Spring 2021 Lecture 1 & 2
Spring 2021 Lecture 1 & 2
2
• Formulation
3
• Graphical Solution
4 • Simplex
• Transportation
5
6
• Assignment
7
• Excel Solver
Grading Policy
• Assignments 13.33%
• Mid-term exam 20%
• Final exam 66.67%
Text and Reference Books
• Hamdy A. Taha, • Fredrik S. Hillier,
“Operations "Introduction to
Research : An Operations
Introduction”, Eighth Research,"
Seventh
Edition, Prentice
Hall, 2007. Edition, McGraw-
Hill, 2001.
Course Content
Topic
Week
Lecture 1 Lecture 2
17th Oct. Introduction & Formulation Formulation Exercises
24th Oct. Compact Formulation Graphical Solution
31th Oct. Graphical Solution Exercises Simplex method
7th Nov. Simplex method Exercises The big-M method (M-
technique)
14th Nov. The Two phase method Exam formulas
12th Dec. Transportation Transportation Exercises
19th Dec. Assignment Model Assignment Model Exercises
26th Dec. Excel solver
9th Jan. Excel Exam
Course Objectives
Students will be aware of the following :
• Linear programming application in
operations management,
21
◼ The decision variables are
• T = number of tables to be produced per
week
• C = number of chairs to be produced per
week
◼ The objective is to
• Maximize profit
◼ The constraints are
1. The hours of carpentry time used cannot
exceed 240 hours per week
2. The hours of painting and varnishing
time used cannot exceed 100 hours per
week
◼ The LP objective function:
• Maximize profit = $70T + $50C
◼ Develop mathematical relationships
for the two constraints
◼ For carpentry, total time used is
• (4 hours per table)(Number of
tables produced)
• + (3 hours per chair)(Number of
chairs produced)
◼ We know that
• Carpentry time used ≤ Carpentry
time available 4T + 3C ≤ 240
(hours of carpentry time)
Holiday Meal Turkey Ranch
Production Quantity
A company makes two products (say, P and Q) using two
machines (say, A and B). Each unit of P that is produced
requires 50 minutes processing time on machine A and
30 minutes processing time on machine B. Each unit of
Q that is produced requires 24 minutes processing time
on machine A and 33 minutes processing time on
machine B. Machine A is going to be available for 40
hours and machine B is available for 35 hours. The
profit per unit of P is $25 and the profit per unit of Q is
$30. Company policy is to determine the production
quantity of each product in such a way as to maximize
the total profit given that the available resources should
not be exceeded
Paint Factory Production
QUESTIONS?