Risk Assessment - IG2
Risk Assessment - IG2
Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).
Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.
Part 1: Background
Description of the area to be included in the The risk assessment will cover the entire construction site of residential buildings, roofs, rooms,
risk assessment parking area including road area.
The project manager directly reports to the managing director who is responsible for the health
Any other relevant information and safety of the employees at site.
Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for
category and and how? required? further actions Responsible
hazard to be person’s job
completed title
(within …)
Working at The workers will be at Scaffoldings were raised by Guardrails, toe guards and brick 2 weeks Project
height harm due to working at trained workers under the guards should be installed at the manager
height above 10 metres supervision of competent edges of working platforms.
Workers have and job supervisor and supervisor.
been observed safety officers will be at Connect life line for anchoring Full 1 week Project
raising harm due to falling Conditions of scaffolding body harness of scaffolders. manager
scaffolding at objects. constituents were checked
height of 10 before erection. Safety net should be mounted 3 days HSE manager
meter without underneath the scaffolding.
anchoring Full Consequences of falling Scaffoldings are inspected in
body harness from scaffold or falling regular interval of 7 days after Loading capacity of working platform 1 day Job
and provision objects may be severe erection. should be determined and overloading supervisor
of life line was injuries like brain damage, should not be allowed.
not well- nerve or spinal injury Usage of helmets is
known. leading to permanent compulsory for scaffolders and Training should be provided to the 1 month Managing
paralysis, multiple broken workers. workers for working at height safely. director
bones and even death.
Movement near scaffolding is Regular health check-up of workers, 1 month Managing
strictly restricted and nobody is scaffolders, supervisors should be director
allowed without safety helmet. done, at least once in a month.
Finance
Workers and scaffolders should be manager and
provided with full body harness and 1 week project
lanyards manager
Lone working Workers will be harmed Training gave to workers who Lone working activities should be 2 weeks Project
who will be going inside was involve in alone working. stopped completely especially high manager
Single worker lift shafts for working. risk activities.
was seen Inspection has been carried out
working inside When alone worker before start work for prevent Lone worker alarm system to raise 2 weeks Project
the lift shafts working inside lift shafts if the any falling objects and alarm and pinpoint the worker need to manager
and he was person fall down or unsafe working platform. be implemented.
alone handling material fall down upon
the work him might be he could not Instructed to all foreman and Monitoring system must be in
equipment. ask help to anyone are no supervisors about alone work operation so that routine 1 week Managing
communicate with anyone not allowed in equipment communication can be achieved and director
operations, suggested to them incident or emergency can dealt with
provide one extra labour with effectively
Vibration Worker who will be Provided supervision on the Provide proper training on handling 2 weeks Project
Prolonged use handling the jack work. the drilling machine and jack manager
of jack hammers and drilling hammers.
hammers and machines. PPEs like helmet, reflective
drilling jacket and safety shoe are Provide weekly health check-up plan 1 week Managing
machines was Vibration can cause provided. to all worker. director
vibrating damage joints, hands and
excessively fingers .Due to vibration Monthly health check-up camp Replaced old vibrating machines with 1 month Project
while breaking tingles, numbness and conducted. new less vibrating machine. manager
the road due White appearance to
to vibration finger .After some time There was no hazard Job rotation must be done for the 3 days Job
body was figure become painful and prevention strategy in the workers. supervisor
vibrating. red. company.
Slips and Workers, visitors, safety We maintained good Provide separate access for man 1 week Site manager
trips officer and job housekeeping on floor for movement where free from obstruction
Radiation The workers, safety PPE like Coverall, Safety Closed area provided with lead wall to 1 month Project
officer, job supervisors Shoes, Helmet. reduce effect. manager
Observed that and other labour workers
the worker will be at harm due to Small Brass wall provided. Job rotation and Job change must be 1 day Shift
when doing radiation. given at regular intervals. supervisor
industrial Training was given last month
radiography, Radiations can have to the workers regarding the Provide signage to indicate radiation 1 day Safety officer
they did not acute effect like nausea, radiation and radiation activity is being performed. and site
cover the cataracts or even chronic exposure limit supervisor
gamma rays effect like cancer or birth
with heavy defects.
