 8 14 1 1 0.95 13.30 - - - - -
Grid C12-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid D4-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Page 54
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid D7-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid D9-C2 - - - - - - ###
Main Bars-1 20 4 1 1 2.65 - - - - 10.60 -
Main Bars-2 16 4 1 1 2.65 - - - 10.60 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid D12-C2 - - - - - - ###
Main Bars-1 20 4 1 1 2.65 - - - - 10.60 -
Main Bars-2 16 4 1 1 2.65 - - - 10.60 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid E10-C8 - - - - - - ###
Main Bars 12 8 1 1 2.65 - - 21.20 - - -
Rectangle Stirrups 8 14 1 1 0.75 10.50 - - - - -
Dimond Stirrups 8 14 1 1 0.58 8.12 - - - - -
Grid E11-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid E13-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid F4-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid F7-C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid G10-C8 - - - - - - ###
Page 55
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Main Bars 12 8 1 1 2.65 - - 21.20 - - -
Rectangle Stirrups 8 14 1 1 0.75 10.50 - - - - -
Dimond Stirrups 8 14 1 1 0.58 8.12 - - - - -
Grid G11-C3 - - - - - - ###
Main Bars 16 8 1 1 2.75 - - - 22.00 - -
Rectangle Stirrups 8 13 1 1 1.19 15.47 - - - - -
Dimond Stirrups 8 13 1 1 0.95 12.35 - - - - -
Grid G13-C3 - - - - - - ###
Main Bars 16 8 1 1 2.85 - - - 22.80 - -
Rectangle Stirrups 8 13 1 1 1.19 15.47 - - - - -
Dimond Stirrups 8 13 1 1 0.95 12.35 - - - - -
Grid G'4 -C3 - - - - - - ###
Main Bars 16 8 1 1 2.65 - - - 21.20 - -
Rectangle Stirrups 8 12 1 1 1.19 14.28 - - - - -
Dimond Stirrups 8 12 1 1 0.95 11.40 - - - - -
Grid G'7-C2 - - - - - - ###
Main Bars-1 20 4 1 1 2.75 - - - - 11.00 -
Main Bars-2 16 4 1 1 2.75 - - - 11.00 - -
Rectangle Stirrups 8 13 1 1 1.19 15.47 - - - - -
Dimond Stirrups 8 13 1 1 0.95 12.35 - - - - -
Grid H'4 -C6 - - - - - - ###
Main Bars 16 8 1 1 2.8 - - - 22.40 - -
Rectangle Stirrups 8 13 1 1 1.05 13.65 - - - - -
Dimond Stirrups 8 13 1 1 0.82 10.66 - - - - -
Grid H'6 -C1 - - - - - - ###
Main Bars 20 8 1 1 2.8 - - - - 22.40 -
Rectangle Stirrups 8 13 1 1 1.19 15.47 - - - - -
Dimond Stirrups 8 13 1 1 0.95 12.35 - - - - -
Grid J10- C2 - - - - - - ###
Main Bars-1 20 4 1 1 2.95 - - - - 11.80 -
Main Bars-2 16 4 1 1 2.95 - - - 11.80 - -
Rectangle Stirrups 8 14 1 1 1.19 16.66 - - - - -
Dimond Stirrups 8 14 1 1 0.95 13.30 - - - - -
Grid J11-C3 - - - - - - ###
Main Bars 16 8 1 1 2.95 - - - 23.60 - -
Rectangle Stirrups 8 14 1 1 1.19 16.66 - - - - -
Page 56
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dimond Stirrups 8 14 1 1 0.95 13.30 - - - - -
Grid J13-C3 - - - - - - ###
Main Bars 16 8 1 1 3.05 - - - 24.40 - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid K4-C1A - - - - - - ###
Main Bars 25 8 1 1 2.75 - - - - - 22.00
Rectangle Stirrups 8 13 1 1 1.19 15.47 - - - - -
Dimond Stirrups 8 13 1 1 0.95 12.35 - - - - -
Grid K6-C1A - - - - - - ###
Main Bars 25 8 1 1 2.8 - - - - - 22.40
Rectangle Stirrups 8 13 1 1 1.19 15.47 - - - - -
Dimond Stirrups 8 13 1 1 0.95 12.35 - - - - -
Grid K10-C2 - - - - - - ###
Main Bars-1 20 4 1 1 2.85 - - - - 11.40 -
Main Bars-2 16 4 1 1 2.85 - - - 11.40 - -
Rectangle Stirrups 8 13 1 1 1.19 15.47 - - - - -
Dimond Stirrups 8 13 1 1 0.95 12.35 - - - - -
Grid K11-C3 - - - - - - ###
Main Bars 16 8 1 1 2.95 - - - 23.60 - -
Rectangle Stirrups 8 14 1 1 1.19 16.66 - - - - -
Dimond Stirrups 8 14 1 1 0.95 13.30 - - - - -
Grid K13-C2 - - - - - - ###
Main Bars-1 20 4 1 1 3.15 - - - - 12.60 -
Main Bars-2 16 4 1 1 3.15 - - - 12.60 - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid L4-C1 - - - - - - ###
Main Bars 20 8 1 1 3.2 - - - - 25.60 -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid L6-C1 - - - - - - ###
Main Bars 20 8 1 1 2.85 - - - - 22.80 -
Rectangle Stirrups 8 13 1 1 1.19 15.47 - - - - -
Dimond Stirrups 8 13 1 1 0.95 12.35 - - - - -
Grid L8-C1 - - - - - - ###
Page 57
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Main Bars 20 8 1 1 2.95 - - - - 23.60 -
Rectangle Stirrups 8 14 1 1 1.19 16.66 - - - - -
Dimond Stirrups 8 14 1 1 0.95 13.30 - - - - -
Grid L11-C3 - - - - - - ###
Main Bars 16 8 1 1 3.05 - - - 24.40 - -
Rectangle Stirrups 8 14 1 1 1.19 16.66 - - - - -
Dimond Stirrups 8 14 1 1 0.95 13.30 - - - - -
Grid L12-C1 - - - - - - ###
Main Bars 20 8 1 1 3.15 - - - - 25.20 -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid L13-C2 - - - - - - ###
Main Bars-1 20 4 1 1 3.22 - - - - 12.88 -
Main Bars-2 16 4 1 1 3.22 - - - 12.88 - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid L14-C7 - - - - - - ###
Main Bars 20 8 1 1 3.22 - - - - 25.76 -
Circular Stirrups 8 17 1 1 1.31 22.27 - - - - -
Grid L15-C7 - - - - - - ###
Main Bars 20 8 1 1 3.22 - - - - 25.76 -
Circular Stirrups 8 17 1 1 1.31 22.27 - - - - -
Grid M4-C1 - - - - - - ###
Main Bars 20 8 1 1 3.2 - - - - 25.60 -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid M6-C1 - - - - - - ###
Main Bars 20 8 1 1 3.25 - - - - 26.00 -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid M8-C1 - - - - - - ###
Main Bars 20 8 1 1 3.35 - - - - 26.80 -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid M11-C3 - - - - - - ###
Main Bars 16 8 1 1 3.4 - - - 27.20 - -
Page 58
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid M12-C1 - - - - - - ###
Main Bars 20 8 1 1 3.45 - - - - 27.60 -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid M13-C2 - - - - - - ###
Main Bars-1 20 4 1 1 3.55 - - - - 14.20 -
Main Bars-2 16 4 1 1 - - - - - -
Rectangle Stirrups 8 17 1 1 1.19 20.23 - - - - -
Dimond Stirrups 8 17 1 1 0.95 16.15 - - - - -
Grid M14-C7 - - - - - - ###
Main Bars 20 8 1 1 3.55 - - - - 28.40 -
Circular Stirrups 8 19 1 1 1.31 24.89 - - - - -
Grid M15-C7 - - - - - - ###
Main Bars 20 8 1 1 3.55 - - - - 28.40 -
Circular Stirrups 8 19 1 1 1.31 24.89 - - - - -
Grid N 4-C1A - - - - - - ###
Main Bars 25 8 1 1 3.45 - - - - - 27.60
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid N6-C3 - - - - - - ###
Main Bars 16 8 1 1 3.35 - - - 26.80 - -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid N 7-C8 - - - - - - ###
Main Bars 12 8 1 1 3.4 - - 27.20 - - -
Rectangle Stirrups 8 18 1 1 0.75 13.50 - - - - -
Dimond Stirrups 8 18 1 1 0.58 10.44 - - - - -
Grid N10-C8 - - - - - - ###
Main Bars 12 8 1 1 3.45 - - 27.60 - - -
Rectangle Stirrups 8 19 1 1 0.75 14.25 - - - - -
Dimond Stirrups 8 19 1 1 0.58 11.02 - - - - -
Grid N 11-C3 - - - - - - ###
Main Bars 16 8 1 1 3.5 - - - 28.00 - -
Rectangle Stirrups 8 17 1 1 1.19 20.23 - - - - -
Page 59
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dimond Stirrups 8 17 1 1 0.95 16.15 - - - - -
Grid N13-C2 - - - - - - ###
Main Bars-1 20 4 1 1 3.65 - - - - 14.60 -
Main Bars-2 16 4 1 1 3.65 - - - 14.60 - -
Rectangle Stirrups 8 17 1 1 1.19 20.23 - - - - -
Dimond Stirrups 8 17 1 1 0.95 16.15 - - - - -
Grid Q10-C8 - - - - - - ###
Main Bars 12 8 1 1 3.65 - - 29.20 - - -
Rectangle Stirrups 8 20 1 1 0.75 15.00 - - - - -
Dimond Stirrups 8 20 1 1 0.58 11.60 - - - - -
Grid Q11-C3 - - - - - - ###
Main Bars 16 8 1 1 3.7 - - - 29.60 - -
Rectangle Stirrups 8 18 1 1 1.19 21.42 - - - - -
Dimond Stirrups 8 18 1 1 0.95 17.10 - - - - -
Grid Q13-C3 - - - - - - ###
Main Bars 16 8 1 1 3.85 - - - 30.80 - -
Rectangle Stirrups 8 18 1 1 1.19 21.42 - - - - -
Dimond Stirrups 8 18 1 1 0.95 17.10 - - - - -
Grid R4-C5 - - - - - - ###
Main Bars 12 8 1 1 3.45 - - 27.60 - - -
Rectangle Stirrups 8 16 1 1 1.05 16.80 - - - - -
Dimond Stirrups 8 16 1 1 0.82 13.12 - - - - -
Grid R6-C5 - - - - - - ###
Main Bars 12 8 1 1 3.55 - - 28.40 - - -
Rectangle Stirrups 8 17 1 1 1.05 17.85 - - - - -
Dimond Stirrups 8 17 1 1 0.82 13.94 - - - - -
Grid R''4-C2 - - - - - - ###
Main Bars-1 20 4 1 1 3.75 - - - - 15.00 -
Main Bars-2 16 4 1 1 3.75 - - - 15.00 - -
Rectangle Stirrups 8 18 1 1 1.19 21.42 - - - - -
Dimond Stirrups 8 18 1 1 0.95 17.10 - - - - -
Grid R''7-C2 - - - - - - ###
Main Bars-1 20 4 1 1 4.05 - - - - 16.20 -
Main Bars-2 16 4 1 1 4.05 - - - 16.20 - -
Rectangle Stirrups 8 19 1 1 1.19 22.61 - - - - -
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
Page 60
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid S10-C8 - - - - - - ###
Main Bars 12 8 1 1 3.85 - - 30.80 - - -
Rectangle Stirrups 8 21 1 1 0.75 15.75 - - - - -
Dimond Stirrups 8 21 1 1 0.58 12.18 - - - - -
Grid S11-C3 - - - - - - ###
Main Bars 16 8 1 1 3.85 - - - 30.80 - -
Rectangle Stirrups 8 18 1 1 1.19 21.42 - - - - -
Dimond Stirrups 8 18 1 1 0.95 17.10 - - - - -
Grid S13-C3 - - - - - - ###
Main Bars 16 8 1 1 3.9 - - - 31.20 - -
Rectangle Stirrups 8 19 1 1 1.19 22.61 - - - - -
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
Grid T 4-C3 - - - - - - ###
Main Bars 16 8 1 1 4.1 - - - 32.80 - -
Rectangle Stirrups 8 20 1 1 1.19 23.80 - - - - -
Dimond Stirrups 8 20 1 1 0.95 19.00 - - - - -
Grid T 7-C3 - - - - - - ###
Main Bars 16 8 1 1 4.1 - - - 32.80 - -
Rectangle Stirrups 8 20 1 1 1.19 23.80 - - - - -
Dimond Stirrups 8 20 1 1 0.95 19.00 - - - - -
Grid U10-C8 - - - - - - ###
Main Bars 12 8 1 1 3.9 - - 31.20 - - -
Rectangle Stirrups 8 21 1 1 0.75 15.75 - - - - -
Dimond Stirrups 8 21 1 1 0.58 12.18 - - - - -
Grid U11-C3 - - - - - - ###
Main Bars 16 8 1 1 3.95 - - - 31.60 - -
Rectangle Stirrups 8 19 1 1 1.19 22.61 - - - - -
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
Grid U13-C3 - - - - - - ###
Main Bars 16 8 1 1 3.95 - - - 31.60 - -
Rectangle Stirrups 8 19 1 1 1.19 22.61 - - - - -
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
Grid V 4-C3 - - - - - - ###
Main Bars 16 8 1 1 4.15 - - - 33.20 - -
Rectangle Stirrups 8 20 1 1 1.19 23.80 - - - - -
Dimond Stirrups 8 20 1 1 0.95 19.00 - - - - -
Page 61
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid V 7-C3 - - - - - - ###
Main Bars 16 8 1 1 4.55 - - - 36.40 - -
Rectangle Stirrups 8 22 1 1 1.19 26.18 - - - - -
Dimond Stirrups 8 22 1 1 0.95 20.90 - - - - -
Grid V 9-C2 - - - - - - ###
Main Bars-1 20 4 1 1 4.65 - - - - 18.60 -
Main Bars-2 16 4 1 1 4.65 - - - 18.60 - -
Rectangle Stirrups 8 22 1 1 1.19 26.18 - - - - -
Dimond Stirrups 8 22 1 1 0.95 20.90 - - - - -
Grid V12-C2 - - - - - - ###
Main Bars-1 20 4 1 1 4.95 - - - - 19.80 -
Main Bars-2 16 4 1 1 4.95 - - - 19.80 - -
Rectangle Stirrups 8 24 1 1 1.19 28.56 - - - - -
Dimond Stirrups 8 24 1 1 0.95 22.80 - - - - -
Grid W4-C3 - - - - - - ###
Main Bars 16 8 1 1 4.3 - - - 34.40 - -
Rectangle Stirrups 8 21 1 1 1.19 24.99 - - - - -
Dimond Stirrups 8 21 1 1 0.95 19.95 - - - - -
Grid W7 -C3 - - - - - - ###
Main Bars 16 8 1 1 4.65 - - - 37.20 - -
Rectangle Stirrups 8 22 1 1 1.19 26.18 - - - - -
Dimond Stirrups 8 22 1 1 0.95 20.90 - - - - -
Grid W9 -C4 - - - - - - ###
Main Bars-1 16 4 1 1 4.75 - - - 19.00 - -
Main Bars-2 12 4 1 1 4.75 - - 19.00 - - -
Rectangle Stirrups 8 26 1 1 1.19 30.94 - - - - -
Dimond Stirrups 8 26 1 1 0.95 24.70 - - - - -
Grid W12-C3 - - - - - - ###
Main Bars 16 8 1 1 5.05 - - - 40.40 - -
Rectangle Stirrups 8 24 1 1 1.19 28.56 - - - - -
Dimond Stirrups 8 24 1 1 0.95 22.80 - - - - -
Grid X8-C3 - - - - - - ###
Main Bars 16 8 1 1 4.75 - - - 38.00 - -
Rectangle Stirrups 8 23 1 1 1.19 27.37 - - - - -
Dimond Stirrups 8 23 1 1 0.95 21.85 - - - - -
Grid X12 -C3 - - - - - - ###
Page 62
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Main Bars 16 8 1 1 5.15 - - - 41.20 - -
Rectangle Stirrups 8 25 1 1 1.19 29.75 - - - - -
Dimond Stirrups 8 25 1 1 0.95 23.75 - - - - -
Grid Y 8-C3 - - - - - - ###
Main Bars 16 8 1 1 4.85 - - - 38.80 - -
Rectangle Stirrups 8 23 1 1 1.19 27.37 - - - - -
Dimond Stirrups 8 23 1 1 0.95 21.85 - - - - -
Grid Y12-C3 - - - - - - ###
Main Bars 16 8 1 1 5.25 - - - 42.00 - -
Rectangle Stirrups 8 25 1 1 1.19 29.75 - - - - -
Dimond Stirrups 8 25 1 1 0.95 23.75 - - - - -
Total Length In mts 2,662.59 4,760.45 2,442.45 1,329.48 513.20 72.00
Unit Wt/mt 0.395 0.617 0.888 1.580 2.46 3.858
Total Reinforcement Qty 1,051.72 2,937.20 2,168.90 2,100.58 1,262.47 277.78 9,798.64 Kgs
Total Weight Say MT 9.80 MT
Page 63
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Haveri Tq,
:- Haveri District.
:- Boys Dormitory Block
Ground Floor RA BILL NO - 01
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2-2.2 : Earthwork excavation by manual means for foundation of buildings, culverts, water supply and sanitary
lines and electrical conduits etc, either in pits or in trenches 1.5m and above in width, in hard soil not exceeding 1.5
4 2.4
m. in depth including dressing the bottom and sides of pits and trenches, stacking the excavated soil clear from edges
of excavation with lead upto 50 m. including breaking of clods complete as per specifications. No. KBS 2.1(a) / 2.3.5
Page 64
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid C9-F1 1 3.00 2.70 0.30 2.43
Grid C11-F3 1 2.70 2.40 0.35 2.27
Grid C12-F3 1 2.70 2.40 0.38 2.46
Grid C14-F1 1 3.00 2.70 0.30 2.43
Grid C17-F3 1 2.70 2.40 0.35 2.27
Grid C20-F4 1 2.60 2.30 0.35 2.09
Grid C21-F6 1 2.40 2.20 0.30 1.58
Grid D2-F4 1 2.60 2.30 0.30 1.79
Grid D7-F7 1 2.00 1.80 0.35 1.26
Grid D10-F7 1 2.00 1.80 0.30 1.08
Grid D11-F7 1 2.00 1.80 0.35 1.26
Grid D12-F7 1 2.00 1.80 0.35 1.26
Grid D13-F7 1 2.00 1.80 0.35 1.26
Grid D15-F7 1 2.00 1.80 0.35 1.26
Grid D20-F4 1 2.60 2.30 0.38 2.27
Grid E1-F6 1 2.20 2.00 0.35 1.54
Grid E2-F5 1 2.40 2.20 0.35 1.85
Grid E4-F5 1 2.40 2.20 0.35 1.85
Grid E7 -F2 1 2.80 2.60 0.30 2.18
Grid E10- F7 1 2.00 1.80 0.30 1.08
Grid E11-F7 1 2.00 1.80 0.35 1.26
Grid E12-F7 1 2.00 1.80 0.38 1.37
Grid E13-F7 1 2.00 1.80 0.30 1.08
Grid E15-F2 1 2.80 2.60 0.35 2.55
Grid E18-F5 1 2.40 2.20 0.35 1.85
Grid E20-F5 1 2.40 2.20 0.38 2.01
Grid E21-F6 1 2.20 2.00 0.35 1.54
B/W E&F 10 F7 1 2.00 1.80 0.35 1.26
Page 65
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
B/W E&F 13 F7 1 2.00 1.80 0.35 1.26
Grid F1-F6 1 2.20 2.00 0.30 1.32
Grid F2-F5 1 2.40 2.20 0.30 1.58
Grid F4-F4 1 2.60 2.30 0.35 2.09
Grid F7-F3 1 2.70 2.40 0.38 2.46
Grid F9-F7 1 2.00 1.80 0.30 1.08
Grid F11-F7 1 2.00 1.80 0.35 1.26
Grid F12-F7 1 2.00 1.80 0.35 1.26
Grid F13-F7 1 2.00 1.80 0.38 1.37
Grid F15-F3 1 2.70 2.40 0.35 2.27
Grid F18-F4 1 2.60 2.30 0.35 2.09
Grid F20-F5 1 2.40 2.20 0.35 1.85
Grid F21-F6 1 2.20 2.00 0.30 1.32
Grid G3-F6 1 2.20 2.00 0.30 1.32
Grid G6-F4 1 2.60 2.30 0.35 2.09
Grid G10-F4 1 2.60 2.30 0.38 2.27
Grid G11-F4 1 2.60 2.30 0.30 1.79
Grid G12-F4 1 2.60 2.30 0.35 2.09
Grid G13-F4 1 2.60 2.30 0.35 2.09
Grid G16-F4 1 2.60 2.30 0.38 2.27
Grid G19-F6 1 2.20 2.00 0.35 1.54
Grid H3-F6 1 2.20 2.00 0.35 1.54
Grid H6-F4 1 2.60 2.30 0.35 2.09
Grid H10-F4 1 2.60 2.30 0.30 1.79
Grid H11-F3 1 2.70 2.40 0.30 1.94
Grid H12-F2 1 2.80 2.60 0.35 2.55
Grid H13-F3 1 2.70 2.40 0.38 2.46
Grid H16-F3 1 2.70 2.40 0.30 1.94
Page 66
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid H19-F6 1 2.20 2.00 0.35 1.54
Grid I8- F4 1 2.60 2.30 0.35 2.09
Grid I11-F3 1 2.70 2.40 0.38 2.46
Grid I12-F2 1 2.80 2.60 0.35 2.55
Grid I14 -F1 1 3.00 2.70 0.35 2.84
Grid J10-F7 1 2.00 1.80 0.35 1.26
Grid j13- F7 1 2.00 1.80 0.30 1.08
Grid K6-F7 1 2.00 1.80 0.30 1.08
Grid K10- F3 1 2.70 2.40 0.35 2.27
Grid K13-F3 1 2.70 2.40 0.38 2.46
Grid K16 -F7 1 2.00 1.80 0.30 1.08
Grid L 10-F6 1 2.20 2.00 0.35 1.54
Grid L 13- F6 1 2.20 2.00 0.35 1.54
Total Qty 152.36 Cum
KSRB 2-2.4 : Excavation by manual means for foundation of buildings, water supply & sanitary lines and electrical
conduits etc., either in pits or in trenches 1.50m and above in width, in soft rock without blasting 1.50mtrs in depth
5 2.6 including stacking the excavated stuff clear from edges of excavation with lead upto 50mt including cost of
explosives,
labour, HOM of equipment complete as per specifications. specification. No. KBS 2.1C/2.9.4/2.18/2.19
Footing Earth work Excavation
Grid A1-F5 1 2.40 2.20 1.15 6.07 ###
Grid A2-F5 1 2.40 2.20 1.15 6.07 ###
Grid A5-F3 1 2.70 2.40 1.12 7.26 ###
Grid A9-F3 1 2.70 2.40 1.20 7.78 ###
Grid A11-F4 1 2.60 2.30 1.15 6.88 ###
Grid A12-F4 1 2.60 2.30 1.15 6.88 ###
Grid A14-F3 1 2.70 2.40 1.12 7.26 ###
Grid A17-F3 1 2.70 2.40 1.15 7.45 ###
Grid A20-F5 1 2.40 2.20 1.20 6.34 ###
Page 67
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A21-F5 1 2.40 2.20 1.20 6.34 ###
Grid B2-F5 1 2.40 2.20 1.15 6.07 ###
Grid B20-F5 1 2.40 2.20 1.15 6.07 ###
Grid C1-F6 1 2.20 2.00 1.45 6.38 ###
Grid C2-F4 1 2.60 2.30 1.50 8.97 ###
Grid C5-F3 1 2.70 2.40 1.50 9.72 ###
Grid C9-F1 1 3.00 2.70 1.50 12.15 ###
Grid C11-F3 1 2.70 2.40 1.45 9.40 ###
Grid C12-F3 1 2.70 2.40 1.42 9.20 ###
Grid C14-F1 1 3.00 2.70 1.50 12.15 ###
Grid C17-F3 1 2.70 2.40 1.45 9.40 ###
Grid C20-F4 1 2.60 2.30 1.45 8.67 ###
Grid C21-F6 1 2.40 2.20 1.50 7.92 ###
Grid D2-F4 1 2.60 2.30 1.50 8.97 ###
Grid D7-F7 1 2.00 1.80 1.45 5.22 ###
Grid D10-F7 1 2.00 1.80 1.50 5.40 ###
Grid D11-F7 1 2.00 1.80 1.45 5.22 ###
Grid D12-F7 1 2.00 1.80 1.45 5.22 ###
Grid D13-F7 1 2.00 1.80 1.45 5.22 ###
Grid D15-F7 1 2.00 1.80 1.45 5.22 ###
Grid D20-F4 1 2.60 2.30 1.42 8.49 ###
Grid E1-F6 1 2.20 2.00 1.45 6.38 ###
Grid E2-F5 1 2.40 2.20 1.15 6.07 ###
Grid E4-F5 1 2.40 2.20 1.15 6.07 ###
Grid E7 -F2 1 2.80 2.60 1.20 8.74 ###
Grid E10- F7 1 2.00 1.80 1.20 4.32 ###
Grid E11-F7 1 2.00 1.80 1.15 4.14 ###
Grid E12-F7 1 2.00 1.80 1.12 4.03 ###
Page 68
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid E13-F7 1 2.00 1.80 1.20 4.32 ###
Grid E15-F2 1 2.80 2.60 1.15 8.37 ###
Grid E18-F5 1 2.40 2.20 1.15 6.07 ###
Grid E20-F5 1 2.40 2.20 1.42 7.50 ###
Grid E21-F6 1 2.20 2.00 1.45 6.38 ###
B/W E&F 10 F7 1 2.00 1.80 1.45 5.22 ###
B/W E&F 13 F7 1 2.00 1.80 1.45 5.22 ###
Grid F1-F6 1 2.20 2.00 1.50 6.60 ###
Grid F2-F5 1 2.40 2.20 1.50 7.92 ###
Grid F4-F4 1 2.60 2.30 1.45 8.67 ###
Grid F7-F3 1 2.70 2.40 1.42 9.20 ###
Grid F9-F7 1 2.00 1.80 1.50 5.40 ###
Grid F11-F7 1 2.00 1.80 1.45 5.22 ###
Grid F12-F7 1 2.00 1.80 1.45 5.22 ###
Grid F13-F7 1 2.00 1.80 1.42 5.11 ###
Grid F15-F3 1 2.70 2.40 1.45 9.40 ###
Grid F18-F4 1 2.60 2.30 1.45 8.67 ###
Grid F20-F5 1 2.40 2.20 1.45 7.66 ###
Grid F21-F6 1 2.20 2.00 1.50 6.60 ###
Grid G3-F6 1 2.20 2.00 1.50 6.60 ###
Grid G6-F4 1 2.60 2.30 1.15 6.88 ###
Grid G10-F4 1 2.60 2.30 1.12 6.70 ###
Grid G11-F4 1 2.60 2.30 1.20 7.18 ###
Grid G12-F4 1 2.60 2.30 1.15 6.88 ###
Grid G13-F4 1 2.60 2.30 1.15 6.88 ###
Grid G16-F4 1 2.60 2.30 1.12 6.70 ###
Grid G19-F6 1 2.20 2.00 1.15 5.06 ###
Grid H3-F6 1 2.20 2.00 1.15 5.06 ###
Page 69
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid H6-F4 1 2.60 2.30 1.15 6.88 ###
Grid H10-F4 1 2.60 2.30 1.50 8.97 ###
Grid H11-F3 1 2.70 2.40 1.50 9.72 ###
Grid H12-F2 1 2.80 2.60 1.45 10.56 ###
Grid H13-F3 1 2.70 2.40 1.42 9.20 ###
Grid H16-F3 1 2.70 2.40 1.50 9.72 ###
Grid H19-F6 1 2.20 2.00 1.45 6.38 ###
Grid I8- F4 1 2.60 2.30 1.45 8.67 ###
Grid I11-F3 1 2.70 2.40 1.42 9.20 ###
Grid I12-F2 1 2.80 2.60 1.45 10.56 ###
Grid I14 -F1 1 3.00 2.70 1.45 11.75 ###
Grid J10-F7 1 2.00 1.80 1.45 5.22 ###
Grid j13- F7 1 2.00 1.80 1.50 5.40 ###
Grid K6-F7 1 2.00 1.80 1.50 5.40 ###
Grid K10- F3 1 2.70 2.40 1.45 9.40 ###
Grid K13-F3 1 2.70 2.40 1.42 9.20 ###
Grid K16 -F7 1 2.00 1.80 1.50 5.40 ###
Grid L 10-F6 1 2.20 2.00 1.45 6.38 ###
Grid L 13- F6 1 2.20 2.00 1.45 6.38 ###
Total Qty 604.17 Cum
KSRB-3.2: Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating
continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of
the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top
7 3.2 surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits, with chloropyriphos
emulsifiable concentrates of 20% concentration, including cost of chemical, diluting in water to one percent
concentration, labour, HOM of equipments, complete as per specifications. (Plinth area of the building at ground floor
only shall be measured ) Specification No. KBS : 3.2.6 / 3.2.7
Anti-Termite Treatment
Page 70
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A1A21-F1F21 1 32.38 14.35 464.65
Grid F3F19-G3G19 1 20.92 8.46 176.98
Grid H8H15-i8i15 1 11.39 3.00 34.17
Grid i8i14-J8J14 1 10.92 4.46 48.70
Grid K10'K12'-L10'L12' 1 7.13 6.75 48.13
Deductions
OTS Centre -1 9.00 6.00 -54.00
Garden Near CDA -1 6.00 1.50 -9.00
Garden B/W Dormitory -2 3.00 2.00 -12.00
Garden Near Staircase -1 3.60 3.00 -10.80
Total Qty 686.84 Sqm
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 with OPC cement @ 220kgs, with
40mm and down size graded granite metal coarse aggregates @0.892cum and fine aggregates @ 0.465cum machine
8 4.2 mixed, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation including
cost
of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2
Footing PCC
F1 3 2.60 2.30 0.10 1.79
F2 4 2.40 2.20 0.10 2.11
F3 16 2.30 2.00 0.10 7.36
F4 17 2.20 1.90 0.10 7.11
F5 12 2.00 1.80 0.10 4.32
F6 12 1.80 1.60 0.10 3.46
F7 20 1.60 1.40 0.10 4.48
Total Qty 30.63 Cum
Page 71
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of Design mix M20 with OPC cement @
320kgs, with 20mm and down size graded granite metal coarse aggregates @0.69cum and fine aggregtes @ 0.460
cum, with super plasticisers @ 3 liters confirming to IS 9103-1999 reafirmed-2008, machine mixed, concrete laid in
14 4.11 layers not exceeding 15 cms thick, vibrated for all works in foundation for footings, pedastals, retaining walls, return
walls, walls (any thickness) including attached pilasters, columnspillars, posts, struts, buttresses, bed blocks, anchor
blocks & plinths etc., including cost of all materials, labour, HOM of machinery, curing, complete but
excluding cost of reinforcement as per specifications. Specification No. KBS 4.1, 4.6
Footing Concrete
F1 3 2.40 2.10 0.60 9.07
F2 4 2.20 2.00 0.55 9.68
F3 16 2.10 1.80 0.50 30.24
F4 17 2.00 1.70 0.45 26.01
F5 12 1.80 1.60 0.40 13.82
F6 12 1.60 1.40 0.35 9.41
F7 20 1.40 1.20 0.30 10.08
Total Qty 108.31 Cum
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
19 4.28 foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per
specificaitons. Specification No. KBS 4.6.2
Page 72
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
17 2 1.90 0.10 6.46
F5 12 2 2.00 0.10 4.80
12 2 1.80 0.10 4.32
F6 12 2 1.80 0.10 4.32
12 2 1.60 0.10 3.84
F7 20 2 1.60 0.10 6.40
20 2 1.40 0.10 5.60
Shutter For Footing Concrete
F1 3 2 2.40 0.60 8.64
3 2 2.10 0.60 7.56
F2 4 2 2.20 0.55 9.68
4 2 2.00 0.55 8.80
F3 16 2 2.10 0.50 33.60
16 2 1.80 0.50 28.80
F4 17 2 2.00 0.45 30.60
17 2 1.70 0.45 26.01
F5 12 2 1.80 0.40 17.28
12 2 1.60 0.40 15.36
F6 12 2 1.60 0.35 13.44
12 2 1.40 0.35 11.76
F7 20 2 1.40 0.30 16.80
20 2 1.20 0.30 14.40
Total Qty 306.33 Sqm
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking,
placing in position, lapping and / or welding wherever required, tying with binding wire and anchoring to the adjoining
28 4.46.2
members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost
of materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3 - TMT bars Fe 500
Footing Steel 3.25
Page 73
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Total Qty 3.25 Tonne
Page 74
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Haveri Tq,
:- Haveri District.
:- Boys Dormitory Block
Ground Floor Steel Fabrication RA BILL NO - 01
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dormitory
Footing Mat Steel
Footings-F1 - - - - - -
A-Bars 12 18 1 3 2.90 - - 156.60 - - -
B-Bars 12 21 1 3 2.60 - - 163.80 - - -
Footings-F2 - - - - - -
A-Bars 12 17 1 4 2.65 - - 180.20 - - -
B-Bars 12 19 1 4 2.65 - - 201.40 - - -
Footings-F3 - - - - - -
A-Bars 10 19 1 16 2.50 - 760.00 - - - -
B-Bars 10 22 1 16 2.20 - 774.40 - - - -
Footings-F4 - - - - - -
A-Bars 10 18 1 15 2.35 - 634.50 - - - -
B-Bars 10 22 1 15 2.05 - 676.50 - - - -
Footings-F5 - - - - - -
A-Bars 10 14 1 8 2.10 - 235.20 - - - -
B-Bars 10 16 1 8 1.90 - 243.20 - - - -
Footings-F6 - - - - - -
A-Bars 10 11 1 12 1.85 - 244.20 - - - -
B-Bars 10 14 1 12 1.65 - 277.20 - - - -
Footings-F7 - - - - - -
A-Bars 10 9 1 14 1.60 - 201.60 - - - -
B-Bars 10 11 1 14 1.40 - 215.60 - - - -
Total Length In mts - 4,262.40 702.00 - - -
Page 75
Unit Wt/mt 0.395 0.617 0.888 1.580 2.460 3.858
Total Reinforcement Qty - 2,629.90 623.38 - - - 3,253.28 Kg's
Total Weight Say MT 3.25 MT
Page 76
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Haveri Tq,
:- Haveri District.
:- Girls Dormitory Block
Ground Floor RA BILL NO - 01
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2-2.2 : Earthwork excavation by manual means for foundation of buildings, culverts, water supply and sanitary
lines and electrical conduits etc, either in pits or in trenches 1.5m and above in width, in hard soil not exceeding 1.5
4 2.4 m. in depth including dressing the bottom and sides of pits and trenches, stacking the excavated soil clear from
edges of excavation with lead upto 50 m. including breaking of clods complete as per specifications. No. KBS
2.1(a) / 2.3.5
Footing Earth work Excavation
Grid A1-F5 1 2.40 2.20 0.30 1.58
Grid A2-F5 1 2.40 2.20 0.35 1.85
Grid A5-F3 1 2.70 2.40 0.38 2.46
Grid A9-F3 1 2.70 2.40 0.25 1.62
Grid A11-F4 1 2.60 2.30 0.30 1.79
Grid A12-F4 1 2.60 2.30 0.30 1.79
Grid A14-F3 1 2.70 2.40 0.35 2.27
Grid A17-F3 1 2.70 2.40 0.35 2.27
Grid A20-F5 1 2.40 2.20 0.30 1.58
Grid A21-F5 1 2.40 2.20 0.25 1.32
Grid B2-F5 1 2.40 2.20 0.30 1.58
Grid B20-F5 1 2.40 2.20 0.35 1.85
Grid C1-F6 1 2.20 2.00 0.35 1.54
Grid C2-F4 1 2.60 2.30 0.30 1.79
Grid C5-F3 1 2.70 2.40 0.35 2.27
Grid C9-F1 1 3.00 2.70 0.30 2.43
Grid C11-F3 1 2.70 2.40 0.35 2.27
Page 77
Grid C12-F3 1 2.70 2.40 0.35 2.27
Grid C14-F1 1 3.00 2.70 0.30 2.43
Grid C17-F3 1 2.70 2.40 0.35 2.27
Grid C20-F4 1 2.60 2.30 0.35 2.09
Grid C21-F6 1 2.40 2.20 0.30 1.58
Grid D2-F4 1 2.60 2.30 0.30 1.79
Grid D7-F7 1 2.00 1.80 0.35 1.26
Grid D10-F7 1 2.00 1.80 0.30 1.08
Grid D11-F7 1 2.00 1.80 0.35 1.26
Grid D12-F7 1 2.00 1.80 0.30 1.08
Grid D13-F7 1 2.00 1.80 0.35 1.26
Grid D15-F7 1 2.00 1.80 0.35 1.26
Grid D20-F4 1 2.60 2.30 0.25 1.50
Grid E1-F6 1 2.20 2.00 0.30 1.32
Grid E2-F5 1 2.40 2.20 0.30 1.58
Grid E4-F5 1 2.40 2.20 0.30 1.58
Grid E7 -F2 1 2.80 2.60 0.35 2.55
Grid E10- F7 1 2.00 1.80 0.25 0.90
Grid E11-F7 1 2.00 1.80 0.30 1.08
Grid E12-F7 1 2.00 1.80 0.35 1.26
Grid E13-F7 1 2.00 1.80 0.25 0.90
Grid E15-F2 1 2.80 2.60 0.30 2.18
Grid E18-F5 1 2.40 2.20 0.35 1.85
Grid E20-F5 1 2.40 2.20 0.38 2.01
Grid E21-F6 1 2.20 2.00 0.35 1.54
B/W E&F 10 F7 1 2.00 1.80 0.30 1.08
B/W E&F 13 F7 1 2.00 1.80 0.35 1.26
Grid F1-F6 1 2.20 2.00 0.30 1.32
Grid F2-F5 1 2.40 2.20 0.30 1.58
Grid F4-F4 1 2.60 2.30 0.35 2.09
Grid F7-F3 1 2.70 2.40 0.38 2.46
Grid F9-F7 1 2.00 1.80 0.30 1.08
Page 78
Grid F11-F7 1 2.00 1.80 0.35 1.26
Grid F12-F7 1 2.00 1.80 0.35 1.26
Grid F13-F7 1 2.00 1.80 0.38 1.37
Grid F15-F3 1 2.70 2.40 0.35 2.27
Grid F18-F4 1 2.60 2.30 0.35 2.09
Grid F20-F5 1 2.40 2.20 0.35 1.85
Grid F21-F6 1 2.20 2.00 0.30 1.32
Grid G3-F6 1 2.20 2.00 0.30 1.32
Grid G6-F4 1 2.60 2.30 0.35 2.09
Grid G10-F4 1 2.60 2.30 0.38 2.27
Grid G11-F4 1 2.60 2.30 0.30 1.79
Grid G12-F4 1 2.60 2.30 0.35 2.09
Grid G13-F4 1 2.60 2.30 0.30 1.79
Grid G16-F4 1 2.60 2.30 0.38 2.27
Grid G19-F6 1 2.20 2.00 0.35 1.54
Grid H3-F6 1 2.20 2.00 0.35 1.54
Grid H6-F4 1 2.60 2.30 0.35 2.09
Grid H10-F4 1 2.60 2.30 0.30 1.79
Grid H11-F3 1 2.70 2.40 0.30 1.94
Grid H12-F2 1 2.80 2.60 0.30 2.18
Grid H13-F3 1 2.70 2.40 0.38 2.46
Grid H16-F3 1 2.70 2.40 0.30 1.94
Grid H19-F6 1 2.20 2.00 0.35 1.54
Grid I8- F4 1 2.60 2.30 0.35 2.09
Grid I11-F3 1 2.70 2.40 0.38 2.46
Grid I12-F2 1 2.80 2.60 0.35 2.55
Grid I14 -F1 1 3.00 2.70 0.35 2.84
Grid J10-F7 1 2.00 1.80 0.35 1.26
Grid j13- F7 1 2.00 1.80 0.25 0.90
Grid K6-F7 1 2.00 1.80 0.25 0.90
Grid K10- F3 1 2.70 2.40 0.30 1.94
Grid K13-F3 1 2.70 2.40 0.35 2.27
Page 79
Grid K16 -F7 1 2.00 1.80 0.30 1.08
Grid L 10-F6 1 2.20 2.00 0.35 1.54
Grid L 13- F6 1 2.20 2.00 0.35 1.54
Total Qty 146.51 Cum
KSRB 2-2.4 : Excavation by manual means for foundation of buildings, water supply & sanitary lines and electrical
conduits etc., either in pits or in trenches 1.50m and above in width, in soft rock without blasting 1.50mtrs in depth
5 2.6 including stacking the excavated stuff clear from edges of excavation with lead upto 50mt including cost of
explosives,
labour, HOM of equipment complete as per specifications. specification. No. KBS 2.1C/2.9.4/2.18/2.19
Footing Earth work Excavation
Grid A1-F5 1 2.60 2.20 1.20 6.86 ###
Grid A2-F5 1 2.60 2.20 1.15 6.58 ###
Grid A5-F3 1 2.70 2.40 1.12 7.26 ###
Grid A9-F3 1 2.70 2.40 1.25 8.10 ###
Grid A11-F4 1 2.60 2.30 1.20 7.18 ###
Grid A12-F4 1 2.60 2.30 1.20 7.18 ###
Grid A14-F3 1 2.70 2.40 1.15 7.45 ###
Grid A17-F3 1 2.70 2.40 1.15 7.45 ###
Grid A20-F5 1 2.60 2.20 1.20 6.86 ###
Grid A21-F5 1 2.60 2.20 1.25 7.15 ###
Grid B2-F5 1 2.40 2.20 1.20 6.34 ###
Grid B20-F5 1 2.40 2.20 1.15 6.07 ###
Grid C1-F6 1 2.20 2.00 1.45 6.38 ###
Grid C2-F4 1 2.60 2.30 1.50 8.97 ###
Grid C5-F3 1 2.70 2.40 1.45 9.40 ###
Grid C9-F1 1 3.00 2.70 1.50 12.15 ###
Grid C11-F3 1 2.70 2.40 1.45 9.40 ###
Grid C12-F3 1 2.70 2.40 1.45 9.40 ###
Grid C14-F1 1 3.00 2.70 1.50 12.15 ###
Grid C17-F3 1 2.70 2.40 1.45 9.40 ###
Grid C20-F4 1 2.60 2.30 1.45 8.67 ###
Grid C21-F6 1 2.40 2.20 1.50 7.92 ###
Page 80
Grid D2-F4 1 2.60 2.30 1.50 8.97 ###
Grid D7-F7 1 2.00 1.80 1.45 5.22 ###
Grid D10-F7 1 2.00 1.80 1.50 5.40 ###
Grid D11-F7 1 2.00 1.80 1.45 5.22 ###
Grid D12-F7 1 2.00 1.80 1.50 5.40 ###
Grid D13-F7 1 2.00 1.80 1.45 5.22 ###
Grid D15-F7 1 2.00 1.80 1.45 5.22 ###
Grid D20-F4 1 2.60 2.30 1.55 9.27 ###
Grid E1-F6 1 2.20 2.00 1.50 6.60 ###
Grid E2-F5 1 2.40 2.20 1.20 6.34 ###
Grid E4-F5 1 2.40 2.20 1.20 6.34 ###
Grid E7 -F2 1 2.80 2.60 1.15 8.37 ###
Grid E10- F7 1 2.00 1.80 1.25 4.50 ###
Grid E11-F7 1 2.00 1.80 1.20 4.32 ###
Grid E12-F7 1 2.00 1.80 1.15 4.14 ###
Grid E13-F7 1 2.00 1.80 1.25 4.50 ###
Grid E15-F2 1 2.80 2.60 1.20 8.74 ###
Grid E18-F5 1 2.40 2.20 1.15 6.07 ###
Grid E20-F5 1 2.40 2.20 1.42 7.50 ###
Grid E21-F6 1 2.20 2.00 1.45 6.38 ###
B/W E&F 10 F7 1 2.00 1.80 1.50 5.40 ###
B/W E&F 13 F7 1 2.00 1.80 1.45 5.22 ###
Grid F1-F6 1 2.20 2.00 1.50 6.60 ###
Grid F2-F5 1 2.40 2.20 1.50 7.92 ###
Grid F4-F4 1 2.60 2.30 1.45 8.67 ###
Grid F7-F3 1 2.70 2.40 1.42 9.20 ###
Grid F9-F7 1 2.00 1.80 1.50 5.40 ###
Grid F11-F7 1 2.00 1.80 1.45 5.22 ###
Grid F12-F7 1 2.00 1.80 1.45 5.22 ###
Grid F13-F7 1 2.00 1.80 1.42 5.11 ###
Grid F15-F3 1 2.70 2.40 1.45 9.40 ###
Grid F18-F4 1 2.60 2.30 1.45 8.67 ###
Page 81
Grid F20-F5 1 2.40 2.20 1.45 7.66 ###
Grid F21-F6 1 2.20 2.00 1.50 6.60 ###
Grid G3-F6 1 2.20 2.00 1.50 6.60 ###
Grid G6-F4 1 2.60 2.30 1.15 6.88 ###
Grid G10-F4 1 2.60 2.30 1.12 6.70 ###
Grid G11-F4 1 2.60 2.30 1.20 7.18 ###
Grid G12-F4 1 2.60 2.30 1.15 6.88 ###
Grid G13-F4 1 2.60 2.30 1.20 7.18 ###
Grid G16-F4 1 2.60 2.30 1.12 6.70 ###
Grid G19-F6 1 2.20 2.00 1.15 5.06 ###
Grid H3-F6 1 2.20 2.00 1.15 5.06 ###
Grid H6-F4 1 2.60 2.30 1.15 6.88 ###
Grid H10-F4 1 2.60 2.30 1.50 8.97 ###
Grid H11-F3 1 2.70 2.40 1.50 9.72 ###
Grid H12-F2 1 2.80 2.60 1.50 10.92 ###
Grid H13-F3 1 2.70 2.40 1.42 9.20 ###
Grid H16-F3 1 2.70 2.40 1.50 9.72 ###
Grid H19-F6 1 2.20 2.00 1.45 6.38 ###
Grid I8- F4 1 2.60 2.30 1.45 8.67 ###
Grid I11-F3 1 2.70 2.40 1.42 9.20 ###
Grid I12-F2 1 2.80 2.60 1.45 10.56 ###
Grid I14 -F1 1 3.00 2.70 1.45 11.75 ###
Grid J10-F7 1 2.00 1.80 1.45 5.22 ###
Grid j13- F7 1 2.00 1.80 1.55 5.58 ###
Grid K6-F7 1 2.00 1.80 1.55 5.58 ###
Grid K10- F3 1 2.70 2.40 1.50 9.72 ###
Grid K13-F3 1 2.70 2.40 1.45 9.40 ###
Grid K16 -F7 1 2.00 1.80 1.50 5.40 ###
Grid L 10-F6 1 2.20 2.00 1.45 6.38 ###
Grid L 13- F6 1 2.20 2.00 1.45 6.38 ###
Total Qty 612.14 Cum
Page 82
KSRB-3.2: Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating
continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of
the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top
7 3.2 surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits, with chloropyriphos
emulsifiable concentrates of 20% concentration, including cost of chemical, diluting in water to one percent
concentration, labour, HOM of equipments, complete as per specifications. (Plinth area of the building at ground
floor only shall be measured ) Specification No. KBS : 3.2.6 / 3.2.7
Anti-Termite Treatment
Grid A1A21-F1F21 1 32.38 14.35 464.65
Grid F3F19-G3G19 1 20.92 8.46 176.98
Grid H8H15-i8i15 1 11.39 3.00 34.17
Grid i8i14-J8J14 1 10.92 4.46 48.70
Grid K10'K12'-L10'L12' 1 7.13 6.75 48.13
Deductions
OTS Centre -1 9.00 6.00 -54.00
Garden Near CDA -1 6.00 1.50 -9.00
Garden B/W Dormitory -2 3.00 2.00 -12.00
Garden Near Staircase -1 3.60 3.00 -10.80
Total Qty 686.84 Sqm
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 with OPC cement @ 220kgs, with
40mm and down size graded granite metal coarse aggregates @0.892cum and fine aggregates @ 0.465cum
8 4.2 machine mixed, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation
including cost
of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2
Footing PCC
F1 3 2.60 2.30 0.10 1.79
F2 4 2.40 2.20 0.10 2.11
F3 16 2.30 2.00 0.10 7.36
F4 17 2.20 1.90 0.10 7.11
F5 12 2.00 1.80 0.10 4.32
F6 12 1.80 1.60 0.10 3.46
F7 20 1.60 1.40 0.10 4.48
Page 83
Total Qty 30.63 Cum
KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of Design mix M20 with OPC cement @
320kgs, with 20mm and down size graded granite metal coarse aggregates @0.69cum and fine aggregtes @ 0.460
cum, with super plasticisers @ 3 liters confirming to IS 9103-1999 reafirmed-2008, machine mixed, concrete laid in
14 4.11 layers not exceeding 15 cms thick, vibrated for all works in foundation for footings, pedastals, retaining walls, return
walls, walls (any thickness) including attached pilasters, columnspillars, posts, struts, buttresses, bed blocks, anchor
blocks & plinths etc., including cost of all materials, labour, HOM of machinery, curing, complete but
excluding cost of reinforcement as per specifications. Specification No. KBS 4.1, 4.6
Footing Concrete
F1 3 2.40 2.10 0.60 9.07
F2 4 2.20 2.00 0.55 9.68
F3 16 2.10 1.80 0.50 30.24
F4 17 2.00 1.70 0.45 26.01
F5 12 1.80 1.60 0.40 13.82
F6 12 1.60 1.40 0.35 9.41
F7 20 1.40 1.20 0.30 10.08
Total Qty 108.31 Cum
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
19 4.28 foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per
specificaitons. Specification No. KBS 4.6.2
Page 84
8 2 1.80 0.10 2.88
F6 12 2 1.80 0.10 4.32
12 2 1.60 0.10 3.84
F7 14 2 1.60 0.10 4.48
14 2 1.40 0.10 3.92
Shutter For Footing Concrete
F1 3 2 2.40 0.60 8.64
3 2 2.10 0.60 7.56
F2 4 2 2.20 0.55 9.68
4 2 2.00 0.55 8.80
F3 16 2 2.10 0.50 33.60
16 2 1.80 0.50 28.80
F4 15 2 2.00 0.45 27.00
15 2 1.70 0.45 22.95
F5 8 2 1.80 0.40 11.52
8 2 1.60 0.40 10.24
F6 12 2 1.60 0.35 13.44
12 2 1.40 0.35 11.76
F7 14 2 1.40 0.30 11.76
14 2 1.20 0.30 10.08
Total Qty 271.15 Sqm
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking,
placing in position, lapping and / or welding wherever required, tying with binding wire and anchoring to the
28 4.46.2 adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured
and paid) cost of materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3 -
TMT bars Fe 500
Page 85
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Haveri Tq,
:- Haveri District.
