J 2016 SCC OnLine APTEL 105 2310 Cnluacin 20240808 150736 1 36
J 2016 SCC OnLine APTEL 105 2310 Cnluacin 20240808 150736 1 36
J 2016 SCC OnLine APTEL 105 2310 Cnluacin 20240808 150736 1 36
In the Matter of
Jaiprakash Power Ventures Limited (Ertwhile M/s. Bina Power
Supply Company Ltd. Since Merged with Jaiprakash Power
Ventures Limited) Sector 128, Noida-201304 Uttar Pradesh …
Appellant;
Versus
1. Madhya Pradesh Electricity Regulatory Commission 5th Floor,
Metro Plaza, Arera Colony, Bittan Market, Bhopal-462 016
Madhya Pradesh … Respondent No 1.
2. Madhya Pradesh Power Transmission Company Limited
Nayagaon, Rampur, Jabalpur-482008 Madhya Pradesh …
Respondent No 2.
3. Madhya Pradesh Power Management Company Ltd. Shakti
Bhawan, Vidyut Nagar, Rampur, Jabalpur-482008 Madhya
Pradesh … Respondent No 3.
4. State Load Despatch Centre, Madhya Pradesh Power
Transmission Company Limited Nayagaon, Rampur, Jabalpur-
482008 Madhya Pradesh … Respondent No 4.
Appeal No. 34 of 2016 And IA No. 87 of 2016 And IA No. 88 of 2016
Decided on August 22, 2016
Counsel for the Appellant(s): Mr. Sanjay Sen, Sr. Adv, Mr. S. Venkatesh, Mr. Varun
Singh, Mr. Shashank Khurana Mr. Anuj P. Agarwala
Counsel for the Respondent(s): Ms. Mandakini Ghosh Ms. Ritika Singhal for R-1, Mr.
Manoj Dubey for R-2 and R-4, Mr. M.G. Ramachandran, Mr. Manoj Dubey, Mr.
Shubham Arya for R-3
The Judgment of the Court was delivered by
I.J. KAPOOR, TECHNICAL MEMBER:— The present Appeal is being filed by Jaiprakash
Power Ventures Ltd. (hereinafter referred to as the “Appellant” under Section 111 of
the Electricity Act, 2003 challenging the legality, validity and propriety of the
Impugned Order dated 07.01.2016 passed by the Madhya Pradesh Electricity
Regulatory Commission (hereinafter referred to as the “State Commission”) in
Petition No. 54 of 2015.
2. The Appellant, M/s. Jaiprakash Power Ventures Ltd. is a Generating Company
within the meaning of Section 2 of the Electricity Act, operating a 2 × 250 MW (Phase-
1) Bina Power plant in the State of Madhya Pradesh.
3. The Respondent No 1 is the Electricity Regulatory Commission for the State of
Madhya Pradesh exercising jurisdiction and discharging functions in terms of the
Electricity Act, 2003. The Respondent No 2 is Madhya Pradesh Power Transmission
Company Limited (“MPPTCL”) is State Transmission Utility in the state of Madhya
Pradesh. The Respondent No 3 is Madhya Pradesh Power Management Company
Limited (“MPPMCL”). The Respondent No 4 is State Load Despatch Centre (“SLDC”) in
the state of Madhya Pradesh.
4. Aggrieved by the Order dated 07.01.2016 passed by the State Commission, the
Appellant has preferred the present appeal broadly on the following grounds:
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 2 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
a) The State Commission while passing the Impugned Order adopted a pedantic
approach by superintending the focal issue raised by the Appellant, i.e. that each
participant of the Electrical System including the Appellant generator and the
Respondents have the responsibility of operating the electrical system in an
efficient manner which is also enshrined under the Preamble of the Electricity
Act, 2003 and the policies framed thereunder and relegated the dispute into a
purely contractual matter.
b) The State Commission while passing the Impugned Order has consigned the
focal issue raised by the Appellant about the efficiency of Appellants' generation
into a simpliciter contractual dispute. The Appellant in the Petition before the
State Commission had urged that ‘Technical Minimum’ generation of the
Appellant's generation capacity is not being maintained by the Respondent No 4,
SLDC and the Respondent No 3, Procurer on the pretext that the same is limited
to the Contract/Agreement between the Appellant and the Respondent No. 3.
The Appellant's contention that it is an accepted practice that ‘Technical
Minimum’ generation as a concept is only relatable to the Generating Plant/Unit's
physical generation capacity and not an agreement was entirely ignored by the
State Commission on the solitary premise that the same is not defined under the
PPA or the Regulations framed by the State Commission.
c) The Appellant in the proceedings before the State Commission had raised a
larger sectoral issue which was germane in the current market scenario wherein
the State Utilities have tied up PPA's more than their actual demand. In the
present scheme of things it is most imperative that the State Commission as a
regulator ensures that the electrical system (which includes the generator) of the
state operates in the most efficient and economical manner which it has failed to
do so in the present case.
d) The State Commission in passing the Impugned Order has failed to address the
larger issue of efficiency of the operation of Appellant's Power Plants by
pedantically interpreting the PPA signed between the Appellant and the
Respondent No. 3.
e) The State Commission in passing the Impugned Order has failed to appreciate
that the Statutory PPA was not signed with the intent that the Appellant would
only receive the Capacity Charges without actually generating power leading to
inefficiency in the operations of the Appellant. Whereas the objective behind the
PPA is that the Appellant would generate power in an efficient manner and the
Respondent No. 3 will off take such generated power on payment of the
regulated Tariff. The State Commission has also failed to appreciate that
inefficient generation cannot be the intent behind the Agreement or the Act and
the Regulations framed thereunder.
5. Facts of the present Appeal:
a) On 15.11.1994 the Appellant was incorporated under the Companies Act, 1956
by the name of Bina Power Supply Company Limited (BPSCL).
b) On 21.12.1994 Jaiprakash Hydro-Power Limited was incorporated under the
Companies Act, 1956. Subsequently, the name of the company was changed to
Jaiprakash Power Ventures Limited (JPVL) on 23.12.2009.
c) On 17.06.2008 a Meeting was held between the representative of the
Government of Madhya Pradesh (“GoMP”)/Madhya Pradesh State Electricity
Board (“MPSEB”) and the Appellant herein. As per the minutes of the meeting
recorded the Appellant undertook to supply 42% of the installed capacity of the
proposed capacity of plant i.e. 5 × 250 MW Phase-I (2 × 250 MW) and Phase-II
(3 × 250 MW) based on availability of the coal (for Phase II) for the plant to the
State and/or its Nominated Agencies for period of 25 years at the Tariff approved
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 3 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
enclosed) has intimated that in case of thermal power generating units the
backing down of power is to be limited up to 70% of the entitled power to MP
in case of capacity below 250 MW and 60% in case of above 250 MW. The
above letter of CGM (PM), MPPMCL further clarified that MPPMCL would not
permit generation more than above-mentioned limits of technical minimum
generation under surrender conditions. In view of the above, whenever the
power surrender instructions to technical minimum quantum of MP is issued
the same shall be limited to 60%/70% (as the case may be) of the contracted
ex-bus capacity of MP.”
