Casing Design PDF
Casing Design PDF
30" CP
20" csg
13 3/8" csg
“standard" profile”
9 5/8" csg
8 1/2“ hole
• The depth at which the conductor pipe (C.P.) will be fixed must allow
the mud to circulate to the surface.
• Shallow gas.
Onshore wells
Offshore wells
¾ - Fixed platform
¾ - Jack-up Rig
¾ - Floating Rig (Semisub-Drilling ship)
Shallow Gas
Onshore wells
¾ Low risk
¾ Medium risk (Diverter)
¾ High risk (Move to a safer well location)
dm (E + H) −1.03H
Hi =
(1.03+ 0.67(GOV −1.03)) − d f
Where:
Hi = Length of CP in m (actual penetration from the seabed)
E = Distance from rotary table to sea level – m
H = water depth – m
Gov = density of sediments at C.P. shoe depth – kg/cm2/10m
dm = density of the mud in the next stage – kg/dm3
¾ Protect fresh water sands from contamination with the drilling mud.
Etc.
The production casing string will serve to isolate the productive intervals, to
facilitate proper reservoir maintenance and/or prevent the influx of
undesired fluids.
This is the string through which the well will be completed, produced and
controlled throughout its life.
Diameter.
INTERMEDIATE LINER
PRODUCTION LINER
LITHOLOGICAL PROBLEMS
HYDROCARBON TARGETS
¾ SAFETY;
¾ HYDROCARBON TARGETS;
¾ EVAPORITE FORMATIONS (SALT – ANHYDRITES);
¾ OVERTHURST FORMATIONS;
¾ SEPARATION BETWEEN CLASTS AND CARBONATES.
DRILLING PROBLEMS
DEVELOPMENT OF PRESSURE GRADIENT
CHOKE MARGIN
DIFFERENTIAL PRESSURE
INCOMPATIBILITY BETWEEN DIFFERENT
GRADIENT FORMATIONS
DIRECTIONAL WELLS
MARGIN AT THE
CHOKE
Pore gradient
MUD density
Fracturing gradient
DIFFERENTIAL PRESSURE
PORE gradient
Mud Density
Fracturing gradient
FRACTURING
PRESSURE
Depth 1 P1
Depth m
Depth 2 P2
PORE PRESSURE
P3
Depth 3
Depth 4 P4
Pressure
Pressure gradients
(kg/cm2/10m)
13 3/8”
Intermediate
Casing
at m 1200
“Standard “Slim"
13 3/8" CP
Casing Profile” 30" CP Casing Profile
9 5/8" csg
20" csg
4 1/2“ Hole
8 1/2" Hole
30” CP
24 1/2” CP
”Standard" 24 1/2”
“Lean" 18 5/8”
Profile Profile
(5 casing (5 casing
strings) 18 5/8” strings) 16”
13 3/8” 13 3/8”
9 5/8” 9 5/8”
8 1/2”
8 1/2” Hole
Hole
¾ Outside Diameters
¾ Wall tickness weights (lb/ft)
¾ Caliper
¾ Length (range 1-2-3)
Drift
Steel grade (coloured bands)
Connections
etc…
• BIG OMEGA
• MANNESMAN
Flush Joint
ATLAS BRADFORD
BURST
COLLAPSE
TENSION
9 Plastic formations
9 Dog legs
9 Buckling
9 Wear
9 Squeezing / acid jobs
9 Corrosion
9 etc.
1. BURST
2. COLLAPSE
3. Verification of TENSION
Pressure Gradients
Kg/cm2/10m
Fracturing 20”
500 Gradient
1000
Mud
Pressure gradients density
13 3/8”
(Kg/cm2/10m) 1500
Formation
Gradient
2000
2500 9 5/8”
7”
3000
RESULTING PRESSURE
THE BURST STRENGTH LINE IS OBTAINED BY SUBTRACTING THE
EXTERNAL PRESSURE FROM THE INTERNAL PRESSURE AT THE VARIOUS
DEPTHS.
RESULTING PRESSURE
THE BURST STRENGTH LINE IS OBTAINED BY SUBTRACTING THE
EXTERNAL PRESSURE FROM THE INTERNAL PRESSURE AT THE VARIOUS
DEPTHS.
13 3/8”
Intermediate
Casing
at 1200 m
9 5/8”
Intermediate
Casing
at 2500 m
9AT THE SHOE the sum of the well-head pressure plus the hydrostatic pressure of the
completion fluid and the fluid above the packer .
RESULTING PRESSURE
THE BURST STRENGTH LINE IS OBTAINED BY SUBTRACTING THE EXTERNAL
PRESSURE FROM THE INTERNAL PRESSURE AT THE DIFFERENT DEPTHS
7”
PRODUCTION
Casing
at 3000 m
RESULTING PRESSURE
THE BURST STRENGTH LINE IS OBTAINED BY SUBTRACTING THE
INTERNAL PRESSURE FROM THE EXTERNAL PRESSURE AT THE
DIFFERENT DEPTHS
Well Area Operations
Agip KCO Drilling Supervisors Training Course
Drilling Technology
1st Part
RPW2021A 53
CASING DESIGN COLLAPSE
Surface
Casing
400 m
RESULTING PRESSURE
THE RESULTING COLLAPSE STRENGTH WILL BE GIVEN BY THE
DIFFERENCE BETWEEN THE EXTERNAL PRESSURE AND THE INTERNAL
PRESSURE AT THE DIFFERENT DEPTHS
300
13 3/8”
Intermediate
D1 D2 D3 = External pressure
Casing 600
equal
at 1200 m to the PORE
D1= 82.4 Pressure.
