MS5 M2009 Lecture Slides
MS5 M2009 Lecture Slides
Judge
MST Business
Michaelmas 2009 School • Part I (lecture 1-4): Factory-level planning
• Part II (lecture 5-8): Supply chain management
Operations p
• Four supervisions ((see Camtools for g
groups
p and dates))
Not always right answer, so no cribs!
Management • Past exams / “The Goal” Goldratt (session 5)
• Contact details:
Centre for Process Excellence and Innovation
M i k Stevens
Merieke St 14 Trumpington Street
Tel: 01223 7 48827
E il [email protected]
Email: 700@ k
Page 2
Page 4
What is Operations Management? Why does OM matter?
– Operations Management (OM) is the activity of managing the
resources which are devoted to the production and delivery of products
• One of the three core activities of the firm
and services to end customers. Marketing and sales
Product/service development
– OM uses p process thinking g to meet and exceed customer demand
Operations
while using all resources efficiently in order to maximise the value of the
organisation. • Operational decisions have strong financial
– Anything which repeats in the operation can be seen as a process. i li ti
implications...
The repetitive nature of processes allows for improvement.
• ... and often forgotten: also determine the day-to-
day to
– Project management : low volume, high variety operations with defined day service level at the customer end!
beginning and end.
Page 5 Page 6
Page 8
Input - Output Diagram Productivity, Efficiency and Improvement
Basic definitions in Operations Management all relate to the
Input-Output process model:
I
Inputs
t O t t
Outputs
– Productivity = Ratio of Σ Outputs to Σ Inputs
Subsystem
E.g. Vehicles produced per labour hour
or “Benchmarking” as comparative analysis across firms
What are the main mechanisms for increasing productivity?
Transformation
process
– Efficiency
Aims at usingg the least amount of resources to p
produce a g
given g
good or
service at the lowest possible unit cost
Flows of orders, information, data,
energy, material, people, etc.
– Improvement = [ Productivity(t) / Productivity(t
Productivity(t-1)
1) -1]*100
1]*100
Input-output diagrams are a way of defining a system, Considers output per unit resource over time
e g a manufacturing System
e.g. Tracks productivity development over time
Page 9 Page 10
Page 11 Page 12
Example: A Bakery III A Simplified Manufacturing System
External
influences;
• Product variety adds complexity System boundary Taxation etc
Taxation, etc.
R
Raw material
t i l Planning &
suppliers Purchasing Scheduling
Elements outside El
Elements
t in
i the
th system
t
the system
Page 13 Page 14
Page 15 Page 16
Exercise capacity utilisation Overall Equipment Effectiveness (OEE)
“Load balancing”
Value- Quality Defects / scrap
p Value-added time
Quality q =
added time losses Net operating time
Exercise OEE
Maximum time available:
Management decides machine works 150 hrs: available time
Availability losses: 10 hrs (machine set-up) + 5 hrs (breakdowns)
Total operating time: available time – availability losses:
p
Speed losses: 5 hrs ((idling)
g) + 10% ((when the machine runs):
)
Page 19
Plane and car manufacture Manufacturing Process Types
• How do these two operations differ?
High
Project
Jobbing
Variety
Batch
Mass
Conti-
Low
nuous
Page 21 Page 22
Assembly
Page 25 Page 26
Running
Commutators Front Axles
Boards
Assembly
250,000
, Vehicles Per Year,, One Model
Page 27 Page 28
Mass/Line production: Automobiles Continuous processing: Oil refinery
Page 29 Page 30
High
operation is the trade-off in its design between production Diverse / Project
Intermittent
complex
volume and p product variety y
Jobbing
Defines types of job design required
Defines necessary tools and technology
Variety
Batch
Defines cost structure
Defines relationship with suppliers Mass
Low
Repeated Continuous nuous
/ simple
Low Volume High
Page 31 Page 32
What are we trying to achieve in OM?
External objectives:
Objectives
j and Trade-offs
Additional metrics: Flexibility, Safety and Service
Page 34
Page 38
Inventory – Definitions
‘An accumulation of a commodity that will be used to satisfy
future demand.’
Johnson and Montgomery (Operations Research)
‘Dead material.’
Taiichi
T ii hi Oh
Ohno (F
(Father
th off th
the T
Toyota
t Production
P d ti S System)
t )
Page 39 Page 40
Types of Inventory The Inventory Cycle (‘Sawtooth’)
Raw Materials:
Materials to which the manufacturer has not yet added value
Work-in-progress or Work-in-process (WIP): Order Quantity (Q)
Materials to which the manufacturer has added some value but still has
evel
more to add
Inventory Le
Finished Goods
Goods ready for shipment to the customers, with no more value to be
added
Also consider service parts...
