Im Notes
Im Notes
ESTIMATING COSTING
10
StzBNTS OF COST
(l) Direct
laboar, and (Il)
Indirect Jabour.
(l) Direct Labour. The workers, who actually work or process tbe
different materials manually or with the aid of machineg is, known as
Labour". This is also called Productive Labour. The nature of their duties
is such that their wages can be directly charged to the job, which they are
manufacturing.
Workers engaged for operating on various production machines in
machine shop welding shop, pattern making shop, electric winding shop
and assembly shop etc. is known as Direct Labour.
(H) Indirect labour. Any other labour, who help the
productive labour in performing their duties is known as Indirect
Labour. The nature of their duties is such that their wages can not
be charged directly to a particular job but are charged on the total
number of products produced in the plant during a particular
period.
Foremen, Supervisors, Inspectors, Chowkidars, Gate-
keepers. Store-keeper, Crane Driver and Gangmen etc., are
classified as Indirect Labour.
Now again consider the above example of Milling Machine Shop.
The worker who is producing gears continuously on the milling machine
is known as Direct Labour, while the Foreman, supervising in the milling
machine shop. the inspector checking the accuracy of gears and helper,
who is bringing and taking away the gear blanks from the worker are
examples of Indirect Labour.
3. Expenses. We have discussed, direct material cost and
direct labour cost but apart from this, you
will find that, in each factory there are several other
expenditures, such as cost of advertisement. building rent,
depreciation charges of plant and factory building, cost of
packing, cost of transportation, salaries and commission to
salesman etc. All these expenditures are known as "Expenses". So,
we can say that except direct material and direct labour cost, all
other expenses, which occur in the factory are known as
"Expenses".
The cost of Indirect material and Indirect labour is also
included in the expenses.
Expenses may be of two classes.
(i) Direct or chargeable Expenses, and (ii)
Indirect Expenses.
(i) These are those expenses, which can be
charged directly to a particular job and are done for that specific
job only. For example, cost of special jigs
and fixtures, cost of some special patterns and cost of
experimental work on a particular j 0b etc.
(It) Indirect Tbe»e are also known aa overhead
12 BTIMATING COSTING
Now, management wants profit of Rs. on the gross cost, t,.e. total
cost.
110x 583•20
Hence, Selling price of 100 pieces = 100
— Rs. 641•52
641•52
Hence,' Selling price of each work piece— 100
= Rs. 6•4152
Say, Rs. 6•42 Ans.
MECHANICAL AND
2. The market price of a lathe is Rs. 5000 and the discount
allowed to the distributor is 20% of the market price. It is found;
that the selling expenses cost is the factory cost and if the mate-rial
cost, labour cost and factory overbead charges are in the of I :
4 : 2 : what profit is made by the factory on each lathe, if the.
material cost is Rs. 400 ? Neglect other overheads. Solution.
Market price of a lathe= Rs. 5000
Discount allowed —200/0 on market price
5000 x 20
1000.
100
Hence, Selling price of factory=Rs. (5000—1000)
100
Total cost of20
—179•20.
Total cost 179•20
• Per unit cost of production
No. of —Rs. 8•96.
Hence the production cost of each connecting rod will
be 8 96 only. Ans.
4. A factory is producing 1000 bolts and nuts per hour on a
machine. Its material cost is Rs. 375, labour cost R'. 245 and the
direct expense is 80. The factory oncost is
150% of the total laboar cost and once on cost is 30% of
the total factory cost. If the selling price of each bolt
and nut is Rs. I •30, calculate whether the
management is going in loss or gain and by what amount.
Solution.
Material cost —Rs. 375
Labour cost —Rs. 245
Direct expense —Rs. 80
•arge•. Factory on cost—1500/o of total
labour
MECHANICAL AND
cost —Rs. 367•50
100
factory
—Rs. 1067•50
Now, once oncost is 30% of total factory
cost
1067•50x30
—Re. 320•25
00
COST
OF
854
610x40
= Rs. 244
Total
Hence, substituting in Eqn. (I)
T4•6R
854, —R— 100
or R—IOOO,
í8 BTIMATINO cosmo
=Rs. 5,000
5000
Hourly rate of depreciation= —Re,
0•2S. Ans. 20,000
COST 27
(b) Hourly rate of depreciation—Re. 0•25
Hourly cost of power consumption
-Re. 0•50
Repairs and maintenance cost for
150 hours. 30
1•35
Total machine
7. A factory owner employed 50 workers during
the month of • April '1969, whose details of
exFnditure are given below :
(t) Material cost —Re. 30,0.
(It) Rate of wages for each worker
10,0
Total=Rs. 73,100
.
(v) Selling overheads are :
—Pay to salesmen—Rg. 10,000. Ans.
(pi) Total cost —Factory cost+Administrative
overhead
+selling overhead
—Rs. 737,600.
22 ÈsTIMAt1NG COSTINÖ
58,500/units. Fixed
overheads for 58,500 unit
— Rs. 31,690.
Fixed overheads under normal conditions.
— Rs. 35,100,
EhlMAt1NO
Overheads to be unrecovered
Rs. 3410. Ans.
(c) Prodaetion to 130%.
Now, monthly production
= 65000x
= 84500 units.
Fixed overheads for 84500 units
+2,100+500
= As. 1/5,000. Ans.
(d) Total cost or cost of sales
= Cost of Production+Sales
overheads
Rs. Ans.
(e) Selling Price
= Total cost+Profit
Ans.
PIPE FITTING
14. Estimate the direct material cost and
total cost for a pipe fitting as shown in the
layout given below.
x TAP
PLUG
Fig.
The rates for various items are as follows :
Pipe 1'—Rs. I•80/ft. ; Pipe Y—Re. 1•O/ft.
Reducer f toe
-Re. each; Tee l'—Re. 1•00 each ; Reducer Tee
I• to ' —Re. 0•70 each : Tap Y—Rs. 400 each ;
Socket 1'—Re. 0•70 each ; Socket i'—Re. 0•50;
Bend 1'—Re. l•oo ; Plug r—Re. 0•40.
Assume consumption of cotton waste and white
lead as kg. and gm. respectively and these are
available at the rates of 21k& and Rs. 31kg.
respectively. One fitter and one helper are
employed for one day @ Rs. 6•00 and Rs. 4•00 per
day respectively may as 20% of the direct
labour cost.
26 ESTIMAt1NG mSTtN6 Solution. List of
Material Consumed :
overheads Rs. 290. If the selling on cost is 40% of prime cost, what
shoUld be the selling price of each product to obtain a profit of 20%
(i.e., profit is 20% of the selling pnce).
Ans. Rs. 15 each
12. Three workers in a machine shop are engaged on turning of
steel pins. They are paid equally. The weekly wages paid to tiEm are Rs. 205
and averhead expenses Rs. 90/week. Find factory cost per piece, if each
worker completed 420 pieces per week. Neglect material cost.
Ans. Re. 0•24
13. A certain product can be made either by hand or by
mass production. In the first method the time taken is 2 hours and
•overheads are 400/0 of labour cost. In the second method, the time
taken is 15 hours/100 products and overheads are '140% of the.labour
cost The material cost of each product is Rs. 1•50 and rate of labour/
hour is 80 paisa in each case. Estimate which of the two methods will
be more economical.
Ans. (i) Rs. 3•74
(ii) Rs. 1•79
Second method 14. A
factory has a capacity to produce 1000 shapers/annum. But at present it
is working at its 70% capacity. The sales income at this level is Rs.
The fixed cost of the factory is Rs. and variable
cost/piece is 2500. There is a proposal for mechanization, but this will
increase the fixed cost by Rs 400,000 and will reduce the variable cost
by Rs. 500 per unit. Estimate :
(a) Whethêr the proposal is economical ?
(b) If a reduction in selling price by Rs. 200/unit makes
the factory to run at 85% of its full capacity, would this be a better
pro. posal than the first one. Ans. (a) No, (b) Yes.
IS. How the total cost of a product can be
divided into diffe• rent goops ?
16. What are the different products which affect the sales price ?
17. "For the minimum cost of manufacture scrap should not be
kept as minimum". Justify the above statement.
3
INDIRECT EXPENSES
43
Introduction.
These expenses are all the expenses exc9t direct labour, direc material
and direct expenses, inctrred in the production of a concert It includes repair
of plant, power and water charges, depreciatio of building, machines etc ,
taxes, insurances, compensations, salaric of supervisors, administrative
officers and sales agents etc. Becaus there are several types of expenses
incurring on a product during year it is difficult to have an account of these
expenses. Therefor to have a systematic method of charging them, these
expenses ar categorised into certain groups.
Classified statement of different expenses are helpful to knol the
upto•date position of these expenses. These expenses are groupe into
following major categories.
(I) Factory expenses
(ii) Administrative
expenses (ill) Sales expenses.
In the chapter of elements of cost, different expenses made 01 a product
manutäctured in an industry, had already been discussec Direct labour and
direct material costs can be calculated with th help of work order, material
requisition slip, wages sheets etc.
As regards to oncosts, some of them can easily be known fron various
records, examples of such oncosts are, power charges, insu rance, building
rent, water charges, fuel charges etc. But som charges require good knowledge
and experience of the estimat01 These charges are discussed as under :
(I) Depreciation
(2) Obsolescence
(3) Interest on capital
(4) Idleness
(5) Repairs and maintenance.
l. Depreciation. Whenever any machine or equipment per forms useful
work its wear and tear is bound to occur. This can b minimised upto some
extent by proper care and maintenance bu can't be totally
prevented. Its efficiency also reduces with the laps
of time and at one time it uneconomical to be used
fhrthe and needs replacement by another new unit,
30
INDIRECT
Therefore, we can say that efficiency and value of machine or
asset contantly reduces with the lapse of time during use, which is
known as "Depreciation". So some money must be set aside yearly
from the profits, so that when that equipment becomes uneconomical,
it can be replaced by the new one. Therefore the initial cost of machine
plus installation charges+repair charges— scrap value is charged
against overheads and is spread ovú the machines useful life.
For this purpose depreciation account for the complete plant or
individual equipment is opened in the Company's Books and is known
as "Depreciation Fund" or "Sinking Fund". This amount is deducted
yearly from the profits and kept separate to have sufficient money for
replacement at the end of useful life.
2. Obsolescence. Suppose a factory owner purchases a machine
for his production shop but after some duration a better machine comes
in the market, whose production rate is very high and much
economical. Although the old machine is efficient but becomes out of
fashion and uneconomical due to the new better machine which has
come in the market. This is known as "Obsolescence". Consideration
of this factor is of much importance and some money should also be
set aside from the profits for this cause.
Hence "Obfolescence'.' is the depreciation of existing machinery or
asset due to new and better invention, design, equipment or processes etc.
It is very difficult problem for the estimator to provide for the on-cost
on obsolescence, because no body can say when a revolutionary change in the
machine is coming in the market. But it is a general practice to reduce the life
of a machine so as to account the effect of obsolescence. Now the depreciation
and obsolescence charges are calculated in the reduced life.
Suppose an estimator expects the life of machine as 20 years thin the
depreciation rate will be By considering obsolescence also, its
life may be taken as 15 years. Then the combined depreciation and
obsolescence charges will be instead of 5%. Therefore, the difference
= I •66% will be obsolescence charges.
The other causes of depreciation are physical decay, accidents, deferred
maintenance and neglect, inadequacy etc.
For further understanding depreciation can be classified as under
:
Depreciation
and neglect
uacy
Obsolescence
32 MECHANICAL ESTIMATING AND
depreciation, D = Rs.
20
37,000
20
Depreciation in value of boiler per year = Rs.