:- Girls Dormitory Block
Ground Floor Steel Fabrication RA BILL NO - 01
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dormitory
Footing Mat Steel
Footings-F1 - - - - - -
A-Bars 12 18 1 3 2.90 - - 156.60 - - -
B-Bars 12 21 1 3 2.60 - - 163.80 - - -
Footings-F2 - - - - - -
A-Bars 12 17 1 4 2.65 - - 180.20 - - -
B-Bars 12 19 1 4 2.65 - - 201.40 - - -
Footings-F3 - - - - - -
A-Bars 10 19 1 16 2.50 - 760.00 - - - -
B-Bars 10 22 1 16 2.20 - 774.40 - - - -
Footings-F4 - - - - - -
A-Bars 10 18 1 15 2.35 - 634.50 - - - -
B-Bars 10 22 1 15 2.05 - 676.50 - - - -
Footings-F5 - - - - - -
A-Bars 10 14 1 8 2.10 - 235.20 - - - -
B-Bars 10 16 1 8 1.90 - 243.20 - - - -
Footings-F6 - - - - - -
A-Bars 10 11 1 12 1.85 - 244.20 - - - -
B-Bars 10 14 1 12 1.65 - 277.20 - - - -
Footings-F7 - - - - - -
A-Bars 10 9 1 14 1.60 - 201.60 - - - -
B-Bars 10 11 1 14 1.40 - 215.60 - - - -
Total Length In mts - 4,262.40 702.00 - - -
Page 86
Unit Wt/mt 0.395 0.617 0.888 1.580 2.460 3.858
Total Reinforcement Qty - 2,629.90 623.38 - - - 3,253.28 Kg's
Total Weight Say MT 3.25 MT
Page 87
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Kitchen & Dining Block
Ground Floor RA BILL NO - 01
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2-2.2 : Earthwork excavation by manual means for foundation of buildings, culverts, water supply and sanitary
lines and electrical conduits etc, either in pits or in trenches 1.5m and above in width, in hard soil not exceeding 1.5 m.
4 2.4
in depth including dressing the bottom and sides of pits and trenches, stacking the excavated soil clear from edges of
excavation with lead upto 50 m. including breaking of clods complete as per specifications. No. KBS 2.1(a) / 2.3.5
Page 88
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid G4 -F1 1 3.20 3.00 0.30 2.88
Grid G5 -F3 1 2.85 2.40 0.30 2.05
Grid G6-F6 1 1.60 1.60 0.35 0.90
Grid G'1 -F4 1 2.70 2.35 0.35 2.22
Grid G'2- F2 1 3.00 2.85 0.35 2.99
Grid H1 -F5 1 2.10 1.90 0.30 1.20
Grid H2 -F3 1 2.85 2.40 0.30 2.05
Grid H4 -F1 1 3.20 3.00 0.25 2.40
Grid H5 -F3 1 2.85 2.40 0.25 1.71
Grid J4 -F3 1 2.85 2.40 0.30 2.05
Grid J5 -F4 1 2.70 2.35 0.35 2.22
Grid K3 -F5 1 2.10 1.90 0.35 1.40
Earth Work For Grade Beam
Grid C1-H1 1 13.92 0.45 0.45 2.82
Grid H1-H3 1 7.86 0.45 0.45 1.59
Grid H3-K3 1 3.77 0.45 0.45 0.76
Grid K3-K4 1 2.73 0.45 0.45 0.55
Grid J4-J5 1 9.23 0.45 0.45 1.87
Grid B5-J5 1 22.38 0.45 0.45 4.53
Grid B4-B5 1 9.23 0.45 0.45 1.87
Grid A3-A4 1 2.73 0.45 0.45 0.55
Grid A3-C3 1 3.77 0.45 0.45 0.76
Grid C1-C3 1 7.86 0.45 0.45 1.59
Deductions
Grid C1-H1 -1 9.35 0.45 0.45 -1.89
Grid H1-H3 -1 3.95 0.45 0.45 -0.80
Grid H3-K3 -1 1.10 0.45 0.45 -0.22
Grid K3-K4 -1 2.40 0.45 0.45 -0.49
Page 89
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid J4-J5 -1 2.78 0.45 0.45 -0.56
Grid B5-J5 -1 11.95 0.45 0.45 -2.42
Grid B4-B5 -1 2.78 0.45 0.45 -0.56
Grid A3-A4 -1 2.40 0.45 0.45 -0.49
Grid A3-C3 -1 1.10 0.45 0.45 -0.22
Grid C1-C3 -1 3.95 0.45 0.45 -0.80
Total Qty 67.08 Cum
KSRB 2-2.4 : Excavation by manual means for foundation of buildings, water supply & sanitary lines and electrical
conduits etc., either in pits or in trenches 1.50m and above in width, in soft rock without blasting 1.50mtrs in depth
5 2.6
including stacking the excavated stuff clear from edges of excavation with lead upto 50mt including cost of explosives,
labour, HOM of equipment complete as per specifications. specification. No. KBS 2.1C/2.9.4/2.18/2.19
Earth Work For Footing
Grid A2- F6 1 1.60 1.60 1.50 3.84
Grid A3 -F5 1 2.10 1.90 1.45 5.79
Grid B4 -F3 1 2.85 2.40 1.40 9.58
Grid B5 -F4 1 2.70 2.35 1.50 9.52
Grid C1- F5 1 2.10 1.90 1.55 6.18
Grid C2- F4 1 2.70 2.35 1.45 9.20
Grid C4 -F1 1 3.20 3.00 1.40 13.44
Grid C5 -F3 1 2.85 2.40 1.40 9.58
Grid D1 -F4 1 2.70 2.35 1.45 9.20
Grid D2 -F2 1 3.00 2.85 1.45 12.40
Grid E4 -F1 1 3.20 3.00 1.50 14.40
Grid E5-F3 1 2.85 2.40 1.50 10.26
Grid E6-F6 1 1.60 1.60 1.45 3.71
Grid F1 -F4 1 2.70 2.35 1.35 8.57
Grid F2 -F2 1 3.00 2.85 1.35 11.54
Grid G4 -F1 1 3.20 3.00 1.50 14.40
Page 90
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid G5 -F3 1 2.85 2.40 1.50 10.26
Grid G6-F6 1 1.60 1.60 1.45 3.71
Grid G'1 -F4 1 2.70 2.35 1.45 9.20
Grid G'2- F2 1 3.00 2.85 1.45 12.40
Grid H1 -F5 1 2.10 1.90 1.50 5.98
Grid H2 -F3 1 2.85 2.40 1.50 10.26
Grid H4 -F1 1 3.20 3.00 1.55 14.88
Grid H5 -F3 1 2.85 2.40 1.55 10.60
Grid J4 -F3 1 2.85 2.40 1.50 10.26
Grid J5 -F4 1 2.70 2.35 1.45 9.20
Grid K3 -F5 1 2.10 1.90 1.45 5.79
Total Qty 254.14 Cum
KSRB-3.2: Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating
continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of
the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top
7 3.2 surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits, with chloropyriphos
emulsifiable concentrates of 20% concentration, including cost of chemical, diluting in water to one percent
concentration, labour, HOM of equipments, complete as per specifications. (Plinth area of the building at ground floor
only shall be measured ) Specification No. KBS : 3.2.6 / 3.2.7
Anti-Termite Treatment
Grid C1H1-C3H3 1 13.92 7.86 109.41
Grid A3K3-A4K4 1 22.38 2.96 66.24
Grid B4J4-B5J5 1 21.46 9.23 198.08
Total Qty 373.73 Sqm
Page 91
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 with OPC cement @ 220kgs, with
40mm and down size graded granite metal coarse aggregates @0.892cum and fine aggregates @ 0.465cum machine
8 4.2
mixed, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation including
cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2
Footing PCC
F1 4 2.80 2.60 0.10 2.91
F2 3 2.60 2.45 0.10 1.91
F3 7 2.45 2.00 0.10 3.43
F4 6 2.30 1.95 0.10 2.69
F5 4 1.70 1.50 0.10 1.02
F6 3 1.20 1.20 0.10 0.43
PCC Under Grade Beam
Grid C1-F1 1 5.16 0.45 0.10 0.23
Grid F1-G'1 1 4.89 0.45 0.10 0.22
Grid G'1-H1 1 2.50 0.45 0.10 0.11
Grid A3-C3 1 3.78 0.45 0.10 0.17
Grid H3-K3 1 3.78 0.45 0.10 0.17
Grid B5-J5 1 20.08 0.45 0.10 0.90
Grid A3-A4 & K3-K4 2 2.50 0.45 0.10 0.23
Grid B4-B5 & J4-J5 2 8.78 0.45 0.10 0.79
Grid C1-C3 & 1 7.64 0.45 0.10 0.34
Grid H1-H2 1 4.78 0.45 0.10 0.22
Grid H2-H3 1 2.18 0.45 0.10 0.10
PCC Under Plinth Beam
Grid b/w 1-2 & C-D 2 2.50 0.45 0.38 0.86
Grid b/w 1-2 & G'-H 1 2.50 0.45 0.38 0.43
Grid C2-F2 1 5.27 0.45 0.45 1.07
Grid F2-G'2 1 5.83 0.45 0.45 1.18
Page 92
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid G'2-H2 1 2.50 0.45 0.45 0.51
Grid D3-H3 1 10.27 0.45 0.45 2.08
Grid A4-C4 & H4-K4 2 4.00 0.45 0.38 1.37
Grid C4-E4 & G4-H4 2 4.54 0.45 0.45 1.84
Grid E4-G4 1 3.91 0.45 0.60 1.06
Grid D1-D4 1 9.69 0.45 0.45 1.96
Grid F2-F4 1 4.76 0.45 0.60 1.29
Grid G2-G3 1 2.40 0.45 0.38 0.41
Grid G'1-G'2 1 4.78 0.45 0.45 0.97
Grid G'2-G'4 1 5.13 0.45 0.60 1.39
Total Qty 32.27 Cum
KSRB 2.3 : Filling available excavated earth ( excluding rock ) in sides of foundations upto plinth in layers not
12 2.10 exceeding 20 cms. in depth, compacting each deposited layer by ramming after watering with lead upto 50 m. and lift
upto 1.5 m. including cost of all labour complete as per specifications. Specification. No. KBS 2.9
Earth Filling in Sides of Foundation
Same As Hard Soil 67.08
Same As Soft Rock 254.14
Total Qty 321.22
Deductions
Pcc under Footings 32.27
Footing And Column concrete 84.23
BBM in Foundation 83.08
Total Qty 199.57
Total filling Qty 121.64
Extra Qty required. 54.57
Available Soil For Filling as per item code no 2.4 67.08 Cum
Page 93
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2.5 : Earthwork excavation in all soil deposits and filling sides of foundation upto plinth in layers not exceeding
13 2.12 20cms. in depth, compacting each deposited layer by ramming after watering with all lead and lift including cost of all
labour complete as per specifications. specification. No. KBS 2.9.9 / 2.9.10.1 / 2.1.1
Plinth Filling
Grid C1H1-C3H3 1 13.92 7.86 1.50 164.12
Grid A3K3-A4K4 1 22.38 2.96 1.30 86.12
Grid B4J4-B5J5 1 21.46 9.23 1.10 217.88
Qty required for foundation sides as per item
54.57
No 10 Code no 2.10 above
Total Qty 522.69 Cum
KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of Design mix M20 with OPC cement @
320kgs, with 20mm and down size graded granite metal coarse aggregates @0.69cum and fine aggregtes @ 0.460
cum, with super plasticisers @ 3 liters confirming to IS 9103-1999 reafirmed-2008, machine mixed, concrete laid in
14 4.11 layers not exceeding 15 cms thick, vibrated for all works in foundation for footings, pedastals, retaining walls, return
walls, walls (any thickness) including attached pilasters, columnspillars, posts, struts, buttresses, bed blocks, anchor
blocks & plinths etc., including cost of all materials, labour, HOM of machinery, curing, complete but
excluding cost of reinforcement as per specifications. Specification No. KBS 4.1, 4.6
Footing Concrete
F1 4 2.60 2.40 0.60 14.98
F2 3 2.40 2.25 0.55 8.91
F3 7 2.25 1.80 0.50 14.18
F4 6 2.10 1.75 0.45 9.92
F5 4 1.50 1.30 0.30 2.34
F6 3 1.00 1.00 0.30 0.90
Column Concrete Upto Plinth Top fd
Grid A2- C8 1 0.04 2.90 0.12 Grid A2-
Grid A3 -C4 1 0.45 0.23 2.85 0.29 Grid A3 -
Page 94
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid B4 -C2 1 0.60 0.23 2.60 0.36 Grid B4 -
Grid B5 -C2 1 0.60 0.23 2.25 0.31 Grid B5 -
Grid C1- C4 1 0.45 0.23 3.05 0.32 Grid C1-
Grid C2- C4 1 0.45 0.23 2.75 0.28 Grid C2-
Grid C4 -C1 1 0.60 0.23 2.35 0.32 Grid C4 -
Grid C5 -C1 1 0.60 0.23 2.20 0.30 Grid C5 -
Grid D1 -C4 1 0.45 0.23 2.90 0.30 Grid D1 -
Grid D2 -C5 1 0.45 0.23 2.60 0.27 Grid D2 -
Grid E4 -C1 1 0.60 0.23 2.35 0.32 Grid E4 -
Grid E5-C1 1 0.60 0.23 2.20 0.30 Grid E5-F
Grid E6-C7 1 0.07 2.40 0.17 Grid E6-F
Grid F1 -C6 1 0.45 0.23 2.90 0.30 Grid F1 -F
Grid F2 -C3 1 0.60 0.23 2.60 0.36 Grid F2 -F
Grid G4 -C1 1 0.60 0.23 2.35 0.32 Grid G4 -
Grid G5 -C1 1 0.60 0.23 2.20 0.30 Grid G5 -
Grid G6-C7 1 0.07 2.40 0.17 Grid G6-F
Grid G'1 -C4 1 0.45 0.23 2.90 0.30 Grid G'1
Grid G'2- C3 1 0.60 0.23 2.60 0.36 Grid G'2-
Grid H1 -C4 1 0.45 0.23 3.05 0.32 Grid H1 -
Grid H2 -C4 1 0.45 0.23 2.65 0.27 Grid H2 -
Grid H4 -C1 1 0.60 0.23 2.35 0.32 Grid H4 -
Grid H5 -C1 1 0.60 0.23 2.20 0.30 Grid H5 -
Grid J4 -C2 1 0.60 0.23 2.45 0.34 Grid J4 -F
Grid J5 -C2 1 0.60 0.23 2.25 0.31 Grid J5 -F
Grid K3 -C4 1 0.45 0.23 2.90 0.30 Grid K3 -
Grade Beam Concrete
Grid C1-F1 1 5.16 0.23 0.45 0.53
Grid F1-G'1 1 4.89 0.23 0.45 0.51
Page 95
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid G'1-H1 1 2.50 0.23 0.45 0.26
Grid A3-C3 1 3.78 0.23 0.45 0.39
Grid H3-K3 1 3.78 0.23 0.45 0.39
Grid B5-J5 1 20.08 0.23 0.45 2.08
Grid A3-A4 & K3-K4 2 2.50 0.23 0.45 0.52
Grid B4-B5 & J4-J5 2 8.78 0.23 0.45 1.82
Grid C1-C3 & 1 7.64 0.23 0.45 0.79
Grid H1-H2 1 4.78 0.23 0.45 0.49
Grid H2-H3 1 2.18 0.23 0.45 0.23
Plinth Beam Concrete
Grid C1-F1,PB5 1 5.16 0.23 0.45 0.53
Grid F1-G'1,PB3 1 4.89 0.23 0.45 0.51
Grid G'1-H1,PB5 1 2.50 0.23 0.45 0.26
Grid b/w 1-2 & C-D,PB6 2 2.50 0.23 0.38 0.44
Grid b/w 1-2 & G'-H,PB6 1 2.50 0.23 0.38 0.22
Grid C2-F2,PB5 1 5.27 0.23 0.45 0.55
Grid F2-G'2,PB2 1 4.63 0.23 0.45 0.48
Grid G'2-H2,PB3 1 2.50 0.23 0.45 0.26
Grid A3-C3,PB3 1 3.78 0.23 0.45 0.39
Grid D3-H3,PB3 1 10.27 0.23 0.45 1.06
Grid H3-K3,PB3 1 3.78 0.23 0.45 0.39
Grid A4-C4 & H4-K4,PB4 2 4.00 0.23 0.38 0.70
Grid C4-E4 & G4-H4,PB2 2 4.54 0.23 0.45 0.94
Grid E4-G4,PB1 1 3.91 0.23 0.60 0.54
Grid B5-J5,PB4 1 20.08 0.23 0.38 1.75
Grid A3-A4 & K3-K4, PB6 2 2.50 0.23 0.38 0.44
Grid B4-B5 & J4-J5,PB1 2 8.78 0.23 0.60 2.42
Grid C1-C4 &,PB2 1 9.32 0.23 0.45 0.96
Page 96
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D1-D4,PB2 1 9.69 0.23 0.45 1.00
Grid F2-F4,PB1 1 4.76 0.23 0.60 0.66
Grid G2-G3,PB6 1 2.40 0.23 0.38 0.21
Grid G'1-G'2,PB3 1 4.78 0.23 0.45 0.49
Grid G'2-G'4,PB1 1 5.13 0.23 0.60 0.71
Grid H1-H2,PB3 1 4.78 0.23 0.45 0.49
Grid H2-H4,PB1 1 4.54 0.23 0.60 0.63
Total Qty 84.23 Cum
KSRB 4.2.4 : Providing and laying in position reinforced cement concrete of mix M10 with OPC cement @ 220kgs, with
20mm and down size graded granite metal coarse aggregates @0.792cum and fine aggregtes @ 0.465cum, machine
mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all works in foundation plinth and ground floor
15 4.13 level for roof slabs, staircase, lintles, retaining walls, return walls, walls ( any thickness ) including attached plasters,
columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks,
anchor blocks, plain window cills, fillets etc., including cost of all materials, labour, HOM of machinery, curing, complete
as per specifications. Specification No. KBS 4.1, 4.6
Page 97
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid C2-F2 1 5.27 0.23 0.15 0.18
Grid F2-G'2 1 4.63 0.23 0.15 0.16
Grid G'2-H2 1 2.50 0.23 0.15 0.09
Grid A3-C3 1 3.78 0.23 0.15 0.13
Grid D3-K3 1 14.05 0.23 0.15 0.48
Grid A4-C4 1 4.00 0.23 0.15 0.14
Grid C4-D4 1 2.73 0.23 0.15 0.09
Grid G4-H4 1 4.55 0.23 0.15 0.16
Grid H4-K4 1 4.00 0.23 0.15 0.14
Grid B5-J5 1 19.85 0.23 0.15 0.68
Grid A3-A4 1 2.50 0.23 0.15 0.09
Grid B4-B5 1 8.63 0.23 0.15 0.30
Grid C1-C4 1 9.23 0.23 0.15 0.32
Grid D1-D4 1 9.69 0.23 0.15 0.33
Grid F2-F3 1 2.26 0.23 0.15 0.08
Grid G'1-G'2 1 4.78 0.23 0.15 0.16
Grid G'2-G'4 1 5.13 0.23 0.15 0.18
Grid H1-H2 1 4.78 0.23 0.15 0.16
Grid H2-H4 1 4.54 0.23 0.15 0.16
Grid J4-J5 1 8.63 0.23 0.15 0.30
Grid K3-K4 1 2.50 0.23 0.15 0.09
KSRB
Total 4.2.10
Qty : Providing and laying in position reinforced cement concrete of design mix M20 with OPC16.57 cement Cum
@
24kgs, with 12mm and down size graded granite metal coarse aggregates @0.05175cum and fine aggregtes @
0.0345cum, with superplastisiser @0.225lts, machine mixed, well compacted for plain chajja of 7.5 cms. average
16 4.19
thickness, upto ground floor level, including cost of all materials, labour, HOM of machinery, finishing, curing, complete
but excluding cost of
Chejja's
reinforcement as per specifications. Specification No. KBS 4.1, 4.6
W 12 2.10 0.60 15.12
D 2 1.50 0.60 1.80
Page 98
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
D 2 2.96 0.60 3.55
GD 1 2.96 0.60 1.78
W.C & Bath 1 2.96 0.60 1.78
Total Qty 24.02 Sqm
KSRB 4-1.6 ; Providing and laying in position plain cement concrete of mix 1:2:4 with cement @ 240kgs, with 20mm
and down size graded granite metal coarse aggregates @ 0.878 cum and fine aggregtes @ 0.53cum, machine mixed,
18 4.6
concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation, plinth and cills, ncluding cost of all
materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2
Coping Concrete
Grid C1-F1 1 5.16 0.23 0.10 0.12
Grid F1-G'1 1 4.89 0.23 0.10 0.11
Grid G'1-H1 1 2.50 0.23 0.10 0.06
Grid A3-C3 1 3.78 0.23 0.10 0.09
Grid H3-K3 1 3.78 0.23 0.10 0.09
Grid B5-J5 1 20.08 0.23 0.10 0.46
Grid A3-A4 & K3-K4 2 2.50 0.23 0.10 0.12
Grid B4-B5 & J4-J5 2 8.78 0.23 0.10 0.40
Grid C1-C3 & 1 7.64 0.23 0.10 0.18
Grid H1-H2 1 4.78 0.23 0.10 0.11
Grid H2-H3 1 2.18 0.23 0.10 0.05
Cill Concrete Beam
Grid C1-F1 1 5.16 0.23 0.075 0.09 ###
Grid F1-G'1 1 4.89 0.23 0.075 0.08 ###
Grid G'1-H1 1 2.50 0.23 0.075 0.04 ###
Grid C2-F2 1 5.27 0.23 0.075 0.09 ###
Grid F2-G'2 1 4.63 0.23 0.075 0.08 ###
Grid G'2-H2 1 2.50 0.23 0.075 0.04 ###
Grid A3-C3 1 3.78 0.23 0.075 0.07 ###
Page 99
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D3-K3 1 14.05 0.23 0.075 0.24 ###
Grid A4-C4 1 4.00 0.23 0.075 0.07 ###
Grid C4-D4 1 2.73 0.23 0.075 0.05 ###
Grid G4-H4 1 4.55 0.23 0.075 0.08
Grid H4-K4 1 4.00 0.23 0.075 0.07 ###
Grid B5-J5 1 19.85 0.23 0.075 0.34 ###
Grid A3-A4 1 2.50 0.23 0.075 0.04 ###
Grid B4-B5 1 8.63 0.23 0.075 0.15 ###
Grid C1-C4 1 9.23 0.23 0.075 0.16 ###
Grid D1-D4 1 9.69 0.23 0.075 0.17 ###
Grid F2-F3 1 2.26 0.23 0.075 0.04 ###
Grid G'1-G'2 1 4.78 0.23 0.075 0.08 ###
Grid G'2-G'4 1 5.13 0.23 0.075 0.09 ###
Grid H1-H2 1 4.78 0.23 0.075 0.08 ###
Grid H2-H4 1 4.54 0.23 0.075 0.08 ###
Grid J4-J5 1 8.63 0.23 0.075 0.15 ###
Grid K3-K4 1 2.50 0.23 0.075 0.04 ###
Deductions
MD -1 1.80 0.23 0.075 -0.03
D -4 1.20 0.23 0.075 -0.08
D1 -3 1.00 0.23 0.075 -0.05
D2 -1 0.90 0.23 0.075 -0.02
D3 -2 0.75 0.23 0.075 -0.03
GD -1 1.80 0.23 0.075 -0.03
O -4 1.20 0.23 0.075 -0.08
Openings -2 1.20 0.23 0.075 -0.04
Total Qty 3.84 Cum
Page 100
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
19 4.28 foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per
specificaitons. Specification No. KBS 4.6.2
Page 101
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
3 2 1.00 0.30 1.80
Total Qty 121.81 Sqm
KSRB 4-6.5 : Providing and removing centering, shuttering, strutting, propping etc., for columns, pillars, post and
21 4.32 struts, square / rectangular/polygon in plan including cost of all materials, labour complete as per specifications.
Specification No. KBS 4.6.2
Column Shuttering
Grid A3 -C4 1 1.36 2.85 3.88 Grid A3 -
Grid B4 -C2 1 1.66 2.60 4.32 Grid B4 -
Grid B5 -C2 1 1.66 2.25 3.74 Grid B5 -
Grid C1- C4 1 1.36 3.05 4.15 Grid C1-
Grid C2- C4 1 1.36 2.75 3.74 Grid C2-
Grid C4 -C1 1 1.66 2.35 3.90 Grid C4 -
Grid C5 -C1 1 1.66 2.20 3.65 Grid C5 -
Grid D1 -C4 1 1.36 2.90 3.94 Grid D1 -
Grid D2 -C5 1 1.36 2.60 3.54 Grid D2 -
Grid E4 -C1 1 1.66 2.35 3.90 Grid E4 -
Grid E5-C1 1 1.66 2.20 3.65 Grid E5-F
Grid F1 -C6 1 1.36 2.90 3.94 Grid F1 -F
Grid F2 -C3 1 1.66 2.60 4.32 Grid F2 -F
Grid G4 -C1 1 1.66 2.35 3.90 Grid G4 -
Grid G5 -C1 1 1.66 2.20 3.65 Grid G5 -
Grid G'1 -C4 1 1.36 2.90 3.94 Grid G'1
Grid G'2- C3 1 1.66 2.60 4.32 Grid G'2-
Grid H1 -C4 1 1.36 3.05 4.15 Grid H1 -
Grid H2 -C4 1 1.36 2.65 3.60 Grid H2 -
Grid H4 -C1 1 1.66 2.35 3.90 Grid H4 -
Grid H5 -C1 1 1.66 2.20 3.65 Grid H5 -
Grid J4 -C2 1 1.66 2.45 4.07 Grid J4 -F
Page 102
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid J5 -C2 1 1.66 2.25 3.74 Grid J5 -F
Grid K3 -C4 1 1.36 2.90 3.94 Grid K3 -
Column Concrete Upto Roof Bottem
C1 8 1.66 3.60 47.81
C2 4 1.66 3.60 23.90
C3 2 1.66 3.60 11.95
C4 8 1.36 3.60 39.17
C5 1 1.36 3.60 4.90
C6 1 1.36 3.60 4.90
Total Qty 226.15 Sqm
KSRB 4-6.6 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
22 4.33 columns, pillars,post and struts, circular or curved in plan including cost of all materials, labour complete as per
specifications. Specification No. KBS 4.6.2
Page 103
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid C2-F2 1 2 5.27 0.15 1.58
Grid F2-G'2 1 2 4.63 0.15 1.39
Grid G'2-H2 1 2 2.50 0.15 0.75
Grid A3-C3 1 2 3.78 0.15 1.13
Grid D3-K3 1 2 14.05 0.15 4.22
Grid A4-C4 1 2 4.00 0.15 1.20
Grid C4-D4 1 2 2.73 0.15 0.82
Grid G4-H4 1 2 4.55 0.15 1.36
Grid H4-K4 1 2 4.00 0.15 1.20
Grid B5-J5 1 2 19.85 0.15 5.96
Grid A3-A4 1 2 2.50 0.15 0.75
Grid B4-B5 1 2 8.63 0.15 2.59
Grid C1-C4 1 2 9.23 0.15 2.77
Grid D1-D4 1 2 9.69 0.15 2.91
Grid F2-F3 1 2 2.26 0.15 0.68
Grid G'1-G'2 1 2 4.78 0.15 1.43
Grid G'2-G'4 1 2 5.13 0.15 1.54
Grid H1-H2 1 2 4.78 0.15 1.43
Grid H2-H4 1 2 4.54 0.15 1.36
Grid J4-J5 1 2 8.63 0.15 2.59
Grid K3-K4 1 2 2.50 0.15 0.75
Centering at Openings
MD 1 1 1.80 0.23 0.41
D 4 1 1.20 0.23 1.10
D1 3 1 1.00 0.23 0.69
D2 1 1 0.90 0.23 0.21
D3 2 1 0.75 0.23 0.35
W 12 1 1.80 0.23 4.97
Page 104
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Total Qty 49.90 Sqm
KSRB 4-6.4 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
25 4.31 vertical surface such as walls at any thickness, including attached pilasters, buttresses, plinth cills and string courses
cost of all materials, labour complete as per specifications. Specification No. KBS 4.6.2
Page 105
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A4-C4 & H4-K4,PB4 2 2 4.00 0.38 6.08
Grid C4-E4 & G4-H4,PB2 2 2 4.54 0.45 8.17
Grid E4-G4,PB1 1 2 3.91 0.60 4.69
Grid B5-J5,PB4 1 2 20.08 0.38 15.26
Grid A3-A4 & K3-K4, PB6 2 2 2.50 0.38 3.80
Grid B4-B5 & J4-J5,PB1 2 2 8.78 0.60 21.07
Grid C1-C4 &,PB2 1 2 9.32 0.45 8.39
Grid D1-D4,PB2 1 2 9.69 0.45 8.72
Grid F2-F4,PB1 1 2 4.76 0.60 5.71
Grid G2-G3,PB6 1 2 2.40 0.38 1.82
Grid G'1-G'2,PB3 1 2 4.78 0.45 4.30
Grid G'2-G'4,PB1 1 2 5.13 0.60 6.16
Grid H1-H2,PB3 1 2 4.78 0.45 4.30
Grid H2-H4,PB1 1 2 4.54 0.60 5.45
Shuttering For Coping Concrete
Grid C1-F1 1 2 4.66 0.10 0.93
Grid F1-G'1 1 2 4.89 0.10 0.98
Grid G'1-H1 1 2 2.50 0.10 0.50
Grid A3-C3 1 2 3.78 0.10 0.76
Grid H3-K3 1 2 3.78 0.10 0.76
Grid B5-J5 1 2 20.08 0.10 4.02
Grid A3-A4 & K3-K4 2 2 2.50 0.10 1.00
Grid B4-B5 & J4-J5 2 2 8.78 0.10 3.51
Grid C1-C3 & 1 2 7.64 0.10 1.53
Grid H1-H2 1 2 4.78 0.10 0.96
Grid H2-H3 1 2 2.18 0.10 0.44
Shuttering For PCC Under Plinth Beam
Grid b/w 1-2 & C-D 2 2 2.50 0.38 3.80
Page 106
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid b/w 1-2 & G'-H 1 2 2.50 0.38 1.90
Grid C2-F2 1 2 5.27 0.45 4.74
Grid F2-G'2 1 2 5.83 0.45 5.25
Grid G'2-H2 1 2 2.50 0.45 2.25
Grid D3-H3 1 2 10.27 0.45 9.24
Grid A4-C4 & H4-K4 2 2 4.00 0.38 6.08
Grid C4-E4 & G4-H4 2 2 4.54 0.45 8.17
Grid E4-G4 1 2 3.91 0.60 4.69
Grid D1-D4 1 2 9.69 0.45 8.72
Grid F2-F4 1 2 4.76 0.60 5.71
Grid G2-G3 1 2 2.40 0.38 1.82
Grid G'1-G'2 1 2 4.78 0.45 4.30
Grid G'2-G'4 1 2 5.13 0.60 6.16
Cill Concrete Shuttering Beam
Grid C1-F1 1 2 5.16 0.075 0.77 ###
Grid F1-G'1 1 2 4.89 0.075 0.73 ###
Grid G'1-H1 1 2 2.50 0.075 0.38 ###
Grid C2-F2 1 2 5.27 0.075 0.79 ###
Grid F2-G'2 1 2 4.63 0.075 0.69 ###
Grid G'2-H2 1 2 2.50 0.075 0.38 ###
Grid A3-C3 1 2 3.78 0.075 0.57 ###
Grid D3-K3 1 2 14.05 0.075 2.11 ###
Grid A4-C4 1 2 4.00 0.075 0.60 ###
Grid C4-D4 1 2 2.73 0.075 0.41 ###
Grid G4-H4 1 2 4.55 0.075 0.68
Grid H4-K4 1 2 4.00 0.075 0.60 ###
Grid B5-J5 1 2 19.85 0.075 2.98 ###
Grid A3-A4 1 2 2.50 0.075 0.38 ###
Page 107
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid B4-B5 1 2 8.63 0.075 1.29 ###
Grid C1-C4 1 2 9.23 0.075 1.38 ###
Grid D1-D4 1 2 9.69 0.075 1.45 ###
Grid F2-F3 1 2 2.26 0.075 0.34 ###
Grid G'1-G'2 1 2 4.78 0.075 0.72 ###
Grid G'2-G'4 1 2 5.13 0.075 0.77 ###
Grid H1-H2 1 2 4.78 0.075 0.72 ###
Grid H2-H4 1 2 4.54 0.075 0.68 ###
Grid J4-J5 1 2 8.63 0.075 1.29 ###
Grid K3-K4 1 2 2.50 0.075 0.38 ###
Deductions
MD -1 2 1.80 0.075 -0.27
D -4 2 1.20 0.075 -0.72
D1 -3 2 1.00 0.075 -0.45
D2 -1 2 0.90 0.075 -0.14
D3 -2 2 0.75 0.075 -0.22
GD -1 2 1.80 0.075 -0.27
O -4 2 1.20 0.075 -0.72
Openings -2 2 1.20 0.075 -0.36
Total Qty 324.98 Sqm
KSRB 4-6.10 :Providing and removing centering, shuttering, strutting, propping etc., for chajjas, corbels etc., including
26 4.37
edges including cost of all materials, labour complete as per specifications. Specification No. KBS 4.6.2
Page 108
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
W.C & Bath 1 3.06 0.60 1.84
Total Qty 25.94 Sqm
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking,
placing in position, lapping and / or welding wherever required, tying with binding wire and anchoring to the adjoining
28 4.46.2
members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost
of materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3 - TMT bars Fe 500
Footing Steel 10.40
Total Qty 10.40 Tonne
KSRB 6-1.3 : Providing and constructing burnt brick masonry for basement and superstructure with approved quality of non-modular bricks of
29 6.3 standard size of class designation 3.5Newton per sqmm with cement mortar1:6 including cost of materials, labour charges, scaffolding, curing
complete as per specifications. Specification No. KBS 6.2
BBM In Basement GL
Grid C1-F1 1 5.16 0.23 0.95 1.13 ###
Grid F1-G'1 1 4.89 0.23 0.95 1.07 ###
Grid G'1-H1 1 2.50 0.23 0.95 0.55 ###
Grid A3-C3 1 3.78 0.23 0.75 0.65 ###
Grid H3-K3 1 3.78 0.23 0.80 0.70 ###
Grid B5-J5 1 20.08 0.23 0.37 1.71 ###
Grid A3-A4 & K3-K4 2 2.50 0.23 0.72 0.83 ###
Grid B4-B5 & J4-J5 2 8.78 0.23 0.30 1.21 ###
Grid C1-C3 & 1 7.64 0.23 0.85 1.49 ###
Grid H1-H2 1 4.78 0.23 0.85 0.93 ###
Grid H2-H3 1 2.18 0.23 0.85 0.43 ###
BBM Upto Roof Level Beam
Grid C1-F1 1 5.16 0.23 3.02 3.59 ###
Grid F1-G'1 1 4.89 0.23 2.87 3.23 ###
Grid G'1-H1 1 2.50 0.23 3.02 1.74 ###
Grid C2-F2 1 5.27 0.23 3.02 3.67 ###
Page 109
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F2-G'2 1 4.63 0.23 2.87 3.06 ###
Grid G'2-H2 1 2.50 0.23 3.02 1.74 ###
Grid A3-C3 1 3.78 0.23 3.02 2.63 ###
Grid D3-K3 1 14.05 0.23 3.02 9.78 ###
Grid A4-C4 1 4.00 0.23 3.02 2.78 ###
Grid C4-D4 1 2.73 0.23 2.87 1.81 ###
Grid G4-H4 1 4.55 0.23 0.80 0.84
Grid H4-K4 1 4.00 0.23 3.02 2.78 ###
Grid B5-J5 1 19.85 0.23 3.02 13.81 ###
Grid A3-A4 1 2.50 0.23 3.02 1.74 ###
Grid B4-B5 1 8.63 0.23 2.87 5.71 ###
Grid C1-C4 1 9.23 0.23 2.97 6.32 ###
Grid D1-D4 1 9.69 0.23 2.97 6.63 ###
Grid F2-F3 1 2.26 0.23 2.87 1.49 ###
Grid G'1-G'2 1 4.78 0.23 3.02 3.33 ###
Grid G'2-G'4 1 5.13 0.23 2.87 3.39 ###
Grid H1-H2 1 4.78 0.23 3.02 3.33 ###
Grid H2-H4 1 4.54 0.23 2.87 3.00 ###
Grid J4-J5 1 8.63 0.23 2.87 5.71 ###
Grid K3-K4 1 2.50 0.23 3.02 1.74 ###
Deductions
MD -1 1.80 0.23 2.55 -1.06
D -4 1.20 0.23 2.40 -2.65
D1 -3 1.00 0.23 2.40 -1.66
D2 -1 0.90 0.23 2.40 -0.50
D3 -2 0.75 0.23 2.10 -0.72
GD -1 1.80 0.23 2.40 -0.99
W -13 1.80 0.23 1.50 -8.07
Page 110
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
V -7 1.80 0.23 0.60 -1.74
V1 -1 0.60 0.23 0.60 -0.08
O -4 1.20 0.23 2.40 -2.65
Openings -2 1.20 0.23 2.40 -1.32
Total Qty 83.08 Cum
Providing RCC loft (atta) 7.5cms thick with cement concrete design mix M20 using clean granite or trap jelly of 20mm
36 4.54 and down size with necessary reinforcements at 20cms centre to centre as per design including form work, centring,
curing, etc., complete (exclusive of cost of steel and fabrication charges).
