18 ABC Backflushed X 2
18 ABC Backflushed X 2
18 ABC Backflushed X 2
II. Definition
Backflush costing or backflushing is a short-cut approach to accounting for the flow of
manufacturing operations. It delays recording journal entires until the goods moved through
the production process.
Activity-Based Costing
I. Introduction
Activity-based costing (ABC) has been popularized because of the rapid increase in the
automation of manufacturing process, which has led to a significant increase in the
incurrence of indirect costs and a consequent need for more accurate cost allocation.
Under the activity-based costing, as the name implies, costs are accumulated by activity
rather than by department or function for purposes of product costing.
II. Definition
ABC Costing is one means of refining a cost system to avoid what has been called
peanut-butter costing. Inaccurately averaging or spreading costs like peanut-butter over
products that use different amounts of resources results in a product-cost-cross-
subsidization.
Product-cost cross-subsidization describes the condition in which the miscasting of one
product causes the miscasting of other products.
In the Accounting Glossary of the Statements of Management Accounting. ABC was
defined as a system that:
1. Identifies the causal relationship between the incurrence of cost and activities
2. Determines the underlying driver of the activities
3. Established cost pools related to individual drivers
4. Develops costing rates
5. Applies cost to product on the basis of resources consumed (drivers)
III. Nature of Activity-Based Costing
In this costing system, cost drivers are identified and used as a basis for cost allocation.
Cost drivers are the factors that will contribute to increasing or decreasing costs. In
addition, under the activity-based costing approach, those activities that do not add
value to the product are reduced to the extent possible.
ABC determines the value-adding activities associated with the incurrence of costs and
then accumulates a cost pool for each activity using the appropriate activity base (cost
driver). Cost pools are then assigned to cost objects. ABC may be employed with job-
order or process-costing methods.
An Activity-Based Costing is a two stage allocation process traced to departments.
First, costs are trace to activities, and then to products.
MCQ - THEORY
1
. An accounting system that collects financial and operating data o the basis of the underlying
nature and extent of the cost drivers is
a. Activity-based costing. c. Delivery cycle time costing.
b. Target costing. d. Variable costing. Punzalan 2014
2
. Multiple or departmental manufacturing overhead rates are considered preferable to a single
or plant-wide overhead when
a. Manufacturing is limited to a single product flowing through identical departments in a
fixed sequence. Punzalan 2014
b. Various products are manufactured that do not pass through the same departments or
use the same manufacturing techniques.
c. Individual cost drivers cannot accurately be determined with respect to cause and effect
relationships.
d. The single or plant-wide rate is related to several identified cost drivers.
3
. Cost drivers are
a. Activities that causes costs to increase as the activity increases.
b. Accounting techniques used to control costs.
c. Accounting measurements used to evaluate whether performance is proceeding
according to plan.
d. A mechanical basis, such as machine hours, computer time, size of equipment, or
square footage of factory, used to assign costs to activities. Punzalan 2014
4
. A base used to allocate the cost of a resource to the different activities using that resource is
called.
a. Resource Driver c. Final cost driver
b. Activity Driver d. Driver Punzalan 2014
5
. A base used to allocate the cost of products, customer, or others final cost objects is called
a. Resource Driver c. Final cost driver
b. Activity Driver d. Driver Punzalan 2014
6
. Activity-based management (ABM) is Punzalan 2014
a. A costing system in which multiple overhead cost pools are allocated using bases that include
one or more non-volume related factors.
b. A base used to allocate the cost of a resource to the different activities using it.
c. The use of information obtained from ABC to make improvements in the firm
d. A base used to allocate the cost of an activity to products and customers.
ACTIVITY-BASED COSTING
Consumption Ratio
Questions 1 & 2 are based on the following: Dayag 2013
25
. Principal, Inc. produces three products. Production and cost information is as follows:
Model A Model B Model C
Units produced 2,000 6,000 12,000
Direct labor hours 4,000 2,000 4,000
Number of setups 100 150 250
The consumption ratios for number of setups would be:
A B C A B C
a. 40% 20% 40% c. 10% 30% 60%
b. 20% 30% 50% d. 5% 22% 73%
26
. Using the same information in No. 40, compute the consumption ratios based on units
produced would be:
A B C A B C
a. 40% 20% 40% c. 10% 30% 60%
b. 20% 30% 50% d. 5% 22% 73%
Activity Rates
Comprehensive
27
. Product 53 uses 200 hours of direct labor and has 2,000 machine steps. Kate Ong, the cost
accountant, has been considering using either direct labor hours or machine steps as the
cost driver. The ratio of overhead cost to direct labor hours is P60. The assignment of
overhead cost to Product 53 using direct labor hours would result in a higher charge by
P4,000 than if machine steps were used as the cost driver.
Determine the ratio of overhead cost to machine steps.
a. P6 c. P60
b. 2 d. 4 Dayag 2013
Applied Overhead
Labor-Related Overhead Cost
28
. Cebu Enterprises is a Philippine exporter of souvenir items manufactured in the capital city of
Jerusalem. The following overhead cost data have been accumulated:
Amount
Activity Center Cosf Driver of Activity Center Costs
Materials Handling Grams handled 100,000 grams P 50,000
Painting Units painted 50,000 units 200,000
Assembly Labor hours 4,000 hours 120,000
Job 1234 contains 3,000 units. It weighs 10,000 grams and uses 300 hours of labor.
Compute the total overhead costs that should be assigned to Job 1234.
a. P31,955 c. P26,000
b. 27,750 d. 32,000 Dayag 2013
Comprehensive
Questions 1 & 2 are based on the following: Dayag 2013
29
. UST Community Hospital has found itself under increasing pressure to be accountable for the
charges it assesses its patients. Its current pricing system is ad hoc, based on pricing norms
for the geographical area, and it only explicitly considers direct costs for surgery, medication,
and other treatments. UST's controller has suggested that the hospital try to improve its
pricing policies by seeking a tighter relationship between costs and pricing. This approach
would make prices for services less arbitrary. As a first step, the controller has determined
that most costs can be assigned to one of three cost pools. The three cost pools follow along
with the estimated amounts and activity drivers.
The hospital provides service in three broad categories. The services are listed below with
their volume measures for the activity centers.
Service Professional Hours Square Feet Number of Patients
Surgery 6,000 1,200 200
Housing patients 20,000 12,000 500
Outpatient care 4,000 1,800 300
Unit Cost
Questions 1 & 2 are based on the following: Dayag 2013
32
. Katherine Inc. of Cebu Ltd. has decided to institute a pilot activity-based costing project in its
five-person purchasing department. Annual departmental costs are P473,500. Because
finding the best supplier takes the majority of effort in the department, most of the costs are
allocated to this area.