1850 only.
Now, depreciation fund on 15th June, 1955, i.e.
9. Instalments, (From 1st January, 1946 to 15th
June,' 1955) could be accumulated.
Depreciation fund collected upto 15 June, 1955
— Rs. — Rs. 16650•OO only.
(b) As after 12 years tubes have been replaced
and cost of placement is Rs 1500.
Now, book value in 12 years will be Rs. 52000— 12 x
1850
much during the early years, when the repairs and renewals are not
costly.
So under this method, the book value of the machine goes on
decreasing as its existence continues. A certain percentage of the
current book value is taken as the depreciation. Therefore, this is also
called "Percentage on Book Value" method.
In this, let x be the fixed percentage taken to calculate the yearly
depreciation on the book value.
Then,
where, C Initial cost, S = Scrap value, N = No. of years of life. It
will be more clear by the following solved
problem.
Problem 2. A lathe is purchased for Rs. 8.000 and the assumed
life is 10 years and scrap value Rs. 2,000. If the depreciation is charged
by Diminishing Balance method, calculate the percentage by which
value of the lathe is reducing every year and depreciation fund after 2
years.
Solution. Here C = 8,000 s —
2,000 N =
10.
1
We know that I-cr
Substituting the given values in the above formula 1
1
1
Solving by log, we get
1
= 0•8706
.x— — 0•1294
A Required 0/0 1294. Ans.
Value of lathe after 1 year
— Rs. $64•80.
Depreciation fund after I year
— Rs. 8000—Rs. 6964•80
— Re. 1035-20.
51
36 COSTING
= Rs. 6063•55
Depreciation of 2nd year
— 696380—606355
Henceby substitutio
n,
(2•U8U—1
)
Hence, required depreciation is Rs. 1157•40
per year. Ans.
4. The Annuity Charging Method. In
this, interest is charged on the cost of
machine or asset every year On the book value,
but the rate of depreciation is constant every
year.
Let C = Cost of machine
S = Scrap value
N — No. of years of machine
life
E'PENFES
Then D = CiR+C1—C2 =
Hence, the standard formula will be
[C(l +R)N —SICI —(1
+R)]
Here,
R = 0•08 C = Rs.
200,000
S = Rs. 20,000
N = 20 so,
4342
=Rs. 43,420
He sold the plant for Rs. at the end of 10 years The value of
plant received at the end of 10 years
43,420
38
0•Í
—Rs. 6
1650
.
Hence, depreciation annuity—Rs. 1650. Ans.
Now, suppose we have to calculate the
reduced value of asset aner two years, it can
be done in this way :
(8000x 1 •1 x --0•05
1550 —
C— 5500 only.
the reduced value of asset aner two years
will be R'.
INDIRBœr
5. The Insurance Policy Method. This method covers the risk, if the
machine becomes unserviceable before its estimated life.
In this machine is insured with the Insurance Company and premiums
are paid on the Insurance Policy. When thetpolicy matures, The company
provides sufficient sum to replace the machine.
6. Revaluation or Regular Valuation Method. This is not a standard
method. In this, every year the value of machine is revalued and the
55
difference between the book value and revalued •value is charged as
depreciation fund.
7.Machine Hoar Basis Method. In this, rate of depreciation is
calculated, considering the total number of hours a machine runs in a
year and therefore a work hour chart of every machine is maintained to
know the total number of hours the machine runs in a year.
This will be clear by the following problem.
Problem 6. What are Depreciation Charges ?
A machine is costing Rs. 11,000 and is expected to run for 10 years at
the end oftwhich its scrap value is likely to be Rs. 1000.
Machine is expected to run 2000 hour/year on the average. Estimate the
depreciation charges per hour of the machine.
(B.T.E., Rajasthan May 1970)
Solution.
Cost of Machine = Rs. 11,000 Scrap value
= Rss 1000
Depreciation Fund
— Rs. = Rs. 10,000
Life of Machine = 10 years
= 20.000 hours.
Depreciation charges/hr 10,000
20,000
= SO paise/hr. Ans.
Problem 7. The estimated life of a lathe is 10 years and it
16 hours a day. The initial cost of lathe is Rs. 8000 and scrap value
after 10 years is Rs. 2500. If the machine works for 5840 hours in a
year, calculate the rate of deprecíation charged annually unde machine
hour basis method.
Soluti0A Here N — 10 years
C Rs, 8000
S — Rs. 2500.
C—S — Rs. 8000-4Rs. 2500—Rs. 5500
Therefo:t loss in lathe in •10
5500
MECHANICAL ESTIMATING AND COSTING
40
Now, life of machine in hours
— 10x365x 16
Depreciation/hour
5
5500
Depreciation in one year (In one year
lathe works for 5840 hours).
55 x
5840=550.
584
Rate of depreciation/year
=Rs. 550. Ans.
8. The Sum of the Year's Digits Method.
In this, as the new equipment is installed,
the reduction in value will be greater
initially and it will go on decreasing
gradually. This fact is taken into account
and therefore greater amount of depreciation
is made during the early years of life and
it goes on reducing as the life of equipment
decreases. Therefore, for calculating
depreciation, the net amount (Total cost—
Scrap value) is spread over whole life in a
decreasing proportion.
It will be more clear by the following
problem.
Problem 8. The cost of a machine is Rs.
16,000 and its scrap value is Rs. 4000.
Determine depreciation charges for each
year, if the estimated life of machine is 4
years.
Solution. Here C =
16,000
s —
4000
N = 4 years. c—s =
57
Now, sum'of the digits of the years will
be
(1+2+3+4) = 10
Now, depreciation charges for each year can
be calculated as follows :
Depreciation charges for the 1st year
10
R'. 4800. Ans.
Depreciation charges for the 2nd year
10
= Re. 3600. An..
Depreciation charges for the 3rd year
10
— As. 200. Ans.
INDmBCT BXPNES
Fig. $3
43
44 ESTIMATING
61
I = Length of one side of parallelogram
„ another side of parallelogran h = beigh
of parallelogram
Area = I Xh
Perimeter = 2(l+b)
4. Triangle. (Fig. 4•4)
TRIANGLE
Fig.
Let a, b and c are the lengths of the sides of the triangle.
h = height of A from base BC
then, Area axh
= x Base X Perpendicular
Perimeter = a+b+c
and if
then, area =
Height
Area
HEXA60N
Fig 45
6. Any regular Polygon.
General formulae for any regular polygon having n sides of
length 'a' units each, are :
MECHANICAL AND COSTING
Perimeter ma
Anea i x Perimeter x Inner radius.
MENSURATION
Fig.
9. Sector. (Fig. 4•8)
Let r = Radius of circle
= angle in
radians I length of arc
I = re
Angle of sector
Area x Area of
2rc
circle
1 l.r Fig.
63
—ere
272 2
10. (Fig. 4•9) r =
Fillet. radius
fillet
of the
SECTOR
then,
Area of fillet =
— O•215r2 FILLET
4
= (approx.) Fig.
46
$ig.
a semi•major axis b =
semi-minor axis
Area •ra b
Perimeter = a(a+b).
Fig. 4•10 (a)
12. of a Circle. [Fig. 4' 10
(b))
MECHANICAL AND COSTING
—
?-hxl
where,
AREAS OF IRREGULAR FIGURES
There are. various methods of calculating area of irregular fares.
These methods give only approximate results. Some
of the important methods are given below :
I. By Simpson's Rale. (Fig. 4•11)
Divide the base of figure into even number of equal parts and
ordinates on each part as shown in the Fig. 4•11.
ey
Fig. 4•12
If h, yr.. ...yo are the lengths of ordinates and h = distance:
between each ordinate
then Area =
3. By Planimeter.
1
MECHANICAL AND
43 ESTIMATING cosrma
2. Prisms. (Fig. 4•14)
3. Cylinders. (Fig.
4• 15)
Let d = dia. of
cylinder
mtSM
Fig. 4•14
I = length of cylinder
. Volume of cylinder = —
CYLINDER and Surface area = "dl+
Fig. 4•15
4. Pyramids and Cones. (Fig. 4•16)
Perpendicular height H
Volume = Area of base X
3
Surface Area — Area of base+Perimeter of base
xl length of slant side L.
67
Fig. 016
UnSURATION
PYRAMID
Fig. 4•17
Volume =
where, al and aa are the areas of the two ends, but for frustum of
cone,
Volume
SPHERE 6
Fig. 4•18 • Tar'.
68 MECHANICAL AND
7. Hollow Sphere. (Fig. 4•19)
W'tow SPHEm
Fig. 4•19
Volume
$56MGNT A
= 27RXrr2
Fig.
69
10. *ricaISector. (Fig.
4•22)
Volume of sector
2
ACBD
Fig. 422
Spherica
l
Volume
$23
70 MECHANICAL AND
4. Method of Counting Squares. Draw the actual irregular
diagrams on a graph paper to some scale and count the number of
squares covered by this diagram, taking those squares greater than one
half as bne and neglecting those having less than one-half of them as
covered by the diagram. This gives approximate areas and used where
much accuracy is not desired. Area of figures = No. of squarex Area of
one square Trapezium
= Distance between successive ordinates x Sum of half the first
and last ordinates, together with all the remaining ordinates.
The Midordinate Method. (Fig. 4•24)
Divide the base line of the figure into any
number of small equal parts and at the centre of each of these
parts draw ordinates as shown in Fig 4•24. Calculate the average length
of these ordinates and multiply by the length of base line.
This also gives approximate areas.
Area
Fig.
GD — AD where AD is the
median DO
4•2S
2. Square. (Fig. 4•26)
a2
Fig. 426
3. Trapeziod. (Fig. 4•27)
Fig. 4•27
Bisect E and DC at F. Join EF. Setoff BY— DC
and DM = AB. Inter-section of EF and MN is at G. So c.g. will be at G.
(2a+h) (at b)
4. of a Circular Arc. (Fig. 4
28)
Fig.
72 MECHANICAL AND
Here xG=YG
= O•637R
BG = O•9R
R Radius of circular arc Fig. 4•28
S. Semi-circular Arc. (Fig. $29)
OG = O•637R
where R — radius of arc.
Fig. $29
6. of of Circle.
(Fig. $30) xG — YG
— O•424R
xG=yG
— O•223R from AB or BC
Fig. $32
9. Parabolic Segment. (Fig.• 4•33)
Fig. 4•33
10. Quadrant of an ellipse. (Fig. 4•34)
Fig.
Guldinus Rules
With the help of Guldinus rules the estimation of surface areas and
volumes of solids of revolution can be determined.
Estimadon of Surface Areas
According to Guldinus Rules, surface area of solid of revolution
= Perimeter of revolving figurexpath of its
centroid For example :
(a) Determine the surface area of a straight line parallel to the axis of
revolution.
The straight line pq revolving about yy traces out
a cylinder. If G is the c.g. of the straight line at a
distance R from the axis of revolution.
Then, surface area of cylinder generated by pq
revolving about yy
= 2"Rxpq
where pq
Fig. 4•37
(b) Determine surface area of solid of revolution of a semi-circle as
shown in Fig. 4•38.
The semi-circle-revolving about its diameter
will trace out a sphere.
Let r be the radius of the semi-circle then the
length of the arc of semi.circle — Tr.
If G is the c.g. of the semi-circle, then
distance OG —from m.
. Surface area of solid of revolution by
Guldinus
Fig. 4 38
Fig. 4•39
3
Volume of solid of revolution
x O X' It will then trace out a sphere. By Fig. 4•41 Guldinus rule
the volume of that sphere is the product of the area of the semicircle and
the path of its c.g.
