Ineos-Ecr-Osb-Ss-Energization Plan 2

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.

LOPEZ Settings

6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today

Updated on: Saved on: 220

ids Item Details 29-May-23 1-Jun-23

s r Team ind. ind. d. d. d. d. Work


id Type Description Role ⚠ item
Start End Start End % M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M
id id Member Start End id conn lag days

1 1 # S SS-05 ACTIVITIES (FIRST FIRE) Auto FS 54 3-Feb-25 17-Apr-25 0%

2 1 # M START SS-05 EQUIPMENT INSTALLATION E.PULGAR 3-Feb-25 FS 1 3-Feb-25 3-Feb-25 ◆

TDG-SS-05 - EQUIPMENT INSTALLATION - TEMPORARY DIESEL


3 1 # T
GENERATOR (CABLE PULLING & CONNECTION)
TDG-SS-05 E.PULGAR 2 ↖ (M) START S…
SS 5 3-Feb-25 7-Feb-25
TPDP-SS-05 - EQUIPMENT INSTALLATION - TEMPORARY POWER
4 1 # T
DISTRIBUTION PANEL (CABLE PULLING & CONNECTION)
TPDP-SS-05 E.PULGAR 2 ↖ (M) START S…
SS 5 3-Feb-25 7-Feb-25

5 1 # T OSB-SS-05-BC-W-01 - EQUIPMENT INSTALLATION - BATTERY CHARGER OSB-SS-05-BC-W-01 E.PULGAR 2 ↖ (M) START S…


SS 10 3-Feb-25 14-Feb-25

6 1 # T OSB-SS-05-BC-W-02 - EQUIPMENT INSTALLATION - BATTERY CHARGER OSB-SS-05-BC-W-02 E.PULGAR 2 ↖ (M) START S…


SS 10 3-Feb-25 14-Feb-25
OSB-SS-05-DB-W-01 - EQUIPMENT INSTALLATION - DC DISTRIBUTION
7 1 # T OSB-SS-05-DB-W-01 E.PULGAR 2 ↖ (M) START S…
SS 10 3-Feb-25 14-Feb-25
BOARD
OSB-SS-05-DB-W-02 - EQUIPMENT INSTALLATION - DC DISTRIBUTION
8 1 # T OSB-SS-05-DB-W-02 E.PULGAR 2 ↖ (M) START S…
SS 10 3-Feb-25 14-Feb-25
BOARD
OSB-SS-05-DSW-W-01 - EQUIPMENT INSTALLATION - BATTERY
9 1 # T
ISOLATOR SWITCH
OSB-SS-05-DSW-W-01 E.PULGAR 2 ↖ (M) START S…
SS 10 3-Feb-25 14-Feb-25
OSB-SS-05-DSW-W-02 - EQUIPMENT INSTALLATION - BATTERY
10 1 # T OSB-SS-05-DSW-W-02 E.PULGAR 2 ↖ (M) START S…
SS 10 3-Feb-25 14-Feb-25
ISOLATOR SWITCH

11 1 # T OSB-SS-05-BAT-W-01 - EQUIPMENT INSTALLATION - BATTERY RACK OSB-SS-05-BAT-W-01 E.PULGAR 2 ↖ (M) START S…


SS 10 3-Feb-25 14-Feb-25

12 1 # T OSB-SS-05-BAT-W-02 - EQUIPMENT INSTALLATION - BATTERY RACK OSB-SS-05-BAT-W-02 E.PULGAR 11 ↖ (T) OSB-SS-…


SS 4 10 7-Feb-25 20-Feb-25
CABLE PULLING & CONNECTION - TO FEED BATTERY CHARGER FROM
13 1 # T E.PULGAR 6 ↖ (T) OSB-SS-…
FS 5 17-Feb-25 21-Feb-25
TEMPORARY PDP
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
14 1 # T
BATT SWITCH
E.PULGAR 12 ↖ (T) OSB-SS-…
SS 5 15 14-Feb-25 6-Mar-25
OSB-SS-05-BC-W-01 - ENERGIZATION - BATTERY CHARGER
15 1 # T OSB-SS-05-BC-W-01 E.PULGAR 14 ↖ (T) CABLE P…
FS 5 7-Mar-25 13-Mar-25
TEMPORARY ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-05-BC-W-02 - ENERGIZATION - BATTERY CHARGER
16 1 # T
TEMPORARY ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-05-BC-W-02 E.PULGAR 14 ↖ (T) CABLE P…
FS 5 7-Mar-25 13-Mar-25
OSB-SS-05-SG-E-01 - EQUIPMENT INSTALLATION - 36 kV HV
17 1 # T OSB-SS-05-SG-E-01 E.PULGAR 2 ↖ (M) START S…
SS 40 3-Feb-25 28-Mar-25
SWITCHGEAR
OSB-SS-05-SG-E-01 - EQUIPMENT TESTING - 36 kV HV SWITCHGEAR
18 1 # T OSB-SS-05-SG-E-01 E.PULGAR 16 ↖ (T) OSB-SS-…
FS 25 14-Mar-25 17-Apr-25
(VENDOR ASSISTANCE)
CABLE PULLING & CONNECTION FINISHED - 36 kV POWER SUPPLY
19 1 # M E.PULGAR 17 ↖ (T) OSB-SS-…
FS 1 31-Mar-25 31-Mar-25 ◆
FROM OSB-GS-01-GS-E-01 - BY OTHER

20 1 # T OSB-SS-05-SG-E-01 - ENERGIZATION - 36 kV HV SWITCHGEAR OSB-SS-05-SG-E-01 E.PULGAR 19 ↖ (M) CABLE P…


SS 10 31-Mar-25 11-Apr-25

21 1 # M READY TO ENERGIZE SS-03 E.PULGAR 20 ↖ (T) OSB-SS-…


FS 1 14-Apr-25 14-Apr-25 ◆

22 1 # M READY TO ENERGIZE SS-04 E.PULGAR 20 ↖ (T) OSB-SS-…


FS 1 14-Apr-25 14-Apr-25 ◆

1 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings

6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today

Updated on: Saved on: 220

ids Item Details 29-May-23 1-Jun-23

s r Team ind. ind. d. d. d. d. Work


id Type Description Role ⚠ item
Start End Start End % M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M
id id Member Start End id conn lag days