Number of Total
Activity Allocation Measure People Cost
Find best suppliers Number of telephone calls 3 P300,000
Issue purchase orders Number of purchase orders 1 100,000
Review receiving reports Number of receiving reports 1 73,500
During the year, the purchasing department made 150,000 telephone calls, issued
10,000 purchase orders, and reviewed 7,000 receiving reports. Many purchase orders
are received in a single shipment.
One product manufactured by Cebu Ltd. required the following purchasing department
activities: 125 telephone calls, 60 purchase orders, and 15 receipts.
What amount of purchasing department cost should be assigned to the product?
a. P1,007.50 c. P921.48
b. 4,500.00 d. 327.55
Comprehensive
Activity Rate, Unit Cost
Questions 1 & 2 are based on the following: Dayag 2013
36
. Ongchan Metal Fabricators has a diverse product line and a complex cost structure, with
some jobs requiring much labor and little machine use and others requiring the opposite mix.
Because no single base for a predetermined overhead rate will provide Ongchan Metal
management with reliable product cost information, overhead is classified into two cost pools
and two predetermined overhead rates are used. For 2001, it is estimated that total overhead
costs will consist of P200,000 of overhead related to the usage of direct labor hours and
P300,000 of overhead related to machine usage. Total machine usage is expected to be
4,000 hours for the year, and total direct labor hours are expected to be 16,000.
Job 345 required P2,000 of direct material, 30 hours of labor at P10 per hour, and 10
hours of machine time.
Determine the dual predetermined overhead rates:
Per Direct Labor Hour Per Machine Hour
a. P 3.75 P75.00
b. 375.00 7.50
c. 12.50 12.50
d. 12.50 75.00
37
. Using the same information in No. 1, compute the cost of Job 345:
a. P2,300.00 c. P3,425.00
b. 3,162.50 d. 5,800.00
P280,000
The following information was collected on three jobs that were completed during the year:
Side A Side B
a. P46.97 P48.65
b. 43.06 44.59
c. 20.18 24.77
d. 20.00 25.00
Product A Product B
Units produced 2,000 1,000
Total direct labor hours 5,000 20,000
Set-up cost per batch PI,000 P2,000
Batch size 100 50
Total set-up cost incurred P20,000 P40,000
Direct labor hour per unit 2 1
A traditional costing system would allocate setup costs on the basis of direct labor hours. An
ABC system would trace costs by spreading the cost per batch over the units in a batch.
What is the setup cost per unit of Product A under each costing system.
Traditional Costing ABC
A. P 4.80 P 10
B. P 2.40 P 10
C. P40.00 P200
D. P4.80 P 20 Guerrero 2013
following:
Model X Model Y
Units produced 100 200
Material moves 10 40
Direct labor hours per unit 1 2
Materials handling costs total PI00,000. Under ABC, the materials handling costs allocated to
each unit of Model would be:
Model X Model Y Model X Model Y
a. P400 P200 c. P143 P429
b. 200 400 d. 429 143
50
. Using the same information in No. 1, except that direct labor hours (traditional / conventional)
were used to allocate overhead costs. The material handling costs allocated to each unit of
Model would be (assuming that 2 DLH per unit for Model Y):
Wall Specialty
Mirrors Windows
Units produced 25 25
Material moves per product line 5 15
Direct labor hours per unit 200 200
Budgeted materials handling costs. P50,000
Under a costing system that allocates overhead on the basis of direct labor hours (traditional),
the materials handling costs allocated to one unit of wall mirrors would be
a. P1,000 c. P2,000
b. 500 d. 5,000
52
. Using the same information in No. 1, the materials handling costs allocated to one unit of wall
mirrors under Activity-Based Costing would be:
a. P1,000 c. P1,500
b. 500 d. 2,500
Wall Specialty
Mirrors Windows
Units produced 25 25
Material moves per product line 5 15
Direct labor hours per unit 200 200
Budgeted materials handling costs P50,000
53
. Under a costing system that allocates overhead on the basis of direct labor hours (traditional),
the materials handling costs allocated to one unit of wall mirrors Would be
a. P1,000 c. P2,000
b. P500 d. P5,000
54
. Under activity based costing (ABC), what is the materials handling costs allocated to one unit
of wall mirrors?
a. P1,000 c. P1,500
b. P500 d. P2,500
Comprehensive
Questions 1 thru 4 are based on the following: Dayag 2013
55
. Ambrose Company uses three products with the following production and cost information:
Overhead costs include setups of P45,000; shipping cost of P70,000; and engineering
costs of P90,000. What would be the per unit overhead cost for each model if direct
labor hours (traditional/conventional costing) were the allocation base?
Model S Model M Model S Model M.
Quantity for
Activity Cost Driver Cost Rates Satin Sheen
Income
material
inspection Type of material P11.50 per type 12 types
In-process
Inspection Number of units P0.14 per unit 17,500 units
Product
Certification Per order P77 per order 25 orders
The monthly quality control cost assigned to Satin Sheen makeup using activity-based
costing is
a. P88.64 per order.
b. P525.50 lower than the cost using the traditional system.
c. P8,500.50
d. P525.50 higher than the cost using the traditional system. Dayag 2013
Cost, sales, and production data for one of the organization's products for the coming year
are as follows:
Prime costs:
Direct material cost per unit P4.40
Direct labor cost per unit
.05 DLH @ P15.00/DLH 75
Total prime cost P5.15
What is the monthly quality control assigned to product X using the ABC?
a. P686.40 per order.
b. P5,255 higher than the traditional costing system.
c. P8 5,000
d. P5,255 lower than the traditional costing system. Guerrero 2013
66
. The Manila Company manufactures and sells packaging machines. It recently used an
activity-based approach to refine the job costing system at its Bulacan plant. The resulting job
costing system has one direct-cost category (direct materials) and four indirect manufacturing
cost pools. These four indirect cost pools and their allocation bases are:
machine has direct material costs of P3,000 requires 50 component parts, 12 machine-hours,
15 assembly-hours, and 4 inspection hours. Manila Company's previous costing system had
one direct-cost category (direct materials) and one indirect-cost category (manufacturing
overhead allocated at the rate of PI00 per assembly-hour). In comparison to the traditional
costing system used by Manila Company, the total manufacturing cost of the machines sold
under the ABC is:
a. P114,850 higher c. P114,950 higher
b. P141,850 lower d. Equal Guerrero 2013
BACKFLUSHING
RIP to Finished Goods
68
. The Pampanga Manufacturing Company uses a raw and in process (RIP) inventory account
and expenses all conversion costs to the cost of goods sold account. At the end of each
month, all inventories are counted, their conversion cost components are estimated, and
inventory account balances are adjusted accordingly. Raw material cost is backflushed from
RIP to Finished Goods. The following information is for the month of April:
Beginning balance of RIP account, including P1,400
of conversion cost P 31,000
Raw materials received on credit 367,000
Ending RIP inventory per physical count, including
P1,800 conversion cost estimate 33,000
Compute the amount to be backflushed from RIP to Finished goods:
a. P365,000 c. P367,000
b. 368,600 d. 365,400 Dayag 2013
69
. The Backflushers Manufacturing Corp. uses a Raw and In Process inventory account and
expenses all conversion costs to the cost of goods sold account. At the end each month, all
inventories are counted, their conversion cost components are estimated and inventory
account balances are adjusted accordingly. Raw material cost is backflushed from RIP to
finished goods. The following information is for the month of May:
Raw and In Process inventory account, May 1, including
P500 of conversion cost P 5,000
Raw materials received during May (50% down, balance in
four installments) 100,000
Raw and In Process inventory account, May 31, including
P650 of estimated conversion cost 5,250
What is the amount to be backflushed from RIP to finished goods?