(i) If G is the c.g. of the semi-circle then distance OG
= from its base.
Volume of sphere generated
4
— wrt.
where R
is the distance of c.g. of
the body from the axis
of rotation.
Fig. 4•42
(d) Determine the volume of solid of revolution of a trapezoid
about axis XX at a distance R
from c.g.
A trapezoid revolving about the axis
XX will generate a ring of trapeziodal
section.
5
ESTIMATION OF MATERIAL COST
Procedure
For calculating the material cost of a
product, following procedure should be adopted
(i) Break up the product into simple parts so that their volumes can
be easily calculated.
(ii) Neglect rounded corners and small fillets and take
suitable approximation wherever necessary.
(iii) By applying the formulae of mensuration, calculate the
volume of each part.
(iv) Add volumes of the parts to give,
volume of complete product.
(v) Calculate weight of material by multiplying the volume
by its density.
(VI) Lastly, calculate the material cost by multiplying the cost per
unit weight to the weight of material.
78 MEOHANICAL ESTIMATING AND
Following table gives the densities of different materials requir•
ed for estimating the weight of material.
Materials Wt. in gm./c.c.
1. Cast Iron
2. Aluminium 2•685
3. Brass 8•081
4. Bronze 8•496
5. Mild Steel 7•85
6. Teak wood 0•657 —0•882
7. Tin 7'420
Examples for estimating weights and material costs are being.
Sven under
Example 1. Estimate the weight of C.I. used in manufacturing step
pulley as shown in Fig. $1. Assume density of C.I. as 7•2• gm./c.c.
57
ESTIMATING
COSTDIG
Solution.
Break up this step pulley into 4 following
simple part A, B, C and D.
Part A :
As volume = —
= —x gm.
= 53 kg. Ans.
Example 2. Find out the weight of 10 M.S. spindles, the •shape and
size of which -are givea in Fig. $2. Also calçulate the weight of scrap, if they
are turned out from a M.S. rod of 25 mm. dia. and facing and parting off
allowances can be taken as I mm. and 5 mm., respectively. Assume that 15
mm. length of rod is requir.d for grip in the chuck. Desity of M.S. is gm./c.c.
-t
MECHANICAL
Volume of C 4= cm.'
Volume of D 4
Volume of B = Volume of frustum of
cone dia. cm. and 2 cm.
and height as I cm.
heigt
h
cm.
Volume of finished spindle = A+B+C—D
11•1 cm.8
= = 360 cm.' 4
= 302•18 cm.a
Weight of material = 302•18
= 2357 gm. = 2 357 kg.
Hence, material cost for lathe centre = 2•357X 1•20 =
Rs. 2 83.
Ans.
Example 4. Calculate the number of
rivets of dimensions shown in Fig which can
be •manufactured from 4 kg. of M.S.
Assume that there is no wastage of material.
Density of M.S. is 8 gm./c.c.
Solution. Break up the artical into
simple parts A, A and B.
Volume of head A (Two in All dimensions are in
Nos). Fig.
volume of A =
= 26•5 cm.'
Volume of cylindrical part B
4{(3)2X4
= 28•26 cm.'
Total volume = 2A+B
81•26 cm.'
81•26x8
Weight of one rivet 0•65 kg.
No. of rivets which can be manufactured from 4 kg. M.S. (Neglecting
wastage)
— 6 (say)
MBCRANICAL STIMATINO
0650
6 rivets.
62 ANDICOSTINQ
Volume of A
7 — 6
cm.'
Volume of C Z
Volume cm.'
— 4
of D
Volume of E =
416
Volume
of F
Total
volume —
ETIMATrON OF
— 17•2 cm.' Ans.
Hence, weight of 10 such
articles
lox
17•2x8
1000
1•376 kg. Ans.
= = 0•7854 cm.'
4
— 3•667 cm.'
Volume
of E
— 0•343 cm.'
Total volume = volume of A+volume of
B+volume of.
C+volume of D+volume of
E
= 11•8354 cm.'
Weight of material/shaft
— 11•8354X8 gm.
— 94•6832
ETIMATrON OF
costN0
= 9•47 kg.
. Cost of material
— 9•47x1
Rs. 9•47. Ans.
•Then 127•4
127•4x4
18
Imgth of bar required 18 Ans.
MECHANICAL ESTIMATING AND
MATn1AL COST 65
6-
5cm.
loan.
B
4 307.
Fig.
Solution. up the component into simple parts A,
B, C and D.
(20+10)
Volume of trapezium A = 2 525 cm.'
12+10
Volume of trapezium B = -2 —x3x3 5 —• 115•5 cm.a
arei cm
Aldimensions
Fig5•10
Solution. As crank shaft is similar in
dimensions on both the side of line XY. Therefore
volume on one side can be calculated and the total
volume will be twice of that on one side.
Breaking the drawing into simple parts A, B, C, D
and E.
MATERIAL COST 67
Fig. 5•11
(c) Volume of hollow portion
1287 cm.a
4
(d) Volume of 2 bolt holes (D)
4
(e) Volume of triangular portion MNO by
Guldinus Rule.
— Circumference through C.G. x
Area of triangle MNO
ETIMATrON OF
(As C.G. lies at Ih from base dia. through
C.C. will be
Difference of dia.
= Innerdia+ 3
10 8 a
a
Volume of triangular 2•51rcm.
portion MNO
COSTING
Total volume of gland
= 115•49" cm.'
363 Ans.
Spokes
4 X 2
elliptical
Volume — Z = 520,
Volume of hub B — -L = cm.s
4
Vole—o of •ach arn C — Area of cross-sectionxlength of each
Fig. S•13
35 cm.a
Volume of part C = 16x2x5 — 160 cm.'
Volume of each hole D
Fig. $14
Solution. Break up the component into
simple parts A, B, C, D and E.
Volume of each part A
= Volume of semi-circular
part+Lower rectangular
part.
= ( —d2 >4
= 146•24 cm.a
Volume of = = 192 cm.'
Volume of part C Area of trapezoidal sec.
x Length
x2x11 cm.'
Volume of each hole D
STIMATION
14•13 cm.'
—12•56)
— 531•66 cm.'
OF MA'm1AL COST 71
1000 kg.
= $00 kg. (Approx). Ans.
14. Calculate the weight of C.I. bracket
shown in the sketch $15. Assume density of C.I.
as gm./c.c.
Break up the bracket into simple
parts A, B, C and D.
Volume of part A
= Volume of semi-circular part+Volume of
rectangular part.
= { 12— x— +7x15x2
= 248•5 cm.a
Fig. 5•15
Volume of each Part B
96 MECHANICAL nTIMATING AND
Volume of semi-circular part +Volume of
rætangular part.
= { 12 +(4x10x2)
= 158•5 cm.'
= +(3x2x2)
18•28 cm.'
ESTIMATION MATERIAL
= 18•28
= 534'66 cm.a
Hence, weight of C I. bracket
534•66 x
1000
= 4 kg (nearly). Ans.
Example 15. Calculate the volume of the component shown
in Fig. $16.
lcm.4WLE 207' R c
A Pcm.
E
tcm.•
Fig. 5•16
x4xo•5
= 1314 cm.8
Volume of base B = 12x6xl = 72 cm.'
Volume ofeach hole C = = O•4cm'. , nearly 4
98 MECHANICAL AND COSTING
Volume of each hole D
4
= cm.' (nearly).
Total volume =
OF COST 73.
Volume of each
part A =
32"
4
=
Volume of each part B
4 —
9R
Volume of part C 4
= 237•6 cm.a
237•6 x
Weight of bush =
1000
= 1•97 kg.
Hence, weight of material required for 20
bushes
1•97 x20x (considering
loss) = 43•34 kg.
Material cost = 43•34 x 10
Rs. 433•40. Ans.
5tm.
2-5cm.
Fig. 5•18
Example 18. Calculate the weight of C.I. pedestal shown ,below.
Assume the density of C.I. as gm./c.c. [Fig. $20].
Solution. Break up the component into simple parts A, B, C, -D, E
and F as shown in Fig. $17.
Volume of part A = where XX = W3 as
explained in Fig. $19.
= 169•5 cm.a
Volume of part B — XXx height x 7 =
4v'3x1x7
— 48•5 cm.a
•Volume ofeach fillet C =
— 0•215
= 2008 cm.'
op cosr
ESTIMATION MATERIAL
Fig. 5•19 From this
figure
= 20 xx =
Volume of hollow cylindrical part D
„x1Xix3 —4•71
ESTIMATING
PLAN g•CTnM
Fig5•21
.
Solution. Break up the drawing into simple parts A, B and C,
Volume of rim A = x 15
= 7665" cm.8
Of hub x 25
= 7817 cm. a
Volume of part B =
= 0'39 cm.'
Fig. 5•22
cm., h 1 cm.,
where RI = cm., =
Volume of D = 2 x 1
28•55 cm.'
Volume of spherical portion E
where,
— 7•18 h = (8—00 =
= 0•82 cm.
Volume of E =
3
= 16 cm.8 (nearly)
Area of filletF= 0•215 =
= 0•86 cm.2
Peripheral length of fillet F (By
Guldinus Rule)
27tx,
where x = distance of C.G. of fillet from XX
axis . . Volume offillet F = = $10 cm.'
Total volume — A+B+C+D+E+F
= 63•17 cm.a
Volume of 100 such valves
63•17x 100 = 6317 cm.a
Weight of 100 such valves
— 50•54kg.
Ans.
1000
Example 21. Calculaje the weight of 50 metres of a
steel' chain, one link of which is shown in the Fig. 5•23.
Assume weight of steel rod of I cm. dia. as gm./cm.
length.
OF MATERIAL
RAN Solution.
Effective length of
the link is the inner
length which
determines the
length of chain and is
equal to 10—2 (dia.
of steel rod).
= — 8cm.
No, of such links required for
50 m. chain
50 x 100
— 625
Fig. $23 8
ErlMATION cosr
Fig. 5•24
This block is like a frustum of cone
h
Volume =
here h — 20 cm.
al = rxaxb, where a and b are semi
•major and minor axes.
2 2
— 31•4
cm.2
6 3
Similariy
14
cm.a
: ESTIMATING
COSTING
=
442 cm. a
Wt. cf
M.S. block
3536 gm.
OF MATERIAL
= 3536 kg. Ans.
Example 23. Find out the weight
of the overhung crank as shown in
the Fig. $25, if the weight of
steel is gm./cma. All s dimensions
are in cm.
Fig. 5•25
Total volume
of overhung
crank
= Volume of
A+volume of
B+volumc
Volume of A
= 3
104cm. 3
7
OF MATERIAL OOST
STIMArION
—Xlx5—2x2x72
3
— 90-334—7
= 79•66 cm.'
vol. of c = of keyway
500 cm.
Total
•volume —
104+79•66+500 —
68366 cm.8
Weight = 683 gm. =
533 kg. Ans.
Example 24. It is proposed to provide an angle Iron frame around
an opening 450 mm. square and cover the opening by a chequered
plaìe 6 mm. thick as shown in Fig $25. Find out the weight of steel used
if angle iron 75 mm. x 7 mm. mm. weighs as 7 kg. per metre, bar 25
mm x6 mm. weighs kg/metre, chequered plate 6 mm. thick weighs 60
kg./square metre and bar 12 mm. dia. weighs 1 kg. per metre. (B.T.E.
Punjab) Solution.
(a) Length of angle iron 75 mm. X 75 mm. X 6 mm = 0<450 mm—1800 mm,
— metre.
