Pert
Pert
edistribution
Pfaq curve
Frequency
Of
no
activity
BBB jemadar
I
Me
É K I I EE
ay
Cir ma E
Pessimistic
NOTES
Properties of frequency distribution curve
1 Mean time I X t Xa t Xn
n
Probability Distribution
In frequency distribution we me
analysis
behaviour but in probability
group
an the distribution
distribution we analysis
of probability values of diff all possible
outcomes
a
f
µ
A probability distribution curve is plot of
function f n teamed as Probability
distribution
function w r t to time Height of which
is standauized such that area under this
curve is
unity A j y du
Ex dn
NOTE
The ordinate of this curve for
absicca x does any
not gives probability
but function f x
Hence probability at point X is given
any
by ratio of area of curve upto that point
and total area of the curve
P x Area of curve upto x
Total area
IT X dx
Fx dx
f x dx
if P.D.ci symmetric about open it is
teamed
normal Gaussain Bell shaped curve
as
and it is not symmetric about open it is
termed as B distribution curve
Limits Areal
I 36 0.15 I
o
N X 50
fo I
36 Assumptions
36 error at 3
fp
X IO 68
I 120 95 Ap to 5 30
I 36
I 30 99.7 tp to 60
BE
1
A
age time in which an activity
or mean
can be completed ITit is the time
in which 507 chance in t for completion
of an
activity
If the shapeof probability distribution
its known is expected
curve AN for activity
time can be calculated directly
But practically it is not known1 Hence
this time is computed by taking
weighted
by
te to 4than
Ip6
BE
pm Im
I
i
a
an
Central limit theorem
tell te 23 te 34 teas
2 z 4 5
10 B Fei
in teej
13
j t 27 Imax
a ai
t j 29
tei 2g
am
it UM.TEi
fi g
TEJ Tei tei j man
Slack
It is the time
by which occurance of an
Mhm
slack Te 15
A
If 0
S TL TE 7 O
Ti TE 7 R
ve slack indicates Te 10
1 The events are ahead
running can
of the schedule hence be delayed
by time value equal to slack without
delaying project
2 These events are termed as sub critical
event
B S
f S Slack O
TL TE D TL TE
e Slack indicates that this event is on
schedule and we can not afford the
this event
delay in the occurance
mm of
in occurance this event of
as
delay
would delay the entire project
2 These events are termed as critical event
C
If Slack O
S TL TE C O
TL TE Te 10 day
g u 7
TE 13
day
the slack indicates that this event is
running behind the schedule
These events are termed as super critical
event
Critical Path
Critical Path is the longest path in terms
of time in network in which the project
can be completed
Critical path is shortest path in terms of
time in which project can be completed
as
early as possible
Critical path is that path which joins
critical event C E for which slack is
zero
Intase a network has multiple critical
path then emphasis is made on that
critical
path whose variance on standard
deviation is more
NOTE
As per central limit theorem
variance
of any path critical path it will be
equal to sum of variance of activities
along that path or critical path
Question The expected time of completion
in days for each activities of
network is shown in the fig
Determine
the critical path if scheduled
completion time is 21 days
te 6
2 y
9
te te
tess te 6
n 3
f
te te
s
te te
te 3 test
z a 8
E
E
E
E
E Fffftd
E
so
The
probability of completion of the project
in schedule time is computed as follows
STEP
Determine standard deviation of project
along critical path Use central limit
theorem
im i
r
fue of standard deviation
of critical activity on variance
STEP
Determine Ts Te and expressed it in
terms of parameter i e probability
factor on normal deviate L
I Ts and this 2 is linked
ITE with
I
probability
I 0 2
Probability 50 84 19 97.79 99.9 7
L I 2 3
15.9 2.3 0.1
Activity to ten tp te r
HEY
1 2 2 5 8 5 I
2 3 8 11 20 12 4
2 4 4 7 16 8
2 5 4 9 20 10
3 4 O O O O O
3 7 3 5 13 6
9 6 7 10 13 10 I
5 6 3 7 17 8
6 7 2 3 10 4 1.77
7 8 2 4 6 4 0.44
72 31
5517 8
Tu 31
y
I
8 8
T
9 6
TEES
T D FEI't g
TE 227 1235
2 27 520
5 0 8 0
g
TE 19
Te 19
Critical Path 1 2 3 4 6 7 8
6 922 6223 6324 6425 6627 672 8
Iii r I a OH 1.77 0 44
6 2.86
I 84.1 95 p
motor
97.7 1 2
2 2 1 X 95.84
84.1 97.7
I 1.80 I
1 80I Ts 35
2 86
Ts 40.15 41 days
iv Ts 30 I
days III
30 35
2 86
1.74
L P
I 15 9 P 15.9 15.9 2.3
X
2 2 I 2 75
P 5.79
BEBEE
BEE
pm
e ot3PBA
me