Work Operators, workers, job Authorised person only we Provide guard like fixed guards, inter 1 week Finance
Equipment supervisor and might be allowed to operate the high locked guards, and adjustable guards manager
harmed. risky equipment like bar to all machines for prevent a person and project
Un guarded bending & Cutting machines protected from dangerous moving manager
moving parts During operation of bar parts
grinding bending & cutting Training provided to all
machine and machine the operators operators about safe operation Dead man switch should be placed on 2 weeks Project
cutters using, body parts like fingers, procedure of machinery all machines for stop the machine manager
Fire Welders, nearby workers, Welders are using helmets with Welding and other hot work activities 3 days Site manager
safety officer and job face shield, leather hand should be done in selected zones with
Combustible supervisor present at site gloves, safety shoes and fire fire resistant floors and walls
materials like might get harmed. retardant aprons
wood and Good housekeeping work should be 1 day Site manager
plastics were Welding sparks may Fire extinguishers are present ensured.
seen adjacent strike the inflammable at the site and persons are
to welding materials present nearby trained to use them. Fire detection and fire alarm system 1 month Finance
operation. can cause fire. This can should be installed at the site. manager
result in skin burn injuries No smoking and fire safety
which can be fatal, posters are displayed at the Manual call point to alert the workers 1 week HSE manager
damage to building and site. in case of fire should be designated.
Periodical fire mock drill is Fire escape stairs and walkways 1 day Site manager
conducted. should be labelled.
Safe Driver, workers, safety Authorized person was not Provide separate access for 1 week Project
movement of officers and supervisors there to drive the vehicle. pedestrian and vehicle. manager
people and will be at risk from
vehicles vehicles. Driver should have proper Driver identity card system to be 1 week Managing
driving license. implemented. director
Vehicles and The accidents will cause
peoples have injuries to head, fractures, Regular Inspection of vehicles Only trained driver must be allowed to 1 week Project
same routes crushing, and bleeding is done. drive. manager
and road signs due to cuts.
are not Vehicle should not overload. 1 day Job
provided. supervisor
Manual Worker & operators, job Portable trolley provided to Avoid manual lifting from floor level or 1 day Job
handling supervisors. workers for shifting cement above shoulder height, especially supervisor
bags, blocks for easy handling heavy loads
Manual Manual handling activities
handling of generate the possibility of Training has been gave to all Access should be clear and free from 1 day Site manager
blocks, cement injuries, most of which are manual handling workers about any obstruction in manual handling
bags, steel. musculoskeletal injuries taken precaution during load access area for prevent trip hazard
handling also prevent of during manual handling
Back injury, tendon and musculoskeletal health
ligament injuries, muscle disorders
injuries, hernias and Work breaks should be given to all 1 day Project
Load Workers, operators, The tower crane, hoist and Over load activities should be avoided 1 week Job
Handling visitors, banks man, trucks are check properly with for prevent the crane collapse or load supervisor
equipment supervisor and safety competent person or third party fall down as well as for hoist truck.
officers might get harm. person for prevent failure.
Material fall Crane, Hoist and truck operation 1 day Job
down and Load handling risk is also Appointed competent bank should be stopped when heavy rains, supervisor
equipment fall machinery due to lack of mans for safe signal given to heavy wind speed
down from guards, also feet chance operators during loading,
cranes, hoist to trap into under truck loading and vehicle reversing Out riggers and structure supports 1 day Safety officer
due to wheel while lowering load. should be check before lifting.
overloading. Severity in this case Competent operator has been Project
workers or operators appointed for safe operation of Safety device to be provide such as 1 month manager and
chance get major serious hoists, cranes and trucks over load alarms and limit switches. finance
injury like body parts manager
crushing, cutting, Safe working load displayed in
fractures. Sometimes every equipment for prevent
minor cut injuries also the overload Project
may occur. Maintenance should be done with 1 month manager
Training has been gave to all authorised person to ensure safe
Moral, general legal and financial The Reliable construction main moral goal is to achieve complete safety of workers and zero
arguments incident/accident at site, so every time we take care about our workers safety & health. Every
workers working at site earn wages to look after their families. When health and safety is not
achieved appropriately any workers at site can get injured or sometimes death might also occur,
other than these some may suffer by severe disease that will huge impact not only on workers, but
also on their children’s, families, friends and co-workers. This suffering is ethically undesirable and
society as a whole demands that people are safe during work. So the company will be fully
responsible for safeguard the workers at site.