Loft's
Store 1 9.06 0.60 5.44
Dry Store 1 3.80 0.60 2.28
Dish Store 1 11.00 0.60 6.60
P.Store 1 4.40 0.60 2.64
Pantry 1 8.00 0.60 4.80
Total Qty 21.76 Sqm
Page 111
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Kitchen & Dining Block Steel
Ground Floor Steel Fabrication RA BILL NO - 01
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Footing Mat Steel
F1 - - - - - -
A-Bars 12 21 1 4 3.10 - - 260.40 - - -
B-Bars 12 22 1 4 2.90 - - 255.20 - - -
F2 - - - - - -
A-Bars 12 19 1 3 2.85 - - 162.45 - - -
B-Bars 12 21 1 3 2.70 - - 170.10 - - -
F3 - - - - - -
A-Bars 10 19 1 7 2.65 - 352.45 - - - -
B-Bars 10 24 1 7 2.30 - 386.40 - - - -
F4 - - - - - -
A-Bars 10 19 1 6 2.45 - 279.30 - - - -
B-Bars 10 22 1 6 2.10 - 277.20 - - - -
F5 - - - - - -
A-Bars 10 10 1 4 1.70 - 68.00 - - - -
B-Bars 10 11 1 4 1.50 - 66.00 - - - -
F6 - - - - - -
A-Bars 10 8 1 3 1.20 - 28.80 - - - -
B-Bars 10 8 1 3 1.20 - 28.80 - - - -
Column Steel Upto Plinth Top - - - - - -
Grid A2- C8 - - - - - -
Main Bars 12 6 1 1 3.65 - - 21.90 - - -
Circular Stirrups 8 20 1 1 0.48 9.60 - - - - -
Grid A3 -C4 - - - - - -
Main Bars 12 8 1 1 3.60 - - 28.80 - - -
Rectangular Stirrups 8 19 1 1 1.19 22.61 - - - - -
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
Grid B4 -C2 - - - - - -
Main Bars 20 8 1 1 3.55 - - - - 28.40 -
Rectangular Stirrups 8 17 1 1 1.49 25.33 - - - - -
Page 112
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dimond Stirrups 8 17 1 1 1.25 21.25 - - - - -
Grid B5 -C2 - - - - - -
Main Bars 20 8 1 1 3.15 - - - - 25.20 -
Rectangular Stirrups 8 15 1 1 1.49 22.35 - - - - -
Dimond Stirrups 8 15 1 1 1.25 18.75 - - - - -
Grid C1- C4 - - - - - -
Main Bars 12 8 1 1 3.80 - - 30.40 - - -
Rectangular Stirrups 8 21 1 1 1.19 24.99 - - - - -
Dimond Stirrups 8 21 1 1 0.95 19.95 - - - - -
Grid B4 -C2 - - - - - -
Main Bars 20 8 1 1 3.65 - - - - 29.20 -
Rectangular Stirrups 8 20 1 1 1.49 29.80 - - - - -
Dimond Stirrups 8 20 1 1 1.25 25.00 - - - - -
Grid C4 -C1 - - - - - -
Main Bars-1 25 4 1 1 3.40 - - - - - 13.60
Main Bars-2 20 4 1 1 3.40 - - - - 13.60 -
Rectangular Stirrups 8 16 1 1 1.49 23.84 - - - - -
Dimond Stirrups 8 16 1 1 1.25 20.00 - - - - -
Grid C5 -C1 - - - - - -
Main Bars-1 25 4 1 1 3.15 - - - - - 12.60
Main Bars-2 20 4 1 1 3.15 - - - - 12.60 -
Rectangular Stirrups 8 15 1 1 1.49 22.35 - - - - -
Dimond Stirrups 8 15 1 1 1.25 18.75 - - - - -
Grid D1 -C4 - - - - - -
Main Bars 12 8 1 1 3.80 - - 30.40 - - -
Rectangular Stirrups 8 21 1 1 1.19 24.99 - - - - -
Dimond Stirrups 8 21 1 1 0.95 19.95 - - - - -
Grid B4 -C2 - - - - - -
Main Bars 20 8 1 1 3.60 - - - - 28.80 -
Rectangular Stirrups 8 19 1 1 1.49 28.31 - - - - -
Dimond Stirrups 8 19 1 1 1.25 23.75 - - - - -
Grid E4 -C1 - - - - - -
Main Bars-1 25 4 1 1 3.40 - - - - - 13.60
Main Bars-2 20 4 1 1 3.40 - - - - 13.60 -
Rectangular Stirrups 8 16 1 1 1.49 23.84 - - - - -
Dimond Stirrups 8 16 1 1 1.25 20.00 - - - - -
Grid E5-C1 - - - - - -
Main Bars-1 25 4 1 1 3.15 - - - - - 12.60
Main Bars-2 20 4 1 1 3.15 - - - - 12.60 -
Page 113
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Rectangular Stirrups 8 15 1 1 1.49 22.35 - - - - -
Dimond Stirrups 8 15 1 1 1.25 18.75 - - - - -
Grid E6-C7 - - - - - -
Main Bars 16 8 1 1 3.15 - - - 25.20 - -
Circular Stirrups 8 15 1 1 0.69 10.35 - - - - -
Grid F1 -C6 - - - - - -
Main Bars 16 8 1 1 3.80 - - - 30.40 - -
Rectangular Stirrups 8 18 1 1 1.19 21.42 - - - - -
Dimond Stirrups 8 18 1 1 0.95 17.10 - - - - -
Grid F2 -C3 - - - - - -
Main Bars-1 20 4 1 1 3.60 - - - - 14.40 -
Main Bars-2 16 4 1 1 3.60 - - - 14.40 - -
Rectangular Stirrups 8 17 1 1 1.49 25.33 - - - - -
Dimond Stirrups 8 17 1 1 1.25 21.25 - - - - -
Grid G4 -C1 - - - - - -
Main Bars-1 25 4 1 1 3.40 - - - - - 13.60
Main Bars-2 20 4 1 1 3.40 - - - - 13.60 -
Rectangular Stirrups 8 16 1 1 1.49 23.84 - - - - -
Dimond Stirrups 8 16 1 1 1.25 20.00 - - - - -
Grid G5 -C1 - - - - - -
Main Bars-1 25 4 1 1 3.15 - - - - - 12.60
Main Bars-2 20 4 1 1 3.15 - - - - 12.60 -
Rectangular Stirrups 8 15 1 1 1.49 22.35 - - - - -
Dimond Stirrups 8 15 1 1 1.25 18.75 - - - - -
Grid G6-C7 - - - - - -
Main Bars 16 8 1 1 3.15 - - - 25.20 - -
Circular Stirrups 8 15 1 1 0.69 10.35 - - - - -
Grid G'1 -C4 - - - - - -
Main Bars 12 8 1 1 3.80 - - 30.40 - - -
Rectangular Stirrups 8 21 1 1 1.19 24.99 - - - - -
Dimond Stirrups 8 21 1 1 0.95 19.95 - - - - -
Grid G'2- C3 - - - - - -
Main Bars-1 20 4 1 1 3.60 - - - - 14.40 -
Main Bars-2 16 4 1 1 3.60 - - - 14.40 - -
Rectangular Stirrups 8 17 1 1 1.49 25.33 - - - - -
Dimond Stirrups 8 17 1 1 1.25 21.25 - - - - -
Grid H1 -C4 - - - - - -
Main Bars 12 8 1 1 3.80 - - 30.40 - - -
Rectangular Stirrups 8 21 1 1 1.19 24.99 - - - - -
Page 114
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dimond Stirrups 8 21 1 1 0.95 19.95 - - - - -
Grid B4 -C2 - - - - - -
Main Bars 20 8 1 1 3.60 - - - - 28.80 -
Rectangular Stirrups 8 19 1 1 1.49 28.31 - - - - -
Dimond Stirrups 8 19 1 1 1.25 23.75 - - - - -
Grid H4 -C1 - - - - - -
Main Bars-1 25 4 1 1 3.40 - - - - - 13.60
Main Bars-2 20 4 1 1 3.40 - - - - 13.60 -
Rectangular Stirrups 8 16 1 1 1.49 23.84 - - - - -
Dimond Stirrups 8 16 1 1 1.25 20.00 - - - - -
Grid H5 -C1 - - - - - -
Main Bars-1 25 4 1 1 3.15 - - - - - 12.60
Main Bars-2 20 4 1 1 3.15 - - - - 12.60 -
Rectangular Stirrups 8 15 1 1 1.49 22.35 - - - - -
Dimond Stirrups 8 15 1 1 1.25 18.75 - - - - -
Grid J4 -C2 - - - - - -
Main Bars 20 8 1 1 3.40 - - - - 27.20 -
Rectangular Stirrups 8 16 1 1 1.49 23.84 - - - - -
Dimond Stirrups 8 16 1 1 1.25 20.00 - - - - -
Grid J5 -C2 - - - - - -
Main Bars 20 8 1 1 3.15 - - - - 25.20 -
Rectangular Stirrups 8 15 1 1 1.49 22.35 - - - - -
Dimond Stirrups 8 15 1 1 1.25 18.75 - - - - -
Grid K3 -C4 - - - - - -
Main Bars 12 8 1 1 3.65 - - 29.20 - - -
Rectangular Stirrups 8 20 1 1 1.19 23.80 - - - - -
Dimond Stirrups 8 20 1 1 0.95 19.00 - - - - -
Grade Beam Steel - - - - - -
Grid C1-F1 - - - - - -
Top & Bottem Bars 12 6 1 1 6.02 - - 36.12 - - -
Stirrups @ 200mm C/C Spacing 8 29 1 1 1.31 37.99 - - - - -
Grid F1-G'1 - - - - - -
Top & Bottem Bars 12 6 1 1 6.02 - - 36.12 - - -
Stirrups @ 200mm C/C Spacing 8 29 1 1 1.31 37.99 - - - - -
Grid G'1-H1 - - - - - -
Top & Bottem Bars 12 6 1 1 3.41 - - 20.46 - - -
Stirrups @ 200mm C/C Spacing 8 16 1 1 1.31 20.96 - - - - -
Grid A3-C3 - - - - - -
Top & Bottem Bars 12 6 1 1 4.91 - - 29.46 - - -
Page 115
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups @ 200mm C/C Spacing 8 24 1 1 1.31 31.44 - - - - -
Grid H3-K3 - - - - - -
Top & Bottem Bars 12 6 1 1 4.91 - - 29.46 - - -
Stirrups @ 200mm C/C Spacing 8 24 1 1 1.31 31.44 - - - - -
Grid B5-J5 - - - - - -
Top & Bottem Bars 12 6 1 1 21.91 - - 131.46 - - -
Stirrups @ 200mm C/C Spacing 8 109 1 1 1.31 142.79 - - - - -
Grid A3-A4 & K3-K4 - - - - - -
Top & Bottem Bars 12 6 1 2 3.41 - - 40.92 - - -
Stirrups @ 200mm C/C Spacing 8 16 1 2 1.31 41.92 - - - - -
Grid B4-B5 & J4-J5 - - - - - -
Top & Bottem Bars 12 6 1 2 10.43 - - 125.16 - - -
Stirrups @ 200mm C/C Spacing 8 51 1 2 1.31 133.62 - - - - -
Grid C1-C3 - - - - - -
Top & Bottem Bars 12 6 1 1 9.22 - - 55.32 - - -
Stirrups @ 200mm C/C Spacing 8 45 1 1 1.31 58.95 - - - - -
Grid H1-H2 - - - - - -
Top & Bottem Bars 12 6 1 1 6.13 - - 36.78 - - -
Stirrups @ 200mm C/C Spacing 8 30 1 1 1.31 39.30 - - - - -
Grid H2-H3 - - - - - -
Top & Bottem Bars 12 6 1 1 3.31 - - 19.86 - - -
Stirrups @ 200mm C/C Spacing 8 16 1 1 1.31 20.96 - - - - -
Plinth Beam Steel - - - - - -
Grid C1-F1,PB5 - - - - - -
Top & Bottem Bars 12 6 1 1 6.02 - - 36.12 - - -
Stirrups @ 175mm C/C Spacing 8 33 1 1 1.31 43.23 - - - - -
Grid F1-G'1,PB3 - - - - - -
Top & Bottem Bars 16 4 1 1 6.02 - - - 24.08 - -
Extra Bars at End Support 16 2 1 1 4.13 - - - 8.26 - -
Extra Bars at Mid Span 16 2 1 1 4.18 - - - 8.36 - -
Stirrups @ 150mm C/C Spacing 8 26 1 1 1.31 34.06 - - - - -
Stirrups @ 200mm C/C Spacing 8 11 1 1 1.31 14.41 - - - - -
Spacer Bars 25 5 1 1 0.20 - - - - - 1.00
Grid G'1-H1,PB5 - - - - - -
Top & Bottem Bars 12 6 1 1 3.41 - - 20.46 - - -
Stirrups @ 175mm C/C Spacing 8 18 1 1 1.31 23.58 - - - - -
Grid b/w 1-2 & C-D,PB6 - - - - - -
Top & Bottem Bars 12 5 1 2 3.34 - - 33.40 - - -
Stirrups @ 175mm C/C Spacing 8 18 1 2 1.17 42.12 - - - - -
Page 116
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid b/w 1-2 & G'-H,PB6 - - - - - -
Top & Bottem Bars 12 5 1 1 3.34 - - 16.70 - - -
Stirrups @ 175mm C/C Spacing 8 18 1 1 1.17 21.06 - - - - -
Grid C2-F2,PB5 - - - - - -
Top & Bottem Bars 12 6 1 1 6.41 - - 38.46 - - -
Stirrups @ 175mm C/C Spacing 8 36 1 1 1.31 47.16 - - - - -
Grid F2-G'2,PB2 - - - - - -
Top & Bottem Bars 16 6 1 1 7.11 - - - 42.66 - -
Extra Bars at End Support 16 2 1 1 4.85 - - - 9.70 - -
Extra Bars at Mid Span 16 2 1 1 5.00 - - - 10.00 - -
Stirrups @ 150mm C/C Spacing 8 31 1 1 1.31 40.61 - - - - -
Stirrups @ 200mm C/C Spacing 8 13 1 1 1.31 17.03 - - - - -
Spacer Bars 25 6 1 1 0.20 - - - - - 1.20
Grid G'2-H2,PB3 - - - - - -
Top & Bottem Bars 16 4 1 1 3.78 - - - 15.12 - -
Extra Bars at End Support 16 2 1 1 2.65 - - - 5.30 - -
Extra Bars at Mid Span 16 2 1 1 2.50 - - - 5.00 - -
Stirrups @ 150mm C/C Spacing 8 16 1 1 1.31 20.96 - - - - -
Stirrups @ 200mm C/C Spacing 8 7 1 1 1.31 9.17 - - - - -
Spacer Bars 25 6 1 1 0.20 - - - - - 1.20
Grid A3-C3,PB3 - - - - - -
Top & Bottem Bars 16 4 1 1 4.91 - - - 19.64 - -
Extra Bars at End Support 16 2 1 1 3.39 - - - 6.78 - -
Extra Bars at Mid Span 16 2 1 1 3.35 - - - 6.70 - -
Stirrups @ 150mm C/C Spacing 8 21 1 1 1.31 27.51 - - - - -
Stirrups @ 200mm C/C Spacing 8 9 1 1 1.31 11.79 - - - - -
Spacer Bars 25 5 1 1 0.20 - - - - - 1.00
Grid D3-H3,PB3 - - - - - -
Top & Bottem Bars 16 4 1 1 11.64 - - - 46.56 - -
Extra Bars at End Support 16 2 1 1 1.31 - - - 2.62 - -
Extra Bars at Mid Span 16 2 1 1 1.31 - - - 2.62 - -
Stirrups @ 150mm C/C Spacing 8 51 1 1 7.85 400.35 - - - - -
Stirrups @ 200mm C/C Spacing 8 21 1 1 8.40 176.40 - - - - -
Spacer Bars 25 6 1 1 0.20 - - - - - 1.20
Grid H3-K3,PB3 - - - - - -
Top & Bottem Bars 16 4 1 1 4.91 - - - 19.64 - -
Extra Bars at End Support 16 2 1 1 1.31 - - - 2.62 - -
Extra Bars at Mid Span 16 2 1 1 1.31 - - - 2.62 - -
Stirrups @ 150mm C/C Spacing 8 21 1 1 3.39 71.19 - - - - -
Page 117
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups @ 200mm C/C Spacing 8 9 1 1 3.35 30.15 - - - - -
Spacer Bars 25 5 1 1 0.20 - - - - - 1.00
Grid A4-C4 & H4-K4,PB4 - - - - - -
Top & Bottem Bars 16 4 1 2 4.84 - - - 38.72 - -
Extra Bars at End Support 16 1 1 2 3.32 - - - 6.64 - -
Extra Bars at Mid Span 16 1 1 2 3.35 - - - 6.70 - -
Stirrups @ 150mm C/C Spacing 8 21 1 2 1.17 49.14 - - - - -
Stirrups @ 200mm C/C Spacing 8 9 1 2 1.17 21.06 - - - - -
Grid C4-E4 & G4-H4,PB2 - - - - - -
Top & Bottem Bars 16 6 1 2 5.45 - - - 65.40 - -
Extra Bars at End Support 16 2 1 2 3.75 - - - 15.00 - -
Extra Bars at Mid Span 16 2 1 2 3.75 - - - 15.00 - -
Stirrups @ 150mm C/C Spacing 8 23 1 2 1.31 60.26 - - - - -
Stirrups @ 200mm C/C Spacing 8 10 1 2 1.31 26.20 - - - - -
Spacer Bars 25 5 1 2 0.20 - - - - - 2.00
Grid E4-G4,PB1 - - - - - -
Top Bars 16 2 1 1 4.97 - - - 9.94 - -
Bottem Bars 20 2 1 1 4.97 - - - - 9.94 -
Extra Bars at End Support 20 2 1 1 3.48 - - - - 6.96 -
Extra Bars at Mid Span 16 2 1 1 3.28 - - - 6.56 - -
Stirrups @ 150mm C/C Spacing 8 21 1 1 1.61 33.81 - - - - -
Stirrups @ 200mm C/C Spacing 8 9 1 1 1.61 14.49 - - - - -
Spacer Bars 25 5 1 1 0.20 - - - - - 1.00
Grid B5-J5,PB4 - - - - - -
Top & Bottem Bars 16 4 1 1 21.84 - - - 87.36 - -
Extra Bars at End Support 16 1 1 1 14.54 - - - 14.54 - -
Extra Bars at Mid Span 16 1 1 1 16.10 - - - 16.10 - -
Stirrups @ 150mm C/C Spacing 8 96 1 1 1.17 112.32 - - - - -
Stirrups @ 200mm C/C Spacing 8 38 1 1 1.17 44.46 - - - - -
Grid A3-A4 & K3-K4, PB6 - - - - - -
Top & Bottem Bars 12 5 1 2 3.34 - - 33.40 - - -
Stirrups @ 175mm C/C Spacing 8 18 1 2 1.17 42.12 - - - - -
Grid B4-B5 & J4-J5,PB1 - - - - - -
Top Bars 16 2 1 2 10.58 - - - 42.32 - -
Bottem Bars 20 2 1 2 10.58 - - - - 42.32 -
Extra Bars at End Support 20 2 1 2 7.19 - - - - 28.76 -
Extra Bars at Mid Span 16 2 1 2 7.49 - - - 29.96 - -
Stirrups @ 150mm C/C Spacing 8 45 1 2 1.61 144.90 - - - - -
Stirrups @ 200mm C/C Spacing 8 18 1 2 1.61 57.96 - - - - -
Page 118
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Spacer Bars 25 7 1 2 0.20 - - - - - 2.80
Grid C1-C4 &,PB2 - - - - - -
Top & Bottem Bars 16 6 1 1 11.17 - - - 67.02 - -
Extra Bars at End Support 16 2 1 1 7.53 - - - 15.06 - -
Extra Bars at Mid Span 16 2 1 1 8.04 - - - 16.08 - -
Stirrups @ 150mm C/C Spacing 8 49 1 1 1.31 64.19 - - - - -
Stirrups @ 200mm C/C Spacing 8 20 1 1 1.31 26.20 - - - - -
Spacer Bars 25 8 1 1 0.20 - - - - - 1.60
Grid D1-D4,PB2 - - - - - -
Top & Bottem Bars 16 6 1 1 11.27 - - - 67.62 - -
Extra Bars at End Support 16 2 1 1 7.59 - - - 15.18 - -
Extra Bars at Mid Span 16 2 1 1 8.12 - - - 16.24 - -
Stirrups @ 150mm C/C Spacing 8 49 1 1 1.31 64.19 - - - - -
Stirrups @ 200mm C/C Spacing 8 20 1 1 1.31 26.20 - - - - -
Spacer Bars 25 7 1 1 0.20 - - - - - 1.40
Grid F2-F4,PB1 - - - - - -
Top Bars 16 2 1 1 6.19 - - - 12.38 - -
Bottem Bars 20 2 1 1 6.19 - - - - 12.38 -
Extra Bars at End Support 20 2 1 1 4.29 - - - - 8.58 -
Extra Bars at Mid Span 16 2 1 1 4.19 - - - 8.38 - -
Stirrups @ 150mm C/C Spacing 8 26 1 1 1.61 41.86 - - - - -
Stirrups @ 200mm C/C Spacing 8 11 1 1 1.61 17.71 - - - - -
Spacer Bars 25 6 1 1 0.20 - - - - - 1.20
Grid G2-G3,PB6 - - - - - -
Top & Bottem Bars 12 5 1 1 3.24 - - 16.20 - - -
Stirrups @ 175mm C/C Spacing 8 18 1 1 1.17 21.06 - - - - -
Grid G'1-G'2,PB3 - - - - - -
Top & Bottem Bars 16 4 1 1 5.91 - - - 23.64 - -
Extra Bars at End Support 16 2 1 1 4.05 - - - 8.10 - -
Extra Bars at Mid Span 16 2 1 1 4.10 - - - 8.20 - -
Stirrups @ 150mm C/C Spacing 8 26 1 1 1.31 34.06 - - - - -
Stirrups @ 200mm C/C Spacing 8 11 1 1 1.31 14.41 - - - - -
Spacer Bars 25 5 1 1 0.20 - - - - - 1.00
Grid G'2-G'4,PB1 - - - - - -
Top Bars 16 2 1 1 6.19 - - - 12.38 - -
Bottem Bars 20 2 1 1 6.19 - - - - 12.38 -
Extra Bars at End Support 20 2 1 1 4.29 - - - - 8.58 -
Extra Bars at Mid Span 16 2 1 1 4.19 - - - 8.38 - -
Stirrups @ 150mm C/C Spacing 8 26 1 1 1.61 41.86 - - - - -
Page 119
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups @ 200mm C/C Spacing 8 11 1 1 1.61 17.71 - - - - -
Spacer Bars 25 5 1 1 0.20 - - - - - 1.00
Grid H1-H2,PB3 - - - - - -
Top & Bottem Bars 16 4 1 1 6.13 - - - 24.52 - -
Extra Bars at End Support 16 2 1 1 4.20 - - - 8.40 - -
Extra Bars at Mid Span 16 2 1 1 4.26 - - - 8.52 - -
Stirrups @ 150mm C/C Spacing 8 26 1 1 1.31 34.06 - - - - -
Stirrups @ 200mm C/C Spacing 8 11 1 1 1.31 14.41 - - - - -
Spacer Bars 25 6 1 1 0.20 - - - - - 1.20
Grid H2-H4,PB1 - - - - - -
Top Bars 16 2 1 1 6.19 - - - 12.38 - -
Bottem Bars 20 2 1 1 6.19 - - - - 12.38 -
Extra Bars at End Support 20 2 1 1 4.29 - - - - 8.58 -
Extra Bars at Mid Span 16 2 1 1 4.19 - - - 8.38 - -
Stirrups @ 150mm C/C Spacing 8 26 1 1 1.61 41.86 - - - - -
Stirrups @ 200mm C/C Spacing 8 11 1 1 1.61 17.71 - - - - -
Spacer Bars 25 7 1 1 0.20 - - - - - 1.40
Column Steel Upto Roof Top - - - - - -
C1 - - - - - -
Main Bars-1 25 4 1 8 3.75 - - - - - 120.00
Main Bars-2 20 4 1 8 3.75 - - - - 120.00 -
Rectangular Stirrups 8 20 1 8 1.49 238.40 - - - - -
Dimond Stirrups 8 20 1 8 1.25 200.00 - - - - -
C2 - - - - - -
Main Bars 20 8 1 4 3.75 - - - - 120.00 -
Rectangular Stirrups 8 20 1 4 1.49 119.20 - - - - -
Dimond Stirrups 8 20 1 4 1.25 100.00 - - - - -
C3 - - - - - -
Main Bars-1 20 4 1 2 3.75 - - - - 30.00 -
Main Bars-2 16 4 1 2 3.75 - - - 30.00 - -
Rectangular Stirrups 8 20 1 2 1.49 59.60 - - - - -
Dimond Stirrups 8 20 1 2 1.25 50.00 - - - - -
C4 - - - - - -
Main Bars 12 8 1 8 3.75 - - 240.00 - - -
Rectangular Stirrups 8 23 1 8 1.19 218.96 - - - - -
Dimond Stirrups 8 23 1 8 0.95 174.80 - - - - -
C5 - - - - - -
Main Bars-1 16 4 1 1 3.75 - - - 15.00 - -
Main Bars-2 12 4 1 1 3.75 - - 15.00 - - -
Page 120
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Rectangular Stirrups 8 23 1 1 1.19 27.37 - - - - -
Dimond Stirrups 8 23 1 1 0.95 21.85 - - - - -
C6 - - - - - -
Main Bars 16 8 1 1 3.75 - - - 30.00 - -
Rectangular Stirrups 8 20 1 1 1.19 23.80 - - - - -
Dimond Stirrups 8 20 1 1 0.95 19.00 - - - - -
C7 - - - - - -
Main Bars 12 6 1 2 3.75 - - 45.00 - - -
Circular Stirrups 8 20 1 2 0.85 34.00 - - - - -
C8 - - - - - -
Main Bars 12 6 1 1 1.50 - - 9.00 - - -
Circular Stirrups 8 9 1 1 0.62 5.58 - - - - -
Lintle Beam Steel - - - - - -
Grid C1-F1 - - - - - -
Top & Bottem Bars 10 4 1 1 6.22 - 24.88 - - - -
Stirrups @ 175mm C/C Spacing 8 36 1 1 0.71 25.56 - - - - -
Grid F1-G'1 - - - - - -
Top & Bottem Bars 10 4 1 1 5.72 - 22.88 - - - -
Stirrups @ 175mm C/C Spacing 8 33 1 1 0.71 23.43 - - - - -
Grid G'1-H1 - - - - - -
Top & Bottem Bars 10 4 1 1 3.11 - 12.44 - - - -
Stirrups @ 175mm C/C Spacing 8 18 1 1 0.71 12.78 - - - - -
Grid C2-F2 - - - - - -
Top & Bottem Bars 10 4 1 1 6.11 - 24.44 - - - -
Stirrups @ 175mm C/C Spacing 8 35 1 1 0.71 24.85 - - - - -
Grid F2-G'2 - - - - - -
Top & Bottem Bars 10 4 1 1 5.61 - 22.44 - - - -
Stirrups @ 175mm C/C Spacing 8 33 1 1 0.71 23.43 - - - - -
Grid G'2-H2 - - - - - -
Top & Bottem Bars 10 4 1 1 3.48 - 13.92 - - - -
Stirrups @ 175mm C/C Spacing 8 20 1 1 0.71 14.20 - - - - -
Grid A3-C3 - - - - - -
Top & Bottem Bars 10 4 1 1 4.61 - 18.44 - - - -
Stirrups @ 175mm C/C Spacing 8 27 1 1 0.71 19.17 - - - - -
Grid D3-K3 - - - - - -
Top & Bottem Bars 10 4 1 1 15.35 - 61.40 - - - -
Stirrups @ 175mm C/C Spacing 8 88 1 1 0.71 62.48 - - - - -
Grid A4-C4 - - - - - -
Top & Bottem Bars 10 4 1 1 4.61 - 18.44 - - - -
Page 121
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups @ 175mm C/C Spacing 8 27 1 1 0.71 19.17 - - - - -
Grid C4-D4 - - - - - -
Top & Bottem Bars 10 4 1 1 3.34 - 13.36 - - - -
Stirrups @ 175mm C/C Spacing 8 20 1 1 0.71 14.20 - - - - -
Grid G4-H4 - - - - - -
Top & Bottem Bars 10 4 1 1 5.16 - 20.62 - - - -
Stirrups @ 175mm C/C Spacing 8 30 1 1 0.71 21.30 - - - - -
Grid H4-K4 - - - - - -
Top & Bottem Bars 10 4 1 1 4.61 - 18.44 - - - -
Stirrups @ 175mm C/C Spacing 8 27 1 1 0.71 19.17 - - - - -
Grid B5-J5 - - - - - -
Top & Bottem Bars 10 4 1 1 21.38 - 85.52 - - - -
Stirrups @ 175mm C/C Spacing 8 123 1 1 0.71 87.33 - - - - -
Grid A3-A4 - - - - - -
Top & Bottem Bars 10 4 1 1 3.11 - 12.44 - - - -
Stirrups @ 175mm C/C Spacing 8 18 1 1 0.71 12.78 - - - - -
Grid B4-B5 - - - - - -
Top & Bottem Bars 10 4 1 1 9.98 - 39.92 - - - -
Stirrups @ 175mm C/C Spacing 8 58 1 1 0.71 41.18 - - - - -
Grid C1-C4 - - - - - -
Top & Bottem Bars 10 4 1 1 10.88 - 43.52 - - - -
Stirrups @ 175mm C/C Spacing 8 63 1 1 0.71 44.73 - - - - -
Grid D1-D4 - - - - - -
Top & Bottem Bars 10 4 1 1 10.97 - 43.88 - - - -
Stirrups @ 175mm C/C Spacing 8 63 1 1 0.71 44.73 - - - - -
Grid F2-F3 - - - - - -
Top & Bottem Bars 10 4 1 1 3.24 - 12.96 - - - -
Stirrups @ 175mm C/C Spacing 8 19 1 1 0.71 13.49 - - - - -
Grid G'1-G'2 - - - - - -
Top & Bottem Bars 10 4 1 1 5.61 - 22.44 - - - -
Stirrups @ 175mm C/C Spacing 8 33 1 1 0.71 23.43 - - - - -
Grid G'2-G'4 - - - - - -
Top & Bottem Bars 10 4 1 1 5.74 - 22.96 - - - -
Stirrups @ 175mm C/C Spacing 8 33 1 1 0.71 23.43 - - - - -
Grid H1-H2 - - - - - -
Top & Bottem Bars 10 4 1 1 5.83 - 23.32 - - - -
Stirrups @ 175mm C/C Spacing 8 34 1 1 0.71 24.14 - - - - -
Grid H2-H4 - - - - - -
Top & Bottem Bars 10 4 1 1 5.74 - 22.96 - - - -
Page 122
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups @ 175mm C/C Spacing 8 33 1 1 0.71 23.43 - - - - -
Grid J4-J5 - - - - - -
Top & Bottem Bars 10 4 1 1 9.98 - 39.92 - - - -
Stirrups @ 175mm C/C Spacing 8 58 1 1 0.71 41.18 - - - - -
Grid K3-K4 - - - - - -
Top & Bottem Bars 10 4 1 1 3.11 - 12.44 - - - -
Stirrups @ 175mm C/C Spacing 8 18 1 1 0.71 12.78 - - - - -
Chejja Steel - - - - - -
W - - - - - -
Main Bars 8 15 1 12 1.31 235.80 - - - - -
Distribution Bars 8 3 1 12 2.10 75.60 - - - - -
D - - - - - -
Main Bars 8 11 1 2 1.31 28.82 - - - - -
Distribution Bars 8 3 1 2 1.50 9.00 - - - - -
D - - - - - -
Main Bars 8 21 1 2 1.31 55.02 - - - - -
Distribution Bars 8 3 1 2 2.96 17.76 - - - - -
GD - - - - - -
Main Bars 8 21 1 1 1.31 27.51 - - - - -
Distribution Bars 8 3 1 1 2.96 8.88 - - - - -
W.C & Bath - - - - - -
Main Bars 8 21 1 1 1.31 27.51 - - - - -
Distribution Bars 8 3 1 1 2.96 8.88 - - - - -
Loft's Steel - - - - - -
Store - - - - - -
Main Bars 8 62 1 1 1.31 81.22 - - - - -
Distribution Bars 8 3 1 1 9.06 27.18 - - - - -
Dry Store - - - - - -
Main Bars 8 25 1 1 1.31 32.75 - - - - -
Distribution Bars 8 3 1 1 3.80 11.40 - - - - -
Dish Store - - - - - -
Main Bars 8 75 1 1 1.31 98.25 - - - - -
Distribution Bars 8 3 1 1 11.00 33.00 - - - - -
P.Store - - - - - -
Main Bars 8 31 1 1 1.31 40.61 - - - - -
Distribution Bars 8 3 1 1 4.40 13.20 - - - - -
Pantry - - - - - -
Main Bars 8 55 1 1 1.31 72.05 - - - - -
Distribution Bars 8 3 1 1 8.00 24.00 - - - - -
Page 123
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Total Length In mts 6,702.22 2,140.93 2,114.51 1,117.98 747.26 246.00
Unit Wt/mt 0.395 0.617 0.888 1.580 2.46 3.858
Total Reinforcement Qty 2,647.38 1,320.95 1,877.68 1,766.41 1,838.26 949.07 10,399.75 KG'S
Total Weight Say MT 10.40 MT
Page 124
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:-Principal Quarters
Ground Floor RA Bill-01
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2-2.2 : Earthwork excavation for foundation of buildings, water supply, sanitary lines and electrical
conduits either in pits or in trenches 1.5m and above in width, in hard soil not exceeding 1.5 m. in depth
4 2.4 including dressing the bottom and sides of pits and trenches, stacking the excavated soil clear from edges of
excavation with lead upto 50 m. after breaking of clods complete as per specifications. specification. No. KBS
2.1(b) / 2.3.5
Footing Earth work Excavation
Grid A6-F3 1 2.00 1.80 0.35 1.26
Grid A7-F2 1 2.20 2.00 0.30 1.32
Grid A8-F3 1 2.00 1.80 0.40 1.44
Grid B2-F4 1 1.80 1.80 0.30 0.97
Grid B3-F3 1 2.00 1.80 0.35 1.26
Grid B5-F2 1 2.20 2.00 0.30 1.32
Grid D1-F4 1 1.80 1.80 0.35 1.13
Grid D3-F3 1 2.00 1.80 0.30 1.08
Grid D5-F2 1 2.20 2.00 0.30 1.32
Grid D7-F1 1 2.60 2.40 0.35 2.18
Grid D8-F2 1 2.20 2.00 0.35 1.54
Grid E4-F3 1 2.00 1.80 0.40 1.44
Grid F8-F4 1 1.80 1.80 0.30 0.97
Grid G1-F4 1 1.80 1.80 0.35 1.13
Grid G3-F4 1 1.80 1.80 0.30 0.97
Page 125
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid G5-F3 1 2.00 1.80 0.30 1.08
Grid G7-F3 1 2.00 1.80 0.35 1.26
Earth Work For SSM
Grid A6-A8 1 4.78 1.15 0.30 1.65
Grid B3-B6 1 3.61 1.15 0.30 1.25
Grid D3-D4 1 0.35 1.15 0.30 0.12
Grid E4-E5 1 0.58 1.15 0.30 0.20
Grid F7-F8 1 2.58 1.15 0.30 0.89
Grid G5-G7 1 2.58 1.15 0.30 0.89
Grid B3-D3 1 4.38 1.15 0.30 1.51
Grid D4-E4 1 3.39 1.15 0.30 1.17
Grid E5-G5 1 2.67 1.15 0.30 0.92
Grid A6-B6 1 2.78 1.15 0.30 0.96
Grid F7-G7 1 1.80 1.15 0.30 0.62
Grid A8-F8 1 9.12 1.15 0.30 3.15
Deductions 0.00
Grid A6-A8 -1 2.85 1.15 0.30 -0.98
Grid B3-B6 -1 1.05 1.15 0.30 -0.36
Grid D3-D4 -1 0.43 1.15 0.30 -0.15
Grid E4-E5 -1 0.33 1.15 0.30 -0.11
Grid F7-F8 -1 0.65 1.15 0.30 -0.22
Grid G5-G7 -1 0.65 1.15 0.30 -0.22
Grid B3-D3 -1 3.05 1.15 0.30 -1.05
Grid D4-E4 -1 1.58 1.15 0.30 -0.54
Grid E5-G5 -1 1.58 1.15 0.30 -0.54
Grid A6-B6 -1 1.58 1.15 0.30 -0.54
Grid F7-G7 -1 1.58 1.15 0.30 -0.54
Page 126
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A8-F8 -1 5.45 1.15 0.30 -1.88
Total Qty 27.85 Cum
KSRB 2-2.4 : Excavation 1.5m and above in width in soft rock without blasting for foundation of buildings, water
supply, sanitary lines and electrical conduits either in pits or in trenches not exceeding 1.5 m. in depth, stacking
5 2.6
the excavated stuff from edges of excavation with lead upto 50m including cost of explosives, labour and HOM
of equipment complete as per specifications. specification. No. KBS 2.1.C / 2.9.4 / 2.18 / 2.19
Footing Earth work Excavation
Grid A6-F3 1 2.00 1.80 1.45 5.22
Grid A7-F2 1 2.20 2.00 1.50 6.60
Grid A8-F3 1 2.00 1.80 1.40 5.04
Grid B2-F4 1 1.80 1.80 1.50 4.86
Grid B3-F3 1 2.00 1.80 1.45 5.22
Grid B5-F2 1 2.20 2.00 1.50 6.60
Grid D1-F4 1 1.80 1.80 1.45 4.70
Grid D3-F3 1 2.00 1.80 1.50 5.40
Grid D5-F2 1 2.20 2.00 1.50 6.60
Grid D7-F1 1 2.60 2.40 1.45 9.05
Grid D8-F2 1 2.20 2.00 1.45 6.38
Grid E4-F3 1 2.00 1.80 1.40 5.04
Grid F8-F4 1 1.80 1.80 1.50 4.86
Grid G1-F4 1 1.80 1.80 1.45 4.70
Grid G3-F4 1 1.80 1.80 1.50 4.86
Grid G5-F3 1 2.00 1.80 1.50 5.40
Grid G7-F3 1 2.00 1.80 1.45 5.22
Earth Work For SSM
Grid A6-A8 1 4.78 1.15 0.45 2.47
Grid B3-B6 1 3.61 1.15 0.45 1.87
Grid D3-D4 1 0.35 1.15 0.45 0.18
Page 127
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid E4-E5 1 0.58 1.15 0.45 0.30
Grid F7-F8 1 2.58 1.15 0.45 1.34
Grid G5-G7 1 2.58 1.15 0.45 1.34
Grid B3-D3 1 4.38 1.15 0.45 2.27
Grid D4-E4 1 3.39 1.15 0.45 1.76
Grid E5-G5 1 2.67 1.15 0.45 1.38
Grid A6-B6 1 2.78 1.15 0.45 1.44
Grid F7-G7 1 1.80 1.15 0.45 0.93
Grid A8-F8 1 9.12 1.15 0.45 4.72
Deductions
Grid A6-A8 -1 2.85 1.15 0.45 -1.47
Grid B3-B6 -1 1.05 1.15 0.45 -0.54
Grid D3-D4 -1 0.43 1.15 0.45 -0.22
Grid E4-E5 -1 0.33 1.15 0.45 -0.17
Grid F7-F8 -1 0.65 1.15 0.45 -0.34
Grid G5-G7 -1 0.65 1.15 0.45 -0.34
Grid B3-D3 -1 3.05 1.15 0.45 -1.58
Grid D4-E4 -1 1.58 1.15 0.45 -0.82
Grid E5-G5 -1 1.58 1.15 0.45 -0.82
Grid A6-B6 -1 1.58 1.15 0.45 -0.82
Grid F7-G7 -1 1.58 1.15 0.45 -0.82
Grid A8-F8 -1 5.45 1.15 0.45 -2.82
Total Qty 104.99 Cum
Page 128
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB-3.2: Providing and injecting chemical emulsion for Preconstructional Anti-Termite Treatment, creating
continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top
surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints,
7 3.2 over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits, with
chloropyriphos emulsifiable concentrates of 20% concentration, including cost of chemical, diluting in water to
one percent concentration, labour, HOM of equipments, complete as per specifications. (Plinth area of the
building at ground floor only shall be measured ) Specification No. KBS : 3.2.6 / 3.2.7
Anti-Termite Treatment
Grid A7-A8,F7-F8 1 3.73 8.0 29.73
Grid A6-A7,B6-B7 1 2.20 2.1 4.62
Grid B'5-B'7,G5-G7 1 3.70 6.5 24.12
Grid B3-B5,D3-D5 1 3.23 3.2 10.43
Grid D4-D5,E4-E5 1 1.73 2.2 3.88
Total Qty 72.78 Sqm
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 with OPC cement @ 220kgs,
with 40mm and down size graded granite metal coarse aggregates @0.892cum and fine aggregates @
8 4.2 0.465cum machine mixed, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted,
in foundation including cost of all materials, labour, HOM of machinery, curing complete as per specifications.
Specification No. KBS 4.1, 4.2
Footing PCC
F1 1 2.20 2.00 0.10 0.44
F2 4 1.80 1.60 0.10 1.15
F3 7 1.60 1.40 0.10 1.57
F4 5 1.40 1.40 0.10 0.98
PCC Under SSM
Grid A6-A8 1 4.78 0.75 0.10 0.36
Grid B3-B6 1 3.61 0.75 0.10 0.27
Grid D3-D4 1 0.35 0.75 0.10 0.03
Grid E4-E5 1 0.58 0.75 0.10 0.04
Grid F7-F8 1 2.58 0.75 0.10 0.19
Page 129
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid G5-G7 1 2.58 0.75 0.10 0.19
Grid B3-D3 1 4.38 0.75 0.10 0.33
Grid D4-E4 1 3.39 0.75 0.10 0.25
Grid E5-G5 1 2.67 0.75 0.10 0.20
Grid A6-B6 1 2.78 0.75 0.10 0.21
Grid F7-G7 1 1.80 0.75 0.10 0.14
Grid A8-F8 1 9.12 0.75 0.10 0.68
Deductions
Grid A6-A8 -1 2.85 0.75 0.10 -0.21
Grid B3-B6 -1 1.05 0.75 0.10 -0.08
Grid D3-D4 -1 0.43 0.75 0.10 -0.03
Grid E4-E5 -1 0.33 0.75 0.10 -0.02
Grid F7-F8 -1 0.65 0.75 0.10 -0.05
Grid G5-G7 -1 0.65 0.75 0.10 -0.05
Grid B3-D3 -1 3.05 0.75 0.10 -0.23
Grid D4-E4 -1 1.58 0.75 0.10 -0.12
Grid E5-G5 -1 1.58 0.75 0.10 -0.12
Grid A6-B6 -1 1.58 0.75 0.10 -0.12
Grid F7-G7 -1 1.58 0.75 0.10 -0.12
Grid A8-F8 -1 5.45 0.75 0.10 -0.41
PCC Under Plinth Beam
Grid B5-B7 1 3.50 0.45 0.10 0.16
Grid C7-C8 1 3.50 0.45 0.10 0.16
Grid D7-D8 1 3.50 0.45 0.10 0.16
Grid B5-D5 1 3.00 0.45 0.10 0.14
Grid A7-D7 1 4.48 0.45 0.10 0.20
Grid D7-G7 1 3.32 0.45 0.10 0.15
Page 130
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Flooring PCC
Verandah 1 1.50 2.00 0.10 0.30
Kitchen 1 3.00 3.00 0.10 0.90
Utility 1 4.59 1.46 0.10 0.67
Dining 1 3.50 2.63 0.10 0.92
Living 1 3.50 3.77 0.10 1.32
Ensuit 1 2.00 1.90 0.10 0.38
Bed Room 2 3.60 3.00 0.10 2.16
C.Toilet 1 3.60 1.50 0.10 0.54
Total Qty 13.63 Cum
KSRB 5.2-3 : Providing and constructing granite / trap / basalt size stone masonry in foundation cement mortar
9 5.6 1:6, stone hammerd dressed in courses not less than 20 cms high, bond stones at two m. apart in each course
including cost of materials, labour, curing complete as per specifications. KBS 5.1.13
SSM in Foundation
Grid A6-A8 1 4.78 0.60 0.65 1.86
Grid B3-B6 1 3.61 0.60 0.65 1.41
Grid D3-D4 1 0.35 0.60 0.65 0.14
Grid E4-E5 1 0.58 0.60 0.65 0.23
Grid F7-F8 1 2.58 0.60 0.65 1.01
Grid G5-G7 1 2.58 0.60 0.65 1.01
Grid B3-D3 1 4.38 0.60 0.65 1.71
Grid D4-E4 1 3.39 0.60 0.65 1.32
Grid E5-G5 1 2.67 0.60 0.65 1.04
Grid A6-B6 1 2.78 0.60 0.65 1.08
Grid F7-G7 1 1.80 0.60 0.65 0.70
Grid A8-F8 1 9.12 0.60 0.65 3.56
Page 131
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
SSM Over Footings
Grid A6-A8 1 2.85 0.60 0.65 1.11
Grid B3-B6 1 1.05 0.60 0.65 0.41
Grid D3-D4 1 0.43 0.60 0.70 0.18
Grid E4-E5 1 0.33 0.60 0.70 0.14
Grid F7-F8 1 0.65 0.60 0.75 0.29
Grid G5-G7 1 0.65 0.60 0.70 0.27
Grid B3-D3 1 3.05 0.60 0.70 1.28
Grid D4-E4 1 1.58 0.60 0.70 0.66
Grid E5-G5 1 1.58 0.60 0.70 0.66
Grid A6-B6 1 1.58 0.60 0.70 0.66
Grid F7-G7 1 1.58 0.60 0.70 0.66
Grid A8-F8 1 5.45 0.60 0.70 2.29
Deductions Above GL
Grid A6-C2 -1 0.30 0.23 1.35 -0.09 Grid A6-F3
Grid A7-C3 -1 0.38 0.23 1.30 -0.11 Grid A7-F2
Grid A8-C3 -1 0.38 0.23 1.35 -0.12 Grid A8-F3
Grid B2-C2 -1 0.30 0.23 1.40 -0.10 Grid B2-F4
Grid B3-C2 -1 0.30 0.23 1.35 -0.09 Grid B3-F3
Grid B5-C2 -1 0.30 0.23 1.30 -0.09 Grid B5-F2
Grid D3-C2 -1 0.30 0.23 1.35 -0.09 Grid D3-F3
Grid D8-C2 -1 0.30 0.23 1.30 -0.09 Grid D8-F2
Grid E4-C2 -1 0.30 0.23 1.35 -0.09 Grid E4-F3
Grid F8-C2 -1 0.30 0.23 1.40 -0.10 Grid F8-F4
Grid G5-C2 -1 0.30 0.23 1.35 -0.09 Grid G5-F3
Grid G7-C2 -1 0.30 0.23 1.35 -0.09 Grid G7-F3
Total Qty 22.52 Cum
Page 132
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 5.3-3 : Providing and constructing granite / trap / basalt size stone masonry in basement with cement
10 5.9 mortar 1:6, edges of stones chistle dressed in courses not less than 15 cms high, bond stones at two m. apart in
each course including cost of materials, labour, curing complete as per specifications. KBS 5.1.13
SSM in Basement
Grid A6-A8 1 4.78 0.45 0.45 0.97 ###
Grid B3-B6 1 3.61 0.45 0.20 0.32 ###
Grid D3-D4 1 0.35 0.45 0.15 0.02 ###
Grid E4-E5 1 0.58 0.45 0.20 0.05 ###
Grid F7-F8 1 2.58 0.45 0.45 0.52 ###
Grid G5-G7 1 2.58 0.45 0.30 0.35 ###
Grid B3-D3 1 4.38 0.45 0.15 0.30 ###
Grid D4-E4 1 3.39 0.45 0.20 0.31 ###
Grid E5-G5 1 2.67 0.45 0.20 0.24 ###
Grid A6-B6 1 2.78 0.45 0.30 0.37 ###
Grid F7-G7 1 1.80 0.45 0.35 0.28 ###
Grid A8-F8 1 9.12 0.45 0.55 2.26 ###
Deductions
Grid A6-C2 -1 0.30 0.23 0.30 -0.02 Grid A6-F3
Grid A7-C3 -1 0.38 0.23 0.35 -0.03 Grid A7-F2
Grid A8-C3 -1 0.38 0.23 0.55 -0.05 Grid A8-F3
Grid B2-C2 -1 0.30 0.23 0.05 0.00 Grid B2-F4
Grid B3-C2 -1 0.30 0.23 0.15 -0.01 Grid B3-F3
Grid B5-C2 -1 0.30 0.23 0.20 -0.01 Grid B5-F2
Grid D3-C2 -1 0.30 0.23 0.15 -0.01 Grid D3-F3
Grid D8-C2 -1 0.30 0.23 0.55 -0.04 Grid D8-F2
Grid E4-C2 -1 0.30 0.23 0.20 -0.01 Grid E4-F3
Grid F8-C2 -1 0.30 0.23 0.55 -0.04 Grid F8-F4
Page 133
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid G5-C2 -1 0.30 0.23 0.20 -0.01 Grid G5-F3
Grid G7-C2 -1 0.30 0.23 0.35 -0.02 Grid G7-F3
Total Qty 5.73 Cum
KSRB 2.3 : Filling available excavated earth ( excluding rock ) in sides of foundations upto plinth in layers not
12 2.10 exceeding 20 cms. in depth, compacting each deposited layer by ramming after watering with lead upto 50 m.