Safety and Cycle Stock Reorder point
Safety stock: non-active component to protect against fluctuations of
demand, production and supply
Cycle stock: active component that depletes over time, and is 0 Lead Time
replenished cyclically
Order time Order
Terminology: Stock-keeping Unit (SKU): an item at particular location Placed (LT) Received
Page 41 Page 42
Page 43 Page 44
Inventory – Arguments against Hidden Costs of Inventory
Cost involved:
• Longer lead times
Cost of capital: value
value*ii, i=interest rate per unit time
Opportunity cost: How much would the capital earn otherwise? • Reduced responsiveness
Depreciation of goods
Stock obsolescence and deterioration • Underlying problems are hidden rather than being
Quality defects due to handling exposed and solved
Labour and handling
• Quality
Q lit problems
bl are nott id
identified
tifi d iimmediately
di t l
Warehousing, rent and energy
Insurance and overhead to admin labour, space, etc. • No incentive for improvement of the process
Overall costs:
Typical estimate is 20-30%, but often excludes quality,
depreciation, and opportunity cost
Key issue: estimates almost always too conservative!
Page 45 Page 46
Reduced
Rock = Problems Inventory Rock = Problems Inventory Level
Defects Defects
Supply Shortages Supply
Damage Issues
Equipment
Damage Issues Shortages
Breakdowns Equipment
Breakdowns
Page 47 Page 48
Little’s Law Exercise Little’s Law
John D.C. Little’s Theorem (or Little's Law) gives a simple relation • A company assembles computers. The process has
between inventory and lead-time. Applies to all types of systems!
three stages – assembly,
assembly testing and packing – which
take 975 minutes in total
I = R *T • A work day has 7
7.5
5 hours
I is the number of items or inventory in a system [units] • Average daily demand is 1,600 units
R is the production rate at which items arrive/leave [units/day]
T is the lead-time (here, the time a job spends in the system) [days] • Current WIP levels (for all three presses combined) are
g , steady-state
all based on average, y values. 4,800 units. Consultants hired by the CEO think this is
I determines the minimum pipeline stock needed! too much, and suggest to reduce stock by 50%
py
• Your reply?
Page 49 Page 50
180
Ford
Stock Turns is the number of times an organisation replaces 160
GM
its stocks during a period (usually measured annually) Honda
140
80
>40.
60
Volkswagen
£1 2
£1.25m at the
h end d off the
h year. T
Totall sales
l iin the
h year were £36m.
£36 20
Hyundai
Ja 6
M 7
Se 7
Ja 7
M 8
Se 8
Ja 8
M 9
Se 9
Ja 9
M 0
Se 0
Ja 0
M 1
Se 1
Ja 1
M 2
Se 2
Ja 2
M 3
Se 3
Ja 3
M 4
Se 4
Ja 4
M 5
Se 5
05
-9
-9
9
-9
9
-9
9
-9
0
-0
0
-0
0
-0
0
-0
0
-0
0
-0
p-
n-
p-
n-
p-
n-
p-
n-
p-
n-
p-
n-
p-
n-
p-
n-
p-
n-
p-
ay
ay
ay
ay
ay
ay
ay
ay
ay
ay
n
Ja
Se
M
Page 51 Page 52
Part Classification Pareto, ABC & the ’80-20 Rule’
All inventory control models are part-specific % of Impact
(Value x Volume)
Attention given to part depends on cost impact
100%
ABC Classification, H Ford Dickie, 1951 95%
c.20%
0 c.50% % of SKU
SKU’ss
Page 53 Page 54
Page 55 Page 56
Basic Approaches to Ordering
• 1. Fixed Order Quantity Models
Economic Order Quantity (EOQ)
Re-order Point
• 2.
2 Fixed Period Requirements
Fixed Period Ordering
Lot-for-Lot ordering
g
Period Order Quantity
Ordering and • 3. Variable order q
quantity
y and ordering
g interval
B t h Sizing
Batch Si i Least Unit Cost
Decisions
ec s o s Least Total Cost
Part-Period Balancing
• 4. Material Requirements Planning (MRP)
Calculates time-phased requirements
Page 58
Fixed Order Quantity Systems (s,Q) Fixed Period Ordering Systems (R,S)
Fixed Order point
nventorry Levell
S
Order
evel
Quantity
=Q
ntory Le
Q
In
s ROP
O Inven
Time 0 R R R
0
Page 61 Page 62
Page 63 Page 64
EOQ basic trade-off model Economic Order Quantity
Cost per
period Ordering
O d i
Slope = 0
Total CO Cost
EOQ = 2 D
Minimum
CH Holding Cost
Holding cost,
cost CH
Annual Demand
Page 65 Page 66
Page 67 Page 68
EOQ considering volume discounts Period Order Quantity (POQ)
EOQ logic, modified so that we order to cover demand for a
whole number of periods,
periods while still minimising cost
Example:
D = 200 units per year and EOQ = 58 units, with “period” equal to
one month
EOQ/D = 58 units / 200 units = 0
0.29
29 years between orders
0.29 years = 3.48 months, so order every 3 months to cover
p
expected demand in the next 3 months
Page 69 Page 70
• What if we are producing the batch ourselves, rather than Assume a constant production rate of R>D for each batch
ordering it in from an external supplier? Inventory
• Most of the issues are the same as they were when we Q(1-D/R)
Slope= -D
were ordering the batch in. The differences are: Slope=R-D
Page 71 Page 72
Problems with EOQ and EPQ Variable Order Quantity and Ordering Interval
Rigid Assumptions! Methods that allow lot size & ordering interval to vary from period to period
1. Demand is constant and steady, and continues indefinitely We still assume that demand is known, even if it is not constant
2
2. EOQ assumes whole h l replenishment
l i h t llott arrives
i att same titime
Seek to cover demand for a whole number of periods (why?)
