Table 4
Table 4
Table 4
During WTA study observed in Mubadala Tower, 6 no’s of AHU’s don’t have VFD and
CHWP circuit 2 having 2 pumps, one pump is running at full speed which is not working
based on the DPT logic.
All 6 AHUs are operating at full speed without any control logic.
All AHU’s, Fresh air supply duct doesn’t have any damper and actuator and it’s fully
open.
There is no control of fresh air in the space area. Fresh air damper control is not
based on CO2 level.
CHWP circuit 2 serving high rise tower from level 26 to roof which have 2 nos of
pump in that circuit, one pump VFD is operating at full speed (50 Hz) which is not
based on the DPT logic i.e.; pumps speeds are not varying with respect to building
load
Installation of new VFDs to 6 Nos AHUs and integrate with existing Honeywell EBI
BMS.
Control the AHUs fan speed based on return air temperature and damper control
based on the CO2 sensor as per demand.
Limiting of fresh air mixing in recirculation AHUs based on return duct CO2 sensor.
Optimisation of equipment operation through time schedules and VFD limits and
cooling demands through summer and winter seasonal set points.
Installation and calibration of new DPT sensor for CHWP circuit 2
Implement the sequence of operation of pumps to achieve the DPT logic setpoint
and to automate the pump control based on cooling load.
The system will be integrated with Enova Hub grade IoT platform for ensuring better
visibility and performance.
Rationale for using this ESM
As per the Fan’s affinity law, modulating fan speed based on temperature.This will
improve the fan efficiency as per cooling demand.
Modulating fresh air damper based on CO2 sensor to optimise fresh air temperature
and hence it will reduce the cooling load.
Integration of existing chilled water pump VFDs with new BMS to automate the pump
control based DPT logic w.r.t cooling load.
Based on above WTA study of AHU’s It observed that VFDs are not installed and
running at fixed speed.
Based on above WTA study, AHUs loading factor is consider for baseline and saving
calculation.
Any change in loading factors and operation hours, ESM baseline will adjust as per
the M & V Plan.
Integration of 6 no’s of VFDs for AHU’s with sensors,dampers & actuator and
Optimization of CHWP’s based on DPT as per below Scope
S.N Total
Field Devices Description
o Quantity
Supply and Installation of required DDC panel with IO modules for As
1
the integration of below items Required
2 Hardwire integration of VFD’s to the DDC panel 6
3 Supply, Installation of CO2 Sensor 11
Supply Dampers + Actuators - Modulating type - 20 Nm with
4 11
position feedback switch
Supply and Installation of new DPT for the CHWPS by replacing
5 1
the existing DPT
6 Hardwire integration of above sensors to the DDC panel 22
Supply of cables and cables pulling from the newly installed As
7
devices to the DDC panel Required
As
8 Cables, conduits, Trunking for installation
Required
As
9 DDC Controllers and Panels
Required
Modification of SOO and configuration of schedules and other As
10
control parameters Required
11 Graphics modification As required
ADIC
Six numbers of electric hot water calorifiers (90 kW, 4 W +2S) use to serve hot water
for the domestic application in the ADIC. It is working based on temperature set point
given from local control panel.
Fourseasons
Two numbers of CNG based hot water boiler (1500 kW, 1 W +1 S) use to serve hot
water for the domestic application in the Fourseasons Hotel. It is working based on
temperature set point given from local control panel.
Rosewood
Four numbers of electric hot water calorifiers (116kW- 2 Nos, 1 W+1S) & (140 kW-2
Nos, 1 W +1S) use to serve hot water for the domestic application in the Rosewood
Hotel. It is working based on temperature set point given from local control panel.
Based on WTA study analysis at Mubadala tower, ADIC, Fourseasons & Rosewood
hot water calorifiers,
Hot water calorifier actual thermal load is less than 50% load (<50 kW), So accordingly
consider 50 kW capacity water to water heat pump which including one working & one
standby condition.
Swimming pool heater actual thermal is less than 40% load (<45 kW), So accordingly
consider 45 kW capacity Air to water heat pump which including one working & one
standby condition.
For ADIC
Hot water calorifier actual thermal load is less than 40% load (<150 kW), So
accordingly consider 165 kW capacity water to water heat pump which including one
working & one standby condition.
