Foreword
5
Operational excellence is the prerequisite to reach our profit and growth tar-
gets. The top+ philosophy and the Siemens Management System with the com-
pany programs Innovation, Customer Focus and Global Competitiveness are a
solid base for driving and supporting successful business.
And PM@Siemens is an important initiative for our project-oriented business
which accounts for 50 % of the whole company. So, excellent project manage-
ment is crucial for the global competitiveness of those businesses. Successful
project management first of all is continuous and sustainable improvement of
the processes towards process excellence. This has to be done in all project-
related businesses and especially in line with the specific business require-
ments.
PM@Siemens as an overall Inititative supports this by
Harmonization and standardization of processes, methodologies and tools
Offering a platform for best practice exchange and transfer
Providing tools and systems for performance measurement
Providing assessments to measure the maturity of the processes and to
identify fields for improvement.
Finally, however, it is the people that make the difference. Therefore, the well-
designed programs for the qualification and development of Project Managers as
“functional experts” have to be implemented worldwide.
PM@Siemens is a successful approach for driving process excellence and its imple-
mentation Siemens-wide - in all related business units at headquarters and in the
Regions.
Johannes Feldmayer
January 2006
6
The goal of the PM@Siemens initiative, which was launched in fiscal 00/01, is to fur-
ther improve our success and profitability in designing and handling projects.
Effective measures have been defined on the basis of best practices, and most have
been introduced. However, there is still much to be done if we are to reach our goal
of directly contributing to higher earnings at Siemens through systematic process
discipline in our projects. Our focus now is on improving the early stages of projects,
particularly calculation, bid preparation and project start-up.
In an effort to firmly establish the PM@Siemens system in the Groups and Regions,
5400 employees have been informed of the initiative’s contents through the
“PM experience” project simulation. Soon the number of employees who have gone
through the simulation will exceed 10,000 and include employees on every conti-
nent. In line with the principles of People Excellence, PM@Siemens places particular
emphasis on the 5000 and more project managers. The qualifications-building
opportunities in project management that are offered worldwide through the
PM@Siemens Academy are supported by Learning Campus.
Introducing best practices and building skills and expertise is one thing. Actually
living the discipline is something else entirely. That’s why the PM@Siemens initi-
tive requires regular assessments by special assessors from Corporate Technology.
More than 70 units will have their discipline examined and critiqued objectively in
accordance with a proven maturity method by the end of this year. We plan to meas-
ure our progress in “lived” project management on a regular basis in the future.
I wish you continued success with your projects and continually improved contri-
butions to profitability through good project management.
Edward G. Krubasik
November 2005
7
PM@Siemens continues to systematically pursue the initiative’s goals that were
drafted in October 2000. That is, to steadily improve our processes. The current
focus of the initiative is on the global rollout, the early stages of projects and
making long-term improvements to all project organizations worldwide.
As globalization progresses, the Regions must take on more and more responsibility
for projects. The global rollout will create the transparency needed to purposefully
implement issues relevant to PM@Siemens and thus develop and secure expertise
in projects business. At the same time, PM Future World will give the Regions a tool
with which to select and certify qualified project managers. All of these activities
should ensure the availability of the right project management expertise in the
Regions.
Many of the problems that arise during project handling originate in the early
stages of the project (launch and start-up). In addition, having suitable project
managers available and putting together a project team on time is still often a
major challenge. That’s why another focus of the initiative will be on analyzing and
improving these situations in the future.
Furthermore, for all project organizations in the Groups and Regions the cooperate
department CT SE will determine the current level of maturity by way of Maturity in
Project Management Assessments (MPM Assessment). The results of the assess-
ments will be discussed with the project organizations and corrective actions will be
developed. This will help improve the project organizations for the long term and
serves as yet another step toward enhancing the profitability of our projects.
We have already achieved a great deal. Now we have to continue to systematically
implement the best practices, improve processes for the long term and take on and
resolve further developments. To do so, we need you on board. We need everyone
who has an impact on the flow and outcome of our projects.
8
w
vie
er
Ov
» Project Management –
the Siemens way
«
Overview
Project Management – the Siemens way
Overview
11
Status, Developments, New Topics
The PM@Siemens initiative includes only We have agreed on the following project
projects that focus on Group-external cus- definition:
tomers.
Projects that focus on Group-external
Also, as we were developing the cross-Group customers are defined as projects that
project categorization system (see question provide uniquely defined and temporally
5), it became clear that we needed to clearly bounded services in accordance with
define which projects are relevant to customer-specific requirements, and for
PM@Siemens. which reliable cost and profit calculations
can be made. Furthermore, there is a con-
tract in which the obligations of the par-
ties are clearly defined (services, prices,
deadlines, duties to cooperate).
The description above generally applies to
plant business, solutions business and serv-
ice business. Pure component business and
product delivery business are not considered
to fit the definition of “relevant project busi-
ness.”
The exact differences between the relevant
business types are explained in further detail
in Module 1, Processes and Roles.
12
2. How has project business at Siemens developed,
and how mature is it now?
13
3. How can we efficiently organize the
worldwide rollout of PM@Siemens?
The Global Competitiveness Board Steering The current classification is shown on the fol-
Committee has decided to cease concentrat- lowing image. Contacts and future region-
ing the rollout only on European countries al/national divisions will be updated on the
and the United States and intensify the roll- PM@Siemens home page.
out worldwide.
For this purpose, a global structure was de-
veloped for the initiative. Countries were
chosen on each continent to act as drivers
and multipliers for the content of
PM@Siemens and named as “Hubs” for the
entire Region.
Overview Fig. 1
14
A “Hub” bundles the reporting, suggestions, The totality of all Group and hub coordina-
and queries from several Regional Com- tors forms the “PM@Siemens Global
panies and acts as the local PM@Siemens Coordinators Board,” which works together
expert. The management of the hub coun- to define the standards and specify the core
try names a responsible hub coordinator themes of the initiative. This allows the
who supports the operative implementation Regional representatives to be directly inte-
of PM@Siemens in all countries assigned to grated into the initiative. They take on
the hub. The hub coordinator represents responsibility within the initiative, bring
these countries in the global PM@Siemens their concerns directly into the discussion
initiative. and get all necessary information first-hand.
Development of the worldwide hub struc-
ture requires a new and effective communi-
cations model. To do justice to this idea, a
model was developed and approved with
the support of the Regions. This model is
explained in more detail in Module 9,
Transfer and Implementation.
15
4. How do we create more value for our customers
in Siemens One projects?
Large-scale projects with a high Siemens The general project manager must have a
share across all Groups have special signifi- clear mandate endowed with clear authority
cance. They are a lever for additional growth from all affected Groups and Regions. The
and bring Siemens into a position as a pio- success of the project and of Siemens as a
neer who is ahead of the competition. With whole is the main point of focus.
our large selection of products, systems, and
The special role of Siemens One in the
services, we can offer a unique total solu-
various process phases is considered in
tion that allows us to create more value for
Module 1, Processes and Roles.
the customer.
More detailed information is available on
Our challenge is to manage large-scale
the Siemens One Intranet page:
projects and complex projects professionally
http://intranet.siemens.com/siemensone
across all Groups and all Regions. This re-
quires an open and sincere working relation-
ship between the Groups and Regions. All in-
ternal deliveries should conform to market
conditions, be handled openly, and also be
available as a “last call option.”
16
5. How do we categorize Siemens projects in a uniform
way around the world – across all Groups and Regions?
In the past, an important point for the After a successful pilot phase that tested clas-
PM@Siemens initiative was the creation of a sifications rules in various Groups and
uniform project categorization system for A, Regions, an ABC project categorization tool
B, and C projects, including the separation was developed in Excel and archived at the
for small-scale projects (D and smaller) PM@Siemens home page. The tool is a multi-
across all Groups and Regions. Among other ple-choice worksheet with main- and
things, the categorization system is used for: subcluster and customized point distribu-
tions. The maximum number of points avail-
Selecting the project managers
able for each of the main cluster are as fol-
(PM, SPM, PDir) for a given project
lows:
Applying the incentive and bonus
Financial 470 points
program
Contractual 300 points
Applying the standardized Siemens- Technical Complexity 420 points
wide PM career model Organizational
Making decisions about the necessity of Considerations 320 points
certifying responsible employees within
the framework of the PM career model The total score reveals which category the
project is in:
Qualifications planning
A > 1000 points
Application of the PMA+ Assessment B > 500 and <
= 1000 points
C <
= 500 points
17
Level 1 Level 2
Financial 30 95
Order Value
Total Estimated
Risk Volume
Project Profit
Gross Margin
Category Limits
Triggers Small Projects
A > 1000 points B > 500 to 1000 points C = 0 to 500 points
18
Level 3 Level 4 Level 5 Value
15 30 50 0
medium high very high
15 30 50 0
675 1000 1510
Management adjustment
Total: 0
Category
Überblick Fig. 2
19
Using the ABC project categorization tool However, the following mandatory rules for
may also separate a project, i.e., assign the ABC project categorization tool have
it a category of D or smaller. This happens been set down by the experts from the
automatically based on how the user Groups and Regions of the PM@Siemens
answers certain questions within the multi- initiative:
ple-choice worksheet.
The 4 main cluster and 15 subcluster
The application of the tool must be specified listed here are the defined minimum
in a Group-specific or Region-specific man- requirements and must not be altered.
ner. This means that each Group or Region
The weighting (number of points) for
defines its own initial criteria and/or applica-
the 4 main topics
tion criteria, such as project volume or com-
• Financial
plexity with respect to the contract, technol-
• Contractual
ogy and other general conditions.
• Technical
• Organizational
is set and must not be altered.
Each Group or Region may add additional
subcluster and adjust the point distri-
bution within the specified point totals
for each main cluster.
Top management may upgrade a
project by one level.
20
6. How do we improve the initial phase and create
better conditions for projects to be successful?
PM@Siemens has paid special attention to the “as sold” calculation made by the person
the initial phase of a project and developed responsible for the bid (PM070), which in
the following basic principles: turn forms the basis for providing incentives
to all project participants. It is the duty of
a) Involvement of project the responsible business manager to clear
managers up any remaining discrepancies.
Project management personnel must act in- This process ensures that the project manag-
dependently of sales personnel during the er is involved in A and B projects at a very
bid and realization phase. early stage (see Fig. 3) and able to use his ex-
perience to report any possible risks before
Sales personnel and project management the contract is signed, allowing him to work
personnel must come to an amicable agree- together with Sales to take precautions to
ment on bids and order releases for A and B counter those risks.
projects.
The order profit/loss calculation made by the
project manager (PM100) must agree with
Project
Bid Contract Project
opening &
preparation negotiations handover
clarification
Early appointment and involvement of PM, depending on the complexity and probability of winning the order
Overview Fig. 3
21
b) Recording NCC
(“non-conformance costs” –
cost overruns)
Empirical data show that 60% to 70% of all The results will be aggregated and analyzed
non-conformance costs occur during the ex- by PM@Siemens once a suitable level of
ecution of a project, but these costs actually data quality has been achieved. The analysis
originate back at the acquisition phase of a will be used to derive measures to avoid the
project. most significant NCCs and develop new
standards.
To analyze this trend more closely, a pilot
project during the 2005–06 fiscal year is
now (Jan. 2006) encouraging the Groups to
identify their NCCs, match them to their orig-
inal values, and report them on a quarterly
basis to the PM@Siemens initiative.
As was mentioned at the beginning of this PM@Siemens has approved a planning pro-
section (question 2), MPM Assessments will cess to ensure the professional planning and
be performed on a regular basis for all execution of MPM Assessments in all rele-
project organization units. The PM@Siemens vant project organization units. This process
initiative has set a maturity target level of is described in detail in Module 10, PM
3.0 for the MPM Assessment. As of Assessment.
December 2005, 103 relevant project organi-
zation units had been identified. Most of
these units have already taken their first as-
sessment. However, as a rule, a re-
assessment must be performed every 18
months.
22
8. How do we rank our project managers
in our PM career model?
23
9. How do we create a common PM basis and a
common PM language?
a) Module structure
24
25
How do we organize PM@Siemens?
Overview Fig. 4
Module 9: Transfer and Implementation
Project
What parts of How can I
this do I need to support everyone
support small Module 1: Processes and Roles involved with
projects the project with
efficiently? common IT?
Module 12: Module 2: Contract Management Module 7: Operative Quality Management Module 6:
Small Projects PM Portal
Project Controlling
Modul 3:3:Projektcontrollng
Module Module 11: Project Purchasing
Module 1 1.1 Implement project stages with the described milestone system and quality gates
Processes 1.2 Implement required results for milestones
and Roles 1.3 Implement project roles
1.4 Implement project steps
Module 2 2.1 Implement independent contract management function
Contract 2.2 Implement full-time contract managers in the bid and negotiation stage for
Management the highest project/risk class
2.3 Implement documented bid/no-bid process/release to prepare bid
2.4 Implement bid release process with Group-specific and Region-specific
project and risk classes
2.5 Final bid release by review board; seek input from Group Executive Management or
Regional Management for highest project/risk class
2.6 Provide full-time contract managers to handle projects at the highest project/risk level
2.7 Implement mandatory review for “unacceptable provisions”
2.8 Implement mandatory Group/Region policy for project business
2.9 Ensure intensive use of standards and tools provided
2.10 Hold mandatory training session on contract law and claim management for technical/
commercial employees in Sales and Project Management
2.11 Install contract management community at the Group/Region level
Module 3 3.1 Establish project-driven organization
Project 3.2 Apply integrated project controlling process from bid/no-bid decision to project
Controlling wrap-up, esp. integrated management of risks, modifications, opportunities, and claims
3.3 Implement mandatory milestones/quality gates in the project process
3.4 Implement management-driven project discussion meetings at regular intervals using
standardized reporting procedures
Module 4 4.1 Implement personnel development in project management
Personnel 4.2 Create letter of empowerment
Management 4.3 Conclude goal agreement
4.4 Include project goals in special payments
4.5 Implement project incentive system
Module 5 5.1 Determine qualification needs
Qualification 5.2 Carry out qualification measures
5.3 Safeguard quality requirements for qualification measures
26
PM@Siemens
Modules PM@Siemens recommendations
Module 6 6.1 Use MS Project, Primavera, SAP PS, Spiridon solution “Solution Business”
PM Portal as standard tools
6.2 Work on further development and implementation of the PM portal as a
standard solution for project workstations
Module 7 7.1 Actively integrate quality management function into the project
Operative 7.2 Appointment of Project Quality Manager
Quality 7.3 Drawing up project-specific Quality Plan (Q-plan)
Management 7.4 Systematic project closure
Module 8 8.1 Build project management sub-community
Knowledge 8.2 Implement project learning cycle including Lessons Learned/Project De-Briefing
Management 8.3 Pass on knowledge through coaching in PACT workshops
9.1 Establish implementation process
Module 9
Transfer 9.2 Determine implementation status
and Imple- 9.3 Create PM scorecard
mentation 9.4 Analyze project business
Module 10 10.1 Implement PMA+ assessments using Group/Region-specific specifications
PM Assessment 10.2 Perform CT SE Assessment in organizational units with project business
Module 11 11.1 Ensure early and continuous integration of Purchasing in the process,
Project from acquisition to warranty
Purchasing 11.2 A project procurement manager (PPM) must support each project (this is mandatory)
11.3 Procurement processes defined in a Group-specific manner, including change
management processes, must be complied with
11.4 Customer contract provisions in supplier contracts (“back to back”) must be completely
checked and confirmed with contract management
11.5 Perform project-specific supplier evaluation to lower costs and improve quality for
both internal and external suppliers
Modul 12 12.1 Implement processes and roles for small projects
Small Projects 12.2 Ensure contract management for small projects
12.3 Implement personnel management for small projects
12.4 Perform qualification screening for small projects
12.5 Implement transfer and implementation processes for small projects
12.6 Perform PM assessement for small projects
Overview Fig. 5
27
c) Major changes from Version 3 Module 1 – Processes and Roles:
(June 2003) to Version 4 Integration of large-scale service projects,
(January 2006) including detailed depiction of process
steps (Level 4) and results
Overview: Description of business types relevant
Project definition added to PM@Siemens
Siemens One added Reference to Siemens Reference Process
House (RPH) described in greater detail
Project categorization added
Early project stages added Module 2 – Contract Management:
Module overview figure revised LoA (Limit of Authority) process described
in more detail
Overview of recommendations
re-numbered New topic for recommendation 2.11
Recommendation 2.12 deleted with
no replacement
28
c) Major changes from Version 3 Module 1 – Processes and Roles:
(June 2003) to Version 4 Integration of large-scale service projects,
(January 2006) including detailed depiction of process
steps (Level 4) and results
Overview: Description of business types relevant
Project definition added to PM@Siemens
Siemens One added Reference to Siemens Reference Process
House (RPH) described in greater detail
Project categorization added
Early project stages added Module 2 – Contract Management:
Module overview figure revised LoA (Limit of Authority) process described
in more detail
Overview of recommendations
re-numbered New topic for recommendation 2.11
Recommendation 2.12 deleted with
no replacement
29
s
sse
les
Pro d
ce
an
Ro
» The Secret to Good Projects «
Categorization …
D
C
B
A Small
projects
Plant and solutions
Project type
Service
33
Differences and similarities in
systems/solutions projects and service projects
The main difference between plant and solu- (sub)projects in accordance with the differ-
tions projects and large-scale service pro- ent project management processes (Fig.