3. Replenishment lead-time is known
4. Order size is not constrained by supplier, no min/max restrictions As in EOQ, objective of minimising the sum of setup and inventory cost
5. Holding cost per item per period is a constant
6. Cost of ordering/setup varies linearly with replenishment size LUC - Least Unit Cost
7. Item is independent of others; benefits from joint reviews are ignored See next slide
8. Doesn’t encourage us to decrease fixed ordering/setup costs
LTC - Least Total Cost
Problem Cost Accuracy:
Consider seeking
g to cover demand for next 1,2,3...
, , periods
p (as
( LUC))
How much does a set-up or placing an order cost? Choose n to most closely balance set-up and inventory cost for this batch
Holding costs: often calculated at interest level (cost of capital)
PPB - Part-Period Balancing
Conclusion
Basic version as LTC, but advanced versions include ‘look-ahead / look-back’
Simple model, often reasonable, though with limitations
facility to see if simple modifications to schedule reduce total costs.
Page 73 Page 74
Page 78
Page 81 Page 82
mean
demand • A 4-period moving average is the average of the last 4
15
Qu
ti
time periods
i d
5
• The general formula for moving average is:
-5
-10 0 10 20 30 40 St = ( x t + x t -1 + .. + x t -n +1 ) / n
Time Random noise
NB: by convention, St is an average based on data up to time
t, but used as a forecast for time t+1
Page 83 Page 84
Exercise 4-Period Moving Average Forecasting Exercise 4-Period Moving Average Forecasting
Time Demand Forecast Time Demand Forecast
-3 504 -3 504
-2 484 -2 484
-1 493 -1 493
0 423 0 423
1 458 1 458
2 440 2 440
3 485 3 485
4 395 4 395
5 368 5 368
6 344 6 344
Page 85 Page 86
St = α ⋅ xt + α ⋅ (1 − α ) xt −1 + α ⋅ (1 − α ) 2 xt − 2 + α ⋅ (1 − α ) 3 xt −3 + ... S9 = α x9 + α (1 − α ) x8 + α (1 − α ) 2 x7 + α (1 − α ) 3 x6 …
= α x9 + (1 − α ) [α x8 + α (1 − α ) x7 + α (1 − α ) 2 x6 + … ]
St is based on all (available) data up to period t to forecast xt+1
= α x9 + (1 − α ) S8
St = α xt + (1 − α ) St −1
Alternative notation:
St = St −1 +αε t ε t = xt − St −1
Page 89 Page 90
Time Demand Forecast α=0.1 Forecast α=0.9 Time Demand Forecast α=0.1 Forecast α=0.9
0 504 0 504
1 484 1 484
2 493 2 493
3 423 3 423
4 458 4 458
5 440 5 440
6 485 6 485
7 395 7 395
8 368 8 368
9 344 9 344
Page 91 Page 92
Exponential Smoothing: α = ? ES: Step change in demand
Choosing α: depends on how rapidly we want the smoothed
value to respond to changes in demand The forecast “locks
“locks-on”
on” to the demand (that’s good)
Usually α=0.1 to 0.3
The larger α, the more responsive (nervous) is the forecast
12
1.2
The smaller α, the less reactive and more stable the forecast
1
S t = α x t + α (1 − α ) x t-1 + α (1 − α ) x t-2 + α (1 − α ) x 3 ..