23 2 # S SS-04 ACTIVITIES (FIRST FIRE) Auto FS 275 30-Jan-24 17-Feb-25 0%

24 2 # M START SS-04 EQUIPMENT INSTALLATION E.PULGAR 3-Feb-25 FS 1 3-Feb-25 3-Feb-25 ◆

25 2 # M UPS EQUIPMENT AVAILABLE AT SITE (PO 1216) PO 1216 E.PULGAR 30-Jan-24 FS 5 30-Jan-24 5-Feb-24

26 2 # M POWER TRANSFORMER AVAILABLE AT SITE (PO 1201) PO 1201 E.PULGAR 24-Jun-24 1 24-Jun-24 24-Jun-24

27 2 # M HV SWITCHGEAR 6.3 kV AVAILABLE AT SITE (PO 1210) PO 1210 E.PULGAR 3-Aug-24 2 3-Aug-24 5-Aug-24

28 2 # M 6 kV BUS DUCT AVAILABLE AT SITE (PO 1206) PO 1206 E.PULGAR 3-Aug-24 2 3-Aug-24 5-Aug-24
TDG-SS-04 - EQUIPMENT INSTALLATION - TEMPORARY DIESEL
29 2 # T
GENERATOR (CABLE PULLING & CONNECTION)
TDG-SS-04 E.PULGAR 24 ↖ (M) START S…
SS 3 3-Feb-25 5-Feb-25
TPDP-SS-04 - EQUIPMENT INSTALLATION - TEMPORARY POWER
30 2 # T
DISTRIBUTION PANEL (CABLE PULLING & CONNECTION)
TPDP-SS-04 E.PULGAR 24 ↖ (M) START S…
SS 3 3-Feb-25 5-Feb-25
ECR-SS-04-UPS-W-01 - EQUIPMENT INSTALLATION - BATTERY
31 2 # T ECR-SS-04-UPS-W-01 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
CHARGER
ECR-SS-04-UPS-W-02 - EQUIPMENT INSTALLATION - BATTERY
32 2 # T ECR-SS-04-UPS-W-02 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
CHARGER
ECR-SS-04-DB-W-01 - EQUIPMENT INSTALLATION - DC DISTRIBUTION
33 2 # T ECR-SS-04-DB-W-01 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
BOARD
ECR-SS-04-DB-W-02 - EQUIPMENT INSTALLATION - DC DISTRIBUTION
34 2 # T ECR-SS-04-DB-W-02 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
BOARD
ECR-SS-04-DSW-W-01 - EQUIPMENT INSTALLATION - BATTERY
35 2 # T
ISOLATOR SWITCH
ECR-SS-04-DSW-W-01 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
ECR-SS-04-DSW-W-02 - EQUIPMENT INSTALLATION - BATTERY
36 2 # T ECR-SS-04-DSW-W-02 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
ISOLATOR SWITCH

37 2 # T ECR-SS-04-BAT-W-01 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-W-01 E.PULGAR 24 ↖ (M) START S…


FS 10 4-Feb-25 17-Feb-25

38 2 # T ECR-SS-04-BAT-W-02 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-W-02 E.PULGAR 24 ↖ (M) START S…


FS 10 4-Feb-25 17-Feb-25
ECR-SS-04-TR-E-01 - EQUIPMENT INSTALLATION - 36/6.3 kV
39 2 # T
TRANSFORMER - 25MVA
ECR-SS-04-TR-E-01 E.PULGAR 24 ↖ (M) START S…
SS 5 3-Feb-25 7-Feb-25
ECR-SS-04-NER-N-01 - EQUIPMENT INSTALLATION - NEUTRAL
40 2 # T
EARTHING RESISTOR
ECR-SS-04-NER-N-01 E.PULGAR 24 ↖ (M) START S…
SS 5 3-Feb-25 7-Feb-25
ECR-SS-04-TR-E-02 - EQUIPMENT INSTALLATION - 36/6.3 kV
41 2 # T ECR-SS-04-TR-E-02 E.PULGAR 24 ↖ (M) START S…
SS 5 5 10-Feb-25 14-Feb-25
TRANSFORMER - 25MVA
ECR-SS-04-NER-N-02 - EQUIPMENT INSTALLATION - NEUTRAL
42 2 # T
EARTHING RESISTOR
ECR-SS-04-NER-N-02 E.PULGAR 24 ↖ (M) START S…
SS 5 5 10-Feb-25 14-Feb-25
ECR-SS-04-SG-N-01 - EQUIPMENT INSTALLATION - 6 kV - MV
43 2 # T
SWITCHGEAR
ECR-SS-04-SG-N-01 E.PULGAR 24 ↖ (M) START S…
SS 25 3-Feb-25 7-Mar-25
CABLE PULLING & CONNECTION - TO FEED BOTH BATTERY CHARGER
44 2 # T
FROM TEMPORARY PDP
E.PULGAR 33 ↖ (T) ECR-SS-…
FS 5 11-Feb-25 17-Feb-25
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
45 2 # T
BATT SWITCH
E.PULGAR 37 ↖ (T) ECR-SS-…
FS 15 18-Feb-25 10-Mar-25
ECR-SS-04-TR-E-01 / 02 - POWER & CONTROL CABLE PULLING & CONN -
46 2 # T
TRANF-NER-SWG-BATTERY CHARGER
ECR-SS-04-TR-E-01 / 02 E.PULGAR 47 ↙ (T) ECR-SS-…
FS 30 25-Mar-25 5-May-25

2 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings

6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today

Updated on: Saved on: 220

ids Item Details 29-May-23 1-Jun-23

s r Team ind. ind. d. d. d. d. Work


id Type Description Role ⚠ item
Start End Start End % M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M
id id Member Start End id conn lag days
ECR-SS-04-UPS-W-01 / 02 EQUIPMENT TESTING - BATTERY CHARGER
47 2 # T
TESTING (VENDOR ASSISTANCE)
ECR-SS-04-UPS-W-01 / 02 E.PULGAR 45 ↖ (T) CABLE P…
FS 10 11-Mar-25 24-Mar-25
ECR-SS-04-SG-N-01 - EQUIPMENT TESTING - 6 kV - MV SWITCHGEAR
48 2 # T ECR-SS-04-SG-N-01 E.PULGAR 46 ↖ (T) ECR-SS-…
FS 40 6-May-25 30-Jun-25
(VENDOR ASSISTANCE)
ECR-SS-04-TR-E-01 / 02 - EQUIPMENT TESTING - POWER
49 2 # T ECR-SS-04-TR-E-01 / 02 E.PULGAR 46 ↖ (T) ECR-SS-…
FS 8 6-May-25 15-May-25
TRANSFORMER (VENDOR ASSISTANCE)
ECR-SS-04-UPS-W-01 - ENERGIZATION - BATTERY CHARGER
50 2 # T ECR-SS-04-UPS-W-01 E.PULGAR 47 ↖ (T) ECR-SS-…
FS 5 25-Mar-25 31-Mar-25
TEMPORARY ENERGIZATION (VENDOR ASSISTANCE)
ECR-SS-04-UPS-W-02 - ENERGIZATION - BATTERY CHARGER
51 2 # T
TEMPORARY ENERGIZATION (VENDOR ASSISTANCE)
ECR-SS-04-UPS-W-02 E.PULGAR 47 ↖ (T) ECR-SS-…
FS 5 25-Mar-25 31-Mar-25

52 2 # M PAR-152 STEEL STRUCTURE ERECTION FINISHED PAR-152 (AREA 4) E.PULGAR 5-Jan-25 4 5-Jan-25 8-Jan-25 ◆

53 2 # M PAR-003 TRANSPORT TO FINAL LOCATION FINISHED PAR-003 (ECR) E.PULGAR 26-Sep-24 4 26-Sep-24 1-Oct-24

54 2 # M PAR-002 TRANSPORT TO FINAL LOCATION FINISHED PAR-002 (ECR) E.PULGAR 29-Oct-24 4 29-Oct-24 1-Nov-24

55 2 # M PR-09 STEEL STRUCTURE ERECTION FINISHED PR-00-09 (ECR) E.PULGAR 18-Oct-24 4 18-Oct-24 23-Oct-24
NORTH ROUTINTG CABLETRAY BY
56 2 # M NORTH ROUTING CABLETRAY AVAILABLE - BY OTHER E.PULGAR 60 ↙ (T) PAR-152…
FS 3 27-Feb-25 3-Mar-25 ◆
OTHER