CENTE
Rtnn,w
xwmr
Fig.$26
IS
(d) length bar 12 mm. diL of
Weight Of bar
steel used
—rtMATION op 83
Unsolved Problems
Fig. $27
Fig. $28
Fig. 929
7. Assume density of cast steel as gmlc.c. Estimate
the weight of the casting shown in Fig. $30. 3 13 kg.)
112 MECHANICAL AND
Fiø. $30
8. Fig. $31 shows an ink blotting block of aluminium or
density $8 gm./c.c. Find the weight of biock. (Ans. 1•65 kg)
Fig.
COST
Fig. $32
•Fig. $33
114 MECHANICAL AND
Fig. $34
6
ESTIMATION IN MACHINE SHOP
Procedure
For estimation purposes, machining cost is calculated after finding
the material cost. Michining is done, to get the exact size and shape of
the product on castings, on forgings and oa bar stocks etc.
We shall' discuss in the chapter on 'Estimún of castings' that
certain amount of material is included as machining, allowance. For this
purpose, we took slightly bigger dimensions than that from finished
drawings on the sides which are to be machined.
Generally following different operations are performed in the
machine shop, on different machines
(I) Turning, (2) Knurling, (3) Facing, (4) Drilling, (5) Boring (6)
Reaming, (7) Threading, .(8) Tapping (9) Milling; (10) Grinding, (Il)
Shaping, (12) Planing.
In estimating, our aim is to find out the time, which a labour ukes
for perfõrming the machining operation, for calculating their wages. In
addition to this machining time (also known as operation time),
following time considerations are taken :
(i) Setting up the job.
(it) Setting up the tool or cutters.
(lii) Inspection ofjob.
(b') Fatigue allowance.
In the study of the machining operation time tams are Fnerally
used :
(a) Catting Speed. It is the distance at which tool along the
material in minute. Its unit is
14t us consider an example, in which a job of D cm. die.
rwolving at a speed of N r.p.m. Then, distanoetravelled by the
87
116 AND COSTING
bŒCBANtCAL
LATHE OPERATIONS
Now we shall discuss about the estimation on operations to be
performed on lathe.
l. It is the operationof metal removal in which job is rot+ted
against a tool.
S Cutting sped in m./min. D Dia. of
job to iurncd in cm. N Rev.
AND COSTING
MECHANICAL ESTIMATINC and
Feed/rev. m./min.
F
100
"D r.p.m.
As we know that feed/min.
— r.p.m. x feed/rev.
and. Time taken to turn unit length
1
Feed/min
Time taken to turn L metre length
Feed rev.xr.p.m.
Hence Length of the job to be turned
Feed/rev. x r.p.m.
min.
where S = 30 m./min.
318 r.p.m,
AB 267b
or AB = x V2
= 0•707 cm.
Now, Time for chamfering,
Fi
Length of cut
Feed xr.p.m.
FxN
0•707
min.
= 0•07 minute
= $2 seconds.
Example 3. Estimate the total time taken to turn
a 10 cm. long 2 5 cm diameter m.s. rod to a
diameter of cm. in a single cut. Assuming cutting
speed to be 25 m/min, feed to be mmf rev. and the
mounting time in a shelf centring 3 jaw chuck to-be
40 seconds. Neglect time taken for setting up tools
etc.
(B.T.E., Rajasthan Ñov. 1969,
Solution. Here L = 10 cm.
S 25 m/min.
F — 0•01 cm/rev.
As
100x25
318 r.p.m.
AND COSTING
10
3•14 min.
Now, it is Sven that job mounting time is 40
92 MECHANICAL BSruATINO
215
Ti — min.
Second step.
IN SHOP
Reducing the diameter from 54 mm. to 42
mm, by turning. As depth of cut is 3 mm.,
therefore
54—42
2 will be the number of
cuts.
6
1st
100 s
118 r.p.m.
= 0'8 min.
STD'ATION MACHINB 93
2nd Cut
100 s
100x20
= 132•7 r.p.m.
115
132•7 —
min.
Total turning time
32 minute. Ans.
Example 5. What do you mean by step turning? Calculate the
time required to turn a stepped shaft of the dimensions shown in Fig.
trom m s. stock of approximate length and 4 cm. diaDeter. Neglect
facing and setting up time The depth of cut should not exceed 0•25
cm. Assume the cutting speed to be 20 mtmin. and feed to be 0 3
mm/rev. for each cut. (B.T.E., Rqjasthan, May 1967)
41
Fig.
AND COSTING
' All dimensions are in cm.
Solution. First Step.
Reducing the diameter from 4 cm to 35 cm. for a length or 9 cm.
in single cut as depth of cut is 0•25 cm.
159•2
r.p.m.
1 "rev. x r p.m.
9 003 •
159•2 1 9
min.
Second step.
Reducing the diameter from 35 cm to 3 cm. for a length or
5 cm. in single cut as depth of cut is 0 25 cm.
100 s
182 r.p.m.
AND
94 ESTIMATING cosrmo
5 min.
0 03 x 182
Total turning time
= minute. Ans.
6. A circular aluminium rod is to be
reduced from 5 cm. to 4 cm. for a length of 8
cm. in two cuts. Assuming cutting speed as 300
m./min. and feed as 001 cm./rev., estimate the
time required for turning.
Solution. As we are requited to turn the above
rod in cuts, therefore considering first cut
100 s As
FxN
8
0•42 min.
6000
o•ol x
Now considering second cut,
As diam•ter is to be reduced by I cm. in
two cuts, therefore after first cut dia. will
be cm.
Speed of rod for second cut,
WD
•S — 300 m./min. D =
4-5 cm.
2120 r.p.m.
min.
where. L = 5 cm. ; F = 0•02 cm.
and 100 s
IOOx30
— 240 r.p.m.
5
— 1•04
0•02x240
Sept. Ill. Turning time required for reducing the dia. from.
4 cm. to cm. for remaining length,
min.
10
= 2•08 min.'
002 X 240 Total
time required
IN SHOP
1+1 •04+2 08
= 4•12 min. Ans.
2. Knurling is the process used for making: diamond
shaped impressions on the surface of a component to pro. due a rough
surface to facilitate easy grip. This is done with the helpa knurling tool
also known as knurl. This process is performed on a lathe machine.
Time required for knurling operation be cdculated by;the same
formula as that for turning.
i.e. fine for for knurling
100 s
As N
2cm.3
S 20 m./min.
D 3 cm. 2c 6cm.
n
IOOx20 Fig. $4 —
212 r.p.m.
Now, as,
Length of cut 6 cm.
Feed : 0 03 cm./rev.
Length of cut
2 cm.
-2-
Feed/rev. 0•03
cm.lrev. and N 100
r.p.n.
*TIMATION IN SHOP 129
MACHINE
Solution. In
this case drilling wilj -r
be done in two steps.
cm.
Step 1. Drilling the hole with 1 —L drill
for depth of 7 cm.
Time — Depth of hole
Feed/rev. X r.p.m.
where, Depth of hole cm.
Feedlrev. = 0•02 cm.lrev.
100 s 100x22
r.p.m. Ni — 700 r.p.m.
7
= 0 5 min.
Step 11. Now drilling the hole with 2 cm. drill up to 2 depth.
100
In this case, Na = = 350 r.p.m.
Depth of hole
Time
Feed/rev. x r.p.m.
= 2 = 0 29 min. o•02x350 7
Total time for drilling T = TI+T,
and
Time T
soo
0 03 x
the 13. A hollow spindle is bored to enlarge its hole
C02
diameter from 2 cm. to cm. upto 10 cm. depth in single cut.
1. Aluminium 4
2. Brass 3
3. Copper 5
4. Cast rron 6
5. Mild steel 7
2min./cut
Pitch x r.p.m. where,
L — Length of threaded portion D =
Dia. of tap used
The above formula gives the time required to push the tap
inside the job. Time for returning the tap is taken at of the time
required for pushing it in the job. Therefore, total time for cutting
threads
Pitch X r.p.m.
Example 14. Estimate the time required for cutting 3 mm.
pitch threads on a mild steel bar of cm. dia. and 8 cm. long.
Assume the cutting speed for threading as 15 m./min.
Solution. As, Pitch = 3 mm. = cm,
Bar dia. D = cm. Length L
— 8 cm.
Cutting speed S = 15 m/min.
r.p.m.
Pitch
136 nCHANICAL AND
Cutting speed S = Il
m./min.
for
= 1000 r.p.m.
xN
and time required
10
min.
To cut the threads upto full depth in
aluminium 4 cuts are required. Hence total
time required, will be
= O•2x4 08 min. Ans.
Example 17. Estimate the time required
for tapping a 2 cm. dia. hole with a 3 mm. pitch tap, in a
mild steel plate up to a depth of 3 cm. Assume cutting
speed as 10 m./min. and also assume that
return speed of tap is 2 times the cutting
speed.
Solution. As,
100 s
Speed of rotation N =
where, Cutting speed S = 10 m./min.
Hole dia. D 2 cm.
100 x 10
= 159 r.p.m.
D
Time for
Here4 cm.
Pitch = 03 cm.
Pitch
EIIMATION IN MAC.BINB SHOP 137
4
Tapping time/cut = = 0•08 min. o•3x
159
0•08
Time for return = i x
tapping min. min.
Time/cut = Ti+Ts =
This the time for one cut, but for
getting threads up to full depth, let the
total cuts required be 6. Then the total
time required for tapping = = 012 min. Ans.
Example 18. Estimate the time required
for internal thread• ing on a mild steel nut
of 2 cm. bore dia. and 2 cm. length. Pitch
of the thread is mm. Assume cutting speed as
12 m./min. Also consider approach and
Solution. As we know that,
for threading/cut=
Pitch X r.p m.
Let approach and overtravel be cm. each
Pitch
138 nCHANICAL AND
10 cm long. Calculate time required for this,
assuming the speed of thread cutting to be 33
m/min. and no. of cuts taken to be 4.
(B.T.E., Rajasthan 1969)
Solution. Time for threading,
L+O•7
X No. of
cuts/minute Pitch x
r.p.m.
Here L = 10 cm
1
Pitch —
4
threads/cm. = 0•25
cm. No of cuts — 4.
100 s
R.P.M., N =
100x33
= 350 r.p.m.
(10+0•7)
20. An operator is required to
diamete
cut 2 threads/cm OD a job for
a length of 9 cm. This work is to be done on
a lathe with a tool. The lathe spindle is
turning at 45 r.p.m. and 10 cuts are
required to complete the thread. How much
time will be to cut the threads ? (B.T.E.,
Rajasthan Nov. 1970)
L+O•7
min/cut X No. of
cuts
Pitchxr p.m.
L 9 cm.
Pitch
EIIMATION IN MAC.BINB SHOP 139
R.P.M. = 45
No. of cuts = 10
940•7
x 10
= minutes. Ans.
Some Advanced Problems
Example 21. The comparative tooling up time and turning
time for a particular job when made on ordinary lathe and
automatic lathe respectively is as follows :
Machine Tooling up time Turning Time
Ordinary Lathe 20 minute 15 minute
Automatic Lathe 120 minute 3 minute
Determine the number of pieces of job for which it would be more
economical to use the automatic lathe instead of the ordinary lathe.
( B.T.E., Rajasthan, Nov. 1969). Solution. (i) Total time-for the
completion of one job = 20+15 = 35 minutes.
(ii) On Automatic Lathe. Tooling up time is 120 minutes and'
Turning time is 3 minutes. On automatic lathe tooling up is done
only once, after this a large number of pieces at the rate of one
piece in every 3 minutes can be produced.
Minimum pieces to be manufactured on automatic lathe
Total time on ordinary lathe/job
Turning time on automatic lathe/job.