a. 90,900 c. 104,500
b. 99,900 d. 109,100 Punzalan 2014
70
. Cheeta Co. has materials cost in the June 1 Raw and In Process (RIP) of PI0,000 materials
received during the month of June of P205,000 and materials cost in the June 30 Raw and In
Process (RIP) of P 12,500. What would be the amount to be backflushed from RIP to
Finished Goods at the end of June?
a. 215,000 c. 207,500
b. 202,500 d. 217,500 Punzalan 2014
71
. The Hudy Manufacturing Company uses a Raw and In Process (RIP) inventory account and
expensed all conversion costs to the cost of goods sold account. At the end of each month,
all inventories are counted, their conversion cost components are estimated, and inventory
account balances are adjusted accordingly. Raw material cost is backflushed from RIP to
finished Goods. The following information is for the month of April:
Beginning balance of RIP account, including PI,400 .
of conversion cost P 31,000
Raw materials received on credit 367,000
Ending RIP inventory per physical count, including
P1,800 conversion cost estimate 33,000
What is the amount of materials used to be backflushed from RIP to finished goods?
a. P365,000 c. P367,000
b. P368,600 d. P365,400 Guerrero 2013
72
. The Futaba Manufacturing Company uses a Raw and In Process (RIP) inventory account. At
the end of each month, all inventories are counted, their conversion costs components are
estimated, and inventory account balances are adjusted accodingly. Raw materials cost is
backflushed form RIP account to Finished Goods account. The following data is for the month
of August:
RIP Account
74
. The Love Company seeks to streamline the costing system at its Manila plant, it will use a
backflush costing system with three trigger points:
Purchase of raw materials
Completion of finished goods
Sale of finished goods
There are no beginning inventories. The following data pertain to April 2013:
Raw materials purchased P880,000
Raw materials used 850,000
Conversion costs incurred 422,000
Conversion allocated to finished goods 400,000
Costs transferred to finished goods 1,250,000
Pit Shop's standard cost per unit of telephone in June are direct materials, P26; and
conversion costs, PI5. The following data apply to June production:
Raw materials purchased P5,300,000
Conversion costs incurred 3,080,000
Number of finished units manufactured 200,000
Number of finished units sold 192,000
The balances of Raw and In Process and Cost of Goods Sold accounts at the end of June
are:
a. P308,000 and P7,872,000 respectively
b. P5,300,000 and P7,872,000 respectively
c. P308,000 and P4,992,000 respectively
d. P4,992,000 and P2,880,000 respectively Guerrero 2013
The balances of Raw and in Process and Finished Goods inventory accounts at the end of
May are:
A. P25,000 and P945,000 respectively
B. P550,000 and P45,000 respectively
C. P25,000 and P45,000 respectively
D. P550,000 and P945,000 respectively Guerrero 2013
Comprehensive
Questions 1 & 2 are based on the following: Dayag 2013
81
. The Bulacan Manufacturing Company produces only for customer order and most work is
shipped within thirty-six hours of the receipt of an order. Bulacan uses a raw and in process
(RIP) inventory account and expenses all conversion costs to the cost of goods sold account.
Work is shipped immediately upon completion, so there is no finished goods account. At the
end of each month, inventory is counted, its conversion cost component is estimated, and the
RIP account balance is adjusted accodingly. Raw material cost is backflushed from RIP to
Cost of Goods Sold. The following information is for the month of May:
82
. Using the same information in No. 2, compute the amount of Cost of Goods Sold after all
transactions and adjustments were made:
a. P246,000 c. P247,000
b. 246,200 d. 245,000
Determined the October 31 balance in the Cost of Goods Sold account. No adjustment has
been made for overapplied or underapplied conversion cost.
a. P1,300,000 c. P1,600,000
b. 1,495,000 d. 1,195,000
86
. Using the same information in No. 1, what was the overapplied or underapplied conversion
costs for the month?
a. P305,000 overapplied c. P105,000 overapplied
b. 195,000 underapplied d. 105,000 underapplied
87
. Using the same information in Nos. 1 and 2, what is the Cost of Goods Sold after all
transactions-adjustments have been completed?
a. P1,304,000 c. P1,600,000
b. 1,495,000 d. 1,195,000
Determine the September 30 balance in the cost of goods sold amount. No adjustment
has been made for overapplied or underapplied converison cost:
a. P266,000 c. P221,000
b. 276,000 d. 220,000
89
. Using the same information in No. 1, what was the overapplied or underapplied conversion
costs for the month?
a. P16,000 overapplied c. P10,000 underapplied
JUST-IN-TIME
Throughput Time
98
. A company has 500 units production per day and 2,000 units are in process at any time.
What is the throughput time?
a. 1/2day c. Two days
b. 1/4day d. Four days Punzalan 2014
a. 1,250 c. 6,250
b. 31,250 d. 125 Punzalan 2014
101
. Atlas Co. has 10 work stations where work in process is held, 100 average units in work in
process per station, an average cost of a unit in work in process of P75, and annual inventory
carrying cost of 20%. If Atlas plans a 50% reduction in work in process levels, what would be
the expected annual savings in carrying costs?
a. 37,500 c. 30,000
b. 15,000 d. 7,500 Punzalan 2014
102
. A company has an annual carrying cost percentage of 30% and average work in process of
P300,000. The management plans to use Just-In-Time production system to double the
velocity of work in process without changing total annual output. What would be the savings
in annual carrying costs?
a. 90,000 c. 150,000
b. 45,000 d. 180,000 Punzalan 2014
ANSWER KEY
1.A 26.C 51.A 76.C 101.D
2.B 27.D 52.B 77.A 102.B
3.A 28.C 53.A 78.D
4.A 29.C 54.B 79.A
5.B 30.D 55.D 80.B
6.C 31.A 56.B 81.C
7.D 32.A 57.A 82.B
8.A 33.B 58.A 83.C
9.C 34.D 59.C 84.B
10.D 35.D 60.C 85.C
11.D 36.D 61.B 86.C
12.A 37.C 62.D 87.B
13.D 38.A 63.C 88.A
14.A 39.B 64.D 89.C
15.B 40.A 65.B 90.C
16.A 41.A 66.A 91.D
17.A 42.A 67.B 92.C
18.B 43.B 68.D 93.C
19.C 44.A 69.B 94.C
20.D 45.D 70.B 95.B
21.C 46.D 71.D 96.C
22.B 47.C 72.C 97.C
23.D 48.A 73.C 98.D
24.D 49.B 74.A 99.A
25.B 50.C 75.A 100.B
SOLUTIONS
Multiple rates are appropriate when a process differs substantially among departments or when products do not go
through all departments or all processes. The trend in cost accounting is toward activity-based costing, which divides
production into numerous activities and attempts to identify the driver/s most relevant to each. A driver is a factor that
causes changes in a cost. Thus, activity-based costing emphasizes cost assignment based on trading rather than
allocation. The result is a more accurate assignment of costs
3
.Suggested answer (a)
A cost driver is a measure of activity, such as direct labor hours, machine hours, beds occupied, computer time used,
flight hours, etc., that is causal factor in the incurrence of cost to an entity. It is a basis used to assign costs to cost
objects.
