GEMINI ENGI-FAB LIMITED

INTERNAL INSPECTION REPORT Date :


Stage of Inspection / Tests Job No. :11529A/HE
A : Material B : Interim C : Re-Inspection D : Final
Client : Indian Oil Corporation Limited ProjectQty
Equpt. : IOCL-Lupech
: 01 No. Inspection Agency :
Equipment Name : REGENERATOR REBOILER vcs
P.O. NO. & Date: 77154/109/27621024 DT: 02.03.2022
ITP NO. & Date: 077154C-000-SR-0610-001B-B1002-0004
Drawing No. : 077154-000-SR-0610-001B-A2001-0007, Rev:01 EQPT. No. : 1814-E-002A
NOZZLE SETUP ON MAIN SHELL
Sr. Nozzle Nozzle SCH. Orientation Elevation Projection
Rating/Type Remark
No. No. Size THK Reqd. Actual Reqd. Actual Reqd. Actual
SCH 1250 mm from sliding 1250 mm from 1470 mm from centre
1 N3 10" 300# WNRF At 180˚ At 180˚ 1473
100 saddle sliding saddle line

SCH 2100 mm from fixed 2100 mm from fixed 1470 mm from centre
2 N4 10" 300# WNRF At 180˚ At 180˚ 1475
100 saddle saddle line

SCH 1470 mm from centre


3 N5 12" 300# WNRF At 0˚ At 0˚ 6450 mm from T.L 6450 mm from T.L 1473
100 line

SCH 1470 mm from centre


4 N6 12" 300# WNRF At 0˚ At 0˚ 2950 mm from T.L 2950 mm from T.L 1475
100 line

All dimension are in 'mm' unless otherwise specified.

Visual Inspection is carried out and found satisfactory.

Measuring instruments:- 1) measuring tape: MT-04, Due date:01.02.2024.(5 Meter)


2) measuring tape: MT-02, Due date:01.02.2024.(30 meter)

For Gemini Engi-Fab Limited For VCS


Name : Name :

Signature : Signature :
GEMINI ENGI-FAB LIMITED
INTERNAL INSPECTION REPORT Date :
Stage of Inspection / Tests Job No. :11529B/HE
A : Material B : Interim C : Re-Inspection D : Final
Client : Indian Oil Corporation Limited ProjectQty
Equpt. : IOCL-Lupech
: 01 No. Inspection Agency :
Equipment Name : REGENERATOR REBOILER vcs
P.O. NO. & Date: 77154/109/27621024 DT: 02.03.2022
ITP NO. & Date: 077154C-000-SR-0610-001B-B1002-0004
Drawing No. : 077154-000-SR-0610-001B-A2001-0007, Rev:01 EQPT. No. : 1814-E-002A
NOZZLE SETUP ON MAIN SHELL
Sr. Nozzle Nozzle SCH. Orientation Elevation Projection
Rating/Type Remark
No. No. Size THK Reqd. Actual Reqd. Actual Reqd. Actual
SCH 1250 mm from sliding 1250 mm from 1470 mm from centre
1 N3 10" 300# WNRF At 180˚ At 180˚ 1473
100 saddle sliding saddle line

SCH 2100 mm from fixed 2100 mm from fixed 1470 mm from centre
2 N4 10" 300# WNRF At 180˚ At 180˚ 1474
100 saddle saddle line

SCH 1470 mm from centre


3 N5 12" 300# WNRF At 0˚ At 0˚ 6450 mm from T.L 6450 mm from T.L 1473
100 line

SCH 1470 mm from centre


4 N6 12" 300# WNRF At 0˚ At 0˚ 2950 mm from T.L 2950 mm from T.L 1471
100 line

All dimension are in 'mm' unless otherwise specified.


Visual Inspection is carried out and found satisfactory.
Measuring instruments:- 1) measuring tape: MT-04, Due date:01.02.2024.(5 Meter)
2) measuring tape: MT-02, Due date:01.02.2024.(30 meter)

For Gemini Engi-Fab Limited For VCS


Name : Name :

Signature : Signature :