Risk Assessment - IG2

Uploaded by

Hossam Ayed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (4 votes)
3K views17 pages

Risk Assessment - IG2

Uploaded by

Hossam Ayed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 17

Unit IG2: Risk assessment

Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).

Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.

Part 1: Background

You should aim to complete this section in 150 - 200 words.


Topic Comments
Name of organisation* Reliable construction private limited
Site location* Panvel, India
Number of workers 500
Reliable construction private Limited is a diversified company established in 1989 and completing
projects in numerous segments like Transport, Energy & Power, refineries, oil and gas plants,
chemical plants, Construction of Buildings, roads, high rise buildings, hospitals, dams, educational
institutes, and Real Estate etc. The employees will include Project manager, finance manager, job
supervisors, safety officers, HSE manager, site manager, site supervisors, store manager, labor
workers and other third party workers.
Currently it is working on construction of Residential buildings in 3 Wings, The work activities
General description of the organisation done at site are marking, grading, excavation, concreting, brick masonry, plumbing, welding,
electrical works, painting, insulation, roofing and commissioning. The equipments used at site are
excavators, tower cranes, loaders, bulldozers, trucks, cement mixers, grinders, drills, welding
machines, clamps, screwdrivers, brushes, trowels, wrenches and cutters.
The company working pattern is in 3 shifts every shift of 8 hours and 1 weekly off is given to every
workers and festival holidays, sick leaves and emergency leaves are also given.

Description of the area to be included in the The risk assessment will cover the entire construction site of residential buildings, roofs, rooms,
risk assessment parking area including road area.
The project manager directly reports to the managing director who is responsible for the health
Any other relevant information and safety of the employees at site.

Learner number: 00617718 Learner name: Muhid Majid Bade Page 1 of 17


* If you’re worried about confidentiality, you can invent a false name and location for your organisation but, all other information provided must be
factual.

You should aim to complete this section in 100 - 200 words.


Note: this section can be completed after you have competed your risk assessment.
Outline how the risk
assessment was
carried out this should I started by checking whether ILO has any laws OR codes of practice regarding the construction. Then I got to know that
include: ILO has information about the construction- C167 - Safety and Health in Construction Convention, 1988
 sources of https://www.ilo.org/dyn/normlex/en/f?p=NORMLEXPUB:12100:0::NO::P12100_ILO_CODE:C167
information And R175 - Safety and Health in Construction Recommendation, 1988
consulted; https://www.ilo.org/dyn/normlex/en/f?p=NORMLEXPUB:55:0::NO::P55_TYPE,P55_LANG,P55_DOCUMENT,P55_NODE:REC,en,R175,/
Document
 who you spoke
to; and
After going through the information, I started doing inspection. I went spoke to workers .I have spoken to site engineer,
 how you job supervisor and safety officers this help me to identified the hazards. While doing the site visit worker gave me
identified: information like worker was saying that they don’t know about the appropriate PPEs which is suitable for work for
- the example ear plug while doing breaking activity with breaker.
hazards;
- what is I also checked first aid reports of previous accident & incident records and sick absence records of the workers of the
already past 6 months. I also checked documents related health and safety audits. Also I had conducted health check-up to all
being done; workers and employees who are involving above activity and get reports, this reports also I had refer during risk
and assessment.
- Any
Following the site, I checked back the notes which I made during the site tour and information which I have reviewed
additional
already to decide upon the further control measures.
controls/acti
ons that
may be
required.

Learner number: 00617718 Learner name: Muhid Majid Bade Page 2 of 17


Part 2: Risk Assessment

Organisation name: Reliable construction private limited


Date of assessment: 30-09-2021
Scope of risk assessment: Construction site of residential buildings, roofs, rooms, parking area including road area.

Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for
category and and how? required? further actions Responsible
hazard to be person’s job
completed title
(within …)
Working at The workers will be at Scaffoldings were raised by Guardrails, toe guards and brick 2 weeks Project
height harm due to working at trained workers under the guards should be installed at the manager
height above 10 metres supervision of competent edges of working platforms.
Workers have and job supervisor and supervisor.
been observed safety officers will be at Connect life line for anchoring Full 1 week Project
raising harm due to falling Conditions of scaffolding body harness of scaffolders. manager
scaffolding at objects. constituents were checked
height of 10 before erection. Safety net should be mounted 3 days HSE manager
meter without underneath the scaffolding.
anchoring Full Consequences of falling Scaffoldings are inspected in
body harness from scaffold or falling regular interval of 7 days after Loading capacity of working platform 1 day Job
and provision objects may be severe erection. should be determined and overloading supervisor
of life line was injuries like brain damage, should not be allowed.
not well- nerve or spinal injury Usage of helmets is
known. leading to permanent compulsory for scaffolders and Training should be provided to the 1 month Managing
paralysis, multiple broken workers. workers for working at height safely. director
bones and even death.
Movement near scaffolding is Regular health check-up of workers, 1 month Managing
strictly restricted and nobody is scaffolders, supervisors should be director
allowed without safety helmet. done, at least once in a month.
Finance
Workers and scaffolders should be manager and
provided with full body harness and 1 week project
lanyards manager

Learner number: 00617718 Learner name: Muhid Majid Bade Page 3 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for
category and and how? required? further actions Responsible
hazard to be person’s job
completed title
(within …)
Working in Mostly the worker working Ventilation fan was provided Provide SCBA (Self-contained 2 weeks Finance
Confined inside the confined inside the confine space. breathing apparatus) to the worker manager
spaces spaces. who is working in the confined space
Worker and supervisor are
Breathing Worker working inside the uninformed about breathing Provide training on confined spaces 1 month Managing
apparatus is confine space facing apparatus. working to the workers. director
not provided oxygen deficiency
for working in problem and due to that Training was carried out last Implement inspection system before 1 week Managing
confined he can unconscious, fall , month. using breathing apparatus. director
spaces which stressed and can be fatal
will include accident Permit to work system is Provide oxygen and gas checking
manhole, pits implemented before starting machine and check the oxygen and 1 week Finance
and drainage any activity. gas before entry in the confined manager
pits. spaces.

Buddy worker should be provided 1 day Project


while working inside the confined manager
spaces.

Lone working Workers will be harmed Training gave to workers who Lone working activities should be 2 weeks Project
who will be going inside was involve in alone working. stopped completely especially high manager
Single worker lift shafts for working. risk activities.
was seen Inspection has been carried out
working inside When alone worker before start work for prevent Lone worker alarm system to raise 2 weeks Project
the lift shafts working inside lift shafts if the any falling objects and alarm and pinpoint the worker need to manager
and he was person fall down or unsafe working platform. be implemented.
alone handling material fall down upon
the work him might be he could not Instructed to all foreman and Monitoring system must be in
equipment. ask help to anyone are no supervisors about alone work operation so that routine 1 week Managing
communicate with anyone not allowed in equipment communication can be achieved and director
operations, suggested to them incident or emergency can dealt with
provide one extra labour with effectively

Learner number: 00617718 Learner name: Muhid Majid Bade Page 4 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for
category and and how? required? further actions Responsible
hazard to be person’s job
completed title
(within …)
him when use power
equipment’s. Safe access and egress should be
provide to the workplace in case any 1 week Site manager
Radio devices and mobile emergency they have easy to escape
phone has been provided to from there
him for communicated with Project
others. Risk assessment should be carry out 1 month manager and
for lone working and put extra control HSE manager
Medical health check-up has measures if any required
been done before deploy to
work.

Young trainee worker is not


allowed to lone working.

PPEs are provided like full


body harness, helmet, reflected
jacket.

Vibration Worker who will be Provided supervision on the Provide proper training on handling 2 weeks Project
Prolonged use handling the jack work. the drilling machine and jack manager
of jack hammers and drilling hammers.
hammers and machines. PPEs like helmet, reflective
drilling jacket and safety shoe are Provide weekly health check-up plan 1 week Managing
machines was Vibration can cause provided. to all worker. director
vibrating damage joints, hands and
excessively fingers .Due to vibration Monthly health check-up camp Replaced old vibrating machines with 1 month Project
while breaking tingles, numbness and conducted. new less vibrating machine. manager
the road due White appearance to
to vibration finger .After some time There was no hazard Job rotation must be done for the 3 days Job
body was figure become painful and prevention strategy in the workers. supervisor
vibrating. red. company.