2 3
08
0.8
Quantity
y
0.6
Demand (Input)
Steady
• α=0.1 10% 9% 8.1% 7.3% 0.4 state
Weights 0.2
Simple or constant (Type 1) ES
Page 93 Page 94
20
linear trends: double exponential smoothing (sometimes known as
15
Type 2 exponential smoothing)
10
5
0
-10 0 10 20 30
Time
Page 95 Page 96
Definition of Double ES Approaches to Forecasting
Input, xt (Demand) • One approach is to extrapolate past data (MA, ES)
((S1)t ((S2)t
ES1 ES2 This works fine for minor variability
Problem: response to step changes not immediate, forecast may
2 + be late in reacting to trends
-1
1
ALPHA = 0.3
t Demand S1 S2 2*S1 - S2 • Another approach is to learn about the underlying
0
1
0
0
0.00
0 00
0.00
0.00
0 00
0.00
0.00
0 00
0.00
properties of the demand time series
2 1 0.00 0.00 0.00
3 2 0.30 0.00 0.60 Output, yt E.g. demand for turkeys goes up every Christmas
4 3 0.81 0.09 1.53
5
6
4
5
1.47
2.23
0.31
0 3
0.65
2.63
63
3.80
(Forecast) • How to analyse:
7 6 3.06 1.13 4.99
8 7 3.94 1.71 6.18 Regression analysis: what factors matter? E.g. weather and
9 8 4.86 2.38 7.34 sporting
p g events to p
predict beer consumption
p
10 9 5 80
5.80 3 12
3.12 8 48
8.48
11 10 6.76 3.93 9.60 Decomposition/Fourier analysis: the idea is that one complex
12 11 7.73 4.78 10.69
13 12 8.71 5.66 11.76 demand time series can be decomposed into a set of simpler
14 13 9.70 6.58 12.82 series
15 14 10.69 7.51 13.86
16 15 11.68 8.47 14.90
Page 97 Page 98
Original Data
500
Fourier Transform
115
118
100
103
106
109
112
10
13
16
19
22
25
28
31
34
37
40
43
46
49
52
55
58
61
64
67
70
73
76
79
82
85
88
91
94
97
1
4
7
The longer the forecast horizon, the worse the forecast • Let e1, e2, …, en be the forecast errors observed over
n periods
The less aggregated,
aggregated the worse the forecast
• A measure of forecast error over n periods is the
Mean Absolute Deviation (MAD):
n
MAD = 1 ∑ | e |
n
i =1 i
• Another measure of forecast error is the Mean
q
Squared Error (MSE):
( )
n
MSE = 1 ∑ e2
n i =1
=1 i
Page 101 Page 102
Assembly
Line Balancing
g
Page 104
Assembly Line
• An assembly line consists of a sequence of operations
• Some operations modify a single part or item
• Other operations assemble two or more parts together
Heuristic Methods for Assembly Line Balancing Longest Sequential Chain of Followers
• Operation: #1 (4 followers), #2,#3,#4 (3 followers),
• Small problems can be solved “by eye”; #5,#6 (2 followers), #7 (1 follower), #8,#9 (0 followers)
l
larger ones need
dhheuristic
i ti methods
th d • Allocate jobs with more followers first
• Break ties byy taking
g jjobs with longest
g p
processing
g times
• In allocating operations to stations
stations, allocate ‘most
most first, thus Op# 4 (1.0) before #2 (0.4) before #3 (0.3)…
deserving’ operation first, followed by second ‘most
Order of allocation:
#1 (0.6) #4 (1.0) #5 (0.6) #8 (0.7)
deserving’, etc. #1 to Station 1
#4 to Station 2
#2 (0.4)
(0 4) #6 (0.5)
(0 5) #7 (0.8)
(0 8) #9 (0.7)
(0 7) (no room on Stn.1)
• Examples of heuristics: #2 to Station 1
#3 to Station 1
1 Longest sequential chain of followers
1. #3 (0.3)
(0 3) #5 to Station 3
(no room on Stn. 2)
2. Total number of followers #6 to Station 2
1.3 1.5 1.4 1.4 etc
3 Ranked
3. R k d positional
iti l weights
i ht (not
( t partt off syllabus
ll b now))
#1 (0.6)
(0 6) #4 (1.0)
(1 0) #5 (0.6)
(0 6) #8 (0.7)
(0 7) Better: Operators can help
Material each other. Might
increase output with
#2 (0.4)
(0 4) #6 (0.5)
(0 5) #7 (0.8)
(0 8) #9 (0.7)
(0 7) third operator.
operator
Bad: Operators birdcaged. No
chance to increase input
with a third operator.
#3 (0.3)
(0 3) Best: Effective operator access.
Manufacturing Cell
Judge Business School
Session 4
Machine level Scheduling
Machine-level
Page 119
Objectives for Today Scheduling
• What is scheduling? • Deciding in what order and when particular operations
should be carried out
• Scheduling machines in a job shop environment
• For projects:
Minimising
g average
g completion/flow
p time
Scheduling is essentially project management
Minimising maximum lateness Critical Path Analysis (CPA)
Minimise number of late jobs
Mi i i average ttardiness
Minimise di • For batch and flow production:
Minimise makespan in a 2-machine flowshop Standard routing, but some variety. Computer-planned schedules
(MRP / MRPII / ERP), or visual tools (Just-in-Time / Lean)
Cyclic scheduling, capacity planning key (bottlenecks)
• For job shops (our topic today)
No standard routing, no standard lead-times
Multiple machines, identical or different, parallel or in-line, etc...
M/C 1
Washing Welding Brazing
M/C 1 M/C 1 M/C 2
M/C 2
Process split into independent work
centres complex routing and scheduling
centres, scheduling.
