VESSEL NAME: SITHONIA II DATE:31.07.

2021
THALATTA SHIPPING MANAGEMENT S.A.
PARTS HOURS M/E CYLINDERS
1 2 3 4 5 6
CYLINDERS & PISTONS 6000-8000 2552 2552 2552 2552 2552 2552
STUFFING BOX 6000-8000 N N N N N N
EXHAUST VALVES 2000-4000 1623 1623 1623 1623 641 1173
FUEL VALVES 1000-2000 114 114 114 114 114 114
STARTING VALVES 6000-8000 948 948 948 948 948 948
SAFETY VALVES 6000-8000 948 948 948 948 948 948
FUEL PUMPS 6000-8000 1968 1968 1968 1968 1968 1968
CYLINDER LINER 6000 2420 1816 1925 2115 2360 1964
CYLINDER COVER 6000 2340 645 2340 645 645 364
MAIN BEARINGS 6000-8000 1696 2340 2340 2252 2252 2252
CRANKSHAFT 6000-8000 2340 2340 2340 2340 2340 2340
LUB OIL CHANGE 180 DAYS 105 105 105 105 105 105

TURBO CHARGERS
PARTS HOURS TURBO CHARGERS
1
ROTOR OVERHAULING 10,000 6223
BEARING REMOWAL 10,000 6223
GENERATORS or A/E
HOURS 1 2 3
GENERAL OVERHAULING 8000-10000 4230 3960 N/A
EXHAUST VALVES OVERHAULING 4000-5000 1645 2036
INLET VALVES OVERHAULING 4000-5000 4001 2036
INJECTORS OVERHAULING 1,500 1252 1313
CONNECTING RODS INSPECTION 8000-10000 855 1141
TURBOCHARGER OVERHAULING 8000-10000 2728 2386
BEARINGS RENEWAL 8000-10000 3420 3140
OIL COOLER CLEANING 90 DAYS 19 19
JACKET COOLER CLEANING 90 DAYS 19 19
LUBRICATING OIL SYSTEM 180 DAYS 21 22
NAME OF VESSEL : SITHONIA II DATE DONE PLANNED DATE DUE PERIODICITY IN DAYS
THALATTA SHIPPING MANAGEMENT S.A. PLANNED MAINTENANCE SYSTEM
ANCHOR WINDLASS NO 1+2 04.07.2021 180
FORWARD MOORING WINCHES 04.07.2021 180
AFT MOORING WINCHES 04.07.2021 180
DERRICKS HYDRAULIC PUMP 05.07.2021 120
AIR VENTS HEAD 06.07.2021 90
FIRE LINE 07.07.2021 180
DERRICKS WINCHES 07.07.2021 180
DERRICKS HYDRAULIC PUMP COOLER 05.07.2021 120
HOSE TESTING FOR THE WATER TIGHTNESS OF HATCH COVERS N/A 180
FORE PEAK TANK VISUAL INSPECTION 08.07.2021 180
AFTER PEAK TANK VISUAL INSPECTION 08.07.2021 180
BILGE PUMP 09.07.2021 90
BALLAST PUMP 09.07.2021 90
OIL WATER SEPARATOR 10.07.2021 180
STEERING GEAR PUMP NO 1 & 2 10.07.2021 90
FUEL & DIESEL OIL TRANSFER PUMP 11.07.2021 90
AUXILIARY BOILER 11.07.2021 90
EMERGENCY FIRE PUMP 09.07.2021 90
HATCH COVERS HYDRAULIC PUMP UNITS/SYSTEM N/A 180
EMERGENCY DIESEL GENERATOR 14.07.2021 90
SEWAGE PLANT 15.07.2021 180
NAME OF VESSEL: SITHONIA II
INVENTORY (ROB) SPARE PARTS, PAINTS, WIRES & ROPES

PARTS M/E A/E


SPRINGS(PISTON RING 8 18
BEARINGS 2 4
PISTONS 3 2
LINERS 3 4
EXHAUST VALVE 6 12
INJECTOR 18 12
INLET VALVE 6 12

CODE PAINTS LTRS


CS-614 GREY 600
CS-651 WHITE 600
EVAMARINE RED BROWN 600
CS-518 GREEN 300
CS-632 GREEN 80
CS-625 RED 80
CS-618 BUFF 160
CS-622 YELLOW 60
CS-623 ORANGE 40
EVAMARINE SILVER SPAR 60
CS-649 BLUE 60
QD HB RED BROWN 600
QD HB GREY 400
EVAMARINE THINNER 240
EVAMARINE URETHANE THINNER A 60
EVAMARINE EPOXY THINNER A 60
CS-614 UMEGUARD SX GREY 240
CS-649 UNYMARINE TS-I BLUE 240
4480
OPES

TYPE ROPES WIRES


2 COIL 3 COIL HOISTING
3 COIL TOPPING