Cable Laying JSA
Cable Laying JSA
Cable Laying JSA
Sequance of basic job steps Potential Hazard Control Measures / Recommended action Responsible Person
1.Caught in between finger / foot 1. Use of proper PPEs like hand gloves, safety shoes,
injuries safety goggles etc.
Shifting materials to the work 2.Material fall 2.Material should be handled care fully
Site Engineer
area 3.Hit injury 3.Recommended PPEs should be worn
4.Cut injury 5.Ensure per person onely carry below 25kg weight
1.Collapse of Mobile scaffolding 1.PTW system to be follow
2.Fall of material 2.TBT should be conduct before start the job
3.Fall of Person 3.Trained person to be involved in height work
4.All power tools to be handled carefully to avoide
personal injures, Ensure safeguards shall be fitted to
the equipment
Cut and physical injury due to sharp 1. Use all apporpriate PPE along with hand gloves.
Area housekeeping Site Engineer
edge
2.Area should be clear after job completion.
1.Portable fire extinquisher shall be maintained at
1.Fire or explosion location
2.First-aid box to be available
3.Ensure emergencey plan in place and know to all
the engaged people Site Engineer / Safety
Emergency preparedness 2.Severe weather Officer
4.Safe assembly point shall be explained to worker by
supervisor
4.Slip & trip
5.Access should be clear from unwanted materials.
5.Cut & hit injury
Required PPE
Safety helmet Reflective Jacket Double Lanyard FBH with Shock Absorber Ear plug