and lift upto 1.5 m. including cost of all labour complete as per specifications. specification. No. KBS 2.9
Earth Filling in Sides of Foundation
Same As Hard Soil 27.85
Same As Soft Rock 104.99
Total Qty 132.84
Deductions
Pcc under Footings 13.63
Footing And Column concrete 20.05
Ssm in Foundation 22.52
Total Qty 56.19
Qty Required For Filling 76.65
Extra Qty Required For side Filling 48.80
Qty Available for Filling 27.85 Cum
KSRB 2.5 : Earthwork excavation ( in deposited soil ) and filling sides of foundation upto plinth in layers not
13 2.12 exceeding 20 cms. in depth, compacting each deposited layer by ramming after watering with all lead and lift
including cost of all labour complete as per specifications. specification. No. KBS 2.9.9 / 2.9.10.1 / 2.1.1
Earth Filling in Foundation
Grid A7-A8,F7-F8 1 3.73 8.0 1.00 29.73
Grid A6-A7,B6-B7 1 2.20 2.1 0.90 4.16
Grid B'5-B'7,G5-G7 1 3.70 6.5 0.85 20.51
Grid B3-B5,D3-D5 1 3.23 3.2 0.75 7.82
Grid D4-D5,E4-E5 1 1.73 2.2 0.75 2.91
Page 134
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Qty Required For side Filling 48.80
Total Qty 113.92 Cum
KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of design mix M20 with OPC cement @
320kgs, with 20mm and down size graded granite metal coarse aggregates @0.878cum and fine aggregtes @
0.459cum, with superplastisiser @3lts confirming to IS9103-1999 Reaffirmed-2008, machine mixed, concrete
laid in layers not exceeding 15 cms thick, vibrated for all works in foundation plinth and ground floor level for
14 4.11
roof slabs, staircase, lintles, retaining walls, return walls, walls ( any thickness ) including attached plasters,
columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed
blocks, anchor blocks, plain window cills, fillets etc., including cost of all materials, labour, HOM of machinery,
curing, complete as per specifications. Specification No. KBS 4.1, 4.6
Footing Concrete
F1 1 2.00 1.80 0.45 1.62
F2 4 1.60 1.40 0.40 3.58
F3 7 1.40 1.20 0.35 4.12
F4 5 1.20 1.20 0.30 2.16
Column Concrete Upto Plinth Top F Depth
Grid A6-C2 1 0.30 0.23 2.20 0.15 Grid A6-F3
Grid A7-C3 1 0.38 0.23 2.20 0.19 Grid A7-F2
Grid A8-C3 1 0.38 0.23 2.45 0.21 Grid A8-F3
Grid B2-C2 1 0.30 0.23 2.00 0.14 Grid B2-F4
Grid B3-C2 1 0.30 0.23 2.05 0.14 Grid B3-F3
Grid B5-C2 1 0.30 0.23 2.05 0.14 Grid B5-F2
Grid D1-C1 1 0.04 1.90 0.08 Grid D1-F4
Grid D3-C2 1 0.30 0.23 2.05 0.14 Grid D3-F3
Grid D5-C2 1 0.30 0.23 2.00 0.14 Grid D5-F2
Grid D7-C3 1 0.38 0.23 2.15 0.19 Grid D7-F1
Grid D8-C2 1 0.30 0.23 2.40 0.17 Grid D8-F2
Page 135
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid E4-C2 1 0.30 0.23 2.10 0.14 Grid E4-F3
Grid F8-C2 1 0.30 0.23 2.50 0.17 Grid F8-F4
Grid G1-C1 1 0.04 1.90 0.08 Grid G1-F4
Grid G3-C1 1 0.04 2.10 0.09 Grid G3-F4
Grid G5-C2 1 0.30 0.23 2.10 0.14 Grid G5-F3
Grid G7-C2 1 0.30 0.23 2.25 0.16 Grid G7-F3
Plinth Beam Concrete
Grid A6-A8,PB5 1 5.47 0.23 0.45 0.57
Grid B3-B5,PB5 1 2.86 0.23 0.45 0.30
Grid B5-B7,PB4 1 3.50 0.23 0.45 0.36
Grid C7-C8,PB4 1 3.50 0.23 0.45 0.36
Grid D3-D5,PB5 1 2.86 0.23 0.45 0.30
Grid D7-D8,PB5 1 3.50 0.23 0.45 0.36
Grid E4-E5,PB5 1 1.50 0.23 0.45 0.16
Grid F7-F8,PB5 1 3.43 0.23 0.45 0.36
Grid G5-G7,PB5 1 3.50 0.23 0.45 0.36
Grid B3-D3,PB5 1 2.93 0.23 0.45 0.30
Grid D4-E4,PB5 1 2.94 0.23 0.45 0.30
Grid B5-D5,PB3 1 3.00 0.23 0.45 0.31
Grid D5-G5,PB4 1 3.47 0.23 0.45 0.36
Grid A6-B6,PB5 1 1.33 0.23 0.45 0.14
Grid A7-D7,PB1 1 4.48 0.23 0.45 0.46
Grid D7-G7,PB4 1 3.32 0.23 0.45 0.34
Grid A8-D8,PB2 1 4.40 0.23 0.45 0.46
Grid D8-F8,PB4 1 2.89 0.23 0.45 0.30
Total Qty 20.05 Cum
Page 136
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 4.2.4 : Providing and laying in position reinforced cement concrete of mix M10 with OPC cement @ 220kgs,
with 20mm and down size graded granite metal coarse aggregates @0.792cum and fine aggregtes @ 0.465cum,
machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all works in foundation plinth
15 4.13 and ground floor level for roof slabs, staircase, lintles, retaining walls, return walls, walls ( any thickness )
including attached plasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses,
parapets, coping, bed blocks, anchor blocks, plain window cills, fillets etc., including cost of all materials, labour,
HOM of machinery, curing, complete as per specifications. Specification No. KBS 4.1, 4.6
Page 137
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid B5-D5 1 3.00 0.115 0.15 0.05
Grid C7'-D7' 1 1.51 0.115 0.15 0.03
Grid C7-C8 1 3.83 0.115 0.15 0.07
Grid D7-D8 1 3.83 0.115 0.15 0.07
KSRB
Total 4.2.10
Qty : Providing and laying in position reinforced cement concrete of design mix M20 with5.36 OPC cement
Cum @
24kgs, with 12mm and down size graded granite metal coarse aggregates @0.05175cum and fine aggregtes @
0.0345cum, with superplastisiser @0.225lts, machine mixed, well compacted for plain chajja of 7.5 cms. average
16 4.19
thickness, upto ground floor level, including cost of all materials, labour, HOM of machinery, finishing, curing,
complete but excluding cost of
Chejja's
reinforcement as per specifications. Specification No. KBS 4.1, 4.6
W 5 1.50 0.60 4.50
W1 2 0.90 0.60 1.08
W2 1 1.50 0.60 0.90
Total Qty 6.48 Sqm
KSRB 4-1.6 ; Providing and laying in position plain cement concrete of mix 1:2:4 with cement @ 240kgs, with
20mm and down size graded granite metal coarse aggregates @ 0.878 cum and fine aggregtes @ 0.53cum,
18 4.6 machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation, plinth and
cills, ncluding cost of all materials, labour, HOM of machinery, curing complete as per specifications.
Specification No. KBS 4.1, 4.2
Coping Concrete
Grid A6-A8 1 5.47 0.45 0.10 0.25
Grid B3-B5 1 2.86 0.45 0.10 0.13
Grid D3-D5 1 2.86 0.45 0.10 0.13
Grid E4-E5 1 1.50 0.45 0.10 0.07
Grid F7-F8 1 3.43 0.45 0.10 0.15
Grid G5-G7 1 3.50 0.45 0.10 0.16
Grid B3-D3 1 2.93 0.45 0.10 0.13
Grid D4-E4 1 2.94 0.45 0.10 0.13
Grid D5-G5 1 3.47 0.45 0.10 0.16
Grid A6-B6 1 1.33 0.45 0.10 0.06
Page 138
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A8-D8 1 4.40 0.45 0.10 0.20
Grid D8-F8 1 2.89 0.45 0.10 0.13
Cill Concrete
Grid A3-A8 1 5.47 0.23 0.075 0.09 ###
Grid B3-B5 1 2.56 0.23 0.075 0.04 ###
Grid B'5-B'7 1 3.50 0.23 0.075 0.06 ###
Grid D3-D5 1 2.86 0.23 0.075 0.05 ###
Grid E4-E5 1 1.50 0.23 0.075 0.03 ###
Grid F7-F8 1 3.43 0.23 0.075 0.06 ###
Grid G5-G7 1 3.50 0.23 0.075 0.06 ###
Grid A3-B3 1 1.63 0.23 0.075 0.03 ###
Grid B3-D3 1 2.93 0.23 0.075 0.05 ###
Grid D4-E4 1 1.94 0.23 0.075 0.03 ###
Grid D5-G5 1 3.47 0.23 0.075 0.06 ###
Grid A6-B6 1 1.33 0.23 0.075 0.02 ###
Grid A7-D7 1 4.56 0.23 0.075 0.08 ###
Grid D7-G7 1 3.47 0.23 0.075 0.06 ###
Grid A8-D8 1 4.56 0.23 0.075 0.08 ###
Grid D8-F8 1 2.89 0.23 0.075 0.05 ###
Grid B5-D5 1 3.00 0.115 0.075 0.03
Grid C7'-D7' 1 1.51 0.115 0.075 0.01
Grid C7-C8 1 3.83 0.115 0.075 0.03
Grid D7-D8 1 3.83 0.115 0.075 0.03
Deductions
MD -1 1.05 0.23 0.075 -0.02
D -3 0.90 0.23 0.075 -0.05
D1 -2 0.75 0.23 0.075 -0.03
Total Qty 2.56 Cum
Page 139
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
19 4.28 foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per
specificaitons. Specification No. KBS 4.6.2
Page 140
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A6-C2 1 1.06 2.20 2.33 Grid A6-F3
Grid A7-C3 1 1.22 2.20 2.68 Grid A7-F2
Grid A8-C3 1 1.22 2.45 2.99 Grid A8-F3
Grid B2-C2 1 1.06 2.00 2.12 Grid B2-F4
Grid B3-C2 1 1.06 2.05 2.17 Grid B3-F3
Grid B5-C2 1 1.06 2.05 2.17 Grid B5-F2
Grid D3-C2 1 1.06 2.05 2.17 Grid D3-F3
Grid D5-C2 1 1.06 2.00 2.12 Grid D5-F2
Grid D7-C3 1 1.22 2.15 2.62 Grid D7-F1
Grid D8-C2 1 1.06 2.40 2.54 Grid D8-F2
Grid E4-C2 1 1.06 2.10 2.23 Grid E4-F3
Grid F8-C2 1 1.06 2.50 2.65 Grid F8-F4
Grid G5-C2 1 1.06 2.10 2.23 Grid G5-F3
Grid G7-C2 1 1.06 2.25 2.39 Grid G7-F3
Columns Shuttering Upto Roof Top
C2 10 1.06 3.15 33.39
C3 1 1.06 1.65 1.75
C3 3 1.22 3.15 11.53
Total Qty 80.09 Sqm
KSRB 4-6.6 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
22 4.33 columns, pillars,post and struts, circular or curved in plan including cost of all materials, labour complete as per
specifications. Specification No. KBS 4.6.2
Page 141
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Columns Shuttering Upto Roof Top
C1 3 0.72 3.15 6.82
Total Qty 11.09 Sqm
KSRB 4-6.7 :Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
23 4.34 sides and soffits of beams, beam haunchings, cantilever girders, bressumers and lintels not exceeding 1m in
depth including cost of all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2
Lintle Beam Shuttering
Grid A3-A8 1 2 5.47 0.15 1.64 ###
Grid B3-B5 1 2 2.56 0.15 0.77 ###
Grid B'5-B'7 1 2 3.50 0.15 1.05 ###
Grid D3-D5 1 2 2.86 0.15 0.86 ###
Grid E4-E5 1 2 1.50 0.15 0.45 ###
Grid F7-F8 1 2 3.43 0.15 1.03 ###
Grid G5-G7 1 2 3.50 0.15 1.05 ###
Grid B3-D3 1 2 2.93 0.15 0.88 ###
Grid D4-E4 1 2 1.94 0.15 0.58 ###
Grid D5-G5 1 2 3.47 0.15 1.04 ###
Grid A6-B6 1 2 1.33 0.15 0.40 ###
Grid A7-D7 1 2 4.56 0.15 1.37 ###
Grid D7-G7 1 2 3.47 0.15 1.04 ###
Grid A8-D8 1 2 4.56 0.15 1.37 ###
Grid D8-F8 1 2 2.89 0.15 0.87 ###
Grid B5-D5 1 2 3.00 0.15 0.90
Grid C7'-D7' 1 2 1.51 0.15 0.45
Grid C7-C8 1 2 3.83 0.15 1.15
Grid D7-D8 1 2 3.83 0.15 1.15
Centering at Openings
MD 1 1 1.50 0.23 0.35
Page 142
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
D 3 1 0.90 0.23 0.62
D1 2 1 0.75 0.23 0.35
W 5 1 1.20 0.23 1.38
W1 2 1 0.60 0.23 0.28
W2 2 1 1.20 0.23 0.55
Openings 3 1 1.20 0.23 0.83
Total Qty 22.38 Sqm
KSRB 4-6.4 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
25 4.31 vertical surface such as walls at any thickness, including attached pilasters, buttresses, plinth and string courses
cost of all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2
Plinth Beam Shuttering
Grid A6-A8,PB5 1 2 5.47 0.45 4.92
Grid B3-B5,PB5 1 2 2.86 0.45 2.57
Grid B5-B7,PB4 1 2 3.50 0.45 3.15
Grid C7-C8,PB4 1 2 3.50 0.45 3.15
Grid D3-D5,PB5 1 2 2.86 0.45 2.57
Grid D7-D8,PB5 1 2 3.50 0.45 3.15
Grid E4-E5,PB5 1 2 1.50 0.45 1.35
Grid F7-F8,PB5 1 2 3.43 0.45 3.09
Grid G5-G7,PB5 1 2 3.50 0.45 3.15
Grid B3-D3,PB5 1 2 2.93 0.45 2.64
Grid D4-E4,PB5 1 2 2.94 0.45 2.65
Grid B5-D5,PB3 1 2 3.00 0.45 2.70
Grid D5-G5,PB4 1 2 3.47 0.45 3.12
Grid A6-B6,PB5 1 2 1.33 0.45 1.19
Grid A7-D7,PB1 1 2 4.48 0.45 4.03
Grid D7-G7,PB4 1 2 3.32 0.45 2.98
Page 143
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A8-D8,PB2 1 2 4.40 0.45 3.96
Grid D8-F8,PB4 1 2 2.89 0.45 2.60
Shuttering For PCC Under Plinth Beam
Grid B5-B7 1 2 3.50 0.10 0.70
Grid C7-C8 1 2 3.50 0.10 0.70
Grid D7-D8 1 2 3.50 0.10 0.70
Grid B5-D5 1 2 3.00 0.10 0.60
Grid A7-D7 1 2 4.48 0.10 0.90
Grid D7-G7 1 2 3.32 0.10 0.66
Shuttering For Coping Concrete
Grid A6-A8 1 2 5.47 0.10 1.09
Grid B3-B5 1 2 2.86 0.10 0.57
Grid D3-D5 1 2 2.86 0.10 0.57
Grid E4-E5 1 2 1.50 0.10 0.30
Grid F7-F8 1 2 3.43 0.10 0.69
Grid G5-G7 1 2 3.50 0.10 0.70
Grid B3-D3 1 2 2.93 0.10 0.59
Grid D4-E4 1 2 2.94 0.10 0.59
Grid D5-G5 1 2 3.47 0.10 0.69
Grid A6-B6 1 2 1.33 0.10 0.27
Grid A8-D8 1 2 4.40 0.10 0.88
Grid D8-F8 1 2 2.89 0.10 0.58
Cill Concrete Shuttering
Grid A3-A8 1 2 10.00 0.075 1.50 ###
Grid B3-B5 1 2 2.93 0.075 0.44 ###
Grid B'5-B'7 1 2 3.50 0.075 0.53 ###
Grid D3-D5 1 2 2.86 0.075 0.43 ###
Grid E4-E5 1 2 1.50 0.075 0.22 ###
Page 144
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F7-F8 1 2 3.43 0.075 0.51 ###
Grid G5-G7 1 2 3.50 0.075 0.53 ###
Grid A3-B3 1 2 1.63 0.075 0.24 ###
Grid B3-D3 1 2 2.93 0.075 0.44 ###
Grid D4-E4 1 2 1.94 0.075 0.29 ###
Grid D5-G5 1 2 3.47 0.075 0.52 ###
Grid A6-B6 1 2 1.33 0.075 0.20 ###
Grid A7-D7 1 2 4.56 0.075 0.68 ###
Grid D7-G7 1 2 3.47 0.075 0.52 ###
Grid A8-D8 1 2 4.56 0.075 0.68 ###
Grid D8-F8 1 2 2.89 0.075 0.43 ###
Grid B5-D5 1 2 3.00 0.075 0.45
Grid C7'-D7' 1 2 1.51 0.075 0.23
Grid C7-C8 1 2 3.83 0.075 0.57
Grid D7-D8 1 2 3.83 0.075 0.57
Deductions
MD -1 2 1.05 0.075 -0.16
D -3 2 0.90 0.075 -0.41
D1 -2 2 0.75 0.075 -0.22
Total Qty 73.95 Sqm
KSRB 4-6.10 :Providing and removing centering, shuttering, strutting, propping etc., for chajjas, corbels etc.,
26 4.37
including edges including cost of all materials, labour complete as per specifications. Specification No. KBS 4.6.2
Page 145
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Total Qty 8.68 Sqm
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending,
hooking, placing in position, lapping and / or welding wherever required, tying with binding wire and anchoring
28 4.46.2 to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be
measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Specification
No. KBS 4.6.3
Steel 2.82
Total Qty 2.82 Tonne
KSRB 6-1.3 : Providing and constructing burnt brick masonry for basement and superstructure with approved
quality of non-modular bricks of standard size of class designation 3.5N per Sqmm with cement mortar 1:6
29 6.3
including cost of materials, labour charges, scaffolding, curing complete as per specifications. Specification No.
KBS 6.2
BBM Upto Roof Level
Grid A3-A8,B4 1 5.47 0.23 2.625 3.30 ###
Grid B3-B5,B4 1 2.93 0.23 2.625 1.77 ###
Grid B'5-B'7,B3 1 3.50 0.23 2.545 2.05 ###
Grid D3-D5,B3 1 2.86 0.23 2.545 1.67 ###
Grid E4-E5,B4 1 1.50 0.23 2.625 0.91 ###
Grid F7-F8,B3 1 3.43 0.23 2.545 2.01 ###
Grid G5-G7,B4 1 3.50 0.23 2.625 2.11 ###
Grid A3-B3,CB1 1 1.63 0.23 2.545 0.95 ###
Grid B3-D3,B3 1 2.93 0.23 2.545 1.72 ###
Grid D4-E4,B4 1 1.94 0.23 2.625 1.17 ###
Grid D5-G5,B3 1 3.47 0.23 2.545 2.03 ###
Grid A6-B6,B4 1 1.33 0.23 2.625 0.80 ###
Grid A7-D7,B1 1 4.56 0.23 2.475 2.59 ###
Grid D7-G7,B2 1 3.47 0.23 2.545 2.03 ###
Grid A8-D8,B2 1 4.56 0.23 2.545 2.67 ###
Grid D8-F8,B3 1 2.89 0.23 2.545 1.69 ###
Page 146
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Deductions
MD -1 1.20 0.23 2.10 -0.58
D -2 0.90 0.23 2.10 -0.87
D1 -1 0.75 0.23 2.10 -0.36
W -5 1.20 0.23 1.20 -1.66
W1 -2 0.60 0.23 1.20 -0.33
W2 -1 1.20 0.23 0.90 -0.25
V -2 0.60 0.23 0.60 -0.17
Openings -2 1.20 0.23 2.10 -1.16
Total Qty 24.09 Cum
Providing RCC loft (atta) 7.5cms thick with cement concrete design mix M20 using clean granite or trap jelly of
36 4.54 20mm and down size with necessary reinforcements at 20cms centre to centre as per design including form
work, centring, curing, etc., complete (exclusive of cost of steel and fabrication charges).
Loft's
Bed Room-1 1 1.80 0.60 1.08
Bed Room-2 1 2.00 0.60 1.20
Total Qty 2.28 Sqm
Page 147
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Principal Quarters Steel
Ground Floor Steel Fabrication RA BILL NO - 01
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Principal Quarters
Footing Mat Steel
Footings-F1 - - - - - -
A-Bars 10 16 1 1 2.35 - 37.60 - - - -
B-Bars 10 17 1 1 2.15 - 36.55 - - - -
Footings-F2 - - - - - -
A-Bars 10 11 1 4 1.90 - 83.60 - - - -
B-Bars 10 12 1 4 1.70 - 81.60 - - - -
Footings-F3 - - - - - -
A-Bars 10 9 1 7 1.65 - 103.95 - - - -
B-Bars 10 11 1 7 1.45 - 111.65 - - - -
Footings-F4 - - - - - -
A-Bars 10 9 1 5 1.40 - 63.00 - - - -
B-Bars 10 9 1 5 1.40 - 63.00 - - - -
Column Steel - - - - - - B to T
Grid A6-C2 - - - - - - ###
Main Bars-1 16 4 1 1 3.00 - - - 12.00 - -
Main Bars-2 12 4 1 1 3.00 - - 12.00 - - -
Rectangle Stirrups 8 16 1 1 0.89 14.24 - - - - -
DimondStirrups 8 16 1 1 0.69 11.04 - - - - -
Grid A7-C3 - - - - - - ###
Main Bars-1 16 4 1 1 3.05 - - - 12.20 - -
Main Bars-2 12 4 1 1 3.05 - - 12.20 - - -
Rectangle Stirrups 8 16 1 1 1.05 16.80 - - - - -
DimondStirrups 8 16 1 1 0.89 14.24 - - - - -
Page 148
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid A8-C3 - - - - - - ###
Main Bars-1 16 4 1 1 3.25 - - - 13.00 - -
Main Bars-2 12 4 1 1 3.25 - - 13.00 - - -
Rectangle Stirrups 8 17 1 1 1.05 17.85 - - - - -
DimondStirrups 8 17 1 1 0.89 15.13 - - - - -
Grid B2-C2 - - - - - - ###
Main Bars-1 16 4 1 1 2.75 - - - 11.00 - -
Main Bars-2 12 4 1 1 2.75 - - 11.00 - - -
Rectangle Stirrups 8 15 1 1 0.89 13.35 - - - - -
DimondStirrups 8 15 1 1 0.69 10.35 - - - - -
Grid B3-C2 - - - - - - ###
Main Bars-1 16 4 1 1 2.85 - - - 11.40 - -
Main Bars-2 12 4 1 1 2.85 - - 11.40 - - -
Rectangle Stirrups 8 15 1 1 0.89 13.35 - - - - -
DimondStirrups 8 15 1 1 0.69 10.35 - - - - -
Grid B5-C2 - - - - - - ###
Main Bars-1 16 4 1 1 2.9 - - - 11.60 - -
Main Bars-2 12 4 1 1 2.9 - - 11.60 - - -
Rectangle Stirrups 8 15 1 1 0.89 13.35 - - - - -
DimondStirrups 8 15 1 1 0.69 10.35 - - - - -
Grid D1-C1 - - - - - - ###
Main Bars 12 6 1 1 2.65 - - 15.90 - - -
Stirrups 8 14 1 1 0.65 9.10 - - - - -
Grid D3-C2 - - - - - - ###
Main Bars-1 16 4 1 1 2.85 - - - 11.40 - -
Main Bars-2 12 4 1 1 2.85 - - 11.40 - - -
Rectangle Stirrups 8 15 1 1 0.89 13.35 - - - - -
DimondStirrups 8 15 1 1 0.69 10.35 - - - - -
Grid D5-C2 - - - - - - ###
Main Bars-1 16 4 1 1 2.85 - - - 11.40 - -
Main Bars-2 12 4 1 1 2.85 - - 11.40 - - -
Rectangle Stirrups 8 15 1 1 0.89 13.35 - - - - -
DimondStirrups 8 15 1 1 0.69 10.35 - - - - -
Grid D7-C3 - - - - - - ###
Page 149
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Main Bars-1 16 4 1 1 3.05 - - - 12.20 - -
Main Bars-2 12 4 1 1 3.05 - - 12.20 - - -
Rectangle Stirrups 8 16 1 1 1.05 16.80 - - - - -
DimondStirrups 8 16 1 1 0.89 14.24 - - - - -
Grid D8-C2 - - - - - - ###
Main Bars-1 16 4 1 1 3.25 - - - 13.00 - -
Main Bars-2 12 4 1 1 3.25 - - 13.00 - - -
Rectangle Stirrups 8 17 1 1 0.89 15.13 - - - - -
DimondStirrups 8 17 1 1 0.69 11.73 - - - - -
Grid E4-C2 - - - - - - ###
Main Bars-1 16 4 1 1 2.9 - - - 11.60 - -
Main Bars-2 12 4 1 1 2.9 - - 11.60 - - -
Rectangle Stirrups 8 15 1 1 0.89 13.35 - - - - -
DimondStirrups 8 15 1 1 0.69 10.35 - - - - -
Grid F8-C2 - - - - - - ###
Main Bars-1 16 4 1 1 3.25 - - - 13.00 - -
Main Bars-2 12 4 1 1 3.25 - - 13.00 - - -
Rectangle Stirrups 8 17 1 1 0.89 15.13 - - - - -
DimondStirrups 8 17 1 1 0.69 11.73 - - - - -
Grid G1-C1 - - - - - - ###
Main Bars 12 6 1 1 2.65 - - 15.90 - - -
Stirrups 8 14 1 1 0.65 9.10 - - - - -
Grid G3-C1 - - - - - - ###
Main Bars 12 6 1 1 2.85 - - 17.10 - - -
Stirrups 8 15 1 1 0.65 9.75 - - - - -
Grid G5-C2 - - - - - - ###
Main Bars-1 16 4 1 1 2.9 - - - 11.60 - -
Main Bars-2 12 4 1 1 2.9 - - 11.60 - - -
Rectangle Stirrups 8 15 1 1 0.89 13.35 - - - - -
DimondStirrups 8 15 1 1 0.69 10.35 - - - - -
Grid G7-C2 - - - - - - ###
Main Bars-1 16 4 1 1 3.05 - - - 12.20 - -
Main Bars-2 12 4 1 1 3.05 - - 12.20 - - -
Rectangle Stirrups 8 16 1 1 0.89 14.24 - - - - -
Page 150
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
DimondStirrups 8 16 1 1 0.69 11.04 - - - - -
Plinth Beam Steel - - - - - - CL
Grid A6-A8,PB5 - - - - - - ###
Top & Bottom Bars 12 4 1 1 6.61 - - 26.44 - - -
Extra Bars at End Support 12 1 1 1 4.52 - - 4.52 - - -
Extra Bars at Mid Span 12 1 1 1 4.62 - - 4.62 - - -
Stirrups 200mmc/c 8 32 1 1 1.31 41.92 - - - - -
Grid B3-B5,PB5 - - - - - - ###
Top & Bottom Bars 12 4 1 1 3.84 - - 15.36 - - -
Extra Bars at End Support 12 1 1 1 2.69 - - 2.69 - - -
Extra Bars at Mid Span 12 1 1 1 2.54 - - 2.54 - - -
Stirrups 200mmc/c 8 18 1 1 1.31 23.58 - - - - -
Grid B5-B7,PB4 - - - - - - ###
Top & Bottom Bars 12 4 1 1 4.41 - - 17.64 - - -
Extra Bars at End Support 12 2 1 1 3.06 - - 6.12 - - -
Extra Bars at Mid Span 12 2 1 1 2.97 - - 5.94 - - -
Stirrups 200mmc/c 8 21 1 1 1.31 27.51 - - - - -
Grid C7-C8,PB4 - - - - - - ###
Top & Bottom Bars 12 4 1 1 4.41 - - 17.64 - - -
Extra Bars at End Support 12 2 1 1 3.06 - - 6.12 - - -
Extra Bars at Mid Span 12 2 1 1 2.97 - - 5.94 - - -
Stirrups 200mmc/c 8 21 1 1 1.31 27.51 - - - - -
Grid D3-D5,PB5 - - - - - - ###
Top & Bottom Bars 12 4 1 1 3.91 - - 15.64 - - -
Extra Bars at End Support 12 1 1 1 2.73 - - 2.73 - - -
Extra Bars at Mid Span 12 1 1 1 2.60 - - 2.60 - - -
Stirrups 200mmc/c 8 19 1 1 1.31 24.89 - - - - -
Grid D7-D8,PB5 - - - - - - ###
Top & Bottom Bars 12 4 1 1 4.41 - - 17.64 - - -
Extra Bars at End Support 12 1 1 1 3.06 - - 3.06 - - -
Extra Bars at Mid Span 12 1 1 1 2.97 - - 2.97 - - -
Stirrups 200mmc/c 8 21 1 1 1.31 27.51 - - - - -
Grid E4-E5,PB5 - - - - - - ###
Top & Bottom Bars 12 4 1 1 2.41 - - 9.64 - - -
Page 151
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Extra Bars at End Support 12 1 1 1 1.74 - - 1.74 - - -
Extra Bars at Mid Span 12 1 1 1 1.47 - - 1.47 - - -
Stirrups 200mmc/c 8 11 1 1 1.31 14.41 - - - - -
Grid F7-F8,PB5 - - - - - - ###
Top & Bottom Bars 12 4 1 1 4.41 - - 17.64 - - -
Extra Bars at End Support 12 1 1 1 3.06 - - 3.06 - - -
Extra Bars at Mid Span 12 1 1 1 2.97 - - 2.97 - - -
Stirrups 200mmc/c 8 21 1 1 1.31 27.51 - - - - -
Grid G5-G7,PB5 - - - - - - ###
Top & Bottom Bars 12 4 1 1 4.41 - - 17.64 - - -
Extra Bars at End Support 12 1 1 1 3.06 - - 3.06 - - -
Extra Bars at Mid Span 12 1 1 1 2.97 - - 2.97 - - -
Stirrups 200mmc/c 8 21 1 1 1.31 27.51 - - - - -
Grid B3-D3,PB5 - - - - - - ###
Top & Bottom Bars 12 4 1 1 3.91 - - 15.64 - - -
Extra Bars at End Support 12 1 1 1 2.73 - - 2.73 - - -
Extra Bars at Mid Span 12 1 1 1 2.60 - - 2.60 - - -
Stirrups 200mmc/c 8 19 1 1 1.31 24.89 - - - - -
Grid D4-E4,PB5 - - - - - - ###
Top & Bottom Bars 12 4 1 1 3.92 - - 15.69 - - -
Extra Bars at End Support 12 1 1 1 2.74 - - 2.74 - - -
Extra Bars at Mid Span 12 1 1 1 2.60 - - 2.60 - - -
Stirrups 200mmc/c 8 19 1 1 1.31 24.89 - - - - -
Grid B5-D5,PB3 - - - - - - ###
Top Bars 12 2 1 1 3.91 - - 7.82 - - -
Bottem Bars 16 2 1 1 3.91 - - - 7.82 - -
Extra Bars at End Support 16 2 1 1 2.73 - - - 5.46 - -
Extra Bars at Mid Span 16 2 1 1 2.60 - - - 5.20 - -
Stirrups 150mmc/c 8 17 1 1 1.31 22.27 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.31 10.48 - - - - -
Grid D5-G5,PB4 - - - - - - ###
Top & Bottom Bars 12 4 1 1 4.45 - - 17.78 - - -
Extra Bars at End Support 12 2 1 1 3.09 - - 6.18 - - -
Extra Bars at Mid Span 12 2 1 1 3.00 - - 6.00 - - -
Page 152
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups 200mmc/c 8 21 1 1 1.31 27.51 - - - - -
Grid A6-B6,PB5 - - - - - - ###
Top & Bottom Bars 12 4 1 1 2.31 - - 9.22 - - -
Extra Bars at End Support 12 1 1 1 1.67 - - 1.67 - - -
Extra Bars at Mid Span 12 1 1 1 1.39 - - 1.39 - - -
Stirrups 200mmc/c 8 11 1 1 1.31 14.41 - - - - -
Grid A7-D7,PB1 - - - - - - ###
Top & Bottom Bars 16 4 1 1 5.69 - - - 22.74 - -
Extra Bars at End Support 16 3 1 1 3.91 - - - 11.73 - -
Extra Bars at Mid Span 16 3 1 1 3.93 - - - 11.79 - -
Stirrups 150mmc/c 8 25 1 1 1.31 32.75 - - - - -
Stirrups 200mmc/c 8 10 1 1 1.31 13.10 - - - - -
Spacer Bars 25 23 1 1 0.20 - - - - - 4.60
Grid D7-G7,PB4 - - - - - - ###
Top & Bottom Bars 12 4 1 1 4.45 - - 17.78 - - -
Extra Bars at End Support 12 2 1 1 3.09 - - 6.18 - - -
Extra Bars at Mid Span 12 2 1 1 3.00 - - 6.00 - - -
Stirrups 200mmc/c 8 21 1 1 1.31 27.51 - - - - -
Grid A8-D8,PB2 - - - - - - ###
Top Bars 12 2 1 1 5.53 - - 11.06 - - -
Bottom Bars 16 2 1 1 5.53 - - - 11.06 - -
Extra Bars at End Support 16 2 1 1 3.80 - - - 7.60 - -
Extra Bars at Mid Span 16 2 1 1 3.81 - - - 7.62 - -
Stirrups 150mmc/c 8 24 1 1 1.31 31.44 - - - - -
Stirrups 200mmc/c 8 10 1 1 1.31 13.10 - - - - -
Grid D8-F8,PB4 - - - - - - ###
Top & Bottom Bars 12 4 1 1 3.87 - - 15.46 - - -
Extra Bars at End Support 12 2 1 1 2.70 - - 5.40 - - -
Extra Bars at Mid Span 12 2 1 1 2.56 - - 5.12 - - -
Stirrups 200mmc/c 8 18 1 1 1.31 23.58 - - - - -
Column Steel Upto Roof Top - - - - - -
C1 - - - - - -
Main Bars 12 6 1 1 3.15 - - 18.90 - - -
Circular Stirrups 8 17 1 1 0.48 8.16 - - - - -
Page 153
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
C2 - - - - - -
Main Bars-1 16 4 1 10 3.15 - - - 126.00 - -
Main Bars-2 12 4 1 10 3.15 - - 126.00 - - -
Rectangle Stirrups 8 17 1 10 0.89 151.30 - - - - -
Dimond Stirrups 8 17 1 10 0.69 117.30 - - - - -
C2 - - - - - -
Main Bars-1 16 4 1 1 3.15 - - - 12.60 - -
Main Bars-2 12 4 1 1 3.15 - - 12.60 - - -
Rectangle Stirrups 8 10 1 1 0.89 8.90 - - - - -
Dimond Stirrups 8 10 1 1 0.69 6.90 - - - - -
C3 - - - - - -
Main Bars-1 16 4 1 3 3.15 - - - 37.80 - -
Main Bars-2 12 4 1 3 3.15 - - 37.80 - - -
Rectangle Stirrups 8 17 1 3 1.05 53.55 - - - - -
Dimond Stirrups 8 17 1 3 0.82 41.82 - - - - -
Lintle Steel - - - - - - CL
Grid A3-A8 - - - - - - ###
Top Bars 10 2 1 1 11.07 - 22.14 - - - -
Bottem Bars 12 2 1 1 11.07 - - 22.14 - - -
Bottem Bars 16 1 1 1 11.07 - - - 11.07 - -
Stirrrups 8 74 1 1 0.71 52.54 - - - - -
Grid B3-B5 - - - - - - ###
Top Bars 10 2 1 1 3.61 - 7.22 - - - -
Bottem Bars 12 2 1 1 3.61 - - 7.22 - - -
Bottem Bars 16 1 1 1 3.61 - - - 3.61 - -
Stirrrups 8 15 1 1 0.71 10.65 - - - - -
Grid B'5-B'7 - - - - - - ###
Top Bars 10 2 1 1 4.34 - 8.68 - - - -
Bottem Bars 12 2 1 1 4.34 - - 8.68 - - -
Bottem Bars 16 1 1 1 4.34 - - - 4.34 - -
Stirrrups 8 29 1 1 0.71 20.59 - - - - -
Grid D3-D5 - - - - - - ###
Top Bars 10 2 1 1 3.61 - 7.22 - - - -
Bottem Bars 12 2 1 1 3.61 - - 7.22 - - -
Page 154
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Bottem Bars 16 1 1 1 3.61 - - - 3.61 - -
Stirrrups 8 25 1 1 0.71 17.75 - - - - -
Grid E4-E5 - - - - - - ###
Top Bars 10 2 1 1 2.11 - 4.22 - - - -
Bottem Bars 12 3 1 1 2.11 - - 6.33 - - -
Stirrrups 8 11 1 1 0.71 7.81 - - - - -
Grid F7-F8 - - - - - - ###
Top Bars 10 2 1 1 4.11 - 8.22 - - - -
Bottem Bars 12 2 1 1 4.11 - - 8.22 - - -
Bottem Bars 16 1 1 1 4.11 - - - 4.11 - -
Stirrrups 8 28 1 1 0.71 19.88 - - - - -
Grid G5-G7 - - - - - - ###
Top Bars 10 2 1 1 4.11 - 8.22 - - - -
Bottem Bars 12 2 1 1 4.11 - - 8.22 - - -
Bottem Bars 16 1 1 1 4.11 - - - 4.11 - -
Stirrrups 8 28 1 1 0.71 19.88 - - - - -
Grid A3-B3 - - - - - - ###
Top Bars 10 2 1 1 2.31 - 4.61 - - - -
Bottem Bars 12 3 1 1 2.31 - - 6.92 - - -
Stirrrups 8 12 1 1 0.71 8.52 - - - - -
Grid B3-D3 - - - - - - ###
Top Bars 10 2 1 1 3.61 - 7.22 - - - -
Bottem Bars 12 2 1 1 3.61 - - 7.22 - - -
Bottem Bars 16 1 1 1 3.61 - - - 3.61 - -
Stirrrups 8 25 1 1 0.71 17.75 - - - - -
Grid D4-E4 - - - - - - ###
Top Bars 10 2 1 1 2.62 - 5.25 - - - -
Bottem Bars 12 3 1 1 2.62 - - 7.87 - - -
Stirrrups 8 14 1 1 0.71 9.94 - - - - -
Grid D5-G5 - - - - - - ###
Top Bars 10 2 1 1 4.15 - 8.29 - - - -
Bottem Bars 12 2 1 1 4.15 - - 8.29 - - -
Bottem Bars 16 1 1 1 4.15 - - - 4.15 - -
Stirrrups 8 28 1 1 0.71 19.88 - - - - -
Page 155
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid A6-B6 - - - - - - ###
Top & Bottom Bars 10 5 1 1 2.01 - 10.02 - - - -
Stirrrups 8 11 1 1 0.71 7.81 - - - - -
Grid A7-D7 - - - - - - ###
Top Bars 10 2 1 1 5.47 - 10.93 - - - -
Bottem Bars 12 2 1 1 5.47 - - 10.93 - - -
Bottem Bars 16 1 1 1 5.47 - - - 5.47 - -
Stirrrups 8 37 1 1 0.71 26.27 - - - - -
Grid D7-G7 - - - - - - ###
Top Bars 10 2 1 1 4.30 - 8.59 - - - -
Bottem Bars 12 2 1 1 4.30 - - 8.59 - - -
Bottem Bars 16 1 1 1 4.30 - - - 4.30 - -
Stirrrups 8 29 1 1 0.71 20.59 - - - - -
Grid A8-D8 - - - - - - ###
Top Bars 10 2 1 1 5.39 - 10.77 - - - -
Bottem Bars 12 2 1 1 5.39 - - 10.77 - - -
Bottem Bars 16 1 1 1 5.39 - - - 5.39 - -
Stirrrups 8 36 1 1 0.71 25.56 - - - - -
Grid D8-F8 - - - - - - ###
Top Bars 10 2 1 1 3.57 - 7.13 - - - -
Bottem Bars 12 2 1 1 3.57 - - 7.13 - - -
Bottem Bars 16 1 1 1 3.57 - - - 3.57 - -
Stirrrups 8 24 1 1 0.71 17.04 - - - - -
Grid B5-D5 - - - - - - ###
Top Bars 10 2 1 1 3.61 - 7.22 - - - -
Bottem Bars 12 2 1 1 3.61 - - 7.22 - - -
Bottem Bars 16 1 1 1 3.61 - - - 3.61 - -
Stirrrups 8 25 1 1 0.64 16.00 - - - - -
Grid C7'-D7' - - - - - - ###
Top Bars 10 2 1 1 1.89 - 3.78 - - - -
Bottem Bars 12 3 1 1 1.89 - - 5.67 - - -
Stirrrups 8 10 1 1 0.64 6.40 - - - - -
Grid C7-C8 - - - - - - ###
Top Bars 10 2 1 1 4.33 - 8.65 - - - -
Page 156
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Bottem Bars 12 2 1 1 4.33 - - 8.65 - - -
Bottem Bars 16 1 1 1 4.33 - - - 4.33 - -
Stirrrups 8 29 1 1 0.64 18.56 - - - - -
Grid D7-D8 - - - - - - ###
Top Bars 10 2 1 1 4.33 - 8.65 - - - -
Bottem Bars 12 2 1 1 4.33 - - 8.65 - - -
Bottem Bars 16 1 1 1 4.33 - - - 4.33 - -
Stirrrups 8 29 1 1 0.64 18.56 - - - - -
Chejja's Steel - - - - - -
W - - - - - -
Main Bars 8 11 1 1 1.31 14.41 - - - - -
Distribution Bars 8 3 1 1 1.50 4.50 - - - - -
W1 - - - - - -
Main Bars 8 9 1 1 1.31 11.79 - - - - -
Distribution Bars 8 3 1 1 1.20 3.60 - - - - -
W2 - - - - - -
Main Bars 8 11 1 1 1.31 14.41 - - - - -
Distribution Bars 8 3 1 1 1.50 4.50 - - - - -
Loft's Steel - - - - - -
Bed Room-1 - - - - - -
Main Bars 8 13 1 1 1.31 17.03 - - - - -
Distribution Bars 8 3 1 1 1.80 5.40 - - - - -
Bed Room-2 - - - - - -
Main Bars 8 15 1 1 1.31 19.65 - - - - -
Distribution Bars 8 3 1 1 2.00 6.00 - - - - -
Total Length In mts ### 747.98 957.20 504.59 - 4.60
Unit Wt/mt 0.395 0.617 0.888 1.580 2.460 3.858
Total Reinforcement Qty 692.30 461.50 849.99 797.26 - 17.75 2,818.81 Kgs
Total Weight Say MT 2.82 MT
Page 157
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Teaching Staff Quarters-1
Ground Floor RA Bill-01
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2-2.2 : Earthwork excavation for foundation of buildings, water supply, sanitary lines and electrical conduits either
in pits or in trenches 1.5m and above in width, in hard soil not exceeding 1.5 m. in depth including dressing the bottom
4 2.4
and sides of pits and trenches, stacking the excavated soil clear from edges of excavation with lead upto 50 m. after
breaking of clods complete as per specifications. specification. No. KBS 2.1(b) / 2.3.5
Earth work excavation For Footings
Grid A1-F2 1 2.10 1.90 0.30 1.20
Grid A3-F5 1 2.70 2.50 0.35 2.36
Grid A4-F2 1 2.10 1.90 0.25 1.00
Grid A5-F2 1 2.10 1.90 0.20 0.80
Grid A6-F5 1 2.70 2.50 0.35 2.36
Grid A8-F2 1 2.10 1.90 0.35 1.40
Grid B1-F4 1 2.50 2.30 0.30 1.72
Grid B3-F6 1 2.90 2.70 0.25 1.96
Grid B4-F4 1 2.50 2.50 0.20 1.25
Grid B5-F4 1 2.50 2.30 0.35 2.01
Grid B6-F6 1 2.90 2.70 0.35 2.74
Grid B8-F4 1 2.50 2.30 0.30 1.72
Grid C4-F5 1 2.70 2.50 0.25 1.69
Grid C5-F5 1 2.70 2.50 0.30 2.03
Grid D1-F3 1 2.30 2.10 0.35 1.69
Grid D2-F6 1 2.90 2.70 0.30 2.35
Grid D7-F6 1 2.90 2.70 0.30 2.35
Page 158
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D8-F3 1 2.30 2.10 0.35 1.69
Grid F1-F1 1 1.85 1.70 0.30 0.94
Grid F2-F4 1 2.50 2.30 0.25 1.44
Grid F4-F5 1 2.70 2.50 0.25 1.69
Grid F5-F5 1 2.70 2.50 0.25 1.69
Grid F7-F4 1 2.50 2.30 0.35 2.01
Grid F8-F1 1 1.85 1.70 0.35 1.10
Deductions
Grid F1-A1 -1 6.75 1.15 0.30 -2.33
Grid A1-A4 -1 4.23 1.15 0.25 -1.22
Grid A4-C4 -1 4.95 1.15 0.20 -1.14
