T&C Plan FA&FF
T&C Plan FA&FF
Arar Land port Fire Fighting & Fire Alarm Works 21SACG00001
اسم المشروع رقم المشروع
Client Contract No.
ZATCA
المالك رقم العقد
Consultant Prototype
IMAR
الستشاري النموذج
Contractor Site No.
Redwater Project Engineering Company
المقاول رقم الموقع
To
IMAR
إلى
Attention
DOCUMENT SUBMITTAL عناية
Mr. Mohammed Sid Ahmed
FORM From
من
Redwater Project Engineering Company
Discipline التخصص □ Civil/Str. إنشائي/مدني □ Architectural معماري □ Electrical كهرباء □ Mechanical ميكانيكا
Testing and Commissioning Plan (Fire alarm and Firefighting Work) for Admin area
Document Description
وصف المستند
Consultant’s
Comments
مالحظات
الستشاري □ Approved □ Approved with Comments □ Revise and Resubmit □ Rejected □ Received for Information
موافقة موافقة مع مالحظات مراجعة وإعادة تقديم مرفوض نسخة منقحة للمعلومية
Approved by Consultant’s Discipline Engineer Approved by Project Manager
يعتمد من مهندس القسم لالستشاري يعتمد من مدير المشروع لالستشاري
Distribution Copy to نسخة إلى □ Contractor المقاول □ ZATCA EPMO Representative ممثل إدارة المشاريع بالجمارك السعودية
Note: These documents have been reviewed for general conformity with Contract terms & هذه.تمت مراجعة هذه المستندات للتوافق العام مع شروط وأحكام العقد والمواصفات وجداول الكميات :مالحظة
conditions, the specifications and bill of quantities. Such review doesn’t relieve the المراجعة ال تعفي المقاول من مسؤولياته التعاقدية بموجب شروط العقد وال تعتبر موافقة على أي
Contractor of his responsibilities under the terms of the Contract and shall not be deemed
as approval for any further compensation or permission to carry out additional works. .تعويض إضافي أو إذن لتنفيذ أعمال إضافية
Date 30/04/2024
Quality information
Electrical Engineer
Revision History
#0
Table of Contents
1. Introduction .................................................................................................... 4
2. Project Details................................................................................................ 4
8. Details of systems………………………………..…………………………….......11
1. Introduction
Purpose
Testing & Commissioning Plan Guide outlines the required tools to manage and complete Testing
& Commissioning phase. This includes strategy, procedures, requirements and documentation
obligatory in order to test and commission various structures and components of projects within
SAC EPMO
Definition
Testing and Commissioning Plan (T&CP) is defined as the complete set of all required documents
to fulfill the planning, execution and commission all categories of systems within SAC EPMO
projects. Documents consist of Pre-requisite deliverables prior to testing equipment and systems.
And the required deliverables as testing takes place. T&CP also describes processes to provide
resolution for issues such as scheduling, roles and responsibilities, construction testing, pre-
commissioning testing, system stand-alone testing, integrated testing, doomsday testing and
approvals.
2. Project Details
IMAR Engineering
Consultant: Consultant
AECOM PM:
MR.Mohammed Siraj
3. Project Scope
Arar Land port is a strategic land port at the Kingdom of Saudi Arabia Borders with Iraq.
This land port is projected by Zakat, Tax and Customs Authority (ZATCA) for development
The existing Arar LBC Fire Detection, Alarm and Firefighting Systems require upgrading and
improvement in keeping with Zakat, Tax and Customs Authority safety and security, and Civil Defense
requirements.
Undertake a Condition Report of the Arar Land Port and residential area fire life safety systems and
develop the fire strategy pertaining thereto
Develop a Fire Life Safety assessment with recommendations to rectify critical issues identified and
bring the site up to standard where so required under KSA requirements.
Refurbishment where required of the existing mechanical and electrical works inside and outside the
buildings to comply with the requirements of fire life safety
Documentation, installation and Testing and Commissioning new Fire detection, and life safety work to
buildings and areas of the land port area not currently having adequate Fire protection.
Testing & commissioning works for the systems shall be done as per the following
procedures, requirements, roles & responsibilities:
Phase Party
Description
# Contractor Supplier Consultant IMAR SAC EPMO End User
• Provide • Put remarks and • Verify consultant
Method • Communicate Start-Up recommendations recommendation
1 with all parties. Method of on Start-UP Method and grant approval --
Statement
Statement. of Statement. for the statement.
