Ineos-Ecr-Osb-Ss-Energization Plan 2
Ineos-Ecr-Osb-Ss-Energization Plan 2
Ineos-Ecr-Osb-Ss-Energization Plan 2
LOPEZ Settings
6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today
1 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings
6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today
25 2 # M UPS EQUIPMENT AVAILABLE AT SITE (PO 1216) PO 1216 E.PULGAR 30-Jan-24 FS 5 30-Jan-24 5-Feb-24
26 2 # M POWER TRANSFORMER AVAILABLE AT SITE (PO 1201) PO 1201 E.PULGAR 24-Jun-24 1 24-Jun-24 24-Jun-24
27 2 # M HV SWITCHGEAR 6.3 kV AVAILABLE AT SITE (PO 1210) PO 1210 E.PULGAR 3-Aug-24 2 3-Aug-24 5-Aug-24
28 2 # M 6 kV BUS DUCT AVAILABLE AT SITE (PO 1206) PO 1206 E.PULGAR 3-Aug-24 2 3-Aug-24 5-Aug-24
TDG-SS-04 - EQUIPMENT INSTALLATION - TEMPORARY DIESEL
29 2 # T
GENERATOR (CABLE PULLING & CONNECTION)
TDG-SS-04 E.PULGAR 24 ↖ (M) START S…
SS 3 3-Feb-25 5-Feb-25
TPDP-SS-04 - EQUIPMENT INSTALLATION - TEMPORARY POWER
30 2 # T
DISTRIBUTION PANEL (CABLE PULLING & CONNECTION)
TPDP-SS-04 E.PULGAR 24 ↖ (M) START S…
SS 3 3-Feb-25 5-Feb-25
ECR-SS-04-UPS-W-01 - EQUIPMENT INSTALLATION - BATTERY
31 2 # T ECR-SS-04-UPS-W-01 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
CHARGER
ECR-SS-04-UPS-W-02 - EQUIPMENT INSTALLATION - BATTERY
32 2 # T ECR-SS-04-UPS-W-02 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
CHARGER
ECR-SS-04-DB-W-01 - EQUIPMENT INSTALLATION - DC DISTRIBUTION
33 2 # T ECR-SS-04-DB-W-01 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
BOARD
ECR-SS-04-DB-W-02 - EQUIPMENT INSTALLATION - DC DISTRIBUTION
34 2 # T ECR-SS-04-DB-W-02 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
BOARD
ECR-SS-04-DSW-W-01 - EQUIPMENT INSTALLATION - BATTERY
35 2 # T
ISOLATOR SWITCH
ECR-SS-04-DSW-W-01 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
ECR-SS-04-DSW-W-02 - EQUIPMENT INSTALLATION - BATTERY
36 2 # T ECR-SS-04-DSW-W-02 E.PULGAR 24 ↖ (M) START S…
FS 5 4-Feb-25 10-Feb-25
ISOLATOR SWITCH
2 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings
6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today
52 2 # M PAR-152 STEEL STRUCTURE ERECTION FINISHED PAR-152 (AREA 4) E.PULGAR 5-Jan-25 4 5-Jan-25 8-Jan-25 ◆
53 2 # M PAR-003 TRANSPORT TO FINAL LOCATION FINISHED PAR-003 (ECR) E.PULGAR 26-Sep-24 4 26-Sep-24 1-Oct-24
54 2 # M PAR-002 TRANSPORT TO FINAL LOCATION FINISHED PAR-002 (ECR) E.PULGAR 29-Oct-24 4 29-Oct-24 1-Nov-24
55 2 # M PR-09 STEEL STRUCTURE ERECTION FINISHED PR-00-09 (ECR) E.PULGAR 18-Oct-24 4 18-Oct-24 23-Oct-24
NORTH ROUTINTG CABLETRAY BY
56 2 # M NORTH ROUTING CABLETRAY AVAILABLE - BY OTHER E.PULGAR 60 ↙ (T) PAR-152…
FS 3 27-Feb-25 3-Mar-25 ◆
OTHER