Grid C4-C5 -1 3.27 1.15 0.25 -0.94
Grid C5-A5 -1 4.95 1.15 0.25 -1.42
Grid A5-A8 -1 4.23 1.15 0.30 -1.46
Page 159
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A8-F8 -1 6.75 1.15 0.25 -1.94
Grid F1-F8 -1 10.96 1.15 0.25 -3.15
Total Qty 57.28 Cum
KSRB 2-2.4 : Excavation 1.5m and above in width in soft rock without blasting for foundation of buildings, water supply,
sanitary lines and electrical conduits either in pits or in trenches not exceeding 1.5 m. in depth, stacking the excavated
5 2.6
stuff from edges of excavation with lead upto 50m including cost of explosives, labour and HOM of equipment complete
as per specifications. specification. No. KBS 2.1.C / 2.9.4 / 2.18 / 2.19
Page 160
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F4-F5 1 2.70 2.50 1.55 10.46
Grid F5-F5 1 2.70 2.50 1.55 10.46
Grid F7-F4 1 2.50 2.30 1.45 8.34
Grid F8-F1 1 1.85 1.70 1.45 4.56
Earth Work For SSM
Grid F1-A1 1 12.84 1.15 0.40 5.90
Grid A1-A4 1 6.80 1.15 0.45 3.52
Grid A4-C4 1 8.88 1.15 0.50 5.10
Grid C4-C5 1 3.69 1.15 0.45 1.91
Grid C5-A5 1 8.88 1.15 0.45 4.59
Grid A5-A8 1 6.80 1.15 0.40 3.13
Grid A8-F8 1 12.84 1.15 0.45 6.64
Grid F1-F8 1 18.87 1.15 0.45 9.77
Grid A'1-A'4 1 5.70 1.15 0.45 2.95
Grid A'5-A'8 1 5.70 1.15 0.40 2.62
Grid A-A' in 1,4,5,8 4 1.20 1.15 0.40 2.21
Deductions
Grid F1-A1 -1 6.75 1.15 0.40 -3.10
Grid A1-A4 -1 4.23 1.15 0.45 -2.19
Grid A4-C4 -1 4.95 1.15 0.50 -2.85
Grid C4-C5 -1 3.27 1.15 0.45 -1.69
Grid C5-A5 -1 4.95 1.15 0.45 -2.56
Grid A5-A8 -1 4.23 1.15 0.40 -1.95
Grid A8-F8 -1 6.75 1.15 0.45 -3.49
Grid F1-F8 -1 10.96 1.15 0.45 -5.67
Total Qty 233.37 Cum
Page 161
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB-3.2: Providing and injecting chemical emulsion for Preconstructional Anti-Termite Treatment, creating continuous
chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth
filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of
7 3.2 consolidated earth on which apron is to be laid, surrounding of pipes and conduits, with chloropyriphos emulsifiable
concentrates of 20% concentration, including cost of chemical, diluting in water to one percent concentration, labour,
HOM of equipments, complete as per specifications. (Plinth area of the building at ground floor only shall be measured )
Specification No. KBS : 3.2.6 / 3.2.7
Anti-Termite Treatment
Grid A1-A4,F1-F4 1 8.00 13.88 111.04
Grid A5-A8,F5-F8 1 2.96 4.43 13.12
Grid C4-C5,F4-F5 1 8.00 13.88 111.04
Total Qty 235.20 Sqm
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 with OPC cement @ 220kgs, with
40mm and down size graded granite metal coarse aggregates @0.892cum and fine aggregates @ 0.465cum machine
8 4.2
mixed, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation including
cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2
Page 162
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid C5-A5 1 8.88 0.75 0.10 0.67
Grid A5-A8 1 6.80 0.75 0.10 0.51
Grid A8-F8 1 12.84 0.75 0.10 0.96
Grid F1-F8 1 18.87 0.75 0.10 1.42
Grid A'1-A'4 1 6.50 1.15 0.10 0.75
Grid A'5-A'8 1 6.50 1.15 0.10 0.75
Grid A-A' in 1,4,5,8 4 1.20 1.15 0.10 0.55
Deductions of Footings
Grid F1-A1 -1 6.75 0.75 0.10 -0.51
Grid A1-A4 -1 4.23 0.75 0.10 -0.32
Grid A4-C4 -1 4.95 0.75 0.10 -0.37
Grid C4-C5 -1 3.27 0.75 0.10 -0.25
Grid C5-A5 -1 4.95 0.75 0.10 -0.37
Grid A5-A8 -1 4.23 0.75 0.10 -0.32
Grid A8-F8 -1 6.75 0.75 0.10 -0.51
Grid F1-F8 -1 10.96 0.75 0.10 -0.82
PCC BELOW PLINTH BEAM
Grid A'3'-A'4, 1 0.98 0.45 0.10 0.04
Grid A'5-A'5' 1 0.98 0.45 0.10 0.04
Grid B1-B3 1 3.90 0.45 0.10 0.18
Grid B3-B4 1 3.18 0.45 0.10 0.14
Grid B5-B6 1 3.18 0.45 0.10 0.14
Grid B6-B8 1 4.13 0.45 0.10 0.19
Grid D1-D2 1 3.00 0.45 0.10 0.14
Grid D2-D4 1 4.31 0.45 0.10 0.19
Grid D5-D7 1 4.31 0.45 0.10 0.19
Grid D7-D8 1 3.00 0.45 0.10 0.14
Grid B2-D2 1 4.28 0.45 0.10 0.19
Page 163
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D2-F2 1 3.00 0.45 0.10 0.14
Grid A3-B3 1 3.56 0.45 0.10 0.16
Grid A3'-B3' 1 4.00 0.45 0.10 0.18
Grid D3'-F3' 1 3.00 0.45 0.10 0.14
Grid C4-F4 1 3.53 0.45 0.10 0.16
Grid C5-F5 1 3.53 0.45 0.10 0.16
Grid A5'-B5' 1 4.00 0.45 0.10 0.18
Grid D5'-F5' 1 3.00 0.45 0.10 0.14
Grid A6-B6 1 3.56 0.45 0.10 0.16
Grid B7-D7 1 4.28 0.45 0.10 0.19
Grid D7-F7 1 3.00 0.45 0.10 0.14
Flooring PCC
Bed Room-1 2 4.13 4.00 0.10 3.30
Bed Room-2 2 3.00 4.50 0.10 2.70
Kitchen 2 3.00 3.00 0.10 1.80
Living 2 4.31 7.73 0.10 6.66
W.C 2 1.55 1.55 0.10 0.48
Bath 2 1.55 2.35 0.10 0.73
Passage 2 1.51 4.00 0.10 1.21
Staircase 2 2.50 3.95 0.10 1.98
Total Qty 35.92 Cum
KSRB 5.2-3 : Providing and constructing granite / trap / basalt size stone masonry in foundation cement mortar 1:6,
9 5.6 stone hammerd dressed in courses not less than 20 cms high, bond stones at two m. apart in each course including
cost of materials, labour, curing complete as per specifications. KBS 5.1.13
SSM In Foundations
Grid F1-A1 1 12.84 0.60 0.60 4.62
Grid A1-A4 1 6.80 0.60 0.60 2.45
Page 164
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A4-C4 1 8.88 0.60 0.60 3.20
Grid C4-C5 1 2.34 0.60 0.60 0.84
Grid C5-A5 1 8.88 0.60 0.60 3.20
Grid A5-A8 1 6.80 0.60 0.60 2.45
Grid A8-F8 1 12.84 0.60 0.60 4.62
Grid F1-F8 1 18.87 0.60 0.60 6.79
Grid A'1-A'4 1 7.10 0.60 0.60 2.56
Grid A'5-A'8 1 7.10 0.60 0.60 2.56
Grid A-A' in 1,4,5,8 4 1.20 0.60 0.60 1.73
Over Footings
Grid F1-F1 1 1.71 0.60 0.70 0.72
Grid D1-F3 1 1.90 0.60 0.60 0.68
Grid B1-F4 1 2.10 0.60 0.55 0.69
Grid A1-F2 1 1.71 0.60 0.65 0.67
Grid A3-F5 1 2.30 0.60 0.50 0.69
Grid A4-F2 1 1.71 0.60 0.65 0.67
Grid B4-F4 1 2.10 0.60 0.55 0.69
Grid C4-F5 1 2.54 0.60 0.50 0.76
Grid C5-F5 1 2.54 0.60 0.50 0.76
Grid B5-F4 1 2.10 0.60 0.55 0.69
Grid A5-F2 1 1.71 0.60 0.65 0.67
Grid A6-F5 1 2.10 0.60 0.50 0.63
Grid A8-F2 1 1.71 0.60 0.65 0.67
Grid B8-F2 1 2.10 0.60 0.65 0.82
Grid D8-F3 1 1.90 0.60 0.60 0.68
Grid F8-F1 1 1.71 0.60 0.70 0.72
Grid F7-F4 1 2.10 0.60 0.55 0.69
Grid F5-F5 1 2.10 0.60 0.50 0.63
Page 165
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F4-F5 1 2.10 0.60 0.50 0.63
Grid F2-F4 1 2.10 0.60 0.55 0.69
Deduction of Column Quantity
Grid F1-C1 -1 0.23 0.45 1.35 -0.14 ###
Grid D1-C2 -1 0.23 0.45 1.20 -0.12 ###
Grid B1-C2 -1 0.23 0.45 1.35 -0.14 ###
Grid A1-C1 -1 0.23 0.45 1.35 -0.14 ###
Grid A3-C2 -1 0.23 0.45 1.20 -0.12 ###
Grid A4-C1 -1 0.23 0.45 1.35 -0.14 ###
Grid B4-C2 -1 0.23 0.45 1.25 -0.13 ###
Grid C4-C3 -1 0.23 0.45 1.25 -0.13 ###
Grid C5-C3 -1 0.23 0.45 1.25 -0.13 ###
Grid B5-C2 -1 0.23 0.45 1.25 -0.13 ###
Grid A5-C1 -1 0.23 0.45 1.20 -0.12 ###
Grid A6-C2 -1 0.23 0.45 1.20 -0.12 ###
Grid A8-C1 -1 0.23 0.45 1.30 -0.13 ###
Grid B8-C2 -1 0.23 0.45 1.30 -0.13 ###
Grid D8-C2 -1 0.23 0.45 1.40 -0.14 ###
Grid F8-C1 -1 0.23 0.45 1.25 -0.13 ###
Grid F7-C2 -1 0.23 0.45 1.20 -0.12 ###
Grid F5-C3 -1 0.23 0.45 1.20 -0.12 ###
Grid F4-C3 -1 0.23 0.45 1.25 -0.13 ###
Grid F2-C2 -1 0.23 0.45 1.40 -0.14 ###
Total Qty 46.24 Cum
KSRB 5.3-3 : Providing and constructing granite / trap / basalt size stone masonry in basement with cement mortar 1:6,
10 5.9 edges of stones chistle dressed in courses not less than 15 cms high, bond stones at two m. apart in each course
including cost of materials, labour, curing complete as per specifications. KBS 5.1.13
Page 166
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
SSM in Basement
Grid F1-A1 1 12.84 0.45 0.35 2.02
Grid A1-A4 1 6.80 0.45 0.50 1.53
Grid A4-C4 1 8.88 0.45 0.65 2.60
Grid C4-C5 1 2.34 0.45 0.45 0.47
Grid C5-A5 1 8.88 0.45 0.65 2.60
Grid A5-A8 1 6.80 0.45 1.00 3.06
Grid A8-F8 1 12.84 0.45 1.10 6.35
Grid F1-F8 1 18.87 0.45 0.55 4.67
Grid A'1-A'4 1 7.10 0.45 0.95 3.04
Grid A'5-A'8 1 7.10 0.45 1.45 4.63
Grid A-A' in 1,4,5,8 4 1.20 0.45 1.10 2.38
Deduction For Columns
Grid A1-C1 -1 0.23 0.45 0.32 -0.03 Grid A1-
Grid A3-C2 -1 0.23 0.45 0.52 -0.05 Grid A3-
Grid A4-C1 -1 0.23 0.45 0.82 -0.08 Grid A4-
Grid A5-C1 -1 0.23 0.45 0.82 -0.08 Grid A5-
Grid A6-C2 -1 0.23 0.45 1.12 -0.12 Grid A6-
Grid A8-C1 -1 0.23 0.45 1.27 -0.13 Grid A8-
Grid B1-C2 -1 0.23 0.45 0.22 -0.02 Grid B1-
Grid B4-C2 -1 0.23 0.45 0.82 -0.08 Grid B4-
Grid B5-C2 -1 0.23 0.45 0.82 -0.08 Grid B5-
Grid B8-C2 -1 0.23 0.45 1.22 -0.13 Grid B8-
Grid C4-C3 -1 0.23 0.45 0.52 -0.05 Grid C4-
Grid C5-C3 -1 0.23 0.45 0.57 -0.06 Grid C5-
Grid D1-C2 -1 0.23 0.45 0.25 -0.03 Grid D1-
Grid D8-C2 -1 0.23 0.45 1.07 -0.11 Grid D8-
Grid F1-C1 -1 0.23 0.45 0.27 -0.03 Grid F1-F
Page 167
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F2-C2 -1 0.23 0.45 0.32 -0.03 Grid F2-F
Grid F4-C3 -1 0.23 0.45 0.47 -0.05 Grid F4-F
Grid F5-C3 -1 0.23 0.45 0.52 -0.05 Grid F5-F
Grid F7-C2 -1 0.23 0.45 0.87 -0.09 Grid F7-F
Grid F8-C1 -1 0.23 0.45 0.97 -0.10 Grid F8-F
Total Qty 31.92 Cum
KSRB 2.3 : Filling available excavated earth ( excluding rock ) in sides of foundations upto plinth in layers not exceeding
12 2.10 20 cms. in depth, compacting each deposited layer by ramming after watering with lead upto 50 m. and lift upto 1.5 m.
including cost of all labour complete as per specifications. specification. No. KBS 2.9
KSRB 2.5 : Earthwork excavation ( in deposited soil ) and filling sides of foundation upto plinth in layers not exceeding
13 2.12 20 cms. in depth, compacting each deposited layer by ramming after watering with all lead and lift including cost of all
labour complete as per specifications. specification. No. KBS 2.9.9 / 2.9.10.1 / 2.1.1
Page 168
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A5-A8,F5-F8 1 2.96 4.43 1.30 17.05
Grid C4-C5,F4-F5 1 8.00 13.88 0.90 99.94
Qty Required For side Filling 116.92
Total Qty 328.29 Cum
KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of design mix M20 with OPC cement @
320kgs, with 20mm and down size graded granite metal coarse aggregates @0.878cum and fine aggregtes @
0.459cum, with superplastisiser @3lts confirming to IS9103-1999 Reaffirmed-2008, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in foundation plinth and ground floor level for roof slabs,
14 4.11
staircase, lintles, retaining walls, return walls, walls ( any thickness ) including attached plasters, columns, piers,
abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain
window cills, fillets etc., including cost of all materials, labour, HOM of machinery, curing, complete as per
specifications. Specification No. KBS 4.1, 4.6
Footings Concrete
F1 2 1.25 1.10 0.30 0.83
F2 4 1.50 1.30 0.35 2.73
F3 2 1.70 1.50 0.40 2.04
F4 6 1.90 1.70 0.45 8.72
F5 6 2.00 1.80 0.50 10.80
F6 4 2.20 2.00 0.55 9.68
Column Concrete Upto Plinth Beam Top F Depth
Grid A1-C1 1 0.23 0.45 2.05 0.21 Grid A1-
Grid A3-C2 1 0.23 0.45 2.10 0.22 Grid A3-
Grid A4-C1 1 0.23 0.45 2.55 0.26 Grid A4-
Grid A5-C1 1 0.23 0.45 2.55 0.26 Grid A5-
Grid A6-C2 1 0.23 0.45 2.70 0.28 Grid A6-
Grid A8-C1 1 0.23 0.45 3.00 0.31 Grid A8-
Grid B1-C2 1 0.23 0.45 1.85 0.19 Grid B1-
Grid B3-C3 1 0.23 0.45 2.05 0.21 Grid B3-
Page 169
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid B4-C2 1 0.23 0.45 2.45 0.25 Grid B4-
Grid B5-C2 1 0.23 0.45 2.45 0.25 Grid B5-
Grid B6-C3 1 0.23 0.45 2.65 0.27 Grid B6-
Grid B8-C2 1 0.23 0.45 2.85 0.29 Grid B8-
Grid C4-C3 1 0.23 0.45 2.10 0.22 Grid C4-
Grid C5-C3 1 0.23 0.45 2.15 0.22 Grid C5-
Grid D1-C2 1 0.23 0.45 1.93 0.20 Grid D1-
Grid D2-C3 1 0.23 0.45 1.85 0.19 Grid D2-
Grid D7-C3 1 0.23 0.45 2.40 0.25 Grid D7-
Grid D8-C2 1 0.23 0.45 2.75 0.28 Grid D8-
Grid F1-C1 1 0.23 0.45 2.05 0.21 Grid F1-F
Grid F2-C2 1 0.23 0.45 1.95 0.20 Grid F2-F
Grid F4-C3 1 0.23 0.45 2.05 0.21 Grid F4-F
Grid F5-C3 1 0.23 0.45 2.10 0.22 Grid F5-F
Grid F7-C2 1 0.23 0.45 2.50 0.26 Grid F7-F
Grid F8-C1 1 0.23 0.45 2.75 0.28 Grid F8-F
Plinth Beam Concrete
Grid A1-A3,PB1 1 4.13 0.23 0.38 0.36
Grid A3-A4,PB3 1 3.18 0.23 0.38 0.28
Grid A5-A6,PB3 1 3.18 0.23 0.38 0.28
Grid A6-A8,PB1 1 4.13 0.23 0.38 0.36
Grid A'3'-A'4,PB4 1 1.44 0.23 0.38 0.13
Grid A'5-A'5',PB4 1 1.44 0.23 0.38 0.13
Grid B1-B3,PB3 1 4.13 0.23 0.38 0.36
Grid B3-B4,PB3 1 3.18 0.23 0.38 0.28
Grid B5-B6,PB3 1 3.18 0.23 0.38 0.28
Grid B6-B8,PB3 1 4.13 0.23 0.38 0.36
Grid C4-C5,PB2 1 2.49 0.23 0.38 0.22
Page 170
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D1-D2,PB3 1 3.00 0.23 0.38 0.26
Grid D2-D4,PB1 1 4.31 0.23 0.38 0.38
Grid D5-D7,PB1 1 4.31 0.23 0.38 0.38
Grid D7-D8,PB3 1 3.00 0.23 0.38 0.26
Grid F1-F2,PB3 1 3.00 0.23 0.38 0.26
Grid F2-F4,PB1 1 4.09 0.23 0.38 0.36
Grid F4-F5,PB1 1 2.49 0.23 0.38 0.22
Grid F5-F7,PB1 1 4.09 0.23 0.38 0.36
Grid F7-F8,PB3 1 3.00 0.23 0.38 0.26
Grid A1-B1,PB1 1 3.56 0.23 0.38 0.31
Grid B1-D1,PB2 1 4.28 0.23 0.38 0.37
Grid D1-F1,PB1 1 2.78 0.23 0.38 0.24
Grid B2-D2,PB2 1 4.28 0.23 0.38 0.37
Grid D2-F2,PB1 1 3.00 0.23 0.38 0.26
Grid A3-B3,PB1 1 3.56 0.23 0.38 0.31
Grid A3'-B3',PB4 1 4.00 0.23 0.38 0.35
Grid D3'-F3',PB4 1 3.00 0.23 0.38 0.26
Grid A4-B4,PB1 1 3.56 0.23 0.38 0.31
Grid B4-C4,PB1 1 3.57 0.23 0.38 0.31
Grid C4-F4,PB1 1 3.53 0.23 0.38 0.31
Grid A5-B5,PB1 1 3.56 0.23 0.38 0.31
Grid B5-C5,PB1 1 3.57 0.23 0.38 0.31
Grid C5-F5,PB1 1 3.53 0.23 0.38 0.31
Grid A5'-B5',PB4 1 4.00 0.23 0.38 0.35
Grid D5'-F5',PB4 1 3.00 0.23 0.38 0.26
Grid A6-B6,PB1 1 3.56 0.23 0.38 0.31
Grid B7-D7,PB2 1 4.28 0.23 0.38 0.37
Grid D7-F7,PB1 1 3.00 0.23 0.38 0.26
Page 171
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A8-B8,PB1 1 3.56 0.23 0.38 0.31
Grid B8-D8,PB2 1 4.05 0.23 0.38 0.35
Grid D8-F8,,PB1 1 2.78 0.23 0.38 0.24
Total Qty 53.15 Cum
KSRB 4.2.4 : Providing and laying in position reinforced cement concrete of mix M10 with OPC cement @ 220kgs, with
20mm and down size graded granite metal coarse aggregates @0.792cum and fine aggregtes @ 0.465cum, machine
mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all works in foundation plinth and ground floor
15 4.13 level for roof slabs, staircase, lintles, retaining walls, return walls, walls ( any thickness ) including attached plasters,
columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks,
anchor blocks, plain window cills, fillets etc., including cost of all materials, labour, HOM of machinery, curing, complete
as per specifications. Specification No. KBS 4.1, 4.6
Lintle Concrete
Grid A1-A3,L1 1 4.13 0.23 0.15 0.14
Grid A3-A4,L1 1 3.18 0.23 0.15 0.11
Grid A5-A6,L1 1 3.18 0.23 0.15 0.11
Grid A6-A8,L1 1 4.13 0.23 0.15 0.14
Grid B1-B3,L1 1 4.13 0.23 0.15 0.14
Grid B3-B4,L1 1 3.18 0.23 0.15 0.11
Grid B5-B6,L1 1 3.18 0.23 0.15 0.11
Grid B6-B8,L1 1 4.13 0.23 0.15 0.14
Grid C4-C5,L1 1 2.49 0.23 0.15 0.09
Grid D1-D2,L2 1 3.00 0.23 0.15 0.10
Grid D3'-D4,L1 1 1.20 0.23 0.15 0.04
Page 172
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D5-D5',L1 1 1.20 0.23 0.15 0.04
Grid D7-D8,L2 1 3.00 0.23 0.15 0.10
Grid F1-F2,L1 1 3.00 0.23 0.15 0.10
Grid F2-F4,L1 1 4.09 0.23 0.15 0.14
Grid F5-F7,L1 1 4.09 0.23 0.15 0.14
Grid F7-F8,L1 1 3.00 0.23 0.15 0.10
Grid A1-B1,L1 1 3.56 0.23 0.15 0.12
Grid B1-D1,L1 1 4.28 0.23 0.15 0.15
Grid D1-F1,L1 1 2.78 0.23 0.15 0.10
Grid B2-D2,L1 1 4.28 0.23 0.15 0.15
Grid A3-B3,L2 1 3.56 0.23 0.15 0.12
Grid D3'-F3',L1 1 3.00 0.23 0.15 0.10
Grid A4-B4,L1 1 3.56 0.23 0.15 0.12
Grid B4-C4,L1 1 3.57 0.23 0.15 0.12
Grid C4-F4,L2 1 3.53 0.23 0.15 0.12
Grid A5-B5,L1 1 3.56 0.23 0.15 0.12
Grid B5-C5,L1 1 3.57 0.23 0.15 0.12
Grid C5-F5,L2 1 3.53 0.23 0.15 0.12
Grid D5'-F5',L1 1 3.00 0.23 0.15 0.10
Grid A6-B6,L2 1 3.56 0.23 0.15 0.12
Grid B7-D7,L1 1 4.28 0.23 0.15 0.15
Grid A8-B8,L1 1 3.56 0.23 0.15 0.12
Grid B8-D8,L1 1 4.05 0.23 0.15 0.14
Grid D8-F8,L1 1 2.78 0.23 0.15 0.10
KSRB
Total 4.2.10
Qty : Providing and laying in position reinforced cement concrete of design mix M20 with OPC cement 11.91 @ Cum
24kgs, with 12mm and down size graded granite metal coarse aggregates @0.05175cum and fine aggregtes @
0.0345cum, with superplastisiser @0.225lts, machine mixed, well compacted for plain chajja of 7.5 cms. average
16 4.19
thickness, upto ground floor level, including cost of all materials, labour, HOM of machinery, finishing, curing, complete
but excluding cost of
reinforcement as per specifications. Specification No. KBS 4.1, 4.6
Page 173
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Chejja's
W 4 2.10 0.60 5.04
W1 4 1.50 0.60 3.60
KW 4 1.50 0.60 3.60
Total Qty 12.24 Sqm
KSRB 4-1.6 ; Providing and laying in position plain cement concrete of mix 1:2:4 with cement @ 240kgs, with 20mm and
down size graded granite metal coarse aggregates @ 0.878 cum and fine aggregtes @ 0.53cum, machine mixed,
18 4.6
concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation, plinth and cills, ncluding cost of all
materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2
Coping Concrete
Grid A1-A3 1 4.13 0.45 0.075 0.14
Grid A3-A4 1 3.18 0.45 0.075 0.11
Grid A5-A6 1 3.18 0.45 0.075 0.11
Grid A6-A8 1 4.13 0.45 0.075 0.14
Grid C4-C5 1 2.49 0.45 0.075 0.08
Grid F1-F2 1 3.00 0.45 0.075 0.10
Grid F2-F4 1 4.09 0.45 0.075 0.14
Grid F4-F5 1 2.49 0.45 0.075 0.08
Grid F5-F7 1 4.09 0.45 0.075 0.14
Grid F7-F8 1 3.00 0.45 0.075 0.10
Grid A1-B1 1 3.56 0.45 0.075 0.12
Grid B1-D1 1 4.28 0.45 0.075 0.14
Grid D1-F1 1 2.78 0.45 0.075 0.09
Grid A4-B4 1 3.56 0.45 0.075 0.12
Grid B4-C4 1 3.57 0.45 0.075 0.12
Grid A5-B5 1 3.56 0.45 0.075 0.12
Grid B5-C5 1 3.57 0.45 0.075 0.12
Grid A8-B8 1 3.56 0.45 0.075 0.12
Page 174
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid B8-D8 1 4.05 0.45 0.075 0.14
Grid D8-F8 1 2.78 0.45 0.075 0.09
Grid A'1-A'4 1 7.10 1.15 0.075 0.61
Grid A'5-A'8 1 7.10 1.15 0.075 0.61
Grid A-A' in 1,4,5,8 4 1.20 1.15 0.075 0.41
Cill Concrete
Grid A1-A3 1 4.13 0.23 0.075 0.07
Grid A3-A4 1 3.18 0.23 0.075 0.05
Grid A5-A6 1 3.18 0.23 0.075 0.05
Grid A6-A8 1 4.13 0.23 0.075 0.07
Grid B1-B3 1 4.13 0.23 0.075 0.07
Grid B3-B4 1 3.18 0.23 0.075 0.05
Grid B5-B6 1 3.18 0.23 0.075 0.05
Grid B6-B8 1 4.13 0.23 0.075 0.07
Grid C4-C5 1 2.49 0.23 0.075 0.04
Grid D1-D2 1 3.00 0.23 0.075 0.05
Grid D3'-D4 1 1.20 0.23 0.075 0.02
Grid D5-D5' 1 1.20 0.23 0.075 0.02
Grid D7-D8 1 3.00 0.23 0.075 0.05
Grid F1-F2 1 3.00 0.23 0.075 0.05
Grid F2-F4 1 4.09 0.23 0.075 0.07
Grid F4-F5 1 2.49 0.23 0.075 0.04
Grid F5-F7 1 4.09 0.23 0.075 0.07
Grid F7-F8 1 3.00 0.23 0.075 0.05
Grid A1-B1 1 3.56 0.23 0.075 0.06
Grid B1-D1 1 4.28 0.23 0.075 0.07
Grid D1-F1 1 2.78 0.23 0.075 0.05
Grid B2-D2 1 4.28 0.23 0.075 0.07
Page 175
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D2-F2 1 3.00 0.23 0.075 0.05
Grid A3-B3 1 3.56 0.23 0.075 0.06
Grid D3'-F3' 1 3.00 0.23 0.075 0.05
Grid A4-B4 1 3.56 0.23 0.075 0.06
Grid B4-C4 1 3.57 0.23 0.075 0.06
Grid C4-F4 1 3.53 0.23 0.075 0.06
Grid A5-B5 1 3.56 0.23 0.075 0.06
Grid B5-C5 1 3.57 0.23 0.075 0.06
Grid C5-F5 1 3.53 0.23 0.075 0.06
Grid D5'-F5' 1 3.00 0.23 0.075 0.05
Grid A6-B6 1 3.56 0.23 0.075 0.06
Grid B7-D7 1 4.28 0.23 0.075 0.07
Grid D7-F7 1 3.00 0.23 0.075 0.05
Grid A8-B8 1 3.56 0.23 0.075 0.06
Grid B8-D8 1 4.05 0.23 0.075 0.07
Grid D8-F8 1 2.78 0.23 0.075 0.05
Deductions
ED -2 1.05 0.23 0.075 -0.04
D -6 0.90 0.23 0.075 -0.09
Toilet Passage -2 0.90 0.23 0.075 -0.03
Kitchen Passage -2 0.90 0.23 0.075 -0.03
Total Qty 5.97 Cum
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
19 4.28 foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per
specificaitons. Specification No. KBS 4.6.2
Page 176
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
2 2 1.30 0.10 0.52
F2 4 2 1.70 0.10 1.36
4 2 1.50 0.10 1.20
F3 2 2 1.90 0.10 0.76
2 2 1.70 0.10 0.68
F4 6 2 2.10 0.10 2.52
6 2 1.90 0.10 2.28
F5 6 2 2.20 0.10 2.64
6 2 2.00 0.10 2.40
F6 4 2 2.40 0.10 1.92
4 2 2.20 0.10 1.76
Shuttering For Footings Concrete
F1 2 2 1.25 0.30 1.50
2 2 1.10 0.30 1.32
F2 4 2 1.50 0.35 4.20
4 2 1.30 0.35 3.64
F3 2 2 1.70 0.40 2.72
2 2 1.50 0.40 2.40
F4 6 2 1.90 0.45 10.26
6 2 1.70 0.45 9.18
F5 6 2 2.00 0.50 12.00
6 2 1.80 0.50 10.80
F6 4 2 2.20 0.55 9.68
4 2 2.00 0.55 8.80
Total Qty 95.12 Sqm
KSRB 4-6.5 : Providing and removing centering, shuttering, strutting, propping etc., for columns, pillars, piers,
21 4.32 abutments, post and struts, square / rectangular / polygon in plan including cost of all materials, labour complete as per
specificaiton. Specification No. KBS 4.6.2
Page 177
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Shuttering For Column Concrete
Grid A1-C1 1 1.36 2.05 2.79
Grid A3-C2 1 1.36 2.10 2.86
Grid A4-C1 1 1.36 2.55 3.47
Grid A5-C1 1 1.36 2.55 3.47
Grid A6-C2 1 1.36 2.70 3.67
Grid A8-C1 1 1.36 3.00 4.08
Grid B1-C2 1 1.36 1.85 2.52
Grid B3-C3 1 1.36 2.05 2.79
Grid B4-C2 1 1.36 2.45 3.33
Grid B5-C2 1 1.36 2.45 3.33
Grid B6-C3 1 1.36 2.65 3.60
Grid B8-C2 1 1.36 2.85 3.88
Grid C4-C3 1 1.36 2.10 2.86
Grid C5-C3 1 1.36 2.15 2.92
Grid D1-C2 1 1.36 1.93 2.62
Grid D2-C3 1 1.36 1.85 2.52
Grid D7-C3 1 1.36 2.40 3.26
Grid D8-C2 1 1.36 2.75 3.74
Grid F1-C1 1 1.36 2.05 2.79
Grid F2-C2 1 1.36 1.95 2.65
Grid F4-C3 1 1.36 2.05 2.79
Grid F5-C3 1 1.36 2.10 2.86
Grid F7-C2 1 1.36 2.50 3.40
Grid F8-C1 1 1.36 2.75 3.74
Columns UptO Roof Bottem
C1 6 1.36 3.0 24.48
C2 10 1.36 3.0 40.80
Page 178
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
C3 8 1.36 3.0 32.64
Total Qty 173.85 Sqm
KSRB 4-6.7 :Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for sides
23 4.34 and soffits of beams, beam haunchings, cantilever girders, bressumers and lintels not exceeding 1m in depth including
cost of all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2
Lintle Beam Shuttering
Grid A1-A3,L1 1 2 4.13 0.15 1.24
Grid A3-A4,L1 1 2 3.18 0.15 0.95
Grid A5-A6,L1 1 2 3.18 0.15 0.95
Grid A6-A8,L1 1 2 4.13 0.15 1.24
Grid B1-B3,L1 1 2 4.13 0.15 1.24
Grid B3-B4,L1 1 2 3.18 0.15 0.95
Grid B5-B6,L1 1 2 3.18 0.15 0.95
Grid B6-B8,L1 1 2 4.13 0.15 1.24
Grid C4-C5,L1 1 2 2.49 0.15 0.75
Grid D1-D2,L2 1 2 3.00 0.15 0.90
Grid D3'-D4,L1 1 2 1.20 0.15 0.36
Grid D5-D5',L1 1 2 1.20 0.15 0.36
Grid D7-D8,L2 1 2 3.00 0.15 0.90
Grid F1-F2,L1 1 2 3.00 0.15 0.90
Grid F2-F4,L1 1 2 4.09 0.15 1.23
Grid F5-F7,L1 1 2 4.09 0.15 1.23
Grid F7-F8,L1 1 2 3.00 0.15 0.90
Grid A1-B1,L1 1 2 3.56 0.15 1.07
Grid B1-D1,L1 1 2 4.28 0.15 1.28
Grid D1-F1,L1 1 2 2.78 0.15 0.83
Grid B2-D2,L1 1 2 4.28 0.15 1.28
Grid A3-B3,L2 1 2 3.56 0.15 1.07
Page 179
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D3'-F3',L1 1 2 3.00 0.15 0.90
Grid A4-B4,L1 1 2 3.56 0.15 1.07
Grid B4-C4,L1 1 2 3.57 0.15 1.07
Grid C4-F4,L2 1 2 3.53 0.15 1.06
Grid A5-B5,L1 1 2 3.56 0.15 1.07
Grid B5-C5,L1 1 2 3.57 0.15 1.07
Grid C5-F5,L2 1 2 3.53 0.15 1.06
Grid D5'-F5',L1 1 2 3.00 0.15 0.90
Grid A6-B6,L2 1 2 3.56 0.15 1.07
Grid B7-D7,L1 1 2 4.28 0.15 1.28
Grid A8-B8,L1 1 2 3.56 0.15 1.07
Grid B8-D8,L1 1 2 4.05 0.15 1.21
Grid D8-F8,L1 1 2 2.78 0.15 0.83
Centering at Openings
ED 2 1 1.05 0.23 0.48
D 6 1 0.9 0.23 1.24
D1 4 1 0.75 0.23 0.69
W 4 1 1.8 0.23 1.66
W1 6 1 1.2 0.23 1.66
KW 4 1 1.2 0.23 1.10
Openings 2 1 0.9 0.23 0.41
Total Qty 42.74 Sqm
KSRB 4-6.4 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
25 4.31 vertical surface such as walls at any thickness, including attached pilasters, buttresses, plinth and string courses cost of
all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2
Page 180
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A3-A4,PB3 1 2 3.18 0.45 2.86
Grid A5-A6,PB3 1 2 3.18 0.45 2.86
Grid A6-A8,PB1 1 2 4.13 0.45 3.72
Grid A'3'-A'4,PB4 1 2 1.44 0.45 1.29
Grid A'5-A'5',PB4 1 2 1.44 0.45 1.29
Grid B1-B3,PB3 1 2 4.13 0.45 3.72
Grid B3-B4,PB3 1 2 3.18 0.45 2.86
Grid B5-B6,PB3 1 2 3.18 0.45 2.86
Grid B6-B8,PB3 1 2 4.13 0.45 3.72
Grid C4-C5,PB2 1 2 2.49 0.45 2.24
Grid D1-D2,PB3 1 2 3.00 0.45 2.70
Grid D2-D4,PB1 1 2 4.31 0.45 3.88
Grid D5-D7,PB1 1 2 4.31 0.45 3.88
Grid D7-D8,PB3 1 2 3.00 0.45 2.70
Grid F1-F2,PB3 1 2 3.00 0.45 2.70
Grid F2-F4,PB1 1 2 4.09 0.45 3.68
Grid F4-F5,PB1 1 2 2.49 0.45 2.24
Grid F5-F7,PB1 1 2 4.09 0.45 3.68
Grid F7-F8,PB3 1 2 3.00 0.45 2.70
Grid A1-B1,PB1 1 2 3.56 0.45 3.20
Grid B1-D1,PB2 1 2 4.28 0.45 3.85
Grid D1-F1,PB1 1 2 2.78 0.45 2.50
Grid B2-D2,PB2 1 2 4.28 0.45 3.85
Grid D2-F2,PB1 1 2 3.00 0.45 2.70
Grid A3-B3,PB1 1 2 3.56 0.45 3.20
Grid A3'-B3',PB4 1 2 4.00 0.45 3.60
Grid D3'-F3',PB4 1 2 3.00 0.45 2.70
Grid A4-B4,PB1 1 2 3.56 0.45 3.20
Page 181
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid B4-C4,PB1 1 2 3.57 0.45 3.21
Grid C4-F4,PB1 1 2 3.53 0.45 3.18
Grid A5-B5,PB1 1 2 3.56 0.45 3.20
Grid B5-C5,PB1 1 2 3.57 0.45 3.21
Grid C5-F5,PB1 1 2 3.53 0.45 3.18
Grid A5'-B5',PB4 1 2 4.00 0.45 3.60
Grid D5'-F5',PB4 1 2 3.00 0.45 2.70
Grid A6-B6,PB1 1 2 3.56 0.45 3.20
Grid B7-D7,PB2 1 2 4.28 0.45 3.85
Grid D7-F7,PB1 1 2 3.00 0.45 2.70
Grid A8-B8,PB1 1 2 3.56 0.45 3.20
Grid B8-D8,PB2 1 2 4.05 0.45 3.65
Grid D8-F8,,PB1 1 2 2.78 0.45 2.50
Shuttering For Pcc Below Plinth Beam
Grid A'3'-A'4, 1 2 1.44 0.10 0.29
Grid A'5-A'5' 1 2 1.44 0.10 0.29
Grid B1-B3 1 2 4.13 0.10 0.83
Grid B3-B4 1 2 3.18 0.10 0.64
Grid B5-B6 1 2 3.18 0.10 0.64
Grid B6-B8 1 2 4.13 0.10 0.83
Grid D1-D2 1 2 3.00 0.10 0.60
Grid D2-D4 1 2 4.31 0.10 0.86
Grid D5-D7 1 2 4.31 0.10 0.86
Grid D7-D8 1 2 3.00 0.10 0.60
Grid B2-D2 1 2 4.28 0.10 0.86
Grid D2-F2 1 2 3.00 0.10 0.60
Grid A3-B3 1 2 3.56 0.10 0.71
Grid A3'-B3' 1 2 4.00 0.10 0.80
Page 182
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D3'-F3' 1 2 3.00 0.10 0.60
Grid C4-F4 1 2 3.53 0.10 0.71
Grid C5-F5 1 2 3.53 0.10 0.71
Grid A5'-B5' 1 2 4.00 0.10 0.80
Grid D5'-F5' 1 2 3.00 0.10 0.60
Grid A6-B6 1 2 3.56 0.10 0.71
Grid B7-D7 1 2 4.28 0.10 0.86
Grid D7-F7 1 2 3.00 0.10 0.60
Shuttering For Coping Concrete
Grid A1-A3 1 2 4.13 0.075 0.62
Grid A3-A4 1 2 3.18 0.075 0.48
Grid A5-A6 1 2 3.18 0.075 0.48
Grid A6-A8 1 2 4.13 0.075 0.62
Grid C4-C5 1 2 2.49 0.075 0.37
Grid F1-F2 1 2 3.00 0.075 0.45
Grid F2-F4 1 2 4.09 0.075 0.61
Grid F4-F5 1 2 2.49 0.075 0.37
Grid F5-F7 1 2 4.09 0.075 0.61
Grid F7-F8 1 2 3.00 0.075 0.45
Grid A1-B1 1 2 3.56 0.075 0.53
Grid B1-D1 1 2 4.28 0.075 0.64
Grid D1-F1 1 2 2.78 0.075 0.42
Grid A4-B4 1 2 3.56 0.075 0.53
Grid B4-C4 1 2 3.57 0.075 0.53
Grid A5-B5 1 2 3.56 0.075 0.53
Grid B5-C5 1 2 3.57 0.075 0.53
Grid A8-B8 1 2 3.56 0.075 0.53
Grid B8-D8 1 2 4.05 0.075 0.61
Page 183
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D8-F8 1 2 2.78 0.075 0.42
Grid A'1-A'4 1 2 7.10 0.075 1.07
Grid A'5-A'8 1 2 7.10 0.075 1.07
Grid A-A' in 1,4,5,8 4 2 1.20 0.075 0.72
Cill Concrete Shuttering
Grid A1-A3 1 2 4.13 0.075 0.62
Grid A3-A4 1 2 3.18 0.075 0.48
Grid A5-A6 1 2 3.18 0.075 0.48
Grid A6-A8 1 2 4.13 0.075 0.62
Grid B1-B3 1 2 4.13 0.075 0.62
Grid B3-B4 1 2 3.18 0.075 0.48
Grid B5-B6 1 2 3.18 0.075 0.48
Grid B6-B8 1 2 4.13 0.075 0.62
Grid C4-C5 1 2 2.49 0.075 0.37
Grid D1-D2 1 2 3.00 0.075 0.45
Grid D3'-D4 1 2 1.20 0.075 0.18
Grid D5-D5' 1 2 1.20 0.075 0.18
Grid D7-D8 1 2 3.00 0.075 0.45
Grid F1-F2 1 2 3.00 0.075 0.45
Grid F2-F4 1 2 4.09 0.075 0.61
Grid F4-F5 1 2 2.49 0.075 0.37
Grid F5-F7 1 2 4.09 0.075 0.61
Grid F7-F8 1 2 3.00 0.075 0.45
Grid A1-B1 1 2 3.56 0.075 0.53
Grid B1-D1 1 2 4.28 0.075 0.64
Grid D1-F1 1 2 2.78 0.075 0.42
Grid B2-D2 1 2 4.28 0.075 0.64
Grid D2-F2 1 2 3.00 0.075 0.45
Page 184
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A3-B3 1 2 3.56 0.075 0.53
Grid D3'-F3' 1 2 3.00 0.075 0.45
Grid A4-B4 1 2 3.56 0.075 0.53
Grid B4-C4 1 2 3.57 0.075 0.53
Grid C4-F4 1 2 3.53 0.075 0.53
Grid A5-B5 1 2 3.56 0.075 0.53
Grid B5-C5 1 2 3.57 0.075 0.53
Grid C5-F5 1 2 3.53 0.075 0.53
Grid D5'-F5' 1 2 3.00 0.075 0.45
Grid A6-B6 1 2 3.56 0.075 0.53
Grid B7-D7 1 2 4.28 0.075 0.64
Grid D7-F7 1 2 3.00 0.075 0.45
Grid A8-B8 1 2 3.56 0.075 0.53
Grid B8-D8 1 2 4.05 0.075 0.61
Grid D8-F8 1 2 2.78 0.075 0.42
Deductions
ED -2 2 1.05 0.075 -0.32
D -6 2 0.90 0.075 -0.81
Toilet Passage -2 2 0.90 0.075 -0.27
Kitchen Passage -2 2 0.90 0.075 -0.27
Total Qty 175.05 Sqm
KSRB 4-6.10 :Providing and removing centering, shuttering, strutting, propping etc., for chajjas, corbels etc., including
26 4.37
edges including cost of all materials, labour complete as per specifications. Specification No. KBS 4.6.2
Page 185
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Total Qty 13.68 Sqm
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking,
placing in position, lapping and / or welding wherever required, tying with binding wire and anchoring to the adjoining
28 4.46.2
members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of
materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3
6.53
Total Qty 6.53 Tonne
KSRB 6-1.3 : Providing and constructing burnt brick masonry for basement and superstructure with approved quality of
29 6.3 non-modular bricks of standard size of class designation 3.5N per Sqmm with cement mortar 1:6 including cost of
materials, labour charges, scaffolding, curing complete as per specifications. Specification No. KBS 6.2
Page 186
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F1-F2 1 3.00 0.23 2.475 1.71
Grid F2-F4 1 4.09 0.23 2.475 2.33
Grid F4-F5 1 2.49 0.23 2.475 1.42
Grid F5-F7 1 4.09 0.23 2.475 2.33
Grid F7-F8 1 3.00 0.23 2.475 1.71
Grid A1-B1 1 3.56 0.23 2.475 2.03
Grid B1-D1 1 4.28 0.23 2.475 2.44
Grid D1-F1 1 2.78 0.23 2.475 1.58
Grid B2-D2 1 4.28 0.23 2.475 2.44
Grid D2-F2 1 3.00 0.23 1.2 0.83
Grid A3-B3 1 3.56 0.23 2.475 2.03
Grid D3'-F3' 1 3.00 0.23 2.475 1.71
Grid A4-B4 1 3.56 0.23 2.475 2.03
Grid B4-C4 1 3.57 0.23 2.475 2.03
Grid C4-F4 1 3.53 0.23 2.475 2.01
Grid A5-B5 1 3.56 0.23 2.475 2.03
Grid B5-C5 1 3.57 0.23 2.475 2.03
Grid C5-F5 1 3.53 0.23 2.475 2.01
Grid D5'-F5' 1 3.00 0.23 2.475 1.71
Grid A6-B6 1 3.56 0.23 2.475 2.03
Grid B7-D7 1 4.28 0.23 2.475 2.44
Grid D7-F7 1 3.00 0.23 1.2 0.83
Grid A8-B8 1 3.56 0.23 2.475 2.03
Grid B8-D8 1 4.05 0.23 2.475 2.31
Grid D8-F8 1 2.78 0.23 2.475 1.58
Deductions
ED -2 1.05 0.23 2.10 -1.01
D -6 0.90 0.23 2.10 -2.61
Page 187
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Toilet Passage -2 0.90 0.23 2.10 -0.87
Kitchen Passage -2 0.90 0.23 1.20 -0.50
SC -2 1.50 0.23 1.35 -0.93
KW -4 1.20 0.23 1.00 -1.10
W -6 1.08 0.23 1.35 -2.01
W1 -6 1.20 0.23 1.35 -2.24
V -4 0.60 0.23 0.45 -0.25
Total Qty 59.17 Cum
Providing RCC loft (atta) 7.5cms thick with cement concrete design mix M20 using clean granite or trap jelly of 20mm
36 4.54 and down size with necessary reinforcements at 20cms centre to centre as per design including form work, centring,
curing, etc., complete (exclusive of cost of steel and fabrication charges).
