FAT Procedure of PLC Panel
FAT Procedure of PLC Panel
OJSTCMER:
CONSULTANT:
PRO..ECT:
PME CON1RAC1llt:
COLLABORATCR
JOB NO.
STATUS
· -
---
FAT Procedure of PLC Panel
-
FAT
LIENT:
PROJECT :
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
CONTENTS
Introduction General
FAT Schedule
FUNCTIONING
BOARDS
3 .1 FUNCTIONAL TEST OF
RELAYS
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
FAT
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
The purpose of this test is to review the documents on the basis of which the inspection is
conducted.. PROCEDURE
Check that the ‘Construction’ drawings have been established on the basis of the approved
drawings
transmitted at the time of inspection call.
Check that the modifications carried by the ‘Construction’ drawings are marked in blue pen and dated
and signed by the engineer-in- charge.
Check that the modifications carried in the drawings do not affect the design.
CRITERIA
The ‘construction’ documents show the same revision number that the documents submitted at the
inspection call.
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
The purpose of this test is to insure the safety of the personnel while handling the panel, and safety of
the installed equipment from any electrical hazards/ short – circuits.
PROCEDURE
Check that the 0V inside the panel is connected to the earth bar.
Check that the panel chassis is connected to the earth bar (multi-meter)
CRITERIA
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE All hardware components for which test certificates exist are subjected to complete
testing before being staged for inspection.
OBJECTIVE The purpose of this test is to verify test certificates for the following items exist :
1. Input/ Output modules
2. I/O Rack
3. PLC processor system
4. Communication modules
REFERENCE
1. PLC system configuration as per approved drawing.
2. Bill of material as per approved drawing
PROCEDURE
1. Check that the tests certificates are available for above items
CRITERIA
1. Certificate of conformity with serial nos. for PLC modules are available.
2. Certificate of conformity of operation of PLC
modules
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
All protection devices show a rated capacity in conformity with the design.
OBJECTIVE
The purpose of this test is to verify proper protection as per design.
1. MCBs
2. Fuses
REFERENCE
1. Panel internal wiring diagram
2. Product data sheet
PROCEDURE
1. Compare the rated capacity of each protection device in the product data sheet and the rating
indicated in the panel internal wiring diagram as per approved drawings
CRITERIA
1. Exact match with the rating indicated in the panel internal wiring diagram
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
To Verify System Architecture.
OBJECTIVE
The purpose of this test is to verify that :
one. REFERENCE
PROCEDURE
2. Visually check that processors & I/O’s are connected on EHTERNET Bus as per approved
system architecture
3. Visually check the availability of the Ethernet port for connection to Ethernet network, being
used for Programming & SCADA..
CRITERIA
The quantity, location & physical connectivity of these items are in accordance with the approved
system architecture.
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
All I/O modules and communication modules are assigned during detailed engineering, and
quantity/position of each item installed in the PLC panel are of utmost importance.
OBJECTIVE
The purpose of this test is to verify quantity, mounting & location of :
1. Input/ Output modules
2. I/O Rack
3. Rack Power supply
4. PLC processor system
5. Communication modules
REFERENCE
1. Approved PLC system configuration drawing no.
2. PLC panel general arrangement drawing no.
3. Internal wiring diagram and IO interconnection
drawings. PROCEDURE
1. Check the rack power supply input voltage rating,
2. Visually check that each I/O base is correct in quantity and installed in the correct position
3. Visually check that all labeling is in
order CRITERIA
The quantity and location of the I/O bases are in accordance with the system configuration.
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
The power supplies incoming to the panel and generated inside the panel are conforming to the
design.
OBJECTIVE
The purpose of this test is to ensure that the control panel is powered in normal conditions and the
control panel delivers interrogation voltage in conformity with the design.
REFERENCE
1. Internal wiring diagram
2. Power supply data sheet
PROCEDURE
1. Measure the voltage of incoming power supplies.
2. Measure the voltage of power supplies generated inside the panel as per approved data
sheet and approved wiring diagram no
CRITERIA
1. The incoming voltage is matching the value indicated in the internal wiring diagram with a
tolerance of +/- 10%
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
COMMENTS
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
PLC goes to normal operation on powering up, provided that all application software are stored in
respective PLC’s.
OBJECTIVE
The purpose of this test is to ensure that PLC automatically boots up from Power off to operation .
PROCEDURE
1. Power on the entire system
2. Power off the PLC
3. Power on the PLC again
CRITERIA
The PLC goes to Run mode
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OBJECTIVE
To check Input wiring.
REFERENCE
Approved Panel Internal wiring diagram
PROCEDURE
1. Connect jumper to digital input field termination block as per wiring drawings to toggle
field input.
2. Observe LED indication on PLC Input modules.
3. Observe corresponding status in the PLC memory on programming terminal.
4. Observe corresponding control on scada screen.
CRITERIA
1. Digital Input Indication as per internal wiring
diagram.