35
-3
= 1 1•66. Say 12 pieces. Ans.
Example 22. In a C.I. component a 35 mm cored hole, an internal
relief is to be provided over a length of 15 ) mm. Determine the total time
to machine the bore (in two passes) and turning the relief (in one cut) in
the component. Cutting speed is 15 m/min. and a feed of 0•10 mm/rev.
(Fig. 6•8).
(B.T.E., Rajasthan May 1970)
First Step.
Enlarging (boring) the dia. from 35 mm. to 40
for a length of 200 mm.
MECHANICAL AND
Fig
ESTIMATING costma
100 s
Here
100x15
— 136•4 r.p.m.
Time for enlarging the dia. from 35 mm.
to 40 mm. for a flength of 200 mm. in two
cuts
20•o
0•01 X 136
4 — 14•7 Min.
Second Step.
Time for providing a relief for a length
of 150 mm. in one cut
100 xs
= 119•4 r.p.m.
15•0
001 x 119•4
= 12•5 min.
Total time, T =
= 27 2 minutes. Ans.
Example 23. Find the time taken to
prepare a job accordin tto the dimensions
shown in Fig. 6 9 from a bar 35 cm diameter
an cm. long. Assume following data :
IN MACHINE SHOP 141
(1) Cutting speed for turning and
boring = 20 m/min.
(2) Cutting speed for drilling
= 30 m/min.
(3) Feed for turning and boring
= mm/rev.
(4) Feed for drilling = 0 23 mm/rev.
(5) Depth of cut not to e¥ceed
= 3 mm.
(B.T.E., Rajasthan, May 1972)
'ESTIMATION
First Step.
Solution. In this problem the dia. of bar stock is 35 cm. First
lit has to be reduced to 3 cm. by turning in single cut as depth of
cut is 3 mm.
Here DI = cm.
S = 20 m/min.
002 cm./rev.
100 s,
182 r.p.m.
Length of cut
1 Feed/rev. x r.p.m.
6
= min. 1
0•02 x 182
Second Step.
Drilling hole of 2 cm. diameter to a length of 6 cm.
MECHANICAL AND
Time for Drilling,
Length to be drilled Feed/rev.
X r.p.m.
100 sa
Here
3rd Step.
Enlarging a hole from 2 cm diameter to cm. diameter for a length
of 2 cm.
100 s,
7
— 318 r.p.m.
FxNi
100
0'53 min.
Similarly
100
IOOx30 Ix
MECHANICAL AND COSTING,
.x4•S
:BSTIMRTION
Second Step.
Reducing the dia. from 40 mm. to 30 mm. for a length of 80 mm. in two
cuts. As depth of cut is mm. Therefore no. of cuts
40-30
25x2
80
—— for Ist cut
100x30 1x
80 X X 4
= 0•33 minute
100x3
80
= 0 31 minute
3rd Step.
Reducing the dia. from 30 mm. to 25 mm. for a length Of 50 mm.
in single cut.
Fxr.p.m.
50
=
4th Step.
Drilling for a length Of 30 mm and dia. 10 mm.
30
= 0•157 min.
10,) x 30
o•2x
Sth Step.
Threading for a length of 30 mm. dia. 10 mm. pitch 2 mm.
Let No. of cuts 7
IN MACHINE SHOP 145
30
100x9
20 x
= 0•36 min.
6th Step
Threading for a lcngth of 40 mm, dia. 25 mm pitch 3 mm. Let
no. of cuts = 7.
40
„x2•5
= 081 min.
Fig. 6-11
This uestion is solved in the following
steps.
Step . Turning the job from 30 mm. dia. to required'
size :
(i) First the job is turned from 30 mm. to
25 mm. for the 200' mm. lengtb.
= 0•21 min.
(Il) Now the dia. is reduced from 25 mm. to 20 mm. for length of
(considering, that mm. length will be redu-
ced in facing on each side).
3600-
Time required, t, =
= 0•14 min.
(iii) Now the dia. is reduced from 20 mm. to 10 mm. in cute
for a length of 25 mm., assuming that each cut takes same time-
25
Time required, ta =
. Turning time —
O'
Step n. Facing. =
(t) First of all facing is done on 25 mm. dia, on one end.
25 Time =
Length Feedlrev. for X facir.p.m.ng
— 0•032 min.
STIMATION IN MACHINE SHOP
111/
Ix
Total facingltime, T,
tl+t' = 0•053 min.
Step Ill. Knurling.
Cutting speed during knurling is assumed to be same as that for
turning.
Length for knurling 40
Time, Ta =
Feed/rev. xr.p.m. 100 x 30
„•x2•5
0034 min.
Step IV. Threading.
Threading time for one cut
Length for threadin
Pitch X r.p.m.
130
0•28 min.
100 x 10
Let 4 cuts be required to get full threads, then Total
time T, — o•28x4 — 1•12 min.
Total machining time required for the component, T =
Tl+T,+Ta+T,
Ix
(assuming feed as I mm./rev.) 0•24
mm.
•112 BSr1MATING
= 0•064 min.
r X 35
(ii) Time required for turning to reduce
the dia. from 35 mm. to 25 mm. in 2 cuts for a
length of 60 mm. and assuming that each
. cut requires same time,
60
X
rx3•5 0•22 min.
Total time for turning T,
= t1+t2 = = 0•284 min.
step 111. Facing.
(i) Facing time required for facing on 30
mm. dia. side, assumng feed as mm./rev. is
30—15
= 0•04 min.
STIMATION IN MACHINE SHOP
(ii) Facing time required for facing on 25 mm.
dia. side
ts 1— 0•02 min.
Total facing time
Ta = = 006 min.
Step. IV. Boring. Time required for enlarging
the hole from mm. to 20 mm. for a length of 15
mm.
15
- = 0•012 min.
Total time required
T = Tl+T2+T8TT,
Machining
o•2x
STIMATION IN MACHINE SHOP
BTIMATING
—0•088 min.
Step IV. Turning.
(t) Time required to reduce the dia. from 5 cm. to 46 cm. for
cm. length,
= 0•30 min.
(ii) Time required for reducing the dia. from cm. to 3
cm. in 3 cuts and for a length of 6 cm.
6x3
o•2x
Total turning time T, = tl+ta-= = 0•95 min.
Total machining time T = Tl+Ta+Ta+T,
= min. Ans.
Example 29. A manufacturer desires to manufacture 100
bolts/day from mild steel bars of length 2 m. and dia. as 25 mm.
Assume :
(t) Feed for turning cm./rev.
(ii) Cutting speed foriturning = 20 m./min.
(iii) Cutting speed for threading = 10 m./min.
(iv) Depth of cut = maximum of 3 mm.
(v) Pitch for threads mm.
(vi) No. of cuts required for threading = 6.
Calculate the machining time for 100 bolts, if the operator is
paid at the rate of Rs. I •251hr. Estimate the laboor charges,
considering other allowances for fatigue etc. as 100%.
Solution.
Step
I.
*cm.
Turning
152 MECHANICAL AND COSTINO
(i) Reducing the dia. from 25 mm. to 20 mm. for a length of 10 cm.
Turning time
Fig. 6•1S
Length
Feed/rcv. x r.p.m.
10
O•2min.
100x20
o•2x
(10 Reducing the dia. from 20 mm. to 12 mm. in two cuts a
length of 9 cm.
us
Time required in first cut to reduce the dia. from 20 mm. to
16 mm.
9
0•15 min.
And time required in second cut 9 ioo— x20=
0•12 min. o•2x—
Total turning time
0 47 min.
Step Il. Threading.
Threading time for one cut
Length
Pitch x r.p.m.
30
= 0045 min.
100 x 10
2•5x—
Total threading time for 6 cuts
= 0 045 X 6 = 027 min.
Total machining time
= 047+0•27 = 074 min.
Time required for 100 bolts
STIMATION IN MACHINE SHOP
= 070<100 = 74 min. Ans.
By considering allowances as 100%
Time taken by operator= 74><2
= 148 min. = 2-46 hrs.
Labour cost — 2•46 x 1 •25
Rs. 3 08. Ans.
Example 30. Estimate total cost of gun metal component as shown
in Fig. 6•16. If material lost in machining is 20% of the weight Of
component, then find out the weight of gun metal required. Assume—
density of gun metal as 8 gm.lc.c., cost of gun-metal is Rs. 15/kg.,
machining charges are 10 paise per 10 sq. cm. of finished surface and
total overhead charges are 100/0 of the material
cost. Solution.
Material Cost
Fig. 6•17
Solution. (i) Turnlng andfacing charges :
(a) Turning area of the portion where theading is done Al =
RX l•5X5 7•5" sq.
(b) Turning area of the collar,
As TX2•5X2 sq. cm.
IN MACHINE SHOP
mtMATION 117
1•56r
sq
4
Total @ Re.0•02/
charges
facing turning and
sq,
— Re. 080.
(iv) Material cost/piece,
C, = Re. 0 20
(given) Total cost of one
spindle
0•89+0
= Rs. 2•14.
Cost of 1000 spindles
= 2•14x1000
= Rs.2140. Ans.
Example 32. Estimate the manufacturing
cost of 100 pieces of a component shown in
Fig. 6•18. These components are to be made
from a cm. mild steel stock. Assume the
following data :
(t) Density of material = 8 gm./ç.c.
(ti) Material cost
156 MECHANICAL AND COSTINO
(iii) Parting off and facing allowance/piece
= 1 cm.
(ip) Cost of machining = 2 paise/cu cm. of
material removed (y) Overhead charges = 500/0
of labour cost.
fig. '18
Solution. Material
Length of stock required/piece
6+2+2+1
— Il cm. (considering I cm. as parting allowance)
Volume of material required/piece
106 cm.'
X (3)2 X 6
= Rg. .3•40
tomm zomm
Fig. 6•19
Solution.
Step 1. Turning.
Reducing the diameter from 30 mm. to 25 mm.
in two cuts, as the depth of cut is 1 •5 mm. In
first cut the diameter will be reduced to
27 mm. and in second cut the diameter
min.
158 MECHANICAL AND COSTINO
will be reduced to (27—2 x l) = 25 mm. This
being the finishing cut, depth of cut can be
taken as I mm.
100
s
r.p.
0•673min.
50x2•7
o•35x2000
MECHANICAL BSTIMATING AND
lio cosr2i0
Step 2. Facing.
Facing of the face of 25 mm. dia.
Length to be
faced Feed x
r.p m. = Length
to be faced
12•5 mm.
Feed x r p.m.
rxdiaofdri
1
2000
25
=
0•717 min.
2000
o•06x —
Step 4. Turning.
To reduce the diameter, from 25 mm. to
20 mm. for a length of 15 mm. in 2 cuts.
min.
160 MECHANICAL BSTIRATING AND
Length of cut reducing dia.
to 22 mm. Feed x r.p.m.
Here 1
1 — 0•18 min.
035 x 800
„x2
reducing dia.
to 20 mm o•35x
= 0•157
o•15x
20
10
— 0•227 min.
Hence total Machining Time
= TI+T,+...... I T'
30
min.
162 MECHANICAL BSTIRATING AND
(v) The sum of approach length and over-run is called Added Table
Travel.
Operations performed on the milling machines are mainly .cutting
and facing. The time taken for performing these operations , can be
obtained by using the same formula, i.e. Length of cut
Time required/cut =
Feed/rev. x r.p.m.
Approach length AB
— v' Dd—d'
In these operations over-travel is generally taken as 5 mm.