Page 188
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Teaching Staff Quarters-1
Ground Floor Steel Fabrication RA BILL NO - 01
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Teaching Staff Quarters
Footings
F1
Bars-A 10 9 1 2 1.45 - 26.10 - - - -
Bars-B 10 10 1 2 1.30 - 26.00 - - - -
F2 - - - - - -
Bars-A 10 10 1 4 1.75 - 70.00 - - - -
Bars-B 10 11 1 4 1.55 - 68.20 - - - -
F3 - - - - - -
Bars-A 10 11 1 2 2.00 - 44.00 - - - -
Bars-B 10 13 1 2 1.80 - 46.80 - - - -
F4 - - - - - -
Bars-A 10 15 1 6 2.25 - 202.50 - - - -
Bars-B 10 17 1 6 2.05 - 209.10 - - - -
F5 - - - - - -
Bars-A 10 19 1 6 2.40 - 273.60 - - - -
Bars-B 10 21 1 6 2.20 - 277.20 - - - -
F6 - - - - - -
Bars-A 10 21 1 4 2.65 - 222.60 - - - -
Bars-B 10 23 1 4 2.45 - 225.40 - - - -
- - - - - -
Column Steel - - - - - -
Grid A1-C1 - - - - - -
Main Bars 12 8 1 1 2.90 - - 23.20 - - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Page 189
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid A3-C2 - - - - - -
Main Bars-1 16 4 1 1 3.10 - - - 12.40 - -
Main Bars-2 12 4 1 1 3.10 - - 12.40 - - -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid A4-C1 - - - - - -
Main Bars 12 8 1 1 3.40 - - 27.20 - - -
Rectangle Stirrups 8 18 1 1 1.19 21.42 - - - - -
Dimond Stirrups 8 18 1 1 0.95 17.10 - - - - -
Grid A5-C1 - - - - - -
Main Bars 12 8 1 1 3.40 - - 27.20 - - -
Rectangle Stirrups 8 18 1 1 1.19 21.42 - - - - -
Dimond Stirrups 8 18 1 1 0.95 17.10 - - - - -
Grid A6-C2 - - - - - -
Main Bars-1 16 4 1 1 3.70 - - - 14.80 - -
Main Bars-2 12 4 1 1 3.70 - - 14.80 - - -
Rectangle Stirrups 8 20 1 1 1.19 23.80 - - - - -
Dimond Stirrups 8 20 1 1 0.95 19.00 - - - - -
Grid A8-C1 - - - - - -
Main Bars 12 8 1 1 3.80 - - 30.40 - - -
Rectangle Stirrups 8 21 1 1 1.19 24.99 - - - - -
Dimond Stirrups 8 21 1 1 0.95 19.95 - - - - -
Grid B1-C2 - - - - - -
Main Bars-1 16 4 1 1 2.80 - - - 11.20 - -
Main Bars-2 12 4 1 1 2.80 - - 11.20 - - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid B3-C3 1 1 - - - - - -
Main Bars 16 8 1 1 3.10 - - - 24.80 - -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid B4-C2 - - - - - -
Main Bars-1 16 4 1 1 3.40 - - - 13.60 - -
Main Bars-2 12 4 1 1 3.40 - - 13.60 - - -
Rectangle Stirrups 8 18 1 1 1.19 21.42 - - - - -
Page 190
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dimond Stirrups 8 18 1 1 0.95 17.10 - - - - -
Grid B5-C2 - - - - - -
Main Bars-1 16 4 1 1 3.40 - - - 13.60 - -
Main Bars-2 12 4 1 1 3.40 - - 13.60 - - -
Rectangle Stirrups 8 18 1 1 1.19 21.42 - - - - -
Dimond Stirrups 8 18 1 1 0.95 17.10 - - - - -
Grid B6-C3 - - - - - -
Main Bars 16 8 1 1 3.70 - - - 29.60 - -
Rectangle Stirrups 8 17 1 1 1.19 20.23 - - - - -
Dimond Stirrups 8 17 1 1 0.95 16.15 - - - - -
Grid B8-C2 - - - - - -
Main Bars-1 16 4 1 1 3.80 - - - 15.20 - -
Main Bars-2 12 4 1 1 3.80 - - 15.20 - - -
Rectangle Stirrups 8 20 1 1 1.19 23.80 - - - - -
Dimond Stirrups 8 20 1 1 0.95 19.00 - - - - -
Grid C4-C3 - - - - - -
Main Bars 16 8 1 1 3.10 - - - 24.80 - -
Rectangle Stirrups 8 14 1 1 1.19 16.66 - - - - -
Dimond Stirrups 8 14 1 1 0.95 13.30 - - - - -
Grid C5-C3 - - - - - -
Main Bars 16 8 1 1 3.10 - - - 24.80 - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid D1-C2 - - - - - -
Main Bars-1 16 4 1 1 2.80 - - - 11.20 - -
Main Bars-2 12 4 1 1 2.80 - - 11.20 - - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid D2-C3 - - - - - -
Main Bars 16 8 1 1 2.90 - - - 23.20 - -
Rectangle Stirrups 8 13 1 1 1.19 15.47 - - - - -
Dimond Stirrups 8 13 1 1 0.95 12.35 - - - - -
Grid D7-C3 - - - - - -
Main Bars 16 8 1 1 3.40 - - - 27.20 - -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Page 191
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid D8-C2 - - - - - -
Main Bars-1 16 4 1 1 3.60 - - - 14.40 - -
Main Bars-2 12 4 1 1 3.60 - - 14.40 - - -
Rectangle Stirrups 8 19 1 1 1.19 22.61 - - - - -
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
Grid F1-C1 - - - - - -
Main Bars 12 8 1 1 2.80 - - 22.40 - - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid F2-C2 - - - - - -
Main Bars-1 16 4 1 1 2.90 - - - 11.60 - -
Main Bars-2 12 4 1 1 2.90 - - 11.60 - - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid F4-C3 - - - - - -
Main Bars 16 8 1 1 3.00 - - - 24.00 - -
Rectangle Stirrups 8 14 1 1 1.19 16.66 - - - - -
Dimond Stirrups 8 14 1 1 0.95 13.30 - - - - -
Grid F5-C3 - - - - - -
Main Bars 16 8 1 1 3.10 - - - 24.80 - -
Rectangle Stirrups 8 14 1 1 1.19 16.66 - - - - -
Dimond Stirrups 8 14 1 1 0.95 13.30 - - - - -
Grid F7-C2 - - - - - -
Main Bars-1 16 4 1 1 3.40 - - - 13.60 - -
Main Bars-2 12 4 1 1 3.40 - - 13.60 - - -
Rectangle Stirrups 8 18 1 1 1.19 21.42 - - - - -
Dimond Stirrups 8 18 1 1 0.95 17.10 - - - - -
Grid F8-C1 - - - - - -
Main Bars 12 8 1 1 3.50 - - 28.00 - - -
Rectangle Stirrups 8 19 1 1 1.19 22.61 - - - - -
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
- - - - - -
Plinth Beam Steel - - - - - -
Grid A1-A3,PB1 - - - - - -
Page 192
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid A3-A4,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.94 - - - 15.76 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid A5-A6,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.94 - - - 15.76 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 77 1 1 1.27 97.79 - - - - -
Grid A6-A8,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid A'3'-A'4,PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 2.23 - - 13.35 - - -
Stirrups 150mmc/c 8 10 1 1 1.27 12.70 - - - - -
Stirrups 200mmc/c 8 4 1 1 1.27 5.08 - - - - -
Grid A'5-A'5',PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 2.23 - - 13.38 - - -
Stirrups 150mmc/c 8 10 1 1 1.27 12.70 - - - - -
Stirrups 200mmc/c 8 4 1 1 1.27 5.08 - - - - -
Grid B1-B3,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Page 193
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B3-B4,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.94 - - - 15.76 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid B5-B6,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.94 - - - 15.76 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid B6-B8,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid C4-C5,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 3.25 - - - 13.00 - -
Extra Bars at End Support 16 2 1 2 1.58 - - - 6.32 - -
Extra Bars at Mid Span 16 2 1 1 2.9 - - - 5.80 - -
Stirrups 150mmc/c 8 14 1 1 1.27 17.78 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Grid D1-D2,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.76 - - - 15.04 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid D2-D4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 5.08 - - - 20.32 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Page 194
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 22 1 1 1.27 27.94 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid D5-D7,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 5.08 - - - 20.32 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 22 1 1 1.27 27.94 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid D7-D8,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.76 - - - 15.04 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid F1-F2,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.98 - - - 15.92 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid F2-F4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 5.08 - - - 20.32 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 22 1 1 1.27 27.94 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid F4-F5,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.25 - - - 13.00 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 14 1 1 1.27 17.78 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Grid F5-F7,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 5.08 - - - 20.32 - -
Page 195
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 22 1 1 1.27 27.94 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid F7-F8,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.76 - - - 15.04 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid A1-B1,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.76 - - - 19.04 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B1-D1,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 5.48 - - - 21.92 - -
Extra Bars at End Support 16 2 1 2 1.58 - - - 6.32 - -
Extra Bars at Mid Span 16 2 1 1 2.9 - - - 5.80 - -
Stirrups 150mmc/c 8 24 1 1 1.27 30.48 - - - - -
Stirrups 200mmc/c 8 9 1 1 1.27 11.43 - - - - -
Grid D1-F1,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.98 - - - 15.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid B2-D2,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 5.28 - - - 21.12 - -
Extra Bars at End Support 16 2 1 2 1.58 - - - 6.32 - -
Extra Bars at Mid Span 16 2 1 1 2.9 - - - 5.80 - -
Stirrups 150mmc/c 8 23 1 1 1.27 29.21 - - - - -
Stirrups 200mmc/c 8 9 1 1 1.27 11.43 - - - - -
Grid D2-F2,PB1 - - - - - -
Page 196
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Top & Bottom Bars 16 4 1 1 3.98 - - - 15.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid A3-B3,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.76 - - - 19.04 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid A3'-B3',PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 4.76 - - 28.56 - - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid D3'-F3',PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 3.79 - - 22.74 - - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid A4-B4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.78 - - - 19.12 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B4-C4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.78 - - - 19.12 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid C4-F4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.73 - - - 18.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Page 197
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid A5-B5,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.76 - - - 19.04 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B5-C5,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.78 - - - 19.12 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid C5-F5,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.73 - - - 18.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid A5'-B5',PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 4.78 - - 28.68 - - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid D5'-F5',PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 3.78 - - 22.68 - - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid A6-B6,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.76 - - - 19.04 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B7-D7,PB2 - - - - - -
Page 198
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Top & Bottom Bars 16 4 1 1 5.26 - - - 21.04 - -
Extra Bars at End Support 16 2 1 2 1.58 - - - 6.32 - -
Extra Bars at Mid Span 16 2 1 1 2.9 - - - 5.80 - -
Stirrups 150mmc/c 8 23 1 1 1.27 29.21 - - - - -
Stirrups 200mmc/c 8 9 1 1 1.27 11.43 - - - - -
Grid D7-F7,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.98 - - - 15.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid A8-B8,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.76 - - - 19.04 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B8-D8,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 5.25 - - - 21.00 - -
Extra Bars at End Support 16 2 1 2 1.58 - - - 6.32 - -
Extra Bars at Mid Span 16 2 1 1 2.9 - - - 5.80 - -
Stirrups 150mmc/c 8 23 1 1 1.27 29.21 - - - - -
Stirrups 200mmc/c 8 9 1 1 1.27 11.43 - - - - -
Grid D8-F8,,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.98 - - - 15.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Column Steel - - - - - -
C1 - - - - - -
Main Bars 12 8 1 6 3.15 - - 151.20 - - -
Rectangle Stirrups 8 19 1 6 1.35 153.90 - - - - -
Dimond Stirrups 8 19 1 6 0.95 108.30 - - - - -
C2 - - - - - -
Page 199
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Main Bars-1 16 4 1 10 3.15 - - - 126.00 - -
Main Bars-2 12 4 1 10 3.15 - - 126.00 - - -
Rectangle Stirrups 8 19 1 10 1.35 256.50 - - - - -
Dimond Stirrups 8 19 1 10 0.95 180.50 - - - - -
C3 - - - - - -
Main Bars 16 8 1 8 3.15 - - - 201.60 - -
Rectangle Stirrups 8 17 1 8 1.35 183.60 - - - - -
Dimond Stirrups 8 17 1 8 0.95 129.20 - - - - -
- - - - - -
Lintle Steel - - - - - -
Grid A1-A3,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.74 - 23.70 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid A3-A4,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 3.79 - 18.96 - - - -
Stirrups at 200mm C/C 8 20 1 1 0.71 14.20 - - - - -
Grid A5-A6,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 3.79 - 18.96 - - - -
Stirrups at 200mm C/C 8 20 1 1 0.71 14.20 - - - - -
Grid A6-A8,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.74 - 23.70 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid B1-B3,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.74 - 23.70 - - - -
Stirrups at 200mm C/C 8 20 1 1 0.71 14.20 - - - - -
Grid B3-B4,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 3.79 - 18.96 - - - -
Stirrups at 200mm C/C 8 20 1 1 0.71 14.20 - - - - -
Grid B5-B6,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 3.79 - 18.96 - - - -
Stirrups at 200mm C/C 8 20 1 1 0.71 14.20 - - - - -
Grid B6-B8,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.74 - 23.70 - - - -
Stirrups at 200mm C/C 8 16 1 1 0.71 11.36 - - - - -
Grid C4-C5,L1 - - - - - -
Page 200
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Top & Bottem Bars 10 5 1 1 3.10 - 15.51 - - - -
Stirrups at 200mm C/C 8 16 1 1 0.71 11.36 - - - - -
Grid D1-D2,L2 - - - - - -
Top & Bottem Bars 10 4 1 1 3.61 - 14.44 - - - -
Stirrups at 200mm C/C 8 19 1 1 0.71 13.49 - - - - -
Grid D3'-D4,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 1.81 - 9.05 - - - -
Stirrups at 200mm C/C 8 10 1 1 0.71 7.10 - - - - -
Grid D5-D5',L1 - - - - - -
Top & Bottem Bars 10 5 1 1 1.81 - 9.05 - - - -
Stirrups at 200mm C/C 8 10 1 1 0.71 7.10 - - - - -
Grid D7-D8,L2 - - - - - -
Top & Bottem Bars 10 4 1 1 3.61 - 14.44 - - - -
Stirrups at 200mm C/C 8 19 1 1 0.71 13.49 - - - - -
Grid F1-F2,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 3.83 - 19.15 - - - -
Stirrups at 200mm C/C 8 20 1 1 0.71 14.20 - - - - -
Grid F2-F4,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.92 - 24.60 - - - -
Stirrups at 200mm C/C 8 25 1 1 0.71 17.75 - - - - 12.60
Grid F5-F7,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.92 - 24.60 - - - -
Stirrups at 200mm C/C 8 25 1 1 0.71 17.75 - - - - 12.60
Grid F7-F8,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 3.83 - 19.15 - - - -
Stirrups at 200mm C/C 8 20 1 1 0.71 14.20 - - - - -
Grid A1-B1,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.61 - 23.05 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid B1-D1,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 5.33 - 26.65 - - - -
Stirrups at 200mm C/C 8 27 1 1 0.71 19.17 - - - - -
Grid D1-F1,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 3.83 - 19.15 - - - -
Stirrups at 200mm C/C 8 20 1 1 0.71 14.20 - - - - -
Page 201
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid B2-D2,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 5.11 - 25.55 - - - -
Stirrups at 200mm C/C 8 26 1 1 0.71 18.46 - - - - -
Grid A3-B3,L2 - - - - - -
Top & Bottem Bars 10 4 1 1 4.61 - 18.44 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid D3'-F3',L1 - - - - - -
Top & Bottem Bars 10 5 1 1 3.61 - 18.05 - - - -
Stirrups at 200mm C/C 8 19 1 1 0.71 13.49 - - - - -
Grid A4-B4,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.61 - 23.05 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid B4-C4,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.62 - 23.08 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid C4-F4,L2 - - - - - -
Top & Bottem Bars 10 4 1 1 4.58 - 18.32 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid A5-B5,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.61 - 23.05 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid B5-C5,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.62 - 23.08 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid C5-F5,L2 - - - - - -
Top & Bottem Bars 10 4 1 1 4.58 - 18.32 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid D5'-F5',L1 - - - - - -
Top & Bottem Bars 10 5 1 1 3.61 - 18.05 - - - -
Stirrups at 200mm C/C 8 19 1 1 0.71 13.49 - - - - -
Grid A6-B6,L2 - - - - - -
Top & Bottem Bars 10 4 1 1 4.61 - 18.44 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid B7-D7,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 5.11 - 25.55 - - - -
Page 202
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups at 200mm C/C 8 26 1 1 0.71 18.46 - - - - -
Grid A8-B8,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 4.61 - 23.05 - - - -
Stirrups at 200mm C/C 8 24 1 1 0.71 17.04 - - - - -
Grid B8-D8,L1 - - - - - -
Top & Bottem Bars 10 5 1 1 5.10 - 25.50 - - - -
Stirrups at 200mm C/C 8 26 1 1 0.71 18.46 - - - - -
Grid D8-F8,L1 - - - - - -
Top & Bottem Bars 10 8 1 1 3.83 - 30.64 - - - -
Stirrups at 200mm C/C 8 20 1 1 0.71 14.20 - - - - -
Chejja Steel - - - - - -
W - - - - - -
Main Bars 8 15 1 4 1.30 78.00 - - - - -
Distribution Bars 8 3 1 4 2.10 25.20 - - - - -
W1 - - - - - -
Main Bars 8 13 1 4 1.30 67.60 - - - - -
Distribution Bars 8 3 1 4 1.80 21.60 - - - - -
KW - - - - - -
Main Bars 8 13 1 4 1.30 67.60 - - - - -
Distribution Bars 8 3 1 4 1.80 21.60 - - - - -
Loft Steel - - - - - -
Bed Room-1 - - - - - -
Main Bars 8 23 1 2 1.30 59.80 - - - - -
Distribution Bars 8 3 1 2 3.23 19.38 - - - - -
Bed Room-2 - - - - - -
Main Bars 8 23 1 2 1.30 59.80 - - - - -
Distribution Bars 8 3 1 2 3.00 18.00 - - - - -
Total Length In mts 4,329.90 2,413.14 696.59 1,655.32 - 25.21
Unit Wt/mt 0.395 0.617 0.888 1.580 2.460 3.858
Total Reinforcement Qty 1,710.31 1,488.91 618.57 2,615.41 - 97.24 6,530.44 Kgs
Total Weight Say MT 6.53 MT
Page 203
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Teaching Staff Quarters-2
Ground Floor RA Bill-01
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2-2.2 : Earthwork excavation for foundation of buildings, water supply, sanitary lines and electrical conduits either
in pits or in trenches 1.5m and above in width, in hard soil not exceeding 1.5 m. in depth including dressing the bottom
4 2.4
and sides of pits and trenches, stacking the excavated soil clear from edges of excavation with lead upto 50 m. after
breaking of clods complete as per specifications. specification. No. KBS 2.1(b) / 2.3.5
Earth work excavation For Footings
Grid A1-F2 1 2.10 1.90 0.30 1.20 ###
Grid A3-F5 1 2.70 2.50 0.35 2.36 ###
Grid A4-F2 1 2.10 1.90 0.35 1.40 ###
Grid A5-F2 1 2.10 1.90 0.35 1.40 ###
Grid A6-F5 1 2.70 2.50 0.35 2.36 ###
Grid A8-F2 1 2.10 1.90 0.35 1.40 ###
Grid B1-F4 1 2.50 2.30 0.30 1.72 ###
Grid B3-F6 1 2.90 2.70 0.25 1.96 ###
Grid B4-F4 1 2.50 2.50 0.25 1.56 ###
Grid B5-F4 1 2.50 2.30 0.35 2.01 ###
Grid B6-F6 1 2.90 2.70 0.35 2.74 ###
Grid B8-F4 1 2.50 2.30 0.30 1.72 ###
Grid C4-F5 1 2.70 2.50 0.25 1.69 ###
Grid C5-F5 1 2.70 2.50 0.30 2.03 ###
Grid D1-F3 1 2.30 2.10 0.35 1.69 ###
Grid D2-F6 1 2.90 2.70 0.30 2.35 ###
Grid D7-F6 1 2.90 2.70 0.35 2.74 ###
Page 204
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D8-F3 1 2.30 2.10 0.35 1.69 ###
Grid F1-F1 1 1.85 1.70 0.30 0.94 ###
Grid F2-F4 1 2.50 2.30 0.25 1.44 ###
Grid F4-F5 1 2.70 2.50 0.25 1.69 ###
Grid F5-F5 1 2.70 2.50 0.30 2.03 ###
Grid F7-F4 1 2.50 2.30 0.35 2.01 ###
Grid F8-F1 1 1.85 1.70 0.35 1.10 ###
Deductions
Grid F1-A1 -1 6.75 1.15 0.30 -2.33
Grid A1-A4 -1 4.23 1.15 0.25 -1.22
Grid A4-C4 -1 4.95 1.15 0.25 -1.42
Grid C4-C5 -1 3.27 1.15 0.25 -0.94
Grid C5-A5 -1 4.95 1.15 0.30 -1.71
Grid A5-A8 -1 4.23 1.15 0.30 -1.46
Page 205
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A8-F8 -1 6.75 1.15 0.25 -1.94
Grid F1-F8 -1 10.96 1.15 0.30 -3.78
Total Qty 60.55 Cum
KSRB 2-2.4 : Excavation 1.5m and above in width in soft rock without blasting for foundation of buildings, water supply,
sanitary lines and electrical conduits either in pits or in trenches not exceeding 1.5 m. in depth, stacking the excavated
5 2.6
stuff from edges of excavation with lead upto 50m including cost of explosives, labour and HOM of equipment complete
as per specifications. specification. No. KBS 2.1.C / 2.9.4 / 2.18 / 2.19
Page 206
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F4-F5 1 2.70 2.50 1.55 10.46
Grid F5-F5 1 2.70 2.50 1.50 10.13
Grid F7-F4 1 2.50 2.30 1.45 8.34
Grid F8-F1 1 1.85 1.70 1.45 4.56
Earth Work For SSM
Grid F1-A1 1 12.84 1.15 0.45 6.64
Grid A1-A4 1 6.80 1.15 0.50 3.91
Grid A4-C4 1 8.88 1.15 0.50 5.10
Grid C4-C5 1 3.69 1.15 0.50 2.12
Grid C5-A5 1 8.88 1.15 0.45 4.59
Grid A5-A8 1 6.80 1.15 0.45 3.52
Grid A8-F8 1 12.84 1.15 0.50 7.38
Grid F1-F8 1 18.87 1.15 0.45 9.77
Grid A'1-A'4 1 5.70 1.15 0.40 2.62
Grid A'5-A'8 1 5.70 1.15 0.40 2.62
Grid A-A' in 1,4,5,8 4 1.20 1.15 0.40 2.21
Deductions
Grid F1-A1 -1 6.75 1.15 0.45 -3.49
Grid A1-A4 -1 4.23 1.15 0.50 -2.43
Grid A4-C4 -1 4.95 1.15 0.50 -2.85
Grid C4-C5 -1 3.27 1.15 0.50 -1.88
Grid C5-A5 -1 4.95 1.15 0.45 -2.56
Grid A5-A8 -1 4.23 1.15 0.45 -2.19
Grid A8-F8 -1 6.75 1.15 0.50 -3.88
Grid F1-F8 -1 10.96 1.15 0.45 -5.67
Total Qty 232.02 Cum
Page 207
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB-3.2: Providing and injecting chemical emulsion for Preconstructional Anti-Termite Treatment, creating continuous
chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth
filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of
7 3.2 consolidated earth on which apron is to be laid, surrounding of pipes and conduits, with chloropyriphos emulsifiable
concentrates of 20% concentration, including cost of chemical, diluting in water to one percent concentration, labour,
HOM of equipments, complete as per specifications. (Plinth area of the building at ground floor only shall be measured )
Specification No. KBS : 3.2.6 / 3.2.7
Anti-Termite Treatment
Grid A1-A4,F1-F4 1 8.00 13.88 111.04
Grid A5-A8,F5-F8 1 2.96 4.43 13.12
Grid C4-C5,F4-F5 1 8.00 13.88 111.04
Total Qty 235.20 Sqm
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 with OPC cement @ 220kgs, with
40mm and down size graded granite metal coarse aggregates @0.892cum and fine aggregates @ 0.465cum machine
8 4.2
mixed, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation including
cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2
Page 208
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid C4-C5 1 3.69 0.75 0.10 0.28
Grid C5-A5 1 8.88 0.75 0.10 0.67
Grid A5-A8 1 6.80 0.75 0.10 0.51
Grid A8-F8 1 12.84 0.75 0.10 0.96
Grid F1-F8 1 18.87 0.75 0.10 1.42
Grid A'1-A'4 1 6.50 1.15 0.10 0.75
Grid A'5-A'8 1 6.50 1.15 0.10 0.75
Grid A-A' in 1,4,5,8 4 1.20 1.15 0.10 0.55
Deductions of Footings
Grid F1-A1 -1 6.75 0.75 0.10 -0.51
Grid A1-A4 -1 4.23 0.75 0.10 -0.32
Grid A4-C4 -1 4.95 0.75 0.10 -0.37
Grid C4-C5 -1 3.27 0.75 0.10 -0.25
Grid C5-A5 -1 4.95 0.75 0.10 -0.37
Grid A5-A8 -1 4.23 0.75 0.10 -0.32
Grid A8-F8 -1 6.75 0.75 0.10 -0.51
Grid F1-F8 -1 10.96 0.75 0.10 -0.82
PCC BELOW PLINTH BEAM
Grid A'3'-A'4, 1 0.99 0.45 0.10 0.04
Grid A'5-A'5' 1 0.99 0.45 0.10 0.04
Grid B1-B3 1 4.13 0.45 0.10 0.19
Grid B3-B4 1 3.18 0.45 0.10 0.14
Grid B5-B6 1 3.18 0.45 0.10 0.14
Grid B6-B8 1 4.13 0.45 0.10 0.19
Grid D1-D2 1 3.00 0.45 0.10 0.14
Grid D2-D4 1 4.31 0.45 0.10 0.19
Grid D5-D7 1 4.31 0.45 0.10 0.19
Grid D7-D8 1 3.00 0.45 0.10 0.14
Page 209
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid B2-D2 1 4.28 0.45 0.10 0.19
Grid D2-F2 1 3.00 0.45 0.10 0.14
Grid A3-B3 1 3.56 0.45 0.10 0.16
Grid A3'-B3' 1 4.00 0.45 0.10 0.18
Grid D3'-F3' 1 3.00 0.45 0.10 0.14
Grid C4-F4 1 3.53 0.45 0.10 0.16
Grid C5-F5 1 3.53 0.45 0.10 0.16
Grid A5'-B5' 1 4.00 0.45 0.10 0.18
Grid D5'-F5' 1 3.00 0.45 0.10 0.14
Grid A6-B6 1 3.56 0.45 0.10 0.16
Grid B7-D7 1 4.28 0.45 0.10 0.19
Grid D7-F7 1 3.00 0.45 0.10 0.14
Flooring PCC
Bed Room-1 2 4.13 4.00 0.10 3.30
Bed Room-2 2 3.00 4.50 0.10 2.70
Kitchen 2 3.00 3.00 0.10 1.80
Dining 2 3.00 2.14 0.10 1.28
Living 2 4.31 5.63 0.10 4.85
W.C 2 1.55 1.55 0.10 0.48
Bath 2 1.55 2.35 0.10 0.73
Passage 2 1.51 4.00 0.10 1.21
Staircase 2 2.50 3.95 0.10 1.98
Total Qty 35.41 Cum
KSRB 5.2-3 : Providing and constructing granite / trap / basalt size stone masonry in foundation cement mortar 1:6,
9 5.6 stone hammerd dressed in courses not less than 20 cms high, bond stones at two m. apart in each course including cost
of materials, labour, curing complete as per specifications. KBS 5.1.13
SSM In Foundations
Page 210
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F1-A1 1 12.84 0.60 0.60 4.62
Grid A1-A4 1 6.80 0.60 0.60 2.45
Grid A4-C4 1 8.88 0.60 0.60 3.20
Grid C4-C5 1 2.34 0.60 0.60 0.84
Grid C5-A5 1 8.88 0.60 0.60 3.20
Grid A5-A8 1 6.80 0.60 0.60 2.45
Grid A8-F8 1 12.84 0.60 0.60 4.62
Grid F1-F8 1 18.87 0.60 0.60 6.79
Grid A'1-A'4 1 7.10 0.60 0.60 2.56
Grid A'5-A'8 1 7.10 0.60 0.60 2.56
Grid A-A' in 1,4,5,8 4 1.20 0.60 0.60 1.73
Over Footings
Grid F1-F1 1 1.71 0.60 0.70 0.72
Grid D1-F3 1 1.90 0.60 0.60 0.68
Grid B1-F4 1 2.10 0.60 0.55 0.69
Grid A1-F2 1 1.71 0.60 0.65 0.67
Grid A3-F5 1 2.30 0.60 0.50 0.69
Grid A4-F2 1 1.71 0.60 0.65 0.67
Grid B4-F4 1 2.10 0.60 0.55 0.69
Grid C4-F5 1 2.54 0.60 0.50 0.76
Grid C5-F5 1 2.54 0.60 0.50 0.76
Grid B5-F4 1 2.10 0.60 0.55 0.69
Grid A5-F2 1 1.71 0.60 0.65 0.67
Grid A6-F5 1 2.10 0.60 0.50 0.63
Grid A8-F2 1 1.71 0.60 0.65 0.67
Grid B8-F2 1 2.10 0.60 0.65 0.82
Grid D8-F3 1 1.90 0.60 0.60 0.68
Grid F8-F1 1 1.71 0.60 0.70 0.72
Page 211
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F7-F4 1 2.10 0.60 0.55 0.69
Grid F5-F5 1 2.10 0.60 0.50 0.63
Grid F4-F5 1 2.10 0.60 0.50 0.63
Grid F2-F4 1 2.10 0.60 0.55 0.69
Deduction of Column Quantity
Grid F1-C1 -1 0.23 0.45 1.35 -0.14 ###
Grid D1-C2 -1 0.23 0.45 1.20 -0.12 ###
Grid B1-C2 -1 0.23 0.45 1.35 -0.14 ###
Grid A1-C1 -1 0.23 0.45 1.35 -0.14 ###
Grid A3-C2 -1 0.23 0.45 1.20 -0.12 ###
Grid A4-C1 -1 0.23 0.45 1.35 -0.14 ###
Grid B4-C2 -1 0.23 0.45 1.25 -0.13 ###
Grid C4-C3 -1 0.23 0.45 1.25 -0.13 ###
Grid C5-C3 -1 0.23 0.45 1.25 -0.13 ###
Grid B5-C2 -1 0.23 0.45 1.25 -0.13 ###
Grid A5-C1 -1 0.23 0.45 1.20 -0.12 ###
Grid A6-C2 -1 0.23 0.45 1.20 -0.12 ###
Grid A8-C1 -1 0.23 0.45 1.30 -0.13 ###
Grid B8-C2 -1 0.23 0.45 1.30 -0.13 ###
Grid D8-C2 -1 0.23 0.45 1.40 -0.14 ###
Grid F8-C1 -1 0.23 0.45 1.25 -0.13 ###
Grid F7-C2 -1 0.23 0.45 1.20 -0.12 ###
Grid F5-C3 -1 0.23 0.45 1.20 -0.12 ###
Grid F4-C3 -1 0.23 0.45 1.25 -0.13 ###
Grid F2-C2 -1 0.23 0.45 1.40 -0.14 ###
Total Qty 46.24 Cum
Page 212
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 5.3-3 : Providing and constructing granite / trap / basalt size stone masonry in basement with cement mortar 1:6,
10 5.9 edges of stones chistle dressed in courses not less than 15 cms high, bond stones at two m. apart in each course
including cost of materials, labour, curing complete as per specifications. KBS 5.1.13
SSM in Basement
Grid F1-A1 1 12.84 0.45 0.45 2.60 ###
Grid A1-A4 1 6.80 0.45 0.60 1.84 ###
Grid A4-C4 1 8.88 0.45 0.75 3.00 ###
Grid C4-C5 1 2.34 0.45 0.55 0.58 ###
Grid C5-A5 1 8.88 0.45 0.75 3.00 ###
Grid A5-A8 1 6.80 0.45 1.10 3.37 ###
Grid A8-F8 1 12.84 0.45 1.20 6.93 ###
Grid F1-F8 1 18.87 0.45 0.65 5.52 ###
Grid A'1-A'4 1 7.10 0.45 1.05 3.35 ###
Grid A'5-A'8 1 7.10 0.45 1.55 4.95 ###
Grid A-A' in 1,4,5,8 4 1.20 0.45 1.20 2.59 ###
Deduction For Columns
Grid A1-C1 -1 0.23 0.45 0.42 -0.04 Grid A1-
Grid A3-C2 -1 0.23 0.45 0.62 -0.06 Grid A3-
Grid A4-C1 -1 0.23 0.45 0.92 -0.10 Grid A4-
Grid A5-C1 -1 0.23 0.45 0.92 -0.10 Grid A5-
Grid A6-C2 -1 0.23 0.45 1.22 -0.13 Grid A6-
Grid A8-C1 -1 0.23 0.45 1.37 -0.14 Grid A8-
Grid B1-C2 -1 0.23 0.45 0.32 -0.03 Grid B1-
Grid B4-C2 -1 0.23 0.45 0.92 -0.10 Grid B4-
Grid B5-C2 -1 0.23 0.45 0.92 -0.10 Grid B5-
Grid B8-C2 -1 0.23 0.45 1.32 -0.14 Grid B8-
Grid C4-C3 -1 0.23 0.45 0.62 -0.06 Grid C4-
Grid C5-C3 -1 0.23 0.45 0.67 -0.07 Grid C5-
Page 213
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D1-C2 -1 0.23 0.45 0.35 -0.04 Grid D1-
Grid D8-C2 -1 0.23 0.45 1.17 -0.12 Grid D8-
Grid F1-C1 -1 0.23 0.45 0.37 -0.04 Grid F1-
Grid F2-C2 -1 0.23 0.45 0.42 -0.04 Grid F2-
Grid F4-C3 -1 0.23 0.45 0.57 -0.06 Grid F4-
Grid F5-C3 -1 0.23 0.45 0.62 -0.06 Grid F5-
Grid F7-C2 -1 0.23 0.45 0.97 -0.10 Grid F7-
Grid F8-C1 -1 0.23 0.45 1.07 -0.11 Grid F8-
Total Qty 36.09 Cum
KSRB 2.3 : Filling available excavated earth ( excluding rock ) in sides of foundations upto plinth in layers not exceeding
12 2.10 20 cms. in depth, compacting each deposited layer by ramming after watering with lead upto 50 m. and lift upto 1.5 m.