Financial impacts could be broken down into Direct cost and Indirect cost:
Direct costs: Compensation payable to the victim or his/her family in case of death, fines in the
criminal court, first-aid treatment, worker sick pay, repairs to or replacement of damaged equipment
of building, lost or damaged product, lost production time while dealing with the injury, overtime to
make up for lost time and costs associated with the recovery of the injured worker.
Indirect costs: Loss of staff morale, cost of remedial action following an investigation, cost of
recruiting and training temporary or replacement staff, loss of goodwill of customers, difficult in
recruiting and retaining staffs as an indirect result of the accident and damage to public image and
business reputation.
The company will face civil trial by the enforcement agencies, they will make the prohibition on
certain activities or they will give improvement notice meaning that the action will be improved on
given time or else face serious consequences. This will major business impact if the activities are
stopped. Other than this organisation will be fined or sued by the civil court for the civil claims made
Provide SCBA (Self-contained breathing apparatus) to the worker who is working in the confine
Action
space (hazard category- Working in Confined spaces)
Specific legal arguments As per the International labour organisation (ILO) C167 safety and health in construction
convention, 1988 in Article 30 it stated that Employer should provide appropriate PPEs ,PPEs
should be as per the standard provide to the Employee . As per the International labour
organisation (ILO) “Working in confine space” Reduced oxygen levels, risks from noxious fumes, or
a risk of fire while working in a confined space it’s very dangerous Other danger like flooding or
asphyxiation from other source .
Other dangers may include flooding/drowning or asphyxiation from some other source such as
dust, grain or other contaminant. Working in confine space required breathing apparatus or
ventilation if there is not enough oxygen. Make sure that person is enough train to work inside the
confine space.
The likelihood of the workers getting ill suddenly while working in confined spaces without a
Consideration of likelihood AND severity
breathing apparatus is very high. This is due to low oxygen levels in the confined space area. 2-3
workers will be involve in this activity for at least 1-2 hours.
The severity rating for this hazard is set at high. As the low oxygen levels will make unconscious
and there will be oxygen deficiency, breathlessness causing fatal accident. Immediate treatment will
be required for the ILL worker and worst case scenario will be death.
How effective the action is likely to be in
The SCBA will protect users against oxygen deficiency, dust, gases and vapours in confined
controlling the risk. This should include:
spaces. The main benefit of action is to save the life of the worker working inside the confined
the intended impact of the action; space. Providing breathing apparatus will defiance the legal requirement also and it prevent the
justification for the timescale that you cost of accident. Breathing apparatus will reduce the risk who is working inside the confine space
indicated in your risk assessment; I have given timescale of 1 month to provide this breathing apparatus. Finance manager will be
and responsible for this action, he will then discuss with the managing director about this breathing
Whether you think the action will fully apparatus to be available at site and thus he will place an order to the supplier.
control the risk.
The action will fully control the risk of oxygen deficiency in the confined spaces as long as this
Action Setting up of MCBs at all the electrical supply boarding (hazard category ‘electricity’)
Specific legal arguments International labour organisation has convention C167 - Safety and Health in Construction Convention,
1988 in that it states in Article 26 that all electrical equipment and installations shall be constructed,
installed and maintained by a competent person, and so used as to guard against danger.
International labour organisation has discussed in their ELECTRICAL SAFETY that The risk
assessment should take into consideration the type of electrical equipment used, the way in which it
is used and the environment that it is used in and Employers must make sure that the electrical
installation and the electrical equipment is suitable for its intended use and the conditions in which it
is operated.
Consideration of likelihood AND severity The likelihood of accident from an electrical distribution board without MCB is very likely. Every day
3 technicians and 4 workers used the electrical equipments which is connected to the Power
distribution board. In case of current load, cables will be inflamed resulting in electrical fire.
