Ufgs 33 05 23
Ufgs 33 05 23
Ufgs 33 05 23
DIVISION 33 - UTILITIES
SECTION 33 05 23
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Microtunneling
1.2.2 Jacking Precast Concrete Pipe
1.2.3 Jacking Precast Concrete Box Sections
1.3 SUBMITTALS
1.4 PRE-CONSTRUCTION
1.5 QUALITY CONTROL
1.5.1 STATEMENT OF CONTRACTOR QUALIFICATIONS
1.5.2 RECORDS
1.5.2.1 DAILY WORK LOG
1.6 DELIVERY, STORAGE, AND HANDLING
1.6.1 Handling
1.7 SAFETY
1.7.1 General
1.7.2 Equipment
1.7.3 Sheeting, Shoring and Dewatering
1.7.4 Tunnel Bore
1.8 QUALITY ASSURANCE
1.8.1 Microtunneling PlanBoring and Jacking Plan
1.8.1.1 Operational Layout
1.8.1.1.1 Layout Plan
1.8.1.1.2 Pedestrian Access Around Site
1.8.1.2 Method and Procedures
PART 2 PRODUCTS
SECTION 33 05 23 Page 1
2.1.1.2 Design Calculations of Pipe Casing
2.2 EQUIPMENT
2.2.1 Microtunneling System
2.2.1.1 General Requirements
2.2.1.2 Control System
2.2.2 Boring and Jacking System
2.2.3 Pipe Jacking Equipment
2.3 MATERIALS
2.3.1 Pipe Casing
2.3.1.1 Reinforced Concrete Pipe
2.3.1.1.1 Pipe
2.3.1.1.2 Joints and Jointing Material
2.3.1.1.3 Internal Diameter
2.3.1.1.4 Wall Thickness
2.3.1.1.5 End Squareness
2.3.1.1.6 Roundness
2.3.1.1.7 Length of Pipe
2.3.1.1.8 Length of Two Opposite Sides
2.3.1.2 Steel Pipe
2.3.1.2.1 Pipe
2.3.1.2.2 Joints
2.3.1.2.3 Roundness
2.3.1.2.4 Circumference
2.3.1.2.5 Straightness
2.3.1.2.6 Pipe Ends
2.3.2 Grout
2.3.3 CONCRETE
2.3.4 Lubricating Fluid (Bentonite or Polymer)
2.3.5 SOIL MATERIALS
2.4 Incidental Materials
2.4.1 Casing Insulators/Bore Spacers
2.4.2 End Closures/Bulkheads
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 Access Shaft and Pit Construction Plan
3.1.1.1 Design Requirements
3.2 CONSTRUCTION
3.2.1 Access Shafts
3.2.1.1 Construction Requirements
3.3 INSTALLATION
3.3.1 Installation of Tracer Wire
3.3.2 Connections to Existing Lines
3.3.3 Advancing the Pipe
3.3.3.1 Installation Requirements
3.3.4 [Carrier Pipe] [Conduit] Installation
3.3.4.1 Cleaning
3.3.4.2 [Carrier Pipe] [Conduit Joints]
3.3.4.3 Casing Insulators/Spacers
3.3.4.4 End Closures/Bulkheads and Grouting of Casing Pipe
3.3.5 Ventilation
3.3.6 Lighting
3.3.7 Spoil Transportation
3.4 TOLERANCES
3.4.1 Tolerances
3.5 FIELD QUALITY CONTROL
3.5.1 Instrumentation/Survey
3.5.1.1 Mandatory Requirements
SECTION 33 05 23 Page 2
3.5.1.2 Supplemental Requirements
3.5.2 Field Tests
3.5.2.1 Pipe Casing
3.5.2.1.1 Testing Requirements for Gravity Mains
3.5.2.1.2 Non-Standard Pipe Lengths
3.5.2.1.3 Elevations
3.5.3 Inspections
3.6 CLEANUP AND FINAL CLOSEOUT
3.6.1 Site Cleanup
3.6.2 Drilling Fluid
3.6.3 Record Drawings and Daily Work Logs
3.7 DISPOSITION OF MATERIAL
SECTION 33 05 23 Page 3
**************************************************************************
USACE / NAVFAC / AFCEC UFGS-33 05 23 (August 2015)
Change 2 - 08/16
------------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-33 05 23.19 (April 2006)
SECTION 33 05 23
**************************************************************************
NOTE: This guide specification covers the
requirements for work related to the installation of
utility pipelines (i.e., electrical power,
communications, water, gas, oil, petroleum products,
steam, sewage, drainage, irrigation, and similar
facilities) utilizing microtunneling or boring and
jacking trenchless construction methods.
