Two Methods Calculate Forward Backward Pass
Two Methods Calculate Forward Backward Pass
Start – 0
C Start 6
B Start 4
P Start 3
A C,B,P 7
U P 4
T A 2
R A 3
N U 6
End T,R,N 0
This article complements information in Rita Mulcahy’s™ PMP® Exam Prep book, 11th edition. If you are preparing for the CAPM®, consider
contacting RMC Learning Solutions® at [email protected] to find the best prep strategy for you.
p. 1 of 4
Two Methods to Calculate the Forward
and Backward Passes in a Network Diagram
Based on the above chart and network diagram, you can determine that the critical path is Start–C–A–R–End. Using
the One Method and starting with activity C, the earliest it can begin is at the beginning of week one, so Early Start
(ES) = 1. To find the Early Finish (EF), you count the ES and continue counting to reach the duration of the activity. In this
case, you start with 1 and then continue to count until you have counted the duration, which is 6. So the ES=1, and the
EF = 6 for activity C. This technique works well for many people who like to use a simple method to calculate forward
and backward passes. Others who prefer to have a standard formula can use EF = ES + D – 1 for the forward pass.
This article complements information in Rita Mulcahy’s™ PMP® Exam Prep book, 11th edition. If you are preparing for the PMP®, consider
contacting RMC Learning Solutions® at [email protected] to find the best prep strategy for you.
p. 2 of 4
Two Methods to Calculate the Forward
and Backward Passes in a Network Diagram
Now we can move on to the next activity you would increment by one, making activity A’s ES = 7. We need to
consider convergence as well as duration. Both activity C and B must be complete before we can start activity A. The EF
of C = 6, and the EF of B = 4. Since both activities have to be complete, we use the later EF of the two activities, which is
6. We then increment this number by one. The ES of A is the beginning of week 7, as shown on the network diagram.
You can use the same simple counting method to determine that the EF of activity A is the end of week 13. You continue
in this manner, watching for convergence, until you have completed all the activities on the network. You will then have
completed the forward pass.
Once you have finished the forward pass, you can begin the backward pass. You start by using the duration of the
critical path (as calculated above) for the late finishes (LF) of the final activities. In this example, activities T, R, and N
would be included.
Let’s focus on activity T first. For this activity, the LF is at the end of week 16. You can count backward from 16 to
determine the Late Start (LS) for T. Since the duration is only 2 for this activity, you stop counting at 15. Therefore, the LS
of T is at the beginning of week 15. You then decrement this number by one to find the LF of the previous activity. Be
careful here as well, as there is a convergence of two paths back into activity A. You need to consider the LS of both
activities T and R before you can determine the LF of activity A. In this case, activity T’s LF is the beginning of week 15
and activity R’s LS is the beginning of week 14. On the backward pass, use the earlier of the two LS numbers. Thus, the
LF of activity A is 14 decremented by one, which equals the end of week 13. Continue this process, watching for path
convergence, until you reach the start of the project. For those who like formulas, LS = LF – D + 1 for the backward pass.
The differences between the LF and EF or the LS and ES for each activity are the same number. This number
represents the activity’s float.
Zero Method
Now let’s look at the Zero Method. Remember the starts and finishes both represent the end of a time period. In this
case, they represent the end of a week. Based on the same network diagram, the earliest the activity can begin is at the
end of week zero. Therefore, Early Start (ES) = 0. To find the Early Finish (EF), just add the duration to the ES
(formula:EF=ES+D). In this case, you start with 0 and add 6, so the ES = 0 and the EF = 6 for activity C. This technique is a
simple method to use on the exam as it is fast and, by using it, you are less prone to make mathematical errors. To
determine the ES of the next activity, just use the EF from the previous activity.
This article complements information in Rita Mulcahy’s™ PMP® Exam Prep book, 11th edition. If you are preparing for the CAPM®, consider
contacting RMC Learning Solutions® at [email protected] to find the best prep strategy for you.
p. 3 of 4
Two Methods to Calculate the Forward
and Backward Passes in a Network Diagram
With the Zero Method, you’ll also need to consider convergence. Both activity C and B must be complete before you
can start activity A. The EF of C = 6, and the EF of B = 4. Since both activities have to be complete, use the later EF of the
two, which is 6. You then carry this number to the ES of activity A. So the ES of A is the end of week 6. Next, add the
duration of activity A to determine that the EF of activity A is the end of week 13. Continue in this manner, watching for
convergence, until you have completed all the activities on the network. You will then have completed the forward pass.
As with the One Method, once you have finished the forward pass, you can begin the backward pass. Start by using
the duration of the critical path for the late finishes (LF) of the final activities. In this example, it includes activities T, R,
and N.
Let’s focus on activity T. If the LF of activity T is at the end of week 16, you can just subtract the duration of T to
determine the activity’s Late Start (LS) (formula: LS = LF – D). Therefore, subtract 2 from 16 to get 14. As a result, activity
T’s LS is the end of week 14. Then carry this number over to find the LF of the previous activity. Again, be careful here,
since there is a convergence of two paths back into activity A. You need to consider the LS of both activities T and R
before you can determine the LF of activity A. In this case, activity T’s LF is the end of week 14 and activity R’s LS is the
end of week 13. On the backward pass, use the earlier of the two LS numbers. Thus, the LF of activity A is the end of
week 13.
Continue this process, watching for path convergence, until you reach the start of the project.
As with the One Method, the differences between the LF and EF or LS and ES for each activity are the same number.
This number represents the activity’s float.
How can you tell which method you are using? Here is a quick check to help you figure it out.
You are using the One Method if: You increased the finish number by one to calculate the start of the next activity
on your critical path.
You are using the Zero Method if: The finish is the same number as the start of the next activity on your
critical path.
Because the Zero Method uses the same number for the finish and start of adjacent activities, it makes the
calculations for the exam simpler than the One Method. However, the One Method is more intuitive and is more
applicable to the real world. Ultimately, the method you use is up to you, but it is helpful to understand each method for
the exam.
This article complements information in Rita Mulcahy’s™ PMP® Exam Prep book, 11th edition. If you are preparing for the PMP®, consider
contacting RMC Learning Solutions® at [email protected] to find the best prep strategy for you.
p. 4 of 4