4
.Suggested answer (a) resource driver
The name resources driver is new, but the idea is not. For example, most traditional accounting system allocate some
plant-wide costs to departments based on each department's allocation bases like the number of employees or square
footage occupied. If an ABC system allocates the cost of a resource to several activities based on the square footage
or number of employees devoted to each activity, then square footage and the number of employees are called
resource drivers.
5
.Suggested answer (b) activity driver
An activity driver is a base used to allocate the cost of an activity to products, customers, or other final cost objects.
The word final refers to the last step in cost allocation. The nature and variety of activity drivers is what distinguishes
ABC from traditional costing.
6
.Suggested answer (c) the use of information obtained from ABC to make improvements in the firm
Activity-based management is a detailed analysis of activities and expenses created by those activities used as a basis
for controlling and improving efficiency or the use of information obtained from activity-based costing to make
improvement in a firm.
7
.Suggested answer (d) Increase, Increase
In an activity-based cost system, cost assignment is more precise than in traditional cost system, because activities
rather than functions or departments are defined as cost objects. This structure permits assignment to more cost pools
and the identification of a driver specifically related to each.. A driver is a factor that causes a change in a cost. Thus an
activity based cost system uses more cost pools and cost assignment bases than a traditional system
8
.Suggested answer (d) Increase, Increase
In an activity-based cost system, cost assignment is more precise than in traditional cost system, because activities
rather than functions or departments are defined as cost objects. This structure permits assignment to more cost pools
and the identification of a driver specifically related to each.. A driver is a factor that causes a change in a cost. Thus an
activity based cost system uses more cost pools and cost assignment bases than a traditional system
9
.Suggested answer (c) No, Yes
An ABC system determines activities associated with the incurrence of costs and then accumulates a cost pools for
each activity. It identifies the driver/s used to trace those costs to such cost object as products or services. A driver is a
factor that causes a change in a cost. Activities that do not add value are identified arid eliminated to the extent
possible. However, all drivers cannot be eliminated.
10
.Suggested answer (d) Raw materials storage activity
ABC assign costs more precisely than traditional cost system because cost pools are accumulated for activities rather
than functions or departments. This structure permits assignment to more cost pools and the identification of the
driver/s used to reassign costs to cost objects. Analysis by activity also provides for better cost control, because of
identification of nonvalue activities. For example, raw materials storage may be greatly reduced or eliminated in a JIT
system without affecting customer value.
11
.Suggested answer (d) high quality and balanced work loads
Just in time is a philosophy centered on the reduction of costs through elimination of inventory. Elimination of
inventories eliminates storage and carrying costs, however, it also eliminates the cushion against production errors and
imbalances that inventories provide. As a result, high quality and balanced work loads are required in a JIT system to
avoid costly shutdowns and customer ill will. Because of the need for quality and balanced production, JIT has come to
be closely identified with efforts to eliminate waste in all its forms, and thus it is an important part of many total quality
management (TQM) efforts.
12
.Suggested answer (a) backflush production
The most visible aspect of JIT is the effort to reduce inventories of work in process and raw materials. Most writing on
JIT concentrate on this one aspect, which is called stockless production, lean production, or zero inventory production.
While backflush costing is an abbreviated approach to accounting for the flow of manufacturing costs, which is
applicable to mature JIT system in which velocity is too high that traditional accounting is impractical.
13
.Suggested answer (d) Cost of goods sold
In backflush costing, direct labor and overhead costs are expensed to the cost of goods sold account. The estimated
conversion cost components of the RIP and finished goods inventory account balances are adjusted at the end of each
month, with the offsetting entry representing a correction of cost of goods sold. If conversion cost increased during the
month, cost of goods sold is credited; however, when conversion cost decreased, cost of goods sold is debited.
14
.(a)
A cost allocation base is the common denominator for systematically correlating indirect costs and a cost object. The
cost driver of the indirect costs is ordinarily the allocation base. In a homogeneous cost pool, all costs should have the
same or a similar cause and-effect relationship with the cost allocation base.
15
.(b)
Multiple rates are appropriate when a process differs substantially among departments or when products do not go
through all departments or all processes. The trend in cost accounting is toward activity-based costing, which divides
production into numerous activities and identifies the cost driver(s) most relevant to each. The result is a more accurate
assignment of costs.
Answer (a) is incorrect because one rate may be cost beneficial when a single product proceeds through
homogeneous processes. Answer (c) is incorrect because individual cost drivers for all relationships must be known to
use multiple application rates. Answer
(d) is incorrect because, if one rate is related to several cost drivers, it can be used as a surrogate for multiple rates.
16
.(a)
An activity-based costing (ABC) system identifies the causal relationship between the incurrence of costs and activities,
determines the cost driver for each activity, and applies costs to products on the basis of resources (drivers)
consumed.
Answer (b) is incorrect because target costing determines the maximum allowable cost of a product before the product
is designed or produced: it deducts an acceptable profit margin from a forecasted selling price. Answer (c) is incorrect
because cycle time is the period from the time a customer places an order to the time that product is delivered. Answer
(d) is incorrect because variable costing expenses fixed factory overhead as incurred.
17
.(a)
A cost driver is "a measure of activity, such as direct labor hours, machine hours, beds occupied, computer time used,
flight hours, miles driven, or contracts, that is a causal factor in the incurrence of cost to an entity." It is a basis used to
assign costs to cost objects.
Answer (b) is incorrect because cost drivers are not controls. Answer (c) is incorrect because cost drivers are
measures of activities that cause costs. Answer (d) is incorrect because, although cost drivers may be used to assign
costs, they are not necessarily mechanical. For example, a cost driver for pension benefits is employee salaries.
18
.(b)
A%C determines the activities associated with the incurrence of costs and then accumulates a cost pool for each
activity using the appropriate activity base (cost driver). However, given one product, all costs are assigned to the one
product; the particular method used to allocate the costs does not matter.