Page 123 Page 124
Scheduling Objectives Minimising Average Completion Time (1 m/c)
The objectives we might face in scheduling are: Job A B C D
M/C 1
Minimise average
g completion/flow
p time of a set of jjobs Processing Times 11 3 4 2
Minimise the maximum lateness
Minimise the number of late jobs • If we do jobs in alphabetical order, and start at t=0, the schedule is:
Minimising Maximum Lateness (1 m/c) Minimising the number of late jobs (1 m/c)
Job A B C D Job A B C D E F G H I
M/C 1 M/C 1
Processing Time 3 3 4 5 Processing Time 2 7 3 8 4 4 6 8 5
Due Date 9 8 16 9 Due Date 5 10 15 22 23 24 25 30 33
• New
N EDD order
d iis: • Final schedule is:
J b
Job Job
Completion
l Time Completion Time
• Observation:
Ob ti minimising
i i i i average llateness
t iis a d
daft
ft id
idea!! • W
We could
ld ttry EDD
EDD; if th
there iis only
l one llate
t jjob,
b EDD
minimises the average tardiness
• Lateness = (completion date) – (due date)
hence it could be negative • But for more than one late job, there is no algorithm for
this problem
• But in real life, there is often little/no benefit from finishing
a job early • However, there is a heuristic: the Modified Due Date
(MDD) Rule: put jobs in order of increasing MDD
• Instead,, define Tardiness of a job
j = maximum of 0 and
the Lateness of the job (we write: max(0,Lateness)) • At time t, MDD = the maximum of the due date and the
earliest time at which we can complete a job:
• Minimising average tardiness is a meaningful objective
i.e. MDDi = max(di,t+pi)
• How do we achieve it? where di = due date, pi = processing time for job i
Job A B C D E F G H I Job A B C D E F G H I
Here, ... has the smallest MDD (...), and completes at t= ...
Job A B C D E F G H I Job A B C D E F G H I
Here, ... has the smallest MDD (...), and completes at t= ... Here, ... has the smallest MDD (...), and completes at t= ...
Job A B C D E F G H I Job A B C D E F G H I
Here, ... has the smallest MDD (...), and completes at t= ... Here, ... has the smallest MDD (...), and completes at t= ...
Job A B C D E F G H I Job A B C D E F G H I
Here, ... has the smallest MDD (...), and completes at t= ... Here, ... has the smallest MDD (...), and completes at t= ...
Job A B C D E F G H I
Job A B C D E F G H I
Processing Times 2 7 3 8 4 4 6 8 5
Processing Times 2 7 3 8 4 4 6 8 5
Due Dates 5 10 15 22 23 24 25 30 33
Due Dates 5 10 15 22 23 24 25 30 33
Modified Due Dates
Modified Due Dates
Final job is ..., which completes at t=...
Here, ... has the smallest MDD (...), and completes at t= ... How to measure the quality of my schedule?
Final Schedule:
Original Due Dates:
Total tardiness is , the average tardiness is
M/C 2 A B C D E
Jobs A B C D E 6 11 13 19 25 28 32
Page 151
Marketing, Design, Manufacture
Order Fulfilment
Strategies
Page 153
This requires co-ordination within and between firms aiming at: Order fulfilment strategy
Balanced flow of work - all tasks take the same time How far back does the order go into the supply chain?
Steady demand for products - and hence for inputs
Which is appropriate under which circumstances?
Ideal demand is smooth and predictable:
Total demand = maximum output capacity of resources Two basic factors are important
Any changes are perfectly forecast in sufficient time to allow capacity
change Production Lead-time P: How long does it take to make the
But…. product?
Real demand is usually not predictable Demand Lead-time D: How long is the customer willing to wait for
Demand has peaks - lunchtime/Saturday/summer etc the product?
g p
Demand varies through product life cycle
y & competition
p
Page 155
The P:D Ratio P:D Ratio
Incoming
g P
Customer D Engineer-to-Order
Orders
Customer Lead-time D Design
P
D Make-to-Order
Components
Start Production Process Lead-time P Finish P
D Assemble-to-Order
Components
P D
Make-to-Stock
FGI
Hal Mather, 1988, ‘Competitive Manufacturing’, Prentice Hall Time
Supply Chain Factory Marketplace
p
Page 159
Order Fulfilment in Electronics Sector - Mass Customization
E
Example:
l DELL
..an oxymoron?
Sales Order
Component Assembly 1-2hrs The need to ‘customize’ mass-produced goods to
Warehouse 25min
5 customer needs
An umbrella concept
Suppliers
pp Logistics
Customer
Centre Build-to-Order
Long Assemble-to-Order
Transportation 3-Day Order Fulfilment
within UK;
L
Late C
Configuration
fi i
Lead Time
“Merge-in Transit” Customisation at point of use
distribution C t i ti th
Customisation through
h service
i
Production Planning
g
T
Two basic
b i approaches:
h PUSH and
d PULL scheduling
h d li
and Control
R
Raw material
t i l Planning &
suppliers Purchasing Scheduling
Material Requirements
q Planning
g
Goods In/ Component Final Customers
Receiving
g Manufacture Assembly
y FGI
Elements outside El
Elements
t in
i the
th system
t
the system
Central Planning MRP system were invented in 1960s to cope with computational
and
d Scheduling
S h d li complexity of scheduling
Need to plan at top level-item, for all items made in the plant
What happens if components are used in several final products?