57 2 # T PAR-003 CABLETRAY INSTALLATION (HOOK UP) PAR-003 (ECR) E.PULGAR 53 ↖ (M) PAR-003…
FS 45 25 4-Dec-24 7-Jan-25
59 2 # T PAR-002 CABLETRAY INSTALLATION (HOOK UP) PAR-002 (ECR) E.PULGAR 54 ↖ (M) PAR-002…
FS 45 25 6-Jan-25 7-Feb-25
3 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings
6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today
64 3 # M LV SWITCHGEAR AVAILABLE AT SITE (PO 1212) PO 1212 E.PULGAR 25 ↖ (M) UPS EQU…
SS 5 30-Jan-24 5-Feb-24
ECR-SS-04-TR-E-03 - EQUIPMENT INSTALLATION - 36/6.3 kV
65 3 # T ECR-SS-04-TR-E-03 E.PULGAR 24 ↖ (M) START S…
SS 5 3-Feb-25 7-Feb-25
TRANSFORMER - 25MVA
ECR-SS-04-NER-N-03 - EQUIPMENT INSTALLATION - NEUTRAL
66 3 # T ECR-SS-04-NER-N-03 E.PULGAR 24 ↖ (M) START S…
SS 5 3-Feb-25 7-Feb-25
EARTHING RESISTOR
ECR-SS-04-TR-E-04 - EQUIPMENT INSTALLATION - 36/6.3 kV
67 3 # T
TRANSFORMER - 25MVA
ECR-SS-04-TR-E-04 E.PULGAR 24 ↖ (M) START S…
SS 5 5 10-Feb-25 14-Feb-25
ECR-SS-04-NER-N-04 - EQUIPMENT INSTALLATION - NEUTRAL
68 3 # T
EARTHING RESISTOR
ECR-SS-04-NER-N-04 E.PULGAR 24 ↖ (M) START S…
SS 5 5 10-Feb-25 14-Feb-25
ECR-SS-04-SG-N-02 - EQUIPMENT INSTALLATION - 6 kV - MV
69 3 # T ECR-SS-04-SG-N-02 E.PULGAR 43 ↖ (T) ECR-SS-…
SS 15 25 24-Feb-25 28-Mar-25
SWITCHGEAR
ECR-SS-04-BD-N-01 - EQUIPMENT INSTALLATION - 6 kV - BUS DUCT
70 3 # T
(TESTING INCLUDED)
ECR-SS-04-BD-N-01 E.PULGAR 43 ↖ (T) ECR-SS-…
FS 15 10-Mar-25 28-Mar-25
ECR-SS-04-BD-N-02 - EQUIPMENT INSTALLATION - 6 kV - BUS DUCT
71 3 # T ECR-SS-04-BD-N-02 E.PULGAR 43 ↖ (T) ECR-SS-…
FS 7 15 19-Mar-25 8-Apr-25
(TESTING INCLUDED)
ECR-SS-04-BD-N-03 - EQUIPMENT INSTALLATION - 6 kV - BUS DUCT
72 3 # T ECR-SS-04-BD-N-03 E.PULGAR 71 ↖ (T) ECR-SS-…
SS 7 15 28-Mar-25 17-Apr-25
(TESTING INCLUDED)
ECR-SS-04-BD-N-04 - EQUIPMENT INSTALLATION - 6 kV - BUS DUCT
73 3 # T ECR-SS-04-BD-N-04 E.PULGAR 72 ↖ (T) ECR-SS-…
SS 7 15 8-Apr-25 28-Apr-25
(TESTING INCLUDED)
ECR-SS-04-TR-N-05 - EQUIPMENT INSTALLATION - 6/0.72 kV
74 3 # T ECR-SS-04-TR-N-05 E.PULGAR 67 ↖ (T) ECR-SS-…
FS 5 17-Feb-25 21-Feb-25
TRANSFORMER - 4MVA
ECR-SS-04-TR-N-06 - EQUIPMENT INSTALLATION - 6/0.72 kV
75 3 # T
TRANSFORMER - 4MVA
ECR-SS-04-TR-N-06 E.PULGAR 74 ↖ (T) ECR-SS-…
SS 5 5 24-Feb-25 28-Feb-25
ECR-SS-04-TR-N-07 - EQUIPMENT INSTALLATION - 6/0.72 kV
76 3 # T ECR-SS-04-TR-N-07 E.PULGAR 75 ↖ (T) ECR-SS-…
FS 5 3-Mar-25 7-Mar-25
TRANSFORMER - 5MVA
ECR-SS-04-TR-N-08 - EQUIPMENT INSTALLATION - 6/0.72 kV
77 3 # T ECR-SS-04-TR-N-08 E.PULGAR 76 ↖ (T) ECR-SS-…
SS 5 5 10-Mar-25 14-Mar-25
TRANSFORMER - 5MVA
ECR-SS-04-TR-N-03 - EQUIPMENT INSTALLATION - 6/0.72 kV
78 3 # T ECR-SS-04-TR-N-03 E.PULGAR 77 ↖ (T) ECR-SS-…
FS 5 17-Mar-25 21-Mar-25
TRANSFORMER - 4MVA