57 2 # T PAR-003 CABLETRAY INSTALLATION (HOOK UP) PAR-003 (ECR) E.PULGAR 53 ↖ (M) PAR-003…
FS 45 25 4-Dec-24 7-Jan-25

58 2 # T PR-00-09 CABLETRAY INSTALLATION PR-00-09 (ECR) E.PULGAR 55 ↖ (M) PR-09 S…


FS 45 25 26-Dec-24 29-Jan-25

59 2 # T PAR-002 CABLETRAY INSTALLATION (HOOK UP) PAR-002 (ECR) E.PULGAR 54 ↖ (M) PAR-002…
FS 45 25 6-Jan-25 7-Feb-25

60 2 # T PAR-152 CABLETRAY INSTALLATION PAR-152 (AREA 4) E.PULGAR 52 ↖ (M) PAR-152…


FS 10 25 23-Jan-25 26-Feb-25
ECR-SS-04-TR-E-01 / 02 - POWER & CONTROL CABLE PULLING & CONN -
61 2 # T
NORTH ROUTING
ECR-SS-04-TR-E-01 / 02 E.PULGAR 56 ↖ (M) NORTHFS
R… 15 4-Mar-25 24-Mar-25
ECR-SS-04-TR-E-01 / 02 - ENERGIZATION - POWER TRANSFORMER
62 2 # T ECR-SS-04-TR-E-01 / 02 E.PULGAR 215 ↙ (M) CABLE P…
FS 5 3-Jul-25 9-Jul-25
(VENDOR ASSISTANCE)

3 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings

6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today

Updated on: Saved on: 220

ids Item Details 29-May-23 1-Jun-23

s r Team ind. ind. d. d. d. d. Work


id Type Description Role ⚠ item
Start End Start End % M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M
id id Member Start End id conn lag days

63 3 # S SS-04 ACTIVITIES (MILESTONE READY TO ENERGIZE) Auto FS 329 22-Apr-24 24-Jul-25 0%

64 3 # M LV SWITCHGEAR AVAILABLE AT SITE (PO 1212) PO 1212 E.PULGAR 25 ↖ (M) UPS EQU…
SS 5 30-Jan-24 5-Feb-24
ECR-SS-04-TR-E-03 - EQUIPMENT INSTALLATION - 36/6.3 kV
65 3 # T ECR-SS-04-TR-E-03 E.PULGAR 24 ↖ (M) START S…
SS 5 3-Feb-25 7-Feb-25
TRANSFORMER - 25MVA
ECR-SS-04-NER-N-03 - EQUIPMENT INSTALLATION - NEUTRAL
66 3 # T ECR-SS-04-NER-N-03 E.PULGAR 24 ↖ (M) START S…
SS 5 3-Feb-25 7-Feb-25
EARTHING RESISTOR
ECR-SS-04-TR-E-04 - EQUIPMENT INSTALLATION - 36/6.3 kV
67 3 # T
TRANSFORMER - 25MVA
ECR-SS-04-TR-E-04 E.PULGAR 24 ↖ (M) START S…
SS 5 5 10-Feb-25 14-Feb-25
ECR-SS-04-NER-N-04 - EQUIPMENT INSTALLATION - NEUTRAL
68 3 # T
EARTHING RESISTOR
ECR-SS-04-NER-N-04 E.PULGAR 24 ↖ (M) START S…
SS 5 5 10-Feb-25 14-Feb-25
ECR-SS-04-SG-N-02 - EQUIPMENT INSTALLATION - 6 kV - MV
69 3 # T ECR-SS-04-SG-N-02 E.PULGAR 43 ↖ (T) ECR-SS-…
SS 15 25 24-Feb-25 28-Mar-25
SWITCHGEAR
ECR-SS-04-BD-N-01 - EQUIPMENT INSTALLATION - 6 kV - BUS DUCT
70 3 # T
(TESTING INCLUDED)
ECR-SS-04-BD-N-01 E.PULGAR 43 ↖ (T) ECR-SS-…
FS 15 10-Mar-25 28-Mar-25
ECR-SS-04-BD-N-02 - EQUIPMENT INSTALLATION - 6 kV - BUS DUCT
71 3 # T ECR-SS-04-BD-N-02 E.PULGAR 43 ↖ (T) ECR-SS-…
FS 7 15 19-Mar-25 8-Apr-25
(TESTING INCLUDED)
ECR-SS-04-BD-N-03 - EQUIPMENT INSTALLATION - 6 kV - BUS DUCT
72 3 # T ECR-SS-04-BD-N-03 E.PULGAR 71 ↖ (T) ECR-SS-…
SS 7 15 28-Mar-25 17-Apr-25
(TESTING INCLUDED)
ECR-SS-04-BD-N-04 - EQUIPMENT INSTALLATION - 6 kV - BUS DUCT
73 3 # T ECR-SS-04-BD-N-04 E.PULGAR 72 ↖ (T) ECR-SS-…
SS 7 15 8-Apr-25 28-Apr-25
(TESTING INCLUDED)
ECR-SS-04-TR-N-05 - EQUIPMENT INSTALLATION - 6/0.72 kV
74 3 # T ECR-SS-04-TR-N-05 E.PULGAR 67 ↖ (T) ECR-SS-…
FS 5 17-Feb-25 21-Feb-25
TRANSFORMER - 4MVA
ECR-SS-04-TR-N-06 - EQUIPMENT INSTALLATION - 6/0.72 kV
75 3 # T
TRANSFORMER - 4MVA
ECR-SS-04-TR-N-06 E.PULGAR 74 ↖ (T) ECR-SS-…
SS 5 5 24-Feb-25 28-Feb-25
ECR-SS-04-TR-N-07 - EQUIPMENT INSTALLATION - 6/0.72 kV
76 3 # T ECR-SS-04-TR-N-07 E.PULGAR 75 ↖ (T) ECR-SS-…
FS 5 3-Mar-25 7-Mar-25
TRANSFORMER - 5MVA
ECR-SS-04-TR-N-08 - EQUIPMENT INSTALLATION - 6/0.72 kV
77 3 # T ECR-SS-04-TR-N-08 E.PULGAR 76 ↖ (T) ECR-SS-…
SS 5 5 10-Mar-25 14-Mar-25
TRANSFORMER - 5MVA
ECR-SS-04-TR-N-03 - EQUIPMENT INSTALLATION - 6/0.72 kV
78 3 # T ECR-SS-04-TR-N-03 E.PULGAR 77 ↖ (T) ECR-SS-…
FS 5 17-Mar-25 21-Mar-25
TRANSFORMER - 4MVA
ECR-SS-04-TR-N-04 - EQUIPMENT INSTALLATION - 6/0.72 kV
79 3 # T
TRANSFORMER - 4MVA
ECR-SS-04-TR-N-04 E.PULGAR 78 ↖ (T) ECR-SS-…
SS 5 5 24-Mar-25 28-Mar-25

80 3 # T ECR-SS-04-MCC-R-02 - EQUIPMENT INSTALLATION - 0.69 kV - MCC ECR-SS-04-MCC-R-02 E.PULGAR 24 ↖ (M) START S…


SS 15 3-Feb-25 21-Feb-25

81 3 # T ECR-SS-04-MCC-R-03 - EQUIPMENT INSTALLATION - 0.69 kV - MCC ECR-SS-04-MCC-R-03 E.PULGAR 24 ↖ (M) START S…


SS 7 20 12-Feb-25 11-Mar-25

82 3 # T ECR-SS-04-MCC-R-01 - EQUIPMENT INSTALLATION - 0.69 kV - MCC ECR-SS-04-MCC-R-01 E.PULGAR 24 ↖ (M) START S…


SS 20 15 3-Mar-25 21-Mar-25
ECR-SS-04-BD-R-03 - EQUIPMENT INSTALLATION - LV - BUS DUCT
83 3 # T
(TESTING INCLUDED)
ECR-SS-04-BD-R-03 E.PULGAR 75 ↖ (T) ECR-SS-…
FS 10 3-Mar-25 14-Mar-25
ECR-SS-04-BD-R-04 - EQUIPMENT INSTALLATION - LV - BUS DUCT
84 3 # T
(TESTING INCLUDED)
ECR-SS-04-BD-R-04 E.PULGAR 83 ↖ (T) ECR-SS-…
FS 10 17-Mar-25 28-Mar-25
ECR-SS-04-BD-R-05 - EQUIPMENT INSTALLATION - LV - BUS DUCT
85 3 # T
(TESTING INCLUDED)
ECR-SS-04-BD-R-05 E.PULGAR 82 ↖ (T) ECR-SS-…
FS 10 24-Mar-25 4-Apr-25
ECR-SS-04-BD-R-06 - EQUIPMENT INSTALLATION - LV - BUS DUCT
86 3 # T
(TESTING INCLUDED)
ECR-SS-04-BD-R-06 E.PULGAR 85 ↖ (T) ECR-SS-…
FS 10 7-Apr-25 18-Apr-25
ECR-SS-04-BD-R-01 - EQUIPMENT INSTALLATION - LV - BUS DUCT
87 3 # T
(TESTING INCLUDED)
ECR-SS-04-BD-R-01 E.PULGAR 144 ↙ (T) POWER FS
&… 10 7-Apr-25 18-Apr-25