Order Order Order
– Computerised inventory control & production planning system
Process Process – Schedules component items and processes when needed - no earlier
Suppliers and no later
Raw #1 #2
Materials WIP Definitions:
‘MRP
MRP is a set of priority planning techniques for planning component
– In a PUSH system, the orders are planned and issued centrally items below the product or end item level’
– Upon completion, the order is moved forward, until the next process is ‘A set of techniques which uses the bill of materials (BOMs), inventory
iissued
d with
ith th
the order
d tto start
t t processing
i it data and the master production schedule to calculate future
requirements for materials. It essentially makes recommendations to
– Hence, the LAST process sees the new order FIRST release material to the production system.’
– This is called BACKWARD scheduling
PLUS MINUS PLUS EQUALS Net • MRP Systems inherently distort demand patterns in the
Req’ments
R ’ t supply chain
Scheduled
Allocations
Receipts
Page 178
MRP is...
A good database
A good transaction processor
Essential source of information and almost impossible to replace in many
p
companies!
MRP is not..
A good scheduler
Why? Just-in-Time
– Assumes infinite capacity & Lean Production
– Works on fixed batches
– Works on fixed lead times
– Schedules backwards,, therefore cannot synchronise
y
Page 188
Traditional vs.. JIT Inventory TPS Elements - Taiichi Ohno
All processes driven to be in control and capable
Standardised work practices
p
Traditional “Simplify, highlight deviations, mistake-proof”
Inventory Level
Problems are natural and are opportunities to learn, not to blame!
Most problems arise from not following standards
Every problem has root cause and counter-measures
Every activity must add value
Average
Inventory Eliminate waste
JIT Make what customers want when they want it, just-in-time
Smooth production “pulse”
Select and invest in people
0 Time
Managers chosen as best teachers/problem-solvers
Empowerment & multi
multi-skilling
skilling
Session 6
Process
#1 Toyota Production
Bottle- Process
I
Neck #3 System and Lean Thinking
R
Resource
Process
#2 ROPE BUFFER DRUM
Page 194
Improvement
p
Gradual / incremental improvements
N lilimit
No it iin ffocus, often
ft extends
t d tto suppliers
li and
d di
distribution
t ib ti
Kaizen Office: dedicated team leading improvement activities
Æ Kaizen and Kaikaku only work in conjunction!
i
improvementt
Improvement
Actual
improvement
“Breakthrough
Improvements” Actual
Lean Thinking
g
improvement
Time
Where does the term ‘LEAN’ come from? The NUMMI Experience
Joint Venture GM/Toyota plant, closed 1982, reopened in 1984
MIT International Motor Vehicle Program
Dramatic improvements compared to previous GM plant
Started in 1979, ongoing to date! Assembly hours/car 36 to 19
Comparative research – the International Assembly Plant Study Transfer to other GM plants took many years
GM management lacked commitment – embarrassment for Roger Smith
Policy forums for senior industry
industry, government and union officials
NUMMI plant visits for management were for brief time periods only
‘Lean Production’ coined by John Krafcik (1989) Visiting teams below critical size
Æ b t NUMMI showed
Æ..but: h d that
th t llean was nott culturally
lt ll bound!
b d!
Policy Deployment
Demand Smoothing
Lean
Value
Stream
Pro
Pro-
JIT Jidouka
motion
Organi-
sation
Cases:
Office
Production Smoothing Lean Retailing
5S / Shop Floor Teams / 7 Q Tools / PDCA
Lean Services
Successful Implementation
Judge Business School
1 Senior management buy
1. buy-in
in and support is a critical
enabler
Rewards and responsibilities often need to be changed
2. Long-term support & consistent objectives are key Session 7
Beware of “Fad
Fad of the Month
Month” Problem Service
3. Ownership of improvements needs to reside at process Quality and Six Sigma
level
Beware of how consulting resources are used Project Management
4 Measures need to be aligned to top
4. top-level
level goal
“What you get is what you measure”!
The “Bottom-up”
Bottom up myth
Page 221
Service Process Matrix
Low
Degree of customisation High
Low
facility & equipment services’.
ct
er contac
e.g.. Airlines, Hotels, e.g.. Car repair,
Fast food ‘Routine’ hospitals
Custome
Service Operations
p
Mass Service Professional
Customers treated as Service
C
similar Costs principally for
High
e.g.. Retailing, ‘elite’ labour.
banking e.g.. Lawyers,
accountants
Page 223
Page 226
2
Page 225
Demand & Revenue Management Revenue Management: How does it work?
Problem: finite capacity, uncertain demand
Price
1. Segmentation
500 Some customers value time
Some customers value money
400
2 Differentiation
2.
P)
BA: LHR
LHR-HAM
HAM
Airfare (in US$ or GBP
y (am)
y (pm)
5 days
3 days
Departure Date
weeks
weeks
weeks
weeks
weeks
weeks
weeks
weeks
weeks
week
Demand
1w
9w
8w
7w
6w
5w
4w
3w
2w
2w
1 day
1 day
ÆIt might make sense to sell below cost at times,
if price paid > (variable cost for empty seat+
g
marginal cost for full seat))
ÆMax profit might not occur at full load!