ECR-SS-04-TR-N-04 - EQUIPMENT INSTALLATION - 6/0.72 kV
79 3 # T
TRANSFORMER - 4MVA
ECR-SS-04-TR-N-04 E.PULGAR 78 ↖ (T) ECR-SS-…
SS 5 5 24-Mar-25 28-Mar-25
4 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings
6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today
101 3 # T ECR-SS-04-MCC-R-04 - EQUIPMENT INSTALLATION - 0.69 kV - MCC ECR-SS-04-MCC-R-04 E.PULGAR 82 ↖ (T) ECR-SS-…
FS 15 24-Mar-25 11-Apr-25
102 3 # T ECR-SS-04-SG-S-01 - EQUIPMENT INSTALLATION - 0.69 kV - MCC ECR-SS-04-SG-S-01 E.PULGAR 101 ↖ (T) ECR-SS-…
SS 8 15 3-Apr-25 23-Apr-25
103 3 # T ECR-SS-04-SG-S-04 - EQUIPMENT INSTALLATION - 0.69 kV - MCC ECR-SS-04-SG-S-04 E.PULGAR 102 ↖ (T) ECR-SS-…
SS 8 15 15-Apr-25 5-May-25
ECR-SS-04-EDG-R-01 - EQUIPMENT INSTALLATION - 0.69 kV
104 3 # T
EMERGENCY DIESEL GENERATOR
ECR-SS-04-EDG-R-01 E.PULGAR 24 ↖ (M) START S…
SS 10 3-Feb-25 14-Feb-25
ECR-SS-04-EDG-R-02 - EQUIPMENT INSTALLATION - 0.69 kV
105 3 # T
EMERGENCY DIESEL GENERATOR
ECR-SS-04-EDG-R-02 E.PULGAR 24 ↖ (M) START S…
SS 5 10 10-Feb-25 21-Feb-25
ECR-SS-04-SG-R-01 - EQUIPMENT INSTALLATION - 0.69 kV -
106 3 # T ECR-SS-04-SG-R-01 E.PULGAR 82 ↖ (T) ECR-SS-…
SS 15 3-Mar-25 21-Mar-25
EMERGENCY SWG
ECR-SS-04-SG-R-02 - EQUIPMENT INSTALLATION - 0.69 kV -
107 3 # T
EMERGENCY SWG
ECR-SS-04-SG-R-02 E.PULGAR 82 ↖ (T) ECR-SS-…
SS 10 15 17-Mar-25 4-Apr-25
109 3 # T OSB-SS-04-UPS-U-03- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-03 E.PULGAR 32 ↖ (T) ECR-SS-… 3 5 14-Feb-25 20-Feb-25
110 3 # T OSB-SS-04-UPS-U-05- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-05 E.PULGAR 109 ↖ (T) OSB-SS-…
FS 5 21-Feb-25 27-Feb-25
111 3 # T OSB-SS-04-UPS-U-07- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-07 E.PULGAR 109 ↖ (T) OSB-SS-…
FS 3 5 26-Feb-25 4-Mar-25
OSB-SS-04-DB-U-01 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
112 3 # T
BOARD
OSB-SS-04-DB-U-01 E.PULGAR 34 ↖ (T) ECR-SS-…
FS 5 11-Feb-25 17-Feb-25
OSB-SS-04-DB-U-03 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
113 3 # T
BOARD
OSB-SS-04-DB-U-03 E.PULGAR 34 ↖ (T) ECR-SS-…
FS 3 5 14-Feb-25 20-Feb-25
OSB-SS-05-DB-U-05 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
114 3 # T
BOARD
OSB-SS-04-DB-U-05 E.PULGAR 113 ↖ (T) OSB-SS-…
FS 5 21-Feb-25 27-Feb-25
OSB-SS-07-DB-U-07 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
115 3 # T
BOARD
OSB-SS-04-DB-U-07 E.PULGAR 114 ↖ (T) OSB-SS-…
SS 3 5 26-Feb-25 4-Mar-25
OSB-SS-04-DSW-U-01 - EQUIPMENT INSTALLATION - BATTERY
116 3 # T OSB-SS-04-DSW-U-01 E.PULGAR 36 ↖ (T) ECR-SS-…
FS 5 11-Feb-25 17-Feb-25
ISOLATOR SWITCH
5 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings
6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today