**************************************************************************
NOTE: Boring and jacking is a term applied to a
horizontal auger boring process characterized as
mechanically boring and casing a hole through the
soil with a cutting head on a continuous flight of
augers mounted inside the casing pipe. The casing
is advanced simultaneously with the boring operation
via a hydraulic jacking system. Line and grade
SECTION 33 05 23 Page 4
accuracy may not be achieved to the degree of
microtunneling, but this method is often used to
economically install 100 mm to 1.8 m 4 inch to 72
inch diameter casing pipe under roads and railroads
through a wide variety of soil types (including
weathered rock and small cobbles/gravels) up to
distances of 122 m 400 feet.
SECTION 33 05 23 Page 5
In microtunneling boring and jacking permanent pipe
casing can be used as the carrier pipe or a separate
pipe may be placed inside the casing. The Designer
of Record specifies the pipe materials to be used.
The Contractor is responsible for proper selection
of equipment and methods for installation.
**************************************************************************
NOTE: Project Drawings:
SECTION 33 05 23 Page 6
e. New pipeline profiles, to show existing
conditions.
PART 1 GENERAL
SECTION 33 05 23 Page 7
techniques at locations indicated. The Contractor is responsible for all
work related to the provision of utilities installed, including assessing
surface, subsurface, and environmental (seasonal) conditions.
1.1 REFERENCES
**************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in
this paragraph by organization, designation, date,
and title.
SECTION 33 05 23 Page 8
and Larger
1.2 DEFINITIONS
1.2.1 Microtunneling
SECTION 33 05 23 Page 9
1.2.2 Jacking Precast Concrete Pipe
1.3 SUBMITTALS
**************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit
the following list, and corresponding submittal
items in the text, to reflect only the submittals
required for the project. The Guide Specification
technical editors have classified those items that
require Government approval, due to their complexity
or criticality, with a "G." Generally, other
submittal items can be reviewed by the Contractor's
Quality Control System. Only add a "G" to an item
if the submittal is sufficiently important or
complex in context of the project.
SECTION 33 05 23 Page 10
Boring and Jacking Plan; G[, [_____]]
**************************************************************************
NOTE: Use other specifications to require
submittals for the actual carrier pipe unless the
pipe casing is going to act as the carrier pipe.
**************************************************************************
**************************************************************************
NOTE: Suggested Submittals:
SECTION 33 05 23 Page 11
SD-08 Manufacturer's Instructions
1.4 PRE-CONSTRUCTION
Microtunneling Plan
1.5.2 RECORDS
a. Hours worked.
SECTION 33 05 23 Page 12
c. Completed field forms, such as steering control logs, for checking
line and grade of boring operation, showing achieved alignment
relative to design alignment.
Inspect materials delivered to site for damage. Unload and store with
minimum handling. Store materials on site in enclosures or under
protective covering. Store [jointing materials and] rubber gaskets under
cover out of direct sunlight. Do not store materials directly on the
ground. Keep inside of pipes free of dirt and debris.
1.6.1 Handling
1.7 SAFETY
1.7.1 General
1.7.2 Equipment
SECTION 33 05 23 Page 13
1.7.4 Tunnel Bore
Unprotected mining of the tunnel bore is not permitted. Fully support the
tunnel face and bore at all times.
When and where installations disrupt pedestrian use of sidewalk areas for
periods exceeding 2 consecutive days, provide an alternate route that
meets current ADA requirements.
SECTION 33 05 23 Page 14
pipe within specified tolerances.
]PART 2 PRODUCTS
SECTION 33 05 23 Page 15
microtunneling methods of installation.
**************************************************************************
NOTE: Use ASCE 36-15, ASCE 27-00, ASCE 28-00 as
applicable.