4 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings

6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today

Updated on: Saved on: 220

ids Item Details 29-May-23 1-Jun-23

s r Team ind. ind. d. d. d. d. Work


id Type Description Role ⚠ item
Start End Start End % M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M
id id Member Start End id conn lag days
ECR-SS-04-BD-R-02 - EQUIPMENT INSTALLATION - LV - BUS DUCT
88 3 # T
(TESTING INCLUDED)
ECR-SS-04-BD-R-02 E.PULGAR 87 ↖ (T) ECR-SS-…
FS 10 21-Apr-25 2-May-25
ECR-SS-04-TR-N-09 - EQUIPMENT INSTALLATION - 6/0.72 kV
89 3 # T ECR-SS-04-TR-N-09 E.PULGAR 79 ↖ (T) ECR-SS-…
FS 5 31-Mar-25 4-Apr-25
TRANSFORMER - 5MVA
ECR-SS-04-TR-N-10 - EQUIPMENT INSTALLATION - 6/0.72 kV
90 3 # T ECR-SS-04-TR-N-10 E.PULGAR 89 ↖ (T) ECR-SS-…
SS 3 5 3-Apr-25 9-Apr-25
TRANSFORMER - 5MVA
ECR-SS-04-BD-R-07 - EQUIPMENT INSTALLATION - LV - BUS DUCT
91 3 # T ECR-SS-04-BD-R-07 E.PULGAR 101 ↙ (T) ECR-SS-…
FS 10 14-Apr-25 25-Apr-25
(TESTING INCLUDED)
ECR-SS-04-BD-R-08 - EQUIPMENT INSTALLATION - LV - BUS DUCT
92 3 # T
(TESTING INCLUDED)
ECR-SS-04-BD-R-08 E.PULGAR 91 ↖ (T) ECR-SS-…
FS 10 28-Apr-25 9-May-25
ECR-SS-04-TR-N-01 - EQUIPMENT INSTALLATION - 6/0.72 kV
93 3 # T
TRANSFORMER - 2MVA
ECR-SS-04-TR-N-01 E.PULGAR 90 ↖ (T) ECR-SS-…
FS 5 10-Apr-25 16-Apr-25
ECR-SS-04-TR-N-02 - EQUIPMENT INSTALLATION - 6/0.72 kV
94 3 # T ECR-SS-04-TR-N-02 E.PULGAR 93 ↖ (T) ECR-SS-…
SS 3 5 15-Apr-25 21-Apr-25
TRANSFORMER - 2MVA
ECR-SS-04-BD-S-01 - EQUIPMENT INSTALLATION - LV - BUS DUCT
95 3 # T
(TESTING INCLUDED)
ECR-SS-04-BD-S-01 E.PULGAR 102 ↙ (T) ECR-SS-…
FS 10 24-Apr-25 7-May-25
ECR-SS-04-BD-S-02 - EQUIPMENT INSTALLATION - LV - BUS DUCT
96 3 # T ECR-SS-04-BD-S-02 E.PULGAR 95 ↖ (T) ECR-SS-…
FS 10 8-May-25 21-May-25
(TESTING INCLUDED)
ECR-SS-04-TR-N-11 - EQUIPMENT INSTALLATION - 6/0.72 kV
97 3 # T ECR-SS-04-TR-N-11 E.PULGAR 94 ↖ (T) ECR-SS-…
FS 5 22-Apr-25 28-Apr-25
TRANSFORMER - 2MVA
ECR-SS-04-TR-N-12 - EQUIPMENT INSTALLATION - 6/0.72 kV
98 3 # T ECR-SS-04-TR-N-12 E.PULGAR 97 ↖ (T) ECR-SS-…
SS 3 5 25-Apr-25 1-May-25
TRANSFORMER - 2MVA
ECR-SS-04-BD-S-03 - EQUIPMENT INSTALLATION - LV - BUS DUCT
99 3 # T ECR-SS-04-BD-S-03 E.PULGAR 103 ↙ (T) ECR-SS-…
FS 10 6-May-25 19-May-25
(TESTING INCLUDED)
ECR-SS-04-BD-S-04 - EQUIPMENT INSTALLATION - LV - BUS DUCT
100 3 # T
(TESTING INCLUDED)
ECR-SS-04-BD-S-04 E.PULGAR 99 ↖ (T) ECR-SS-…
FS 10 20-May-25 2-Jun-25

101 3 # T ECR-SS-04-MCC-R-04 - EQUIPMENT INSTALLATION - 0.69 kV - MCC ECR-SS-04-MCC-R-04 E.PULGAR 82 ↖ (T) ECR-SS-…
FS 15 24-Mar-25 11-Apr-25

102 3 # T ECR-SS-04-SG-S-01 - EQUIPMENT INSTALLATION - 0.69 kV - MCC ECR-SS-04-SG-S-01 E.PULGAR 101 ↖ (T) ECR-SS-…
SS 8 15 3-Apr-25 23-Apr-25

103 3 # T ECR-SS-04-SG-S-04 - EQUIPMENT INSTALLATION - 0.69 kV - MCC ECR-SS-04-SG-S-04 E.PULGAR 102 ↖ (T) ECR-SS-…
SS 8 15 15-Apr-25 5-May-25
ECR-SS-04-EDG-R-01 - EQUIPMENT INSTALLATION - 0.69 kV
104 3 # T
EMERGENCY DIESEL GENERATOR
ECR-SS-04-EDG-R-01 E.PULGAR 24 ↖ (M) START S…
SS 10 3-Feb-25 14-Feb-25
ECR-SS-04-EDG-R-02 - EQUIPMENT INSTALLATION - 0.69 kV
105 3 # T
EMERGENCY DIESEL GENERATOR
ECR-SS-04-EDG-R-02 E.PULGAR 24 ↖ (M) START S…
SS 5 10 10-Feb-25 21-Feb-25
ECR-SS-04-SG-R-01 - EQUIPMENT INSTALLATION - 0.69 kV -
106 3 # T ECR-SS-04-SG-R-01 E.PULGAR 82 ↖ (T) ECR-SS-…
SS 15 3-Mar-25 21-Mar-25
EMERGENCY SWG
ECR-SS-04-SG-R-02 - EQUIPMENT INSTALLATION - 0.69 kV -
107 3 # T
EMERGENCY SWG
ECR-SS-04-SG-R-02 E.PULGAR 82 ↖ (T) ECR-SS-…
SS 10 15 17-Mar-25 4-Apr-25

108 3 # T OSB-SS-04-UPS-U-01 - EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-01 E.PULGAR 32 ↖ (T) ECR-SS-…


FS 5 11-Feb-25 17-Feb-25

109 3 # T OSB-SS-04-UPS-U-03- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-03 E.PULGAR 32 ↖ (T) ECR-SS-… 3 5 14-Feb-25 20-Feb-25