m) In response to the letter dated 01.06.2015 of the Respondent No. 2/4, the
Appellant on 03.06.2015 communicated to Respondent no 2/4 that the definition
of Technical Minimum is for Machine/Unit, as explained in the letter dated
22.05.2015 from MPPMCL. This Technical Minimum cannot be applied to the
contracted capacity.
n) The Respondent No. 2/4 on 03.06.2015 responded to the Appellant saying that
the technical minimum is for the unit. However, it is the responsibility of the
generator to have long term procurers for its full capacity and if not, to sell the
balance quantity through bilateral/collective transactions. The only long term
customer of having 37.5% contracted capacity in the station cannot take
responsibility of supporting technical minimum for full unit capacity.
o) Even though the Technical Minimum of the Appellant's Unit of 250 MW was at
140 MW, the Respondent No. 2/4 issued a scheduling of 109.56 MW on
27.08.2015. The Appellant on the same date responded to the Respondent No.
2/4 with regard to the scheduling sought by stating that the technical minimum
of 250 MW machine is approx. 140 MW (export), which has been historically and
religiously followed by SLDC. Therefore any deviation below 140 MW (export) on
account of oil and other expenses (including reduction in efficiency) would be to
the account of Respondent No. 3.
p) On 28.08.2015 the Respondent No. 2 communicated to the Appellant and stated
that as decided by MPPMCL technical minimum of contracted power comes to 109
MW. Hence the Appellant herein is instructed to maintain 109 MW as per
schedule given by SLDC. Excess generation may be treated as non-compliance of
SLDC instruction.
q) The Appellant on the same date responded to the Respondent No. 2 and stated
that all things regarding technical minimum have been cleared in earlier
communications and unit cannot be run at 109 MW and unit will be run
accordingly to previous communications.
r) The Respondent No. 2 on 06.09.2015 communicated to the Appellant stating that
“JP Bina Unit # 1 has been synchronised at 5.16 hours and schedule was given
by SLDC. JP Bina unit is over injecting into the grid since it attained the load
more than 110 MW. This is violation of grid code. It is requested to adhere to
schedule given by SLDC.”
s) The Appellant on 06.09.2015 issued a letter to Respondent No. 2 inter-alia
stating that “Jaypee Bina can't have merchant power tie up in anticipation of MP
giving generation schedule; these require 24 hrs notice to tie up the balance 30-
40MW capacity on Power Exchange to ensure machine operation above technical
minimum. In the interim if “Jaypee Bina is not scheduled at technical minimum
then the deviation on account of DSM, any penalty on account of over injection
and the difference in additional cost would be to the account of Respondent No.
3.”
t) The Appellant filed Petition No. 54 of 2015 before the State Commission seeking
the following prayers:—
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 5 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
a) Set aside the Impugned Letter dated 01.06.2015 issued by the Respondent
No. 2 and 4.
b) Allow the recovery of any additional cost incurred by the Petitioner in
operating in accordance with the directions issued by the Respondent No. 2
and 4.
c) Grant such order, further relief/s in the facts and circumstances of the case as
this Hon'ble Commission may deem just and equitable in favour of the
Petitioner.
u) On 14.12.2015 the Appellant plant received the MOD from the Respondent No. 3.
As per Appellant the MOD so being prepared by the Respondent No. 3 was not on
the basis of variable cost but on the basis of variable cost, transmission losses
and statutory taxes.
v) The State Commission passed the Impugned Order on 07.01.2016 inter-alia
holding as follows:—“16. In view of the above, it is observed by the Commission
that the use of expression like Technical Minimum by the respondents in the
impugned communication has no relevance since the provisions under the PPA
executed between the procurer and the petitioner are explicitly clear for
commercial and technical obligation to be met by each of them. It is further
observed that the respondent (MPPMCL) is responsible only up to the contracted
capacity of the generating unit as per PPA. Any unscheduled available capacity
within the contracted capacity is compensated by way of fixed cost/capacity
charges paid by the Respondent No. 2 in terms of PPA. Besides, the petitioner is
responsible at its own expenses for maintaining the technical requirement during
operation of the plant while making its obligations under the power purchase
agreement. Therefore, no merit is found in the prayer of the petitioner for
recovery of any additional cost incurred by the petitioner in operating in
accordance with the directions issued by the Respondent No 1 in the impugned
communication. In view of the above observations and discussions, the subject
petition is dismissed and disposed-of.”
w) Aggrieved by the Impugned Order, Appellant has preferred the present Appeal.
6. QUESTIONS OF LAW
As per Appellant, following questions of law arise for consideration in the present
Appeal:
I. Whether the State Commission in passing the Impugned Order has adopted a
pedantic approach by superintending the focal issue raised by the Appellant,
i.e. that each participant of the Electrical System including the Appellant
generator and the Respondents have the responsibility of operating the
electrical system in an efficient manner which is also enshrined under the
Preamble of the Electricity Act, 2003 and the policies framed thereunder?
II. Whether the Appellant in the proceedings before the State Commission had
raised a larger sectoral issue which was germane in the current market
scenario wherein the State Utilities have tied up PPA's more than their actual
demand? Whether in the present scheme of things it is most imperative that
the State Commission as a regulator ensures that the electrical system (which
includes the Appellant) of the state operates in the most efficient and
economical manner which it has failed to do so in the present case?
III. Whether the State Commission in passing the Impugned Order has failed to
address the larger issue of efficiency of the operation of Appellant's Power
Plants by pedantically interpreting the PPA signed between the Appellant and
the Respondent No. 3?
IV. Whether the State Commission in passing the Impugned Order has failed to
appreciate that the Statutory PPA was not signed with the intent that the
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 6 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
Appellant would only receive the Capacity Charges without actually generating
power leading to inefficiency in the operations of the Appellant? Whether the
objective behind the PPA is that the Appellant would generate power in an
efficient manner and the Respondent No. 3 will off take such generated power
on payment of the regulated Tariff? Whether the present Impugned Order has
not considered the above and the State Commission has also failed to
appreciate that inefficient generation cannot be the intent behind the
Agreement or the Act and the Regulations framed thereunder?
V. Whether the State Commission in passing the Impugned Order could brush
aside the focal issue raised by the Appellant against Respondent SLDC on the
basis of the Affidavit filed by the Respondent No. 2?
VI. Whether the State Commission in passing the Impugned Order has failed to
address the issue of ‘Technical Minimum’ as an industry practise only the
pretext that the same is not defined under the State Commission's
Regulations or the PPA signed between the Appellant and the Respondent No.
3?
VII. Whether the State Commission has erred in passing the Impugned Order by
not going into the losses incurred by the Appellant due to scheduling below
‘Technical Minimum’ on the premise that Respondent No. 3 is only obligated
to pay capacity charge for the un-requisitioned capacity?
VIII. Whether the State Commission in passing the Impugned Order has failed
to appreciate that CERC Draft Notification/CERC Order though not
notified/passed in the context of the Appellant/Respondents but in fact is
applicable upon all generators who are directed by the Procurer/SLDC to
operate below the ‘Technical Minimum’?
IX. Whether the State Commission has erred in passing the Impugned Order as
the Respondent SLDC in terms of the Extant Regulations and the scheme of
the Act has to act as the apex body and safeguard the interest of the
generator as well as the procurer?