**************************************************************************
2.1.1.1 Excavations
For pipe crossings under railways use Cooper E-80 locomotive loading
distributions in accordance with AREMA Eng Man specifications for
culverts. Account for loading due to any multiple tracks.
2.2 EQUIPMENT
SECTION 33 05 23 Page 16
e. Capable of injecting lubricant around the exterior of the pipe being
jacked.
**************************************************************************
NOTE: Specify the maximum allowable overcut of the
advancing equipment to satisfy settlement or heave
tolerances. usually overcut is not to exceed 25 mm1
inch on the radius of the pipe.
**************************************************************************
a. Deviation of the MTBM from the required line and grade of the pipeline
(normally by reference to a laser beam).
c. Jacking load.
SECTION 33 05 23 Page 17
2.3 MATERIALS
Provide straight wall pipe casing [of type and diameter indicated] of
[reinforced concrete pipe (RCP)] [steel pipe].
**************************************************************************
NOTE: This section covers tongue and groove,
straight wall reinforced concrete pipe intended for
use as conveyance systems of sewage and storm water,
and for the construction of culverts and industrial
casings installed and constructed by microtunneling
boring and jacking methods.
**************************************************************************
2.3.1.1.1 Pipe
At any location along the length of the pipe, or at any point around its
circumference, the wall thickness cannot vary by more than plus five
percent of the design diameter.
Ensure that each pipe end lies within two planes perpendicular to the
longitudinal center line of the pipe, spaced at 10 mm 3/8 inches apart.
Square the tongue or spigot end to within 5 mm 3/16 inches and the groove
or bell end of the pipe to within 5 mm 3/16 inches.
2.3.1.1.6 Roundness
Ensure that the outside diameter of the pipe does not vary from a true
circle by more than one percent. Permissible out-of-round dimensions are
one half the difference between the maximum and minimum outer diameter of
the pipe at any one location along the barrel.
SECTION 33 05 23 Page 18
2.3.1.1.7 Length of Pipe
Do not deviate from the finished pipe design length by more than plus 3 mm
per 300 mm 1/8 inch per foot with a maximum variation of plus 13 mm 1/2
inch in any length of pipe.
**************************************************************************
NOTE: This section covers steel pipe used as a
casing pipe for other carrier pipes. This section
also covers steel as the carrier pipe for
stormwater, sanitary sewer or other utility lines.
**************************************************************************
2.3.1.2.1 Pipe
**************************************************************************
NOTE: Choose the first paragraph for microtunneling
and the second for boring and jacking. Modify as
needed.
**************************************************************************
2.3.1.2.2 Joints
][Utilize casing pipe having beveled ends with a single V-groove for field
welding. Butt weld joints using a full-penetration weld on the outside
circumference of the pipe prior to jacking. The welds are to conform to
the latest AWS Welding Code by a certified welder. Unless otherwise
specified, inspect and test welds using a non-destructive testing method
consisting of magnetic particle examination (MT), in compliance with the
AWS code. Visually inspect in compliance with AWS D1.1/D1.1M visual
inspection criteria by a certified welder and by the QC manager welds on
casing pipe that is sacrificial (fully grouted internally).
Non-destructive testing is not required on welds on casing pipe that is
sacrificial.
SECTION 33 05 23 Page 19
provide pipe with 51-mm 2-inch diameter tapped holes with threaded plugs
for exterior grouting.
2.3.1.2.3 Roundness
The maximum difference between the major and minor outside diameters
cannot exceed one percent of the specified nominal outside diameter or 6 mm
0.25 inch, whichever is less. [For pipe exceeding 1200 mm 48 inches in
diameter, a maximum deviation of 13 mm 1/2 inch is permitted provided the
circumference tolerance is maintained within 6 mm 1/4 inch.]
2.3.1.2.4 Circumference
Ensure that the outside circumference is within plus one percent of the
nominal circumference or within plus 13 mm 0.50 inches, whichever is less.
2.3.1.2.5 Straightness
Ensure that the end of the pipe is perpendicular to the longitudinal axis
of the pipe and within 5 mm per meter 1/16 inch per foot of diameter, with
a maximum allowable deviation of 6 mm 1/4 inch measured with a square and
straightedge across the end of the pipe.