IN MACHINE SHOP
123
Fig. 6•20
(b) Facing Operation
• (i) If the cutter dia. D is less than the width of the job 'w'
then several cuts are required to face the width w. Fig. 6•21 shows
the first and last position of the facing cutter.
Fig. 6•21
In this case approach is generally taken as D and over• travel
as 7 mm.
(ii) If the cutter dia. D is bigger than the width of the job w,
facing is done only in one cut.
Fig. 6•22 shows how the facing is done when the cutter dia.
ia greater than the width of the job. In this case over-travel is
Fig. 6•22
EC — OC—OE
164 MECHANICAL ESTIMATING
Over-travel
cosme
ÿ. Estimate the time required to prepare a square prism
on a milling machine from a round block 90 mm. length, 40 mm. in
diameter, feed 25 mm./minute and set up and indexing time is 15
minutes. Solution.
Here, length of cut = 90 mm.
Feed = 25 mm/mir.
Let added table travel
10 mm.
90+10
1 25 where 4 is the sides of
square prism i.e. No. of Indexing
16 minute
Here set up and indexing time,
T, = 15 min.
Total time of milling, T
= Tl+Ts
= 16+15
= 31 minute. Ans.
Exam* 36. Estimate the milling time to cut 60 teeth on a Gear
blank 60 mm thick, feed 35 mm/minute and take overall set up üme as 10
minutes. Solution.
Length of cut x No. of Index+set up
Feed/minute time.
= 3•14 cm.
Total table travel— 10+3•14
= 1314 cm.
13•14
Time taken/cut = ————
2 19 min.
120
Total time taken in two cuts
= = $38 min. Ans.
Example 38. A 20 x 5 cm. C.I. surface is to be faced on
milling a cutter having a dia. of 10 cm. and 16 teeths.
if the cutting speed and feed are 50 m/min. and 5 cm./min.
respectively, determine the milling time, r.p.m. of the cutter and
feed per tooth.
Solution. As the dia. of the cutter is larger than the width
the surface, hence only one pass is sufficient.
100x50
159. Ans.
As Feed/min. 5 cm.
Feed/ nin. 5
Feed/rev. = 159
r.p.m.
167 MECHANICAL ESTIMATING AND COSTING
Feed/rev. 5
-WHæ
WORK WORK
(a) (b)
Fig. 6•23
(b) Cylindrical Grinding. As the name suggests, the
process is used for grinding the internal and external surfaces of the
cylindrical jobs which have previously been turned on the lathe, to get
accurate size and smooth finish.
Time required for cylindrical grinding/cut
Length of cut
Feed/rev. x r p.m.
where Length of cut = Length of job+Over-travel
— L+O•5 cm.
2
But, Depth of one cut is 0•25 mm.
No. of cuts required o•1x10
4 cuts
0•25
Length of cut
AsTime/cut =
Feed/rev. X r.p.m.
where
Length of cut — 15+0•5 = 15•5 cm. (assuming cm.
over-travel)'
roughing)
Feedlrev. =
=
and r.p.m. = = 120.
15•5 0•13
Time required/cut min.
Ixi20
Total time required for 4 cuts
= 0•13 X min. Ans.
Example 40. Top of a C.I. table of size 30 cm. X 80 cm. is
to. be grounded by a wheel having 2 cm. face width. If the feed is
ith of the width of the wheel and table moves 8 m. in one minute
find out the time required for grinding in two cuts.
Solution. Time required/stroke
Length of table
STIMATION IN MACHINE SHOP 169
Speed of table
80 1
8x100= 10
Width of wheel
As Feed
0'5 cm.
Width of table
No. of strokes
60
08
As, Time required/cut
= Time/StrokexNo. of
strokes 1
= —X 60 = 6 min. 10
Time required for 2 cuts
= 12 min. Ans.
SHAPING AND PLANING
These operations are carried out on reciprocating
machines. ron these maahines cutting is done in one stroke and
the second is the idle stroke which is also known as return stroke.
To reduce, the total time, the time required for idle stroke
is reduced by increasing the speed of Idle stroke.
Shaping operation. If a shaper bas a length of stroke as .S
cm. and it has N cutting strokes per min., then its effective speed,
E x N m/min.
100
For example, a shaper makes 30 cutting strokes per minute each
20 cm. long. Then effective speed (E) will be
20
= x 30 — 6 m/min.
100
Speed ram during cutting stroke is known as cutting •speed,
this SDeed is maximum at the middle of the stroke and minimum
MECHANICAL ESTIMATING AND COSTING
at the beginning and at the end of the stroke. Therefore, for
calculation purposes an average cutting speed C is considered.
Mostly cutting time is Ith of the total time. Therefore, the
effective speed is Ith of the cutting speed C.
Hence,
5
but, ro
o
NS
3
100 x 3 c 60 —I'strokes/m sc
in.
In the above formulae, S is generally taken as (L+5) cm.,
•where L is the length of the job.
If F is the feed/stroke in cm. then. area swept by the tool/stroke
60C
60 CF
If the width of the job is B cm. then
the width for calculations is:taken as
(B+2•5) cm.
Therefore, time required for shaping —Total
area to be swo! Area swept:min.
min.
60 CF
Planing operations. The effective speed of
the planing •machine is generally Ith of the
cutting speed. For time calcula• tion, stroke
length is taken as (L+25) cm., while width is
taken as '(B-+5) cm.
Similar to that in shaping,
STIMATION IN MACHINE SHOP 171
Time required in planing
7
5
s
Area swept/min. = N x Fx£
75C
o K = —xFxS
r
s
or K = 75CF ...
(2)
Time taken min.
75CF
Example 41. A.C.I. rectangular block of
10 cm. X 3 cm. is required to be shaped to
reduce the thickness from cm. to 1 •3 cm. in
one cut. Determine the time required for
shaping, if cutting speed is 20 m/min and
feed is mm/stroke and the cutting time ratio
is
Solution. S = L+5 = 10+5 15 cm.
Width = (B+2•5) — 3+25 5•scm.
NS
100 5
100 3
20
= 80 r.p.m.
15
Swept area/min. = NxFxS
MECHANICAL ESTIMATING AND COSTING
X x 15
10
24 cm'/min.
173 MECHANICAL AND COSTINO
344
Ans.
42. Find out the time required For shaping a block of 30
cm. x 15 cm. size in two cuts. Assume feed as and cutting speed
as 15 m/min.
Solution. As we kno.•v that,
60x 15 xo•06
35 x 17•5
= 11•3 min./cut
Time required for 2 cut = 22•6 min. Ans.
43. A machine bed is to be planed in two cuts on
planing machine. If it takes 10 seconds in forward stroke and 4 seconds
in return stroke, find out the time required to planeithe bea of width 60
cm. Assume the feed as 2 mm./stroke.
Solution. Width 10 be moved by the tool
— Width of job-I-Tool clearance —
60+5 = 65 cm.
75 CF
—rlMATION
where
100 cm.
20 cm.
10 m Imin.
cm./stroke
75x 10xu 10
125 x 25
= 41•66 m!n. Ans.
75
UNSOLVED PROBLEMS
5•5 .0
0
All dimensions in
cm. Fig. 6•27
16. Estimate the manufacturing cost of
the component shown in Fig. $28. Assume 15% of
the material is lost in machining, machining cost
178 nCHANICAL AND
2 paise per sq. cm. and the cost of material as
Rs. 1•50 per kg. Density of mild steel 8 gmlc.c.
Fig. 6•28
17. Estimate the time for tapping a hole
with 2•54 cm. dia. tap to a length of 2•54 cm. in
mild steel plate, if for return stroke speed is
times the cutting stroke speed, which is 8
m./min.
[Ans. 12 sec.)
ESTIMATING COSTING
Fig.
(y) Raising. It is the process of beating the metal over spherical
head. This process gives a convex shape to the sheet metal. This process
should be done on the sheets, having more than 20' gauge.
Allowance for raising =
(vi) Planishing. This is the process, which gives the final finish to
the hollow or raised surfaces by removing miner bends. This is carried
out by beating the sheet with the help of planishing hammer. Planishing
hammer is a short hammer and has high polish.
(yii) Edge stiffening. For edge stiffening following are the important
ways :
(a) Wiring. In this process, a wire is inserted at the edge of sheet
metal*articles. This wire adds in the stiffness of edges. Generally, wires
used for the Black. Tin plated and G.l. sheets are of mild steel, copper
and G.(. respectively.
Allowance for X dia. of wire+4 X thickness of sheet. (b)
False Wiring. This process is done as that in Wiring process but in the
end wire is taken out so its
appearance is just like that as
it has been wired and therefore
known as False Wiring. In this
process strength will be
weaker as compared to
wiring process.
Allowance = 2'5 X dia. of wire+4 X
thickness of sheet.
(c) Hemming. In this process, edges of sheet is folded when,
folding is done once as shown in Fig. 7•2, it is called single hemming.
'The allowance for it is 4—5 times the sheet thickness. When folding is
done twice at the edges to give larger strength, as shown in Fig. 7•3. it is
as double hemming. Allowance for it is 10 times the sheet thickness.
(d) Flanging. In this process, edge of the sheet is folded, at . an
angle of 900, to give the shape of flange, as shown in Fig. 7 4.
SHEET METAL JOINTS
Sheet metal joints are known as seam joints. Various joints in •
sheet metal are :
(i) Lap Joint. It is the simplest type of
joints. In this, one edge overlaps the other and than
these are either welded, rivetted or soldered.
Fig. Fig.
Blank Lay-Oats
For preparing an article lay-out is required to done on the sheet
metal as first step For this purpose an outline of the object is either
scratched on the sheet of metal directly or first drawn on a paper and later
transferred to the sheet. Sheet is cut in accordance of lay• out and then
different other operations like, forming, assenmbly etc. are performed on
it to give the required shape of the article. • At the time of lay-out
allowances must be kept for different operations like, •raising, wiring,
jointing, hemming etc.
When articles to be produced are in lot, then strips are cut
from long rolls of sheet. Width of each strip should be slightly
more then the blank, so that
(i) material can be handled easily and safely by the operators,
specially when working on the machines ;
(it) ciean blanks can be cut. The amount by which the strips must
be wider than the blank depends on ;
(i) process to be performed ;
(it) how they are to be handled, i e. manually or by
machine ;
(iii) thickness of the sheet ;
ASTIMATION IN SHOP 187
(IV) accuracy desiled. Generally the strip is kept cm. to cm.
wider than the blank. and the distance between two
consecutive blanks (known as bridge) is kept as 0•15 cm.
140
Hence, while procuring power press its crank pin dia. must be
•decided and wnich can be calculated by knowing the maximum
•shearing force required and usiBg the above relations and putting the
proper shearing stress of the material required to be used.
Shearing :stresses for the some of the metals are given hereunder :
Aluminium = 0•72 tonnes,/cma ;
Mild Steel = 3'1 tohnes/cm2 ; Alloy
steel — $7,.tonnes/cm2 ; Tin=
tonnes/cma.
Solved Problems
Example 1. We are required to make B.P. sheet containers •with
open top of size 0•25 m2 are height m. The size of B. P.
•sheet available is m x 1 m. Find out how many maximum
conttainers can be made out of it.
Solution. Size of sheet available
= m. xl m.
2-3m.
Wt. of sheet
= 113 kg.
Hence, cost of sheet @ Re. I per kg.
= = Rs. 11300.
Welding Material Cost. This cost is Rs. 2 per metre of
weld-
Therefore cost 2 x Length of weld
— x4+0•5x4) = Rs. 1200.
Total material cost = Sheet cost-I-Welding material cost = Rs.
133+Rs. 12 = Rs. 1250.