110 3 # T OSB-SS-04-UPS-U-05- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-05 E.PULGAR 109 ↖ (T) OSB-SS-…
FS 5 21-Feb-25 27-Feb-25

111 3 # T OSB-SS-04-UPS-U-07- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-07 E.PULGAR 109 ↖ (T) OSB-SS-…
FS 3 5 26-Feb-25 4-Mar-25
OSB-SS-04-DB-U-01 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
112 3 # T
BOARD
OSB-SS-04-DB-U-01 E.PULGAR 34 ↖ (T) ECR-SS-…
FS 5 11-Feb-25 17-Feb-25
OSB-SS-04-DB-U-03 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
113 3 # T
BOARD
OSB-SS-04-DB-U-03 E.PULGAR 34 ↖ (T) ECR-SS-…
FS 3 5 14-Feb-25 20-Feb-25
OSB-SS-05-DB-U-05 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
114 3 # T
BOARD
OSB-SS-04-DB-U-05 E.PULGAR 113 ↖ (T) OSB-SS-…
FS 5 21-Feb-25 27-Feb-25
OSB-SS-07-DB-U-07 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
115 3 # T
BOARD
OSB-SS-04-DB-U-07 E.PULGAR 114 ↖ (T) OSB-SS-…
SS 3 5 26-Feb-25 4-Mar-25
OSB-SS-04-DSW-U-01 - EQUIPMENT INSTALLATION - BATTERY
116 3 # T OSB-SS-04-DSW-U-01 E.PULGAR 36 ↖ (T) ECR-SS-…
FS 5 11-Feb-25 17-Feb-25
ISOLATOR SWITCH

5 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings

6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today

Updated on: Saved on: 220

ids Item Details 29-May-23 1-Jun-23

s r Team ind. ind. d. d. d. d. Work


id Type Description Role ⚠ item
Start End Start End % M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M
id id Member Start End id conn lag days
OSB-SS-04-DSW-U-03- EQUIPMENT INSTALLATION - BATTERY
117 3 # T
ISOLATOR SWITCH
OSB-SS-04-DSW-U-03 E.PULGAR 116 ↖ (T) OSB-SS-…
SS 5 11-Feb-25 17-Feb-25
OSB-SS-04-DSW-U-05- EQUIPMENT INSTALLATION - BATTERY
118 3 # T OSB-SS-04-DSW-U-05 E.PULGAR 117 ↖ (T) OSB-SS-…
SS 5 11-Feb-25 17-Feb-25
ISOLATOR SWITCH
OSB-SS-04-DSW-U-07 - EQUIPMENT INSTALLATION - BATTERY
119 3 # T OSB-SS-04-DSW-U-07 E.PULGAR 118 ↖ (T) OSB-SS-…
SS 5 11-Feb-25 17-Feb-25
ISOLATOR SWITCH

120 3 # T ECR-SS-04-BAT-U-01 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-01 E.PULGAR 38 ↖ (T) ECR-SS-…
FS 10 18-Feb-25 3-Mar-25

121 3 # T ECR-SS-04-BAT-U-03 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-03 E.PULGAR 120 ↖ (T) ECR-SS-…
SS 7 10 27-Feb-25 12-Mar-25

122 3 # T ECR-SS-04-BAT-U-05 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-05 E.PULGAR 121 ↖ (T) ECR-SS-…
SS 7 10 10-Mar-25 21-Mar-25

123 3 # T ECR-SS-04-BAT-U-07 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-07 E.PULGAR 122 ↖ (T) ECR-SS-…
SS 7 10 19-Mar-25 1-Apr-25

124 3 # T OSB-SS-04-UPS-U-02 - EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-02 E.PULGAR 108 ↖ (T) OSB-SS-…
FS 5 18-Feb-25 24-Feb-25

125 3 # T OSB-SS-04-UPS-U-04- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-04 E.PULGAR 109 ↖ (T) OSB-SS-… 3 5 26-Feb-25 4-Mar-25

126 3 # T OSB-SS-04-UPS-U-06- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-06 E.PULGAR 110 ↖ (T) OSB-SS-…
FS 5 28-Feb-25 6-Mar-25

127 3 # T OSB-SS-04-UPS-U-08- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-08 E.PULGAR 111 ↖ (T) OSB-SS-…
SS 3 5 3-Mar-25 7-Mar-25

128 3 # T OSB-SS-04-UPS-U-09- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-09 E.PULGAR 127 ↖ (T) OSB-SS-…
FS 5 10-Mar-25 14-Mar-25

129 3 # T OSB-SS-04-UPS-U-10- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-10 E.PULGAR 128 ↖ (T) OSB-SS-…
SS 3 5 13-Mar-25 19-Mar-25
OSB-SS-04-DB-U-02 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
130 3 # T OSB-SS-04-DB-U-09 E.PULGAR 112 ↖ (T) OSB-SS-…
FS 5 18-Feb-25 24-Feb-25
BOARD
OSB-SS-04-DB-U-04 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
131 3 # T OSB-SS-04-DB-U-10 E.PULGAR 113 ↖ (T) OSB-SS-…
FS 3 5 26-Feb-25 4-Mar-25
BOARD
OSB-SS-04-DSW-U-02 - EQUIPMENT INSTALLATION - BATTERY
132 3 # T OSB-SS-04-DSW-U-02 E.PULGAR 116 ↖ (T) OSB-SS-…
FS 5 18-Feb-25 24-Feb-25
ISOLATOR SWITCH
OSB-SS-04-DSW-U-04- EQUIPMENT INSTALLATION - BATTERY
133 3 # T
ISOLATOR SWITCH
OSB-SS-04-DSW-U-04 E.PULGAR 117 ↖ (T) OSB-SS-…
SS 5 11-Feb-25 17-Feb-25
OSB-SS-04-DSW-U-06- EQUIPMENT INSTALLATION - BATTERY
134 3 # T
ISOLATOR SWITCH
OSB-SS-04-DSW-U-06 E.PULGAR 118 ↖ (T) OSB-SS-…
SS 5 11-Feb-25 17-Feb-25
OSB-SS-04-DSW-U-08 - EQUIPMENT INSTALLATION - BATTERY
135 3 # T OSB-SS-04-DSW-U-08 E.PULGAR 119 ↖ (T) OSB-SS-…
SS 5 11-Feb-25 17-Feb-25
ISOLATOR SWITCH

136 3 # T ECR-SS-04-BAT-U-02 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-02 E.PULGAR 120 ↖ (T) ECR-SS-…
FS 10 4-Mar-25 17-Mar-25

137 3 # T ECR-SS-04-BAT-U-04 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-04 E.PULGAR 121 ↖ (T) ECR-SS-…
SS 7 10 10-Mar-25 21-Mar-25

138 3 # T ECR-SS-04-BAT-U-06 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-06 E.PULGAR 122 ↖ (T) ECR-SS-…
SS 7 10 19-Mar-25 1-Apr-25

139 3 # T ECR-SS-04-BAT-U-08 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-08 E.PULGAR 123 ↖ (T) ECR-SS-…
SS 7 10 28-Mar-25 10-Apr-25

140 3 # T ECR-SS-04-BAT-U-09 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-09 E.PULGAR 139 ↖ (T) ECR-SS-…
SS 7 10 8-Apr-25 21-Apr-25

141 3 # T ECR-SS-04-BAT-U-10 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-10 E.PULGAR 140 ↖ (T) ECR-SS-…
SS 7 10 17-Apr-25 30-Apr-25