Phase Party
Description
# Contractor Supplier Consultant IMAR SAC EPMO End User
• Review Start-Up • Provide • Advice for any • Advice for any
Method of ITP. needed modification needed
Statement. to comply with modification to
project comply with project
• QA/QC works. requirement. requirement.
Operation and • Communicate
with all parties.
Functional
Performance • QA/QC works. Attend and approve
2 Test (O&FPT) -- FPT works as it is --
Perform FPT --
being successfully
works until it will completed.
be successfully
completed &
approved.
• Communicate
with all parties.
• Perform
commissioning • Attend
works until it will Commissioning
be successfully • Attend & supervise works until it will
completed & Commissioning be successfully
Testing and approved.
3 -- works until it will be completed & --
Commissioning successfully approved.
• QA/QC works. completed &
approve. • Receives all
documents from
• Provide all related Consultant
documentations
to be verified by
consultant
5. List of Systems
Remarks
No. Category Description
6. Equipment List
1.Fire Alarm Equipment List Admin Area
Sub-
# System Mnfr. Model Qty Drawing Ref. #
System
Fire Alarm -- Contex Plus XFP502/X/CON N/A
Control 18
Panel
Smoke -- Contex Plus 55000-685IMC N/A
266
Detector
Heat -- Contex Plus 55000-485IMC N/A
Electrical
19
Detector
Manual Call -- Contex Plus SA5900-908IMC N/A
54
point
-- Contex Plus CON451A/CX/SR N/A
Sounders CON433A/CX/D 80
R/65
Sub-
Drawing
# System Syste Mnfr. Model Qty
Ref. #
m
Emergency Light -- Khanda LF-LED-500F 166 N/A
Electri
Sub- Drawi
# System Syste Mnfr. Model Qty ng Ref.
m #
-- Union Pipe HDPE PIPE100, OD:200 N/A
HDPE Pipe 8 inch 90
Industry MM,SDR11,PN16,L:100M
-- Union Pipe HDPE PIPE100, OD:160 N/A
HDPE Pipe 6 inch 2800
Industry MM,SDR11,PN16,L:100M
-- Union Pipe HDPE PIPE100, OD:110 N/A
HDPE Pipe 4 inch 1100
Industry MM,SDR11,PN16,L:100M
-- Jazeera Steel ASTM A53 SCH.40, E.R.W N/A
black Steel Pipe 6 inch Black Steel Pipe WELDED 17
Mechanical
Sub- Drawi
# System Syste Mnfr. Model Qty ng Ref.
m #
-- Jazeera Steel ASTM A53 SCH.40, E.R.W N/A
black Steel Pipe 2 inch Black Steel Pipe WELDED 153
6MTR SIZE 2 INCH
-- Jazeera Steel ASTM A53 SCH.40, E.R.W N/A
black Steel Pipe 1.5 inch Black Steel Pipe WELDED 600
6MTR SIZE 1.5 INCH
-- Jazeera Steel ASTM A53 SCH.40, E.R.W N/A
black Steel Pipe 1 1/4
Black Steel Pipe WELDED 90
inch
6MTR SIZE 1 1/4 INCH
-- Jazeera Steel ASTM A53 SCH.40, E.R.W N/A
black Steel Pipe 1 inch Black Steel Pipe WELDED 400
6MTR SIZE 1 INCH
Sprinklers -- Lifeco LF310,LF311,LF,320&LF321 213 N/A
* MECHANICLA WORK
12/05/2024 12/05/2024
Firefighting
1. Saudi Post
12/05/2024 12/05/2024
Firefighting
2. Civil Defense building
12/05/2024 12/05/2024
Firefighting
3. Car Workshop
12/05/2024 12/05/2024
Firefighting
4. Kennels building
5. Road Security building Firefighting 12/05/2024 12/05/2024
8.Detail system
Electrical work
Mechanical work
• Fire Hydrant
- Hydrants are accessible.
-Hydrant outlets are slightly more than hand-tight
- There are no leaks in the top of the hydrant when hydrant valve is opened.
- There are no leaks in the gasket under the caps when hydrant valve is opened
- There are no cracks in the hydrant barrel
- Nozzle threads are not damaged
• Sprinkler system
-Check Sprinkler heads that are damaged or painted over must be
replaced.
- Check that sprinkler head and location match the type
indicated on the plans.
-Check any possibility of Leakage in the system after applying pressure.
- All piping and attached accessories subjected to system
working pressure shall be hydrostatically tested at 200 psi
and shall maintain that pressure without loss for 2 hours.