]2.3.2 Grout
Provide cement grout for pressure grouting to fill the voids around the
casing and for filling the interior annular space between carrier pipe and
the casing composed of Portland cement conforming to ASTM C150/C150M, Type
II, and sand meeting requirements of ASTM C33/C33Mfor fine aggregate,
sufficiently fluid to inject through the casing and fill voids, with
prompt setting to control grout flow. Utilize a grout with a minimum
compressive strength of 0.70 MPa 100 psi attained within 24 hours.
Admixtures are to be free of chlorides, corrosive or other material
detrimental to the materials the grout contacts.
2.3.3 CONCRETE
SECTION 33 05 23 Page 20
Section 31 00 00 EARTHWORK.
**************************************************************************
NOTE: If casing pipe transitions to carrier
pipe/utility duct without a structure, provide an
end closure/bulkhead detail for the casing pipe
transition and modify the following as to suit the
detail.
**************************************************************************
Provide Temporary End Closures to contain grout used for filling the
annular space between conduits and the casing. Provide Permanent End
Closures of [_____] meters [_____] feet length as indicated consisting of
brick and mortar (one part cement/two parts sand/water) to completely
encapsulate the conduits transition into the casing. Center the closure
on the casing pipe end.
PART 3 EXECUTION
3.1 PREPARATION
SECTION 33 05 23 Page 21
c. Support all excavations and prevent movement of the soil, pavement,
utilities or structures outside of the excavation. Furnish, place,
and maintain sheeting, bracing, and lining required to support the
sides of all shafts and to provide adequate protection of the work,
personnel, and the general public. Provide a concrete floor in the
jacking access shaft. Design loads on the sides of the jacking and
receiving pit walls are dependent on the construction method and
flexibility of the wall systems.
d. Consider the loading from boring or pipe jacking when preparing the
design of the jacking and receiving pit supports as well as special
provisions and reinforcement around the breakout location. Design the
base of the pits to withstand uplift forces from the full design head
of water, unless approved dewatering or other ground modification
methods are employed.
[ f. If tremie concrete sealing slabs are placed within the earth support
system to prevent groundwater inflow when access shafts are dewatered,
furnish and install sealing slabs of sufficient thickness to provide a
minimum factor of safety of 1.2 against hydrostatic uplift in order to
prevent bottom blowout when the excavation is completely dewatered.
]3.2 CONSTRUCTION
a. Provide ground stabilization in the work area and the thrust block as
required to accomplish the work.
SECTION 33 05 23 Page 22
"Tolerances."
e. Provide security fence around all access shaft areas and provide shaft
cover(s) when the shaft area is not in use.
f. Pit Backfill and Compaction: Upon completion of the pipe jacking and
all tests or inspections are complete remove all equipment, debris,
and unacceptable materials from the pits and commence backfilling
operation. Complete backfilling, compaction, and pavement repairs in
accordance with Section 31 00 00 EARTHWORK.
3.3 INSTALLATION
Install a continuous length of tracer wire for the full length of each run
of nonmetallic pipe in accordance with the American Public Works
Association Uniform Color Code. Attach wire to top of pipe in such a
manner that will not be displaced during construction operations.
Jack each pipe casing section forward as the excavation progresses in such
a way to provide complete and adequate, ground support at all times.
Utilize a bentonite slurry applied to the external surface of the pipe to
reduce skin friction. Provide a jacking frame for developing a uniform
distribution of jacking forces around the periphery of the pipe. Place a
plywood spacer on the outer shoulder of the pipe casing joint. Design and
construct the thrust reaction backstop to withstand the jacking forces.
Continuously maintain a square alignment between the backstop and pipe
casing and support the maximum obtainable jacking pressure with a safety
factor at least 2.0. Continuously monitor the jacking pressure and rate
of cutter head advancement. Exercise special care when setting the pipe
guard rails in the jacking pit to ensure correctness of the alignment,
grade and stability.
d. Do not jack pipe casing until the concrete thrust block and tremie
seal (if selected), and grouted soil zone in jacking and receiving
SECTION 33 05 23 Page 23
shafts have attained the required strength.
e. Jack the pipe into place without causing damage to the coatings,
joints or completed pipe section.
h. Ensure that the welds of steel pipe attain the full strength of the
pipe and are watertight before jacking of the pipe section. Ensure
that the inner face of the internal weld seam is flush with the pipe
to facilitate the installation of the carrier pipe in the pipe casing.
k. Once the tunneling process has begun, continue with that process
uninterrupted until the pipe reaches the receiving shaft. Continue to
push any damaged pipe until that damaged pipe section is pushed into
the receiving shaft and is removed. Notify the [Contracting
Officer][Engineer] immediately if any pipe is known to be or believed
to be damaged.