jects lies in what happens after project acqui- 1.2):
sition:
In light of this, we can differentiate several
The goal of plant/solutions project is the cre- different kinds of large-scale service projects.
ation of a functional technical solution that
“Greenfield” projects:
is provided to the customer on an agreed-
The customer buys a system from Siemens;
upon date for him to operate.
at the same time, the customer signs a long-
The goal of a large-scale service project, on term service agreement. A new service or-
the other hand, is to build a service organiza- ganization must be formed to fill the agree-
tion (including any required technical solu- ment.
tions, if necessary) such that it is able to pro- Example: Maintenance agreement for trains
vide defined services (SLAs – Service Level supplied by Siemens (TS).
Agreements) to the customer over a longer
“Brownfield” projects:
period of time.
Siemens takes over services for the custom-
Large-scale service projects concentrate on er; these services were previously performed
project categories A, B, and C. The Service in- by the customer itself or by another service
itiative has specified that service projects of provider.
project category D and smaller should be Example: Takeover of maintenance of exist-
handled using the guidelines for small ing industrial systems (I&S).
projects.
“Brownfield” integration projects:
Sometimes Siemens ends up providing a cus- Siemens takes over service activities from
tomer with both a functional technical solu- the customer and transfers them to existing
tion and the services required to operate or expanded Siemens service activities. Ex-
said solution. In this case, the services will ample: Outsourcing business (PTD SE and
be provided by two intermeshed SBS).
34
Types of large-scale service projects and correlation
with plant/solutions projects
Opera-
Acquisition Project execution
tions
2 Brownfield: bid for services for existing systems (e.g., 5-year contract
for services to plant/product-related services)
35
Reference processes for project management:
The first version of a reference process for These latter items will be added to the
the management of plant and solutions Siemens Reference Process House Release
projects was developed by PM@Siemens ex- 4.0 as mandatory processes in March 2006.
perts in 2003 and incorporated into the
The generic stage models for the listed
PM@Siemens recommendations. At the
project types were derived from people's ex-
same time, this process was depicted in the
periences in the Groups and Regions. They
Siemens Reference Process House. This creat-
herald the emergence of a common
ed a common foundation for spreading a
Siemens language for the management of
uniform understanding across the company
the various project types and form the basis
about how to manage such projects.
for further detailed explanation and more
The Steering Committee for the Global com- precise refinement of these models in the
petitiveness company program resolved to business units, e.g., by implementing key
revise the reference process with the goal of performance indicators to measure project
creating a mandatory, Spiridon-compatible management quality, cost, and on-time exe-
process definition with a Detail Level of 4 cution.
and making it available in the Siemens Refer-
In the following, the generic project phase
ence Process House. This goal was achieved
models for the 3 project types are shown in
with the publication of Siemens Reference
an overview:
Process House Release 3.0 in March 2005.
The depiction of the revised reference pro-
cess for the management of plant and solu-
tions projects as a PM@Siemens recommen-
dation is happening at the same time as the
depiction of the reference processes for
large-scale service projects and small
projects (see Module 12, Small Projects) in
this manual.
36
Acquisition
Plant and Solutions Business QG
Service Business QG QG
Small Projects
37
Project execution
QG Plant and Solutions Business QG Warranty
QG
Project Purchasing Construc-
Detailed tion/ Commis- Accep- Project
opening & & manu- Dispatch
planning installation sioning tance closure
clarification facture
Service preparation
QG QG Service Business QG
Project execution
Small Projects Warranty
38
Warranty phase
QG Plant and Solutions Business
Project closure
Warranty
Service operations
QG Service Business
Warranty phase
Small Projects
Project closure
Warranty
39
The depiction of a complex, convoluted The following section takes the generic de-
project management process as a linear piction of the process stages and breaks it
stage model seems very theoretical, since down into a more detailed explanation of
the real-world process often proceeds sever- the process stages, process steps, and mile-
al times through the process stages de- stones for large-scale plant/solutions pro-
scribed, or, depending on the business, jects and large-scale service projects. The
some project stages do not occur at all, or process stages correspond to detail level 3
only in the most rudimentary fashion. The (Level 3) of the associated processes in the
stage model, with its process elements and Siemens Reference Process House; the
milestones as well as its inputs/outputs and project steps are a detail level 4 (Level 4).
roles for each process element, still provides
To ensure that a process stage is completed,
a clearly defined and uniform frame of refer-
each milestone is assigned required results
ence for synchronization, even for sub-
that should be consulted for early detection
projects. Therefore, it is valid for every com-
of project problems (quality gates, readiness
ponent/every system and thus has a practi-
reviews, etc.). Depending on the type of
cal benefit of application.
business, all milestone results may also be
By transferring the model into the integrat- achieved in an earlier project stage, but they
ed project schedule, where the individual must be achieved no later than in the
processes for the sub-projects are chronolog- project phase shown in order to ensure a
ically staggered and interlinked in a sensible smooth process.
manner, this linear process approach also be-
Please see Module 12, Small Projects, for a
comes a workable model for operative
detailed description of these processes for
project business.
small projects.
40
Project management for plant and solutions projects
(Project categories A, B, C)
41
Phase Process step Mile- Results
stone
Bid Hand over bid project to bid project PM040 Bid approval
preparation manager Bid Bid documentation
Set up bid project approval Bid project account
Create commercial & contractual Bid project organization
bid part Change order strategy
Create technical bid part Claim strategy
Define product requirements (PLM) List of supplies and services
Select and evaluate reference LoA documents
product (PLM) Minutes of bid project hand over
Create and provide bid data (PLM) Negotiation framework
Create project execution bid part Project category
Perform risk assessment Project plan
Compose bid Release of bid project manager
Prepare and decide on bid release Risk assessment
If necessary: Terminate bid project
42
Project Determine liability PM080 Archived bid project documentation
handover Update project data Start of Bid project closure report
Hand over project to project project Determination of liability
manager Nomination of Commercial Project
Close bid project and release bid Manager
project manager Nomination of Project Manager
Set up project management Order receipt calculation
assessment Project characteristics
Project handover protocol
Release of bid project manager
Result of project management
assessment
Risk assessment
43
Phase Process step Mile- Results
stone
Purchasing Place purchasing, manufacturing & PM300 Delivery Documents
& service orders Dispatch Dispatch Release
manufac- Ensure fulfillment of orders approval Documented supplier selection
ture Prepare & release products for decision
dispatch Products released for dispatch
44
Acceptance Prepare & perform acceptance test PM650 List of open points
Update customer documentation Customer Preliminary Acceptance Certificate
Perform customer debriefing acceptance (PAC)
meeting Result of customer satisfaction
Request Preliminary Acceptance questioning
Certificate (PAC)
45
Project management for large-scale service projects
(Project categories A, B, C)
46
Bid Hand over bid project to bid project PMS040 Bid approval
Preparation manager Bid Bid documentation 1)
Set up bid project Approval Bid project account
Clarify internal Interfaces Bid project organization
Clarify external Interfaces Change order strategy
Develop and agree service concept Claim strategy
Prepare project company concept List of supplies and services
Analyze business model LoA documents
Review and agree financial model Minutes of bid project hand over
Define governance model Negotiation framework
Plan mobilization/ transformation Project category
Plan end of service provision Project plan
Create commercial & contractual Project plan for bid project
bid part Risk assessment
Create service preparation bid part Drafts of Co-operation agreements/
Create technical bid part Letters of intend
Perform risk assessment Contract proposal
Compose bid
Prepare and decide on bid release “Brownfield” projects only:
If necessary: Terminate bid project Due diligence plan
Define service requirements (PLM)
Select & evaluate service portfolio
(PLM)
Create & provide bid data (PLM)
47
Phase Process step Mile- Results
stone
Contract Hand-over bid to customer PMS060 For PMS060:
Negotia- Process customer feedback End of Due Documented request for due
tions If necessary: Repeat bid preparation Diligence: diligence information
for changes Best and Due diligence agreement
Determine negotiation strategy/ Final Offer Due diligence report
nominate negotiation team (for brown- In case of investments or new legal
Nominate project manager and field pro- entity: Investment proposal
commercial project manager jects only) (I-Vorlage)
Organize and conduct contract
negotiations
Obtain contract approval and
conclude contract
Conduct win/loss analysis
If necessary: terminate bid project
48
Project Determine liability PMS080 Archived bid project documentation
Handover Update project data Start of Bid project closure report
Hand over project to project Project Determination of liability
manager Nomination of commercial project
Close bid project and release bid manager
project manager Nomination of project manager
Set up project management Order receipt calculation
assessment Project characteristics
Project handover protocol (incl. work
product register)
Release of bid project manager
Result of project management
assessment
Risk assessment
49
Phase Process step Mile- Results
stone
Detailed Define overall project plan PMS200 Basis time schedule
Planning Define organizational set-up for Approval of Change order strategy
operations detailed Claim strategy
Define processes planning Detailed realization plan
Define infrastructure and material Order requisitions
concept Project plan
Define communication concept Quality documentation
Plan mobilization/ transformation Risk assessment
Detail service concept Risk analysis
Define HR concept (EH&S) Test plan
Populate governance model Training documents
Define project company concept Training Plan
Define external/internal reporting Approved documents for
system construction of service activities3)
Review & plan legal concept Selected suppliers/service providers
Define IT concept Completed elements of service
Define CMMS/SMS concept4)
50
Mobiliza- Implement/Transform project PMS600 (Revised) Service concept
tion/Trans- company concept End of (Revised) Operations handbook
formation Implement/Transform HR concept Mobiliza- Test documentation
Implement/Transform CMMS/SMS tion/Trans-
Implement/Transform governance formation
model
Pre-operational test
Implement/Transform organizatio-
nal set-up
Implement/Transform processes
Implement/Transform IT
Preparation of Maintenance/
Operation Manuals
Implement Infrastructure
Finalize Staff Training
Meilen- Ergebnisse
stein
51
Phase Process step Mile- Results
stone
Regular Perform service operations PMS900 Up to date operation documen-
Operations Perform continuous improvement End of tation
process operations Transition plan
Perform change & claim manage-
ment
52
Enabler processes
Quality Gates
Quality gates have been integrated into the For service business, quality gates must be
process. applied at milestones PMS040, PMS080,
PMS100 and PMS650.
For plant and solutions business, quality
gates must be applied at milestones PM040, No quality gates are defined for small
PM100, PM600, and PM670. As an alterna- projects.
tive to PM100, the quality gate may also be
See Recommendation 7.1 in Module 7,
satisfied at PM080. The gate at PM670 may
Operative Quality Management, for more de-
also be fulfilled at PM650.
tails about quality gates.
53
Siemens One
A major component of the Customer focus business responsibilities of the Groups and
company program is the “Siemens One” ap- bring their portfolio into customized com-
proach, where our Groups work together to plete solutions for selected industries. The
approach customers in certain industries. following additional requirements exist with
By bundling our areas of competence, we regard to the management of cross-selling
complement vertical project development – projects:
Project management –
Additional recommendation of Siemens One (CD SO)
Project PM020/PMS020 Cross-Group bid team & STC are confirmed by involved BU’s*
acquisition Bid decision Overall / technical & commercial bid manager nominated
DI2 and take a BU-neutral role
54
Phase Milestone Additional results
Project PM080/PMS080 Overall/technical & commercial PM have a clear mandate from
handover Start of project all BU’s (letter of empowerment) and take a BU-neutral role
For further information please also refer to the Siemens One Intranet Site at
http://intranet.siemens.com/siemensone
* The terms Business Unit (BU) resp. Group are used synonymously
*** “Limit of Authority” – BU specific also refered to as Bid/No Bid decisions
The displayed reference processes for Access the PM@Siemens views displayed in
project management are shown in the the Siemens Reference Process House via
Siemens Reference Process House as special the following:
PM@Siemens views that give users a quick https://cio.siemens.com/rph
top-level overview of the process phases
Click “Process Views” to enter the individual
and milestones (see figure 1.6).
PM@Siemens views.
55
PM@Siemens view for plant and solutions projects
Project execution
Project
Project Purchasing Vertrags- Construc- closure
Vor- Detailed
Projekt- Angebots- Projekt- Commis-
opening & and manu- verhand-
Dispatch tion/installa- Acceptance
akquisition akquisition
planning erstellung übergabe sioning
clarification facture lung tion Warranty
PM080 PM100 PM200 PM300 PM400 PM550 PM600 PM650 PM670 PM700
Start of Order Approval Dispatch Materials Construction/ Release for Customer Project End of
project receipt of detailed approval and resources installation customer acceptance closure warranty
clarified planning at site completed acceptance
56
Process steps for a process phase in PM@Siemens view
PM100 PM200
CRM
Complete
quality plan
and risk
analysis
SCM
Update re-
quirements spe- Prepare
cification for supply chain
the product
PLM
57
Project roles
A second essential aspect in the standardiza- ciated line organizations and are assigned to
tion of projects business is the uniform defi- people who are appointed for concrete
nition of project roles and functions. A role projects. Depending on the project's com-
is defined by a specifically described set of plexity, various roles may be filled by only
responsibilities/competence areas. Project one person.
roles are defined independently of the asso-
58
Recommendation framework for successful processes and roles
In summary, we can make the following recommendations for
successful processes and roles:
Recommendation 1.1
Implement project phases with the described milestone system and quality gates
Recommendation 1.2
Implement required results for milestones
Recommendation 1.3
Implement project roles
Recommendation 1.4
Implement project steps
59
Con ment
ct
tr a
e
nag
Ma
» Clear contracts and
professional contract management
will assure your projects of success
«
Contract Management
Module 2
Clear contracts and professional contract
management will assure your projects of success.