Learner number: 00617718 Learner name: Muhid Majid Bade Page 5 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for
category and and how? required? further actions Responsible
hazard to be person’s job
completed title
(within …)
Provide rubber mat and thick rubber 2 weeks Finance
sole safety shoes should to decrease manager
the vibration.
Noise Generator operator, D.G. room is kept closed when A silencer pipe should be installed on 1 week Project
workers, safety officers, it is in operation. the exhaust pipe of the D.G. manager
Diesel job supervisors,
generator engineers working near Maintenance of generator is Acoustic Enclosure must be provided 2 weeks Project
used at site the D.G. Room, Site done on monthly basis. around the generator manager
was making Supervisors and visitors
extreme noise. may be affected. Training regarding noise Anti-vibration mounts like rubber 1 week Project
hazards and its controls is mount, spring mount or dampers manager
Exposure to constant provided to all the workers and should be set underneath the
noise of over 100 dB may employees last month. generator to remove vibration and the
cause short-term noise spread.
reduction in hearing Sound level meter are installed
sensitivity and tinnitus, at site to measure the noise Audiometric test for D.G. operator, 1 month Managing
tiredness and stress, level. workers having noise exposure should director
noise induced hearing be done in regular intervals.
damage, headache and Project
loss of focus. Job rotation should be provided to the 1 week manager and
generator operators and the workers shift manager
working near D.G. Room to reduce the
exposure period.
Job
Ear muffs or ear plugs should be given 1 week supervisor
to all the workers, employees present and safety
at the site and instructions to use them officer
effectively should be given.

Slips and Workers, visitors, safety We maintained good Provide separate access for man 1 week Site manager
trips officer and job housekeeping on floor for movement where free from obstruction

Learner number: 00617718 Learner name: Muhid Majid Bade Page 6 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for
category and and how? required? further actions Responsible
hazard to be person’s job
completed title
(within …)
supervisors and if any prevent any trip and slip with fully barricaded
Poor public people comes into hazards Project
housekeeping construction site All floor surface must be appropriate 1 week manager
was observed Training gave to all workers with levelled and must slip resistance.
across access, Slip and trips can cause about slip and trip hazards Site manager
lack of injuries like cut injuries, Arrange separate workers for cleaning 1 week and project
illumination, bruises and Cable stands are provided to floors and access on every day with manager
improper floor musculoskeletal health where cable laying ground for proper supervision.
level, cable issues and head injury, prevent the tripping
laying on floor, neck injury and bone Bund wall should be built where Project
shuttering fractures. In access area shuttering oil chance to come rain water into floor 1 week manager
spillage on usage fully avoided, and and arrange labour instantly for
floor. provide bottles for carrying cleaning the wet floor.
shuttering oil to all carpenters Site
for avoiding spillage of oil Emergency routes must be kept free 1 day supervisor
of obstruction at all times.
Proper sufficient illumination Project
should be provide in main PPE’s should be provide as per 1 day manager
access and throughout work requirement
place.

Radiation The workers, safety PPE like Coverall, Safety Closed area provided with lead wall to 1 month Project
officer, job supervisors Shoes, Helmet. reduce effect. manager
Observed that and other labour workers
the worker will be at harm due to Small Brass wall provided. Job rotation and Job change must be 1 day Shift
when doing radiation. given at regular intervals. supervisor
industrial Training was given last month
radiography, Radiations can have to the workers regarding the Provide signage to indicate radiation 1 day Safety officer
they did not acute effect like nausea, radiation and radiation activity is being performed. and site
cover the cataracts or even chronic exposure limit supervisor
gamma rays effect like cancer or birth
with heavy defects.

Learner number: 00617718 Learner name: Muhid Majid Bade Page 7 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for
category and and how? required? further actions Responsible
hazard to be person’s job
completed title
(within …)
metal when
not in use on
the corner of
the site.
Electricity Electrician, and workers Only licensed electric Setting up of MCBs at all the electrical 1 month Finance
who will be handling the technicians are allowed for supply boarding. manager and
Electrical electrical equipment will electrical work. project
connection be at harm. manager
Panels does Electricians are using insulated
not have MCB. There will be injuries like tools and equipment. Earthing should be checked and 1 day Job
ventricular fibrillation, proper earthing pit should be supervisor
respiratory paralysis, First aid services are available prepared.
muscular contraction, at the site.
physical trauma, cardiac Permit to work must be issued every 1 day Permit issuer
arrest and even death. Safety posters and sign boards time before electrical work.
There will be also about safe electrical works Job
secondary effects like displayed at site. Insulation of all electrical cables and 1 day supervisor
cuts, bruises and broken equipment’s should be checked and safety
bones. There is also risk Electricians are provided with regularly. officer
of arcing, electrical fire safety boots and with safety
and explosions. gloves.
All the electrical circuits should be 1 day Electrical
checked regularly. head