Answer (a) is incorrect because marketing and distribution costs should be allocated to specific products. Answer (c) is
incorrect because, by definition, a cost driver is a factor that affects (drives) the incurrence of a cost. Answer (d) is
incorrect because product-cost-cross-subsidization occurs when products are miscosted. The more accurate cost
allocation provided by ABC minimizes the subsidy received by undercosted products at the expense of overcosted
products.
19
.(C)
Given the automation of factories and the corresponding emphasis on ABC, plantwide application rates are being used
less often because better information can be provided at reasonable cost. ABC results in a more accurate application
of indirect costs because it provides more refined data. Instead of a single cost pool for a process, a department, or an
entire plant, an indirect cost pool is established for each identified activity. The related cost driver, the factor that
changes the cost of the activity, is also identified.
Answer (a) is incorrect because one effect of automation is a decrease in direct labor usage. Thus, some companies
no longer track direct labor costs closely. They treat direct labor as a factory overhead cost. Answer (b) is incorrect
because throughout is the rate of production over a stated time. It clearly drives (influences) costs. Answer (d) is
incorrect because multiple cost pools permit a better allocation of indirect costs to cost objects.
20
.(d)
In an ABC system, cost allocation is more precise than in traditional systems because activities rather than functions or
departments are defined as cost objects. This structure permits allocation to more cost pools and the identification of a
cost driver specifically related to each. A cost driver is a factor that causes a change in the cost pool for a particular
activity. Thus, an ABC system uses more cost pools and allocation bases than a traditional system.
Answer (a), (b), and (c) are incorrect because the numbers of cost pools and allocation bases increase.
21
.(c)
An ABC system determines activities associated with the incurrence of costs and then accumulates a cost pool for
each activity. It then identifies the cost driver for each activity. A cost driver is a factor that causes a change in the cost
pool for a particular cost object. Activities that do not add customer value are identified and eliminated to the extent
possible. A clear understanding of what causes a cost (the cost driver) helps eliminate the non-value-adding activities.
However, all cost drivers cannot be eliminated.
Answer (a),(b), and (d) are incorrect because non value-adding activities are
unnecessary and therefore are eliminated, but not all cost drivers are eliminated.
22
.(b)
A%C identifies the causal relationship between costs and activities, determines the drivers of the activities, establishes
cost pools related to individual drivers, develops costing rates, and applies cost to products on the basis of resources
consumed (drivers). The relationship between the number of components in a finished product and materials handling
costs is direct and causal.
Answer (a) is incorrect because the number of production runs per year does not provide individual unit costs. Answer
(c)\ is incorrect because the time to produce one unit is traditionally used to allocate overhead to units produced in a
labor-intensive process. Answer (d) is incorrect because overhead applied to each completed unit is the result of, not a
basis for, allocation.
23
.(d)
ABC allocates costs more precisely than traditional systems because cost pools are accumulated for activities rather
than functions or departments. This structure permits allocation to more cost pools and the identification of a cost driver
specifically related to each. Analysis by activity also provides for better cost control because of identification of
nonvalue-adding activities. For example, raw materials storage may be greatly reduced or eliminated in a JIT system
without affecting customer value.
Answers (a), (b), and (c) are incorrect because design engineering activity, heat treatment activity, and drill press activity add
value to products in the production process.
24
.(d)
25
.(b)
Ratios based on set-up:
Model A:100- (100+ 150 + 250)20%
Model B:150 + (100 + 150 + 250) 30%
Model C: 250 - (100 + 150 + 250) 50%
26
(c)
Ratios based on units produced:
Model A: 2,000 * (2,000 + 6,000 + 12,000) 10%
Model B:' 6,000 + (2,000 + 6,000 + 12,000) 30%
Model C: 12,000 + (2,000 + 6,000 + 12,000) 60%
27
.(d)
Overhead charge using labor hours: P60 x 200 P12,000
Overhead charge using machine hours: P12,000 - P4,000 P 8,000
Ratio of overhead costs to machine steps
P8,000/2,000 P4/step
28
.(c)
Cost Assignment:
Materials Handling: (P50,000 * 100,000) x 10,000 P5,000
Painting: (P200,000 + 50,000) x 3,000 12,000
Assembly: (P120,000 + 4,000) x 300 9,000
P26,000
29
.(c)
Professional Salaries: P900,000 4- 30,000 P 30 per hour
Building Costs: P450,000 + 15,000 P 30 per sq. ft.
Risk Management: P320,000 * 1,000 P320 perpatient (c)
30
.(d)
Surgery: (6,000 x P30) + (1,200 x P30) + (200 x P320) P280,000
Housing: (20,000 x P30) + (12,000 x P30) + (500 x P320) P1,120,000
Outpatient Case: (4,000 x P30) + (1,800 x P30) + (300 x P320) P270,000
31
.Overhead Rates:
Per Machine Hour: P900,000/3,600 machine hours 250
32
.(a)
Calls: P300,000 * 150,000 calls P2 per call
Purchase Orders: PI 00,000 -f-10,000 purchase orders P10per
Reports: P73,500 -=- 7,000 receiving reports P10.50perR.R.
Cost Assignment:
125 calls x P2 per call P250.00
60 purchase orders x P10 per p.o 600.00
15 receiving report x P10.50 per R.R 157.50
Total costs P1,007.50
33
.(b)
Amount of purchasing department costs P1,007.50
Divided by: No. of units 200
P5.04/unit
34
.Overhead rates:
Material handling (P720.000 +6,000,000 parts) P0.12
Setupcosts(P315,000/750setups) 420
Machining costs (P540,000 * 30,000 hours) 18.00
Quality control (P225,000 + 500batches) 450
Overhead costs:
College chair:
Direct materials P25,000
Direct labor (500 x P20) 10,000
Overhead:
Material handling (3,500 x P0.25) 875
Cutting (3,500 xP2.50) 8,750
Assembly (500 x P25) 12,500 22,125
Total cost P57,125
Units produced -100
Unit cost P571.25
36
.(d)
Per Direct Labor Hour: P200,000 / 16,000 DL hours P12.50
Per Machine Hour: P300,000 / 4,000 machine hours P75.00
37
.(c)
Job # 345:
Direct Materials P2,000
Direct Labor (30 x PI0) 300
Applied Overhead: [(30 x PI2.50) + (10 x P75)] 1,125
P3,425
38
.(a)
Per Machine Hour: P900,000/3,600 machine hours P250
Per Setup: P525,000/300 setups P1,750
39
.(b)
Job# 103:
Parts and Materials P56,000
Applied Overhead [(70 x P250) + (4 x PI ,750)] 24,500
P80,500
40
(a)
A&C allocates overhead costs more precisely than traditional methods. It identifies the activities associated with the
incurrence of costs, determines the cost driver for each activity, and allocates cost accordingly. Thus me cost per setup
is P100 (P20,000 + 200), per inspection P20 (PI30,000 +6,500), per material move P10 (P80.000 +8,000), and per
engineering hour P50 (P50,000 + 1,000). The overhead allocated to Job 101 is thereforeP 1,300 {(1 setup x P100) +
(20 inspections x P20] + (30 material moves x P10) + (10 enginering hours x P50)].