3.3.4.1 Cleaning
Clean the inside of the casing of all foreign matter by using a pipe
cleaning plug.
[Bond all metallic conduit joints within the casing pipe.] Inspect with
the Contracting Officer, prior to backfilling trenches, the transition of
[carrier pipe] [conduit] within the casing to non-cased trenching.
SECTION 33 05 23 Page 24
pipe][conduit] and spacers within the casing pipe, pressure fill the
annular space between the [carrier pipe][conduit] and the casing pipe,
with cement grout specified herein. Regulate pump pressures to
refusal or in accordance with the approved grouting plan. Place grout
in a sequence and manner that will preclude voids or pockets of
entrapped air or water. Use a refusal pressure equal to 8.0 kg/sm per
meter 0.5 psf per foot of overburden.
3.3.5 Ventilation
3.3.6 Lighting
Provide adequate lighting for the nature of the activity being conducted
by workers. Separate and insulate with ground fault interrupters power
and lighting circuits. Comply with requirements with regards to shatter
resistance and illumination requirements.
Match the excavation rate with rate of spoil removal. Utilize a system
capable of balancing groundwater pressures and adjustment to maintain face
stability for the particular soil conditions of the project.
3.4 TOLERANCES
**************************************************************************
NOTE TO DESIGNER - The tolerances for a typical MTBM
project are 125 mm 5 inches on line and 38 mm 1 1/2
inches on grade in a 91.4 m 300 foot installation.
In order to meet local sewerage regulations
regarding slope, it is recommended to design at the
desired slope plus tolerances. Also, consider
adding between 30 - 75 mm 0.1 - 0.25 foot drop
across manholes.
**************************************************************************
SECTION 33 05 23 Page 25
3.4.1 Tolerances
3.5.1 Instrumentation/Survey
**************************************************************************
NOTE: The Engineer should specify minimum
monitoring requirements using the following,
supplemental as required by the project specific
conditions.
**************************************************************************
SECTION 33 05 23 Page 26
driven in the top for level rod placement. Use temporary paint or
other approved materials in pavement areas. Minimize the size of
temporary markings to the greatest extent practical. Remove all
markers and markings prior to completion of work.
Surface - Unpaved +/- 6 [_____] mm +/- 1/4 +/- 19 [_____] mm +/- 3/4
[_____] inch [_____] inch
Surface - Paved +/- 6 [_____] mm +/- 1/4 +/- 13 [_____] mm +/- 1/2 [_____]
[_____] inch inch
**************************************************************************
NOTE: Indicate appropriate Section number and title
in blank below. Specify testing of gravity mains in
accordance with ASTM C1091.
**************************************************************************
SECTION 33 05 23 Page 27
test results, identifying any results that do not meet specified
requirements, to the Contracting Officer within 4 days of test
completion. Provide corrective action and retest pipe not meeting
specified requirements. Provide corrective action as recommended by the
pipe manufacturer and subject to approval by the Contracting Officer.
Inspect and verify that pipe material meets the dimensional tolerances
specified prior to use. Record each days inspection results in the daily
work log.
Cut non-standard joint lengths from full length pipe having satisfactorily
passed the hydrostatic test.
3.5.2.1.3 Elevations
3.5.3 Inspections
Submit an electronic copy and three hard copies of the record drawings to
the Contracting Officer within 5 days after completing the work. Include
in the record drawings a plan, profile, and all information recorded
during the progress of the work. Clearly tie the record drawings to the
project's survey control. Maintain and submit upon completion final Daily
Work Logs of installation operations, signed by the superintendent.
SECTION 33 05 23 Page 28
3.7 DISPOSITION OF MATERIAL
-- End of Section --
SECTION 33 05 23 Page 29