Work Operators, workers, job Authorised person only we Provide guard like fixed guards, inter 1 week Finance
Equipment supervisor and might be allowed to operate the high locked guards, and adjustable guards manager
harmed. risky equipment like bar to all machines for prevent a person and project
Un guarded bending & Cutting machines protected from dangerous moving manager
moving parts During operation of bar parts
grinding bending & cutting Training provided to all
machine and machine the operators operators about safe operation Dead man switch should be placed on 2 weeks Project
cutters using, body parts like fingers, procedure of machinery all machines for stop the machine manager

Learner number: 00617718 Learner name: Muhid Majid Bade Page 8 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for
category and and how? required? further actions Responsible
hazard to be person’s job
completed title
(within …)
unauthorised hands might be stuck in equipment operation when if any body part stuck
persons between machine parts into machines
operations, and steel materials due to Periodically inspection of the
using poor lack of operation equipment is done. Manufacturer’s safety instruction and 1 week Job
quality of knowledge and lack of guidelines should be followed. supervisor
equipment. negligence Provided ELEB, RCCB and
proper body earthing to Ensure all combustible and flammable 1 day Safety officer
Due to unprotected machines from prevent the materials should be remove from
rotated of machine parts electric shocks and inspected grinding and cutting activity areas from
might be get trapped into them on every month once prevent of any fire and explosions
the machines Finance
Permit to work is issued before PPE like cut resistance hand gloves, 1 week manager and
the cutting operation full body aprons need to be provided. project
manager
PPE has been provided all
workers and operators like
hand gloves, safety goggles,
helmet, safety shoes, face
shield etc.

Fire Welders, nearby workers, Welders are using helmets with Welding and other hot work activities 3 days Site manager
safety officer and job face shield, leather hand should be done in selected zones with
Combustible supervisor present at site gloves, safety shoes and fire fire resistant floors and walls
materials like might get harmed. retardant aprons
wood and Good housekeeping work should be 1 day Site manager
plastics were Welding sparks may Fire extinguishers are present ensured.
seen adjacent strike the inflammable at the site and persons are
to welding materials present nearby trained to use them. Fire detection and fire alarm system 1 month Finance
operation. can cause fire. This can should be installed at the site. manager
result in skin burn injuries No smoking and fire safety
which can be fatal, posters are displayed at the Manual call point to alert the workers 1 week HSE manager
damage to building and site. in case of fire should be designated.

Learner number: 00617718 Learner name: Muhid Majid Bade Page 9 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for
category and and how? required? further actions Responsible
hazard to be person’s job
completed title
(within …)
its contents, suffocation
by inhaling toxic smoke First aid facilities are available Fire hydrant and sprinkler system 1 month Finance
and fume and even death. at the site. should be installed. manager

Periodical fire mock drill is Fire escape stairs and walkways 1 day Site manager
conducted. should be labelled.

Safe Driver, workers, safety Authorized person was not Provide separate access for 1 week Project
movement of officers and supervisors there to drive the vehicle. pedestrian and vehicle. manager
people and will be at risk from
vehicles vehicles. Driver should have proper Driver identity card system to be 1 week Managing
driving license. implemented. director
Vehicles and The accidents will cause
peoples have injuries to head, fractures, Regular Inspection of vehicles Only trained driver must be allowed to 1 week Project
same routes crushing, and bleeding is done. drive. manager
and road signs due to cuts.
are not Vehicle should not overload. 1 day Job
provided. supervisor

Manual Worker & operators, job Portable trolley provided to Avoid manual lifting from floor level or 1 day Job
handling supervisors. workers for shifting cement above shoulder height, especially supervisor
bags, blocks for easy handling heavy loads
Manual Manual handling activities
handling of generate the possibility of Training has been gave to all Access should be clear and free from 1 day Site manager
blocks, cement injuries, most of which are manual handling workers about any obstruction in manual handling
bags, steel. musculoskeletal injuries taken precaution during load access area for prevent trip hazard
handling also prevent of during manual handling
Back injury, tendon and musculoskeletal health
ligament injuries, muscle disorders
injuries, hernias and Work breaks should be given to all 1 day Project