Answers (b) is incorect because P2,000 equals the overhead allocation for Job 103. Answer (c) is incorrect because
P5.000 equals the allocation of overhead using direct materials cost as a base. Answer (d) is incorrect because P5.600
equals 2% (2,000 DL cost + P 100,000 budgeted annual DL cost) of budgeted overhead.
41
.(a)
The overhead costs for the activities are PI00 per setup, P20 per inspection, P10. per material move, and P50 per
engineering hour. Thus, overhead allocated to Job 102 is P3.000 [(2 setups x P100) + (10 inspections x P20) + (10
material moves x P10) + (50 engineering hours x P50)}. The production cost of Job 102 is P17.000 (P12,000 DM +
P2.000 DL + P3.000 OH), and the cost per unit is P340 (P17,000 + 50).
Answer (b) is incorrect because P392 assumes overhead is allocated based on direct labor cost. Answer (c) is
incorrect because P440 assumes an overhead allocation of P8.000. Answer (d) is incorrect because P520 assumes
overhead is allocated based on direct materials cost.
42
.(a)
The costs per job for the activities are P100 per setup, P20 per inspection, P10 per material move, and P50 per
engineering hour. Overhead allocated to Job 103 is P2.000 [(4 setups x P100) + (30 inspections x P20j + (50 material
moves x P10) + (10 engineering hours x P50)]. Hence, the production cost of Job 103 is P14,000 (P8.000 DM + P4.000
DL + P2,000 OH), the cost per unit is P70:(P14,000 + 200), and the price is P98 (140% x P70j.
Answer (b) is incorrect because PI00 is the unit cost if overhead is allocated based on direct materials cost. Answer (c)
is incorrect because PI 16 is the unit cost if overhead is allocated based on direct labor cost. Answer (d) is incorrect
because P140 assumes cost is P100.
43
.(b)
Allocation of Costs using an overall rate:
Total Activity Center Costs (P7,500 + P125,000 + P9,750
+ P30.000) P172,250
Divided by: No. of Machine hours (12,000 + 13,000) 25,000
Overall rate P6.89
For Low-Unit: 12,000 x P6.89 P 82,680
ForMed-Unit: 13,000xP6.89 P 89,570
44
. Suggested answer (a) P200.00 P80.00 P125.00
Setups Machining Inspections
Overhead rate:
P100,000/500 P 200.00
P400,000/5,000 P80.00
P50.000/400 P125.00
If in traditional costing system, a single unit level basis of allocation is used to allocate overhead costs to products; ABC
recognizes that to have accurate and meaningful cost data, more than one basis of allocating activity costs to product
is needed. In selecting the basis, ABC seeks to identify the cost drivers that measure the activities performed on the
products. Since this case, there were two products produced, the measurement of activities should be the total for the
two products
45
. Suggested answer (d)?272,500 P277,500
Side A Side B
Setups (200x100) P20,000
(200x400) P80,000
Machining (80 x 3,000) 240,000
(80 x 2,000) 160,000
Inspections (125 x 100) 12,500
(125 x 300) 37,500
Total P 272,500 P 277,500
After determining the overhead rate, to compute the allocated overhead cost, overhead rate will be multiplied by the
number of activities for each product.
46
.Suggested answer (d)P20.00 P25.00
Side A Side B
Overhead cost per unit
(P272,500/l 3,625 units) P20.00
(P277.500/11,100 units) P25.00
47
.Suggested answer (c) 4.00 per step
49
.(b)
Using material moves under ABC costing:
P100,000 4- (10 + 40) = P2,000 per material moves
Model X:P2,000 per mat. moves x 10 mat. moves = P20,000
P20,000 -r 100 units produced = P200 (b)
Material Y: P2,000 per mat. moves x 40 mat. moves = P80,000
P80,000 -r 200 units produced = P400 (b)
50
.(c)
Using direct labor hours under traditional costing:
P100,000 * [(100 units x 1 hr./unit) + (200 units x 3 hrs./unit)]
P100,000 -r 700 hours = P143 per DL hour
Model X: P143 per DL hr. x 1 hr. per unit = 143
Model Y: PI 43 per DL hr. x 3 hrs. per unit = P429
51
.(a)
The P50.000 of costs is allocated over 10,000 hours 1(25 x 200 hrs.) + (25 x 200 hrs.}]. Thus, the overhead cost per
hour is P5 (P50,000 + 10,000 hrs.), and the per unit overhead cost of wall mirrors is PI,000 (PS x 200 direct labor
hours).
Answer (b) is incorrect because P500 is the allocation based on number of material moves. Answer (c) is incorrect
because P2.000 assumes that all the overhead is allocated to the wall mirrors. Answer (d) is incorrect because P5.000
assumes overhead of P250,000.
52
.(b)
A8C allocates overhead costs on the basis of some causal relationship between the incurrence of cost and activities.
Because the moves for wall mirrors constitute 25% (5 -r 20) of total moves, the mirrors should absorb 25% of the total
materials handling costs, or P12.500 {25% x P50.000). The remaining P37.500 is allocated to specialty windows. The
cost per unit of wall mirrors is P500 (P12.500 + 25).
Answer (a) is incorrect because PI,000 uses direct labor as the allocation basis. Answer
(c) is incorrect because P4,500 is the allocation per unit of specialty windows. Answer
(d) js incorrect because P2.500 is not based on the number of material moves.
53
. The P50,000 of costs is allocated over 10,000 hours [(P25 x 200 hrs.) + (25 x 200 hrs.)]. Thus, the overhead cost per
hour is P5 (P50,000 - 10,000 hrs.), and the per unit overhead cost of wall mirrors is P1,000 (P5 x 200 direct labor
hours).
Answer (b) is incorrect because P500 is the allocation based on number of material moves. Answer (c) is incorrect
because P2,000 assumes that all the overhead is allocated to the wall mirrors. Answer (d) is incorrect because P5,000
assumes overhead of P250,000.
54
.ABC allocates overhead costs on the basis of some causal relationship between the incurrence of cost and activities.
Because the moves for wall mirrors constitute 25% (5 t 20) of total moves, the mirrors should absorb 25% of the total
materials handling costs, or P12,500 (25% x P50,000). The remaining P37,500 is allocated to specialty windows. The
cost per unit of wall mirrors is P500 (P 12,500 *25).
Answer (a) is incorrect because P1,000 uses direct labor as the allocation basis. Answer (c) is incorrect because
P4,500 is the allocation per unit of specialty windows. Answer (d) is incorrect because P2,500 is not based on the
number of material moves.
55
.(d)
Traditional Costing (DL hours):
= (P45,000 + P70,000 + P90,000) * (4,000 hrs. + 2,000 hr. + 4,000 hr.)
