3.3.1 Controlled switches control are possible from BCU, HMI or SCADA
Station. Due to different control levels the system has to prove the
Control Authority before starting this test. If Control Authority is not
given to the place of activation, the command must be blocked.
Switching of the relevant switch will be displayed on event list.
3.3.2 Interlocking has to be checked for all switching devices (Circuit
Breakers, Isolators and Earthing switches) for the respective Bay.
Control of switchgear devices is only possible if all interlocking
conditions are fulfilled. Interlocking conditions are shown in FBD
Diagrams or Interlocking matrix printed from the BCU configuration
software.
3.3.3 All tests will be documented bay-wise. Any deviation from the
written logic will lead to failure of the operation. The software
interlocking bypass functionality is given by key switch Software
DE-Interlock (Normal/Interlocking OFF) on BCU. The software
interlocking could be bypassed in case of BCU Local control only.
Interlocking bypass is also possible from local control cubicle when
bay mode is in Emergency.
3.3.4 Before starting this test it is necessary to have print out of FBD or
Interlocking matrix of interlocking used in the IED from the Relay
configuration Software.
3.3.5 The hardware interlocking test and scheme check of wiring should
be finished before starting software interlocking test.
3.3.6 The indication of the SWITCH whose interlocking is to be checked
has be checked on SAS HMI and BCU before starting the software
interlocking test.
Archiving System Website: http://AMAS TP-NG-6250-001-007
NATIONAL GRID SA
Note:
132KV BB Maintenance Earth Switch is to be controlled from LCC/BCU & HMI
not from CRCC.
380KV BB Maintenance Earth Switch is to be controlled only from LCC/BCU not
from HMI/CRCC.
132KV & 380KV CB Service is only possible from HMI & CRCC.
132KV & 380KV CB Test position is possible from LCC/BCU/HMI.
13.8KV CB can be closed in service position from Mimic, BCU, HMI and
CRCC/QRCC.
4.0 EFERENCES
This document shall comply in accordance with the existing Company’s Rules and Regulations.
Any modifications therein found not conformance with the document shall be declared invalid.
For clarification and verification on this document, contact the following:
Substation
Bay
Feeder
DeviceType Serial No
2.0 BCU Control and Monitoring Test in Local and Remote mode
All bay related tests will be checked and documented for each feeder and
equipment separately according with approved Signal List. Control of substation
shall be affected from the interlocking conditions and detailed bay display
diagrams.
Furthermore the displays and handling BCU will be checked and for command
execution some faults will be simulated (e.g. Control authority, CMD interlocked,
CMD Monitoring time).
Not
Command Checked N.A Remarks
Checked
-Circuit Breaker
Control and Display at BCU
Control and Display at HMI
Control and Display at
Simulator of Gateway
__________________ __________________
Date Date
Commissioning Services Department
Not
Checke
Command Checke N.A Remarks
d
d
- Busbar 1 Disconnector
Control and Display at
BCU
Control and Display at
HMI
Control and Display at
Simulator of Gateway
- Busbar 2 Disconnector
Control and Display at
BCU
Control and Display at
HMI
Control and Display at
Simulator of Gateway
- Line Disconnector
Control and Display at
BCU
Control and Display at
HMI
Control and Display at
Simulator of Gateway
- VT Disconnector
Display at BCU (only
position indication)
Display at HMI (only
position indication)
Display at at Simulator of
Gateway (only position
indication)
__________________ __________________
Date Date
Commissioning Services Department
Not
Command Checked N.A. Remarks
Checked
Display at HMI
- High Speed Earthling Switch
Control and Display at BCU
Display at HMI
Note:
1.132KV BB Maintenance Earth Switch is to be controlled from LCC/BCU & HMI not from
CRCC.
2. 380KV BB Maintenance Earth Switch is to be controlled only from LCC/BCU not from
HMI/CRCC.
3. 132KV & 380KV CB Service is only possible from HMI & CRCC.
4. 132KV & 380KV CB Test position is possible from LCC/BCU/HMI.
1. Synchrocheck function
All CB controls have a synchrocheck function implemented in the bay controller (in case of
control from BCU, HMI or Control Center). Synchrocheck routine is as follows:
Close command is given to the BCU. The unit checks the sync – conditions (Vdiff, fdiff,
angel) and closes the breaker if these conditions are fulfilled.
Bypass of synchrocheck is not possible from BCU.
Bypass of synchrocheck is possible from HMI.
Not
Command/Synchrocheck Function Checked N.A. Remarks
Checked
Closing of Circuit Breaker is possible for:
Dead line – dead bus
Live line – dead bus
Dead line – live bus
__________________ __________________
Date Date
Commissioning Services Department
Not
Check
Parameter Setting Measured Chec N.A. Remarks
ed
ked
Min. voltage limit Umin
Max. voltage limit Umax
Threshold without voltage
Maximum duration of
Synchronism-check
Max. Voltage difference
Max. frequency difference
Max. angle difference
Not
Command/Synchrocheck Function Checked Checke N.A. Remarks
d
Closing of Circuit Breaker is possible for:
Dead line – dead bus
Live line – dead bus
Dead line – live bus
Live line – live bus with fulfilled
__________________ __________________
Date Date
Commissioning Services Department
Not
Parameter Setting Measured Checked Check N.A. Remarks
ed
Min. voltage limit Umin
Max. voltage limit Umax
Threshold without voltage
Maximum duration of
Synchronism-check
Max. Voltage difference
Max. frequency difference
Max. angle difference
Interlocking has to be checked for all switching devices (Circuit Breakers, Isolators
and Earthing switches) for the respective feeder. Control of switchgear devices is
only possible if all interlocking conditions are fulfilled. Interlocking conditions are
shown in schematic diagrams of local control cubicles.
During testing Bay Interlocking and Switchgear Interlocking will be checked. All
tests will be documented bay-wise. Any deviation from the written logic will lead to
failure of the operation.
__________________ __________________
Date Date
Commissioning Services Department
__________________ __________________
Date Date
Commissioning Services Department
__________________ __________________
Date Date