Contract Management
Contract Management plays a crucial role On Small Projects, this function is per-
during order execution but is even more formed as part of another role (e.g., PM)
important in the bidding phase. It begins or as a temporary assignment.
with preparation of the bid, proceeds to
Contract managers perform their function in
the stage where the contract is signed
close cooperation with Legal Services and
and continues into the implementation
act as neither an attorney nor as a legal ad-
phase, where the focus is on claim and
viser (“legal advisor,” “legal counsel”) of the
change order management.
Groups.
The Contract Management team of experts Especially in the bid phase, the integration
within the context of PM@Siemens recom- of the contract manager into the organiza-
mends that a global concept be implement- tion should be close to the operative busi-
ed for the Siemens Groups as well as for all ness concerned; however, he/she should be
project and risk categories throughout the sufficiently independent so as to be able to
term of a project. Additionally, there are bring matters before the relevant Division or
recommendations on contract management Subdivision management in the event of
tools, communication and training, rollout any conflicts.
and feedback. The introduction of the bid/no-bid and bid
In this area, Contract Management provides approval procedure (graded according to
expert support in drafting or commenting project and risk categories) is still recom-
on and negotiating the commercial terms mended as an important precondition for im-
and conditions of a bid, supply and service plementing the contract management con-
contracts and also cooperation agreements, cept in the Groups. For the highest risk
along with support (in terms of contract categories, Group or Regional Executive
law) during the implementation phase. Management must be consulted.
For the highest project class and risk class
(e.g., “A projects”), the use of a full-time con-
tract manager specially named for the
project is required. Specialists for this pur-
pose are to be named and trained in the
Groups and Regions.
63
LoA process (Limit of Authority)
The LoA process ensures a controlled review manages the associated risk
of binding bids that ensures agreement with the business
strategy, and
manages the business portfolio.
LoA process
LoA level
defined
Bid
Bid
must be
confirmed
changed
Communications/Training
Mandatory training in contract law and claim management for Sales & Marketing and 2.10
Project Management (technical/commercial) personnel
2.3 Implement documented bid/no-bid Implement bid release procedures with 2.4
procedure/approval for preparing a bid uniform project and risk classes across all
Groups and Regions
2.5 Final bid approval by a Review Board, in Provide full-time contract managers for 2.6
the highest project or risk category the implementation of projects in the
jointly with Group Executive Manage- highest project/risk category
ment or Regional Management
65
Contract Management in the project phases
revising of supply and service contracts tunities and risks, claim potential
and cooperation agreements and the procedures to be applied
Negotiation support up to final contract Drafting and controlling of subcon-
draft and contract signing tractor agreements
Risk management within the project Analysis of contract and issues for claim
team concerning terms and conditions risks and opportunities
Implementation of the claim concept/
claim strategy in the project
Contract Manager profile
66
Recommendation framework for successful contract management
In summary, the following recommendations can be made for
successful contract management:
Recommendation 2.1:
Implement independent contract management function
The independent activity of a contract man- count in the contract, and by providing a
ager covers mainly the project phase up to contractual basis for change order and claim
the stage where the contract is signed. It is management. Contract management is also
his/her responsibility to provide expert sup- responsible for ensuring compliance with
port in drafting or commenting on and nego- business principles and procedures in the
tiating the commercial terms and conditions bid process, as well as for ensuring involve-
of bids, supply and service contracts as well ment of the specialist departments (Legal
as a cooperation agreement (legal advice is Services, VVK etc.), where applicable. In
provided by Legal Services). In this context, smaller projects, this function can be ful-
contract management plays an important filled by using standardized contract provi-
role in risk management by ensuring that sions.
the identified technical, financial, customer
and country-specific risks are taken into ac-
67
Recommendation 2.2:
Involve full-time contract managers in the bid and negotiation phase
for projects in the highest project/risk class
At least in the highest project and risk cate- A contract manager should have sales/-
gory, the function described under marketing and project experience, business
Recommendation 1 must be performed by a administration knowledge, sound experi-
named full-time contract manager appoint- ence in contract law/preparation of con-
ed for the project, but the contract manager tracts, negotiation skills and a good knowl-
may be involved in several projects. He/she edge of business principles and processes.
should be integrated into the organization
such that he/she is able to bring matters be-
fore the relevant Division or Subdivision
management in the event of any conflicts.
Recommendation 2.3:
Implement documented bid/no-bid procedure/approval for preparing a bid
On the basis of a Group-specific or Region- and dealing with opportunities and risks at
specific procedure, the responsible sales an early stage. On that basis, the meeting
unit submits the project in standardized pres- serves to discuss the bid strategy, the factors
entation documents to the relevant manage- involved in success and the prospects there-
ment team for the latter's decision in a meet- of, the unit's own competitive position (if ap-
ing in which the management of the plicable, its unique characteristics), etc., and
necessary specialist units take part. the extent to which the project reflects the
core business policy of the unit. The budget
The Group-specific/Region-specific determi-
for preparation of the bid should also be ap-
nation of the decision-making level depends
proved in this meeting. In case an adden-
on the risk category or project category.
dum is required, it must also be presented to
Within the context of risk management, this the same decision group.
meeting is very important for identifying
68
Recommendation 2.4:
Implement bid release procedures with uniform project and risk classes
across all Groups and Regions
Depending on the business requirements, The bid approval procedure should include
risk categories are identified for the projects. three elements:
In particular, the criteria include: Technical LoA
Business volume and result Commercial/contractual LoA
Financial risks (payment, production and Cost/Price LoA.
export risks, implementation risk,
The technical part of the bid is approved by
financing risk, etc.)
the responsible technical units in accord-
Contractual risks (liability, acceptance, ance with a stipulated risk classification. To
warranty, liquidated damages for delay this end, the technical units must produce
and non-conformance with performance binding commitments, including perfor-
guarantees, applicable law, etc.) mance characteristics.
Technical and schedule-related risks In a parallel process, the units responsible
(innovation, “exotic” solutions, critical for calculating costs submit their binding es-
performance agreements, foreign timates, which are taken into consideration
products, etc.) and in the total cost and price calculation. The es-
sential contractual contents (liability, warran-
Organizational or process risks
ty, liquidated damages etc.) are also to be ap-
(consortial cooperation, involvement of
proved in a standardized fashion, that is to
Regional Company, internal resources,
say, in accordance with Terms & Conditions,
etc.).
Limits of Authority Guidelines or compara-
ble procedures issued by the Group, Division,
For the individual risk categories, the rele-
or Region.
vant approval processes and decision-
making levels should be defined for each
specific Group or Region.
69
Recommendation 2.5:
Final bid approval by a Review Board, in the highest project or risk category jointly
with Group Executive Management or Regional Management
The Review Board approves the bid on the part in this meeting if the highest project/
basis of a standardized brief project presen- risk category is concerned.
tation, which, in addition to pricing/costing,
At a minimum, the manager(s) of the techni-
points out significant technical and contrac-
cal units responsible for significant perfor-
tual risks as well as other possible frame-
mance characteristics and for the scope of
work conditions of importance for the deci-
supply and service, the technical and busi-
sion. Approval is given in a meeting,
ness administration project management,
possibly also in a videoconference. At least
and the contract manager must also attend
one member of Group or Regional Executive
this meeting.
Management and of management of the
sales or business unit affected must take
70
2 After contract signature
“Contract management after contract (costs and time), and the recording of evi-
signature” is focused at the Group or Region dence for defending incoming claims and
level on proactive claim management (in- justifying and substantiating outgoing
cluding change order management). claims.
Analogously to contract management prior Consequently, the requirements to be met
to signing of the contract, Claim by contract management during contract
Management plays an important role in risk processing differ substantially from those
management by identifying the opportuni- that apply to the bid phase. In the implemen-
ties and risks inherent in the customer con- tation phase, the emphasis is less on draft-
tract (including the technical sections), not- ing the contract and analyzing the risk poten-
ing the potential for changes and claims and tial inherent in the terms and conditions of
defining the procedural rules that have to be request for the tender. The primary goal in
observed. Apart from that, the second main the implementation phase is to identify caus-
task of contract management is to support al links in such areas as deviations from
the drafting and administration of subcon- agreed deadlines and quantities, obstacles,
tractor agreements, for the purpose of risk other contract problems and the various in-
transfer and defending or enforcing claims. terfaces to subcontractors/consortium mem-
bers. Therefore, the skill profile required for
Contract processing (customer, consortium
this phase calls for a technically trained
and subcontractor agreements) also in-
claims manager who not only knows how to
volves identifying events relevant to the con-
analyze schedules and portray complex sub-
tract and assessing them in terms of claim
ject matters briefly and in a form illustrating
risks (incoming claims) and claim opportuni-
causal relationships, but is also sufficiently
ties (outgoing claims), documenting these
experienced in international contract law.
events and the resulting consequences
Recommendation 2.6:
Provide full-time contract managers for the implementation of projects
in the highest project/risk category
In view of the importance of claim manage- For large-scale project business comprising
ment and the effects of any deviations from installation and commissioning, a contract
a contract, a full-time contract manager is manager is required to be at the site.
appointed to assume the aforementioned
duties in the highest project/risk categories.
Depending on project size and complexity, a
contract manager may be involved in one or
more projects.
71
B. Standard Contract Management Tools
Recommendation 2.7:
Implement mandatory check for “unacceptable regulations”
“Unacceptable regulations” must be integrat- of criteria for the project release procedure.
ed by each Group or Region into its catalog
Recommendation 2.8:
Implement binding Group and/or Region policy for project business
The Group or Regional Executive Manage- tory) and optional elements for the liability
ment is responsible for implementing Group- concept, warranty, liquidated damages, etc.
specific or Region-specific project policy. are defined and specified in this project
Obligatory elements, key figures (manda- policy.
Recommendation 2.9:
Ensure intensive use of available standards and tools
As a central provider for the Groups and ment with LS and make them available to
Regions, Legal Services (LS) devises and up- their sales units and contract managers via
dates both standard contracts for the the Intranet. We also recommend that
Groups and Regions as well as the LS Legal Group-specific/Region-specific tools and reg-
Manual (which is standard throughout ulations be made accessible to other Groups
Siemens). In addition, the Groups and via a central Intranet platform.
Regions can formulate Group-specific or
Region-specific standard contracts in agree-
72
C. Communication & Training
Recommendation 2.10:
Mandatory training in contract law and claim management for Sales & Marketing
and Project Management (technical/commercial) personnel
73
D. Rollout and Feedback
Recommendation 2.11:
Install a contract management community in the Group/Region
74
Proje g
n
ct
rolli
Cont
» Regular project controlling
creates transparency, prevents
unpleasant surprises, and
allows people to act quickly
to counteract crisis situations «
Project Controlling
Module 3
Regular project controlling creates transparency,
prevents unpleasant surprises, and allows people
to act quickly to counteract crisis situations.
Project Controlling
Project controlling is a significant tool for The standard variables for project control-
handling projects successfully. Ultimately, ling related to the business management
the success of a project is measured in data and risk management are based on CF
terms of profits and customer satisfaction. specifications for all Groups according to US
GAAP (US Generally Accepted Accounting
Which key variables must be recorded in Principles) and according to the KonTraG law
the context of project controlling so as on risk management. This includes value-
to permit a reliable forecast of the profits oriented control that encompasses payment
at the end of the project? flows and funds commitments.
How can risks be detected and evaluated Other key variables not related to financial
early, and how can they be minimized by aspects are stipulated in a business-specific
taking appropriate action? manner for the individual Groups. These vari-
ables include:
How can project controlling, which
includes project reporting, be integrated Technical controlling
uniformly and systematically in the
Milestone and project progress
business processes of the Groups?
controlling
These questions are core issues in the
Change order and business opportunity
Project Controlling module. Project control-
management
ling is sufficiently regulated in all Groups.
Resource management
Customer and employee satisfaction.
Various Good Practices related to these
areas were taken from all Groups and ana-
lyzed by the evaluation team.
77
Recommendation framework for successful project controlling
In summary, the following recommendations can be made for successful
project controlling:
Recommendation 3.1:
Establish a project-driven organization
78
Recommendation 3.2:
Consistent project controlling process from the bid/no bid decision through to the
end of the project, in particular integrated risks, change order/opportunities and
claim management
Empirical data show that 60% to 70% of all In addition to agreed-upon changes (e.g.,
non-conformance costs are identified during change orders), one must also consider devi-
the execution of a project, but these costs ations from plan values (e.g., NCC) or
actually originate at the bid phase of a changed estimates (e.g., of risks). The order
project. For this reason, project controlling entry calculation (OEC) is the starting point
must be performed continuously, all the for such efforts. Changes to the values en-
way from the bid through to the end of all tered there for sales, costs, and precautions
obligations entailed in a project. Modern to counter risks must be recorded, evaluated,
project controlling supports the manage- and documented. Furthermore, each
ment of risks/opportunities, claims and Division must specify internally what level of
change orders as an integral part of the change is required to trigger an escalation or
project process and lies within the project require the agreement of people beyond the
manager’s sphere of responsibility. An impor- project management team.
tant component is the updating of financial
The following figure shows schematically
project planning using change order man-
how elements of change management af-
agement.
fect planned sales and planned costs for the
project.
79
Change Cost impro-
Risk Claim NCC
Order vement
Actual sales
Gross
Marginact.
Gross
Actual costs
MarginOEC
Risk
Contingencies
80
Recommendation 3.3:
Implement required milestones/Quality Gates in the project process
A project must run consistently in accord- The milestones/Quality Gates for the project
ance with defined rules and decision levels process are defined in Module 1 (Processes
even at the bid phase. Implementation of and Roles). In the project process, the man-
required milestones/Quality Gates and datory milestones play an important role in
associated documentation of the results will the success of project activities.
help the project do just that.
Recommendation 3.4:
Hold regular management-driven project meetings on the basis
of standardized reporting
81
Best Practice recommendations
82
Personn t
men
el
M an a ge
» Your Career in Project Management «
Personnel Management
Module 4
Your Career in Project Management
Personnel Management
“A project should be managed like a But what does the term “project entre-
company” – this guiding principle defined preneurship” mean? What best practices in
by the Corporate Executive Committee this area already exist at Siemens AG? And
has a very decisive influence on the en- which of these solutions can be recommend-
tire PM@Siemens initiative, particularly ed for implementation in all Groups and
on Personnel Management. Regions?
Letter of empowerment
Income and
project incentives
Target agreements
Measures
Adequate assignment
PM career model
85
Delegating the responsibility for a project Experience has shown that cooperation with
means primarily that the scope of such re- line management is particularly important
sponsibility must be clearly defined. It also here. Partnership-based cooperation is an es-
means that the project manager must be sential success factor in projects.
willing and prepared to exercise this respon-
Along with project management, which
sibility. To ensure this is the case, it is neces-
begins depending on the project cate-
sary to precisely define the requirements
gorization with the realization of mile-
and compare them to the individual capabil-
stone PM 040 respectively PM 080, the
ities and experience of the project manager.
PM@Siemens project culture must also incor-
However, this alone is not enough. The or- porate management of the bid preparation
ganization must delegate very clear authori- process. Bid preparation is as important for
ties to the Project Manager. This principle of the ultimate success of the project as realiza-
our project culture must be recognized and tion of the project itself. For category A and
practiced in the organization and also be B projects, only employees with realization
conveyed to our customers and project part- and sales experience may be responsible for
ners. bids.