= P20.5 per DL hr.
Model S: P20.5 per DL hr. x 4,000 hrs. = P82,000 + 2,000 units =P41
Model M: P20.5 per DL hr. x 2,000 hr. = P41,000/6,000 units =P6.83
56
.(b)
ABC Costing - Model S:
Setups: P45,000 4- (100 + 150 + 25) = P90 x 100 = P 9,000
Shipping: P70,000 * (200 + 225 + 275) = P100 x 200 = 20,000
Eng'g.: P90,000 + (15 + 10 + 5) = P3,000 x 15 = 45,000
Total allocated costs P74,000
Divided by: No. of units produced 2,000
Cost per unit P37
57
.(a)
ABC Costing - Model M: (refer to No. 37)
Setups: P90x 150 P13,500
Shipping: PI00x225 22,500
Eng'.: P300x 10 30,000
Total allocated cost P66,000
Divided by: No. of units produced 6,000
P11
58
.(a)
ABC Costing - Model L: (refer to No. 37)
Setups: P90 x 250 P22,500
Shipping: PI00x275 27,500
Eng'.: P3,000 x 5 15,000
Total allocated cost P65,000
Divided by: No. of units produced 12,000
P5.42
59
. Suggested answer (c) 5,000
Activity-based costing attempts to improve costing by assigning cost to activities rather than to an organizational unit.
Accordingly, activity-based costing requires identification of the activities that consume resources and that are subject
to demands by ultimate cost objects.
60
.(c)
Indoor Outdoor
Annual revenue P300,000 P600,000
Less: Costs:
Materials P 40,000 P 60,000
Labor 50,000 75,000
Overhead:
Indoor: P500,000/P 125,000
x P50,000 200,000
Outdoor:P500,000/P 125,000
xP75,000 300,000
Total Costs P290.000 P435,000
Income (Loss) P 10,000
61
.(b)
Indoor Outdoor
Annual revenue P300,000 P600,000
Less: Costs:
Materials P 40,000 P 60,000
Labor 50,000 75,000
Overhead:
Maintenance:
Indoor: P200,000 / 100,000
x 80,000 160,000
OutdoorP200,000 / 100,000
x 20,000 40,000
Setups:
Indoor: P175,000/200 x 100 87,5000
Outdoor: P175,000/200 x 100 87,500
Administrative:
Indoor: PI25,000/ PI25,000
x P50.000 50,000
Outdoor:P125,000/ PI 25,000
xP75,000 75,000
Total Costs P387,500 P337,500
Income (Loss) P(.87,500) P26Z500
62
(d)
A&C identifies the causal relationship between the incurrence of cost and activities, determines the drivers of the
activities, establishes cost pools related to the drivers and activities, and assigns costs to ultimate cost objects on the
basis of the demands (resources or drivers consumed) placed on the activities by those cost objects. Hence, ABC
assigns overhead costs based on multiple allocation bases or cost drivers. Under the traditional, single-base system,
the amount allocated is P3.987.50 (P27.5Q0 x 14.5%). Under ABC, the amount allocated is P4.513 [(PI 1.50 x 12) +
(P. 14 x 17,500) + (P77 x25)], or P525.50 more than under the traditional system.
Answer (A) is incorrect because the ABC assignment of P4.513 is at a rate of P180.52 for each of the 25 orders.
Answer (Bj is incorrect because ABC yields a higher allocation. Answer (C) is incorrect because the total is P4.513 on
the ABC basis.
63
.(c)
Given that manufacturing overhead is applied on the basis of machine hours, the overhead rate is P60 per hour
(P1,800,000 . 30,000) or P.96 per unit [(P60 x 80 machine hours per batch) + 5,000 units per batch]. Accordingly, the
unit full cost is P6.11 (P5.15 unit prime cost + P.96).
Answer (a) is incorrect because P5.39 assumes that 80 machine hours are required for the total production of 20,000
units. Answer (b) is incorrect because P5.44 is based on the machining overhead rate (P18). Answer (d) is incorrect
because P6.95 is based on the direct labor hour manufacturing overhead rate.
64
(d)
Materials handling cost per part is P.12 (P720.000 + 6,000,000), cost per setup is P420
(P315.000 + 750), machining cost per hour is P18 (P540.000 + 30,000), and quality cost per batch is P450 (P225.000
+ 500). Hence, total manufacturing overhead applied is P22.920 [(5 parts per unit x 20,000 units x P.12) + (4 batches x
2 setups per batch x P420J + (4
batches x 80 machine hours per batch x PI8) + (4 batches x P450)]. The total unit cost is P6.296 [P5.15 prime cost +
(P22.920 + 20,000 units) overhead].
Answer (A) is incorrect because P6.00 assumes one setup per batch and 80 total machine hours. Answer (b) is
incorrect because P6.08 assumes that only 80 machine hours were used. Answer (c) is incorrect because P6.21
assumes one setup per botch.
65
.ABC:
Material handling (115x12) P1,380
Inspection (P1.40 x 17,500) 24,500
Product certification (P770 x 25) 19,250 P45,130
Traditional costing (P275,000 x 14.5%) 39,875
ABC higher than the traditional costing by P5,255
66
.Traditional costing system:
Direct materials (50 x P3,000) P150,000
Overhead (50 x 15) x P100 75,000
Total cost P225,000
Activity based costing system:
Direct materials P150,000
Overhead:
Material handling (50x50) x P8 20,000
Machining (50x12) xP68 40,800'
Assembly (50x 15) x P75 56,250
Inspection (50x14) xP104 72,800 P339,850
Higher P114,8 50
67
.Suggested answer (b) P2.40
Total overhead [P600 x (8 +2)] P6,000
Cost per machine hour [P6,000/(5 x 1,000)] P1.20
X Z
Traditional cost system
(P1.20x 2 machine hours) P 2.40
(P1.20 x 3 machine hours) P 3.60
Activity-based cost system
(P600x 8/1,000 units) 4.80
(P600 x 2/1,000 units) 1.20
Cross-subsidy per unit (Under) over cost (P 2.40) P 2.40
Peanut butter costing is an inaccurate averaging or spreading of costs over products or service units that use different
amounts of resources results in product cost cross subsidization. This term describes the condition in which the
miscasting of one product causes the miscasting of other product. Thus, the unit amount by which machine hour based
assignment over costs Z and at the same time under costs X (cross-subsidy) is P2.40.