120 3 # T ECR-SS-04-BAT-U-01 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-01 E.PULGAR 38 ↖ (T) ECR-SS-…
FS 10 18-Feb-25 3-Mar-25
121 3 # T ECR-SS-04-BAT-U-03 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-03 E.PULGAR 120 ↖ (T) ECR-SS-…
SS 7 10 27-Feb-25 12-Mar-25
122 3 # T ECR-SS-04-BAT-U-05 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-05 E.PULGAR 121 ↖ (T) ECR-SS-…
SS 7 10 10-Mar-25 21-Mar-25
123 3 # T ECR-SS-04-BAT-U-07 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-07 E.PULGAR 122 ↖ (T) ECR-SS-…
SS 7 10 19-Mar-25 1-Apr-25
124 3 # T OSB-SS-04-UPS-U-02 - EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-02 E.PULGAR 108 ↖ (T) OSB-SS-…
FS 5 18-Feb-25 24-Feb-25
125 3 # T OSB-SS-04-UPS-U-04- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-04 E.PULGAR 109 ↖ (T) OSB-SS-… 3 5 26-Feb-25 4-Mar-25
126 3 # T OSB-SS-04-UPS-U-06- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-06 E.PULGAR 110 ↖ (T) OSB-SS-…
FS 5 28-Feb-25 6-Mar-25
127 3 # T OSB-SS-04-UPS-U-08- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-08 E.PULGAR 111 ↖ (T) OSB-SS-…
SS 3 5 3-Mar-25 7-Mar-25
128 3 # T OSB-SS-04-UPS-U-09- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-09 E.PULGAR 127 ↖ (T) OSB-SS-…
FS 5 10-Mar-25 14-Mar-25
129 3 # T OSB-SS-04-UPS-U-10- EQUIPMENT INSTALLATION - UPS OSB-SS-04-UPS-U-10 E.PULGAR 128 ↖ (T) OSB-SS-…
SS 3 5 13-Mar-25 19-Mar-25
OSB-SS-04-DB-U-02 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
130 3 # T OSB-SS-04-DB-U-09 E.PULGAR 112 ↖ (T) OSB-SS-…
FS 5 18-Feb-25 24-Feb-25
BOARD
OSB-SS-04-DB-U-04 - EQUIPMENT INSTALLATION - UPS DISTRIBUTION
131 3 # T OSB-SS-04-DB-U-10 E.PULGAR 113 ↖ (T) OSB-SS-…
FS 3 5 26-Feb-25 4-Mar-25
BOARD
OSB-SS-04-DSW-U-02 - EQUIPMENT INSTALLATION - BATTERY
132 3 # T OSB-SS-04-DSW-U-02 E.PULGAR 116 ↖ (T) OSB-SS-…
FS 5 18-Feb-25 24-Feb-25
ISOLATOR SWITCH
OSB-SS-04-DSW-U-04- EQUIPMENT INSTALLATION - BATTERY
133 3 # T
ISOLATOR SWITCH
OSB-SS-04-DSW-U-04 E.PULGAR 117 ↖ (T) OSB-SS-…
SS 5 11-Feb-25 17-Feb-25
OSB-SS-04-DSW-U-06- EQUIPMENT INSTALLATION - BATTERY
134 3 # T
ISOLATOR SWITCH
OSB-SS-04-DSW-U-06 E.PULGAR 118 ↖ (T) OSB-SS-…
SS 5 11-Feb-25 17-Feb-25
OSB-SS-04-DSW-U-08 - EQUIPMENT INSTALLATION - BATTERY
135 3 # T OSB-SS-04-DSW-U-08 E.PULGAR 119 ↖ (T) OSB-SS-…
SS 5 11-Feb-25 17-Feb-25
ISOLATOR SWITCH
136 3 # T ECR-SS-04-BAT-U-02 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-02 E.PULGAR 120 ↖ (T) ECR-SS-…
FS 10 4-Mar-25 17-Mar-25
137 3 # T ECR-SS-04-BAT-U-04 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-04 E.PULGAR 121 ↖ (T) ECR-SS-…
SS 7 10 10-Mar-25 21-Mar-25