Learner number: 00617718 Learner name: Muhid Majid Bade Page 10 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for
category and and how? required? further actions Responsible
hazard to be person’s job
completed title
(within …)
chronic soft tissue injuries Health check-up we had manual handling workers like intervals manager
can occur to the arms, arranged to all workers who are of every 2 hours
wrists and hands due to involving in manual handling
repetitive manual also health monitoring to them Risk assessment should be review 3 months Managing
handling activities. with management and extra control director
Protection is provided for all measures should be placed if any
sharp edges for prevent cut required
injuries Job
Good supervision should be required 1 day supervisor
PPE’s already provided to during manual handling and safety
them, like safety shoes, cut officer
resistant hand gloves

Load Workers, operators, The tower crane, hoist and Over load activities should be avoided 1 week Job
Handling visitors, banks man, trucks are check properly with for prevent the crane collapse or load supervisor
equipment supervisor and safety competent person or third party fall down as well as for hoist truck.
officers might get harm. person for prevent failure.
Material fall Crane, Hoist and truck operation 1 day Job
down and Load handling risk is also Appointed competent bank should be stopped when heavy rains, supervisor
equipment fall machinery due to lack of mans for safe signal given to heavy wind speed
down from guards, also feet chance operators during loading,
cranes, hoist to trap into under truck loading and vehicle reversing Out riggers and structure supports 1 day Safety officer
due to wheel while lowering load. should be check before lifting.
overloading. Severity in this case Competent operator has been Project
workers or operators appointed for safe operation of Safety device to be provide such as 1 month manager and
chance get major serious hoists, cranes and trucks over load alarms and limit switches. finance
injury like body parts manager
crushing, cutting, Safe working load displayed in
fractures. Sometimes every equipment for prevent
minor cut injuries also the overload Project
may occur. Maintenance should be done with 1 month manager
Training has been gave to all authorised person to ensure safe

Learner number: 00617718 Learner name: Muhid Majid Bade Page 11 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for
category and and how? required? further actions Responsible
hazard to be person’s job
completed title
(within …)
operators, signal man, running
equipment users about safe Job
operation system Hoist landing platforms should be 1 day supervisor
secure and free from obstruction and and safety
We using PPE’s like safety gaps officer
shoes or boots avoid crush
injuries All lifting equipment’s like wire ropes, Project
web slings, chine slings, material 3 months manager
loading buckets, D-shackles should be
inspected with third party inspector on
every 2 months and keep record

Learner number: 00617718 Learner name: Muhid Majid Bade Page 12 of 17


Part 3: Prioritise 3 actions with justification for the selection
Suggested word counts
Moral and financial arguments for all actions: 300 to 350 words
For EACH action:
Specific legal arguments: 100 to 150 words
Likelihood AND severity: 75 to 150 words
How effective the action is likely to be in controlling the risk: 100 to 150 words

Moral and financial arguments for ALL actions

Moral, general legal and financial The Reliable construction main moral goal is to achieve complete safety of workers and zero
arguments incident/accident at site, so every time we take care about our workers safety & health. Every
workers working at site earn wages to look after their families. When health and safety is not
achieved appropriately any workers at site can get injured or sometimes death might also occur,
other than these some may suffer by severe disease that will huge impact not only on workers, but
also on their children’s, families, friends and co-workers. This suffering is ethically undesirable and
society as a whole demands that people are safe during work. So the company will be fully
responsible for safeguard the workers at site.
Financial impacts could be broken down into Direct cost and Indirect cost:
Direct costs: Compensation payable to the victim or his/her family in case of death, fines in the
criminal court, first-aid treatment, worker sick pay, repairs to or replacement of damaged equipment
of building, lost or damaged product, lost production time while dealing with the injury, overtime to
make up for lost time and costs associated with the recovery of the injured worker.
Indirect costs: Loss of staff morale, cost of remedial action following an investigation, cost of
recruiting and training temporary or replacement staff, loss of goodwill of customers, difficult in
recruiting and retaining staffs as an indirect result of the accident and damage to public image and
business reputation.
The company will face civil trial by the enforcement agencies, they will make the prohibition on
certain activities or they will give improvement notice meaning that the action will be improved on
given time or else face serious consequences. This will major business impact if the activities are
stopped. Other than this organisation will be fined or sued by the civil court for the civil claims made

Learner number: 00617718 Learner name: Muhid Majid Bade Page 13 of 17


by the ill health workers. There will be compensation paid to the worker by the company and courts
and lawyers’ fees will be also high.