68
.(d)
Beginning balance of RIP account (P31,000- PI ,400) P 29,600
Add: Raw materials received on credit 367,000
Total P396,600
Less: Ending balance of RIP inventory per physical count
(P33,000-PI,800) 31,200
Amount to be backflushed from RIP to Finished goods P365,400
69
.Suggested answer (b) P99,900
78
.Total conversion costs P825,000
Adjustments: Increase in conversion costs in RIP
(P4,500-P3,000) (1,500)
Decrease in conversion costs in FG
(P10,000-P8,750) 1,250
Conversion costs of units sold in June P824,750
79
.(a)
Actual Factory Overhead P225,000
Direct Labor Costs Incurred 77,000
Total actual conversion costs P302,000
Less: Applied Conversion Costs to production 300,000
March 31 Conversion Cost balance-debit / under-applied P2,000
80
.(b)
Amount to be backflushed from RIP to Finished Goods P97,000
Applied conversion costs to production 300,000
March 31 finished goods balance, debit P397,000
*Note: There's no RIP beg. and ending balances.
81
.(c)
Beginning balance of RIP account (PI2,300- PI,300) P 11,000
Add: Raw materials received on credit 246,000
Total P257,000
Less: Ending balance of RIP inventory per physical count
(P12,100-P2,100) 10,000
Amount to be backflushed from RIP to Cost of goods sold. P247,00
82
.(b)
Cost of goods-sold P247,000
Less: Adjustment in Conversion Cost (P2,100 – P1,300). 800
P246,200
83
.(c)
Raw materials purchased were requisitioned for production . P950,000* (c)
*Note: There's no RIP beg. and ending balances.
84
.(b)
Amount to be backflushed from RIP to Finished Goods P950,000
Applied conversion costs to production 8,100,000
P9,050,000
85
.(c)
Raw materials requistioned for production / amount to be
backflushed from RIP & CGS P300,000
Applied conversion costs to production 1,300,000
October 31 Cost of goods sold balance, debit P 1,600,000
86
.(c)
Actual factory overhead P995,000
Direct labor costs incurred 200,000
The Actual Conversion Costs P1,195,000
Less: Applied Conversion Costs to production 1,300,000
Overapplied conversion costs P105,000
87
. (b)
Cost of Goods Sold balance (refer to No. 8) P1,600,000
Less: Overapplied conversion costs (refer to No. 9) 105,000
P1,495,000
88
.(a)
Raw materials requisitioned for production / amount to be
fackflushed from RIP to CGS P45,000
Applied conversion cost to production 221,000
September 30 balance in the Cost of Goods Sold
balance, debit P266,000
89
.
Actual Factory Overhead:
Indirect labor P120,000
Utilities costs 15,000
Others 85,000
Direct labor costs incurred P220,000
11,000
Total Actual conversion costs P236,000
Less: Applied Conversion Costs to production 221,000
Underapplied Conversion Costs P10,000
90
.(c)
Beginning balance of RIP account P0
Add:Raw materials purchased 320,000
Applied Conversion Costs* 704,000
Total P1,024,000
Less: Ending balance of RIP account 0
Amount to be backflush from RIP to Finished of goods P1,024,000
* It should be noted that the Applied Conversion costs transaction was entered into the RIP account as stated in the
problem, Normally, applied conversion costs goes directly to CGS account (in some cases, finished goods account).
91
.(d)
Amount backflush from RIP (No. 13) P1,024,000
Divided by: Units completed 16,000
Unit Cost P64
Multiplied by:'Finished goods ending inventory
(16,000 - 15,800) 200
P12,800
92
.Suggested answer (b) P102,900
Raw and In Process inventory, May 1, net of conversion
(P5,000-500) P4,500
Add Materials received during June 100,000
Total 104,500
Less Raw and In Process inventory, June 30, net of
conversion(P5,250-650) 4,600
Amount to be backflushed from RIP to FG P 99,900
Finished goods inventory, May 1, net of conversion
(P11,250-3,250) P 8,000
Add Materials backflushed to finished goods 99,900
Total 107,900
Less Finished goods inventory, May 31, net of
conversion (P7,500 - 2,500) 5,000
Amount to be backflushed from FG to CGS 102,900
As shown earlier, backflushing is from RIP to finished goods, because there is no finished goods inventory, but it
should be pointed out that in this case, backflushing is made directly to cost of goods sold. Further, if there is finished
goods inventory account, the amount to be shown as backflushed is up to cost of goods sold. Note in the above
computations, the amount added to the finished goods inventory is the amount backflushed from RIP to finished goods.
93
.Suggested answer (c) P103,500
Amount backflushed from FG to CGS P102,900
Add net decrease in conversion cost:
Increase (from RIP to FG)
(500-650) 150
Decrease (from FG to CGS)
(3,250-2,500) 750 600
Cost of goods sold balance P103,500
Again, the estimated conversion cost components of the RIP and finished goods inventory account balances are
adjusted at the end of each month, with the offsetting entry representing a correction of cost of goods sold. If
conversion cost increased during the month, cost of goods sold is credited; however, when conversion cost decreased,
cost of goods sold is debited.
94
.Suggested answer (c) 678,800
Raw and in process, May 1 38,700
Add raw materials purchased 680,000
Total 718,700
Less raw and in process, May 31 41,900
Amount to be backflushed from RIP to finished goods 676,800
Throughput time (2,000/500) 4 days In production, there is an important and direct relationship between the size of
work in process and the speed of production. Throughput time is inversely related to velocity and may be computed by
dividing units in process by units produced per day.
99
.Suggested answer (a) 500 units
At individual work stations in a production line, the impact of work in process reduction is simple, fewer units will be
waiting at, or moving to, each station; and this can have an important impact on production losses. In this case, where
500 units were waiting between Step HI and Step #2, the defective units Step #1 might produce before the problem is
discovered is the units Step #7 sends; possibly less, if the problem at Step #7 is discovered or if the defect enters only
some of the units produced. The worst outcome is 500 units, which is the size of work in process at that work station.
100
.Suggested answer (b) P31,250
Total average defective units
(100 x 10%) x ('/2 x 500) 2,500 units
Multiply by reduction in work in process level 50%
Total savings in defective units 1,250 units
Multiply by average peso loss per defective unit 25
Expected annual savings in cost of defective units P31,250
Again, in addition to the effect on inventory carrying costs, a more important result of a work in process reduction is its
effect on production losses. At individual work stations in a production line, the worst outcome on defective units is the
size of work in process in that work station; possibly less, if the problem at a work station is discovered in some other
way or if the defects enters only some of the units produced.
101
.Suggested answer (d)?7,500
Again, because work in process is a costly asset that must be financed and maintained just as any other assets, the
obvious benefit of a work in process reduction is that total investment is reduced, producing savings in inventory
carrying costs. In addition to the effect on inventory carrying costs, a more important result of a work in process
reduction is its effect on production losses.
102
.Suggested answer (b)P45,000
Savings in annual carrying costs
(30% x Vi x P300,000) P45,000
Velocity is the speed in which units or tasks are processed in a system. A strategic benefit of increased velocity is the
reduced time needed to fill production orders. And because work in process is a costly asset that must be financed and
maintained just as any other asset producing savings in the carrying cost of inventory. Where velocity is doubled, the
annual carrying cost percentage is reduced by one-half