X. Whether the State Commission in passing the Impugned Order has erred in
not appreciating that as an industry wide practice it is the SLDC/RLDC who
object to scheduling below ‘Technical Minimum’ if such a requisition is made,
as the same was also observed in the Explanatory Memorandum issued by the
Central Commission which lead to the Draft Indian Grid Code being notified
for public comments?
XI. Whether the State Commission has failed to appreciate that mandate of
Section 32 is to ensure ‘Optimum Scheduling’ and not ‘Scheduling’ as being
interpreted in the Impugned Order?
XII. Whether the State Commission in passing the Impugned Order has wrongly
relied upon Article 4.3.5 of the PPA to hold that the Respondent No. 3 procurer
can requisition any capacity from the generator without considering the fact
that Article 4.3.5 is not the objective behind the Agreement as ultimately the
Agreement was entered for the purpose of setting up a power plant to supply
70% power? Whether Article 4.3.5 of the Agreement is only an exceptional
provision which comes into play in exceptional scenarios and cannot be used
to regulate the manner in which supply of power will be effected between
parties?
XIII. Whether the State Commission in passing the Impugned Order has wrongly
considered Article 4.3.3 of the PPA which does not cast any obligation upon
the generator to sell the un-requisition capacity but only provides an enabling
provision?
XIV. Whether the State Commission in passing the Impugned Order has
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 7 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
erroneously held that the payment of ‘Capacity Charges’ is the only obligation
of the Respondent No. 3 procurer especially when the said procurer has not
invoked Article 4.3 in terms of the PPA?
XV. Whether the State Commission in passing the Impugned Order incorrectly
held that ‘Technical Minimum’ is of no relevance especially when the Central
Commission is now seeking to amend the existing Gird Code to ensure that
generation below ‘Technical Minimum’ is curtailed as a practice and therefore
it is a larger issue at play presently?
XVI. Whether the State Commission has erred in not appreciating that the issue
of operation below ‘Technical Minimum’ is an issue which affects the financial
health of all generators in times to come?
XVII. Whether the State Commission has erred in not considering the submission
of the Appellant that the MOD being prepared by the Respondent No. 3 is
contrary to the Extant laws and hence cannot be the basis for the Respondent
No. 3 scheduling power below the ‘Technical Minimum’ capacity of the
Appellant's generating unit/plant?
XVIII. Whether the State Commission has gravely erred by accepting the
contention of the Respondents that due to ‘proposed regulation of power’ the
scheduling of the Appellant was done below the commercially accepted 140
MW which is the ‘Technical Minimum’ of the Appellant's Generating Unit
without appreciating that ‘Regulation of Power’ per se as a concept has also
not been defined under the extant Regulation of the State Commission or the
PPA signed between the Appellant and the Respondent No. 3.?
XIX. Whether the State Commission in passing the Impugned Order has failed to
appreciate that Appellant's station, being a thermal power station, is a Base
Load Station by design and such stations are designed to operate at a near
constant load and such frequent changes in load can cause severe damage to
the plant and its equipment?
XX. Whether the State Commission in passing the Impugned Order has failed to
appreciate that in the present market scenario where admittedly the
Respondent No. 3 is power surplus greater responsibility is required to be
exercised by the Respondent SLDC in ensuring that the Appellant's Power
Plant is not operated below its technical minimum especially since the
Appellant is the only generator with 70% tied up capacity with the State
Procurer?
XXI. Whether the State Commission in passing the Impugned Order has failed to
appreciate that the Appellant's Power Project has been established for the
specific purpose of ensuring supply of power to the State of Madhya Pradesh
and therefore higher regulatory accountability is required to be exercised by
other State Players to ensure that no undue financial and technical prejudice
is caused to the Appellant?
XXII. Whether the State Commission in passing the Impugned Order has failed
to appreciate that due to sudden and erratic scheduling being sought the
Appellant had been compelled to incur losses and to maintain its ‘Technical
Minimum’ by supplying power on day ahead basis in open market?
XXIII. Whether the State Commission in passing the Impugned Order has
wrongly relied solely upon Article 7.1.1 by not seeing the other comprehensive
provisions of the PPA such as Article 6.1.3 wherein it was the obligation of the
Procurer to keep available the entire contracted capacity unless a notice from
the Procurer under Article 4.3.3 was issued which has not been done till date?
7. We have heard at length Mr. Sanjay Sen, the learned senior Counsel for the
Appellant and Mr. M.G. Ramachandran, the learned Counsel for Respondent No 3, Ms.
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 8 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
Mandakini Ghosh, the learned Counsel for the State Commission and Mr. Manoj Dubey,
the learned Counsel for Respondent No 2 and Respondent No 4 and considered the
arguments put forth by the rival parties and their respective written submissions on
various issues identified in the present Appeal. Gist of the same is discussed
hereunder.
8. The learned Counsel for the Appellant has made following submissions on the
various issues raised in the Appeal for our consideration:
a) In scheduling optimum power from the Generator it is the duty and responsibility
of the Respondent No. 4 to ensure that the generator is not asked to operate
below its machine's Technical Minimum Capacity as the same would cause severe
operational prejudice to the generator, including the requirement to operate the
plant inefficiently on the basis of expensive fuel oil. However, in the present case
the SLDC blindly relied on the letter issued by the Respondent No. 3 to interpret
the ‘Technical Minimum’ of the Appellant's generating capacity to the contracted
capacity in terms as provided in the Power Purchase Agreement dated
05.01.2011.
b) The State Commission completely erred in holding that technical minimum is to
be read in terms of the contract and not the installed capacity of the plant. This
view of State Commission is different from the view of other State Commissions
like MERC Judgment dated 29th January, 2016 passed in Petition No. 121 of 2015
titled Maharashtra State Electricity Distribution Co. Ltd. v. Maharashtra Veej
Grahak Sanghatana and UPERC Judgment dated 20.01.2016 passed in Petition
No. 1070/2015 titled Rosa Power Supply Company Limited v. UPSLDC
c) The Merit Order placed before the State Commission was issued on the basis of
misconceived principles. The State Commission has turned a blind eye towards
the issue of Merit Order Despatch (MOD) and has not recorded any findings on
the issue.
d) Technical Minimum of a Generation Power Plant is based upon the
Unit/Plant Capacity and not the Contracted Capacity.
i. ‘Technical Minimum’ as a concept means the technical parameters below which
the machines should not be permitted to operate as below this level the
machines become unstable and inefficient. This aspect has been recognised by
the Commissions, utilities, generating companies etc. from the very inception.
ii. It is an accepted practice that ‘Technical Minimum’ Generation as a concept is
only relatable to the Generating Plant/Unit's physical generation capacity and
not an agreement between a generator and DISCOM. The Technical Minimum
of the Appellant's Power Plant is not being maintained by the SLDC on the
pretext that the same is limited to the Contract/Agreement between the
Appellant and the Respondent No. 3. The said restriction has been imposed by
the SLDC pursuant to the letter dated 22.05.2015 of the Respondent No. 3
which was challenged before the State Commission.
iii. This issue of Technical minimum was deliberated at length by the Central
Commission in Petition No. 142/MP/2012 wherein the Central Commission
vide its order dated 02nd September 2015 held as follows:—
“45. From the submissions of CEA, it is inferred that the technical
minimum of thermal generating units should not be less than 50% of MCR
loading of the unit for old as well as new plants. In our view operation of
thermal generating station on technical minimum has commercial
implication for the generator in terms of increase in heat rate, secondary
fuel oil consumption and auxiliary energy consumption which enhances the
actual energy charges and the same cannot be loaded to other beneficiaries
which are not being regulated. Therefore there is a need for adjusting the
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 9 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
implication of enhanced energy charges from the revenue earned from sale
of regulated power apart from normative energy charges and fixed charges.