Page 227 Page 228
Distinguish Order Winners from Order Qualifiers The Kano Model I - Product Features
Order Qualifiers: hygiene factor, needed to be considered by customer
Must be (Basics): characteristics or features taken for
Order Winners: distinguishing factors that drive customer choice
granted. (Hotel: clean sheets & hot water)
Order
winning More is better (Performance): we are disappointed if a
criteria need is poorly met, but have increasing satisfaction the
better it is met.
met (Hotel : response time for room service).
service)
Number of orders
More is
What are the Performance factors?
Delighters
Customer better
satisfaction Neutral What are the Delighters?
Must be
What are the Reversal factors?
Reversal
(T ti i)
(Tontini)
Dissatisfaction
Absent Fulfilled
Presence
of characteristic
Quality
Q lit C Control
t l Acceptance sampling
sampling, inspection
inspection, final testing
Six Sigma
g Source:
www stat yale edu
www.stat.yale.edu
Normal distribution
µ: mean
σ: standard deviation
Key Steps
Statistical tools used to analyse processes
Reached quality plateau of 5
5.2σ
2σ (108 ppm) in 1 year and reduced
throughput time by 90% in many processes
Dedicated ‘Black
Black Belt’
Belt resources in 1991
A formal discipline and structured approach developed
Step
p 2: Covert DPMO into a Sigma
g Level
• Use the conversion table
Cave: A 1.5
1 5 Sigma process walk is not considered here,
here but is commonly factored
into the calculation!
Page 250
Yield % Sigma Defects Per Million
Opportunities
Quality L
Lean Variability
TQM, TQC Production 6σ, SPC
Operational
Responsiveness Level Availability Level (Tools):
Agile, Postponement Scheduling, TPM Eliminate Waste
Kanban,
Capacity Takt Time,
Prod. Control
Prod
Drum-Buffer-Rope, etc.
etc
MRPI+II, ERP, APS
Source: Dave Nave, TOC
Quality Progress 2002
Source: Hines, Holweg, Rich (2004) “Learning to Evolve,
A Review of Contemporary Lean Thinking”, IJOPM
Page 257 Page 258
Project Management &
New Product Development (NPD)
• The
Th kkey distinction
di ti ti tto manufacturing
f t i and d service
i iis n=1
1!
• Project Management
There can be a fixed deadline (2012 Olympics)
There can be a fixed budget (public procurement)
There
Th generally
ll is
i a sett off constraints
t i t that
th t need
d to
t be
b balanced
b l d
• New Product Development
Project
j Management
g
The process from idea, concept, design engineering, prototyping,
testing, to product launch (“Job zero”)
New product development is a critical capability, no more or no
less important than manufacturing, or marketing & sales
• From an operational point of view, NPD is a special case
of project management
Page 259 Page 260
Note: In general, do not crash an activity as far as possible, only as far as necessary.
Step 5
5. Cost of project is given by total normal cost of all activities plus the cost
incurred by crashing
Page 261
Exercise Addenbrooke’s Hospital I Exercise Addenbrooke’s Hospital II
• The Head of Department at Haematology wants to The Department Head knows how long each activity takes, its cost, and
establish a new diagnostic service for Leukaemia patients. the cost and extent that expediting
p g is p
possible:
(a) Select operators normally takes 3 weeks at a cost of £4000, but could
• The project budget is £40,000, it needs to be in place be reduced to as little as 1 week, if he is willing to expend £8000.
within six weeks, and the procedure requires a new piece
of equipment to conduct the test. (b) Procure equipment takes 2 weeks at a cost of £5000. He cannot
obtain the equipment more quickly, at any price.
• The project has the initial steps: (c) Complete EU paperwork takes 6 weeks at a cost of £10,000, which
Select operators for the new equipment can be expedited by hiring more clerks, who can get this down to 4
Procure the new piece of equipment weeks,, if he is willing
g to pay
p y £14,000.
,
Complete auditing paperwork on Medical Equipment Purchases (d) Train operators normally takes 4 weeks, at a cost of £8000, but can
be done in 2 weeks, but then the cost is £13,000.
• Further steps include
Train the operators (e) Test equipment normally takes 3 weeks and costs £6000, but can be
done in 1 week, if he will pay £14,000 instead.
q p
Test the equipment for safety
y
Page 267
ory
Average
Days of Invento
“Optimises” intra-firm processes with Focus: dynamic interplay between
Min
respect to the impact on the focal firms
50
firm, and immediate customer
Sub-optimisation
Sub optimisation of the operation at
the local firm in order to support
holistic strategy
0
Local versus Global Optimisation:
mbly WIP
Bought--in Parts
se Parts
mbly WIP
mbly WIP
ed Parts
On-siite Parts
d Transit
Disttribution
ustomer
Inbound Transit
Material
Dispatch
SCM is the differential decision making when
Raw M
In-hous
Cu
Finishe
Pre-Assem
Outbound
Assem
Assem
considering the firm within its value chain network!
ed Parts
bly WIP
bly WIP
se Parts
On-sitte Parts
Outbound Transit
Distrribution
ustomer
Transit
Material
spatch
2. Diagnose
g the cause for the misalignment
g
Assemb
Assemb
Inbound T
Dis
Raw M
In-hous
Finishe
Cu
Arms-length & transactional Long-term & relational Long-term & relational • Problem solving: exit, voice or hybrid strategy?