86
Current status of activities in the early stages of category A and B projects
Appointment and involvement of the PM at an early stage depending on the complexity and likelihood of an order
Personnel Management Fig. 4.2
In both, the bid phase and the realization career in the project management career
phase, we need independent and objective path. This is an alternative to a career in line
project managers who are not beholden to management. We recommend project incen-
anything but the project goals, and who ex- tive systems or individual special payments
ercise their authority on behalf of the respon- related to specific project goals as a form of
sible business manager. recognition with short-term effect for suc-
cessful projects. Both forms of recognition
We can achieve this through empowerment,
enable individual motivation and give the
supported by a target agreement between
Project Manager a share in the success of
the responsible business manager and the
the current project.
person responsible for the bid and/or the
project manager. The Personnel Management panel of ex-
perts analyzed and evaluated the solutions
It is also important to recognize people's ac-
applied in the Siemens Groups and made
complishments in project management. This
the following recommendations based on
occurs in a long-term fashion over an entire
their research.
87
Recommendation framework for successful personnel management
In summary, the following recommendations can be made for
successful personnel management:
Recommendation 4.1:
Implement personnel development in project management
88
Introduction of PM Career Model
The PM@Siemens career model is the basis for personnel development in project management
Participation Practitioner
Technical levels
Experience
in processing/
assembly/
commissioning/ approx. 2–3 years*
engineering
or sales
*Suggested values
89
Those wishing to embark on a career in management of projects of varying degrees
project management should first work in a of complexity represented by the three
technical or sales department and then ro- project categories of A, B, and C. For each of
tate through various project assignments the three levels, project management pro-
with varying responsibilities. files have been defined. These profiles de-
scribe the requirements with respect to are-
The essence of the management levels is
as of responsibility/tasks and the knowledge,
based upon responsibility for results. The dif-
experience, and skills needed against the
ferentiation into the levels of Project Manag-
background of the Siemens competence
er, Senior Project Manager and Project Direc-
model.
tor is the result of the entrepreneurial
Project C B A
Category
Skills Results-oriented attitude, ability to make decisions, excellent organization skills and
focus on quality, customer-focused attitude, assertiveness, ability to motivate others,
excellent communication skills
90
The project management profiles let employ- Project managers at all levels of qualification
ees interested in a project management ca- think and act in an entrepreneurial manner.
reer compare their professional aspirations They lead employees working on the project,
with the listed areas of competence and re- are authorized to make decisions within the
sponsibility and make the appropriate deci- framework of the areas of competence grant-
sions about their professional development. ed to them (see "Letter of Empowerment")
They are also the basis for systematic qualifi- and are invested with the corresponding lev-
cation and PM@Siemens certification. el of responsibility. Based on this, the respon-
Project success depends heavily on the selec- sibility of a project manager for his or her
tion of a qualified Project Manager. The ca- project is comparable to the responsibilities
reer model and the project management pro- of line managers. Thus, the project manage-
files create the necessary transparency for ment career path offers interesting opportu-
efficient resource management. nities for development and advancement.
programs Director
(cross-process
Responsibility/qualification level
91
Project manager certification
Internal Siemens certification of project man- The technical PM knowledge can be docu-
agers is a documented quality indicator for mented with a qualification/attendance cer-
their competence and professionalism and tificate from the PM@Siemens Academy.
creates added value in our relationships Such certificates are issued after a candidate
with partners and customers. attends the PM Learning Programs PM4–
PM1 or selected seminars from the curricu-
As a voluntary measure, it is available at the
lum.
end of the competence management and
qualification process for the individual levels. These certificates do not replace the PM
It is a personnel development measure rele- certification; they are simply proof of
vant to promotion, and it is therefore inte- qualification.
grated into existing and agreed-upon HR
(Human Resources) instruments and process-
es (e.g., EFA/Staff Dialogue).
The goal is to document the breadth of com-
petence of an employee that makes him ca-
pable of independently managing the corre-
sponding customer project categories.
Essentially, for an assessment of a Project
Manager's competence, project experience
92
Concrete implementation
For a successful certification, it is absolutely These prerequisites are based on the project
critical to fulfill the defined entry prerequi- management profiles and reviewed in the
sites. EFA/staff dialog process.
PDir SPM PM
1. Experience/knowledge Comparison through self at least at least at least 1 year
assessment/outside assessment in the preliminary 6 years 2 years with of partici-
discussion with C projects and pation in C, B
Full responsibility for managing projects for B projects more than or A projects
Group-external customers 1 project
5. Statement from staff dialog: Potential for Level PM, PDir SPM PM
SPM, PDir and documentation in the field required required required
“next step ...” on EFA Web/IDD
6. Decision from staff dialog; poss. condition for PDir AC SPM certified as PM
repetition met certification
Personnel Management Fig. 4.7
93
Details about certification
Identifi- Transfer of
cation via certificate/do-
staff dialog/ cumentation/
EFA feedback staff
Certification via question catalog and review board dialog
Feed-
Line Decision
Self- Check by back
manager by the
assess- “neutral” from Line
assess- review
ment body man-
ment board
ager
94
1) certification
using LC or in accordance with LC guideline
2) certification
via question catalog (PM Future World) and review board
95
“PM Future World” Tool
96
The user handbook and answers to selected Certifications via the Learning Campus or in
questions can be accessed on the accordance with the LC guideline take into
PM@Siemens Intranet home page. The tool account valid company agreements. For cer-
itself is provided by the Group, Hub, or Re- tification within the Group (in accordance
gion coordinators. with the LC guideline or using PM Future
World), the Group is responsible for ensur-
ing that all valid company agreements are
complied with.
97
External certificates
Internal Siemens certification is a logical con- External certificates may be earned as sup-
sequence of the PM@Siemens requirement plemental qualifications if customers ex-
for a systematic, standardized project man- plicitly require it, or if the certificates repre-
agement procedure with competent and sent an additional value in the given market
highly qualified project managers. (industry, Region). However, such supple-
Certificates from international professional mental certificates do not replace an inter-
associations PMI1) and IPMA2) cover only nal
some of the Siemens-specific requirements Siemens certification.
regarding international project business and External certifications that have already
the career model. been earned will be considered within the
Therefore, project managers at any level of framework of entry prerequisites for partici-
qualification must be certified in accordance pation in the PM@Siemens certification pro-
with the PM@Siemens and internal Siemens cess.
process.
1) IPMA International Project Management Association,
Zurich
2) PMI Project Management Institute, USA
Project manager database for cross-Group For situations in which a Group/Region can-
and cross-Region PM assignment not use someone from its own ranks for a
category A project, or a complex multi-
In addition to the economic feasibility of con-
Group/multi-Region project is involved, the
tractual obligations, the use of a suitable
search must be expanded beyond the
project manager is critical to the success of a
Group/Region in question. To support the
project. The business manager is responsible
staffing processes, a Siemens-wide PM data-
for selecting the project manager; as a rule,
base was set up under the guidance of Man-
he is supported by the Group/Region staff-
agement Consulting Personnal (MCP).
ing process when making this decision.
As part of the International Development Da-
tabase (IDD), the PM database includes
project managers who have experience with
category A projects (PDir) and project man-
agers for category B projects (SPM) who
have the potential to work with category A
projects. In addition to each candidate's
skills, his or her previous projects, industry
experience, project volume data, and inter-
national expertise should be considered.
98
Overview of cross-Group/cross-Region
PM staffing process
Request 1 5 PM staffing
Centralized PM search
all across Siemens
3 7
2 4 6
Request Search PM-Staffing
PM-?
Group/Region process
1. Inquiry from CEC, corporate units (e.g., Siemens One), or Group/Region resource managers
2. Pre-selection in the PM database by corporate PM resource managers (at MCP)
3. Inquiry to Group/Region resource managers to clarify availability
4. Feedback from potential candidates to corporate PM resource managers (at MCP)
5. Forwarding of “shortlist” to responsible business managers who will make the decision
6. (Bilateral) interviews, negotiations, staffing decision
7. Information given to resource and project managers involved
99
The following roles are integrated into For centralized PM search
the database maintenance and staffing (all across Siemens):
process:
Corporate PM resource manager
To maintain the PM DB: (moderator/broker role at MCP)
Project manager (PMs for category A • can evaluate the relevant data from
projects and PMs for category B the Siemens-wide IDD for PM search
projects who have the potential to • “Moderates“ additional clarification
run category A projects) rounds via the PM resource managers
for the Groups/Regions (suitability
• Maintenance of one's own data on
and availability)
PM skills (esp. project experience)
• Ongoing dialog between manage- Group/Region resource managers
ment and employees (self-evaluation
• Current resource managers: see
and personal goals)
Intranet, PM@Siemens, Modules,
• Integration of data into EFA interview
Module 4
• Ensuring data are up to date (each
• Can evaluate data for PMs in his
person is responsible for his own
Group (worldwide) or his Region
data)
(all Groups)
• Clarifies additional details with man-
Manager
agers and/or PMs in accordance with
• Ongoing dialog between manage- Group/Region-specific processes
ment and employees
(Outside evaluation; SLF feedback, For PM staffing:
agreement on development
The person who has the need or
measures)
announces the need initiates the
• Integration of data into EFA interview
PM staffing process.
• Ensuring data are up to date
The PM staffing decision is made by
the responsible business manager
for the project with the affected
project manager (PM) and his or her
supervisor.
100
Recommendation 4.2:
Create Letter of Empowerment
101
Recommendation 4.3:
Conclude target agreement
Concrete target agreements help everyone The target agreement also constitutes a
get oriented and support effective project point of reference for the EFA interview/staff
handling. A target agreement with the dialog each fiscal year. Where possible, the
project manager – it is recommended to in- parameters mentioned above can be inte-
clude the person responsible for the bid as grated into the balanced scorecard and ap-
well – should include the following parame- plied to the SLF (Siemens Leadership
ters: Framework). The project goals achieved
serve as a basis for the employee’s further
Result
development and as a foundation for the
Deadlines (milestones) definition of variable salary components and
Costs project incentives.
Recommendation 4.4:
Include project goals in special payments
Individual special payments allow outstand- HR (Personnel) in each case so that each
ing achievement in the handling of crisis project management level receives a fair po-
projects to be recognized proportionately to sitioning in the performance portfolio in the
the performance given. The amount of the EFA rounds/staff dialogs.
special payment should be coordinated with
102
Recommendation 4.5:
Implement project incentive system
We recommend that you recognize project project incentive rules. The panel of experts
managers' entrepreneurial achievements us- recommends including the following key
ing project incentives. Allowing project man- points in your project incentive rules. The
agers share in the success of “their” projects Groups already have examples of best prac-
is an important step toward the goal of im- tice. Remember to consider current co-
proving project results over the long term. determination rules when approving or
Groups are responsible for developing amending project incentive rules.
103
Qualification
» Training costs less than
having to learn the hard
way in a project ...
«
Qualification
Module 5
“Training costs less than having to learn
the hard way in a project … ”
Qualification
107
PM@Siemens Academy
President
Steering Committee
Jürgen Schott
Regions
Qualification measures
Acquiring project management knowledge
and expertise appropriate for the given job
profile is a must for every project manager.
To build project management competence,
the PM@Siemens initiative recommends the
qualification measures developed, made
available, and implemented by the Learning
Campus on behalf of the PM@Siemens Acad-
emy. As a supplement, we recommend indi-
vidual skill building through project manag-
ers' own on-the-job experiences, through
coaching and best practice sharing.
108
The qualification measures of the Learning Enabling of systematic personnel develop-
Campus (PM Learning Programs PM4–PM1, ment and qualification for project manag-
PM@Siemens curriculum) fulfill the follow- ers and employees on the basis of the
ing criteria of a Siemens-wide standardized PM@Siemens career model
approach to project management that simul-
Promotion of cooperation at all phases of
taneously leaves sufficient flexibility for
project management, especially in the
Group-specific and/or Region-specific re-
sales/bid phase (e.g., using cross-
quirements:
functional bids)
Uniform qualification standards
Support of an issue-oriented and techni-
Focus on defined, approved project cally-oriented international project
management profiles management network.
Implementation of uniform methods,
procedures, and terminology
PM@Siemens Curriculum
Director
PM Learning Programs
Management of A/B/C-projects
Senior Project Manager
Senior Project
Management of PM2 Manager
B/C projects
Project Manager
Project
Management of PM3 Manager
C projects
Project Practitioner
Project
Team function PM4 Practitioner
Entry level
109
Two specific qualification models have been PM@Siemens curriculum. Both models
developed. The first is the PM Learning are tailored to the job profiles of the
Programs PM4–PM1; the second is the PM@Siemens career model.
The PM Learning Programs PM4–PM1 are tai- The PM Learning Programs PM4–PM1 are
lored to the job profiles and are recommend- built in a modular fashion. The combination
ed as qualification measures by the of classroom training and practice phases
PM@Siemens initiative because they ensure (learning on the job) offers participants the
a uniform training program for project man- opportunity to implement the project man-
ager, much as the general Siemens agement methods, communication skills,
Management Learning Programs do for line and leadership skills they have learned in
management. their day-to-day work.
Once the candidate has completed the PM
Learning Programs PM4–PM1, the Certi-
ficate of Participation issued by the
PM@Siemens Academy confirms that he or
she has reached the corresponding level of
qualification.
110
2. PM@Siemens Curriculum
Negotiation techniques
111
The following graphic summarizes the possi- Certification for the Project Manager, Senior
ble qualification options. Project Manager and Project Director levels
is a Group/Region-specific process for which
the Groups/Regions are responsible. (cf.
Module 4, Personnel Management)
Qualification
PM@Siemens Academy
• PM Learning Programs
• PM@Siemens Curriculum
Competence
Certification
analysis
Staff dialog
Job Profiles Project Experience
112
International availability of PM@Siemens Academy
Regional partners/
contacts for PM@Siemens qualification
(as of July 2005):
Germany
Siemens AG, Learning Campus (LC)
Munich, Elisabeth Bittner
E-mail: [email protected]
Tel.: +49 89 636 33311
113
Recommendation framework for successful qualification
In summary, the following recommendations can be made for
successful qualification:
Recommendation 5.1:
Determine need for qualification
Determining the need for project manage- This need is derived from:
ment qualification presumes a goal-driven,
the results of the EFA rounds and
business-oriented analysis. In the process,
staff dialogs
particular attention should be paid to special
requirements, e.g., with respect to coopera- the catalog of measures from the project
tion during the sales phase, deployment as a and process assessment (see Module 10,
project quality manager, etc. PM Assessment)
The project management profiles with their PM Future World as a placement and
defined requirements developed in the certification tool
Personnel Management module are a good cross-Group assessment of qualification
basis for determining an individual employ- needs (e.g., via interviews, best practice
ee's qualification needs. sharing …)
114
Recommendation 5.2:
Implement qualification measures
All Groups and Regions commit themselves This systematic process supports an efficient
to make consistent use of the qualification and strategic approach to personnel develop-
offerings developed and made available by ment while maintaining an individualized ap-
the Learning Campus on behalf of the proach to continuing education.
PM@Siemens Academy.
The qualification concept of the
As part of their annual EFA process/staff dia- PM@Siemens Academy will strengthen the
log, Groups and Regions will plan their quali- Siemens project culture on a best practice
fication load for the coming fiscal year and level.
act promptly to coordinate the training
schedule with the Learning Campus.