The Commission has proposed amendment to the Central Electricity
Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010 by
prescribing a technical minimum of 55% along with compensation
mechanism to make good the loss of the generating station. Therefore, the
issue of operation of the thermal generating unit at technical minimum and
its operational and financial implication during the period of regulation of
power supply shall be dealt with in accordance with the amendment to the
Grid Code which will be finalized and notified shortly.”
iv. The Central Commission issued Draft Notification of the Central Electricity
Regulatory Commission (Indian Electricity Grid Code) (Fourth Amendment)
Regulations, 2015 in July, 2015, wherein the Central Commission had sought
to introduce the definition of “Technical Minimum Schedule” at sub-regulation
6.3 B of Draft Regulations which is as follows:—
“The technical minimum schedule of operation in respect of ISGS shall
be 55% of the MCR loading of unit/units of generating station.”
v. In the Explanatory Memorandum of the draft regulations issued by Central
Commission, following was specified for specifying minimum technical
operation of generating stations on unit basis:
“36. It is proposed that the technical minimum may initially be kept as
55% of Installed Capacity/MCR of unit/units for old as well as new plants in
due consideration of CEA recommendations and giving some margin over
the recommended technical minimum of 50% by CEA. However, the
operation at 55% loading has commercial implication for the generator in
terms of increase in heat rate, secondary fuel oil consumption and auxiliary
energy consumption, thereby increasing the actual energy charges. The
generator will have to be compensated for this increase in energy charges.
37. It is felt that any reduction in loading of units below 85% on account
of low despatch schedule given by beneficiaries/RLDCs may have to be
compensated by the beneficiaries. The Standard Bidding Documents (SBD)
for case-II/UMPP projects brought out by Ministry of Power provide for heat
rate degradation for part load operation corresponding to different unit
loadings. In accordance with the same, following heat rate degradation for
part load operation corresponding to different unit loadings may be
provided:
…………………………….
…………………………….
…………………………….
Below 55%, the station may go for reserve shut down.
38. The generating company may be allowed to seek relief at the end of
the year based on average unit loading due to low despatch schedule given
by beneficiaries/RLDC but not because of any other reason including short
supply of fuel/shortage of fuel; Commission may allow compensation for
increase in station heat rate, secondary fuel oil consumption and auxiliary
energy consumption after prudence check on a petition to be filed by the
generating company giving requisite details of unit loadings, forced
outages, planned outages, PLF, generation at generator terminal, energy
sent out exbus, actual heat rate, number of start-ups, actual secondary fuel
oil consumption, actual auxiliary energy consumption etc. In case of gas
based stations, compensation shall be decided based on the characteristic
curve provided by the manufacturer and after prudence check of the actual
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 10 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
covered by the provisions under Section 33(1) of the Act. Under Section 33
(1) of the Act, SLDC has to decide the request for scheduling made by the
Appellant only in accordance with the parameters prescribed under the Act.
Thus, SLDC is required to take into account only issues relating to
transmission and the transmission network when deciding any request for
scheduling of power. “In view of the above observations of this Tribunal, it
is abundantly clear that the SLDC while discharging its functions has to act
as an independent autonomous body and cannot in any manner act as an
extended arm of the Government Utility.
iii. As per clause 4.3.5 of the PPA, it is the Procurer, who is required to issue
Notice to the Appellant to the effect that it will not procure its contracted
capacity for a particular period. The SLDC cannot now be permitted to say that
the letter dated 28.08.2015 is a notice under Clause 4.3.5 of the PPA, which
notice had to be issued by the Respondent Procurer, who is a party of the PPA
(and not the SLDC). The notice for seeking power below the contracted
capacity has till date not been issued by the Respondent Procurer. It is only
after such notice, the Appellant can plan the sale of its un-scheduled capacity.
The procurer has been drastically reducing the schedules on a day ahead basis
for a base load thermal power plant, which is both contrary to the intention of
the contract and impractical for day to day operations.
iv. As per Regulation 1.6.6 of the State Commission's Grid Code, the SLDC is
obligated not to unduly discriminate or prefer amongst any stakeholders.
However, in the present case, SLDC in the guise of carrying out its
responsibility of optimum scheduling and dispatch of electricity has issued the
impugned communications fixing the Technical Minimum of the Appellant's
Power Plant to the contracted capacity with the Respondent No. 3.
v. The running of Project below technical minimum has led to severe expenditure
on account of secondary fuel consumption and other related costs which has
not been compensated to the Appellant.
vi. Further, for any offer of power on Exchange the Appellant cannot take
recourse to FSA Coal (obtained under Coal India's linkage policy) and is
necessarily compelled to procure Coal from open market, which substantially
increases the cost of generation. This makes the offer uncompetitive. If the
procurer had followed the due procedure stipulated under the PPA then this
situation could have been avoided and an equitable opportunity would have
been given to the Appellant to ensure that its generation is suitably tied up.
vii. As an accepted practice if there is any difference between the scheduling of
the Procurer and the generators availability, the RLDC/SLDC refuse scheduling
and direct the parties to come at a settlement and such RLDC/SLDC under no
circumstance impose the requisition of the procurer upon the generator.
Reference has been made to the communication of WRLDC dated 03.06.2015
wherein it was stated “that WRLDC schedules contracts which are mutually
agreed. In case of disagreement, it is not a contract and hence from now
onwards such disputed requisitions shall be scheduled as zero.”
viii. The action of SLDC to ensure that the requisition of procurer i.e. Respondent
No. 3 is implemented at any cost without considering the technical minimum
limitations of the Appellant is also contrary to the mandate of Section 32 of
the Act.
f) The Act mandates “Optimum Scheduling and Dispatch”
i. The Act or the Regulation in no manner indicates that the SLDC shall act only
to promote procurement by state utilities without considering the technical
capabilities of the Appellant's generating plant. If the intent of the legislature
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 12 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
was to limit the operation of SLDC to the contract entered into between the
procurer and the generator, then the legislature would not have used the word
‘optimum’ in Section 32 of the Act. The sole purpose of incorporating the word
‘optimum’ in Section 32 is to entrust the responsibility upon SLDC to balance
the interest of both the procurer as well as the generator, which the said
Respondent SLDC has failed to do in the present case.
ii. The Respondent No. 3 procures 70% of the power generated from the
Appellant's plant, which is a substantial portion of the entire generation by the
Appellant. Further, in such circumstances, wherein the Respondent No. 3 has
tied up PPA's for more than its actual demand, the Respondent SLDC is
obligated to ensure that the electrical system (which includes the generator)
of the state operates in the most efficient and economical manner. In such a
situation, greater regulatory responsibility, judiciousness and ownership is
required to be exercised by the Respondents, in ensuring that the Appellant's
Power Plant is not operated below its Technical Minimum ability especially
since the Appellant is the only generator with 70% tied up capacity with the
State Procurer.
g) Any off take/scheduling below the contracted capacity has to be done
strictly in accordance with the Terms and Conditions of the PPA.
i. Any off take/scheduling below the contracted capacity can only be made if two
conditions are satisfied i.e.
a) Firstly, a due Notice under Article 4.3.5 is to be issued by the Procurer to
the Generator for the lower quantum specifying the period for which such a
supply would be taken, and
b) Secondly, when the said Quantum is either above ‘Technical Minimum’ of
the Unit Capacity or Zero in cases of RSD as enumerated in the 4th
Amendment of the IEGC.
ii. In the present case, the requirement of Article 4.3.5 of the PPA has admittedly
not been fulfilled till date. Therefore, by virtue of Section 54 of the Contract
Act, 1872, the Respondent No. 3 is in breach of the PPA signed between the
Appellant and the Respondent No. 3.
