Audit Report#2 - Group 11
Audit Report#2 - Group 11
1. Executive Summary
I. Objectives of this report:
The report is submitted as part of the Capstone Research Project deliverables. The deliverable
summarizes the results of an analysis of a previous project completed by the Sponsor's
company. The report's goal is to learn by critically assessing the sponsors' practices and utilizing
expert judgment to make recommendations that the sponsors might use in future initiatives.
The project team creates the report after doing extensive qualitative and quantitative research
on the sponsor's practice. The data for the studies were gathered through Sponsor interviews
and knowledge-sharing sessions that focused on the sponsor's project as well as the tasks and
procedures done throughout the project cycle.
II. Purpose of Sponsor Project
The project is being worked on by the Project Team, which reports to Humber College's Project
Management Department. The project's goal is to get first-hand project management
experience and put all the knowledge areas covered by the Project Management Body of
Knowledge to use (PMBOK). The team will try to comprehend the procedures that were
followed during the sponsor's earlier project. The project also provides the team with the
chance to operate in a setting that is professional and offers first-hand experience. The team
interacts with a project sponsor from the industry and collaborates with them to manage and
carry out a project.
III. Audit Approach Results & Lessons Learned
The audit was directed by the Project Team in the wake of acquiring the necessary information
from the support by means of meetings and information-sharing meetings. The review was
directed at the Quantitative and Qualitative parts of the task. The qualitative audit contained
inquiry questions considering the sponsor's training and the quantitative review estimated the
consistency score of the support practice. The consistency score was produced after estimating
the Tools and Techniques embraced by the sponsor and aligning them with the PMBOK (project
management body of knowledge) standard.
IV. Key Findings
The key results found after completing the audit on the Sponsor's project were that the sponsor
used an average of about 80% of the tools and methods during the project's execution. The
sponsor's company has a small PMO team managing the project's major project management
tasks, and the sponsor's organization has placed a high value on project management based on
the structure and principles provided in the Project Management Body of Knowledge.
V. Key Recommendations
The Project team's key recommendation to the sponsor would be to integrate the PMBOK
techniques into the offshore operations as well. As teams were working on both inshore and
offshore teams, it would be extremely beneficial for the organization if the offshore teams could
also implement PM strategies into their day-to-day operations as resource managers.
3. Audit Results
1.1 Project Integration Management
Sponsor's Practice
The PM was involved in the process of establishing the project charter, as were expertise area
specialists in the fields of banking, finance, and IT. These experts were active throughout the project
to supervise teams and throughout crucial process activities. It also included the process of applying
past project information and benchmarking goals and success criteria. The project plan was created
based on the needs and requirements of the project, which were gathered from the clients. Regular
meetings were8 held with the sponsors, clients, and operational teams to stay on schedule, create
deliverables, and manage project activity. Project Knowledge and information were gathered and
kept track of in PMIS software and scheduling tools such as MS Project, Jira, etc. To The most
significant part of doing Integrated Change Manage, along with expert judgement to examine
feasibility and cost-benefit, was data analysis to monitor and control the project as well as make
needed modifications. Clients would propose these adjustments depending on the progress of the
project and their product, and they would be adopted following meetings with the client and project
team. The project closing phase also demonstrates a maximum compliance level, and the key
stakeholders for this phase were the clients' operational teams because they were able to measure
the final products acceptance criteria
Findings
Process Areas of Compliance Gaps Quantitative
Result
1. Develop Project 1. Expert Judgement N/A 100%
Charter 2. Data Gathering
3. Interpersonal Skills 4. Team Meetings
2. Develop Project 1. Expert Judgement N/A 100%
Management 2. Data Gathering
Plan 3. Interpersonal Skills 4. Team Meetings
3. Direct and 1. Expert Judgement N/A 100%
Manage Work 2. Team Meetings 3. PMIS Tools
4. Monitor and 1. Expert Judgement N/A 100%
Control Project 2. Data Analysis
Work 3. Decision Making 4. Team Meetings
5. Close Project 1. Expert Judgement N/A 100%
2. Team Meetings 3. Data Analysis
Findings
Process Areas of Compliance Gaps Quantitativ
(ALL evaluation criteria met) (Evaluation criteria unmet) e Result
1. Plan Scope 1. Meetings N/A 100%
Management 2. Data Analysis
3. Expert Judgement
2. Collect 1. Data Analysis Interpersonal and team 57%
Requirements 2. Data Gathering skills
3. Expert Judgement Prototypes
4. Decision Making Flowcharts/Diagrams
3. Define Scope 1. Data Analysis N/A 60%
4. Create WBS 1. Expert Judgement N/A 100%
2. Decomposition
5. Validate Scope 1. Decision Making N/A 100%
2. Inspection
6. Control Scope 1. Data Analysis N/A 100%
Findings
Process Areas of Compliance Gaps Quantitativ
(ALL evaluation criteria met) (Evaluation criteria unmet) e Result
1. Plan Cost 1. Expert Judgement 2. Data Analysis 3. N/A 100%
Management Meetings
2. Estimate Cost 1. Expert Judgement 2. Parametric 1. Three-point estimating 87.5%
Estimating 3. Analogous Estimating 4.