Recommendation 5.3:
Ensure that qualification measures fulfill quality requirements
To ensure that the products of the Learning In addition, the Groups and Regions will
Campus (PM Learning Programs and meet their obligations as outlined in the
PM@Siemens curriculum) meet the required Rules of Internal Procedure, e.g., through
quality standards, the PM@Siemens partnerships for the PM Learning Programs
Academy performs regular quality control- and by participating in expert panels and
ling audits. The Groups and Regions collect closing events in the Learning Programs
feedback from participants and pass it back PM4 through PM1.
to the PM@Siemens Academy as input.
115
» The PM Portal –
PM Portal
the Web-based workplace
for all internal and
«
external parties
to the project
PM Portal
Module 6
The PM Portal – the Web-based workplace for
all internal and external parties to the project
PM Portal
Contract Analysis
Project
Suppliers Reporting
and Partners Customer
119
Goals and Benefits
The aim of the PM Portal is to improve both Specific alignment of the PM Portal to the
quality and productivity in project manage- project process and to the needs of the
ment within Siemens by enhancing clarity in project team members in accordance with
projects and reducing non-conformance defined project roles should allow everyone
costs in project processing. access to precisely the functions and infor-
mation they need in order to proceed with
Improved clarity in project management
the current job. As a result, cooperation in
must be supported by uniform procedures
the project teams, efficiency in the project
and tools for all those involved in the project,
processes and the quality of project results
including management. In doing so, availa-
will improve.
ble IT processes will be put to more efficient
use through integration into the PM Portal Implementation of the PM Portal on the ba-
and access will be facilitated through uncom- sis of the standard platform Enterprise Portal
plicated operation without additional regis- Services made available throughout the com-
tration procedures (single sign on). pany as a Shared Service by Siemens CIO
aims to advance the standardization of pro-
cesses and tools. At the same time it aims to
optimize the costs for users by utilizing the
effects of scale.
Reduction of
project costs
120
What does the PM Portal offer?
Requirements
Portal functions
PM Portal Fig. 6.3
The IT applications relevant for project Project Manager: The Project Manager
processing, as derived from the standard View displays the project team members
project process, are integrated in the PM and their roles, the project status and
Portal and made available to those involved information on current events in the
in the project. project at a glance.
The information within the PM Portal is struc- Project Staff: The Process View supports
tured according to project roles and views. systematic project processing on the
Each project role is linked to an authoriza- basis of the standard processes defined
tion concept in which the views intended for by PM@Siemens for different project
each role are recorded. types; its aim is to contribute to improv-
Some examples for project roles and views ing the quality of project execution.
allocated to them:
Manager: The Management View allows
Business Managers a quick overview of
the current project situation on the basis
of scorecards and management reports
for their area of responsibility.
121
Status and next steps
The first version of the PM Portal was devel- The Region Germany has since implemented
oped by PTD with the assistance of CIO and a PM Portal for the central RD IT project cur-
uses the Enterprise Portal Services provided rently with about 500 project employees
by CIO. The concept contained in this for based on the experience gained at PTD and
roles and rights resulted in a separate view is now using it productively.
for project staff in the Enterprise Portal.
Other corporate units such as the Region
Apart from a PM frame that can also be used
Spain and CIO are preparing to use the PM
by other Groups and Regions, PTD has inte-
Portal for supporting the processing of their
grated its own business-specific procedures
projects.
and solutions for projects business.
122
Recommendation framework for a successful PM Portal
AInsummary
summary,ofthe
thefollowing
recommendations for a successful
recommendations can be PM Portal
made for
is given below:
successful PM Portal:
Recommendation 6.1:
Use of MS Project, Primavera, SAP PS, SPIRIDON solution “Solution Business”
as standard tools
The planning and control of activities, dead- Since this solution is already linked to the
lines and resources, along with their depend- SPIRIDON Business Warehouse (“MISS
encies and the use of IT tools to support SPIRIDON”), the system also supports the
these processes, are essential elements of quarterly PM@Siemens reporting required.
the project processing task. Within the con-
For project management outside SAP, the fol-
text of the PM@Siemens Initiative, the
lowing tools are recommended as a uniform
Groups involved devised the following recom-
solution for Siemens AG:
mendations:
MS Project: For projects/office applica-
As a uniform solution for deadline manage-
tions with less than 500 activities.
ment in conjunction with SAP, the recom-
MS Project is an application that can
mended tool is the SAP module PS, wherev-
quickly be applied to smaller-scale
er possible.
projects. Only minimal training in its use
Use of the SPIRIDON solution for "Solution is required; its flexibility is advantageous
Business" is recommended, especially for the thanks to its ease of incorporation in the
regional units, as it supports the integrated MS Office world.
processing of project tasks starting with ini-
tial bid preparation, through order process-
ing, up to and including the end of the war-
ranty period and subsequent archiving. This
solution is based on a development from
Synergy+ and is suitable for small and large-
scale projects as well as for Consulting
Business or even large-scale installations.
123
Primavera Enterprise: for projects with Due to its efficiency and complexity,
more than 500 activities for multi-project however, significant training in its use
or multi-user assignments. is required, in addition to support during
introduction and professional system
Primavera Enterprise is an internationally
administration.
recognized PM tool for complex projects.
This tool is both multi-user and multi- See also CIO Circular No. 09/2002 dealing
project capable. Its application as a with this recommendation.
Siemens-wide standard improves cross-
Group communications.
Recommendation 6.2:
Participation in further development and introduction of the PM Portal as a
standard solution for project workplaces
The PM Portal created by PTD and CIO forms The PM@Siemens initiative has thus decided
the basis of a standard solution for Web- that:
based project workplaces. This solution is ful-
the PM Portal should be extended to all
ly compatible with the Siemens standards
Groups/Regions involved.
for portal and portal implementations speci-
fied by CIO (see CIO Circular Nos. 11/2002 the Groups/Regions should use the
and 15/2005). standard solution as the basis for future
project portals of their own.
Active financial and practical cooperation be-
tween all Groups and Regions is required to The Groups will themselves decide as to
ensure that the basis of the standard solu- when they are going to embark on the
tion can be developed further in a target- project. However, until that time they will
oriented fashion and that the requirements refrain from developing project portals
of all Groups/Regions are incorporated. independently.
124
» Professional quality management
ensures the success of projects
«
t
gemen
tive
Quality
Opera
Mana
The aim of Operative Quality Manage- As an expert and partner, the Project Quali-
ment is to lay the foundations for trust- ty Manager supports the Project Manager in
based, effective cooperation with our cus- effective planning, implementation and con-
tomers, partners and staff. Such coopera- trol of the project-specific actions taken for
tion must be based on systematic, clear quality control. The Project Quality Manager
and proactive approaches toward honor- is involved in all project-specific decisions
ing contractually agreed guarantees and and in the escalation process in the case of
performances. Operative Quality Manage- failure to meet customer requirements
ment assists the Project Manager and the and/or project goals. Depending on the
Project Teams in meeting the project re- project category, either an independent
quirements in terms of functionality, Project Quality Manager in the project is ap-
costs and deadline. pointed, or the role is performed by a suita-
bly qualified member of the project team. In
Operative Quality Management is an inte- all projects, the function of the Project Quali-
gral part of the PM@Siemens process and ty Manager in the project is allocated func-
as such includes the planning and safeguard- tionally to the quality organization.
ing of the quality requirements over the en-
The concrete measures for meeting the quali-
tire project period in all its phases and steps.
ty requirements, including deadlines and re-
Quality management is particularly impor-
sources, are defined as part of quality plan-
tant in the bid phase up to the contract finali-
ning in a Quality Plan (Q-plan) that must
zation. Deficits and errors committed in this
be kept updated over the entire project term.
phase can burden the entire project substan-
tially and can rarely be rectified – with all An additional goal is the systematic project
the resultant consequences for the custom- closure, the identification for the reasons
er and our company. for successes or failures, and to draw conclu-
sions from past experience – strengths and
improvement potential – which can be of
benefit to future business.
127
Recommendation framework for successful quality management
In summary, the following recommendations can be made for successful
quality management:
Recommendation 7.1:
Active implementation of the Quality Management function in the project
128
Quality Gates are decision-making cautionary measures in case of risks, and
points at critical places in processes and a decision is taken on the further proce-
projects for checking whether all require- dure if this is possible within the sphere
ments of the customer or client and all of competence of the Project Manager.
other project objectives are fulfilled or
Critical subjects for which the required ac-
whether they can be fulfilled using the
tion exceeds the competence of the
planned method.
Project Manager are submitted to the
The quality gate contains a preparatory Business Manager at a Quality Gate
readiness check. This is a check as to Meeting which may also be attended by
whether the results planned up to the other persons nominated for specific are-
quality gate are correct and complete and as. Proposals for action and alternatives
whether subsequent project planning is are also presented as a basis for deciding
up-to-date and plausible. Alternatives are on further procedure.
shown in case of differences and pre-
Project closure
Project opening
& clarification
Purchasing and
manufacture
Project acquisition
Contract negotiation
Warranty
Pre-acquisition
Project handover
Bid preparation
Dispatch
Commissioning
Acceptance
Detailed planning
129
Continuous risk and activity Continuous quality reporting
management
Continuous quality reporting must
Another important aspect of Operative contain the following elements:
Quality Management is early detection
• Implementation status of the quality
of non-commercial risks and avoidance
assurance functions and measures
or reduction of the likelihood of occur-
stipulated in the Q-plan, including
rence and damage impact by suitable
assessed risks,
preventive measures:
• Status of the results achieved, reflected
• Use of risk assessments from past in the customer requirements and the
projects at an early stage, internal process and business require-
• Assessment of risks by means of FMEA ments,
in case of highly innovative project • Status of correction measures in case
contents, of failure to meet planned targets or
• Preparation of assessment by cross- results.
functional teams,
Ensuring feedback of experience
• Defining and controlling of measures
(Lessons Learned), e.g., by means of
to minimize risks
analysis and processing of experience
• Regular updating of risk assessments.
gained from the project on the basis of
project assessments, reviews, audits,
and project status meetings.
130
Recommendations 7.2:
Appointment of Project Quality Manager
131
Qualification criteria and qualification
The following diagram shows the generic
profile of the Project Quality Manager.
132
Recommendation 7.3:
Drawing up project-specific Quality Plan (Q-plan)
The Q-plan is drawn up in the project plan- The Q-plan must fulfill the following mini-
ning phase and updated over the entire mum requirements in terms of content and
term of the project. It contains the concrete structure:
quality measures for attaining the project
Content:
goals, how these are measured and assessed,
at what times what results are to be Documenting of the quality requirements
achieved, and who is responsible for imple- and deriving quantified quality targets
mentation. The human and financial resourc- from the customer's viewpoint and from
es required for implementing the Q-plan the Siemens viewpoint,
must be taken into account in the project Selection and specification of quality
planning. assurance methods,
It is recommended that a sample Q-plan be Defining the processes, procedures and
drawn up for specific project types. This rules to be applied,
must be adapted (tailored) to the specific
project requirements within the permissible • Approval procedure (bids, milestones,
limits during project planning. Quality Gates),
• Tests and acceptance of project results
(internal/external),
• Quality assurance methods, such as
QFD, FMEA,
• Change management,
• Quality reporting,
• Audits.
Structure:
Cross-functional preparation in the
project team including coordination with
the customer and communication to all
project team members,
Configuration according to the project
structure, i.e., all contents are to be
assigned to the individual project
components and activities.
133
Quality Plan: configuration, structure, approach
Project goals:
Function Subject areas:
Deadline
Design/engineering
Costs, con-
crete, in detail Documentation
Product safety
Method application
(prevention, reviews,
Quality Gates ...)
Lessons Learned Risk management
Processes (change,
error, claim ...)
Suppliers, supply quality
Assembly, production
1) As a chapter of the PM guideline, if required Integration
2) For individual projects, a project-related Internal/external
description / version may be issued, if so acceptance
requested by the customer.
Delivery, dispatch
3) In accordance with the Group
Specifications ...
134
Recommendation 7.4:
Systematic project closure
135
» A mistake can always happen
and an opportunity can be missed –
but only once, please!
«
e nt
Man ledge
agem
w
Kn o
Knowledge Management
Module 8
A mistake can always happen and an opportunity
can be missed – but only once, please!
Knowledge Management
139
Structure and operation of the
“Siemens Global PM Community”
The “Siemens Global PM Community” con- In the initialization phase the sub-commu-
sists of individual sub-communities that are nities are moderated and assisted by staff
grouped together in an umbrella organi- from the PM@Siemens Learning Programs
zation. There are three types of sub- (PM3–PM1). This support comprises practi-
communities: cal help in motivating attendees, in defining
goals and the charters of the sub-com-
1. Network of former participants in the
munities and in organizing and conducting
PM@Siemens Learning Programs
Community Workshops, etc.
(PM1–PM4) of the PM@Siemens
Academy The following supporting services by partici-
pating Project Managers are typical of the
In co-operation with Learning Campus
services provided by the Siemens Global PM
and the PM@Siemens Academy all parti-
Community:
cipants will be able to join the Siemens
Global PM Community (Alumni network), Exchange of experience and information,
in order to keep contact with other if necessary coaching
course attendees and to develop an
Exchange of know-how with external
exchange of experience about other
sources of experience
courses.
Concrete support in projects (Best Practice
2. Sub-communities relevant to particular
Sharing, Debriefing/Lessons Learned,
areas, for example Contract Management
PMA+ ...) with the aim of increasing pro-
3. Business-relevant sub-communities, for ject success
example for cross-selling projects or
Active and creative participation in
multinational projects
meetings, conferences, and workgroups
The members of the Alumni network from
The structure of the community with the
the PM@Siemens Learning Program
sub-communities derived from the qualifi-
(PM1–PM3 = PM, SPM and PDir) have a spe-
cation (subject or project-specific) is config-
cial role to play. They form the core of the
ured as follows:
Siemens Global PM Community and assist
with the building up and initialization of all
other sub-communities.
140
Siemens Global Community – Structure
Special
PDir Theme 2
(PM1-01)
PM
SPM
PM
Regions
SPM
PM
PDir
PDir
SPM (PM1-02)
Project
1
Special
Theme 1 Project
2 External,
e.g., PMI
141
PM experience – the Project Management simulation
from PM@Siemens
The basis for the exchange of information on Attendees at this workshop work in a team
project-relevant topics is a common language to simulate a project with the most impor-
and a mutual understanding of the core top- tant pitfalls and challenges over the entire
ics of the projects business. process PM010–PM700. They simulate a typi-
cal Siemens project completely from acquisi-
To create this basis PM@Siemens offers a
tion to follow-up business. Attendees have
4-hour workshop with a project simulation
to decide jointly on what actions to take in
based on the “Project Management – the
the individual project phases. The initial ex-
Siemens way” standards described in this
change of experience between the attend-
manual.
ees develops automatically in this discussion.
Meanwhile the project management simula-
tion is available in 5 different languages: ger-
man, english, spanish, portuguese, chinese.
Acting together.
Learning together.
142
During the simulation the development of This simulation exercise is directed by a
four identified Key Performance Indicators is trained moderator who guides the partici-
continuously logged: pants through the simulation and assists
with the debriefings and final discussions.
Customer Management
Employees from the operational side of busi-
Scope
ness are trained as moderators and organize
Project team and conduct the workshops at their own lo-
Co-operation with internal & external cations. This minimizes time expenditure
partners. and financial costs for all participants.