Section 54 of the Contract Act is reproduced below:—
“When a contract consists of reciprocal promises, such that one of them
cannot be performed, or that its performance cannot be claimed till the
other has been performed, and the promisor of the promise last mentioned
fails to perform it, such promisor cannot claim the performance of the
reciprocal promise, and must make compensation to the other party to the
contract for any loss which such other party may sustain by the non-
performance of the contract.”
Therefore, in terms of the above quoted Section 54 of the Contract act,
1872 since the Respondent No. 3 has not followed the procedure as
prescribed under Clause 4.3.5 the said Respondent cannot claim equity in
its favor. Moreover, the financial hardship caused to the Appellant will have
to be appropriately compensated.
iii. Further, in terms of the PPA the exact period of shortfall in off take of power is
to be informed to the Appellant as the words “for a period specified in such
notice” mentioned in Article 4.3.5 of the PPA.
iv. The Article 4.3.4 of the PPA dated 5th January 2011, provides for sharing of
“sales realization in excess of Energy Charges”. It is an agreed and accepted
position that a share in profit is equally applicable to share in loss. Therefore,
the claim of the Appellant must be considered on account of losses incurred in
this additional light.
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 13 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
of MP is issued the same shall be limited to 60%/70% (as the case may be) of
the contracted ex-bus capacity of MP.”
d) The Appellant approached the State Commission under incorrect provisions of
the Act. The Appellant filed Petition 54 of 2015 under Section 86(1)(f), (h) and
(k) of the Act, 2003. Clause (1) of Section 86 provides that the State
Commission shall adjudicate upon the disputes between the licensees and
generating companies whereas, in Petition no. 54 of 2015, the Appellant
challenged the legality, validity and proprietary of the directions issued by
Respondent SLDC which is not the licensee. Secondly the other Sections invoked
by the Appellant, 86(1)(h) and (k) pertain to the general functions of the State
Commission relating to specifying M.P. Electricity Grid Code and discharge such
other functions as may be assigned to the State Commission under the Act.
e) The Appellant has relied heavily upon the Draft CERC (Indian Electricity Grid
Code) (Fourth Amendment) Regulations, 2015 to show ‘technical minimum
schedule for Operation and Generating Stations’, however these Regulations are
meant for Inter State Generating Stations (ISGS) whereas, the Appellant's power
plant is not ISGS as per the provisions of M.P. Electricity Balancing and
Settlement Code and M.P. Electricity Grid Code and therefore cannot rely upon
the aforementioned Regulations.
f) The State Commission in its Impugned Order has observed that the use of the
term “Technical Minimum” by SLDC/Respondent No. 4 and M.P. Power
Management Company/Respondent No. 3 had no relevance since the provisions
of the PPA executed between the Appellant and Respondent No. 3 are explicitly
clear with regards to the commercial and technical obligation to be met by each
of them. The State Commission vide Impugned Order has rejected the
Appellant's prayers for compensation in light of the PPA executed between the
Appellant and Respondent No. 3. Therefore, there is no question for grant of
compensation for distress sale and excess oil usage due to lowered generation.
g) The Appellant has challenged the Impugned Order on the following grounds:
(i) The State Commission has failed to address the issue of ‘Technical Minimum’
as an industry practice. The State Commission has erred in relying upon the
PPA and the MPERC Grid Code;
(ii) The State Commission has erred by not accounting for the damage caused to
the Appellant's unit due to frequent changes in load. The State Commission
has erred by not directing Respondent No. 3 to compensate the Appellant for
the distress sale of its' power on lEX and increased use of oil due to
lower/inefficient generation;
(iii) The State Commission has misinterpreted the provisions of the PPA that
Respondent No. 3 is only obligated to pay capacity charge for unrequisitioned
capacity. Such a narrow and pedantic interpretation will result in inefficient
generation which could not have been the intent behind the PPA, the Act and
the Regulations framed therein;
(iv) The State Commission has failed to appreciate that the MOD prepared by
Respondent No. 3 is incorrect and is in violation of Regulation 5(3) of the
Madhya Pradesh Balancing and Settlement Code, 2015.
(v) The State Commission has failed to realize that the Respondent No. 4 has
erroneously acted in contravention of Section 32 of the Act by directing the
Appellant to schedule below 140 MW is the ‘Technical Minimum’ of the
Appellant's generating unit;
h) The State Commission had correctly rejected the Appellant's prayer for setting
aside the impugned letter dated 01.06.2015 issued by Respondent no. 4 and
disallowing recovery of any additional cost incurred by the Appellant in operating
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 16 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
of the plant on account of the directions issued by Respondent no. 2. The State
Commission has refrained from allowing recovering of additional cost in light of
the provisions of the PPA, executed between the Appellant and Respondent no.
3. The terms of the PPA are explicitly clear and the Appellant is adequately
compensated by Respondent no. 3 under the PPA for any unscheduled/unavailed
contracted capacity.
i) The State Commission has passed the Impugned Order on examination of the
following two issues while considering Petition 54 of 2015 filed by the
Appellant:
i. Whether the instructions of backing down of power issued by Respondent
no. 4 to the Appellant on the basis of contract capacity with Respondent
No. 3 are incorrect and bad in law?
ii. Whether the Appellant can be allowed to recover additional cost incurred by
it while operating the power plant, as per the directions of Respondent no.
3, communicated to it by Respondent no. 4?
The State Commissions finding on these two issues are as follows:
Issue No. (i): Whether the instructions of backing down power issued by
Respondent no. 4 to the Appellant on the basis of contract capacity with
Respondent No. 3 are incorrect and bad in law?
a) The scheduling instructions issued by SLDC/Respondent no 4 to the Appellant
on the basis of contract capacity with Respondent No. 3 are correct and good
in law.
b) The Appellant has argued that the scheduling instructions issued by
Respondent no. 4/SLDC required the Appellant to operate its power plant
below its technical minimum capacity and thus the same are in violation of
the Prudent Utility Practices since the instructions require the plant to operate
at a level which is highly inefficient and uneconomical. However these
averments made by the Appellant are untenable in view of the PPA, MPERC
Grid Code.
c) The Appellant and the Respondent No. 3 have executed PPAs for supply of
70% (inclusive of 5% of net generated power at variable cost) of the installed
capacity of Appellant's 2 × 250 MW (Phase 1), i.e. 350 MW for a period of 25
years at a tariff to be approved by the State Commission. The PPA between
the Appellant and Respondent No. 3 is explicitly clear and has the necessary
provisions for commercial and technical obligations/arrangements that have to
be met by each party to the contract. It is stated that the PPA does not
provide for any kind of minimum generation to be compulsorily maintained by
the Appellant. The Appellant is entitled to sell any unscheduled Available
Capacity to an entity other than the Respondent No. 3/procurer on one hand
and also entitled to recover the Fixed (capacity) charges corresponding to
such unscheduled Available Capacity from the procurer on the other hand. The
same has also been acknowledged by the Appellant as being an enabling
provision.
d) Under the PPA, no restrictions have been imposed on the Respondent no. 3, to
limit the quantum of ‘Available Capacity’ to be scheduled by it between zero
and the full contracted capacity declared available by the Appellant. Article
4.3.3, 4.3.4, 4.3.5 of the PPA dealing with ‘Available Capacity’ provides that
Respondent No 3 may, at any time and without assigning any reason request
the Appellant to schedule whole or part of contracted/available capacity.