For FOURSEASONS
Hot water boiler actual thermal load is less than 10% load (<150 kW), So accordingly
consider 165 kW capacity water to water heat pump which including one working &
one standby condition.
For ROSEWOOD
Hot water electrical calorifier actual thermal load is less than 40% load (<150 kW), So
accordingly consider 165 kW capacity water to water heat pump which including one
working & one standby condition.
Based on above WTA study analysis, Hot water calorifier loads, loading factor
consider for ESM Heat pumps baseline and saving calculation.
Any change in loading factors and operation hours, ESM baseline will adjust as per
the M & V Plan.
BOQ
10-15 year
TiSun Energy
1.3 Replacement of existing Air-cooled chillers with new Energy Efficient Chillers with
VSD
During the site visit, it was observed following sites having constant speed air cooled screw
chillers & were not operating efficiently.
2 Nos Mcquay make – 150 TR chillers (1 W+1S) are serving chilled water to ADIC
council building for critical loads
2 Nos Mcquay make – 150 TR chillers (1 W+1S) are serving chilled water to ADIC
Bank building for critical loads
New chillers are versed with modern technology and control optimizations compared to
the older versions.
In competitive market, considering energy efficiency (kW/TR), new chillers are easy to
monitor, control and optimize, compared to the older versions. The new compressors also
perform efficiently compared to the old ones due to depreciation and erosion throughout
the years of operation.
Fig: Tube side of old chiller (with scale and sludge formation) compared to a new chiller.
Rationale for using this ECM
By replacing the old air-cooled chillers with new air-cooled chiller the specific energy
consumption of the chillers will be brought down.
VFD in chillers match the load requirement and generation, to consume least power for
same chilling load.
ECM Scope of work
Decommissioning of chillers.
Installation, integration, testing & commissioning of new chillers.
BOQ
Strata
During the site visit, it was observed following two locations (Strata 1.0 & 1.1) having VSD air
cooled screw chillers with dedicated constant primary and variable secondary pumps.
Strata1.0
7 Nos air cooling chillers (4 W+ 3 S, 372 TR each) with dedicated 7 nos constant
primary pumps (4 W+3S) to supply chilled water to chiller plant.
4 nos variable secondary pump (2 W+ 2S) to supply chilled water to facility (Starta1.0)
depends on DPT logic control.
Strata1.1
5 Nos air cooling chillers (1 W+ 4 S, 250 TR each) with respective 4 nos constant
primary pumps (1 W+3S) to supply chilled water to chiller plant.
4 nos variable secondary pump (2 W+ 2S) to supply chilled water to facility (Starta1.1)
depends on DPT logic control.
Interconnection of chiller plants and converting existing constant primary and variable
secondary to variable primary system by using existing secondary pumps.
Modification-1
Interconnection of two separated loop chiller plant (Strata 1.0 & 1.1) to a single loop chiller plant
system, By interconnecting main header pipelines (both supply and return lines), with all
necessary accessories & modifications.
New header line modification, to connect existing primary pump suction header to discharge
header line to bypass the existing primary pumps and using existing secondary pumps has
variable primary pumps
Modification -3
Bypass line to connect between variable primary pump & 250 TR York chiller header to maintain
a minimum flow requirement w.r.t flow meter & actuator control logic.
BOQ
Voltron or equivalent
1.5 Cooling tower water blowdown reduction system (Chemical less water treatment
for cooling tower)
ESM 5 Cooling tower water blowdown reduction system (Chemical less water
treatment for cooling tower)
Building ADIC
Water
Type of ESM
For cooling tower, following two activities has performed by operation team, i.e.,
3) Chemical dosing to maintain the desired water parameters like PH, Conductivity, etc.,
4) Continuous blowdown to maintain the sump water TDS below 1500 PPM.
Cooling towers make up water consumption is manually monitoring and logging by operation team
on daily basis.
ESM Description & Proposed Solution
Chemical less treatment eliminates/ reduces chemical dosing in the cooling tower. As the scales
removed physically into the Electrolytic reactor, it is possible to operate cooling tower at higher
levels of TDS or conductivity, resulting into reduction of cooling tower blow down water
consumption.