The status of these KPIs forms the basis for Dates for moderator training and up-to-date
making decisions on the actions to be taken information for ordering material can be
in the next phase. On completion of the sim- found on the PM@Siemens Web site.
ulation the KPIs are suitable for examining
the momentary situation in attendees’ own
organizations and for identifying potential
for improvement in Project Management.
This results in measures for implementation
in one’s own projects or in the organization
and a corresponding plan of action.
143
Recommendation framework for successful Knowledge Management
In summary, the following recommendations can be made for
successful Knowledge Management:
Recommendation 8.1:
Establishment of a Project Management sub-community
People learn best in direct exchange with The PM program caters for two types of
one another, not from documents or descrip- communities:
tions. The communication of learning experi-
Topic-oriented PM sub-communities
ences from projects serves two purposes:
Project/process-oriented PM
a) Other people can understand the context
sub-communities.
and identify the person who can help
them with their experience and contact
When establishing a community, the mem-
this person.
bers should agree on the following points:
b) Detailed knowledge or models can be
Name of the community
used on the basis of an existing exchange.
Description/charter of the community
The Project Management sub-community in
(e.g., open or closed)
an organizational unit creates the framework
for this exchange. Activities/milestones of the community
Communities are both personal and virtual Moderating, controlling and organization
networks that are founded on a common of the community by defined drivers
and business-relevant interest. Members of the community
Rules of the community
Type of interaction and communication
within the community
Ways of measuring success and
implementation of these methods.
144
People learn best in direct exchange with The PM program caters for two types of
one another, not from documents or descrip- communities:
tions. The communication of learning experi-
Topic-oriented PM sub-communities
ences from projects serves two purposes:
Project/process-oriented PM
a) Other people can understand the context
sub-communities.
and identify the person who can help
them with their experience and contact
When establishing a community, the mem-
this person.
bers should agree on the following points:
b) Detailed knowledge or models can be
Name of the community
used on the basis of an existing exchange.
Description/charter of the community
The Project Management sub-community in
(e.g., open or closed)
an organizational unit creates the framework
for this exchange. Activities/milestones of the community
Communities are both personal and virtual Moderating, controlling and organization
networks that are founded on a common of the community by defined drivers
and business-relevant interest. Members of the community
Rules of the community
Type of interaction and communication
within the community
Ways of measuring success and
implementation of these methods.
145
PM Community (all Community Members)
PM Development PM Projects
Subject-oriented (Members of Project- & process-oriented
the workgroups and subject groups) (Project manager & project team members)
Sub-Community PM Steering Board Project Subcommunity: Project XY
Sub-Community: ...
146
Recommendation 8.2:
Implementing project learning cycle including Lessons Learned/project debriefing
Project debriefing and Lessons Learned are a Debriefings and Lessons Learned are
fixed component of project work. They pro- mandatory and play an important role in
vide a means of deriving findings explicitly improving project quality at Siemens.
from projects and, in the initial step, of con-
Debriefings (reflecting on experiences)
solidating these findings in a usable form for
should be carried out after completion of a
the participating persons as new knowledge
milestone, at the end of a project activity or
for future projects.
on completion of a project in order to high-
The exchange of information and experi- light successes and also failures and provide
ence about the most important successes a means of measuring them.
and failures, research into their causes from
Other community members and Project
the different points of view of the different
Managers can obtain an insight into Lessons
project team members and analysis of the
Learned on the basis of such reflections and
entire project form the basis for expanding
avoid repeating mistakes.
the horizon of all team members and for
bringing about a lasting improvement in the The “Siemens Global PM Community” offers
ability of the persons involved to act. practical assistance with the design of de-
briefing processes or debriefings in a project.
The essential knowledge and experience
modules are described with details of the
corresponding contact persons so that this
experience can be made accessible to other
people.
147
Outline of a debriefing process
148
Recommendation 8.3:
Passing on knowledge through coaching in PACT* Workshops
149
Teamwork
A PACT Workshop brings the entire pro-
posal/project team together at an early
phase of cooperation. It provides a forum
for discussing interfaces, clarifying unclear
points and sharing knowledge about the
proposal/project.
150
Recommended elements of the PACT Workshop
151
Requirements and implementation
in own Group/Region
152
Links to Group-specific “Best Practices”
153
» 4 steps for winning with
PM@Siemens or:
How do I make PM@Siemens
a business success?
«
d
tat en-
Im er an
ion
m
ple
nsf
Tra
“We've done a great deal of analysis, iden- Following commitment of the Management
tified the causes and developed approach- the main steps in this procedure are as fol-
es to enable us to improve the situation. lows:
Now it's up to us to implement this sys-
tematically and with lasting effect in or- 1. Analysis
der to generate value from our invest- Communicate PM@Siemens in the
ment!” Group/Region
Johannes Feldmayer at the Siemens PM
Day in Nuremberg in October 2004 Create framework
3. Implementation
Elaborate actions
Plan and set up implementation project
Carry out implementation
4. Follow-up
Control implementation
(Scorecard/Shotgun)
Lessons Learned
Best Practice Exchange
157
Main steps in implementation
in a Group or Region
Design
Management
Commitment
Control
implementation
Monitoring
Each Group or Region has a different maturi- The quality and efficiency of the implemen-
ty level with respect to the implementation tation itself also increases with experience.
and application of the 53 recommendations,
Overall this results in the following picture
which also means the recurring application
for the application of the main implementa-
of the main steps. An improvement in the
tion steps with respect to the timeframe and
maturity level of a project organization (CM-
the maturity level of the project organiza-
MI Level, see Module 10: PM Assessment)
tion.
can be expected with each recurring applica-
tion.
158
Main implementation steps plotted against time with development
of the maturity level of a project organization (CMMI Level)
Implementation
maturity level Continuous
Target: improve-
CMMI ment
Level Design
3.0
Analysis Implemen-
tation
Check
implementation
Monitoring
Design
Analysis Implemen-
tation
Check
implementation
Design
Monitoring
Analysis Implemen-
tation
Start: Check
implementation
Manage- Monitoring
ment Time
Commit-
ment Participation Implementation of recommendations Performance
Create org. framework Recommendations imple- Analysis of the maturity level
Create transparency mented or in process of by means of internal PMA+
Define goals implementation assessments
Common general frame- Analysis of the maturity level
work created within the by means of external MPM
Group/Region assessments
Standard reporting
Implementation of devised
established
improvement measures
Transfer and Implementation Fig. 9. 2
159
Recommendation framework for successful transfer and implementation
In summary, the following recommendations can be made for
successful successful transfer and implementation:
Recommendation 9.1:
Establishing implementation process
The following points have materialized as Definition of the specific need for action
important success factors for the implemen-
• Analysis of actual situation (Kick-off
tation of PM@Siemens:
Workshop) for each module
A. Management of the implementation • Elaborating actions for each module
process • Define responsibilities and deadlines
Commitment on the part of management • Integration in a roadmap for implemen-
Definition of roles of all involved in the tation with regular reporting to the
implementation process Group/Regional Management
Well developed communication process Determining the implementation status
with targeted addressing of relevant (Fig. 9.8, 9.9 and 9.10)
participants Monitoring the activities in the PM
Set-up of a program organization Scorecards (Fig. 9.11)
(Fig. 9.6) with Analysis of project business (Fig. 9.12)
• PM@Siemens coordinator Coaching support at all levels
(Group or Region)
Gearing of implementation activities to
• PM driver per Division or regional unit the improvement of project results.
• Experts These points are differently weighted accord-
ing to the situation of the organization and
the implementation maturity level.
160
B. Organizational framework Methodical and results-oriented attitude
to work
The most important basis for success and
for the efficient use of resources in the im- Knowledge of business processes
plementation of PM@Siemens is commit-
Knowledge of Group or Region-specific
ment on the part of management.
standards and guidelines pertaining to
The management has declared its support project management
for the objectives for improving project man-
Experience in improvement programs
agement and has appointed a Coordinator
and team in the organization with clear tar- Communication skills and powers of
gets and responsibilities. persuasion
This team has access to all necessary con-
D. Organizational framework for deci-
tacts and the roles and responsibilities for
sions and supporting the rollout
implementation are defined and communi-
cated. The management is given implemen- A working model with decision making
tation progress reports at regular status body and participation of the coordinators
meetings and plays an active role in imple- from all Groups and representatives of the
mentation on its own responsibility. Regions has been devised as a framework
for the global rollout of PM@Siemens stand-
C. Driver for implementation ards.
An important success factor in operative im-
plementation is the PM@Siemens manager
responsible for implementation on behalf of
the Division Management or the Regional
Management of a Group.
The PM@Siemens manager in a Division or a
regional company should have the following
skill and quality profile:
Several years of experience in managing
projects
Acceptance in the organization
161
Global Organization of PM@Siemens
Driver Operative implementation
1 Group/Hub/Region
Team n Implementation
of PM@Siemens
Transfer and Implementation Fig. 9. 3
162
Lead Regions (so-called “Hubs”) concentrate communications
163
Implementation in a Region or in a Group
Group Executive
Management
Group Coordinator
PM@<Group>
Coordinator Group Div. A
…
Division/Subdivision
Coordinators Div. n
164
E. Clear roles and responsibilities at the Operative implementation and the creation
Headquarters and the Operational Units of actual numerically quantifiable benefit is
the responsibility of the Group’s internal or-
The organization of PM@Siemens is based
ganization or the regional organization.
on the definition of standards on topics that
benefit many businesses in the Group The roles and responsibilities are set out in
and/or Regions based on the experience the following table accordingly.
(Best Practices) and requirements of our
project business.
The global organization is responsible for
the definition of the standards and for sup-
porting implementation in the Divisions of
the Groups and in the Regions.
165
Global Organization
Role Responsibilities and functions
166
Role Responsibility and functions
Hub Coordinator Drives and supports the rollout in the assigned Regions
Consolidates the interests and needs of the Regions in his/her hub
in the direction of the global initiative
Identifies common topics of all Regions and moderates the ex-
change of experience and joint activities
Builds up knowledge and experience for the standards defined in
PM@Siemens and is the local PM@Siemens expert (first level
support)
Assists and advises the Regions in his or her hub on implementa-
tion along the defined maturity levels and clarifies unsettled
points with PM@Siemens
Summarizes the situation with regard to project business for the
hub and reports quarterly as part of the PM@Siemens standard
reporting to all Regions of the hub
Is the mutual information channel between the global initiative
and Regions of their hub
Collaborates on the definition of PM@Siemens standards
Is involved in the further development of PM@Siemens
Group Coordinator Drives and supports the rollout in all Divisions and Regional
Units of the Group
Exchanges Best Practices and collaborates on the definition of
the PM@Siemens standard
Is involved in the further development of PM@Siemens
Monitors (Scorecard) the implementation progress in the
Division/Regional Units of the Group
Supplies Group input for PM@Siemens reporting in the Steering
Committee
Incorporates Best Practices and requirements from PM@Siemens
in their coordinator Group
Supports the Executive Management, e.g., with the definition
of the specific implementation actions
Assists all coordinators of the Division/Subdivision in the Group,
e.g., in Controlling, Scorecard
167
Group-Internal/Regional Organization
Role Responsibility and tasks
168
Role Responsibility and functions
169
Persons responsible for the subject content
contained in each of the 12 modules of this
manual will be appointed from the Group or
the Region.
170
Recommendation 9.2:
Determining the implementation status
The implementation status is evaluated at need for action of the organization unit is
regular intervals and compared with the first defined and the necessary activities de-
plans in order to be able to react promptly to rived from this.
changes and to take measures to achieve
the implementation targets. The specific
Personnel Management
le
mp
Qualification Exa
PM Portal
Operative Quality
Management
Knowledge
Management
Transfer and
Implementation
PM Assessment
Project Procurement
Small Projects
Transfer and Implementation Fig. 9.7
171
Definition of the implementation status (Group/Division/
Subdivision/Business Segment/Region)
No implementation
The PM@Siemens recommendation is not implemented in the Group/Region. There
is a plausible explanation from the Group/Division/Subdivision/Business Segment/Region.
*DI = Degree of implementation according to top+ reporting system. DI 5 is not reported since a
result cannot be derived directly from the recommendations. The effect of the action taken
can be seen from the analysis of the project business and in the Scorecard.
172
Implementation status Modules 1–5 (form) – 1/2
PM@Siemens Group/Div/Subd/BS/Region
module PM@Siemens recommendations
.... .... .... ....
1.1 Implement project phases with the described milestone system and Quality Gates
Module 1 1.2 Implement required results for milestones
Processes 1.3 Implement project roles
and Roles 1.4 Implement project steps
2.1 Implement independent contract management function
Module 2 2.2 Implement full-time contract managers in the bid and negotiation stage for
Contract the highest project/risk class
Management 2.3 Implement documented bid/no-bid process/release to prepare bid
2.4 Implement bid release process with Group-specific and Region-specific
project and risk classes
2.5 Final bid release by review board; seek input from Group Executive Management or
Regional Management for highest project/risk class
2.6 Provide full-time contract managers to handle projects at the highest project/risk level
2.7 Implement mandatory review for “unacceptable provisions”
2.8 Implement mandatory Group/Region policy for project business
2.9 Ensure intensive use of standards and tools provided
2.10 Hold mandatory training session on contract law and claim management for technical/
commercial employees in Sales and Project Management
2.11 Install contract management community at the Group/Region level
3.1 Establish project-driven organization
Module 3 3.2 Apply integrated project controlling process from bid/no-bid decision to project
Project wrap-up, esp. integrated management of risks, modifications, opportunities, and claims
Controlling 3.3 Implement mandatory milestones/Quality Gates in the project process
3.4 Implement management-driven project discussion meetings at regular intervals using
standardized reporting procedures
4.1 Implement personnel development in project management
Module 4
4.2 Create letter of empowerment
Personnel 4.3 Conclude goal agreement
Management 4.4 Include project goals in special payments
4.5 Implement project incentive system
5.1 Determine qualification needs
Module 5 5.2 Carry out qualification measures
Qualification 5.3 Safeguard quality requirements for qualification measures
173
Implementation status Modules 6–12 (form) – 2 /2
PM@Siemens Group/Div/Subd/BS/Region
module PM@Siemens Recommendations
.... .... .... ....
6.1 Use of MS Project, Primavera, SAP PS, SPIRIDON solution “Solution Business” as standard tools
Modul 6
6.2 Participation in further development and introduction of the PM Portal as a standard solution for
PM Portal project workplaces
Module 7 7.1 Active implementation of the Quality Management function in the project
7.2 Appointment of Quality Manager in the project
Operative
7.3 Drawing up project-specific Quality Plan (Q-plan)
Qual. Manag. 7.4 Systematic project closure
Module 8 8.1 Establishment of a Project Management sub-community
8.2 Implementing project learning cycle including Lessons Learned/project debriefing
Knowledge
8.3 Passing on knowledge through coaching in PACT* Workshops
Management
Module 9 9.1 Establishing implementation process
9.2 Determining the implementation status
Transfer a. Im-
9.3 Drawing up PM scorecard
plementation 9.4 Analysis of projects business
Module 10 10.1 Implementing PMA+ Assessment according to Group or Region-specific requirements
10.2 Implementing CT SE Assessment in the Organizational Units with project business
PM Assessment
Modul 11 11.1 Integration of the Purchasing function in the process must be ensured at an early stage
continuously from acquisition through to the warranty period
Project
11.2 Every project must be mandatorily supported by a Project Procurement Manager (PPM)
Purchasing 11.3 Compliance with Group-defined Procurement Processes including Change Management
(utilizing available operative ordering systems) must be assured
11.4 Customer contract contents in supplier contracts (back-to-back) must be consistently secured in
cooperation with Contract Management
11.5 A project-specific supplier evaluation must be performed to reduce costs and improve quality
at both internal and external suppliers
12.1 Introducing processes and roles for Small Projects
Modul 12
12.2 Ensuring Contract Management for Small Projects
Small Projects
12.3 Implementing Personnel Management for Small Projects
12.4 Implementing qualification for Small Projects
12.5 Implementing processes for the transfer and implementation of Small Projects
12.6 Implementing PM Assessment for Small Projects
174
Recommendation 9.3:
Drawing up PM scorecard
The effect of the actions shows up in the op- The trend in the quality of order entry for
erative projects business. A report on the new projects, along with the improved mar-
project business situation of an organiza- gins attainable in projects, serve as a yard-
tional unit is therefore produced at regular stick for effective implementation of elabo-
intervals with the aim of identifying im- rated recommendations.
provements and analyzing how worthwhile
This project Scorecard of the Groups/Regions
measures taken to date have been.
involved is subjected to quarterly controlling
by the Steering Committee.