including cost of all labour complete as per specifications. specification. No. KBS 2.9
Page 214
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2.5 : Earthwork excavation ( in deposited soil ) and filling sides of foundation upto plinth in layers not exceeding
13 2.12 20 cms. in depth, compacting each deposited layer by ramming after watering with all lead and lift including cost of all
labour complete as per specifications. specification. No. KBS 2.9.9 / 2.9.10.1 / 2.1.1
Page 215
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A5-C1 1 0.23 0.45 2.65 0.27 Grid A5-
Grid A6-C2 1 0.23 0.45 2.80 0.29 Grid A6-
Grid A8-C1 1 0.23 0.45 3.10 0.32 Grid A8-
Grid B1-C2 1 0.23 0.45 1.95 0.20 Grid B1-
Grid B3-C3 1 0.23 0.45 2.15 0.22 Grid B3-
Grid B4-C2 1 0.23 0.45 2.55 0.26 Grid B4-
Grid B5-C2 1 0.23 0.45 2.55 0.26 Grid B5-
Grid B6-C3 1 0.23 0.45 2.75 0.28 Grid B6-
Grid B8-C2 1 0.23 0.45 2.95 0.31 Grid B8-
Grid C4-C3 1 0.23 0.45 2.20 0.23 Grid C4-
Grid C5-C3 1 0.23 0.45 2.25 0.23 Grid C5-
Grid D1-C2 1 0.23 0.45 2.03 0.21 Grid D1-
Grid D2-C3 1 0.23 0.45 1.95 0.20 Grid D2-
Grid D7-C3 1 0.23 0.45 2.50 0.26 Grid D7-
Grid D8-C2 1 0.23 0.45 2.85 0.29 Grid D8-
Grid F1-C1 1 0.23 0.45 2.15 0.22 Grid F1-
Grid F2-C2 1 0.23 0.45 2.05 0.21 Grid F2-
Grid F4-C3 1 0.23 0.45 2.15 0.22 Grid F4-
Grid F5-C3 1 0.23 0.45 2.20 0.23 Grid F5-
Grid F7-C2 1 0.23 0.45 2.60 0.27 Grid F7-
Grid F8-C1 1 0.23 0.45 2.85 0.29 Grid F8-
Plinth Beam Concrete
Grid A1-A3,PB1 1 4.13 0.23 0.38 0.36
Grid A3-A4,PB3 1 3.18 0.23 0.38 0.28
Grid A5-A6,PB3 1 3.18 0.23 0.38 0.28
Grid A6-A8,PB1 1 4.13 0.23 0.38 0.36
Grid A'3'-A'4,PB4 1 1.44 0.23 0.38 0.13
Grid A'5-A'5',PB4 1 1.44 0.23 0.38 0.13
Page 216
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid B1-B3,PB3 1 4.13 0.23 0.38 0.36
Grid B3-B4,PB3 1 3.18 0.23 0.38 0.28
Grid B5-B6,PB3 1 3.18 0.23 0.38 0.28
Grid B6-B8,PB3 1 4.13 0.23 0.38 0.36
Grid C4-C5,PB2 1 2.49 0.23 0.38 0.22
Grid D1-D2,PB3 1 3.00 0.23 0.38 0.26
Grid D2-D4,PB1 1 4.31 0.23 0.38 0.38
Grid D5-D7,PB1 1 4.31 0.23 0.38 0.38
Grid D7-D8,PB3 1 3.00 0.23 0.38 0.26
Grid F1-F2,PB3 1 3.00 0.23 0.38 0.26
Grid F2-F4,PB1 1 4.09 0.23 0.38 0.36
Grid F4-F5,PB1 1 2.49 0.23 0.38 0.22
Grid F5-F7,PB1 1 4.09 0.23 0.38 0.36
Grid F7-F8,PB3 1 3.00 0.23 0.38 0.26
Grid A1-B1,PB1 1 3.56 0.23 0.38 0.31
Grid B1-D1,PB2 1 4.28 0.23 0.38 0.37
Grid D1-F1,PB1 1 2.78 0.23 0.38 0.24
Grid B2-D2,PB2 1 4.28 0.23 0.38 0.37
Grid D2-F2,PB1 1 3.00 0.23 0.38 0.26
Grid A3-B3,PB1 1 3.56 0.23 0.38 0.31
Grid A3'-B3',PB4 1 4.00 0.23 0.38 0.35
Grid D3'-F3',PB4 1 3.00 0.23 0.38 0.26
Grid A4-B4,PB1 1 3.56 0.23 0.38 0.31
Grid B4-C4,PB1 1 3.57 0.23 0.38 0.31
Grid C4-F4,PB1 1 3.53 0.23 0.38 0.31
Grid A5-B5,PB1 1 3.56 0.23 0.38 0.31
Grid B5-C5,PB1 1 3.57 0.23 0.38 0.31
Grid C5-F5,PB1 1 3.53 0.23 0.38 0.31
Page 217
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A5'-B5',PB4 1 4.00 0.23 0.38 0.35
Grid D5'-F5',PB4 1 3.00 0.23 0.38 0.26
Grid A6-B6,PB1 1 3.56 0.23 0.38 0.31
Grid B7-D7,PB2 1 4.28 0.23 0.38 0.37
Grid D7-F7,PB1 1 3.00 0.23 0.38 0.26
Grid A8-B8,PB1 1 3.56 0.23 0.38 0.31
Grid B8-D8,PB2 1 4.05 0.23 0.38 0.35
Grid D8-F8,,PB1 1 2.78 0.23 0.38 0.24
Total Qty 53.40 Cum
KSRB 4-1.6 ; Providing and laying in position plain cement concrete of mix 1:2:4 with cement @ 240kgs, with 20mm and
down size graded granite metal coarse aggregates @ 0.878 cum and fine aggregtes @ 0.53cum, machine mixed,
18 4.6
concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation, plinth and cills, ncluding cost of all
materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2
Coping Concrete
Grid A1-A3 1 4.13 0.45 0.075 0.14
Grid A3-A4 1 3.18 0.45 0.075 0.11
Grid A5-A6 1 3.18 0.45 0.075 0.11
Grid A6-A8 1 4.13 0.45 0.075 0.14
Grid C4-C5 1 2.49 0.45 0.075 0.08
Grid F1-F2 1 3.00 0.45 0.075 0.10
Grid F2-F4 1 4.09 0.45 0.075 0.14
Grid F4-F5 1 2.49 0.45 0.075 0.08
Grid F5-F7 1 4.09 0.45 0.075 0.14
Grid F7-F8 1 3.00 0.45 0.075 0.10
Grid A1-B1 1 3.56 0.45 0.075 0.12
Grid B1-D1 1 4.28 0.45 0.075 0.14
Grid D1-F1 1 2.78 0.45 0.075 0.09
Page 218
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A4-B4 1 3.56 0.45 0.075 0.12
Grid B4-C4 1 3.57 0.45 0.075 0.12
Grid A5-B5 1 3.56 0.45 0.075 0.12
Grid B5-C5 1 3.57 0.45 0.075 0.12
Grid A8-B8 1 3.56 0.45 0.075 0.12
Grid B8-D8 1 4.05 0.45 0.075 0.14
Grid D8-F8 1 2.78 0.45 0.075 0.09
Grid A'1-A'4 1 7.10 1.15 0.075 0.61
Grid A'5-A'8 1 7.10 1.15 0.075 0.61
Grid A-A' in 1,4,5,8 4 1.20 1.15 0.075 0.41
Total Qty 3.97 Cum
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
19 4.28 foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per
specificaitons. Specification No. KBS 4.6.2
Page 219
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
F1 2 2 1.25 0.30 1.50
2 2 1.10 0.30 1.32
F2 4 2 1.50 0.35 4.20
4 2 1.30 0.35 3.64
F3 2 2 1.70 0.40 2.72
2 2 1.50 0.40 2.40
F4 6 2 1.90 0.45 10.26
6 2 1.70 0.45 9.18
F5 6 2 2.00 0.50 12.00
6 2 1.80 0.50 10.80
F6 4 2 2.20 0.55 9.68
4 2 2.00 0.55 8.80
Total Qty 95.12 Sqm
KSRB 4-6.5 : Providing and removing centering, shuttering, strutting, propping etc., for columns, pillars, piers,
21 4.32 abutments, post and struts, square / rectangular / polygon in plan including cost of all materials, labour complete as per
specificaiton. Specification No. KBS 4.6.2
Page 220
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid B6-C3 1 1.36 2.75 3.74
Grid B8-C2 1 1.36 2.95 4.01
Grid C4-C3 1 1.36 2.20 2.99
Grid C5-C3 1 1.36 2.25 3.06
Grid D1-C2 1 1.36 2.03 2.76
Grid D2-C3 1 1.36 1.95 2.65
Grid D7-C3 1 1.36 2.50 3.40
Grid D8-C2 1 1.36 2.85 3.88
Grid F1-C1 1 1.36 2.15 2.92
Grid F2-C2 1 1.36 2.05 2.79
Grid F4-C3 1 1.36 2.15 2.92
Grid F5-C3 1 1.36 2.20 2.99
Grid F7-C2 1 1.36 2.60 3.54
Grid F8-C1 1 1.36 2.85 3.88
Total Qty 79.19 Sqm
KSRB 4-6.4 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
25 4.31 vertical surface such as walls at any thickness, including attached pilasters, buttresses, plinth and string courses cost of
all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2
Page 221
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid B5-B6,PB3 1 2 3.18 0.45 2.86
Grid B6-B8,PB3 1 2 4.13 0.45 3.72
Grid C4-C5,PB2 1 2 2.49 0.45 2.24
Grid D1-D2,PB3 1 2 3.00 0.45 2.70
Grid D2-D4,PB1 1 2 4.31 0.45 3.88
Grid D5-D7,PB1 1 2 4.31 0.45 3.88
Grid D7-D8,PB3 1 2 3.00 0.45 2.70
Grid F1-F2,PB3 1 2 3.00 0.45 2.70
Grid F2-F4,PB1 1 2 4.09 0.45 3.68
Grid F4-F5,PB1 1 2 2.49 0.45 2.24
Grid F5-F7,PB1 1 2 4.09 0.45 3.68
Grid F7-F8,PB3 1 2 3.00 0.45 2.70
Grid A1-B1,PB1 1 2 3.56 0.45 3.20
Grid B1-D1,PB2 1 2 4.28 0.45 3.85
Grid D1-F1,PB1 1 2 2.78 0.45 2.50
Grid B2-D2,PB2 1 2 4.28 0.45 3.85
Grid D2-F2,PB1 1 2 3.00 0.45 2.70
Grid A3-B3,PB1 1 2 3.56 0.45 3.20
Grid A3'-B3',PB4 1 2 4.00 0.45 3.60
Grid D3'-F3',PB4 1 2 3.00 0.45 2.70
Grid A4-B4,PB1 1 2 3.56 0.45 3.20
Grid B4-C4,PB1 1 2 3.57 0.45 3.21
Grid C4-F4,PB1 1 2 3.53 0.45 3.18
Grid A5-B5,PB1 1 2 3.56 0.45 3.20
Grid B5-C5,PB1 1 2 3.57 0.45 3.21
Grid C5-F5,PB1 1 2 3.53 0.45 3.18
Grid A5'-B5',PB4 1 2 4.00 0.45 3.60
Grid D5'-F5',PB4 1 2 3.00 0.45 2.70
Page 222
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid A6-B6,PB1 1 2 3.56 0.45 3.20
Grid B7-D7,PB2 1 2 4.28 0.45 3.85
Grid D7-F7,PB1 1 2 3.00 0.45 2.70
Grid A8-B8,PB1 1 2 3.56 0.45 3.20
Grid B8-D8,PB2 1 2 4.05 0.45 3.65
Grid D8-F8,,PB1 1 2 2.78 0.45 2.50
Shuttering For Pcc Below Plinth Beam
Grid A'3'-A'4, 1 2 0.99 0.10 0.20
Grid A'5-A'5' 1 2 0.99 0.10 0.20
Grid B1-B3 1 2 4.13 0.10 0.83
Grid B3-B4 1 2 3.18 0.10 0.64
Grid B5-B6 1 2 3.18 0.10 0.64
Grid B6-B8 1 2 4.13 0.10 0.83
Grid D1-D2 1 2 3.00 0.10 0.60
Grid D2-D4 1 2 4.31 0.10 0.86
Grid D5-D7 1 2 4.31 0.10 0.86
Grid D7-D8 1 2 3.00 0.10 0.60
Grid B2-D2 1 2 4.28 0.10 0.86
Grid D2-F2 1 2 3.00 0.10 0.60
Grid A3-B3 1 2 3.56 0.10 0.71
Grid A3'-B3' 1 2 4.00 0.10 0.80
Grid D3'-F3' 1 2 3.00 0.10 0.60
Grid C4-F4 1 2 3.53 0.10 0.71
Grid C5-F5 1 2 3.53 0.10 0.71
Grid A5'-B5' 1 2 4.00 0.10 0.80
Grid D5'-F5' 1 2 3.00 0.10 0.60
Grid A6-B6 1 2 3.56 0.10 0.71
Grid B7-D7 1 2 4.28 0.10 0.86
Page 223
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D7-F7 1 2 3.00 0.10 0.60
Shuttering For Coping Concrete
Grid A1-A3 1 2 4.13 0.075 0.62
Grid A3-A4 1 2 3.18 0.075 0.48
Grid A5-A6 1 2 3.18 0.075 0.48
Grid A6-A8 1 2 4.13 0.075 0.62
Grid C4-C5 1 2 2.49 0.075 0.37
Grid F1-F2 1 2 3.00 0.075 0.45
Grid F2-F4 1 2 4.09 0.075 0.61
Grid F4-F5 1 2 2.49 0.075 0.37
Grid F5-F7 1 2 4.09 0.075 0.61
Grid F7-F8 1 2 3.00 0.075 0.45
Grid A1-B1 1 2 3.56 0.075 0.53
Grid B1-D1 1 2 4.28 0.075 0.64
Grid D1-F1 1 2 2.78 0.075 0.42
Grid A4-B4 1 2 3.56 0.075 0.53
Grid B4-C4 1 2 3.57 0.075 0.53
Grid A5-B5 1 2 3.56 0.075 0.53
Grid B5-C5 1 2 3.57 0.075 0.53
Grid A8-B8 1 2 3.56 0.075 0.53
Grid B8-D8 1 2 4.05 0.075 0.61
Grid D8-F8 1 2 2.78 0.075 0.42
Grid A'1-A'4 1 2 7.10 0.075 1.07
Grid A'5-A'8 1 2 7.10 0.075 1.07
Grid A-A' in 1,4,5,8 4 2 1.20 0.075 0.72
Total Qty 157.51 Sqm
Page 224
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking,
placing in position, lapping and / or welding wherever required, tying with binding wire and anchoring to the adjoining
28 4.46.2
members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of
materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3
4.49
Total Qty 4.49 Tonne
Page 225
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Teaching Staff Quarters-2
Ground Floor Steel Fabrication RA BILL NO - 01
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Teaching Staff Quarters
Footings
F1
Bars-A 10 9 1 2 1.45 - 26.10 - - - -
Bars-B 10 10 1 2 1.30 - 26.00 - - - -
F2 - - - - - -
Bars-A 10 10 1 4 1.75 - 70.00 - - - -
Bars-B 10 11 1 4 1.55 - 68.20 - - - -
F3 - - - - - -
Bars-A 10 11 1 2 2.00 - 44.00 - - - -
Bars-B 10 13 1 2 1.80 - 46.80 - - - -
F4 - - - - - -
Bars-A 10 15 1 6 2.25 - 202.50 - - - -
Bars-B 10 17 1 6 2.05 - 209.10 - - - -
F5 - - - - - -
Bars-A 10 19 1 6 2.40 - 273.60 - - - -
Bars-B 10 21 1 6 2.20 - 277.20 - - - -
F6 - - - - - -
Bars-A 10 21 1 4 2.65 - 222.60 - - - -
Bars-B 10 23 1 4 2.45 - 225.40 - - - -
- - - - - -
Column Steel - - - - - -
Grid A1-C1 - - - - - -
Main Bars 12 8 1 1 3.00 - - 24.00 - - -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Page 226
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid A3-C2 - - - - - -
Main Bars-1 16 4 1 1 3.20 - - - 12.80 - -
Main Bars-2 12 4 1 1 3.20 - - 12.80 - - -
Rectangle Stirrups 8 17 1 1 1.19 20.23 - - - - -
Dimond Stirrups 8 17 1 1 0.95 16.15 - - - - -
Grid A4-C1 - - - - - -
Main Bars 12 8 1 1 3.50 - - 28.00 - - -
Rectangle Stirrups 8 19 1 1 1.19 22.61 - - - - -
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
Grid A5-C1 - - - - - -
Main Bars 12 8 1 1 3.50 - - 28.00 - - -
Rectangle Stirrups 8 19 1 1 1.19 22.61 - - - - -
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
Grid A6-C2 - - - - - -
Main Bars-1 16 4 1 1 3.80 - - - 15.20 - -
Main Bars-2 12 4 1 1 3.80 - - 15.20 - - -
Rectangle Stirrups 8 21 1 1 1.19 24.99 - - - - -
Dimond Stirrups 8 21 1 1 0.95 19.95 - - - - -
Grid A8-C1 - - - - - -
Main Bars 12 8 1 1 3.90 - - 31.20 - - -
Rectangle Stirrups 8 22 1 1 1.19 26.18 - - - - -
Dimond Stirrups 8 22 1 1 0.95 20.90 - - - - -
Grid B1-C2 - - - - - -
Main Bars-1 16 4 1 1 2.90 - - - 11.60 - -
Main Bars-2 12 4 1 1 2.90 - - 11.60 - - -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid B3-C3 1 1 - - - - - -
Main Bars 16 8 1 1 3.20 - - - 25.60 - -
Rectangle Stirrups 8 17 1 1 1.19 20.23 - - - - -
Dimond Stirrups 8 17 1 1 0.95 16.15 - - - - -
Grid B4-C2 - - - - - -
Main Bars-1 16 4 1 1 3.50 - - - 14.00 - -
Main Bars-2 12 4 1 1 3.50 - - 14.00 - - -
Rectangle Stirrups 8 19 1 1 1.19 22.61 - - - - -
Page 227
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
Grid B5-C2 - - - - - -
Main Bars-1 16 4 1 1 3.50 - - - 14.00 - -
Main Bars-2 12 4 1 1 3.50 - - 14.00 - - -
Rectangle Stirrups 8 19 1 1 1.19 22.61 - - - - -
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
Grid B6-C3 - - - - - -
Main Bars 16 8 1 1 3.80 - - - 30.40 - -
Rectangle Stirrups 8 18 1 1 1.19 21.42 - - - - -
Dimond Stirrups 8 18 1 1 0.95 17.10 - - - - -
Grid B8-C2 - - - - - -
Main Bars-1 16 4 1 1 3.90 - - - 15.60 - -
Main Bars-2 12 4 1 1 3.90 - - 15.60 - - -
Rectangle Stirrups 8 21 1 1 1.19 24.99 - - - - -
Dimond Stirrups 8 21 1 1 0.95 19.95 - - - - -
Grid C4-C3 - - - - - -
Main Bars 16 8 1 1 3.20 - - - 25.60 - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid C5-C3 - - - - - -
Main Bars 16 8 1 1 3.20 - - - 25.60 - -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid D1-C2 - - - - - -
Main Bars-1 16 4 1 1 2.90 - - - 11.60 - -
Main Bars-2 12 4 1 1 2.90 - - 11.60 - - -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid D2-C3 - - - - - -
Main Bars 16 8 1 1 3.00 - - - 24.00 - -
Rectangle Stirrups 8 14 1 1 1.19 16.66 - - - - -
Dimond Stirrups 8 14 1 1 0.95 13.30 - - - - -
Grid D7-C3 - - - - - -
Main Bars 16 8 1 1 3.50 - - - 28.00 - -
Rectangle Stirrups 8 17 1 1 1.19 20.23 - - - - -
Page 228
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dimond Stirrups 8 17 1 1 0.95 16.15 - - - - -
Grid D8-C2 - - - - - -
Main Bars-1 16 4 1 1 3.70 - - - 14.80 - -
Main Bars-2 12 4 1 1 3.70 - - 14.80 - - -
Rectangle Stirrups 8 20 1 1 1.19 23.80 - - - - -
Dimond Stirrups 8 20 1 1 0.95 19.00 - - - - -
Grid F1-C1 - - - - - -
Main Bars 12 8 1 1 2.90 - - 23.20 - - -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid F2-C2 - - - - - -
Main Bars-1 16 4 1 1 3.00 - - - 12.00 - -
Main Bars-2 12 4 1 1 3.00 - - 12.00 - - -
Rectangle Stirrups 8 16 1 1 1.19 19.04 - - - - -
Dimond Stirrups 8 16 1 1 0.95 15.20 - - - - -
Grid F4-C3 - - - - - -
Main Bars 16 8 1 1 3.10 - - - 24.80 - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid F5-C3 - - - - - -
Main Bars 16 8 1 1 3.20 - - - 25.60 - -
Rectangle Stirrups 8 15 1 1 1.19 17.85 - - - - -
Dimond Stirrups 8 15 1 1 0.95 14.25 - - - - -
Grid F7-C2 - - - - - -
Main Bars-1 16 4 1 1 3.50 - - - 14.00 - -
Main Bars-2 12 4 1 1 3.50 - - 14.00 - - -
Rectangle Stirrups 8 19 1 1 1.19 22.61 - - - - -
Dimond Stirrups 8 19 1 1 0.95 18.05 - - - - -
Grid F8-C1 - - - - - -
Main Bars 12 8 1 1 3.60 - - 28.80 - - -
Rectangle Stirrups 8 20 1 1 1.19 23.80 - - - - -
Dimond Stirrups 8 20 1 1 0.95 19.00 - - - - -
- - - - - -
Plinth Beam Steel - - - - - -
Grid A1-A3,PB1 - - - - - -
Page 229
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid A3-A4,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.94 - - - 15.76 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid A5-A6,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.94 - - - 15.76 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 77 1 1 1.27 97.79 - - - - -
Grid A6-A8,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid A'3'-A'4,PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 2.23 - - 13.35 - - -
Stirrups 150mmc/c 8 10 1 1 1.27 12.70 - - - - -
Stirrups 200mmc/c 8 4 1 1 1.27 5.08 - - - - -
Grid A'5-A'5',PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 2.23 - - 13.38 - - -
Stirrups 150mmc/c 8 10 1 1 1.27 12.70 - - - - -
Stirrups 200mmc/c 8 4 1 1 1.27 5.08 - - - - -
Grid B1-B3,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Page 230
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B3-B4,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.94 - - - 15.76 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid B5-B6,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.94 - - - 15.76 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid B6-B8,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid C4-C5,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 3.25 - - - 13.00 - -
Extra Bars at End Support 16 2 1 2 1.58 - - - 6.32 - -
Extra Bars at Mid Span 16 2 1 1 2.9 - - - 5.80 - -
Stirrups 150mmc/c 8 14 1 1 1.27 17.78 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Grid D1-D2,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.76 - - - 15.04 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid D2-D4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 5.08 - - - 20.32 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Page 231
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 22 1 1 1.27 27.94 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid D5-D7,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 5.08 - - - 20.32 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 22 1 1 1.27 27.94 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid D7-D8,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.76 - - - 15.04 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid F1-F2,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.98 - - - 15.92 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid F2-F4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 5.08 - - - 20.32 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 22 1 1 1.27 27.94 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid F4-F5,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.25 - - - 13.00 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 14 1 1 1.27 17.78 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Grid F5-F7,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 5.08 - - - 20.32 - -
Page 232
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 22 1 1 1.27 27.94 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid F7-F8,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.76 - - - 15.04 - -
Extra Bars at End Support 16 3 1 2 1.48 - - - 8.88 - -
Extra Bars at Mid Span 16 3 1 1 2.60 - - - 7.80 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid A1-B1,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.76 - - - 19.04 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B1-D1,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 5.48 - - - 21.92 - -
Extra Bars at End Support 16 2 1 2 1.58 - - - 6.32 - -
Extra Bars at Mid Span 16 2 1 1 2.9 - - - 5.80 - -
Stirrups 150mmc/c 8 24 1 1 1.27 30.48 - - - - -
Stirrups 200mmc/c 8 9 1 1 1.27 11.43 - - - - -
Grid D1-F1,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.98 - - - 15.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid B2-D2,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 5.28 - - - 21.12 - -
Extra Bars at End Support 16 2 1 2 1.58 - - - 6.32 - -
Extra Bars at Mid Span 16 2 1 1 2.9 - - - 5.80 - -
Stirrups 150mmc/c 8 23 1 1 1.27 29.21 - - - - -
Stirrups 200mmc/c 8 9 1 1 1.27 11.43 - - - - -
Grid D2-F2,PB1 - - - - - -
Page 233
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Top & Bottom Bars 16 4 1 1 3.98 - - - 15.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid A3-B3,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.76 - - - 19.04 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid A3'-B3',PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 4.76 - - 28.56 - - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid D3'-F3',PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 3.79 - - 22.74 - - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid A4-B4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.78 - - - 19.12 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B4-C4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.78 - - - 19.12 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid C4-F4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.73 - - - 18.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Page 234
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid A5-B5,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.76 - - - 19.04 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B5-C5,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.78 - - - 19.12 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid C5-F5,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.73 - - - 18.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid A5'-B5',PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 4.78 - - 28.68 - - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid D5'-F5',PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 3.78 - - 22.68 - - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid A6-B6,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.76 - - - 19.04 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B7-D7,PB2 - - - - - -
Page 235
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Top & Bottom Bars 16 4 1 1 5.26 - - - 21.04 - -
Extra Bars at End Support 16 2 1 2 1.58 - - - 6.32 - -
Extra Bars at Mid Span 16 2 1 1 2.9 - - - 5.80 - -
Stirrups 150mmc/c 8 23 1 1 1.27 29.21 - - - - -
Stirrups 200mmc/c 8 9 1 1 1.27 11.43 - - - - -
Grid D7-F7,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.98 - - - 15.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid A8-B8,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 4.76 - - - 19.04 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid B8-D8,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 5.25 - - - 21.00 - -
Extra Bars at End Support 16 2 1 2 1.58 - - - 6.32 - -
Extra Bars at Mid Span 16 2 1 1 2.9 - - - 5.80 - -
Stirrups 150mmc/c 8 23 1 1 1.27 29.21 - - - - -
Stirrups 200mmc/c 8 9 1 1 1.27 11.43 - - - - -
Grid D8-F8,,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.98 - - - 15.92 - -
Extra Bars at End Support 16 1 1 2 1.48 - - - 2.96 - -
Extra Bars at Mid Span 16 1 1 1 2.60 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Total Length In mts 2,397.47 1,691.50 428.19 1,338.12 - -
Unit Wt/mt 0.395 0.617 0.888 1.580 2.460 3.858
Total Reinforcement Qty 947.00 1,043.66 380.23 2,114.23 - - 4,485.12 Kgs
Total Weight Say MT 4.49 MT
Page 236
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:-Non-Teaching Staff Quarters
Ground Floor RA Bill-01
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2-2.2 : Earthwork excavation for foundation of buildings, water supply, sanitary lines and electrical conduits
either in pits or in trenches 1.5m and above in width, in hard soil not exceeding 1.5 m. in depth including dressing
4 2.4
the bottom and sides of pits and trenches, stacking the excavated soil clear from edges of excavation with lead
upto 50 m. after breaking of clods complete as per specifications. specification. No. KBS 2.1(b) / 2.3.5
Earth Work Excavation For Footings
Grid B1-F2 1 2.10 1.60 0.35 1.18
Grid C1-F5 1 2.60 2.40 0.30 1.87
Grid D1-F2 1 2.10 1.60 0.25 0.84
Grid E1-F2 1 2.10 1.60 0.40 1.34
Grid F1-F5 1 2.60 2.40 0.35 2.18
Grid G1-F2 1 2.10 1.60 0.35 1.18
Grid D2-F4 1 2.50 2.30 0.25 1.44
Grid E2-F4 1 2.50 2.30 0.30 1.72
Grid A3-F4 1 2.50 2.30 0.30 1.72
Grid C3-F6 1 2.80 2.60 0.25 1.82
Grid F3-F6 1 2.80 2.60 0.35 2.55
Grid H3-F4 1 2.50 2.30 0.30 1.72
Grid D4-F5 1 2.60 2.40 0.25 1.56
Grid E4-F5 1 2.60 2.40 0.30 1.87
Grid A5-F3 1 2.30 2.10 0.30 1.45
Grid C5-F6 1 2.80 2.60 0.30 2.18
Page 237
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F5-F6 1 2.80 2.60 0.35 2.55
Grid H5-F3 1 2.30 2.10 0.35 1.69
Grid B6-F1 1 1.85 1.70 0.25 0.79
Grid C6-F4 1 2.50 2.30 0.25 1.44
Grid D6-F5 1 2.60 2.40 0.30 1.87
Grid E6-F5 1 2.60 2.40 0.35 2.18
Grid F6-F4 1 2.50 2.30 0.35 2.01
Grid G6-F1 1 1.85 1.70 0.40 1.26
Earth Work Excavation For SSM
Grid B1-D1 1 6.64 1.15 0.35 2.67
Grid D1-D4 1 5.23 1.15 0.30 1.80
Grid D4-E4 1 2.72 1.15 0.25 0.78
Grid E4-E1 1 5.23 1.15 0.35 2.11
Grid E1-G1 1 6.64 1.15 0.35 2.67
Grid G1-G3 1 1.89 1.15 0.30 0.65
Grid H3-H5 1 1.53 1.15 0.30 0.53
Grid G5-G6 1 0.90 1.15 0.35 0.36
Grid B6-G6 1 15.54 1.15 0.30 5.36
Grid B5-B6 1 0.90 1.15 0.25 0.26
Grid A3-A5 1 1.53 1.15 0.30 0.53
Grid B1-B3 1 1.89 1.15 0.30 0.65
Grid B1'-D1' 1 4.33 1.15 0.30 1.49
Grid E1'-G1' 1 4.33 1.15 0.35 1.74
Grid 1-1' IN B,D,E,G 4 1.73 1.15 0.35 2.79
Deductions
Grid B1-D1 -1 3.95 1.15 0.35 -1.59
Grid D1-D4 -1 4.30 1.15 0.30 -1.48
Grid D4-E4 -1 2.30 1.15 0.25 -0.66
Page 238
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid E4-E1 -1 4.30 1.15 0.35 -1.73
Grid E1-G1 -1 3.95 1.15 0.35 -1.59
Grid B6-G6 -1 9.95 1.15 0.30 -3.43
Total Qty 54.33 Cum
KSRB 2-2.4 : Excavation 1.5m and above in width in soft rock without blasting for foundation of buildings, water
supply, sanitary lines and electrical conduits either in pits or in trenches not exceeding 1.5 m. in depth, stacking
5 2.6
the excavated stuff from edges of excavation with lead upto 50m including cost of explosives, labour and HOM of
equipment complete as per specifications. specification. No. KBS 2.1.C / 2.9.4 / 2.18 / 2.19
Earth Work Excavation For Footings
Grid B1-F2 1 2.10 1.60 1.45 4.87
Grid C1-F5 1 2.60 2.40 1.50 9.36
Grid D1-F2 1 2.10 1.60 1.55 5.21
Grid E1-F2 1 2.10 1.60 1.40 4.70
Grid F1-F5 1 2.60 2.40 1.45 9.05
Grid G1-F2 1 2.10 1.60 1.45 4.87
Grid D2-F4 1 2.50 2.30 1.55 8.91
Grid E2-F4 1 2.50 2.30 1.50 8.63
Grid A3-F4 1 2.50 2.30 1.50 8.63
Grid C3-F6 1 2.80 2.60 1.55 11.28
Grid F3-F6 1 2.80 2.60 1.45 10.56
Grid H3-F4 1 2.50 2.30 1.50 8.63
Grid D4-F5 1 2.60 2.40 1.55 9.67
Grid E4-F5 1 2.60 2.40 1.50 9.36
Grid A5-F3 1 2.30 2.10 1.50 7.25
Grid C5-F6 1 2.80 2.60 1.50 10.92
Grid F5-F6 1 2.80 2.60 1.45 10.56
Grid H5-F3 1 2.30 2.10 1.45 7.00
Grid B6-F1 1 1.85 1.70 1.55 4.87
Page 239
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid C6-F4 1 2.50 2.30 1.55 8.91
Grid D6-F5 1 2.60 2.40 1.50 9.36
Grid E6-F5 1 2.60 2.40 1.45 9.05
Grid F6-F4 1 2.50 2.30 1.45 8.34
Grid G6-F1 1 1.85 1.70 1.40 4.40
Earth Work Excavation For SSM
Grid B1-D1 1 6.64 1.15 0.40 3.05
Grid D1-D4 1 5.23 1.15 0.45 2.71
Grid D4-E4 1 2.72 1.15 0.50 1.57
Grid E4-E1 1 5.23 1.15 0.40 2.41
Grid E1-G1 1 6.64 1.15 0.40 3.05
Grid G1-G3 1 1.89 1.15 0.45 0.98
Grid H3-H5 1 1.53 1.15 0.45 0.79
Grid G5-G6 1 0.90 1.15 0.40 0.41
Grid B6-G6 1 15.54 1.15 0.45 8.04
Grid B5-B6 1 0.90 1.15 0.50 0.52
Grid A3-A5 1 1.53 1.15 0.45 0.79
Grid B1-B3 1 1.89 1.15 0.45 0.98
Grid B1'-D1' 1 4.33 1.15 0.45 2.24
Grid E1'-G1' 1 4.33 1.15 0.40 1.99
Grid 1-1' IN B,D,E,G 4 1.73 1.15 0.40 3.18
Deductions
Grid B1-D1 -1 3.95 1.15 0.40 -1.82
Grid D1-D4 -1 4.30 1.15 0.45 -2.23
Grid D4-E4 -1 2.30 1.15 0.50 -1.32
Grid E4-E1 -1 4.30 1.15 0.40 -1.98
Grid E1-G1 -1 3.95 1.15 0.40 -1.82
Grid B6-G6 -1 9.95 1.15 0.45 -5.15
Page 240
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Total Qty 212.78 Cum
KSRB-3.2: Providing and injecting chemical emulsion for Preconstructional Anti-Termite Treatment, creating
continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface
of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the
7 3.2 top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits, with
chloropyriphos emulsifiable concentrates of 20% concentration, including cost of chemical, diluting in water to one
percent concentration, labour, HOM of equipments, complete as per specifications. (Plinth area of the building at
ground floor only shall be measured ) Specification No. KBS : 3.2.6 / 3.2.7
Anti-Termite Treatment,
Grid B1-D1,B6-D6 1 7.61 9.89 75.26
Grid E1-G1,E6-G6 1 7.61 9.89 75.26
Grid A3-B3,A5-B5 1 1.20 3.96 4.75
Grid G3-H3,G5-H5 1 1.20 3.96 4.75
GridD4-E4,D6-E6 1 2.50 4.43 11.08
Total Qty 171.10 Sqm
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 with OPC cement @ 220kgs, with
40mm and down size graded granite metal coarse aggregates @0.892cum and fine aggregates @ 0.465cum
8 4.2 machine mixed, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation
including cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No.
KBS 4.1, 4.2
PCC For Footings
F1 2 1.45 1.30 0.10 0.38
F2 4 1.70 1.50 0.10 1.02
F3 2 1.90 1.70 0.10 0.65
F4 6 2.10 1.90 0.10 2.39
F5 6 2.20 2.00 0.10 2.64
F6 4 2.40 2.20 0.10 2.11
PCC Under SSM
Grid B1-D1 1 6.64 0.75 0.10 0.50
Grid D1-D4 1 5.23 0.75 0.10 0.39
Grid D4-E4 1 2.72 0.75 0.10 0.20
Page 241
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid E4-E1 1 5.23 0.75 0.10 0.39
Grid E1-G1 1 6.64 0.75 0.10 0.50
Grid G1-G3 1 1.89 0.75 0.10 0.14
Grid H3-H5 1 1.53 0.75 0.10 0.11
Grid G5-G6 1 0.90 0.75 0.10 0.07
Grid B6-G6 1 15.54 0.75 0.10 1.17
Grid B5-B6 1 0.90 0.75 0.10 0.07
Grid A3-A5 1 1.53 0.75 0.10 0.11
Grid B1-B3 1 1.89 0.75 0.10 0.14
Grid B1'-D1' 1 4.33 0.75 0.10 0.32
Grid E1'-G1' 1 4.33 0.75 0.10 0.32
Grid 1-1' IN B,D,E,G 4 1.73 0.75 0.10 0.52
Deductions
Grid B1-D1 -1 3.95 0.75 0.10 -0.30
Grid D1-D4 -1 4.30 0.75 0.10 -0.32
Grid D4-E4 -1 2.30 0.75 0.10 -0.17
Grid E4-E1 -1 4.30 0.75 0.10 -0.32
Grid E1-G1 -1 3.95 0.75 0.10 -0.30
Grid B6-G6 -1 9.95 0.75 0.10 -0.75
PCC Below Plinth Beam
Grid 2'C'-2'D 1 1.50 0.45 0.10 0.07
Grid 2'E-2'E' 1 1.50 0.45 0.10 0.07
Grid C2-D2 1 2.91 0.45 0.10 0.13
Grid E2-F2 1 2.91 0.45 0.10 0.13
Grid B'3-B'5 1 3.25 0.45 0.10 0.15
Grid C1-C2 1 2.76 0.45 0.10 0.12
Grid C5-C6 1 2.15 0.45 0.10 0.10
Grid C'1-C'2 1 2.82 0.45 0.10 0.13
Page 242
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D4-D6 1 3.68 0.45 0.10 0.17
Grid E4-E6 1 3.68 0.45 0.10 0.17
Grid E'1-E'2 1 2.82 0.45 0.10 0.13
Grid F1-F2 1 2.76 0.45 0.10 0.12
Grid F5-F6 1 2.15 0.45 0.10 0.10
Grid F'3-F'5 1 3.25 0.45 0.10 0.15
Flooring PCC
Bed Room-1 2 3.04 3.05 0.10 1.85
Bed Room-2 2 3.00 3.25 0.10 1.95
Living 2 4.04 3.25 0.10 2.63
Kitchen 2 3.06 2.44 0.10 1.49
Enterance 2 2.90 2.20 0.10 1.28
Toilet 2 1.50 1.20 0.10 0.36
Bath 2 1.50 1.50 0.10 0.45
Passage 2 1.30 2.82 0.10 0.73
Staircase 1 2.49 2.43 0.10 0.61
Total Qty 25.06 Cum
KSRB 5.2-3 : Providing and constructing granite / trap / basalt size stone masonry in foundation cement mortar 1:6,
9 5.6 stone hammerd dressed in courses not less than 20 cms high, bond stones at two m. apart in each course including
cost of materials, labour, curing complete as per specifications. KBS 5.1.13
SSM In Foundatiom
Grid B1-D1 1 6.79 0.60 0.65 2.65
Grid D1-D4 1 5.83 0.60 0.65 2.27
Grid D4-E4 1 2.34 0.60 0.65 0.91
Grid E4-E1 1 5.83 0.60 0.65 2.27
Grid E1-G1 1 6.79 0.60 0.65 2.65
Page 243
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid G1-G3 1 2.68 0.60 0.65 1.05
Grid G3-H3 1 1.58 0.60 0.65 0.62
Grid H3-H5 1 2.66 0.60 0.65 1.04
Grid G5-H5 1 1.58 0.60 0.65 0.62
Grid G5-G6 1 2.45 0.60 0.65 0.95
Grid B6-G6 1 14.72 0.60 0.65 5.74
Grid B5-B6 1 2.45 0.60 0.65 0.95
Grid A5-B5 1 1.58 0.60 0.65 0.62
Grid A3-A5 1 2.66 0.60 0.65 1.04
Grid A3-B3 1 1.58 0.60 0.65 0.62
Grid B1-B3 1 2.68 0.60 0.65 1.05
Grid B1'-D1' 1 4.33 0.60 0.65 1.69
Grid E1'-G1' 1 4.33 0.60 0.65 1.69
Grid 1-1' IN B,D,E,G 4 1.73 0.60 0.65 2.70
SSM over Footings
Grid B1-F2 1 1.44 0.60 0.70 0.60
Grid C1-F5 1 2.05 0.60 0.50 0.61
Grid D1-F2 1 1.44 0.60 0.65 0.56
Grid D2-F4 1 2.00 0.60 0.55 0.66
Grid D4-F5 1 2.29 0.60 0.50 0.69
Grid E4-F5 1 2.29 0.60 0.50 0.69
Grid E2-F4 1 2.00 0.60 0.50 0.60
Grid E1-F2 1 1.44 0.60 0.65 0.56
Grid F1-F5 1 2.05 0.60 0.50 0.61
Grid G1-F2 1 1.44 0.60 0.65 0.56
Grid H3-F4 1 1.25 0.60 0.55 0.41
Grid H5-F4 1 1.25 0.60 0.55 0.41
Grid G6-F1 1 1.14 0.60 0.70 0.48
Page 244
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F6-F4 1 1.85 0.60 0.55 0.61
Grid E6-F5 1 2.05 0.60 0.50 0.61
Grid D6-F5 1 2.05 0.60 0.50 0.61
Grid C6-F4 1 1.85 0.60 0.55 0.61
Grid B6-F1 1 1.14 0.60 0.70 0.48
Grid A5-F4 1 1.25 0.60 0.55 0.41
Grid A3-F4 1 1.25 0.60 0.55 0.41
Deductions
Grid B1-F2 -1 0.23 0.375 1.35 -0.12
Grid C1-F5 -1 0.23 0.375 1.20 -0.10
Grid D1-F2 -1 0.23 0.375 1.35 -0.12
Grid E1-F2 -1 0.23 0.375 1.35 -0.12
Grid F1-F5 -1 0.23 0.375 1.20 -0.10
Grid G1-F2 -1 0.23 0.375 1.35 -0.12
Grid D2-F4 -1 0.23 0.375 1.25 -0.11
Grid E2-F4 -1 0.23 0.375 1.25 -0.11
Grid A3-F4 -1 0.23 0.375 1.25 -0.11
Grid H3-F4 -1 0.23 0.375 1.25 -0.11
Grid D4-F5 -1 0.23 0.375 1.20 -0.10
Grid E4-F5 -1 0.23 0.375 1.20 -0.10
Grid A5-F3 -1 0.23 0.375 1.30 -0.11
Grid H5-F3 -1 0.23 0.375 1.30 -0.11
Grid B6-F1 -1 0.23 0.375 1.40 -0.12
Grid C6-F4 -1 0.23 0.375 1.25 -0.11
Grid D6-F5 -1 0.23 0.375 1.20 -0.10
Grid E6-F5 -1 0.23 0.375 1.20 -0.10
Grid F6-F4 -1 0.23 0.375 1.25 -0.11
Grid G6-F1 -1 0.23 0.375 1.40 -0.12
Page 245
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Total Qty 40.10 Cum
KSRB 5.3-3 : Providing and constructing granite / trap / basalt size stone masonry in basement with cement mortar
10 5.9 1:6, edges of stones chistle dressed in courses not less than 15 cms high, bond stones at two m. apart in each
course including cost of materials, labour, curing complete as per specifications. KBS 5.1.13
SSM In Basement
Grid B1-D1 1 6.79 0.45 0.22 0.67
Grid D1-D4 1 5.83 0.45 0.42 1.10
Grid D4-E4 1 2.34 0.45 0.47 0.50
Grid E4-E1 1 5.83 0.45 0.52 1.36
Grid E1-G1 1 6.79 0.45 0.62 1.89
Grid G1-G3 1 2.68 0.45 0.72 0.87
Grid G3-H3 1 1.58 0.45 0.72 0.51
Grid H3-H5 1 2.66 0.45 0.72 0.86
Grid G5-H5 1 1.58 0.45 0.72 0.51
Grid G5-G6 1 2.45 0.45 0.72 0.79
Grid B6-G6 1 14.72 0.45 0.47 3.11
Grid B5-B6 1 2.45 0.45 0.22 0.24
Grid A5-B5 1 1.58 0.45 0.22 0.16
Grid A3-A5 1 2.66 0.45 0.22 0.26
Grid A3-B3 1 1.58 0.45 0.22 0.16
Grid B1-B3 1 2.68 0.45 0.22 0.27
Deductions
Grid B1-C1 -1 0.23 0.375 0.22 -0.02
Grid C1-C2 -1 0.23 0.375 0.32 -0.03
Grid D1-C1 -1 0.23 0.375 0.42 -0.04
Grid E1-C1 -1 0.23 0.375 0.52 -0.04
Grid F1-C2 -1 0.23 0.375 0.62 -0.05
Page 246
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid G1-C1 -1 0.23 0.375 0.72 -0.06
Grid D2-C2 -1 0.23 0.375 0.42 -0.04
Grid E2-C2 -1 0.23 0.375 0.52 -0.04
Grid A3-C2 -1 0.23 0.375 0.22 -0.02
Grid H3-C2 -1 0.23 0.375 0.72 -0.06
Grid D4-C3 -1 0.23 0.375 0.42 -0.04
Grid E4-C3 -1 0.23 0.375 0.52 -0.04
Grid A5-C2 -1 0.23 0.375 0.22 -0.02
Grid H5-C2 -1 0.23 0.375 0.72 -0.06
Grid B6-C1 -1 0.23 0.375 0.22 -0.02
Grid C6-C2 -1 0.23 0.375 0.32 -0.03
Grid D6-C3 -1 0.23 0.375 0.42 -0.04
Grid E6-C3 -1 0.23 0.375 0.52 -0.04
Grid F6-C2 -1 0.23 0.375 0.62 -0.05
Grid G6-C1 -1 0.23 0.375 0.72 -0.06
Total Qty 12.46 Cum
KSRB 2.3 : Filling available excavated earth ( excluding rock ) in sides of foundations upto plinth in layers not
12 2.10 exceeding 20 cms. in depth, compacting each deposited layer by ramming after watering with lead upto 50 m. and
lift upto 1.5 m. including cost of all labour complete as per specifications. specification. No. KBS 2.9
Earth Filling in Sides of Foundation
Same As Hard Soil 54.33
Same As Soft Rock 212.78
Total Qty 267.12
Deductions
Pcc under Footings 25.06
Footing And Column concrete 48.89
Ssm in Foundation 40.10
Total Qty 114.05
Page 247
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Qty Required For Filling 153.06
Extra Qty Required For side Filling 98.73
Qty Available for Filling 54.33 Cum
KSRB 2.5 : Earthwork excavation ( in deposited soil ) and filling sides of foundation upto plinth in layers not
13 2.12 exceeding 20 cms. in depth, compacting each deposited layer by ramming after watering with all lead and lift
including cost of all labour complete as per specifications. specification. No. KBS 2.9.9 / 2.9.10.1 / 2.1.1
Earth Filling in Foundation
Grid B1-D1,B6-D6 1 7.61 9.89 0.80 60.21
Grid E1-G1,E6-G6 1 7.61 9.89 1.10 82.79
Grid A3-B3,A5-B5 1 1.20 3.96 0.70 3.33
Grid G3-H3,G5-H5 1 1.20 3.96 1.20 5.70
GridD4-E4,D6-E6 1 2.50 4.43 0.95 10.52
Qty Required For side Filling 98.73
Total Qty 261.28 Cum
KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of design mix M20 with OPC cement @
320kgs, with 20mm and down size graded granite metal coarse aggregates @0.878cum and fine aggregtes @
0.459cum, with superplastisiser @3lts confirming to IS9103-1999 Reaffirmed-2008, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in foundation plinth and ground floor level for roof slabs,
14 4.11
staircase, lintles, retaining walls, return walls, walls ( any thickness ) including attached plasters, columns, piers,
abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks,
plain window cills, fillets etc., including cost of all materials, labour, HOM of machinery, curing, complete as per
specifications. Specification No. KBS 4.1, 4.6
Footing Concrete
F1 2 1.25 1.10 0.30 0.83
F2 4 1.50 1.30 0.35 2.73
2 1.70 1.50 0.40 2.04
F4 6 1.90 1.70 0.45 8.72
F5 6 2.00 1.80 0.50 10.80
F6 4 2.20 2.00 0.55 9.68
Page 248
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Page 249
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid C1-D1,PB3 1 2.91 0.23 0.38 0.25
Grid E1-F1,PB3 1 2.91 0.23 0.38 0.25
Grid F1-G1,PB1 1 3.04 0.23 0.38 0.27
Grid 2'C'-2'D,PB4 1 1.50 0.23 0.38 0.13
Grid 2'E-2'E',PB4 1 1.50 0.23 0.38 0.13
Grid C2-D2,PB3 1 2.91 0.23 0.38 0.25
Grid E2-F2,PB3 1 2.91 0.23 0.38 0.25
Grid A3-C3,PB3 1 3.99 0.23 0.38 0.35
Grid F3-H3,PB3 1 3.99 0.23 0.38 0.35
Grid D4-E4,PB2 1 2.49 0.23 0.38 0.22
Grid A5-C5,PB3 1 3.99 0.23 0.38 0.35
Grid F5-H5,PB3 1 3.99 0.23 0.38 0.35
Grid 5'C-5'D,PB1 1 2.91 0.23 0.38 0.25
Grid 5'E-5'F,PB1 1 2.91 0.23 0.38 0.25
Grid B6-C6,PB2 1 3.06 0.23 0.38 0.27
Grid D6-E6,PB2 1 2.49 0.23 0.38 0.22
Grid F6-G6,PB2 1 3.06 0.23 0.38 0.27
Grid A3-A5,PB2 1 3.25 0.23 0.38 0.28
Grid B1-B3,PB1 1 3.05 0.23 0.38 0.27
Grid B5-B6,PB2 1 2.30 0.23 0.38 0.20
Grid B'3-B'5,PB2 1 3.25 0.23 0.38 0.28
Grid C1-C2,PB1 1 2.76 0.23 0.38 0.24
Grid C5-C6,PB2 1 2.15 0.23 0.38 0.19
Grid C'1-C'2,PB4 1 2.82 0.23 0.38 0.25
Grid D1-D2,PB1 1 2.67 0.23 0.38 0.23
Grid D2-D4,PB1 1 1.81 0.23 0.38 0.16
Grid D4-D6,PB3 1 3.68 0.23 0.38 0.32
Grid E1-E2,PB1 1 2.67 0.23 0.38 0.23
Page 250
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid E2-E4,PB1 1 1.81 0.23 0.38 0.16
Grid E4-E6,PB3 1 3.68 0.23 0.38 0.32
Grid E'1-E'2,PB4 1 2.82 0.23 0.38 0.25
Grid F1-F2,PB1 1 2.76 0.23 0.38 0.24
Grid F5-F6,PB2 1 2.15 0.23 0.38 0.19
Grid F'3-F'5,PB2 1 3.25 0.23 0.38 0.28
Grid G1-G3,PB1 1 3.05 0.23 0.38 0.27
Grid G5-G6,PB2 1 2.30 0.23 0.38 0.20
Grid H3-H5,PB2 1 3.25 0.23 0.38 0.28
Total Qty 48.89 Cum
KSRB 4-1.6 ; Providing and laying in position plain cement concrete of mix 1:2:4 with cement @ 240kgs, with 20mm
and down size graded granite metal coarse aggregates @ 0.878 cum and fine aggregtes @ 0.53cum, machine
18 4.6
mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation, plinth and cills, ncluding
cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2
Coping Concrete
Grid B1-C1 1 3.04 0.45 0.075 0.10
Grid C1-D1 1 2.91 0.45 0.075 0.10
Grid E1-F1 1 2.91 0.45 0.075 0.10
Grid F1-G1 1 3.04 0.45 0.075 0.10
Grid A3-C3 1 3.99 0.45 0.075 0.13
Grid F3-H3 1 3.99 0.45 0.075 0.13
Grid D4-E4 1 2.49 0.45 0.075 0.08
Grid A5-C5 1 3.99 0.45 0.075 0.13
Grid F5-H5 1 3.99 0.45 0.075 0.13
Grid 5'C-5'D 1 2.91 0.45 0.075 0.10
Grid 5'E-5'F 1 2.91 0.45 0.075 0.10
Grid B6-C6 1 3.06 0.45 0.075 0.10
Page 251
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D6-E6 1 2.49 0.45 0.075 0.08
Grid F6-G6 1 3.06 0.45 0.075 0.10
Grid A3-A5 1 3.25 0.45 0.075 0.11
Grid B1-B3 1 3.05 0.45 0.075 0.10
Grid B5-B6 1 2.30 0.45 0.075 0.08
Grid D1-D2 1 2.67 0.45 0.075 0.09
Grid D2-D4 1 1.81 0.45 0.075 0.06
Grid E1-E2 1 2.67 0.45 0.075 0.09
Grid E2-E4 1 1.81 0.45 0.075 0.06
Grid G1-G3 1 3.05 0.45 0.075 0.10
Grid G5-G6 1 2.30 0.45 0.075 0.08
Grid H3-H5 1 3.25 0.45 0.075 0.11
Total Qty 2.39 Cum
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
19 4.28 foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per
specificaitons. Specification No. KBS 4.6.2
Page 252
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
6 2 2.00 0.10 2.40
F6 4 2 2.40 0.10 1.92
4 2 2.2 0.10 1.76
Shuttering For Footing Concrete
F1 2 2 1.25 0.30 1.50
2 2 1.10 0.30 1.32
F2 4 2 1.50 0.35 4.20
4 2 1.30 0.35 3.64
F3 2 2 1.70 0.40 2.72
2 2 1.50 0.40 2.40
F4 6 2 1.90 0.45 10.26
6 2 1.70 0.45 9.18
F5 6 2 2.00 0.50 12.00
6 2 1.80 0.50 10.80
F6 4 2 2.20 0.55 9.68
4 2 2.00 0.55 8.80
Total Qty 95.12 Sqm
KSRB 4-6.5 : Providing and removing centering, shuttering, strutting, propping etc., for columns, pillars, piers,
21 4.32 abutments, post and struts, square / rectangular / polygon in plan including cost of all materials, labour complete as
per specificaiton. Specification No. KBS 4.6.2
Shuttering For Column Concrete
Grid B1-C1 1 1.21 2.05 2.48
Grid C1-C2 1 1.21 2.00 2.42
Grid D1-C1 1 1.21 2.25 2.72
Grid E1-C1 1 1.21 2.35 2.84
Grid F1-C2 1 1.21 2.30 2.78
Grid G1-C1 1 1.21 2.55 3.09
Page 253
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D2-C2 1 1.21 2.15 2.60
Grid E2-C2 1 1.21 2.25 2.72
Grid A3-C2 1 1.21 1.95 2.36
Grid C3-C3 1 1.21 1.95 2.36
Grid F3-C3 1 1.21 2.25 2.72
Grid H3-C2 1 1.21 2.45 2.96
Grid D4-C3 1 1.21 2.10 2.54
Grid E4-C3 1 1.21 2.20 2.66
Grid A5-C2 1 1.21 2.00 2.42
Grid C5-C3 1 1.21 1.95 2.36
Grid F5-C3 1 1.21 2.25 2.72
Grid H5-C2 1 1.21 2.50 3.03
Grid B6-C1 1 1.21 2.10 2.54
Grid C6-C2 1 1.21 2.05 2.48
Grid D6-C3 1 1.21 2.10 2.54
Grid E6-C3 1 1.21 2.20 2.66
Grid F6-C2 1 1.21 2.35 2.84
Grid G6-C1 1 1.21 2.60 3.15
Total Qty 64.01 Sqm
KSRB 4-6.4 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