Data Analysis 5. Bottom-up Estimating
6. Meetings 7. Decision Making
3. Determine 1. Expert Judgement 2. Cost N/A 100%
Budget Aggregation 3. Data Analysis 4.
Historical information review 5.
Funding limit reconciliation 6. Financing
4. Control Cost 1. Expert Judgement 2. Data Analysis 3. N/A 100%
To-complete performance index 4.
PMIS
Findings
Process Areas of Compliance Gaps Quantitativ
(ALL evaluation criteria met) (Evaluation criteria unmet) e Result
1 Plan Quality 1. Expert Judgement 2. Data Gathering N/A 100%
management 3. Data Analysis 4. Decision Making 5.
Data Representation 6. Technical
Inspections 7. Meetings
2 Manage Quality 1. Data Gathering 2. Data Analysis 3. N/A 100%
Decision Making 4. Data
Representation 5. Audits 6. Problem
Solving 7. Quality improvement
methods
3 Control Quality 1. Data Gathering 2. Data Analysis 3. N/A 100%
Inspection 4. Testing 5. Data
Representation 6. Meetings
Findings
Process Areas of Compliance Gaps Quantitativ
(ALL evaluation criteria met) (Evaluation criteria unmet) e Result
Plan Resource 1. Expert Judgement 2. Data 1. Organizational Theory 75%
Management Representation 3. Meetings
Estimate Activity 1. Expert Judgement 2. Parametric N/A 100%
resources Estimating 3. Analogous Estimating 4.
Data Analysis 5. Bottom-up Estimating
6. Meetings. 7. Decision Making
Acquire Resources 1. Decision Making 2. Interpersonal and N/A 100%
team skills 3. Pre-assignment 4. Virtual
Teams
Develop Team 1. Colocation 2. Virtual Teams 3. 1. Recognition and 85%
Communication technology 4. rewards
Interpersonal and team skills 5.
Training 6. Individual Team
Assessments 7. Meetings
Manage Team 1. Interpersonal Team Skills 2. PMIS N/A 100%
Control Resources 1. Data Analysis 2. Problem Solving 3. N/A 100%
Interpersonal skills 4. PMIS
Recommendations
I propose evaluating risks early in the project cycle so that the project team has enough time to create
risk responses and knowledge about different situations to make an educated choice.
Findings
Process Areas of Compliance Gaps Quantitative
(ALL evaluation criteria met) (evaluation Result
criteria unmet)
1. Plan 1. Expert Judgement N/A 100%
Procurement 2. Data Gathering and Analysis
Management 3. Source Selection Analysis
4. Team Meetings
2. Conduct 1. Expert Judgement N/A 100%
Procurement 2. Data Analysis
3. Interpersonal Skills
4. Team Meetings
3. Control 1. Expert Judgement N/A 100%
Procurement 2. Claims Administration
3. Data Analysis
4. Inspections
5. Audit Meetings
Recommendations
We would propose developing a project procurement strategy at the project planning phase to aid in
the successful management of the project procurement procedures.
Recommendations
Defining rules that regulate agile and complicated projects early on would be a recommendation since
having a pre-defined manner of dealing with changes would make handling agile projects more efficient.
4. Appendix A
Audit Questions and Responses
Knowledge Process
Powerful Question Sponsor’s Response
Area (# and name)
The main concern while defining the scope
depended on the earlier scope and just
addition of few things needed to be done.
2.1 Plan The project manager, marketing team, QA,
How was the scope
Project Scope Scope and the other subject experts presented
of the project
Management Management their requirements and sent them to the
decided?
CEO for decision and approval. Meetings
were even organized with internal
stakeholders to list in-scope and out-of-
scope activities.
How was the The current project's scope was
current scope of unchanged, but there were a few small
the project adjustments needed, such as making the
Project Scope
2.2 Defining substantially program function offline and requiring that
Management
Scope different than that any data submitted be updated and saved
originally defined in later to improve usability.
the approved
project plan?
The Work breakdown Structure (WBS) was
created earlier, and some minor changes
How was the WBS
Project Scope were made to them and were sent to the
2.3 Sequence created and was it
Management CEO for approval before sending it to the
Activities approved by the
marketing team. It was approved by the
manager?
CEO and the planned activities were
carried out as per the schedule.
Weekly meetings were held to ensure that
Project Scope How is the the project was on track in accordance
2.4 Validate
Management validation of scope with the triple constraint, and quarterly
scope
performed? touchpoints were maintained to regularly
validate scope.