However, the PPA provides for the Appellant to be compensated by way of
fixed cost to be paid by Respondent No. 3, in terms of PPA, in the event the
Respondent No. 3 off takes less than the contracted capacity. It is reiterated
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 17 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
its non-contracted capacity through Short Term Open Access for sale of
additional power. The Appellant has been selling the 30% on a merchant basis
in the past and may continue doing so in the future. This will ensure that the
Appellant is able to maintain the generation of both the units at the desired
levels without inflating the ARRs of the state distribution licensees by forcing
them to off-take expensive surplus power from its generating units.
b) The Appellant has also prayed that it be allowed to maintain a generation of
140 MW per unit as an otherwise lowered generation will damage the plant's
equipment. Article 7.1.1 of the PPA which deals with efficient and economical
operation of the power station provides that the Appellant is made responsible
at its own expenses to ensuring the operation of power station in an efficient,
coordinated and economical manner so as to meet its obligation under the PPA
and also to avoid any adverse effect on the grid operation. Therefore, any
financial impact suffered by the Appellant due to alleged damage to the
generation plant which in turn is caused by lowered generation is to be
absorbed by the Appellant. The PPA envisages such aforementioned costs (if
at all incurred) to be the Appellant's responsibility even if caused by lowered
generation as long as the levels of generation have been maintained so as to
not adversely affect the grid operations.
c) As per Article 7.1.1 in PPA it is clear that the Appellant may not seek
scheduling of power at ‘Technical Minimum’ nor can they seek any
compensation for lowered generation under the lEGC 2016. It is once again
reiterated that the lEGC 2016 is applicable to ISGS units and CGS where
many constituents are having share as per their allocation and responsible for
submission of requisition up to 55% of their share. The Appellant's 2 × 250
MW generating plant has only one beneficiary-Respondent No. 3 for 70% and
the 30% remains with the Appellant as mercantile capacity. Further, the lEGC
clearly states that for entities not regulated by the CERC, compensation may
be sought at the end of the year only if such provision is included in the PPA.
Clearly, the Appellant cannot seek compensation for increased oil usage due to
lowered generation and distress sale on lEX as the PPA for sale of power does
not provide for compensations for operating at the technical minimum
schedule (as understood under the IEGC 2016 for ISGC and CGS).
j) In view of the afore-mentioned, the State Commission has correctly
passed the Impugned Order while dismissing Petition no. 54 of 2015.
10. The learned counsel for the Respondent No 3, MPPMCL has made following
submissions on the various issues raised in the Appeal for our consideration:—
a) The Appellant's contention is that the Respondent No 3 should be responsible for
maintaining technical minimum of the installed capacity of the Unit instead of
limiting the same to the contracted capacity agreed between the Appellant and
the Respondent No 3.
b) POWER PURCHASE AGREEMENT (“PPA”):
i. The contracted capacity in the PPA dated 05.01.2011 is not for the full installed
capacity of the Appellant's power plant. The contracted capacity is 70% of the
installed capacity.
ii. As per the PPA, there is no obligation for the Respondent No 3 to schedule any
minimum capacity of power and there is no provision of technical minimum
limits.
iii. The Appellant is made responsible at its own expenses to ensure the
operation of power station in an efficient, coordinated and economical manner
so as to meet its obligation under the PPA and also to avoid any adverse effect
on the grid operation.
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 19 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
charges are payable in terms of the PPA. The Merit Order is prepared on a
monthly basis keeping in view the variable cost and is provided to all the
stakeholders including SLDC on a regular basis.
v. The State Commission, to the knowledge of the Respondent No. 3, has never
observed that Merit Order Dispatch is being prepared on unacceptable
principles. Even otherwise, if Merit Order Dispatch is prepared taking in to
consideration the capacity charges along with variable charges in one case and
only variable charges in the other, then too, in both cases the Appellant's
generating station finds place at the highest levels, i.e. to say that, the
Appellant's generating station delivers costliest power in both the cases.
vi. The Appellant's submission that Merit Order is wrong as the Merit Order is
prepared based on variable charges at common point i.e. Madhya Pradesh
periphery for all the generators supplying power to Madhya Pradesh as some
plants are within the State and some are outside. In the most impartial
manner, the total variable costs are brought out at a common platform for
comparison and as such equal treatment is given to all. This procedure has
throughout been in the knowledge of the Appellant and from time to time, all
the stake holders have been apprised of this information.
vii. The Respondent No. 3 further submits that the issue of merit order is
between the Respondent No. 3, the consumers at large and for the State
Commission to decide. The merit order is decided on consideration of various
factors including the meeting of sustained load demands in the State of
Madhya Pradesh. The Appellant cannot compel the Respondent No. 3 to
schedule power, so long the Appellant is being paid the fixed charges in terms
of the applicable regulations of the State Commission and in accordance with
the PPA entered into between the parties.
viii. The allegation made by the Appellant on the aspect of merit order proceeds
on a fundamentally wrong assumption that the generating units of the State
Generating Companies are always being run in an inefficient manner and that
the Appellant's units are being run in an efficient manner. Many of the State
Generating Units are old. The Appellant ought to be in a position to compete
in an efficient manner to produce electricity at which cheaper cost of
generation as compared to the cost of generation of the old generating units,
despite paying cess of 15 Paise per unit. The cess of 15 Paise per unit is a cost
of generation. Ultimately, the Respondent No. 3 is concerned with the total
procurement cost i.e. variable cost, fixed cost need to be paid in any case. The
total variable cost would include Electricity Duty and Cess payable on the
units of electricity generated. These cannot be excluded for the purpose of
comparison.
ix. There is absolutely no rational for the Respondent No. 3 to procure costly
power by considering all the cost factors, when cheaper power is available.
Accordingly, if the imposition of 15 Paise Cess on the power generated by the
Appellant increases the cost of the power procurement of the Appellant as
compared to other generating stations, the Respondent No. 3 is duty bound to
purchase the power from other generating stations and thereby reduce the
financial impact on the consumers at large.
x. In the context of the above, the Regulation notified by the State Commission
on merit order need to be decided with the object and purpose to be achieved.
It is, therefore, wrong on the part of the Appellant to contend that additional
cost item such as Electricity Duty, Cess etc. should not be considered while
determining the merit order. There is absolutely no warrant for such
allegations being made.