Labour Cost. It is 10% of material cost.
Labour cost =
— Rs. 12•50
Total cost of container—Total material cost+Labour cost..
= Rs. 125+Rs. 12•5
= Rs. 137•50. Ans.
Example 3. Cylindrical drums of size m. high and 1 m. mean
diameter are to be fabricated from sheet of 5 mm. thickness by
grooved seam joint and both the covers should be jointed with
ITIMATION IN 191
single seam joint. Calculate the material cost, if sheet is available @
Rs. 15 per m.'
Solution.
(a) Height. Height of cylindrical drum
Fig. 7•13
From Fig. 7•13 (b) for one tray size of sheet required is 41 cm. X
33 cm.
As one sheet has I m.. width, while width of one tray is 33 cm.
From width of sheet, 3 widths of trays can be cut and each part
will give
300
41 7 trays/length
Fig. 7•14
= 6•32 cm.
and sum of circumferences = T = 12 It
Surface area of upper part
= 119 cm.'
Similarly surface area for lower part can also be calculated,
taking two diameters for frustum of cone as 4 cm. and 1 cm.
Surface area = slant height x sum of circumferences
MECHANICAL ESTIMATINO
X (TX4+RX
20•62 cm.
and Circumference of base. Rd X 10
31•a
ESTIMATION IN SRBBr SHOP
Solution.
Pressure required to cut the rectangular blank
= Area to be sheared x shearing stress.
= (total periphery x thickness) x shearing
stress.
= 204•6 Tonnes
While, tbe• maximum pressure which this press can give
— o•75D2
= 168•75 tonnes
Hence it would not be possible to cut the blank of this size
from this press.
Example 10. For m Iking a steel component, I cm. 'thick t is
required to be bent through 900. If the inner radius is 8 em
ulate the length of the metal In the curved portion.
Soludon.
As, length of metal in bend portion
360
where.
r = Mean Radius and
generally Mean Radius
— Inner radius+O•5 thickness of sheet
360
Ans.
MECHANICAL AND COSTING,
148
Fig
l. First of all outline of the base is drawn, as shown at 'A'.
2. Then, two sides (shown by 'c') and ends (shown by 'V)
are drawn as shown jn the above Fig.
3. Lines for preparing hems are drawn as shown by 'D'.
4. Lines for preparing seams are drawn as shown by E.
5. Area to be removed is marked by hatchings.
6. The portions to be bent are indicated by In this way
blank layout is completed.
Example 12. A press making 60 strokes per min. is used for
making 30 blanks of 10 cm. X 12 cm. size from each strip.
Calculate the time required for blanking each strip if only 60% of
the strokes are uti)ised. If boles are also pierced on this press. Find
out the total time for blanking and piercing for 200 components.
for bluking.
(I) Time fŒ inserting one strip 15
sec. (it) If 60% are the effective
then, effective strcWmin.
60xo•6 36 strokes/min.
Time required for 30 blanks
— x 30 min.
36
50 sec.
STIMATION IN SHEET METAL SHOP
100
— 11•25 sec.
. Total time required for blanking one strip (30 blanks) =
86•25 sec.
Time required for blanking 200 blanks
200
30
= 575 sec. Ans.
(B) Estimation for piercing holes.
(i) Time required for loading one blank = 2 sec.
piercing „ = 2 sec. (iii) „ ejecting = 10 sec.
(assuming that it is done manually)
Total 14 sec.
Personal and fatigue time (15%)
15
14x — 100
(b) From each strip blanks of length 15 cm. will be cut. But in between two
blanks a bridge of 0•15 cm. must be provided. Hence effective length of
each blank 15•15 cm.
. No of blanks/strip
500
33.
15•15
Hence, total No. of blanks from the sheet
33 X 19
627 blanks.
Case 11. Blanks are across the length ofsheet.
Width of strip in this case
15•3 cm.
200
No. of strips 13.
15•3
BR106E ALLOWANCE
0-15
an
toacm
T
Fig.7•16
BRIDGE ÅILOWARCE rscms azscms
Isac 5
10 ms
Fig.
7•17
Effective length of each blank = 10•15 cm. A No. of
blanks/strip
49
10 15
Hence, total No. ofblanb bla•s.
Thus tbsecond case will give more No. of blanks and will be
economical.
8
ESTIMATION IN FORGING SHOP
151
152
First. Table
Time requiredfor heating the Job
Job
Medium High Tool or
W.l. C. steel C. steel H.s. steel
Second Table
Time requiredfor performipg operations
91ved Problems
radius
= 140+31
= 149•63 cm.
Fi
Therefore, length of circular rod required is
149•63 Ans.
2. We are required to prepare a hexagonal bolt
of 15 cm. dia. and 25 cm. length from a bar stock
of cm. dia. Calculate the length of the bar stock
required and also give the sequence of operations
for forging the above bolt.
Solution. (A) First, calculate length of bar
stock.
Area of hexagonal head
acm 3v/3
—a2, where a = I gth of
each side
Fig. 82 3V3
IN SHOP
2 2
= 5•85 sq. cm.
Volume of hexagonal head = AreaX
= $85x — 8•775 cm8.
Volume
Therefore, length of bar stockArea ooar
55•5
22 nearly. Ans.
(B) Sequence of operations.
(l) Estimate the length Of bar stock
required.
(2) Cut the required length of bar.
(3) Heat one ehd of bar to mab head.
ESTIMATING
3V3 of each
Volume — xa2 x(2), where a = length
side of hexagon and equal to dia. of bolt.
3v3 2
5.0
cm. 2-5cm.
= 32•5 cm.'
Length of bar *stock
required for making head. cm.
Fig.
Volume
Area of bar
32 5
— = 6•63 cm.
'•ocn
rod dia Mean dia.=lnner dia.+2X
—5+2x 6 cm.
Mean circumference = •X mean dia. cm. Assuming,
scale loss in forgoing 5 0/c.
Then — 18•84x • 0'942 cm.
100
Hence total length of I cm. rod required—
—19•782 cm.
5. A square bar of 3 cm. diameter and 25 cm length is to be
converted by hand forging into a bar of hexagonal section having each
side equal to cm. Calculate the length of hexagonal bar produced,
consider scale loss to be 7% of total.
Solution. Volume of square bar=Area of cross-section x Length
A=
Volume of A =
— 1•025
cm.'
— 663•336 cm.'
Volume
• Length of stock required = Area of stock
663•336
Fig.
Solution. Split up the drawing into simple parts A, B aid
10+8
Volume of part A = ( —2 )x 10 = 5400 cu. mm.
Volume of part B = = 2250 cu. mm.
Ix 19•625 cm.'
(v)
Sprue, let it to be
5% of net volume.
t
Sprue loss
• Gross volume —
280
178•51
Fig.
Volume
— 99•06 cm.'
18 cm.
(iv) Tong loss, taking 2 cm. extra length required for the use of
tong.
Tong loss 2x -E (4)2 = 25•12 cm.'
(v) Sprue loss, assuming it to be 5% of the volume.
Sprue loss — 0•05 = 4•98 cm.'
Total volume of material required for each component
— 155•65 cm.a
Hence, Volume required for 200 pieces
— 31130 cm.'
216 MECHANICAL
Length of bar stock required
31130
— 2478 cm.
24•78 metres
Material cost 24•78x 15 = Rs. 371•70
Forging charges = Rs. 0•01 x (surface area)
127+16+4)
Forging charges for 200 pieces
= 200X R8. 296•OO Now on-
cost is 30% of material cost.
On-cost — — Rs. 111•51.
Therefore, manufacturing cost
= Rs. 371 •70+Rs. 296•OO+Rs. 111•51 =
Rs. 779•21. Ans.
Unsolved Examples
cm.
Fig. 8-8
STIMATION IN SHOP
3. A chain link of dimensions shown in Fig. 8 8 is to be hand
forged from M.S. bar of I cm. dia. Considering all the possible losses
during forging, calculate the length of bar required/piece.
Þ.. I •09 cm.)
Fig.
4. U-shaped links are to be forged from a bar of I cm. dia.
and 5 m. length. Considering all the possible losses, estimate the
total of links, which can be produced. [Ans. 28 links.}
FORGING 163
Fig. 8•10
S. Two workers complete 20 connecting rods, each weighing
kg. by forging per day. They are paid at the rate of Rs. 6•00 and
Rs. 4 00 per day respectively. It the material cost is Rs. I •25/kg. and
600/0 of the direct labour is required to compensate for the factory
overheads, 30 0/0 administrative overheads and 40% sales overheads.
estimate the total cost of each rod. [Ans. Rs, 5•08] 6. 500 MS. bolts
shown in Fig. 8•11 are to be forged in an upsetting machine from 2 cm.
dia. rod. What should be the length of each such bolt before upsetting ?
Also calculate, length of rod required for 500 such bolts, if 5% of
the length goes to scrap. [Ans. 7•65 cm. ; 38•25 m]
218 MECHANICAL
Fig. 8•11
7. 1000 shafts as shown in Fig. 8•11 are to be drop forged
from the bar stock of 5 cm. in dia. Consider all losyes and
assuming that •
(i) Material cost is Rs. 12 per metre.
(ii) Cost of forging is Re. O•05/cm2 surface area forged.
(iii) Overheads to be 50% of material cost.
(IV) Profit 20% of the total cost.
Estimate the selling price of forged shaft. [Ans. Rs. 4•20]
Fig. 8•12
STIMATION IN WBLDNO SHOP
9
ESTIMATION IN WELDING SHOP
FILLET WELDS
Fig
GAS WELDING
In case of gas welding following two welding techniques are
adopted in practice.
(t) Leftward or Fore-hand welding.
(it) Rightward or Back-hand welding.
164
f6S
(i) Welding. In this type, welding is started from right
hand side of the joint and proceeds towards the left band,side. This
method is suitable for welding plates upto 3 mm. thickness with• out
preparation and upto 5 mm. thickness with edge preparation.
(it) Rightward Welding. In this type, welding is started from left
hand side of the joint and proceeds towards the right hand side. This
method is suitable for steel plates which are more than 5 mm.
thickness. In plates upto 8 mm. thickness, edge preparation is not
required and beyOnd 8 mm. thickness, plates should be bevelled to
about 300.
Gas welding can only be done on plates upto 25 mm. thickness.
Table I on next page is useful in estimating the welding cost in case of
gas welding.
ESTIMATION OF WELDING COST
For estimating the welding cost, following costs, should be
considered.
(a) Preparation Cost. It includes the cost of edge
preparation, proper fit up and other elements before actual
starting of welding.
(b) Actual Welding This includes two costs.
(i) Cost of material used in welding process like Oa. CsHz, filbr rod,
flux etc.
(il) Labour Cost. It will be obtained from wage sheets.
(iii) Welding Finishing Cost. This includes, the
expenditure made for finishing the welded joint after welding.
Post welding treatment (such as heat treatment) cost can also be
taken into account.
(iv) Oncost. Atl the other overheads on the equipment
and other facilities connected with welding operations are considered in
oncost heading.
GAS CUTTING
It is the cutting of material with the help of gas flame. It is
generally done with the help of oxy-acetylene flame. It can be done
either by hand or by machine.
STIMATION IN WBLDNO SHOP
Table 2 gives approximate data about the gas cutting
operations.
ESTIMATION OF GAS CUTr1NG COST
Gas cutting cost may be estimated by considering the
following steps :
(9 Actual Cutting Cost. This includes two costs :
(a) Cost of material used in cutting process like cost of
oxygen, acwtelene etc.
