JMC / Foundation Works From Loc No 105A, 143 To 208 - 003
JMC / Foundation Works From Loc No 105A, 143 To 208 - 003
JMC NO : JMC / FOUNDATION WORKS FROM LOC NO 105A, 143 TO 208 - 003
1 FOUNDATION WORKS
1.1 REBAR FIXING, 1ST STAGE AND 2ND STAGE TOWER CONCRETING AND EARTHWORK
Rebar
Sl.No Loc No Tower Type Soil Type 1st Stage 2nd stage Remarks
(MT)
1 105A UAT+6BE+4LE G2 3.72 1 -
JMC NO : JMC / FOUNDATION WORKS FROM LOC NO 105A, 143 TO 208 - 003
1 FOUNDATION WORKS
1.1 REBAR FIXING, 1ST STAGE AND 2ND STAGE TOWER CONCRETING AND EARTHWORK
Rebar
Sl.No Loc No Tower Type Soil Type 1st Stage 2nd stage Remarks
(MT)
29 170 UTT+0BE+6LE G7 3.43 1 1
JMC NO : JMC / FOUNDATION WORKS FROM LOC NO 105A, 143 TO 208 - 003
1 FOUNDATION WORKS
1.1 REBAR FIXING, 1ST STAGE AND 2ND STAGE TOWER CONCRETING AND EARTHWORK
Rebar
Sl.No Loc No Tower Type Soil Type 1st Stage 2nd stage Remarks
(MT)
57 198 UAT+0BE+2LE G1 5.03 1 -
58 199
GANTRY-1+0BE+-1.5LE G1- TG-2 4.59 1 -
59 200
GANTRY-2+0BE+-1.5LE G1- TG-1 3.95 1 -