175
Scorecard PM@Siemens
Knowledge PM Portal
Management
Operative Q4/2005
Quality
Management Q3/2005
176
Recommendation 9.4:
Analysis of projects business
177
Definition of key figures in project analysis
100
1. Group data
80 Total sales in FY 4“444 €
Proportion – projects business
in FY 5“555 €
60
-40
3. Number of project managers certif.
-60
New orders received before FY 2004
Project Manager (overall) 200 150
New orders received in FY 2004
178
» Assessments create the
transparency for improving
projects and processes
«
t
en
ssm
A s PM
se
PM Assessment
Module 10
Assessments create the transparency
for improving projects and processes.
The implementation status of the stan- The processes defined and used in the or-
dards elaborated for the PM@Siemens ganization offer the best possible guarantee
Initiative and the maturity level of the that the same principles will be applied for
processes in the projects and project all projects within an organization. This en-
organizations of the Groups and Regions sures continuity and reproducible quality of
should be analyzed at regular intervals. projects and products to the benefit of the
The results of these analyses form the ba- organization and the customer.
sis for defining appropriate actions for im-
These first two analyses, 1 and 2, are car-
provements that are then implemented.
ried out with the project team members
The analyses are carried out at different and the project organizations.
levels and from different viewpoints:
project, organization, and the initiative it- 3. Analysis of the success of the
self.
PM@Siemens modules and of the
initiative
1. Analysis of projects
The results of analyses 1 and 2 are fed back
Analysis of an ongoing project to determine into the initiative and provide the basis for a
how far the elements of a successful project continuous improvement process.
management system have been realized,
such as planning, contract management, The PM@Siemens initiative records the find-
and risk management. The assessment re- ings about strengths and weaknesses as
sult shows whether a high standard of well as identified Best Practices. Expert
(project) clarity has been attained through teams select Best Practices from this fund of
adequate principles, guidelines, specifica- knowledge or elaborate them jointly. Where
tions, etc. and whether it can thus be en- practical, these are defined as the Siemens
sured that the project is being handled effi- standard.
ciently and effectively.
181
Project Management Assessment Procedure
Only analyses 1 and 2 are dealt with in Two harmonized, mutually complementary
more detail here. procedures/tools are recommended for carry-
ing out assessments:
A method of carrying out such analyses that
has proved its value in practice are assess- PMA+ (Analysis 1) and
ments in which the current status of the de- MPM Assessements* (Analysis 2)
fined processes and procedures actively im-
plemented in the project or within the Both assessment methods
organization are compared with a standard-
follow the principle of the top+ system
ized model of Best Practices.
for consistent optimization of product
and process quality.
are integrated in the particular control
loop for optimizing processes and
projects.
are geared to identifying the need for
action.
* formerly CT SE Assessments
182
Control loop for optimizing processes and projects
PM@Siemens
Organization
Project
MPM Assessment
PMA+ 6
Monitor
progress 1
5 Define
improvement
Implement targets
actions
4 2 PMA+
Define Determine MPM
actions main problem Assessment
3 areas
Identify
improvement
levers
PMA+
MPM-Assessment
183
Recommendation framework for a successful PM Assessment
In summary, the following recommendations can be made for
successful PM Assessment:
Recommendation 10.1:
Implementing PMA+ Assessment according to Group or Region-specific requirements
184
Of particular advantage is its uncomplicated The better the concurrence between the
nature; a typical run takes a few hours. For project analyzed and the specified process
this reason, it can be put to work repeatedly steps and results, the higher the rating.
during the course of a project, e.g., in order
In PMA+, the content-related scope and the
to make sure that important project mile-
project assessment take the form of an
stones/Quality Gates are reached. The list of
Access-based DP application, downloaded
questions can be filtered either for the bid or
from the PM@Siemens Homepage. The tool
the execution phase.
comprises questions on the project manage-
The idea behind PMA+ is the GMP (Associa- ment system; the answers can be entered
tion for Project Management) model for directly into the tool. The assessment is
Project Excellence. This model defines those worked out and presented on the basis of
subject areas that experts unanimously these answers.
agree are essential for a project’s success
(see assessment spider chart). Compared to
the initial model, the individual subject
areas are further broken down in order to
give greater consideration to significant
Project Management issues.
185
Illustration of the results of PMA+
This diagram depicts an example of a PMA+ project management system and deviations
result for a project. The spider chart provides from defined standards at the time of investi-
an overview of the strengths and weakness- gation.
es of the project in relation to the applied
186
Recommendation 10.2:
Implementing Maturity in Project Management Assessment (MPM Assessment)*
in the Organizational Units with project business
187
The MPM Assessment is a practically orient- Evaluation of project documents and a dem-
ed method that analyzes the documented onstration of procedures directly at the work-
process and the process actually applied place round off this compilation of informa-
with respect to project management. It also tion. The maturity level is then determined
examines the optimization potential with automatically by answers to the questions
the greatest leverage effect. At the end, a contained in the underlying list.
list of actions is drawn up and evaluated by
The key assessment results comprise a port-
the assessment team members with respect
folio specifying what needs to be done (de-
to implementation and priorities set for the
rived from the strengths and weaknesses
actions.
profile), along with detailed proposals for ac-
The assessments are carried out by two as- tion.
sessors from CT SE with the participation of
These detailed proposals for action and their
management, managers of the projects at
implementation step by step by means of
the particular project phases from sales,
work packages provide the basis for improv-
through the bidding phase to execution,
ing process quality and rectifying inherent
and project staff (e.g., purchaser, system en-
weaknesses. The results thus benefit all the
gineers, testers, quality assurance officers,
projects of an organization equally.
etc.). Those involved in the assessment do
not need any special preparation, although All results are confidential and responsibility
it is important that all participants are avail- for their use lies with the organization.
able and keep strictly to the schedule. In order to ensure effective implementation,
A complete MPM assessment usually takes CT SE will participate in this process on re-
three weeks from the kick-off event to the fi- quest and offers Improvement Workshops
nal presentation. The organization partici- and individual consulting for this.
pates directly for about 1 week; the rest of A MPM Assessment should be repeated at in-
the time is used for evaluation and process- tervals of one to two years in the interests of
ing of the recommendations for action. a systematic continuous improvement proc-
In separate interview sessions with those in- ess (CIP).
volved, the assessors determine a strengths Contact for planning, arranging dates and
and weaknesses profile for the defined and implementation (worldwide):
practiced project management processes.
CT SE 4, Karl Lebsanft
([email protected])
http://intranet.ct.siemens.de/de/tech/
abteilungen/se/fachzentren/se4/
index.html
188
Illustration of results in the MPM Assessment
The graphic illustration of the assessment The illustration shows comparisons between
concurs with the five stages of the CMMI© the basis for defining goals – i.e., what is
assessment basis. Maturity levels are shown documented and specified – and their actual
for the individual project management top- implementation.
ics and overall process control.
Project Acquisition
Importance
1 Adjusting of process description to requirements
managements for to the redundancies and fix the C M L A
points of intersection between organization
2 Further systematizing of project planning procedure
B M L A
through an use of methods (e.g. target)
189
Assessment planning
Group/
Regional
Coordinator
GC/RC
Assessment
Planner
(CT SE)
Senior Mgt.
(Group)
PM@Siemens
Send up-
Prepare Enter Agree Send file to Initiate Check file
dated
assessment data in data with PM@Siemens regular and agree
calendar to
calendar calendar CT SE 4 checking with CT SE 4
PM@Siemens
PM@Siemens GC/RC coordi- GC/RC GC/RC sends PM@Siemens GC/RC checks GC/RC sends
sends assess- nates assess- agrees on the completed sends the that file is up updated cal-
ment calen- ment planning schedule on file to assessment to date and endar to
dar to the on FY basis with FY basis PM@Siemens calendar to agrees on the PM@Siemens/
GC/RC the Senior Mgt. with CT SE 4 with copy to GC/RC 2 x planning data copy to CT SE 4
of the Division/ planners CT SE 4 per FY with CT SE 4
Subdivision/
Region
Enters the
required data
in the list responsible involved in process
Checks all data
190
Responsibilities in Assessment
Planning
PM@Siemens is responsible for: The CT SE Assessment Planner is responsi-
ble for:
Preparing the assessment calendar
Checking the planning data supplied for
Initiating updating twice per fiscal year
feasibility
(FY)
Making suitable resources available for
Processing the data supplied
implementation of the assessment by
Sending the complete, up-to-date file to CT SE.
CT SE Assessment Planner
Reporting the status to PM@Siemens
Steering Committee (STC).
191
Scheduling process for the start of assessment
Group/
Regional
Coordinator
GC/RC
Assessment
Planner
(CT SE)
Assessors
Assessment
Coordinator
(Org. Unit)
Senior Mgt.
(Group)
PM@Siemens
192
Responsibilities for
scheduling
The Group/Regional Coordinator is respon- The CT SE Planner is responsible for:
sible for: confirming the agreed date for the start
keeping the assessment calendar and providing information about the
updated basic conditions
coordinating planning with the updating the deadline list and publishing
management it on the intranet
assisting management with the selection reporting implementation of the
of the Group Assessment Coordinators. assessment to the Group Coordinator
giving the agreed data to PM@Siemens.
The Assessment Coordinator of the
Organizational Unit is responsible for:
agreeing firm dates for the start of the
MPM Assessment with the
• Management of the Organizational
Unit
and
• CT SE 4 Planner (Changes of date:
with information to GC/RC)
confirming the agreed date in writing
(e.g., mail to CT SE Planner)
helping plan the contents of the assess-
ment and involvement in the assessment
process.
193
» Project procurement is the way
to increase the hit rate and
improve project results
«
Project Procurement
t
en
oc ct
em
Module 11
Pr oje
ur
Pr
Project procurement is the way to increase
the hit rate and improve project results.
Project Procurement
New Old
∆ Exploitation OEC
of potential
by Project
Procurement
t
Bid
Pre- Project preparation
Execution Warranty
acquisition acquisition Contract
negotiation
197
The Project Procurement module describes ing Committee Global Competitiveness)
how the Purchasing function is integrated in have approved it as binding within Siemens.
the principal process steps. The following
As an aid to implementation, the services, in-
recommendations are mandatory for all
formation and input needed from the Pur-
Category A and B projects.
chasing function are described in the particu-
They have been devised jointly by procure- lar project phases (see publication in the
ment experts from the Groups and Regions Global Procurement Web at
participating in the PM@Siemens initiative https://intranet.gpl.siemens.com/
and the Global Procurement and Logistics projekteinkauf).
Corporate Center. The relevant bodies (Glo-
bal Procurement Board, PM@Siemens, Steer-
Recommendation 11.1:
Integration of the Purchasing function in the process must be ensured at an early
stage continuously from acquisition through to the warranty period. This enables
the potentials offered by the procurement market to be exploited permanently.
Process phases
1 2 3 4 5 6
Pre- Project Bid Contract Project Purchasing, Commis- After
acquisition acquisition preparation negotiation handover, dispatch & sioning & Sales
Warranty
opening & construc- acceptance
planning tion
198
Involvement of the Purchasing function in and Regions worldwide; the Groups and Re-
the PM@Siemens process is guaranteed by 6 gions must take organizational measures to
defined involvement points supplementary ensure this.
to the descriptions in the tables in Module 1.
These must be implemented by the Groups
199
Recommendation 11.2:
Every project must be supported by a Project Procurement Manager (PPM);
this is mandatory.
A Project Procurement Manager (PPM) must The PPM is also the interface to the Siemens
be appointed by Purchasing in the project ac- procurement network, in other words to
quisition phase and actively incorporated in centralized entities, use of skeleton agree-
the project as a permanent team member by ments, award of orders to preferred suppli-
the Project Management. ers and the involvement of the Procurement
Engineer.
The PPM is responsible for analyzing the pro-
curement market and assessing the risks on
this market, as well as for cost calculation
for materials and implementing global pro-
curement strategies.
200
Activities and performance of Purchasing in each project phase
Incorporation PM@Siemens Phase Function
points
201
Recommendation 11.3:
Compliance with Group-defined Procurement Processes including
Change Management (utilizing available operative ordering systems)
must be assured.
Recommendation 11.4:
Customer contract contents in supplier contracts (back-to-back)
must be consistently secured in cooperation with Contract Management.
The essential customer contract contents The PPM is supported in this function by a
must be transposed onto the relevant suppli- Contract Manager in the Group, a Contract
er contracts (back-to-back) in order to avoid Manager directly in Purchasing or, for com-
divergences that work to our disadvantage, plex questions, also by Legal Services. The
e.g., in performance characteristics and pay- aim of Contract Management in Purchasing
ment periods (see following illustration). is to continuously identify and assess suppli-
Fulfilling these requirements is one of the er contract loopholes and to eliminate them
core functions of the Project Procurement (see Contract Management module).
Manager (PPM).
This security mechanism (feedback) also ap-
plies to Claim Management in Purchasing. In
this case, the purpose of Claim Management
is to pass on additional expenditure that has
not been calculated to suppliers as fully as
possible and to avert unjustified claims by
suppliers
202
Claim Management aims primarily to pre- The assertion and negotiation of any
vent a deterioration in the calculated project project claims concerning suppliers is han-
results arising from demands made by sup- dled by the PPM in coordination with the
pliers. Contract/Claim Manager applicable (analo-
gous to the descriptions in the Contract
Management module).
Project Specifications
Contract/Claim Management
Risk Management
Change Management
Project Specifications
Contract/Claim Management
Risk Management
Change Management
203
Recommendation 11.5:
A project-specific supplier evaluation must be performed to reduce costs and improve
quality at both internal and external suppliers.
Within the scope of a project analysis and in The results of the evaluation will be incor-
order to further develop the supplier base, a porated in a regular assessment. This forms
cross-functional evaluation of strategic the foundation for the selection and further
project suppliers must be performed by the development of preferred suppliers to en-
project team (PPM and Process Partners in sure that the best suppliers are engaged for
Logistics and Project Management) in ac- project requirements for future awards of
cordance with a method that is uniform orders.
throughout the Groups.
Long-term improvements in efficiency
The evaluation is carried out in the company
resulting in mutual cost benefits can be
tool click4suppliers (c4s) and is initiated by
brought about by consistently further devel-
the PPM.
oping preferred suppliers within the frame-
work of supplier target agreements and
supplier development activities.
Summary
Due to its particular characteristics (batch
size 1, low repetition rates, etc.), projects
business places high demands on
Procurement.