138 3 # T ECR-SS-04-BAT-U-06 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-06 E.PULGAR 122 ↖ (T) ECR-SS-…
SS 7 10 19-Mar-25 1-Apr-25
139 3 # T ECR-SS-04-BAT-U-08 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-08 E.PULGAR 123 ↖ (T) ECR-SS-…
SS 7 10 28-Mar-25 10-Apr-25
140 3 # T ECR-SS-04-BAT-U-09 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-09 E.PULGAR 139 ↖ (T) ECR-SS-…
SS 7 10 8-Apr-25 21-Apr-25
141 3 # T ECR-SS-04-BAT-U-10 - EQUIPMENT INSTALLATION - BATTERY RACK ECR-SS-04-BAT-U-10 E.PULGAR 140 ↖ (T) ECR-SS-…
SS 7 10 17-Apr-25 30-Apr-25
6 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings
6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today
7 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings
6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today
162 3 # M SS-04 PULLING CABLE FINISHED PO 0550 E.PULGAR 9-Jun-25 FF 1 9-Jun-25 9-Jun-25 ◆
177 3 # M EMERGENCY DIESEL GENERATOR AVAILABLE PO 0550 PO 0550 E.PULGAR 22-Apr-24 FS 5 22-Apr-24 26-Apr-24
ECR-SS-04-EDG-R-01 - EQUIPMENT TESTING - 0.69 kV EMERGENCY
178 3 # T
DIESEL GENERATOR (VENDOR ASSISTANCE)
ECR-SS-04-EDG-R-01 E.PULGAR 149 ↖ (T) POWER FS
&… 10 14-Apr-25 25-Apr-25
ECR-SS-04-EDG-R-02 - EQUIPMENT TESTING - 0.69 kV EMERGENCY
179 3 # T
DIESEL GENERATOR (VENDOR ASSISTANCE)
ECR-SS-04-EDG-R-02 E.PULGAR 150 ↖ (T) POWER FS
&… 10 23-Apr-25 6-May-25
ECR-SS-04-SG-R-01 - EQUIPMENT TESTING - 0.69 kV - EMERGENCY
180 3 # T ECR-SS-04-SG-R-01 E.PULGAR 192 ↙ (M) BOTH EM…
FS 15 14-May-25 3-Jun-25
SWG (VENDOR ASSISTANCE)
ECR-SS-04-SG-R-02 - EQUIPMENT TESTING - 0.69 kV - EMERGENCY
181 3 # T
SWG (VENDOR ASSISTANCE)
ECR-SS-04-SG-R-02 E.PULGAR 180 ↖ (T) ECR-SS-…
SS 10 15 28-May-25 17-Jun-25
OSB-SS-04-UPS-U-01 EQUIPMENT TESTING - UPS TESTING (VENDOR
182 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-01 E.PULGAR 151 ↖ (T) CABLE P…
FS 10 16-Apr-25 29-Apr-25
OSB-SS-04-UPS-U-03 EQUIPMENT TESTING - UPS TESTING (VENDOR
183 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-03 E.PULGAR 152 ↖ (T) CABLE P…
FS 10 21-Apr-25 2-May-25
OSB-SS-04-UPS-U-05 EQUIPMENT TESTING - UPS TESTING (VENDOR
184 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-05 E.PULGAR 153 ↖ (T) CABLE P…
FS 10 24-Apr-25 7-May-25
OSB-SS-04-UPS-U-07 EQUIPMENT TESTING - UPS TESTING (VENDOR
185 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-07 E.PULGAR 154 ↖ (T) CABLE P…
FS 10 29-Apr-25 12-May-25
OSB-SS-04-UPS-U-02 EQUIPMENT TESTING - UPS TESTING (VENDOR
186 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-02 E.PULGAR 155 ↖ (T) CABLE P…
FS 10 25-Apr-25 8-May-25
OSB-SS-04-UPS-U-04 EQUIPMENT TESTING - UPS TESTING (VENDOR