6 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings

6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today

Updated on: Saved on: 220

ids Item Details 29-May-23 1-Jun-23

s r Team ind. ind. d. d. d. d. Work


id Type Description Role ⚠ item
Start End Start End % M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M
id id Member Start End id conn lag days
ECR-SS-04-TR-E-01 / 02 - POWER & CONTROL CABLE PULLING & CONN -
142 3 # T
TRANF-NER-SWG-BATTERY CHARGER
ECR-SS-04-TR-E-03 / 04 E.PULGAR 51 ↖ (T) ECR-SS-…
FS 30 1-Apr-25 12-May-25
POWER & CONTROL CABLE PULLING & CONN - TRANF-SWG-BATTERY
143 3 # T ECR-SS-04-MCC-R-02 E.PULGAR 75 ↖ (T) ECR-SS-…
FS 15 3-Mar-25 21-Mar-25
CHARGER
POWER & CONTROL CABLE PULLING & CONN - TRANF-SWG-BATTERY
144 3 # T ECR-SS-04-MCC-R-03 E.PULGAR 77 ↖ (T) ECR-SS-…
FS 15 17-Mar-25 4-Apr-25
CHARGER
POWER & CONTROL CABLE PULLING & CONN - TRANF-SWG-BATTERY
145 3 # T ECR-SS-04-MCC-R-01 E.PULGAR 79 ↖ (T) ECR-SS-…
FS 15 31-Mar-25 18-Apr-25
CHARGER
POWER & CONTROL CABLE PULLING & CONN - TRANF-SWG-BATTERY
146 3 # T
CHARGER
ECR-SS-04-TR-N-09 / 10 E.PULGAR 101 ↖ (T) ECR-SS-…
FS 25 14-Apr-25 16-May-25
POWER & CONTROL CABLE PULLING & CONN - TRANF-SWG-BATTERY
147 3 # T
CHARGER
ECR-SS-04-TR-N-01 / 02 E.PULGAR 102 ↖ (T) ECR-SS-…
FS 25 24-Apr-25 28-May-25
POWER & CONTROL CABLE PULLING & CONN - TRANF-SWG-BATTERY
148 3 # T ECR-SS-04-TR-N-11 / 12 E.PULGAR 103 ↖ (T) ECR-SS-…
FS 25 6-May-25 9-Jun-25
CHARGER
POWER & CONTROL CABLE PULLING & CONN - SWG-GENERATOR-
149 3 # T
BATTERY CHARGER
ECR-SS-04-SG-R-01 E.PULGAR 106 ↖ (T) ECR-SS-…
FS 15 24-Mar-25 11-Apr-25
POWER & CONTROL CABLE PULLING & CONN - SWG-GENERATOR-
150 3 # T ECR-SS-04-SG-R-02 E.PULGAR 149 ↖ (T) POWER SS
&… 7 15 2-Apr-25 22-Apr-25
BATTERY CHARGER
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
151 3 # T OSB-SS-04-UPS-U-01 E.PULGAR 123 ↖ (T) ECR-SS-…
FS 10 2-Apr-25 15-Apr-25
BATT SWITCH
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
152 3 # T OSB-SS-04-UPS-U-03 E.PULGAR 151 ↖ (T) CABLE P…
SS 3 10 7-Apr-25 18-Apr-25
BATT SWITCH
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
153 3 # T OSB-SS-04-UPS-U-05 E.PULGAR 152 ↖ (T) CABLE P…
SS 3 10 10-Apr-25 23-Apr-25
BATT SWITCH
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
154 3 # T
BATT SWITCH
OSB-SS-04-UPS-U-07 E.PULGAR 153 ↖ (T) CABLE P…
SS 3 10 15-Apr-25 28-Apr-25
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
155 3 # T OSB-SS-04-UPS-U-02 E.PULGAR 139 ↖ (T) ECR-SS-…
FS 10 11-Apr-25 24-Apr-25
BATT SWITCH
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
156 3 # T OSB-SS-04-UPS-U-04 E.PULGAR 155 ↖ (T) CABLE P…
SS 3 10 16-Apr-25 29-Apr-25
BATT SWITCH
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
157 3 # T OSB-SS-04-UPS-U-06 E.PULGAR 156 ↖ (T) CABLE P…
SS 3 10 21-Apr-25 2-May-25
BATT SWITCH
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
158 3 # T
BATT SWITCH
OSB-SS-04-UPS-U-08 E.PULGAR 157 ↖ (T) CABLE P…
SS 3 10 24-Apr-25 7-May-25
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
159 3 # T
BATT SWITCH
OSB-SS-04-UPS-U-09 E.PULGAR 158 ↖ (T) CABLE P…
SS 3 10 29-Apr-25 12-May-25
CABLE PULLING & CONNECTION - BATT CHARGER + BATT + BATT DB +
160 3 # T OSB-SS-04-UPS-U-10 E.PULGAR 159 ↖ (T) CABLE P…
SS 3 10 2-May-25 15-May-25
BATT SWITCH
ECR-SS-04-TR-E-01 / 02 - POWER & CONTROL CABLE PULLING & CONN -
161 3 # T ECR-SS-04-TR-E-01 / 02 E.PULGAR 220 ↙ (M) NORTHFS
R… 25 6-Mar-25 9-Apr-25
NORTH ROUTING

7 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings

6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today

Updated on: Saved on: 220

ids Item Details 29-May-23 1-Jun-23

s r Team ind. ind. d. d. d. d. Work


id Type Description Role ⚠ item
Start End Start End % M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M
id id Member Start End id conn lag days