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
All Digital Outputs should be terminated at the proper terminal only.
OBJECTIVE
To check Digital Output wiring.
REFERENCE
Approved Panel Internal Wiring Diagram
PROCEDURE
1. Force the Output with the help of programming software
2. Observe LED Indication in the corresponding digital output termination module
3. Check Relay Operation and check the contacts assigned for particular output.
4. Observe corresponding control on scada screen..
CRITERIA
Digital Output Indication as per Internal Wiring Diagram.
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
All Analog Inputs should be terminated at the proper terminal only.
OBJECTIVE
To check Analog Input wiring.
REFERENCE
1. Approved Panel Internal Wiring Diagram
2. PLC analogue input module data sheet
PROCEDURE
1. Measure the current provided by the source with a multimeter
2. Observe corresponding value on scada
screen. CRITERIA
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
SECTION 1 : PLC HARDWARE I/O FUNCTIONING
OUTLINE
All Analog Outputs should be terminated at the proper terminal only.
OBJECTIVE
To check Analog Output wiring.
REFERENCE
1. Approved Panel Internal Wiring Diagram
2. PLC analog output module data sheet
PROCEDURE
1. Force the Output memory location with the help of programming software.
2. Observe corresponding value on scada screen
CRITERIA
1. Value read is correct in terms of the specified terminals corresponding to the forced value
I/O memory location
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
Operation of the programming terminal through the PLC programming port.
OBJECTIVE
The purpose of this test is to verify that an operator can take control of the system of the PLC via a
programming terminal. The objective is to verify :
1. Correct operation of the PLC programming port
2. Correct operation of the system of the CPU
PROCEDURE
1. Connect the programming terminal to the programming port of the PLC
2. Force I/O from the programming terminal.
3. Add logic while processor is running
4. Delete logic at the end of the test
CRITERIA
1. Check that the corresponding I/O is forced.
2. Check logic is performing according to the change.
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
Connection of the programming terminal to the PLC through all available connection points : Ethernet
.
OBJECTIVE
The purpose of this test is to verify that the Ethernet communication ports is working.
PROCEDURE
1. Connect the programming terminal to all available connection points and laptop.
2. Check that the programming terminal connects to the PLC CPU.
CRITERIA
1. Check that the programming terminal Runs/Stops the PLC from each connection
point
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OUTLINE
All the Relays are functioning and the terminations as per requirements.
OBJECTIVE
The purpose of this test is to test the functionality of Relays and it’s change over contact.
PROCEDURE
1. Apply 24 V DC supply to coil of relay by jumper either by forcing the PLC outputs. .
2. Check the change of state by multi meter across relay
contacts. CRITERIA
1. NO contact of relay will become NC and vice versa. Contact change over shall be tested by
continuity tester/ multi-meter.
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
COMMENTS
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
1. Forcing of I/Os
OBJECTIVE
The purpose of this test is to verify that the console takes control of the PLC program.
PROCEDURE
1. Force I/O from the programming terminal.
CRITERIA
1. CPU REDUNDANCY
2. IO Network Redundancy
OBJECTIVE The purpose of this test is to verify that the CPUs and network are redundant
REFERENCE
1. Approved Panel System Configuration drawing .
PROCEDURE
1. To switch off the Primary PLC and see whether the network switches to secondary PLC
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
OBJECTIVE The purpose of these tests are to verify that the Screens, Security feature, data
archiving, alarms, trending and report generation are made as per customer
requirement.
REFERENCE
1. Approved P&ID Diagram.
OUTLINE
All trip functions are working properly
OBJECTIVE The purpose of this test is to verify that the console takes control of the PLC program.
REFERENCE
1. Approved control philosophy.
PROCEDURE
1. Force Fault
Condition CRITERIA
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
3. GA
4. BOM
5. DIMENSIONS
6. SPARES
OBJECTIVE The purpose of this test is to verify that the all the above mentioned are according to
the drawing
REFERENCE
1. Approved GA drawing no. 2107-301-06
OBJECTIVE The purpose of this test is to verify that the System Config in online state is
correct PROCEDURE
1. check the communication at all available ports. Check logic is performing according to the change.
PREPARED BY – DATE
HEAT TRACE INDIA PVT. LTD. 01.05.23
TITLE - FACTORY ACCEPTANCE TESTS PROCEDURE
REMARK / SIGNATURE
END USER
CONSULTANT
CONTRACTOR
CLIENT
PROJECT NAME :
FAT
SECTION 5 : TESTING OF SOFTWARE
OUTLINE
PLC Program developed as per requirement of system process in ladder or FBD language.
OBJECTIVE
The purpose of this test is to verify the digital interlocks as per to the Operational Logic.
PROCEDURE
Force the inputs and the required interlocks are checked.
REFERENCE
1. Approved control philosophy.