As the entire application needed to be
Are milestone developed in the three months that were
Project Scope deliverables stated as the deadline in the previous
2.5 Control
Management effectively tracked phases, the project's milestones were
Scope
and compared to efficiently tracked. When necessary,
the project plan? schedule compression was also carried
out.
Process
Knowledge
(# and Powerful Question Sponsor’s Response
Area
name)
Meetings with interdepartmental heads to
How did you
Project pick resources were utilized as internal
6.1 Acquire manage the
Resource resources to obtain resources. Meetings
resources resources to ensure
Management with the technical team were carried out to
project success?
lead the project to success path.
Project 6.2 Develop Does the project The current project team had worked
Resource team team have the skills together on the earlier project, and they
Management necessary to had the some prior industry experience and
Projects Performance Possibilities: We Are Leading The Way
Page 16
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
Process
Knowledge
(# and Powerful Question Sponsor’s Response
Area
name)
The impact of the issue on the project and
the project objectives that may be
How were the influenced by these issues might be
Project Risk 8.1 Identify unimplemented risk included in the description of the issue and
Management Risk strategies escalated the priority of the risk strategies are to be
to an issue log? created and implemented and the one who
is responsible to solve is assigned to it and
the deadline is provided.
A more modest PM group would deal with
Who were the vital the risks of the project and go about as the
stakeholders in proprietor of the risks and this future
8.2 Plan
Project Risk arranging risk addressed in the survey gatherings and
Risk
Management reactions and touchpoints to be made noticeable to the
Response
activities to reduce group and senior partners. Any open
possible dangers? hazards identified during these discussions
would then be addressed.
What were the The chain of steps including identifying the
8.3 Perform
provisions made to threats, its probability and impact, the ways
Project Risk Qualitative
access project risks to monitor and review it were performed to
Management Risk
at various project access project risks during daily meetups.
Analysis
stages?
Decisions
1. Report and dissect discoveries from the meeting.
2. Sponsor to survey record of Final Audit report and give criticism to the teacher.
3. Make a final report regarding submission and offer it to the sponsor.
4. The following meeting is to be booked for 15th July to review the Final report with the sponsor.
6. Appendix C
Quantitative Approach
The formula used to analyze and calculate the Process compliance of the individual processes
was as follows:
Process Compliance = # of tools and techniques implemented on the project / PMBOK standard
number of tools and techniques for that knowledge area.
The formula used to calculate the compliance score of the Project Scope Management
knowledge area is as follows:
Knowledge Area compliance = Sum of the compliance scores of the processes / Number of
Processes.
The formula used to calculate the process and knowledge area compliance scores for the
knowledge areas of project stakeholder management and project communications management
produced a quantitative compliance score for the knowledge area.
7. References.
A Guide to the Project Management Body of Knowledge (PMBOK® Guide)–Sixth Edition. (2017). Project
Management Institute.
8. RACI Chart
Team Members
Tasks
Hetvi Sheth Masumi Thakkar Prem Kamdar
1. Executive Summary R A C
2. Noting down sponsor reaction and A C R
approval
3. Auditing project Integration C R A
Management
4. Auditing project Scope Management R A C
5. Auditing project Schedule A C R
Management
6. Auditing project Cost Management C R A
7. Auditing project Resource R A C
Management
8. Auditing project Communication A C R
Management
9. Auditing project Risk Management C R A
10. Auditing project Procurement R A C
Management
11. Auditing project Stakeholder A C R
Management
12. Completion of Appendix A C R A
13. Completion of Appendix B R A C
14. Completion of Appendix C A C R
Legend: R=Quality Responsible, A=Accountable, C=Consult, I=Inform
9. Rubric
1. Exec Summary The following areas are complete and professional, with no
spelling or grammatical errors and does not exceed one page:
Objectives of this report, Purpose of Sponsor Project, Audit
Approach Results, Key Findings, Key Recommendations. /3
3. Integration Audit
Results /2
4. Time Audit
Results /2
Sponsor's Current Practice described using neutral facts. Findings
5. Cost Audit Results /2
demonstrate student analysis/ show opinion with rationale and
specific examples. All processes covered in Areas of Compliance
6. Quality Audit
OR Gaps. Quantitative Results are clear and logical. At least one
Results /2
reasonable recommendation included. No spelling or grammatical
errors. Consistent formatting follows the template, headers clearly
7. Resources Audit
identified, margins and white space reasonable, etc.
Results /2
9. Procurement
Audit Results /2
10. Appendix A: Audit Questions and correlating responses for each knowledge area
Questions & process presented in table format with consistent summarization.
Responses No spelling or grammatical errors. /2
11. Appendix B: Agendas, minutes and any other records from each meeting
Original Notes & provided. No spelling or grammatical errors.
Minutes /0.5
12. Appendix C: Three clear and complete formulas provided, logical and followed.
Quantitative
Approach /0.5
13. Reference Complete, accurate and properly formatted using APA style. /0.5