162 3 # M SS-04 PULLING CABLE FINISHED PO 0550 E.PULGAR 9-Jun-25 FF 1 9-Jun-25 9-Jun-25 ◆

ECR-SS-04-TR-E-03 / 04 - EQUIPMENT TESTING - POWER


163 3 # T ECR-SS-04-TR-E-03 / 04 E.PULGAR 142 ↖ (T) ECR-SS-…
FS 8 13-May-25 22-May-25
TRANSFORMER (VENDOR ASSISTANCE)
ECR-SS-04-SG-N-02 - EQUIPMENT TESTING - 6 kV - MV SWITCHGEAR
164 3 # T ECR-SS-04-SG-N-02 E.PULGAR 142 ↖ (T) ECR-SS-…
FS 40 13-May-25 7-Jul-25
(VENDOR ASSISTANCE)
ECR-SS-04-TR-N-05 / 06 - EQUIPMENT TESTING - POWER
165 3 # T ECR-SS-04-TR-N-05 / 06 E.PULGAR 143 ↖ (T) POWER FS
&… 8 24-Mar-25 2-Apr-25
TRANSFORMER (VENDOR ASSISTANCE)
ECR-SS-04-TR-N-07 / 08 - EQUIPMENT TESTING - POWER
166 3 # T
TRANSFORMER (VENDOR ASSISTANCE)
ECR-SS-04-TR-N-07 / 08 E.PULGAR 144 ↖ (T) POWER FS
&… 8 7-Apr-25 16-Apr-25
ECR-SS-04-TR-N-03 / 04 - EQUIPMENT TESTING - POWER
167 3 # T
TRANSFORMER (VENDOR ASSISTANCE)
ECR-SS-04-TR-N-03 / 04 E.PULGAR 145 ↖ (T) POWER FS
&… 8 21-Apr-25 30-Apr-25
ECR-SS-04-MCC-R-02 - EQUIPMENT TESTING - 0.69 kV - MCC (VENDOR
168 3 # T ECR-SS-04-MCC-R-02 E.PULGAR 143 ↖ (T) POWER FS
&… 15 24-Mar-25 11-Apr-25
ASSISTANCE)
ECR-SS-04-MCC-R-03 - EQUIPMENT TESTING - 0.69 kV - MCC (VENDOR
169 3 # T
ASSISTANCE)
ECR-SS-04-MCC-R-03 E.PULGAR 144 ↖ (T) POWER FS
&… 15 7-Apr-25 25-Apr-25
ECR-SS-04-MCC-R-01 - EQUIPMENT TESTING - 0.69 kV - MCC (VENDOR
170 3 # T ECR-SS-04-MCC-R-01 E.PULGAR 145 ↖ (T) POWER FS
&… 15 21-Apr-25 9-May-25
ASSISTANCE)
ECR-SS-04-TR-N-09 / 10 - EQUIPMENT TESTING - POWER
171 3 # T ECR-SS-04-TR-N-09 / 10 E.PULGAR 146 ↖ (T) POWER FS
&… 8 19-May-25 28-May-25
TRANSFORMER (VENDOR ASSISTANCE)
ECR-SS-04-TR-N-01 / 02 - EQUIPMENT TESTING - POWER
172 3 # T ECR-SS-04-TR-N-01 / 02 E.PULGAR 147 ↖ (T) POWER FS
&… 8 29-May-25 9-Jun-25
TRANSFORMER (VENDOR ASSISTANCE)
ECR-SS-04-TR-N-11 / 12 - EQUIPMENT TESTING - POWER
173 3 # T ECR-SS-04-TR-N-11 / 12 E.PULGAR 148 ↖ (T) POWER FS
&… 8 10-Jun-25 19-Jun-25
TRANSFORMER (VENDOR ASSISTANCE)
ECR-SS-04-MCC-R-04 - EQUIPMENT TESTING - 0.69 kV - MCC (VENDOR
174 3 # T
ASSISTANCE)
ECR-SS-04-MCC-R-04 E.PULGAR 146 ↖ (T) POWER FS
&… 15 19-May-25 6-Jun-25
ECR-SS-04-SG-S-01 - EQUIPMENT TESTING - 0.69 kV - MCC (VENDOR
175 3 # T ECR-SS-04-SG-S-01 E.PULGAR 147 ↖ (T) POWER FS
&… 15 29-May-25 18-Jun-25
ASSISTANCE)
ECR-SS-04-SG-S-04 - EQUIPMENT TESTING - 0.69 kV - MCC (VENDOR
176 3 # T ECR-SS-04-SG-S-04 E.PULGAR 148 ↖ (T) POWER FS
&… 15 10-Jun-25 30-Jun-25
ASSISTANCE)

177 3 # M EMERGENCY DIESEL GENERATOR AVAILABLE PO 0550 PO 0550 E.PULGAR 22-Apr-24 FS 5 22-Apr-24 26-Apr-24
ECR-SS-04-EDG-R-01 - EQUIPMENT TESTING - 0.69 kV EMERGENCY
178 3 # T
DIESEL GENERATOR (VENDOR ASSISTANCE)
ECR-SS-04-EDG-R-01 E.PULGAR 149 ↖ (T) POWER FS
&… 10 14-Apr-25 25-Apr-25
ECR-SS-04-EDG-R-02 - EQUIPMENT TESTING - 0.69 kV EMERGENCY
179 3 # T
DIESEL GENERATOR (VENDOR ASSISTANCE)
ECR-SS-04-EDG-R-02 E.PULGAR 150 ↖ (T) POWER FS
&… 10 23-Apr-25 6-May-25
ECR-SS-04-SG-R-01 - EQUIPMENT TESTING - 0.69 kV - EMERGENCY
180 3 # T ECR-SS-04-SG-R-01 E.PULGAR 192 ↙ (M) BOTH EM…
FS 15 14-May-25 3-Jun-25
SWG (VENDOR ASSISTANCE)
ECR-SS-04-SG-R-02 - EQUIPMENT TESTING - 0.69 kV - EMERGENCY
181 3 # T
SWG (VENDOR ASSISTANCE)
ECR-SS-04-SG-R-02 E.PULGAR 180 ↖ (T) ECR-SS-…
SS 10 15 28-May-25 17-Jun-25
OSB-SS-04-UPS-U-01 EQUIPMENT TESTING - UPS TESTING (VENDOR
182 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-01 E.PULGAR 151 ↖ (T) CABLE P…
FS 10 16-Apr-25 29-Apr-25
OSB-SS-04-UPS-U-03 EQUIPMENT TESTING - UPS TESTING (VENDOR
183 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-03 E.PULGAR 152 ↖ (T) CABLE P…
FS 10 21-Apr-25 2-May-25
OSB-SS-04-UPS-U-05 EQUIPMENT TESTING - UPS TESTING (VENDOR
184 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-05 E.PULGAR 153 ↖ (T) CABLE P…
FS 10 24-Apr-25 7-May-25
OSB-SS-04-UPS-U-07 EQUIPMENT TESTING - UPS TESTING (VENDOR
185 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-07 E.PULGAR 154 ↖ (T) CABLE P…
FS 10 29-Apr-25 12-May-25
OSB-SS-04-UPS-U-02 EQUIPMENT TESTING - UPS TESTING (VENDOR
186 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-02 E.PULGAR 155 ↖ (T) CABLE P…
FS 10 25-Apr-25 8-May-25
OSB-SS-04-UPS-U-04 EQUIPMENT TESTING - UPS TESTING (VENDOR
187 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-04 E.PULGAR 156 ↖ (T) CABLE P…
FS 10 30-Apr-25 13-May-25
OSB-SS-04-UPS-U-06 EQUIPMENT TESTING - UPS TESTING (VENDOR
188 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-06 E.PULGAR 157 ↖ (T) CABLE P…
FS 10 5-May-25 16-May-25
OSB-SS-04-UPS-U-08 EQUIPMENT TESTING - UPS TESTING (VENDOR
189 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-08 E.PULGAR 158 ↖ (T) CABLE P…
FS 10 8-May-25 21-May-25
OSB-SS-04-UPS-U-09 EQUIPMENT TESTING - UPS TESTING (VENDOR
190 3 # T OSB-SS-04-UPS-U-09 E.PULGAR 159 ↖ (T) CABLE P…
FS 10 13-May-25 26-May-25
ASSISTANCE)
OSB-SS-04-UPS-U-10 EQUIPMENT TESTING - UPS TESTING (VENDOR
191 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-10 E.PULGAR 160 ↖ (T) CABLE P…
FS 10 16-May-25 29-May-25

8 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings

6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today

Updated on: Saved on: 220

ids Item Details 29-May-23 1-Jun-23

s r Team ind. ind. d. d. d. d. Work


id Type Description Role ⚠ item
Start End Start End % M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M
id id Member Start End id conn lag days

192 3 # M BOTH EMERGENCY DIESEL GENERATOR READY TO ENERGIZE E.PULGAR 179 ↖ (T) ECR-SS-…
FS 5 7-May-25 13-May-25 ◆

ECR-SS-04-SG-N-01 - ENERGIZATION - 6 kV - MV SWITCHGEAR


193 3 # T ECR-SS-04-SG-N-01 E.PULGAR 48 ↖ (T) ECR-SS-…
FS 10 1-Jul-25 14-Jul-25
(VENDOR ASSISTANCE)
ECR-SS-04-SG-N-02 - ENERGIZATION - 6 kV - MV SWITCHGEAR
194 3 # T ECR-SS-04-SG-N-02 E.PULGAR 164 ↖ (T) ECR-SS-…
FS 10 8-Jul-25 21-Jul-25
(VENDOR ASSISTANCE)