The severity rating electrical accident is major. Electrical fire spreads very fast and causes severe
injuries like ventricular fibrillation, respiratory paralysis, muscular contraction, physical trauma,
cardiac arrest and even death. People can get killed or severely injured. Electrical equipment can
also get damaged from overloading of electrical circuits.
Action Provide guard like fixed guards, inter locked guards, and adjustable guards to all machines for
prevent a person protected from dangerous moving parts. (Hazard category- Work Equipment)
The international labour organisation (ILO) has convention C199- Guarding Machinery Convention
Specific legal arguments
1963 in that it had states in Article 6 that the use of machinery any dangerous part of which,
including the point of operation, is without appropriate guards shall be prohibited by national laws or
regulations or prevented by other equally effective measures: Provided that where this prohibition
cannot fully apply without preventing the use of the machinery it shall apply to the extent that the
use of the machinery permits and Machinery shall be so guarded as to ensure that national
regulations and standards of occupational safety and hygiene are not infringed.
International labour organisation has Recommendation R118 - Guarding of Machinery
Recommendation, 1963 has states in point no 12 that No worker should use any machinery without
the guards provided being in position, nor should any worker be required to use any machinery
without the guards provided being in position.
Consideration of likelihood AND severity The likelihood of injuries happening from operating machines were not covered the rotating parts is
very high. Because every day construction site starts with machinery equipment’s and most of
activities depends on it. And there is a regular work of equipment for at least 4-hrs daily.
The severity rating for this hazard will be very major. During steel cutting with grinder or chop saw
machine grinder wheel might be break and cause major cut injuries which will require hospital
treatment. Sometime operator or co-workers can chance to fatal, it depends on severity of injury.
While operator operate the machine without cover the rotating parts it may cause of body parts like
fingers, hands or other limbs will chance to trapped into the machine and get injury’s like deep cuts,
crushing and fractures.
How effective the action is likely to be in
Machine guarding will provide protection workers from injury as it provides defence to operators
controlling the risk. This should include:
from injury while working and it will reduce the probability of occupational injuries due to mechanical
the intended impact of the action; failures, human error or any electrical failure.
justification for the timescale that you I have given time scale 1 week for the completion of this action. The project manager will have a
indicated in your risk assessment; meeting with the finance manager for purchasing the safe guards of all equipment’s. The finance
and manager will source a supplier for the necessary guards for equipments and it is hoped that this
whether you think the action will fully action will be completed in 1 week.
Planned review date/period with As per the policy of company risk assessment should be reviewed at least every 1 year so therefore
reasoning I set a review date on 1/10/2022 and I will make sure that this will review before the date if any
changes in plant and machinery, Standards that will effects and any changes in shift pattern.
How the risk assessment findings will be I will arrange meeting with the technical persons and management staffs including Project
communicated AND who you need to tell Manager, Site manager, managing director, Finance Manager and HR and will conduct safety
meetings regularly to discuss on risk assessment and control measures. The findings of these
meetings will be communicated to all the employees related to this Risk assessment through emails
sent from HR office. The risk assessment findings will be displayed at all the notice boards.
Projector screens will be set at office and site office to display the risk assessment. The posters will
be printed and displayed at site including bulletin boards. Other than these, the printed copies of
risk assessment will be given to the key persons involved with this project.
How you will follow up on the risk I will set Google alarms prior to completion date of each action. I will be highlight on every day in
assessment to check that the actions our daily work planning meeting which is happing in our site along with site team, there I will remind
have been carried out to every concern person and get update of actions progress. We will also discuss together and try
to get resolve issues if any difficulties during completion of each actions. I will also prepare one
action tracker to each action along with time scale and responsibility person name and display in
site notice board. I will also remind to every responsible person through emails and site social
media groups. Before target date I will be arrange one special meeting with all responsible person
along with project in-charge and get know what is the exact status and if there is any difficulties for
completion or delaying of action then that action will be referred to managing director by the finance
manager, and request them solve the issue within target date.