Project Start Date : 20/02/2006 Construction of ( 2B+G+8+Gym ) for Mr. Abdulrazzaq Ali Hassan Al Zarooni
Expected Project Finish : 19/03/2007 Cash Flow Bar Chart
S Activity Description Value % W.D. Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07
0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.02 0.02
1 Preliminaries 250,000 1.24%
1.00 1.00 1.00 1.00 1.00 1.00 2.00 2.00 2.00 3.50 1.37
12 Electromechanical Works 3,407,320 16.87%
0.16 0.10
13 External Works 51,760 0.26%
Months / Monthly Value 20,200,000.00 100.00% Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07
%Monthly Value 1.60 7.10 5.10 6.10 5.51 6.70 7.00 7.50 7.50 13.00 10.74 11.41 7.98 2.76
%Cumulative Value 1.6 8.7 13.8 19.9 25.4 32.1 39.1 46.6 54.1 67.1 77.9 89.3 97.2 100.00
Monthly Value - Gross 323,200 1,434,200 1,030,200 1,232,200 1,113,020 1,353,400 1,414,000 1,515,000 1,515,000 2,626,000 2,169,480 2,304,820 1,611,960 557,520
Cumulative Value - Gross 323,200 1,757,400 2,787,600 4,019,800 5,132,820 6,486,220 7,900,220 9,415,220 10,930,220 13,556,220 15,725,700 18,030,520 19,642,480 20,200,000
% Cumulative Elapsed Time 1.79% 9.72% 17.39% 25.32% 32.99% 40.92% 48.85% 56.52% 64.45% 72.12% 80.05% 87.98% 95.14% 100.00%
Al Malik Building Cont. Co.
Construction of ( 2B+G+8+Gym ) for Mr. Abdulrazzaq Ali Hassan Al Zarooni
Actual S-Curve versus Planned
Months Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07
Planned Monthly Value 323,200 1,434,200 1,030,200 1,232,200 1,113,020 1,353,400 1,414,000 1,515,000 1,515,000 2,626,000 2,169,480 2,304,820 1,611,960 557,520
Planned Cumulative Value 323,200 1,757,400 2,787,600 4,019,800 5,132,820 6,486,220 7,900,220 9,415,220 10,930,220 13,556,220 15,725,700 18,030,520 19,642,480 20,200,000
Planned % Monthly 1.60% 7.10% 5.10% 6.10% 5.51% 6.70% 7.00% 7.50% 7.50% 13.00% 10.74% 11.41% 7.98% 2.76%
Planned % Cumulative 1.60% 8.70% 13.80% 19.90% 25.41% 32.11% 39.11% 46.61% 54.11% 67.11% 77.85% 89.26% 97.24% 100.00%
Actual % Monthly
Actual % Cumulative
0.9
0.7
0.6
0.5
%
0.4
0.3
0.2
0.1
0
May-06
Sep-06
Feb-06
Mar-06
Apr-06
Jun-06
Jul-06
Aug-06
Oct-06
Nov-06
Dec-06
Jan-07
Feb-07
Mar-07
Project Months
Al Malik Building Cont. Co
Construction of ( 2B+G+8+Gym ) for Mr. Abdulrazzaq Ali Hassan Al Zarooni
Monthly Value Histogram & Cumulative S-Curve
3,000,000
20,000,000
2,626,000
Monthly Value
Cumulative Value
2,500,000
16,000,000
2,304,820
2,169,480
2,000,000
12,000,000
1,611,960
1,515,000 1,515,000
Values
1,434,200
1,500,000
1,414,000
1,353,400
8,000,000
1,232,200
1,113,020
1,030,200
1,000,000
4,000,000
557,520.00
500,000
323,200
0
0
Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07
Months
0 4,000,000 8,000,000 12,000,000 16,000,000 20,000,000
Al Malik Building Cont. Co.
Construction of ( 2B+G+8+Gym ) for Mr. Abdulrazzaq Ali Hassan Al Zarooni
Months Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07
Monthly Value 323,200 1,434,200 1,030,200 1,232,200 1,113,020 1,353,400 1,414,000 1,515,000 1,515,000 2,626,000 2,169,480 2,304,820 1,611,960 557,520.00
Cumulative Value 323,200 1,757,400 2,787,600 4,019,800 5,132,820 6,486,220 7,900,220 9,415,220 10,930,220 13,556,220 15,725,700 18,030,520 19,642,480 20,200,000
% Monthly 1.60% 7.10% 5.10% 6.10% 5.51% 6.70% 7.00% 7.50% 7.50% 13.00% 10.74% 11.41% 7.98% 2.76%
% Cumulative 1.60% 8.70% 13.80% 19.90% 25.41% 32.11% 39.11% 46.61% 54.11% 67.11% 77.85% 89.26% 97.24% 100.00%
100%
90%
80%
70%
60%
% of Compeletion
50%
40%
30%
20%
10%
0%
Sep-06
Feb-06
Mar-06
Apr-06
May-06
Jun-06
Jul-06
Aug-06
Oct-06
Nov-06
Dec-06
Jan-07
Feb-07
Mar-07
Project Months ( Duration )
Al Malik Building Cont. Co.
Construction of ( 2B+G+8+Gym ) for Mr. Abdulrazzaq Ali Hassan Al Zarooni
Months Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07
Monthly Value 323,200 1,434,200 1,030,200 1,232,200 1,113,020 1,353,400 1,414,000 1,515,000 1,515,000 2,626,000 2,169,480 2,304,820 1,611,960 557,520.00
Cumulative Value 323,200 1,757,400 2,787,600 4,019,800 5,132,820 6,486,220 7,900,220 9,415,220 10,930,220 13,556,220 15,725,700 18,030,520 19,642,480 20,200,000
% Monthly 1.60% 7.10% 5.10% 6.10% 5.51% 6.70% 7.00% 7.50% 7.50% 13.00% 10.74% 11.41% 7.98% 2.76%
% Cumulative 1.60% 8.70% 13.80% 19.90% 25.41% 32.11% 39.11% 46.61% 46.61% 59.61% 70.35% 81.76% 89.74% 92.50%
3,000,000
2,626,000
Monthly Value
2,500,000
2,304,820
2,169,480
2,000,000
1,611,960
1,515,000 1,515,000
1,434,200 1,414,000
Value 1,500,000 1,353,400
1,232,200
1,113,020
1,030,200
1,000,000
557,520.00
500,000
323,200
0
Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07
Months
Al Malik Building Cont. Co.
Construction of ( 2B+G+8+Gym ) for Mr. Abdulrazzaq Ali Hassan Al Zarooni
Months Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07
% of Time Monthly 1.79% 7.93% 7.67% 7.93% 7.67% 7.93% 7.93% 7.67% 7.93% 7.67% 7.93% 7.93% 7.16% 4.86%
% of Time Cumulative 1.79% 9.72% 17.39% 25.32% 32.99% 40.92% 48.85% 56.52% 64.45% 72.12% 80.05% 87.98% 95.14% 100.00%
100%
90%
80%
70%
% of Elapsed Time
60%
50%
40%
30%
20%
10%
0%
Feb-06
Mar-06
May-06
Oct-06
Jan-07
Feb-07
Mar-07
Apr-06
Jun-06
Jul-06
Aug-06
Sep-06
Nov-06
Dec-06
Project Months ( Duration )