Justification for action 1

Provide SCBA (Self-contained breathing apparatus) to the worker who is working in the confine
Action
space (hazard category- Working in Confined spaces)
Specific legal arguments As per the International labour organisation (ILO) C167 safety and health in construction
convention, 1988 in Article 30 it stated that Employer should provide appropriate PPEs ,PPEs
should be as per the standard provide to the Employee . As per the International labour
organisation (ILO) “Working in confine space” Reduced oxygen levels, risks from noxious fumes, or
a risk of fire while working in a confined space it’s very dangerous Other danger like flooding or
asphyxiation from other source .
Other dangers may include flooding/drowning or asphyxiation from some other source such as
dust, grain or other contaminant. Working in confine space required breathing apparatus or
ventilation if there is not enough oxygen. Make sure that person is enough train to work inside the
confine space.
The likelihood of the workers getting ill suddenly while working in confined spaces without a
Consideration of likelihood AND severity
breathing apparatus is very high. This is due to low oxygen levels in the confined space area. 2-3
workers will be involve in this activity for at least 1-2 hours.
The severity rating for this hazard is set at high. As the low oxygen levels will make unconscious
and there will be oxygen deficiency, breathlessness causing fatal accident. Immediate treatment will
be required for the ILL worker and worst case scenario will be death.
How effective the action is likely to be in
The SCBA will protect users against oxygen deficiency, dust, gases and vapours in confined
controlling the risk. This should include:
spaces. The main benefit of action is to save the life of the worker working inside the confined
 the intended impact of the action; space. Providing breathing apparatus will defiance the legal requirement also and it prevent the
 justification for the timescale that you cost of accident. Breathing apparatus will reduce the risk who is working inside the confine space
indicated in your risk assessment; I have given timescale of 1 month to provide this breathing apparatus. Finance manager will be
and responsible for this action, he will then discuss with the managing director about this breathing
 Whether you think the action will fully apparatus to be available at site and thus he will place an order to the supplier.
control the risk.
The action will fully control the risk of oxygen deficiency in the confined spaces as long as this

Learner number: 00617718 Learner name: Muhid Majid Bade Page 14 of 17


equipments are inspected before use.

Justification for action 2

Action Setting up of MCBs at all the electrical supply boarding (hazard category ‘electricity’)

Specific legal arguments International labour organisation has convention C167 - Safety and Health in Construction Convention,
1988 in that it states in Article 26 that all electrical equipment and installations shall be constructed,
installed and maintained by a competent person, and so used as to guard against danger.
International labour organisation has discussed in their ELECTRICAL SAFETY that The risk
assessment should take into consideration the type of electrical equipment used, the way in which it
is used and the environment that it is used in and Employers must make sure that the electrical
installation and the electrical equipment is suitable for its intended use and the conditions in which it
is operated.

Consideration of likelihood AND severity The likelihood of accident from an electrical distribution board without MCB is very likely. Every day
3 technicians and 4 workers used the electrical equipments which is connected to the Power
distribution board. In case of current load, cables will be inflamed resulting in electrical fire.
The severity rating electrical accident is major. Electrical fire spreads very fast and causes severe
injuries like ventricular fibrillation, respiratory paralysis, muscular contraction, physical trauma,
cardiac arrest and even death. People can get killed or severely injured. Electrical equipment can
also get damaged from overloading of electrical circuits.

How effective the action is likely to be in


The installation of MCBs at all the electrical distribution boards will be very much effective to
controlling the risk. This should include:
prevent the current overload in the electrical circuits. MCBs will give protection to the circuit when
 the intended impact of the action; there is an overcurrent/overloading When current overload occurs, MCB trips and disconnects the
 justification for the timescale that you electric circuit. It can be reset further.
indicated in your risk assessment; I have given timescale of 1month is for this action because it is a specialised electrical devices. The
and Project manager will discuss with the finance manager about the installation of MCBs at site and
 whether you think the action will fully thus he will approve and get it installed by the electric technician.
control the risk.
This action will fully control the risk as MCBs are very much effective in breaking the circuit in case