195 3 # M MV MOTORS READY TO PRE-COMM E.PULGAR 194 ↖ (T) ECR-SS-…


FS 3 22-Jul-25 24-Jul-25
ECR-SS-04-MCC-R-02 - ENERGIZATION - 0.69 kV - MCC (VENDOR
196 3 # T
ASSISTANCE)
ECR-SS-04-MCC-R-02 E.PULGAR 168 ↖ (T) ECR-SS-…
FS 10 14-Apr-25 25-Apr-25
ECR-SS-04-MCC-R-03 - ENERGIZATION - 0.69 kV - MCC (VENDOR
197 3 # T
ASSISTANCE)
ECR-SS-04-MCC-R-03 E.PULGAR 169 ↖ (T) ECR-SS-…
FS 10 28-Apr-25 9-May-25
ECR-SS-04-MCC-R-01 - ENERGIZATION - 0.69 kV - MCC (VENDOR
198 3 # T ECR-SS-04-MCC-R-01 E.PULGAR 170 ↖ (T) ECR-SS-…
FS 10 12-May-25 23-May-25
ASSISTANCE)

199 3 # M LV MOTORS READY TO PRE-COMM E.PULGAR 197 ↖ (T) ECR-SS-…


FS 5 12-May-25 16-May-25 ◆

ECR-SS-04-MCC-R-04 - ENERGIZATION - 0.69 kV - MCC (VENDOR


200 3 # T ECR-SS-04-MCC-R-04 E.PULGAR 174 ↖ (T) ECR-SS-…
FS 10 9-Jun-25 20-Jun-25
ASSISTANCE)
ECR-SS-04-SG-S-01 - ENERGIZATION - 0.69 kV - MCC (VENDOR
201 3 # T ECR-SS-04-SG-S-01 E.PULGAR 175 ↖ (T) ECR-SS-…
FS 10 19-Jun-25 2-Jul-25
ASSISTANCE)
ECR-SS-04-SG-S-04 - ENERGIZATION - 0.69 kV - MCC (VENDOR
202 3 # T ECR-SS-04-SG-S-04 E.PULGAR 176 ↖ (T) ECR-SS-…
FS 10 1-Jul-25 14-Jul-25
ASSISTANCE)
ECR-SS-04-SG-R-01 - ENERGIZATION - 0.69 kV - EMERGENCY SWG
203 3 # T ECR-SS-04-SG-R-01 E.PULGAR 180 ↖ (T) ECR-SS-…
FS 5 4-Jun-25 10-Jun-25
(VENDOR ASSISTANCE)
ECR-SS-04-SG-R-02 - ENERGIZATION - 0.69 kV - EMERGENCY SWG
204 3 # T
(VENDOR ASSISTANCE)
ECR-SS-04-SG-R-02 E.PULGAR 181 ↖ (T) ECR-SS-…
FS 5 18-Jun-25 24-Jun-25
OSB-SS-04-UPS-U-01 - ENERGIZATION - BATTERY CHARGER
205 3 # T OSB-SS-04-UPS-U-01 E.PULGAR 182 ↖ (T) OSB-SS-…
FS 5 30-Apr-25 6-May-25
ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-04-UPS-U-03 - ENERGIZATION - BATTERY CHARGER
206 3 # T OSB-SS-04-UPS-U-03 E.PULGAR 183 ↖ (T) OSB-SS-…
FS 5 5-May-25 9-May-25
ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-04-UPS-U-05 - ENERGIZATION - BATTERY CHARGER
207 3 # T OSB-SS-04-UPS-U-05 E.PULGAR 184 ↖ (T) OSB-SS-…
FS 5 8-May-25 14-May-25
ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-04-UPS-U-07 - ENERGIZATION - BATTERY CHARGER
208 3 # T
ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-04-UPS-U-07 E.PULGAR 185 ↖ (T) OSB-SS-…
FS 5 13-May-25 19-May-25
OSB-SS-04-UPS-U-02 - ENERGIZATION - BATTERY CHARGER
209 3 # T
ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-04-UPS-U-02 E.PULGAR 186 ↖ (T) OSB-SS-…
FS 5 9-May-25 15-May-25
OSB-SS-04-UPS-U-04 - ENERGIZATION - BATTERY CHARGER
210 3 # T OSB-SS-04-UPS-U-04 E.PULGAR 187 ↖ (T) OSB-SS-…
FS 5 14-May-25 20-May-25
ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-04-UPS-U-06 - ENERGIZATION - BATTERY CHARGER
211 3 # T
ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-04-UPS-U-06 E.PULGAR 188 ↖ (T) OSB-SS-…
FS 5 19-May-25 23-May-25
OSB-SS-04-UPS-U-08 - ENERGIZATION - BATTERY CHARGER
212 3 # T
ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-04-UPS-U-08 E.PULGAR 189 ↖ (T) OSB-SS-…
FS 5 22-May-25 28-May-25
OSB-SS-04-UPS-U-09 - ENERGIZATION - BATTERY CHARGER
213 3 # T
ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-04-UPS-U-09 E.PULGAR 190 ↖ (T) OSB-SS-…
FS 5 27-May-25 2-Jun-25
OSB-SS-04-UPS-U-10 - ENERGIZATION - BATTERY CHARGER
214 3 # T
ENERGIZATION (VENDOR ASSISTANCE)
OSB-SS-04-UPS-U-10 E.PULGAR 191 ↖ (T) OSB-SS-…
FS 5 30-May-25 5-Jun-25

9 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings

6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today

Updated on: Saved on: 220

ids Item Details 29-May-23 1-Jun-23

s r Team ind. ind. d. d. d. d. Work


id Type Description Role ⚠ item
Start End Start End % M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M M
id id Member Start End id conn lag days
CABLE PULLING & CONNECTION - 36 kV POWER SUPPLY FROM SS-05 SOUTH ROUTINTG CABLE PULLING
215 3 # M
(SOUTH ROUTING) FINISHED FINISHED
E.PULGAR 29-Jun-25 4 29-Jun-25 2-Jul-25 ◆

216 3 # M PAR-152 STEEL STRUCTURE ERECTION FINISHED PAR-152 (AREA 4) E.PULGAR 5-Jan-25 4 5-Jan-25 8-Jan-25 ◆

217 3 # M PAR-003 TRANSPORT TO FINAL LOCATION FINISHED PAR-003 (ECR) E.PULGAR 26-Sep-24 4 26-Sep-24 1-Oct-24

218 3 # M PAR-002 TRANSPORT TO FINAL LOCATION FINISHED PAR-002 (ECR) E.PULGAR 26-Oct-24 4 26-Oct-24 30-Oct-24

219 3 # M PR-09 STEEL STRUCTURE ERECTION FINISHED PR-00-09 (ECR) E.PULGAR 18-Oct-24 4 18-Oct-24 23-Oct-24
NORTH ROUTINTG CABLETRAY BY
220 3 # M NORTH ROUTING CABLETRAY AVAILABLE - BY OTHER
OTHER
E.PULGAR 224 ↙ (T) PAR-152…
FS 5 27-Feb-25 5-Mar-25 ◆

221 3 # T PAR-003 CABLETRAY INSTALLATION (HOOK UP) PAR-003 (ECR) E.PULGAR 217 ↖ (M) PAR-003…
FS 45 25 4-Dec-24 7-Jan-25

222 3 # T PR-00-09 CABLETRAY INSTALLATION PR-00-09 (ECR) E.PULGAR 219 ↖ (M) PR-09 S…
FS 45 25 26-Dec-24 29-Jan-25

223 3 # T PAR-002 CABLETRAY INSTALLATION (HOOK UP) PAR-002 (ECR) E.PULGAR 218 ↖ (M) PAR-002…
FS 45 25 2-Jan-25 5-Feb-25

224 3 # T PAR-152 CABLETRAY INSTALLATION PAR-152 (AREA 4) E.PULGAR 216 ↖ (M) PAR-152…
FS 10 25 23-Jan-25 26-Feb-25

10 of 10 6/27/2023; 2:47 PM

You might also like