The nature of the procurement activity in
projects business is such that the very close
interaction between Project Management
and Procurement (Project Procurement
Manager), especially in the project acquisi-
tion phases, has a key influence on the suc-
cess of a project.
The binding recommendations in
PM@Siemens described in this module en-
sure close interlinking and involvement of
the Purchasing function in projects business
at an early stage.
204
» Small Projects –
compact Project Management «
Small Projects
Module 12
ts
all jec
Sm Pro
Small Projects –
the compact approach to Project Management
Introduction to and
Einleitung und Definition
Definition of Small
Kleine Projects
Projekte
207
Initial question Response
1. Volume Yes/No
Is the volume less than the limiting value? (Group-specific)
2. Agreement Yes/No
Is it a standard or framework agreement?
3. Solution/Technology Yes/No
Is it a standard solution or familiar technology?
4. Customer Yes/No
Have any economically or technically successful projects been carried
out for the customer recently?
5. Organizational and time-related risks Yes/No
Can the solution be provided within the required timeframe?
Small Projects are handled increasingly in a mandatory standards and requirements (e.g.
process-oriented fashion in accordance with standard forms and templates).
208
Recommendation framework for successful Small Projects
In summary, the following recommendations can be made for
successful Small Projects:
Recommendation 12.1:
Introducing processes and roles for Small Projects
Minimum Standard
The relevant standard reference process de- The milestone designation is the same as for
scribed in Module 1 is also applied for Small large projects, but the scope of the work re-
Projects in all of their phases and with the sults to be supplied is smaller. The illustra-
defined milestones. However, in order to tion below represents the reduced process
make allowance for the lower complexity of model compared with the overall model.
Small Projects, individual phases have been
combined.
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Bid Project Purcha- Construc-
Pre- Project Contract opening sing & tion,
prepara- Project Detailed Commis- Accep- Project
acquisi- acquisi- negotia- Dispatch installa- Warranty
tion handover & clari- planning Manu- sioning tance closure
tion tion tion fication facture tion
1 2 3 4 5 6 8
Purcha-
12 13 14
Project
Pre- Project
Bid
Contract kick-off sing & Manu-
prepara- Project and clari- facture Accep- Project
acquisi- acquisi-
tion
negotia- Dispatch 9 tance closure
handover fication Construction
Warranty Minimum standards were defined
tion tion tion for each phase in terms of:
Detailed Commis- 10 • Documents
schedule sioning
• Responsibilities
7 11
209
Contrary to Large Service Projects, the mobi- A minimum standard was therefore defined
lization, ramp up and operations phase is on the basis of the project process (Module 1).
not as emphasized and hence some process This minimum standard, which is required for
phases do not even exist. The processes to every project, defines the work results re-
be pursued for Small Service Projects are quired for each project milestone.
quite similar to the ones for Small plant and
solution Projects and therefore to be han- The work results defined here:
dled accordingly. Necessary national adapta-
are considered minimum requirements
tions to the minimum standard are shown in
the reference table below. must be attained in each project
Effective March 2006, the PM@Siemens must be documented adequately and
Views displayed in the Siemens Reference verifiably.
Process House can be accessed via the fol-
lowing link: https://cio.siemens.com/rph The implementation, in particular the stipula-
tion as to the method to be used to perform
the work and document the work results, lies
within each Group's sphere of responsibility.
210
The following reference table describes
the minimum standard for Small Projects
Phase Work results End Description Responsible
milestone
Pre- What does the customer want? PM010 Decision on whether Sales & Marketing
acquisition E.g., inquiry, invitation to tender, Aquisition bid preparation or
Statement of Work Go/No-Go project initiation is to
Likelihood of a project: L decision be considered
Documentation of go/no-go (optional)
Project Categorization of the project, e.g., D-I, escalation PM020 Decision on whether Sales&Marketing
Acquisition level I–IV+ => determining of the “Level of Authority” Bid a bid is to be prepared (for Proposal Factory)
project definition: e.g., project datasheet decision Involving: Proposal Fac-
Risk estimate tory or Proposal Manager
Documentation Bid/no-bid
Bid Bid on basis of standard contracts and the PM040 Decision on whether Proposal Manager/
preparation relevant General Terms & Conditions Bid to submit bid to customer Bid Manager
Costing approval Involving: Sales&Marketing,
Solution concept commercial functions,
Initial project plan Project Manager, if required
Updated risk estimate
Contract Review/update, new creation or archiving (where PM070 Customer’s decision Sales & Marketing
negotiation applicable) of work results generated in preliminary Project to accept/refuse bid
phases (in particular in phase 3) on basis of won/lost
negotiations with customer.
Project Open- Official detailed planning (time, resources, scope PM100 Project implementation Project Responsible
of supplies, expenditure) Order receipt may begin, all conditions
ing and Organization clarified fulfilled
Clarification, Accounting framework PM200
Detailed Claim and CR strategy Approval of
Planning detailed
planning
Purchasing & List of open points and known deficits PM300 From the viewpoint of Project Responsible
Manufacture Proof of performed services, work results and Dispatch approval project implementation,
products, e.g., delivery dockets; PM400 Material all those aspects of the
Dispatch provision of forms for acceptance and resources scope of the contract
Construction at site; which are relevant for
Installation/ PM550 Construct./ acceptance have been
Install. completed submitted or delivered
Service* PM600 to the customer, or have
Commis- Release for cus- been otherwise rendered
sioning tomer accep-
tance
Project List of open points and known deficits for the PM670 Completion of project Project Responsible
closure project are rectified and accepted Project activities
Lessons Learned (optional) closure
Post costing (final) Compiling of project
Recorded handover to service** information for the
Archiving warranty period
211
Explicit Implementation Recom- Link to:
mendation: Process Guidelines for Sales & Marketing,
Based on the above referenced table, each Project Implementation (Small Projects)
Group / each Region creates an overview of and Service
the actual templates and tools with which http://intranet.sbt.siemens.com/top-plus/de/
the work results are to be achieved and docu- browsertree/index.asp
mented, and which roles are responsible. Guide for Small Projects
This overview is then declared as binding https://chestra.mch.sbs.de/chestra/index.
throughout the entire Group/Region. htm?portalview=Small-Projects
Consequently, the contents in the columns Intranet-based Workflow Project
Phase, Work results, End milestone and De- Management
scription must be taken over as is. The https://dms-02.erlm.siemens.de/en/livelink.
Group-specific roles are then entered in the exe?func=ll&objId=162285&objAction=bro
Roles column, while the templates and tools wse&sort=name
which have to be used to achieve the work
results for each phase are entered in their ap- Services – Processes/Project Management
propriate column (see Fig. 12.5). https://intranet.siemens.com/ptd-se-prozesse
Group-specific templates
Templates of the Groups I&S, PTD, SBS and
SBT are an integral part of the above links.
Take over Take over Take over Take over Enter roles Enter group
group specific specific
212
Project Controlling Explicit Implementation Recom-
Project Controlling is an essential basis for mendation:
managing projects successfully. Ultimately, The meetings should cover at least the
the success of a project is measured in terms schedule, additions, deletions, risks and
of profit and customer satisfaction. costs. The results of the project meeting
Because of the reduced project manage- should be documented.
ment budget in Small Projects, the expenses
for controlling and reporting should be limit- Link to:
ed to a standardized minimum. Process Policies for Project Controlling
Therefore, the four-eye principle must be (including Costing), Risk Analysis and
maintained. The Project Controller role will Authorization
be organized to handle multiple projects. http://intranet.sbt.siemens.com/
con_guidelines/de/
At a minimum, regular documented project
meetings with the project's Business Respon- http://intranet.sbt.siemens.com/top-plus/de/
sible must be held. This person does not nec- browsertree/index.asp
essarily have to be the line manager. (see Project Implementation, Process Guide-
line, Monitoring & Controlling)
213
Operational Project Procurement
Quality Management A professional procurement function is as im-
Professional Operational Quality Manage- portant for Small Projects as it is for large
ment is as important for Small Projects as it ones. However, due to budget constraints, it
is for large ones. Operational Quality Man- cannot be generally implemented in a
agement is usually performed by the Project project-specific manner. As a result, Project
Manager, who must have access to support Procurement is performed by a regionally or-
from a certified regional Quality Manager ganized purchasing function.
when necessary. The main task of the regional purchasing
Quality assurance measures such as reviews, function is supplier management. Focusing
tests and acceptance procedures must be on a few preferred suppliers can generate a
taken into account and documented in the pooling effect for Small Projects as well, ide-
Project Plan. ally even across Group and regional borders.
The purchasing function should negotiate
The regional Quality Manager (QM) selects framework agreements with the preferred
sample projects and checks their compliance suppliers from which the Project Managers
with the minimum standards for Small then request their requirements.
Projects. Process improvements are then ini-
tiated on the basis of the error analysis. Qualifying the preferred suppliers also reduc-
es the project risks with respect to schedules
In addition, Customer Satisfaction Surveys and costs.
are initiated by the QM, either for multiple
projects or project specific.
Link to:
Process Guidelines for
Project Procurement
https://intranet.gpl.siemens.com/einkauf
http://intranet.sbt.siemens.com/gpl/en/
guidelines.asp
214
Recommendation 12.2:
Ensuring Contract Management for Small Projects
215
Recommendation 12.3:
Implementing Personnel Management for Small Projects
Small Projects are part of the Project Man- PM4 (plus selected topics with focus on prof-
agement career path. The qualifications for it & loss) (see Module 5).
Project Managers are based on their practi-
Employees with this level of qualification
cal experience in project coordination, sup-
can then carry full responsibility for Small
plemented by corresponding basic training.
Projects (schedule, contents, costs), especial-
The experience as a Project Responsible for
ly with regard to the project budget.
Small Projects and the participation in basic
training for Small Projects correspond in es-
sence to the requirements of training level
Recommendation 12.4:
Implementing qualification for Small Projects
To ensure high quality of Project Man- Since the managers of Small Projects gener-
agement in Small Projects as well, all Project ally perform several roles and run multiple
Managers must undergo qualified training, projects simultaneously, the qualification
where they are taught the applicable program must offer comprehensive, yet com-
Siemens standards and learn to deal with pact process training.
the relevant local circumstances.
To this end, the following requirements have
Cost and acceptance considerations, as well been developed for the qualification pro-
as the fact that Small Projects are almost al- gram:
ways processed locally, require that this type
Joint training of all those involved in
of training be held on site in the respective
Small Projects (i.e. Sales & Marketing, Bid
local language.
Coordinators, commercial staff, Quality
Managers and Project Managers) must be
provided for specific Groups and on the
basis of the approaches, procedures and
directives applicable for that Group.
In order to ensure proximity to actual
work processes, adapting the training for
specific Groups (or parts thereof) on the
basis of a minimum standard is essential.
216
The training must take into account the Explicit Implementation
fact that the parallel execution of projects Recommendations:
creates specific complexities and requires
a special methodology. Learning Campus develops the training
for trainers in cooperation with the partic-
In order to introduce the Siemens stand- ipating Groups
ard comparably worldwide, a “train-the-
trainer” concept must be implemented. The Groups/Regions select the trainers
Experienced Project Managers are select- who will participate in the training pro-
ed as trainers and undergo the same gram in accordance with the above
training at the PM@Siemens Academy, criteria
after which they are responsible for incor- The trainers are responsible for the provi-
sion of training materials in accordance
porating the Siemens standards into the with the Group-specific minimum stand-
local training programs. ards
Training should be provided in a compact The Groups/Regions make certain that all
fashion, in the local business language, project-relevant employees are trained as
and locally on site. per the above concept
The Group Coordinators are responsible The training progress must be document-
for initiating the training, while the ed (target: 80% of relevant employees).
Divisional and Regional Coordinators are
responsible for the execution and success-
ful completion of training programs.
Siemens Academy
Qualified
Train- Selected experienced
the-Trainer Project Managers
phase from the Groups
Local
training
Project Coordinator
Sales & Marketing
Proposal Manager
Project Teams
217
Recommendation 12.5:
Implementing processes for the transfer and implementation of Small Projects
1 2 3
Actual Program Fit-Gap Adaptation
situation set-up Analysis Prioritization
4 5 6 7
Impact Continuous
Training Implementation Monitoring Analysis Improvement
Process (CIP)
The special challenge in the implementation Phase 1: The procedural model for imple-
of standardized processes for Small Pro- menting Module 12 has been communicat-
cesses lies in the spread of their application. ed. The general procedure has been agreed
Since most Small Projects are local business, upon.
the regional organizations worldwide must
Phase 2: The differences from the minimum
be addressed for the project harmonization
standards have been identified. This Fit-Gap
effort. This means not only the country
Analysis is conducted autonomously by a
headquarters, but the local branch offices as
Group or by the local management, e.g.
well.
quarterly. Scope is an entire organizational
To manage this resource-intensive task, we unit (e.g. local Branch), but not a single
must focus on the respective weak points. project.
The prerequisites and processes required for
Phase 3: The basic Group-specific adapta-
a successful rollout can be categorized into
tion of the minimum standards has been de-
seven phases.
veloped. Focus (weak) points have been
specified.
Phase 4: Trainers have been selected and
trained. Training materials and a training
schedule have been developed; training
courses have been conducted.
218
Phase 5: Agreed-upon process changes are The Group and Divisional Coordinators are
being implemented. The line organization in- responsible for the initiation and successful
cludes all the required roles. Project meet- completion of the rollouts.
ings/discussions are being held.
The links shown below guide you to Group-
Phase 6: Reporting of training progress, cov- specific solutions and adaptations of the
erage with project meetings and with the Small Projects module.
roles defined for the line organization.
Project results are measured with shotguns. Link to:
Phase 7: Degree of process improvement is Procedural models
known from repeated fit-gap analyses. https://projectmanagement.sbs.de
(see menu option PM@SBS)
For the measurements required for this ap-
proach, two mechanisms are best suited: http://intranet.sbt.siemens.com/top-
plus/de/process%20excellence/rollout%20
Shotgun diagrams process.asp
In its major points, the system for analyz-
ing Small Projects is the same as that for Measurement methods
Large Projects. One difference is that http://intranet.sbt.siemens.com/top-
with plus/de/process%20excellence/field%20
Small Projects only completed projects process%20assessment.asp
can be analyzed since an ongoing calcula- (Fit-Gap analysis)
tion is not always particularly informative
due to the short project duration. http://intranet.sbt.siemens.com/top-
plus/de/process%20excellence/shotgun.asp
Behavioral assessments (Shotgun)
These assessments analyze to what ex-
tent the processes being “lived” in the
regional units comply with the Group-
wide standard processes (fit-gap analy-
sis).
219
Recommendation 12.6:
Implementing PM Assessment for Small Projects
220
Self-assessments for Small Projects are Therefore the capability maturity assess-
optional, and their application is deter- ment of the line organization is of high
mined and governed individually by the relevance. Organizational assessments to
Groups. define the as-is situation and saving po-
tentials are optional
Organizational assessments (optional):
Because of the reduced project manage-
ment budget in Small Projects, various
functions (quality management, procure-
ment, controlling, contract management)
are not realized project specific, but inte-
grated into the line organization.
221
Siemens AG
Power Transmission
and Distribution
P.O. Box 32 20 Siemens AG
91050 Erlangen © 2006 by Siemens Aktiengesellschaft Berlin
and Munich. All rights reserved.
Germany PM-Guide V4
4th revised edition 02/06
http://projectmanagement.siemens.com For internal use only