Learner number: 00617718 Learner name: Muhid Majid Bade Page 15 of 17


of current overload

Justification for action 3

Action Provide guard like fixed guards, inter locked guards, and adjustable guards to all machines for
prevent a person protected from dangerous moving parts. (Hazard category- Work Equipment)
The international labour organisation (ILO) has convention C199- Guarding Machinery Convention
Specific legal arguments
1963 in that it had states in Article 6 that the use of machinery any dangerous part of which,
including the point of operation, is without appropriate guards shall be prohibited by national laws or
regulations or prevented by other equally effective measures: Provided that where this prohibition
cannot fully apply without preventing the use of the machinery it shall apply to the extent that the
use of the machinery permits and Machinery shall be so guarded as to ensure that national
regulations and standards of occupational safety and hygiene are not infringed.
International labour organisation has Recommendation R118 - Guarding of Machinery
Recommendation, 1963 has states in point no 12 that No worker should use any machinery without
the guards provided being in position, nor should any worker be required to use any machinery
without the guards provided being in position.
Consideration of likelihood AND severity The likelihood of injuries happening from operating machines were not covered the rotating parts is
very high. Because every day construction site starts with machinery equipment’s and most of
activities depends on it. And there is a regular work of equipment for at least 4-hrs daily.
The severity rating for this hazard will be very major. During steel cutting with grinder or chop saw
machine grinder wheel might be break and cause major cut injuries which will require hospital
treatment. Sometime operator or co-workers can chance to fatal, it depends on severity of injury.
While operator operate the machine without cover the rotating parts it may cause of body parts like
fingers, hands or other limbs will chance to trapped into the machine and get injury’s like deep cuts,
crushing and fractures.
How effective the action is likely to be in
Machine guarding will provide protection workers from injury as it provides defence to operators
controlling the risk. This should include:
from injury while working and it will reduce the probability of occupational injuries due to mechanical
 the intended impact of the action; failures, human error or any electrical failure.
 justification for the timescale that you I have given time scale 1 week for the completion of this action. The project manager will have a
indicated in your risk assessment; meeting with the finance manager for purchasing the safe guards of all equipment’s. The finance
and manager will source a supplier for the necessary guards for equipments and it is hoped that this
 whether you think the action will fully action will be completed in 1 week.

Learner number: 00617718 Learner name: Muhid Majid Bade Page 16 of 17


control the risk.
The will fully control the risk once the guard is provided and all the rotating parts are guarded and
the guard must be inspected before use.
Part 4: Review, communicate and check
Suggested word counts for each section:
 Planned review date or period and reasoning for this: 50 - 100 words
 How the risk assessment findings will be communicated and who needs to know the information: 100 - 150 words
 Follow up on the risk assessment: 100 - 150 words.

Planned review date/period with As per the policy of company risk assessment should be reviewed at least every 1 year so therefore
reasoning I set a review date on 1/10/2022 and I will make sure that this will review before the date if any
changes in plant and machinery, Standards that will effects and any changes in shift pattern.
How the risk assessment findings will be I will arrange meeting with the technical persons and management staffs including Project
communicated AND who you need to tell Manager, Site manager, managing director, Finance Manager and HR and will conduct safety
meetings regularly to discuss on risk assessment and control measures. The findings of these
meetings will be communicated to all the employees related to this Risk assessment through emails
sent from HR office. The risk assessment findings will be displayed at all the notice boards.
Projector screens will be set at office and site office to display the risk assessment. The posters will
be printed and displayed at site including bulletin boards. Other than these, the printed copies of
risk assessment will be given to the key persons involved with this project.
How you will follow up on the risk I will set Google alarms prior to completion date of each action. I will be highlight on every day in
assessment to check that the actions our daily work planning meeting which is happing in our site along with site team, there I will remind
have been carried out to every concern person and get update of actions progress. We will also discuss together and try
to get resolve issues if any difficulties during completion of each actions. I will also prepare one
action tracker to each action along with time scale and responsibility person name and display in
site notice board. I will also remind to every responsible person through emails and site social
media groups. Before target date I will be arrange one special meeting with all responsible person
along with project in-charge and get know what is the exact status and if there is any difficulties for
completion or delaying of action then that action will be referred to managing director by the finance
manager, and request them solve the issue within target date.

Learner number: 00617718 Learner name: Muhid Majid Bade Page 17 of 17