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 21 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
“5.7.1(b)- The ABT regime introduced by CERC at the national level has
had a positive impact. It has also enabled a credible settlement mechanism
for intra-day power transfers from licenses with surpluses to licenses
experiencing deficits. SERCs are advised to introduce the ABT regime at the
State level within one year.
5.7.1(d)- Development of power market would need to be undertaken by
the Appropriate Commission in consultation with all concerned.
National Tariff Policy
6.2 Tariff structuring and associated issues
(1) A two-part tariff structure should be adopted for all long term
contracts to facilitate Merit Order dispatch. According to National Electricity
Policy, the Availability Based Tariff (ABT) is to be introduced at State level
by April 2006. This framework would be extended to generating stations
(including grid connected captive plants of capacities as determined by the
SERC). The Appropriate Commission may also introduce differential rates of
fixed charges for peak and off peak hours for better management of load.
Hence the above provisions of National Electricity Policy and National
Tariff Policy identify the need of establishing a framework for implementing
Merit Order Despatch which itself is based on principle of efficient and
economical despatch.
iii. As per Section 5.3 of the BSC 2009, the principle of Merit Order Despatch has
been identified by the State Commission.
“General Principles: Scheduling
5.3 Merit Order Operation: Discoms, will give their requisitions based
on their individual Merit Order i.e. in ascending order of cost of energy (i.e.
variable cost) of ISGS, SSGS, Bilateral and Collective transactions allocated
to individual Discom.”
iv. As per the learned Counsel of the State Commission, the Appellant had not
sought any relief regarding ‘Merit Order Despatch’ in its petition filed before
the State Commission. Secondly, the question raised by the Appellant
regarding preparation of MOD had been adequately replied/addressed by
Respondent No. 3 during the course of proceedings and as recorded in the
Impugned Order.
v. Regarding the issue of “Technical Minimum”, the State Commission in the Para
13 of the Impugned Order stated that the term/expression i.e, “Technical
Minimum” for thermal power plant is not mentioned in any provision of the
Power Purchase Agreement executed between the parties in the matter or M.P.
Electricity Grid Code or Balancing and Settlement Code notified by this
Commission. Moreover, Clause 6.3(b) for Technical Minimum Schedule for
“Operation of Generating Stations” in CERC's draft notification is for Inter
State Generating Stations (ISGS) whereas, the petitioner's power plant in the
subject matter is not ISGS as defined in M.P. Electricity Balancing and
Settlement Code and M.P. Electricity Grid Code. In the Para 16, State
Commission observed that the use of expression like Technical Minimum by
the respondents in the impugned communication has no relevance since the
provisions under the PPA executed between the procurer and the petitioner
are explicitly clear for commercial and technical obligation to be met by each
of them. Besides, the Appellant is responsible at its own expenses for
maintaining the technical requirement during operation of the plant while
making its obligations under the power purchase agreement. As the Appellant
in its petition before the State Commission has not specifically sought the
level of Technical Minimum to be identified by the State Commission and only
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 26 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
contended that the Technical Minimum to be considered for the Unit and not
for the contracted capacity for scheduling purposes, we do find that the State
Commission has discharged its role in ensuring efficient and economic
operation of electrical system in the State.
vi. Hence this issue is also decided against the Appellant.
c) On Question No. 3 i.e. Whether the State Commission in passing the
Impugned Order has failed to address the larger issue of efficiency of the
operation of Appellant's Power Plants by pedantically interpreting the
PPA signed between the Appellant and the Respondent No. 3? and
Issue No 12 i.e. Whether the State Commission in passing the
Impugned Order has wrongly relied upon Article 4.3.5 of the PPA to
hold that the Respondent No. 3 procurer can requisition any capacity
from the generator without considering the fact that Article 4.3.5 is
not the objective behind the Agreement as ultimately the Agreement
was entered for the purpose of setting up a power plant to supply 70%
power? Whether Article 4.3.5 of the Agreement is only an exceptional
provision which comes into play in exceptional scenarios and cannot
be used to regulate the manner in which supply of power will be
effected between parties?
i. Under Section 32 of the Electricity Act, 2003, it is provided that the State Load
Despatch Centre shall be responsible for optimum scheduling and dispatch of
electricity within the State, in accordance with the contracts entered into with
the licensees and the generating companies operating in that State.
ii. The relevant provisions of the PPA dated 05.01.2011 entered between the
procurer i.e. M.P. Power Trading Company Ltd. (now M.P. Power Management
Co. Ltd.), Jabalpur and the Appellant are as under:
“1. Definitions
“Available Capacity” shall mean such the contracted capacity declared available
by the Company in accordance with the ABT;
“Contracted Capacity” shall mean the capacity equivalent to 65% of the Phase
I (2 × 250 MW) and 37% of the Phase II (3 × 250MW) (subject to availability of
coal for Phase II 3 × 250 MW) of Power Station's Installed Capacity contracted with
the Procurer as terms of this Agreement.
……………………………………
……………………………………
……………………………………
4.3 Right to Contracted Capacity and Scheduled Energy
4.3.3 If the Procurer does not schedule the whole or part of the Available
Capacity for any reason whatsoever, the Company shall be entitled to make
available such Available Capacity not scheduled by the Procurer, to any other
person without losing the right to receive the Capacity Charges from the Procurer
for such unscheduled Available Capacity. During this period, this Company will
continue to receive the Capacity Charges from the Procurer. For any such third party
sale, all open access charges including losses, as may be applicable, shall not be
payable by the Procurer. The Company shall maintain accounts and provide all
details regarding price of sale etc. to the Procurer in respect of such sales under this
Article.
4.3.4 In the cases referred in Article 4.3.3, the sale realization in excess of
Energy Charges shall be equally shared by the Company and the Procurer. In the
event, the Company makes available such Available Capacity to any direct or
indirect Affiliate of the Company/shareholders of the Company without obtaining
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 27 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
the prior written consent of the Procurer, the Company shall be liable to make
available such Available Capacity to such entity at a tariff being not less than the
Tariff.
4.3.5 Where the sale under Article 4.3.3 by the Company is consequent to a
notice issued by the Procurer to the Company indicating its unwillingness to
schedule the whole or part of the Available Capacity for a period specified in such
notice, the Procurer shall be entitled to request the Company for the resumption of
availability of the Available Capacity at any time, however, the Company shall not
be liable to resume such availability earlier than the period specified in the said
notice, and subject to the provisions regarding scheduling as per the Grid Code.