Installation
2. Power Supply cabling to the Control Panel - Raw Power, 3 Phase, 415 V, 50 Hz
Eco Max,
1.6 Supply and Installation of New BMS
Building Strata
Total
S.No Field Devices Description- Strata
Quantity
1 Liquid Differential pressure transmitter in chilled water line 2
2 Flow meter Main Return Header 14-inch size with 850 m3/hr (Max) 1
3 Motorised Butterfly Valve actuator (On/Off Type) - 150 mm Pipe size 4
Motorised Butterfly Valve actuator (Modulating) - 250 mm Pipe size for
4 1
Bypass line
Communication card for the chillers and communication cable for
5 12
these chillers need to be considered
6 Supply and Installation of New DDC panel for chiller plant Manager 1
Existing selected AHUs and FAHUs don’t have VFD’s. Following AHUs/FAHUs units operate
at maximum speed.
Mubadala Tower :6 Nos Units
Strata: 4 Nos Units.
Based on WTA study of AHUs/FAHUs, It observed that motor are not integrated with
any control logic and running at fixed speed.
Based on above WTA study, AHUs/FAHUs loading factor is consider for baseline and
saving calculation.
Any change in loading factors and operation hours, ESM baseline will adjust as per
the M & V Plan.
The proposed solution involves installing VFDs to ensure optimal performance. The
typical scope of works includes the following steps:
Assessment and Design: An initial assessment conducted to determine the
appropriate motor, and configuration.
Testing and Commissioning: The entire system is thoroughly tested and
commissioned to ensure proper functionality, performance, and efficiency.
Installing VFD for large fan motors (above 4 KW) to control the fan air flow rate will
enhance building thermal comfort and will save energy through lowering fan motor
speed.
As the air conditioning system designed in constant air volume (CAV) concept, our
methodology for controlling the VFD speed will be based on the return air
temperature values for mixing type AHUs though installing temperature sensors.
FAHUs will control using supply air duct temperature to serving space(s) which will
indicate the amount of cooling requirements and treated fresh air for the serving
areas.
The newly installed VFDs will install in constant speed fresh air handling units. For
the constant speed air handling units VFD will operate based on the Supply air
temperature/ return air temperature and will connect to the BMS to monitor and
remotely control the air flow based on the time schedule / seasonal demand.
Rationale for using this ESM
The typical scope of work is the installation of VFD’s for selected AHU’s and
FAHUs.
Procurement and installation of new VFD.
Integration of advanced control systems for efficient operation.
Through testing, commissioning, and performance verification.
Operator training to ensure proper utilization and maintenance of the new VFD.
BOQ
6 Nos of Variable Speed Drives will be installed for selected AHU motors in Mubadala Tower
Power
S. No Site Name Serving Area Fan Rating
(KW)
Mubadala Air Handling
1 Air Handling Unit 01 GF 5.5
Tower Unit 01 GF
Mubadala Air Handling
2 Air Handling Unit 02 GF 5.5
Tower Unit 02 GF
Mubadala Air Handling
3 Air Handling Unit 03 GF 3
Tower Unit 03 GF
Air Handling
Mubadala Air Handling Unit 08 35th
4 Unit 08 35th 5.5
Tower Floor
Floor
Air Handling
Mubadala Air Handling Unit 09 35th
5 Unit 09 35th 5.5
Tower Floor
Floor
Air Handling
Mubadala Air Handling Unit 10 35th
6 Unit 10 35th 5.5
Tower Floor
Floor
7 Nos Variable Speed Drives will be installed for selected FAHU and AHU motors in Strata.
Power
S. No Site Name Serving Area Fan Rating
(KW)
FAHU paint
1 Strata FAHU paint shop SF 11
shop SF
FAHU paint
2 Strata FAHU paint shop RF 7.5
shop RF
FAHU Core
3 Strata FAHU Core Manufacturing Manufacturing 11
SF
FAHU Core
4 Strata FAHU Core Manufacturing Manufacturing 7.5
RF
FAHU
5 Strata FAHU Reception 7.5
Reception SF
FAHU
6 Strata FAHU Reception 4
Reception RF
7 Strata AHU IT Room AHU IT Room 5.5
ABB/Siemens/Invertek/Control Techniques