187 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-04 E.PULGAR 156 ↖ (T) CABLE P…
FS 10 30-Apr-25 13-May-25
OSB-SS-04-UPS-U-06 EQUIPMENT TESTING - UPS TESTING (VENDOR
188 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-06 E.PULGAR 157 ↖ (T) CABLE P…
FS 10 5-May-25 16-May-25
OSB-SS-04-UPS-U-08 EQUIPMENT TESTING - UPS TESTING (VENDOR
189 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-08 E.PULGAR 158 ↖ (T) CABLE P…
FS 10 8-May-25 21-May-25
OSB-SS-04-UPS-U-09 EQUIPMENT TESTING - UPS TESTING (VENDOR
190 3 # T OSB-SS-04-UPS-U-09 E.PULGAR 159 ↖ (T) CABLE P…
FS 10 13-May-25 26-May-25
ASSISTANCE)
OSB-SS-04-UPS-U-10 EQUIPMENT TESTING - UPS TESTING (VENDOR
191 3 # T
ASSISTANCE)
OSB-SS-04-UPS-U-10 E.PULGAR 160 ↖ (T) CABLE P…
FS 10 16-May-25 29-May-25
8 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings
6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today
192 3 # M BOTH EMERGENCY DIESEL GENERATOR READY TO ENERGIZE E.PULGAR 179 ↖ (T) ECR-SS-…
FS 5 7-May-25 13-May-25 ◆
9 of 10 6/27/2023; 2:47 PM
INEOS - SS ENERGIZATION Project Timespan: 30-Jan-24 - 24-Jul-25 (388) Project Manager: A.LOPEZ Settings
6-Oct-25
13-Oct-25
2-Dec-24
9-Dec-24
16-Dec-24
23-Dec-24
30-Dec-24
6-Jan-25
13-Jan-25
20-Jan-25
27-Jan-25
3-Feb-25
10-Feb-25
17-Feb-25
24-Feb-25
3-Mar-25
10-Mar-25
17-Mar-25
24-Mar-25
31-Mar-25
7-Apr-25
14-Apr-25
21-Apr-25
28-Apr-25
5-May-25
12-May-25
19-May-25
26-May-25
2-Jun-25
9-Jun-25
16-Jun-25
23-Jun-25
30-Jun-25
7-Jul-25
14-Jul-25
21-Jul-25
28-Jul-25
4-Aug-25
11-Aug-25
18-Aug-25
25-Aug-25
1-Sep-25
8-Sep-25
15-Sep-25
22-Sep-25
29-Sep-25
Actual Plan Base Plan Today
216 3 # M PAR-152 STEEL STRUCTURE ERECTION FINISHED PAR-152 (AREA 4) E.PULGAR 5-Jan-25 4 5-Jan-25 8-Jan-25 ◆
217 3 # M PAR-003 TRANSPORT TO FINAL LOCATION FINISHED PAR-003 (ECR) E.PULGAR 26-Sep-24 4 26-Sep-24 1-Oct-24
218 3 # M PAR-002 TRANSPORT TO FINAL LOCATION FINISHED PAR-002 (ECR) E.PULGAR 26-Oct-24 4 26-Oct-24 30-Oct-24
219 3 # M PR-09 STEEL STRUCTURE ERECTION FINISHED PR-00-09 (ECR) E.PULGAR 18-Oct-24 4 18-Oct-24 23-Oct-24
NORTH ROUTINTG CABLETRAY BY
220 3 # M NORTH ROUTING CABLETRAY AVAILABLE - BY OTHER
OTHER
E.PULGAR 224 ↙ (T) PAR-152…
FS 5 27-Feb-25 5-Mar-25 ◆
221 3 # T PAR-003 CABLETRAY INSTALLATION (HOOK UP) PAR-003 (ECR) E.PULGAR 217 ↖ (M) PAR-003…
FS 45 25 4-Dec-24 7-Jan-25
222 3 # T PR-00-09 CABLETRAY INSTALLATION PR-00-09 (ECR) E.PULGAR 219 ↖ (M) PR-09 S…
FS 45 25 26-Dec-24 29-Jan-25
223 3 # T PAR-002 CABLETRAY INSTALLATION (HOOK UP) PAR-002 (ECR) E.PULGAR 218 ↖ (M) PAR-002…
FS 45 25 2-Jan-25 5-Feb-25
224 3 # T PAR-152 CABLETRAY INSTALLATION PAR-152 (AREA 4) E.PULGAR 216 ↖ (M) PAR-152…
FS 10 25 23-Jan-25 26-Feb-25