25 4.31 vertical surface such as walls at any thickness, including attached pilasters, buttresses, plinth and string courses
cost of all materials, labour complete as per specificaitons. Specification No. KBS 4.6.2
Shuttering For Plinth Beam Concrete
Grid B1-C1,PB1 1 2 3.04 0.38 2.31
Grid C1-D1,PB3 1 2 2.91 0.38 2.21
Grid E1-F1,PB3 1 2 2.91 0.38 2.21
Grid F1-G1,PB1 1 2 3.04 0.38 2.31
Page 254
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid 2'C'-2'D,PB4 1 2 1.50 0.38 1.14
Grid 2'E-2'E',PB4 1 2 1.50 0.38 1.14
Grid C2-D2,PB3 1 2 2.91 0.38 2.21
Grid E2-F2,PB3 1 2 2.91 0.38 2.21
Grid A3-C3,PB3 1 2 3.99 0.38 3.03
Grid F3-H3,PB3 1 2 3.99 0.38 3.03
Grid D4-E4,PB2 1 2 2.49 0.38 1.89
Grid A5-C5,PB3 1 2 3.99 0.38 3.03
Grid F5-H5,PB3 1 2 3.99 0.38 3.03
Grid 5'C-5'D,PB1 1 2 2.91 0.38 2.21
Grid 5'E-5'F,PB1 1 2 2.91 0.38 2.21
Grid B6-C6,PB2 1 2 3.06 0.38 2.33
Grid D6-E6,PB2 1 2 2.49 0.38 1.89
Grid F6-G6,PB2 1 2 3.06 0.38 2.33
Grid A3-A5,PB2 1 2 3.25 0.38 2.47
Grid B1-B3,PB1 1 2 3.05 0.38 2.32
Grid B5-B6,PB2 1 2 2.30 0.38 1.74
Grid B'3-B'5,PB2 1 2 3.25 0.38 2.47
Grid C1-C2,PB1 1 2 2.76 0.38 2.10
Grid C5-C6,PB2 1 2 2.15 0.38 1.63
Grid C'1-C'2,PB4 1 2 2.82 0.38 2.14
Grid D1-D2,PB1 1 2 2.67 0.38 2.03
Grid D2-D4,PB1 1 2 1.81 0.38 1.38
Grid D4-D6,PB3 1 2 3.68 0.38 2.80
Grid E1-E2,PB1 1 2 2.67 0.38 2.03
Grid E2-E4,PB1 1 2 1.81 0.38 1.38
Grid E4-E6,PB3 1 2 3.68 0.38 2.80
Grid E'1-E'2,PB4 1 2 2.82 0.38 2.14
Page 255
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid F1-F2,PB1 1 2 2.76 0.38 2.10
Grid F5-F6,PB2 1 2 2.15 0.38 1.63
Grid F'3-F'5,PB2 1 2 3.25 0.38 2.47
Grid G1-G3,PB1 1 2 3.05 0.38 2.32
Grid G5-G6,PB2 1 2 2.30 0.38 1.74
Grid H3-H5,PB2 1 2 3.25 0.38 2.47
Shuttering for PCC Below Plinth Beam
Grid 2'C'-2'D 1 2 1.50 0.10 0.30
Grid 2'E-2'E' 1 2 1.50 0.10 0.30
Grid C2-D2 1 2 2.91 0.10 0.58
Grid E2-F2 1 2 2.91 0.10 0.58
Grid B'3-B'5 1 2 3.25 0.10 0.65
Grid C1-C2 1 2 2.76 0.10 0.55
Grid C5-C6 1 2 2.15 0.10 0.43
Grid C'1-C'2 1 2 2.82 0.10 0.56
Grid D4-D6 1 2 3.68 0.10 0.74
Grid E4-E6 1 2 3.68 0.10 0.74
Grid E'1-E'2 1 2 2.82 0.10 0.56
Grid F1-F2 1 2 2.76 0.10 0.55
Grid F5-F6 1 2 2.15 0.10 0.43
Grid F'3-F'5 1 2 3.25 0.10 0.65
Shuttering For Coping Concrete
Grid B1-C1 1 2 3.04 0.075 0.46
Grid C1-D1 1 2 2.91 0.075 0.44
Grid E1-F1 1 2 2.91 0.075 0.44
Grid F1-G1 1 2 3.04 0.075 0.46
Grid A3-C3 1 2 3.99 0.075 0.60
Grid F3-H3 1 2 3.99 0.075 0.60
Page 256
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Grid D4-E4 1 2 2.49 0.075 0.37
Grid A5-C5 1 2 3.99 0.075 0.60
Grid F5-H5 1 2 3.99 0.075 0.60
Grid 5'C-5'D 1 2 2.91 0.075 0.44
Grid 5'E-5'F 1 2 2.91 0.075 0.44
Grid B6-C6 1 2 3.06 0.075 0.46
Grid D6-E6 1 2 2.49 0.075 0.37
Grid F6-G6 1 2 3.06 0.075 0.46
Grid A3-A5 1 2 3.25 0.075 0.49
Grid B1-B3 1 2 3.05 0.075 0.46
Grid B5-B6 1 2 2.30 0.075 0.34
Grid D1-D2 1 2 2.67 0.075 0.40
Grid D2-D4 1 2 1.81 0.075 0.27
Grid E1-E2 1 2 2.67 0.075 0.40
Grid E2-E4 1 2 1.81 0.075 0.27
Grid G1-G3 1 2 3.05 0.075 0.46
Grid G5-G6 1 2 2.30 0.075 0.34
Grid H3-H5 1 2 3.25 0.075 0.49
Total Qty 101.13 Sqm
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking,
placing in position, lapping and / or welding wherever required, tying with binding wire and anchoring to the
28 4.46.2
adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured
and paid) cost of materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3
Foundation Steel 3.91
Total Qty 3.91 Tonne
Page 257
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Non-Teaching Staff Quarters
Ground Floor Steel Fabrication RA BILL NO - 01
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Footing Mat Steel
F1
Bars-A 10 9 1 2 1.45 - 26.10 - - - -
Bars-B 10 10 1 2 1.30 - 26.00 - - - -
F2 - - - - - -
Bars-A 10 10 1 4 1.75 - 70.00 - - - -
Bars-B 10 11 1 4 1.55 - 68.20 - - - -
F3 - - - - - -
Bars-A 10 11 1 2 2.00 - 44.00 - - - -
Bars-B 10 13 1 2 1.80 - 46.80 - - - -
F4 - - - - - -
Bars-A 10 15 1 6 2.25 - 202.50 - - - -
Bars-B 10 17 1 6 2.05 - 209.10 - - - -
F5 - - - - - -
Bars-A 10 19 1 6 2.40 - 273.60 - - - -
Bars-B 10 21 1 6 2.20 - 277.20 - - - -
F6 - - - - - -
Bars-A 10 21 1 4 2.65 - 222.60 - - - -
Bars-B 10 23 1 4 2.45 - 225.40 - - - -
Column Steel Upto Plinth Top - - - - - -
Grid B1-C1 - - - - - -
Main Bars 12 8 1 1 2.85 - - 22.80 - - -
Page 259
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Rectangle Stirrups 8 15 1 1 1.04 15.60 - - - - -
Dimond Stirrups 8 15 1 1 0.81 12.15 - - - - -
Grid C1-C2 - - - - - -
Main Bars-1 16 4 1 1 2.95 - - - 11.80 - -
Main Bars-2 12 4 1 1 2.95 - - 11.80 - - -
Rectangle Stirrups 8 16 1 1 1.04 16.64 - - - - -
Dimond Stirrups 8 16 1 1 0.81 12.96 - - - - -
Grid D1-C1 - - - - - -
Main Bars 12 8 1 1 3.05 - - 24.40 - - -
Rectangle Stirrups 8 16 1 1 1.04 16.64 - - - - -
Dimond Stirrups 8 16 1 1 0.81 12.96 - - - - -
Grid E1-C1 - - - - - -
Main Bars 12 8 1 1 3.15 - - 25.20 - - -
Rectangle Stirrups 8 17 1 1 1.04 17.68 - - - - -
Dimond Stirrups 8 17 1 1 0.81 13.77 - - - - -
Grid F1-C2 - - - - - -
Main Bars-1 16 4 1 1 3.25 - - - 13.00 - -
Main Bars-2 12 4 1 1 3.25 - - 13.00 - - -
Rectangle Stirrups 8 17 1 1 1.04 17.68 - - - - -
Dimond Stirrups 8 17 1 1 0.81 13.77 - - - - -
Grid G1-C1 - - - - - -
Main Bars 12 8 1 1 3.55 - - 28.40 - - -
Rectangle Stirrups 8 18 1 1 1.04 18.72 - - - - -
Dimond Stirrups 8 18 1 1 0.81 14.58 - - - - -
Grid D2-C2 - - - - - -
Main Bars-1 16 4 1 1 3.05 - - - 12.20 - -
Main Bars-2 12 4 1 1 3.05 - - 12.20 - - -
Rectangle Stirrups 8 16 1 1 1.04 16.64 - - - - -
Dimond Stirrups 8 16 1 1 0.81 12.96 - - - - -
Grid E2-C2 - - - - - -
Main Bars-1 16 4 1 1 3.15 - - - 12.60 - -
Main Bars-2 12 4 1 1 3.15 - - 12.60 - - -
Rectangle Stirrups 8 17 1 1 1.04 17.68 - - - - -
Page 260
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dimond Stirrups 8 17 1 1 0.81 13.77 - - - - -
Grid A3-C2 - - - - - -
Main Bars-1 16 4 1 1 2.85 - - - 11.40 - -
Main Bars-2 12 4 1 1 2.85 - - 11.40 - - -
Rectangle Stirrups 8 15 1 1 1.04 15.60 - - - - -
Dimond Stirrups 8 15 1 1 0.81 12.15 - - - - -
Grid C3-C3 - - - - - -
Main Bars 16 8 1 1 2.95 - - - 23.60 - -
Rectangle Stirrups 8 14 1 1 1.04 14.56 - - - - -
Dimond Stirrups 8 14 1 1 0.81 11.34 - - - - -
Grid F3-C3 - - - - - -
Main Bars 16 8 1 1 3.25 - - - 26.00 - -
Rectangle Stirrups 8 15 1 1 1.04 15.60 - - - - -
Dimond Stirrups 8 15 1 1 0.81 12.15 - - - - -
Grid H3-C2 - - - - - -
Main Bars-1 16 4 1 1 3.35 - - - 13.40 - -
Main Bars-2 12 4 1 1 3.35 - - 13.40 - - -
Rectangle Stirrups 8 18 1 1 1.04 18.72 - - - - -
Dimond Stirrups 8 18 1 1 0.81 14.58 - - - - -
Grid D4-C3 - - - - - -
Main Bars 16 8 1 1 3.05 - - - 24.40 - -
Rectangle Stirrups 8 14 1 1 1.04 14.56 - - - - -
Dimond Stirrups 8 14 1 1 0.81 11.34 - - - - -
Grid E4-C3 - - - - - -
Main Bars 16 8 1 1 3.15 - - - 25.20 - -
Rectangle Stirrups 8 15 1 1 1.04 15.60 - - - - -
Dimond Stirrups 8 15 1 1 0.81 12.15 - - - - -
Grid A5-C2 - - - - - -
Main Bars-1 16 4 1 1 2.85 - - - 11.40 - -
Main Bars-2 12 4 1 1 2.85 - - 11.40 - - -
Rectangle Stirrups 8 15 1 1 1.04 15.60 - - - - -
Dimond Stirrups 8 15 1 1 0.81 12.15 - - - - -
Grid C5-C3 - - - - - -
Page 261
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Main Bars 16 8 1 1 2.95 - - - 23.60 - -
Rectangle Stirrups 8 14 1 1 1.04 14.56 - - - - -
Dimond Stirrups 8 14 1 1 0.81 11.34 - - - - -
Grid F5-C3 - - - - - -
Main Bars 16 8 1 1 3.25 - - - 26.00 - -
Rectangle Stirrups 8 15 1 1 1.04 15.60 - - - - -
Dimond Stirrups 8 15 1 1 0.81 12.15 - - - - -
Grid H5-C2 - - - - - -
Main Bars-1 16 4 1 1 3.35 - - - 13.40 - -
Main Bars-2 12 4 1 1 3.35 - - 13.40 - - -
Rectangle Stirrups 8 18 1 1 1.04 18.72 - - - - -
Dimond Stirrups 8 18 1 1 0.81 14.58 - - - - -
Grid B6-C1 - - - - - -
Main Bars 12 8 1 1 2.85 - - 22.80 - - -
Rectangle Stirrups 8 15 1 1 1.04 15.60 - - - - -
Dimond Stirrups 8 15 1 1 0.81 12.15 - - - - -
Grid C6-C2 - - - - - -
Main Bars-1 16 4 1 1 2.95 - - - 11.80 - -
Main Bars-2 12 4 1 1 2.95 - - 11.80 - - -
Rectangle Stirrups 8 16 1 1 1.04 16.64 - - - - -
Dimond Stirrups 8 16 1 1 0.81 12.96 - - - - -
Grid D6-C3 - - - - - -
Main Bars 16 8 1 1 3.05 - - - 24.40 - -
Rectangle Stirrups 8 14 1 1 1.04 14.56 - - - - -
Dimond Stirrups 8 14 1 1 0.81 11.34 - - - - -
Grid E6-C3 - - - - - -
Main Bars 16 8 1 1 3.15 - - - 25.20 - -
Rectangle Stirrups 8 15 1 1 1.04 15.60 - - - - -
Dimond Stirrups 8 15 1 1 0.81 12.15 - - - - -
Grid F6-C2 - - - - - -
Main Bars-1 16 4 1 1 3.25 - - - 13.00 - -
Main Bars-2 12 4 1 1 3.25 - - 13.00 - - -
Rectangle Stirrups 8 17 1 1 1.04 17.68 - - - - -
Page 262
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Dimond Stirrups 8 17 1 1 0.81 13.77 - - - - -
Grid G6-C1 - - - - - -
Main Bars 12 8 1 1 3.35 - - 26.80 - - -
Rectangle Stirrups 8 18 1 1 1.04 18.72 - - - - -
Dimond Stirrups 8 18 1 1 0.81 14.58 - - - - -
- - - - - -
Plinth Beam Steel - - - - - -
Grid B1-C1,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.8 - - - 15.20 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid C1-D1,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.67 - - - 14.68 - -
Extra Bars at End Support 16 3 1 2 1.1 - - - 6.60 - -
Extra Bars at Mid Span 16 3 1 1 2.6 - - - 7.80 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid E1-F1,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.67 - - - 14.68 - -
Extra Bars at End Support 16 3 1 2 1.1 - - - 6.60 - -
Extra Bars at Mid Span 16 3 1 1 2.6 - - - 7.80 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid F1-G1,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.8 - - - 15.20 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid 2'C'-2'D,PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 2.29 - - 13.74 - - -
Page 263
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups 150mmc/c 8 10 1 1 1.27 12.70 - - - - -
Stirrups 200mmc/c 8 4 1 1 1.27 5.08 - - - - -
Grid 2'E-2'E',PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 2.29 - - 13.74 - - -
Stirrups 150mmc/c 8 10 1 1 1.27 12.70 - - - - -
Stirrups 200mmc/c 8 4 1 1 1.27 5.08 - - - - -
Grid C2-D2,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.67 - - - 14.68 - -
Extra Bars at End Support 16 3 1 2 1.1 - - - 6.60 - -
Extra Bars at Mid Span 16 3 1 1 2.6 - - - 7.80 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid E2-F2,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 3.67 - - - 14.68 - -
Extra Bars at End Support 16 3 1 2 1.1 - - - 6.60 - -
Extra Bars at Mid Span 16 3 1 1 2.6 - - - 7.80 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid A3-C3,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 3 1 2 1.1 - - - 6.60 - -
Extra Bars at Mid Span 16 3 1 1 2.6 - - - 7.80 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid F3-H3,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 3 1 2 1.1 - - - 6.60 - -
Extra Bars at Mid Span 16 3 1 1 2.6 - - - 7.80 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid D4-E4,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 3.25 - - - 13.00 - -
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Page 264
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Stirrups 150mmc/c 8 14 1 1 1.27 17.78 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Grid A5-C5,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 3 1 2 1.1 - - - 6.60 - -
Extra Bars at Mid Span 16 3 1 1 2.6 - - - 7.80 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid F5-H5,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 4.89 - - - 19.56 - -
Extra Bars at End Support 16 3 1 2 1.1 - - - 6.60 - -
Extra Bars at Mid Span 16 3 1 1 2.6 - - - 7.80 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid 5'C-5'D,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.7 - - - 14.80 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid 5'E-5'F,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.7 - - - 14.80 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid B6-C6,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 3.82 - - - 15.28 - -
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid D6-E6,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 3.25 - - - 13.00 - -
Page 265
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Stirrups 150mmc/c 8 14 1 1 1.27 17.78 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Grid F6-G6,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 3.82 - - - 15.28 - -
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid A3-A5,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 4.00 - - - 16.00 - -
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid B1-B3,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.97 - - - 15.88 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid B5-B6,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 3.22 - - - 12.88 - -
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Stirrups 150mmc/c 8 14 1 1 1.27 17.78 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Grid B'3-B'5,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 4.00 - - - 16.00 - -
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Stirrups 150mmc/c 8 18 1 1 1.27 22.86 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Page 266
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid C1-C2,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.81 - - - 15.24 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid C5-C6,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 3.20 - - - 12.80 - -
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Stirrups 150mmc/c 8 14 1 1 1.27 17.78 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Grid C'1-C'2,PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 3.61 - - 21.66 - - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid D1-D2,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.72 - - - 14.88 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid D2-D4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 2.86 - - - 11.44 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 12 1 1 1.27 15.24 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Grid D4-D6,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 4.73 - - - 18.92 - -
Extra Bars at End Support 16 3 1 2 1.1 - - - 6.60 - -
Extra Bars at Mid Span 16 3 1 1 2.6 - - - 7.80 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Page 267
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid E1-E2,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.72 - - - 14.88 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid E2-E4,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 2.86 - - - 11.44 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 12 1 1 1.27 15.24 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Grid E4-E6,PB3 - - - - - -
Top & Bottom Bars 16 4 1 1 4.73 - - - 18.92 - -
Extra Bars at End Support 16 3 1 2 1.1 - - - 6.60 - -
Extra Bars at Mid Span 16 3 1 1 2.6 - - - 7.80 - -
Stirrups 150mmc/c 8 21 1 1 1.27 26.67 - - - - -
Stirrups 200mmc/c 8 8 1 1 1.27 10.16 - - - - -
Grid E'1-E'2,PB4 - - - - - -
Top & Bottom Bars 12 6 1 1 3.61 - - 21.66 - - -
Stirrups 150mmc/c 8 16 1 1 1.27 20.32 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid F1-F2,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.81 - - - 15.24 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 6 1 1 1.27 7.62 - - - - -
Grid F5-F6,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 3.20 - - - 12.80 - -
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Stirrups 150mmc/c 8 14 1 1 1.27 17.78 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Page 268
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Grid F'3-F'5,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 4.00 - - - 16.00 - -
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Stirrups 150mmc/c 8 18 1 1 1.27 22.86 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid G1-G3,PB1 - - - - - -
Top & Bottom Bars 16 4 1 1 3.97 - - - 15.88 - -
Extra Bars at End Support 16 1 1 2 1.1 - - - 2.20 - -
Extra Bars at Mid Span 16 1 1 1 2.6 - - - 2.60 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Grid G5-G6,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 3.22 - - - 12.88 - -
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Stirrups 150mmc/c 8 14 1 1 1.27 17.78 - - - - -
Stirrups 200mmc/c 8 5 1 1 1.27 6.35 - - - - -
Grid H3-H5,PB2 - - - - - -
Top & Bottom Bars 16 4 1 1 4.00 - - - 16.00 - -
Extra Bars at End Support 16 2 1 2 1.20 - - - 4.80 - -
Extra Bars at Mid Span 16 2 1 1 2.90 - - - 5.80 - -
Stirrups 150mmc/c 8 17 1 1 1.27 21.59 - - - - -
Stirrups 200mmc/c 8 7 1 1 1.27 8.89 - - - - -
Total Length In mts ### ### 345.20 ### - -
Unit Wt/mt 0.395 0.617 0.888 1.580 2.460
Total Reinforcement Qty 705.09 ### 306.54 ### - - 3,908.31 KG's
Total Weight Say MT 3.91 MT
Page 269
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Under Ground Sump Tank
RA BILL NO - 01
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2-2.2 : Earthwork excavation by manual means for foundation of buildings, culverts, water supply and sanitary
lines and electrical conduits etc, either in pits or in trenches 1.5m and above in width, in hard soil not exceeding 1.5
1 2.4
m. in depth including dressing the bottom and sides of pits and trenches, stacking the excavated soil clear from edges
of excavation with lead upto 50 m. including breaking of clods complete as per specifications. No. KBS 2.1(a) / 2.3.5
E.W Excavation
Sump 1.0 7.4 4.4 1.2 39.072
Total Qty 39.072 Cum
KSRB 2-2.4 : Excavation by manual means for foundation of buildings, water supply & sanitary lines and electrical
conduits etc., either in pits or in trenches 1.50m and above in width, in soft rock without blasting 1.50mtrs in depth
2 2.6
including stacking the excavated stuff clear from edges of excavation with lead upto 50mt including cost of
explosives, labour, HOM of equipment complete as per specifications. specification. No. KBS 2.1C/2.9.4/2.18/2.19
E.W Excavation
Sump 1.0 7.4 4.4 1.2 37.444
Total Qty 37.444 Cum
KSRB 2.3 : Filling available excavated earth ( excluding rock ) in sides of foundations upto plinth in layers not
3 2.1 exceeding 20 cms. in depth, compacting each deposited layer by ramming after watering with lead upto 50 m. and lift
upto 1.5 m. including cost of all labour complete as per specifications. Specification. No. KBS 2.9
Page 270
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Qty Same as Item No.1-2.4 39.1
Qty Same as Item No.2-2.6 37.4
Deductions
PCC -1 7.1 4.1 0.15 -4.4
Tank Volume -1 6.4 3.4 2.35 -51.1
Total Qty 21.01 Cum
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 with OPC cement @ 220kgs, with
40mm and down size graded granite metal coarse aggregates @0.892cum and fine aggregates @ 0.465cum machine
4 4.2
mixed, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation including
cost of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2
PCC 1 7.1 4.1 0.15 4.4
Total Qty 4.4 Cum
KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of Design mix M20 with OPC cement @
320kgs, with 20mm and down size graded granite metal coarse aggregates @0.69cum and fine aggregtes @ 0.460
cum, with super plasticisers @ 3 liters confirming to IS 9103-1999 reafirmed-2008, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in foundation for footings, pedastals, retaining walls, return
5 4.11
walls, walls (any thickness) including attached pilasters, columnspillars, posts, struts, buttresses, bed blocks, anchor
blocks & plinths etc., including cost of all materials, labour, HOM of machinery, curing, complete but excluding cost of
reinforcement as per specifications.
Specification No. KBS 4.1, 4.6
Base Slab 1 6.80 3.80 0.20 5.17
Vertical Wall 2 6.40 0.20 2.35 6.02
2 3.00 0.20 2.35 2.82
Beam Concrete 3 3.00 0.23 0.23 0.48
Top Slab 1 6.40 3.40 0.15 3.26
Total Qty 17.74 Cum
Page 271
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking,
placing in position, lapping and / or welding wherever required, tying with binding wire and anchoring to the adjoining
6 4.46.2
members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost
of materials, labour, HOM of machinery complete as per specifications. Specification No. KBS 4.6.3 - TMT bars Fe 500
Steel 1.59
Total Qty 1.59 Tonne
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per
7 4.28
specificaitons.
Specification No. KBS 4.6.2
PCC Shuttering 1 2 7.10 0.15 2.13
1 2 4.10 0.15 1.23
Base Slab Shuttering 1 2 6.80 0.20 2.72
1 2 3.80 0.20 1.52
Total Qty 7.60 Sqm
KSRB 4-6.2 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for flat
8 4.18 surface such as roofs, landings, balconies and likes, thickness upto 200 mm including cost of all materials, labour
complete as per specificaitons.up to 3.50m from Ground level. Specification No. KBS 4.6.2
Page 272
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Long Wall 1 2 6.40 2.00 25.6
1 2 6.00 2.00 24.0
Short Wall 1 2 3.40 2.00 13.6
1 2 3.00 2.00 12.0
Total Qty 75.2 Sqm
KSRB15-3.8 : Providing 18mm thick cement plaster in single coat with cement mortar 1:4, to brick masonry including
10 15.16 rounding off corners wherever required smooth rendering, : Providing and removing scaffolding, including cost of
materials, labour, curing complete as per specifications.
KSRB15-3-13 : Providing 12mm thick cement plaster in single coat with cement mortar 1:3, to ceiling including
11 15.21 rounding off corners wherever required smooth rendering, : Providing and removing scaffolding, including cost of
materials, labour, curing complete as per specifications.
KSRB15-3.10 : Providing 20mm thick cement plaster in single coat with cement mortar 1:3, to stone masonry &
12 15.18 concrete surface including rounding off corners wherever required smooth rendering, : Providing and removing
scaffolding, including cost of materials, labour, curing complete as per specifications.
External Plastering
Long Wall 1 2 6.4 2.15 27.5
Page 273
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Short Wall 1 2 3.4 2.15 14.6
Total Qty 42.1 Sqm
KSRB15-4.6 Extra for providing and mixing waterproofing compound in cement plaster for birck masonry work at one
13 15.28 kg per bag or in the proportion recommended by the manufacturers, for cement mortar 1:3, 20mm thick cost of
materials complete as per specifications.
KSRB15-6 : Providing floating coat of cement to plastering and finishing smooth, including cost of materials, labour,
14 15.32
curing complete as per specifications.
Providing & fixing 60mm x 60cm MS inspection door with necessary MS frame made out of MS angle of 50mm x
15 DR 50mm x 6mm & MS shutter of 3 mm thickness with hinges on top & locking arrangements, painting, etc complete
Page 274
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Under Ground Sump Tank Steel
Sump Tank Steel Fabrication RA BILL NO - 01
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Base Slab
Main Bars 10 47 1 2 4.0 - 376.00 - - - -
Distribution Bars 10 27 1 2 7.0 - 378.00 - - - -
Chairs 12 20 1 1 1.25 - - 25.00 - - -
Vertical Wall Steel - - - - - -
Long Wall - - - - - -
Inner Horizantal Bars 8 15 1 2 6.00 180.00 - - - - -
Outer Horizantal Bars 8 15 1 2 6.40 192.00 - - - - -
Inner Vertical Bars 12 41 1 2 2.35 - - 192.70 - - -
Outer Vertical Bars 12 44 1 2 2.35 - - 206.80 - - -
Chairs 12 25 1 1 1.25 - - 31.25 - - -
Short Wall - - - - - -
Inner Horizantal Bars 8 15 1 2 3.00 90.00 - - - - -
Outer Horizantal Bars 8 15 1 2 3.40 102.00 - - - - -
Inner Vertical Bars 12 21 1 2 2.35 - - 98.70 - - -
Outer Vertical Bars 12 24 1 2 2.35 - - 112.80 - - -
Chairs 12 10 1 1 1.25 - - 12.50 - - -
Beam Steel - - - - - -
Top & Bottem Bars 16 6 1 2 3.78 - - - 45.36 - -
2LV Stirrup @ 200mm C/C 8 21 1 2 1.31 55.02 - - - - -
Top Slab Steel - - - - - -
Longer Span - - - - - -
Straight Bars 8 12 1 1 6.40 76.80 - - - - -
Bent Up Bars 8 12 1 1 7.67 92.04 - - - - -
Extra Bar at Top 8 12 1 1 2.50 30.00 - - - - -
Page 275
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Shorter Span - - - - - -
Straight Bars 8 22 1 1 3.40 74.80 - - - - -
Bent Up Bars 8 22 1 1 3.82 84.13 - - - - -
Extra Bar at Top 8 22 1 1 0.70 15.40 - - - - -
Chairs 12 30 1 1 1.25 - - 37.50 - - -
Reinforcement Around Openings - - - - - -
Straight Bars 10 3 4 2 0.90 - 21.60 - - - -
Inclined Bars 10 3 4 2 0.60 - 14.40 - - - -
Total Length In mts 992.19 790.00 717.25 45.36 - -
Unit Wt/mt 0.395 0.617 0.888 1.580 2.46 3.858
Total Reinforcement Qty 391.91 487.43 636.92 71.67 - - 1,587.93 Kgs
Total Weight Say MT 1.59 MT
Page 276
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Borewell And Pump Errection
RA BILL NO - 01
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Supplying, fixing, wiring, earth electrode for grounding conduits, I.C. cutouts and other equipment's on
the meter board using 40mm dia 2.90mm thick GI pipe 2.5 mtr long buried in a pit … The pit should be
filled with equal proportion of salt and charcoal 150mm all-round the pipe to complete depth. The
1 7.1
connection from the pipe to the conduit etc., is to be established through GI wire of size as per ISI
specification 7.3.3. of IS 732 using 12mm dia bolts, nuts, washers and check nuts etc., the pipe shall
have 16 through holes of 122 mm dia
Cutouts 2 2
Total Qty 2 No
Digging of trench of 0.6m deep x 0.50 mtr wide refilling the trench to the required ground level and
2 7.9.2
consolidating etc., complete.(As per Civil SR KSRB I-2, P-7) - In soil (hard)
Borewell-1 to Sump 1 200 200
Borewell-2 to Sump 1 75 75
Borewell-1 to Panel Board 1 20 20
Borewell-2 to Panel Board 1 25 25
Total Qty 320 Mtr
Providing and filling sand in excavated trench to cover already laid UG cable to a depth of 150mm all-
3 7.1
round the cable.
Borewell-1 to Sump 1 200 200
Borewell-2 to Sump 1 75 75
Borewell-1 to Panel Board 1 20 20
Page 277
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Borewell-2 to Panel Board 1 25 25
Total Qty 320 Mtr
Supplying and fixing of class A (medium duty) GI pipe of wall thickness not less than 3.25mm on
4 7.12.1
pole/wall/drain crossing with necessary clamping arrangements for UG cable of 1.1 KV. - 40mm
G.I pipe 2 6 12
Total Qty 12 Mtr
Supplying and fixing L.T. cast Iron pot heads suitable for 1.1 KV class UG cable filled with necessary
5 7.13.3
bitumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc. - 25Sqmm
C.I Pot Heads 2 2
Total Qty 2 Each
Supplying tinned copper lugs and crimping and wiring to terminal point for wire of the following sizes. -
6 7.21.7
25 sqmm Long Barrel
Copper Lugs 16 16
Total Qty 16 Each
Fixing a shunt capacitor of … KVAR capacity with necessary clamps, bolts, and nuts on existing wooden
7 17.15.1
or metal board including banking of more than one capacitor. - Up to 5 KVAR
Capacitor 4 4
Total Qty 4 Each
Supplying of 1.1 KV LT UG cable having aluminum conductor PVC insulated, extruded inner sheathed,
galvanized, steel strip (except 2CX10Sq.mm wire armoured) confirming to IS-3975:1990 (No. of Strip
8 7.4.5
indicated in GTP) & extruded PVC outer sheathed armoured cable with specified IS-1554 Part-1:1988 &
confirming to GTP of GROUP-A. - 3.5 core 25 sqmm
UG Cable
Borewell-1 to Pump House 1 30 30
Borewell-2 to Pump House 1 70 70
Page 278
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Pump House to Pole 1 20 20
Total Qty 120 Each
Labour charges for laying of 1.1 KV class UG cable in existing trench GI pipe / stoneware pipe / on wall /
9 7.8.A.2
on pole as required.In existing trench/duct. - 25 sqmm to 75 sqmm
Page 279
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Sinking of Borewell of 165mm dia clear using super fast hydraulic rig of capacity 250 PSIG & above 900
CMF & above in all strata including over burden upto 20 M. fixing of casing pipes, collars and cap with
necessary cutting, threading and welding including transportation of rig and supporting vehicle, crew
12 9.1.3
charges and cost of consumables etc., complete including yield testing at the final depth with a
minimum working of compressor for one hour (excluding cost of casing pipes, collars, cap etc.,) -
100.00 to 150.00 mtrs
Sinking of Borewell-1 1 50 50
Sinking of Borewell-2 1 50 50
Sinking of Borewell-3 1 50 50
Total Qty 150 Rmtr
Sinking of Borewell of 165mm dia clear using super fast hydraulic rig of capacity 250 PSIG & above 900
CMF & above in all strata including over burden upto 20 M. fixing of casing pipes, collars and cap with
necessary cutting, threading and welding including transportation of rig and supporting vehicle, crew
13 9.1.4
charges and cost of consumables etc., complete including yield testing at the final depth with a
minimum working of compressor for one hour (excluding cost of casing pipes, collars, cap etc.,) -
150.00 to 200.00 mtrs
Sinking of Borewell-1 1 50 50
Sinking of Borewell-2 1 50 50
Sinking of Borewell-3 1 50 50
Total Qty 150 Rmtr
Sinking of Borewell of 165mm dia clear using super fast hydraulic rig of capacity 250 PSIG & above 900
CMF & above in all strata including over burden upto 20 M. fixing of casing pipes, collars and cap with
necessary cutting, threading and welding including transportation of rig and supporting vehicle, crew
14 9.1.5
charges and cost of consumables etc., complete including yield testing at the final depth with a
minimum working of compressor for one hour (excluding cost of casing pipes, collars, cap etc.,) -
200.00 to 250.00 mtrs
Sinking of Borewell-1 1 50 50
Sinking of Borewell-2 1 50 50
Sinking of Borewell-3 1 50 50
Total Qty 150 Rmtr
Page 280
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Sinking of Borewell of 165mm dia clear using super fast hydraulic rig of capacity 250 PSIG & above 900
CMF & above in all strata including over burden upto 20 M. fixing of casing pipes, collars and cap with
necessary cutting, threading and welding including transportation of rig and supporting vehicle, crew
15 9.1.6
charges and cost of consumables etc., complete including yield testing at the final depth with a
minimum working of compressor for one hour (excluding cost of casing pipes, collars, cap etc.,) -
250.00 to 300.00 mtrs
Sinking of Borewell-1 1 50 50
Sinking of Borewell-2 1 50 50
Sinking of Borewell-3 1 50 50
Total Qty 150 Rmtr
Sinking of Borewell of 165mm dia clear using super fast hydraulic rig of capacity 250 PSIG & above 900
CMF & above in all strata including over burden upto 20 M. fixing of casing pipes, collars and cap with
necessary cutting, threading and welding including transportation of rig and supporting vehicle, crew
16 9.1.7
charges and cost of consumables etc., complete including yield testing at the final depth with a
minimum working of compressor for one hour (excluding cost of casing pipes, collars, cap etc.,) -
300.00 to 350.00 mtrs
Sinking of Borewell-1 1 50 50
Sinking of Borewell-2 1 50 50
Sinking of Borewell-3 1 50 50
Total Qty 150 Rmtr
Sinking of Borewell of 165mm dia clear using super fast hydraulic rig of capacity 250 PSIG & above 900
CMF & above in all strata including over burden upto 20 M. fixing of casing pipes, collars and cap with
necessary cutting, threading and welding including transportation of rig and supporting vehicle, crew
17 9.1.8
charges and cost of consumables etc., complete including yield testing at the final depth with a
minimum working of compressor for one hour (excluding cost of casing pipes, collars, cap etc.,) - Above
350.00 mtrs
Page 281
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Geophysical Investigation of site for sinking Borewell for supplying drinking water to the habitation
either through the Hand Pump, MWS or P.W.S.S. by vertical electrical sounding by adopting venner or
Schlumberger's method, including reconnaissance survey of geological formation, Geophysical
investigation of existing Ground water in the vicinity, its quality, quantity & acceptability of the users
18 9.4 indicating the location of site, recommended depth of casing pipe required to seal the top
unconsolidated formation incluing an extra depth of 1.0 metre in consolidated formation for proper
seating of casing pipe, depth of drilling required to cover full depth of aquifer proposed to be tapped,
probable yield and other information required including transportation of instrument and accessories to
work site, engaging
Geophysical technical personal
investigation 3 and labour required etc., 3.00
Total Qty 3.00 Nos
19 10.2.14 Replacement of pump parts - Non return valve (NRV) assembly complete with rubber "O" ring
Non Return Valve 2 2.00
Total Qty 2.00 Nos
20 3.4.2.b PVC Pipes of 6 kg./cm2 - 75mm (0.917)
Borewell-1 1 200 200
Borewell-2 1 75 75
Total Qty 275 Mtr
Multy strand multi core Flat bore well cables 6 Sq.mm 56/0.3 mm dia
21 81
Borewell-1 1 350 350
Borewell-2 1 350 350
Borewell-1to Panel Board 1 20 20
Borewell-2to Panel Board 1 25 25
Total Qty 745 Rmtr
Page 282
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code Galvanized mild steel tube(Contineouslywelded)
No's L
electric resistence B
welded D
(ERW)High Qty
frequency
induction welded (HFIW)hot finished weided type of nominal bore given below,screwed to both ends as
per IS 554/1986 with latest amendments,pipes threaded at both ends,random lenghs of 4 to7
22 DR mtrs .Confirming to IS- 1239 part /I/1990 with amendments 1-5 with all its latest amendments if
any ,the pipes supplied should be with BIS Mark Galvanized Iron pipes ISI239 (part-I)1990 (50mm dia
'C' class heavy duty without collar)
Borewell-1 1 335 335
Borewell-2 1 328 328
Total Qty 663 Rmtr
PROCUREMENT OF PUMP SET & ERRECTION: Providing submesible pump set & Errection suitable for
borewell of 165 mm dia and having the declared duty conditioned as detailed below and satisfying
performance characteristics for pump and motor as declared by the bureau of Indian Standards (With
23 DR all its latest amendments) and should bear ISI certification mark IS 8034:1989 the pumpset should
consists of bronze impellers only(capacity in 12.5HP- 25 stage) capable of discharging 2.46 LPS for a
total head of 87.6 mts all as per directions of PMC/EIC (TEXMO OR EQUQLENT BRANDS)
Page 283
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB13-6.3-6 : Providing and fixing in position brass gate valve with C.I wheel of approved quality
( screwed end ) 50mm nominal bore including cost of all materials, labour and HOM of equipments with
25 13.37
all leads complete as per specifications. Specification No.KBS 13.2.6 / 13.3
Page 284
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Panel Baord 2 2.00
Total Qty 2.00 No
Page 285
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:-Compound Wall
RA Bill-01
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2-2.2 : Earthwork excavation by manual means for foundation of buildings, culverts, water supply and sanitary lines and electrical
1 conduits etc, either in pits or in trenches 1.5m and above in width, in hard soil not exceeding 1.5 m. in depth including dressing the bottom
2.4
and sides of pits and trenches, stacking the excavated soil clear from edges of excavation with lead upto 50 m. including breaking of clods
complete as per specifications. No. KBS 2.1(a) / 2.3.5
E.W Excavation in South Face
For Footings 101 1.4 1.4 1.50 296.94
For Plinth Beam 1 300 0.55 0.45 74.25
Deductions 101 1.4 0.55 0.45 35.00
Total Qty 406.19 Cum
KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix 1:3:6 with OPC cement @ 220kgs, with 40mm and down size
2 graded granite metal coarse aggregates @0.892cum and fine aggregates @ 0.465cum machine mixed, machine mixed, concrete laid in layers
4.2
not exceeding 15 cms. thick, well compacted, in foundation including cost of all materials, labour, HOM of machinery, curing complete as per
specifications. Specification No. KBS 4.1, 4.2
PCC For Footings 101 1.0 1.0 0.10 10.1
PCC Under Plinth Beam 1 300 0.45 0.10 13.5
Deductions -101 0.23 0.23 0.10 -0.53
Total Qty 23.07 Cum
Page 286
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 6-1.3 : Providing and constructing burnt brick masonry for basement and superstructure with approved quality of non-modular bricks
3 6.3 of standard size of class designation 3.5Newton per sqmm with cement mortar1:6 including cost of materials, labour charges, scaffolding,
curing complete as per specifications. Specification No. KBS 6.2
KSRB 4-1.6 ; Providing and laying in position plain cement concrete of mix 1:2:4 with cement @ 240kgs, with 20mm and down size graded
granite metal coarse aggregates @ 0.878 cum and fine aggregtes @ 0.53cum, machine mixed, concrete laid in layers not exceeding 15 cms.
4 4.6 thick, well compacted, in foundation, plinth and cills, ncluding cost of all materials, labour, HOM of machinery, curing complete as per
specifications. Specification No. KBS 4.1, 4.2
KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of Design mix M20 with OPC cement @ 320kgs, with 20mm and
down size graded granite metal coarse aggregates @0.69cum and fine aggregtes @ 0.460 cum, with super plasticisers @ 3 liters confirming
to IS 9103-1999 reafirmed-2008, machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all works in foundation for
5 4.11 footings, pedastals, retaining walls, return walls, walls (any thickness) including attached pilasters, columnspillars, posts, struts, buttresses,
bed blocks, anchor blocks & plinths etc., including cost of all materials, labour, HOM of machinery, curing, complete but excluding cost of
reinforcement as per specifications.
Specification No. KBS 4.1, 4.6
Footing Concrete 101 0.80 0.80 0.25 16.16
Column Concrete Upto Plinth Top 101 0.23 0.23 1.6 8.55
Plinth Beam Concrete 100 2.77 0.23 0.45 28.67
Column Concrete Above Plinth In South 101 0.23 0.23 1.58 8.44
Total Qty 61.82 Cum
Page 287
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
KSRB 2.5 : Earthwork excavation in all soil deposits and filling sides of foundation upto plinth in layers not exceeding 20cms. in depth,
6 2.12 compacting each deposited layer by ramming after watering with all lead and lift including cost of all labour complete as per specifications.
specification. No. KBS 2.9.9 / 2.9.10.1 / 2.1.1
Page 288
Item Measurment Upto date
Sl. No Description of Items Unit Remarks
Code No's L B D Qty
Coping Concrete 100 2 2.77 0.08 44.32
Total Qty 293.62 Sqm
KSRB 4-6.5 : Providing and removing centering, shuttering, strutting, propping etc., for columns, pillars, post and struts, square /
9 4.32 rectangular/polygon in plan including cost of all materials, labour complete as per specifications. Specification No. KBS 4.6.2
Column Shuttering
Column Shuttering Upto Plinth Top 101 0.92 1.60 148.67
Column Shuttering Above Plinth 101 0.92 1.58 146.81
Total Qty 295.49 Sqm
KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position,
lapping and / or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete
11 4.46.2 as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per
specifications. Specification No. KBS 4.6.3 - TMT bars Fe 500
Page 289
WORK :- Construction of MDRS Complex
AGENCY :- R.RAMA REDDY Engineer & Contractor
:- Kalkeri Village,
:- Hanagal Taluk
:- Haveri District.
:- Compound Wall
Compound Steel Fabrication RA BILL NO - 01
Dia Of
Sl. No Shape of bar Nos L 8.00 10 12 16 20 25
bars
Footing Mat Steel
Footings in South Face - - - - - -
X-Direction Bars 10 7 1 101 0.95 - 671.65 - - - -
Y-Direction Bars 10 7 1 101 0.95 - 671.65 - - - -
Column Steel - - - - - -
Main Bars 12 4 1 101 3.88 - - 1,567.52 - - -
Stirrups 8 21 1 101 0.87 1,845.27 - - - - -
Plinth Beam Steel - - - - - -
Top & Bottem Bars 12 6 1 100 3.75 - - 2,250.00 - - -
Stirrups @ 200mm c/c spacing 8 16 1 100 1.31 2,096.00 - - - - -
Total Length In mts 3,941.27 1,343.30 3,817.52 - - -
Unit Wt/mt 0.395 0.617 0.888 1.580 2.46 3.858
Total Reinforcement Qty 1,556.80 828.82 3,389.96 - - - 5,775.58 Kgs
Total Weight Say MT 5.78 MT
Page 290
KARNATAKA RESIDENTIAL EDUCATIONAL INSTITUTIONS SOCIETY, BANGALORE
Name of work : Constuction of MDRS Complex
Location : Kalkeri Village, Hanagal Tq, Haveri District.
Name of the PMC : AMINBHAVI & HEGDE Consulting Engineers Pvt.Ltd
Name of The Agency : R. RAMA REDDY Engineer & Contractor
R P o i V=0.85 x R x P x (i-o)/o
1 Labour component 30.00% 295.00 311.00 324316.96
2 Cement component 11.38% 106.70 111.40 99913.95
23,449,388.17
3 Steel component 9.53% 89.40 106.50 363330.56
4 Other Materials 49.09% 113.20 116.00 242022.13
Total Amount In Rs . 100.00% 1029583.61