……………………………………
……………………………………
……………………………………
7.1.1 The Company shall be responsible at its own expense for ensuring that the
Power Station is ‘operated and maintained in an efficient, coordinated and
economical manner and in accordance with all legal requirements, including the
terms of all Consents, Clearances and Permits, Prudent Utility Practices, and in
particular, the Grid Code, so as to meet its obligations under this Agreement and so
as not to have an adverse effect on the Grid operation.”
iii. The State Commission while issuing the Impugned Order has considered the
above provisions of PPA. The State Commission has observed that the
Respondent No. 3 is responsible only up to the contracted capacity of the
generating unit as per PPA. Any unscheduled available capacity within the
contracted capacity is compensated by way of fixed cost/capacity charges paid
by the Respondent No. 3 to the Appellant in terms of PPA.
iv. Hence we do not find any merit on the issue raised by Appellant on the failure
of State Commission in addressing the issue of efficiency of the operation of
Appellant's Power Plant.
v. Hence both the above issues are decided against the Appellant.
d) On the Question No. 4 i.e. Whether the State Commission in passing the
Impugned Order has failed to appreciate that the Statutory PPA was not
signed with the intent that the Appellant would only receive the Capacity
Charges without actually generating power leading to inefficiency in the
operations of the Appellant? Whether the objective behind the PPA is that
the Appellant would generate power in an efficient manner and the
Respondent No. 3 will off take such generated power on payment of the
regulated Tariff? Whether the present Impugned Order has not
considered the above and the State Commission has also failed to
appreciate that inefficient generation cannot be the intent behind the
Agreement or the Act and the Regulations framed thereunder?
i. The PPA was signed by the Parties for supply of power for 25 years. From the
various provisions of the signed PPA, it is evident that intent of PPA was to pay
Capacity Charges to the Appellant even without scheduling of power for the
contracted capacity from the Appellants plant. Considering the dynamic
requirement of power demand/surpluses, it seems that the provision
regarding right to contracted capacity and scheduled energy was incorporated
in the PPA under Para 4.3. The provisions of PPA under this section deals with
the option of providing such Available Capacity not scheduled by the Procurer,
to any other person without losing the right to receive the Capacity Charges
from the Procurer for such unscheduled Available Capacity. The State
Commission while issuing the Impugned Order has considered the various
provisions of the PPA including provisions of Para 4.3.
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 28 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
ii. The PPA was signed between the Parties for supply of 70% (inclusive of 5% of
net generated power at variable cost) of the installed capacity of Petitioner's 2
× 250 MW (Phase I) of the power station for a period of 25 years at the Tariff
to be approved by the Commission.
iii. The Tariff of the Appellant Power Plant is being determined by the State
Commission in accordance with the Tariff Petition filed by the Appellant as per
Generation Tariff Regulations issued by the State Commission. The Generation
Tariff Regulations are issued by the State Commission for a specific Tariff
Period after considering dynamics of the power market, promoting efficiency,
balancing the interest of Consumers as well as Generators and consultation
with the Stakeholders. The State Commission issues the Tariff orders after
scrutiny of the petition and consultation with the Stakeholders and proper due
diligence.
iv. The issue of efficiency of power generation from the Appellants Power Plant
was not at all the matter raised by the Appellant before the State
Commission. The Appellant had raised its claim before the State Commission
to allow the recovery of any additional cost incurred in operating in accordance
with the directions issued by the Respondent No 2 herein.
v. In view of above, we are not inclined to accept the allegations on the issue as
raised by the Appellant.
vi. Hence this issue is decided against the Appellant.
e) On the Issue raised in Question No 5, 6, 7, 8, 15, 16, 19, 20 & 22 related
to Technical Minimum, we observe as follows:
i. The term ‘Technical Minimum’ is provided in the Indian Electricity Grid
Code (IEGC) notified by the Central Commission in exercise of its powers
under Section 79(1)(h) of the Electricity Act, 2003. Clause 6.3(B) of the IEGC
provides on the aspect of Technical Minimum as under:
“6.3B-Technical Minimum Schedule for operation of Central
Generating Stations and Inter-State Generating Stations
1. The technical minimum for operation in respect of a unit or units of a Central
Generating Station of Inter-State Generating Station shall be 55% of MCR
loading or installed capacity of the unit of a generating station.
2. The CGS or ISGS may be directed by concerned RLDC to operate its unit(s) at
or above the technical minimum but below the normative plant availability
factor on account of grid security or due to the fewer schedules given by the
beneficiaries.
……………………………………
……………………………………
……………………………………
“4. In case of a generating station whose tariff is neither determined nor
adopted by the Commission, the concerned generating company shall have
to factor the above provisions in the PPAs entered into by it for sale of
power in order to claim compensations for operating at the technical
minimum schedule”
ii. As per the IEGC itself, the Technical Minimum in the case of entities other
than the Central Sector Generating Units and Inter State Generating Stations
have to be in accordance with the PPA entered into between the parties.
iii. By the time the Impugned Order was passed by State Commission, the
amendment had not become effective. The amendment is still not given effect
to pending the detailed procedure to be notified by the National Load Dispatch
Centre. In view of the above, the Respondents are right in their contention
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 29 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
Regulation of the MPERC or the PPA signed between the Appellant and
the Respondent No. 3?, our views are as follows;
i. In the Impugned Order the State Commission has made reference to the
various provisions of the PPA and observed that the Procurer (Respondent No.
3) may not schedule the whole or part of the Available Capacity for any reason
and in such case Appellant can make available such unscheduled Available
Capacity to any third party. The Respondent No 3 shall continue to pay the
capacity charges to the Appellant for such unscheduled Available Capacity
“Para 15(iii): There is no direct provision regarding “Technical Minimum” in
the above PPA. On combined perusal of Clause 4.3.3, 4.3.4, 4.3.5 and 7.1.1, it
is clear that the Procurer (Respondent No. 2) may not schedule the whole or
part of the Available Capacity for any reason whatsoever, and in such
situation, the petitioner is entitled to make available the unscheduled
Available Capacity to any party other than the procurer without losing the
right to receive the capacity charges from the procurer for such unscheduled
Available Capacity.”
In our view, State Commission has rightly observed that the provisions
of the PPA do not contain any mandate on Respondent No 3 to schedule a
specific quantum of electricity and Respondent No 3 has every right to
schedule the power from Appellant's power plant based on its requirement
and not limiting to 140 MW of technical minimum quantity as specified by
the Appellant.
ii. Further, the State Commission in its Impugned Order at Para 15(viii) has
recorded its observation on the information submitted by the parties regarding
scheduling of Appellant's Power Station at around 140 MW. The Para 15(viii) is
reproduced as below: “Para 15(viii): It is also mentioned in the submissions
filed by the parties in this matter that the procurer (Respondent No. 2) has
been scheduling 140 MW power most of the time in the past. However, the
petitioner had arranged sale of balance power falling short of 140 MW through
collective transactions to ensure the technical minimum quantum of ex-bus
capacity.”
iii. In our view, the commercial and technical obligations to be met by the
Appellant as well as the Respondent No. 3 are explicitly clear in the PPA and
they are safeguarding the interests of the Appellant and providing the
Appellant to make available the unscheduled capacity of the Respondent No. 3
to any party other than the procurer without losing the right to receive the
capacity charges from the Respondent No. 3 for such unscheduled capacity.
iii. Hence this issue is decided against the Appellant.
k) On Question No. 21 i.e. Whether the State Commission in passing the
Impugned Order has failed to appreciate that the Appellant's Power
Project has been established for the specific purpose of ensuring supply
of power to the State of Madhya Pradesh and therefore higher regulatory
accountability is required to be exercised by other State Players to ensure
that no undue financial and technical prejudice is caused to the
Appellant?, our views are as follows;
i. The Appellant's Power Plant has the Power purchase Agreement with the
Respondent No 3 for supply of 70% (inclusive of 5% of net generated power
at variable cost) of the installed capacity of Appellant's Power Station 2 × 250
MW (Phase I) for a period of 25 years at the rate to be approved by the State
Commission.
ii. The Tariff for Appellant's Power Plant is being determined by the State
Commission in line with the Generation Tariff Regulations issued by the State
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 35 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------