(1.03X800/10)
900
D2= 120
(1.2X1000)/10
D3
1200 F=234-165 D3=(1.375X1200/10) A 1.95 x 1200/10 = 234
= 69 =165
50 100 150 200 250 300 350
300
13 3/8”
Intermediate
D1 D2 D3 = External pressure
Casing 600
equal
at 1200 m to the PORE
D1= 82.4 Pressure.
(1.03X800/10)
900
D2= 120
(1.2X1000)/10
D3
1200 F=234-165 D3=(1.375X1200/10) A 1.95 x 1200/10 = 234
= 69 =165
50 100 150 200 250 300 350
RESULTING PRESSURE
THE BURST STRENGTH LINE IS OBTAINED BY SUBTRACTING THE
INTERNAL PRESSURE FROM THE EXTERNAL PRESSURE AT THE
DIFFERENT DEPTHS
Gpore
• Hmud = Hloss (1- Dmud
)
• where:
• H mud = depth of the mud level inside the csg
• H loss =depth at which there was a mud circulation loss
• Dmud = Planned mud density at mud circulation loss depth
• Gpore = pore pressure at the mud circulation loss depth
13 3/8”
Intermediate
Casing
at 1200 m
13 3/8”
Intermediate
Casing
at 1200 m
9 5/8”
Intermediate
Casing
at 2500 m
7” Production
Casing
at 3000 m
• Calculating sequence:
The selected casing (P110) is suitable as its tension strength is 676 Ton.
ud
TFL
m
1200
of the pipe and to be added to tension load .
n
i
ght
air
The additional load is calculated using the
ei
W
ni
following relation: TFL = 15.52 * ß * 2000
ht
eig
D * Af
W
50 100 150 200 tension
where
ß = angular rate (degrade/30m)
D = nominal diameter of the csg, in
Af = Section of the pipe in cm2
The theory developed by Holmquist and Nadai takes into account the overlap of
the axial stresses due to tension or compression and the tangential tensions
resulting from burst and collapse.
BURST
COMPRESSION TENSION
COLLAPSE
¾ Mud characteristics
¾ Solids content
¾ Lubricants in the mud Tool Joint
¾ Tool joint hard facing
1. Surface Casing
a) Offshore wells
b) Offshore wells
> From Jack-up / Fixed Platform
- Exploration wells
- Development wells
> From Floating Rig
2. INTERMEDIATE CASING
The main aim of the rise of the cement in the annuls is to restore the
hydraulic conditions in the well after the borehole has been drilled (avoid
communication between formations with different pressure gradient and
containing different hydrocarbons), isolate overpressure zones; temperature
problems.
a) Onshore wells
b) Offshore wells
3. PRODUCTION CASING
The main aim of the rise of the cement in the annuls is to restore the
hydraulic conditions in the well after the borehole has been drilled (avoid
communication between formations with different pressure gradient and
containing different hydrocarbons), isolate overpressure zones; temperature
problems.
a) Onshore wells
b) Offshore wells
Some stresses, if not appropriately taken into account, can lead to the deflection or
“collapse” of the casing.
The “overpull of casing to set casing slips ” has the task of eliminating the buckling effect
which can cause the failure of the casing .
Are calculated:
1. Weight in air of the uncemented casing section.
2. Stresses due to internal pressure variations.
3. Stresses due to external pressure variations.
4. Stresses due to temperature variations.
5.Critical Bending force (to be summed only if positive).
THE TOTAL OVER PULL TO APPLY WHEN WELL HEAD CASING SLIPS ARE SET IS
GIVEN BE THE ALGEBRAIC SUM OF THE EFFECTS INDICATED ABOVE.
2. Additional tests must be carried out at least once every two weeks.
3. “Bag Preventer” – the test value, with drill string in the well, must be between
70/100 kg/cm2 .
4. “Blind Rams” – The test value must not be more than 70 kg/cm2 .
5. “Ram Preventers”- The test value must not exceed 70% of the minimum resistance
values of the parts involved (casing/well head/BOP).
6. “Kill/choke lines & choke manifold” must be tested at their pressure rating ( each
valve of the choke manifold must be tested individually ).
- 2.000 psi
- 3.000 psi
- 5.000 psi
- 10.000 psi
- 15.000 psi
Spool height:
Landing Base 470 - 510 mm
Intermediate Spool 470- 850 mm Upper Spool 580 - 750 mm
Well head
Landing Base
13 5/8” 3000 psi
CSG 13 3/8”
Well head
5000 psi
13 5/8” x 11” 5000 psi
Well head
5000 psi
13 5/8” x 11” x 7 1/16” 5000 psi
¾ Housing (Well head body) – housing for the hangers of the subsequent casings.
¾ Casing hanger for each casing string with relative sealing packer.
¾ Tubing hanger.
ADVANTAGES
- The BOPs are run in and installed just once. Marked reduction in times compared to the
traditional well head (BOPs do not need to be dis-assembled for flanging).
- Tests are carried out immediately after casing and insertion of the sealing packing.
- Reduction in the height of the well head.
The pressure rating of the BOPs must be higher than the maximum
pressure predicted at the well head (with the exception of the annular
preventer).
H
Pmax= (GFracture – Ggas)
10
H = Shoe depth in m
GFracture = fracture gradient at the shoe in kg/cm2/10m
Ggas = gradient of the gas equal to 0.3 kg/dm3
H
Pmax= (GFracturing – Ggas)
10
H = Shoe depth in m
GFracture = fracture gradient at the shoe in kg/cm2/10m
Ggas = gradient of the gas equal to 0.3 kg/dm3
Blow-out
Preventers
“Bag Type
Preventer”
Note: the shear rams must be activated on the basis of a “Risk analysis”
assessment and in accordance with local legislation.