Open for new suppliers to bid Set of potential suppliers mostly Open to new suppliers
suppliers, after a vetting
closed period
• Single, dual or multiple sourcing?
Competitive selection by low bid – Selection based on capabilities -- Competitive assessment -- intermediate
frequent and speedy exit exit rare and slow frequency and speed of exit
Design simplified by customer to enlarge Design controlled by customer, Larger design role for supplier, attention
pool of suppliers supplier involved via resident
engineer
to supplier design capabilities
Æ What strategic
g value does the supplier
pp
No equity stake Often an equity stake Equity stake depends on criticality of
contribute?
technology
Contracts for governance Norms /dialogue for governance Norms + process management routines
for governance
Æ Quality
Quality, Cost,
Cost Delivery,
Delivery Service..
Service but also
Codified procedures Tacit procedures Process management routines make
Innovation, Technology, Responsiveness, etc.
procedures explicit
p p
BV Attempt to have
50% in number of platforms best of both worlds?
100%
30% in capacity
p y
RNPO
20% in administration and sales cost
20% in number of distribution subsidiaries
Common global purchasing turnover Nissan and Renault
10% iin number
b off retail
t il outlets
tl t 2001: 30% Æ 2008: 85%
Page 287 Page 288
MC-AFL: Administration for Affiliated Companies, set up 2004: industry-wide steel shortage
g
to improve relationship with suppliers after rigorous
Nissan stopped production for 5 days in November
November-
supply chain restructuring
December 2004, and again for 2 days in March
New Group Enforcement: part of the Nissan Production 2005
Way
Æ 40,000
40 000 cum
cum. units loss of production
E.g. 2005: Nissan acquired 42% of previous supplier
Calsonic-Kansei Æ 16 billion JPY (£120 million) loss in profit
Forecast Collaboration
Collaborative Collaborative
Yes
Forecasting/ Forecasting and
EPOS Exchange Replenishment
Type 0 T
Type 2
Traditional Vendor
No
Supply Chain Managed
Replenishment
F
No Yes
Inventory Collaboration
Page 299
Where does the money go? Take a £15 ‘Made in China’ Key Driver of outsourcing:
plastic ‘Professor
Professor Dumbledore’
Dumbledore figure … Labour Cost Differential (domestic)
£15
Employement and W ages in the US Auto Industry 1980 - 2000
600 OEM 50
550 Supplier
OEM wage
500 40
o yees
Supplier wage
450
$ per hour
Price
300 20
250
200 10
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
Adapted from Slack et al. 2007 Source: Holweg and Pil (2004)
Key Driver of outsourcing: But not only labour costs: Assessing
Labour Cost Differential (internat.)
(internat ) Market Potential
Measure of potential: Vehicles in operation:
(Persons per vehicle) passenger cars (CV),
(CV) ratio of passenger cars/CVs
Germany $29.91 Korea $10.28 Argentina: 5.5 Argentina: 5.7m (1.5m) 3.8
Brazil: 77
7.7 Brazil: 19 4m
19.4m (4 8m)
(4.8m) 40
4.0
Mexico: 4.6 Mexico: 15.6m (7.9m) 2.0
US $21.97 Czech Rep. $4.71
China: 37.5 China: 11.0m ((24m)) 0.46
UK $20 37
$20.37 Brazil $2 67
$2.67 (2002: 87.6) (2002: 0.30)
India: 85.8 India 8.1m (4.9m) 1.7
Japan $20.09 Mexico $2.48
Czech Rep: 2.2 Czech Rep 4.1m (562k) 7.3
Spain $14.96 China $1.3 Russia: 4.3 Russian Fed: 26.8m (5.9m) 4.5
Poland: 2.5 Poland: 13.4m (2.3m) 5.8
Source: US Department of Labor Statistics, Wards, ONS. USA: 1.6 USA: 135.1m (108.9m) 1.2
Germany: 1.7 Germany: 46.6m (3.2m) 14.6
Japan: 17
1.7 Japan: 57 5m
57.5m (16 7m) 3.4
(16.7m) 34
Page 306
Outsourcing: A word on Nike... The 3 Supply Chain ‘Enemies’
1. Inventory & delays
Time worsens ‘swing’
swing of amplification
Decision delays require stock
Safety stock decisions send false signals
2. Unreliability or uncertainty
Any kind of uncertainty needs to be covered with inventory
Unreliable processes cause unreliable delivery
Page 309
Thank you &
Good luck!
Page 311