MECHANICAL ESTIMATING ~
띺 R 은은
999유유
8 a
충§§병형 6 6 6 6 들
8 0 0 8
0 0 0 0 0
ESTIMATION IN WELDINO SHOP 223
AND
(b) Labourcost•
Cost. This is the expendituæ made on finishing and
cleaning the cut parts.
(iii) These are alt the other overhead charges made on
equipmnt• and other items which connected with cutting processes.
ELECTRIC WELDING
Ebctric is very economical because it requires very less that
required for gas welding. Following table gives the approximate data
which helps in estimating the cost of electric welding.
TABLE 3
20 4 35 to 40
2•OO to 2•SO
40t045
ESTIMATION OF ARC WELDING COST
For estimating the cost of arc welding following costs are included.
(l) Material cost—It inclUdes the cost of electrodes.
(it) Labour cost.
(lit) charges.
(IV) Finishihg cost, including post welding treatment cost,
it.any. (y) On-cut.
FACTORS AFFECTING WELDING COST
There is certain• factors which affects larF1y on the welding cosu.
Thesqfactoo are, being discussed below
IN WBLDINO 225
(t) Time required for handling and setting the job and
equipment in position.
(il) Time required for fixing the fixctures.
(lit) Rest and fatigue time allowance. These are FneraIW
ãken as 5 to of the total time for which an operator remain'.
engaged.
(iv) Excessive welding—it increases the cost of welding.
(v) When excessive current is used, welding cost also increases„
Solved Problems
leftward
Fig.
= 48•4 min.
Considering fatigue allowance as 5% ;
Actual time taken by welder for welding one tank
= 38•4x 1•05
= 40•3 min. Ans
100
= Rs. 0•1875
MECHANICAL ESTIMATING AND
(iii) Length of filler rod required for 15 cm. job @
m./m.
.of welding
• •675 m.
But for 10 mm. thick plates, filler rod dia. — 5 mm.
Weight of filler rod consumed
= Volume x density.
gm. — 92•8 gm.
— o•ona kg.
•TIMATION SHOP
Fig.
(a) Groove Cutting : —
Fig. 8-5
= Re. 0•12.
9 2
(it) Amout of acetylene required . cu. m.
0•02 cu. m.
COn1NŒ
6
(ili) Labour cost of cutting @ Re. O•80/hr . — — o•80x
— 60
— Re. 0•08
Total cutting cost = 0•124
— R. 0•30. Aus.
(b) Welding cost. From tables, for i8 mm. thick plate trightward
welding).
Filler rod dia. = 4 mm.
Oxygen consumption = cu. m./hr. Acetylene
consumption = cu. m./hr, Welding time/m.
length = 25 min.
Length of filler rod used/m. of welding — 36 m.
As length of portion to be welded is I m.
Time required for welding = 25 x 1 — 25 min. (i) Oxygen
consumed = O' 5 x -ä — — 0 •209 cu. m.
Cost of oxygen @ Re. O•60/cu. m.
= = Re. O•12S
(ii) Acetylene consumed
25
MECHANICAL ESTIMATING AND
60
= Re. 0•125 cu. m.
Cost of acetylene @ Rs. 5•O/cu. m.
= Re. 0•625.
(ill) Length of filler rod used for 1 m. welding = .36 m-
— Rs. 1•716
Rs. 1•72. Ans.
Hence,
(a) Cost of cutting = Rs. 0•30
(b) Cost ofwelding = Rs. I •72 j
Example 4. Find the welding material cost for making a
rectangular frame for a gate of 2 m. x I m. from angle iron of size
30 mm. x 30 mm. x 5 mm. Assume the following data :
(a) Oxygen consumption = cu. m/hr. which is available @
Re. o•60/cu. m.
(b) Acetylene consumption = cu. m./hr. which is
available @ Rs. 5 0/cu. m.
(c) Welding speed 4 m./hr.
(d) Lenth of filler rod of dia. m/m. of
welding
(e) Filler rod material cost = Rs. 31kg
(f) Welding is to be done on both the sides.
Soladon. Portion to be welded in the frame is shown in Fig. 8•6.
Fig.
Let us consider that first of all welding is done only on
corner, where welding is done on portions AB and AC.
30
Length sin 45
MECHANICAL ESTIMATINO
= 42 4 mm.
and Length AC = 30 mm.
Length of welding on one corner on one side
42•4+30 — 72 4 mm. —
7•24 cm.
174 COSTING
60
Cost of oxygen @ Re. 0•60/cu. m.
= 1•972 m.
Weight of filler rod (assuming the density as 7 gm./c.c.)
= = 67 gm. = 0•067
kg.
Cost of filler rod @ Rs. 3/kg. = = Re.
0•201.
. Total welding material cost
= 0•03448 +0•2900+0 2010
= Re. 0•5258
= Re. 0•53 (say). Ans.
Example. S Two 1 m. long m.s. plates of 10 mm. thickness are to
be welded by a rap joint with the help of a 6 mm. electrode Calculate
cost of welding. Assume following data :
IN WELDING
(i) Cureent used —250 ampere. (ii)
Voltage—30V.
(it) Welding speed = 10 m./ht.
(iv) Electrode used = kg.lm. of welding.
(V) Labour charges=Re. 1 00/hr.
(pi) Power charges Re. 0•20/kWh.
SHOP 175
WELDED CIRCULAR
PLATE
Fig.
— 8•78 m.
(i) Labour Charges. Time required for
welding 8•78 m. is :
8•78
.(a) On outer
side 25
= 351
electro&
Considering 5%
Electrodes consumed— 26•34x 1'05 —
27•66 m.
Cost of electrode @ Re. 0601m.
— 27•66X6 — Rs. 16•60.
(ii) Cost of Power. Power consumption for 17•S6 m. of
• welding
4X
Fig.
For making the pattern, allowances for metal shrinkage (10
mm per metre length) and for machining (2 mm. on each side on
casting) IS added in the dimensions of the finished product.
Now considering these allowances, the dimensions of pattern with
core prints will be as shown in Fig. 9•2.
For simplicity in calculations, Fig. can be split up into parts A,
B and C.
Tbe amount of rough wood
required for each part can be esti•
B mated by considering pattern
finishing allowance 3 mm. on
each surface to be finished. To
make the pattern economical each
part is prepared separately and then
Fig.
fixed together to get the complete
pattern instead of preparing the whole
pattern from one piece of wocd.
Fig.
240 MECHANICAL AND
Part A. Th: size of rough wood required would be :
Length —19 8+0
3+0•3 cm.
Widthcm.
Thickness = 11•1 cm.
Volume —20•4x — 2513 cm.a part B. These are two
in number.
The size of rough wood required would be :
Length17•16 cm.
Width17•16 cm.
Thickness — 2•22+0 3+0•3 — 2•82 cm.
Volume = 1593 cm.'
Part C. There are 2 core prints which are made on the pattern
for resting the core in the mould.
The size of rough wood required would be : Length
— = $15 cm.
PATTERN
= Rs. 600.
Workèr completes pattern in 6 hours and it is assumed that
normal working hours for workers are 8 hours per day.)
(c) Overheads, therefore 100% of material cost,
= Rs. 3•44.
Cost of pattern = Rs. 3•44+Rs. 6•00+Rs. 3•44
= Rs. 12•88. Ans.
MAXING AND FOUNDRY SHOPS 241
Example 2. Find out the cost of wood required for making the
pattern of a Bell crank lever. The finished drawing of C.I. Bell crank
lever is given in Fig. 9•3. Wood is available @ Rs. 8001m.a. Holes are to
be bored on machineg after casting.
26 en
4
Finished Drawing
Solution. To find out the amount of wood required for making the
pattern, shrinkage and pattern finishing allowances would be necessary
to consider :
After considering the shrinkage allowance 10 mm./metre length
and finishing allowance 3 mm. on each side, the sketch of pattern is
shown in Fig. 9•4.
10•1 cm.
o•zcm.
cm
Fig.
242 MECHANICAL AND
Pattern of Bell Crank Lever Fig.
= 980 cm.'
Small Arm B. The size of rough wood required for this arm would
be as follows, considering that this pipe would be fixed with 'arm A.
10•1 8•08
Length = 15 15+
= 24•84 cm.
Width — Dia. of = 10•7 cm.
Thicknes
Volume of rough wood required for B
— 24•84x = 696 cm.'
*PATTERN
Hub C. These are two in number and will be fixed on both the sides
of arm.
The size of rough wood required for making the hub will be as
follows :
10•7 cm.
Length
= 10•7 cm.
Width = 10•1+0 3+0•3
Thickness = 2•62
cm.
Volume of rough would required for C, two hubs
= 600 cm.8
Hub D. These are two in number and each will be fixed on both
the sides of arm A and arm B as shown.
MAXING AND FOUNDRY SHOPS 243
The size of rough wood required will be as follows .
Length cm.
Width cm.
Thickness
cm.
Volume 789 cm.a
To make the pattern economical, each part is prepared separately
from wood pieces and then fixed together to get complete pat. tern,
instead of preparing the whole pattern from one piece of wood. Now,
total volume of wood required will be
= 980+696+600+789
= 3065 cm. 2
3065
0003065 m.'
Rate of wood — Rs. 800/m.a
Cost of = 0 003065 x 800
wood
= Rs. 2•45. Ans.
Example 3. Find the cost of 2000 C.I. pulleys Shown in Fig. 9•5.
Its surfaces are to be machined after casting. The pattern .is supplied by
the customer itself. Following data can be used.
Cost of metal = Re. O•75/kg.
worker/day
Fig.
244 MECHANICAL ESTIMATING AND COSTING.
Melting charges = 20% of metal cost.
Machining allowance on each side may be taken as 2 mm.
Wages of each moulder = Rs. 6/day.
Density of C.I. = gm./c.c.
Overhead charges = 25% of metal cost.
Solution. Size of the casting is shown in sketch Fig. in which
machining allowance has been added.
For easy calculations, split up the drawing into simple parts.
A, B, C and D.
Volume of step A
= 158•4 cm.'
Volume of step B
4
81" cm.s
Volume of step C 4
= 367t
Casting Volume of hole D Fig.
= 27•9
Total volume of pulley
= = 777 cm'.
Weight of C.I. required
= kg. = $6 kg.
Costing. Cost for each piece is determined as under :
(a) Material cost= Rs. 4•20
(b) Melting charges
= = = Re. 0•84
6
(c) Moulding charges = —20
= Re. 0•30
MAXING AND FOUNDRY SHOPS 245
1•05
Total 1•05
A Cost of 2000 castings
Fig.
MECHANICAL ESTIMATION AND COSTING
= 2245
-j-(al+aa+
597•7 cm. 98
Volume of A
Volume of B
=
a 86
Volume of C = -3 n— (al+as+stqaa)
1454•4 cm.
Volume of D = — 19•4
= 280 cm. s
Volume of E 192 cm.'
4
Total volume of casted gear blank
Fig.
MAXING AND FOUNDRY SHOPS 248
QATTERN
= (10)2 x20
= 1902 cm.8
Wt. of C.I. pipe= 0 = 13 7 kg.
Process scrap @ 2% net wt. of casting
10
Moulding minutes Re. 0•50 Rs. 2•OO/hr.
Fig. 9•10
Solution. Volume of rim,
Volume of hole
MECHANICAL ESTIMATION AND COSTING
Length of one spoke, = = $25 cm. C
2
Volume of 4 spokes,
3•34 cm.s
= 144•20 cm.8
e.rrERN
c
10
(i) Moulding charges = Re. 0•08
Production cost
— Rs. 2•60
3
Fig. 9•11
Estimate the wt. of casting, if
contraction allowance anc achining
allowance is considered.