Se Commercial 3ph Inverter W Synergy Tech Installation Guide PN SExxK Xxxxixxxx
Se Commercial 3ph Inverter W Synergy Tech Installation Guide PN SExxK Xxxxixxxx
Se Commercial 3ph Inverter W Synergy Tech Installation Guide PN SExxK Xxxxixxxx
Disclaimers
Important Notice
Copyright © SolarEdge Inc. All rights reserved.
No part of this document may be reproduced, stored in a retrieval system or
transmitted, in any form or by any means, electronic, mechanical, photographic,
magnetic or otherwise, without the prior written permission of SolarEdge Inc.
The material furnished in this document is believed to be accurate and reliable.
However, SolarEdge assumes no responsibility for the use of this material. SolarEdge
reserves the right to make changes to the material at any time and without notice. You
may refer to the SolarEdge web site (www.solaredge.com) for the most updated version.
All company and brand products and service names are trademarks or registered
trademarks of their respective holders.
Patent marking notice: see http://www.solaredge.com/patent
The general terms and conditions of delivery of SolarEdge shall apply.
The content of these documents is continually reviewed and amended, where
necessary. However, discrepancies cannot be excluded. No guarantee is made for the
completeness of these documents.
The images contained in this document are for illustrative purposes only and may vary
depending on product models.
Emission Compliance
This equipment has been tested and found to comply with the limits applied by the
local regulations.
These limits are designed to provide reasonable protection against harmful
interference. This equipment generates, uses and can radiate radio frequency energy
and, if not installed and used in accordance with the instructions, may cause harmful
interference to radio communications. However, there is no guarantee that interference
will not occur in a particular installation. If this equipment does cause harmful
interference to radio or television reception, which can be determined by turning the
equipment off and on, you are encouraged to try to correct the interference by one or
more of the following measures:
Reorient or relocate the receiving antenna.
Increase the separation between the equipment and the receiver.
Connect the equipment into an outlet on a circuit different from that to which the
receiver is connected.
Consult the dealer or an experienced radio/TV technician for help.
Changes or modifications not expressly approved by the party responsible for
compliance may void the user’s authority to operate the equipment.
Revision History
Version 1.3 (May. 2022)
Change in connection method to the DC terminals of the Synergy Manager. Updated
links to circuit breaker rating documents.
Version 1.2, September 2021: Change in connection method to the DC terminals of the
Synergy Manager
Version 1.1, September 2021: Added Synergy Unit connectors drawing
Version 1.0, April 2021: Initial release
Contents
Disclaimers 1
Important Notice 1
Emission Compliance 2
Revision History 3
HANDLING AND SAFETY INSTRUCTIONS 6
Safety Symbols Information 6
Chapter 1: Introducing the SolarEdge Power Harvesting System 9
Power Optimizer 9
Three Phase Inverter with Synergy Technology 10
Monitoring Platform 11
Designer 11
Supported AC Grids 11
Installation Tools and Material List 11
Installation Procedure 12
Chapter 2: Installing the Power Optimizers 14
Safety 14
Installation Guidelines 15
Step 1: Mounting the Power Optimizers 18
Step 2: Connecting a PV module to a Power Optimizer 19
Step 3: Connecting Power Optimizers in PV strings 19
Step 4: Verifying Proper Power Optimizer Connection 21
Chapter 3: Installing the Synergy Manager and Synergy Units 22
Synergy Manager Package Contents 22
Synergy Unit Package Contents 22
Identifying the Units 22
Front Interface of Synergy Manager 23
Inverter Interconnection Cable Interfaces 27
Synergy Manager External Cable Interface 28
Synergy Unit Interface Connectors 29
Mounting and Connecting the Synergy Manager and Synergy Units 29
Chapter 4: Connecting PV Modules and AC to the Synergy Manager 34
Connecting PV Modules to the Synergy Manager 34
Connection Methods 35
Connecting PV Strings to the Synergy Manager 37
Connecting PV Arrays to the Synergy Manager 39
Connecting Ground and AC Wires to the Synergy Manager 40
Grid Connection Guidelines 40
Chapter 5: Activating, Commissioning and Configuring the System 47
On-grid Commissioning of the inverter 48
Disposal requirements under the Waste Electrical and Electronic Equipment (WEEE)
regulations:
NOTE
Discard this product according to local regulations or send it back to SolarEdge.
Warning!
To reduce the risk of injury, read all instructions in this document.
WARNING!
When servicing or replacing SolarEdge equipment, instructions in the
SolarEdge Inverter Installation Guide must be followed to maintain the integrity
of the PV hazard control system. SolarEdge Power Optimizers and/or inverters
may only be replaced with SolarEdge Power Optimizers and/or inverters. Third
party equipment is not compatible with SolarEdge equipment.
WARNING!
Using this equipment in a manner not specified by SolarEdge in this document
may impair the protection provided by this equipment.
WARNING!
The inverter cover must be opened only after switching the inverter ON/OFF/P
switch located at the bottom of the inverter to OFF. This disables the DC voltage
inside the inverter. Wait five minutes before opening the cover. Otherwise,
there is a risk of electric shock from energy stored in the capacitors.
WARNING!
Before operating the inverter, ensure that the inverter AC power cable and wall
outlet are grounded properly. This product must be connected to a grounded,
metal, permanent wiring system, or an equipment-grounding conductor must
be run with the circuit conductors and connected to the equipment grounding
terminal or lead on the product.
WARNING!
Opening the inverter and repairing or testing under power must be performed
only by qualified service personnel familiar with this inverter.
WARNING!
Do not touch the PV panels or any rail system connected when the inverter
switch is ON, unless grounded.
WARNING!
SafeDC complies with IEC60947-3 when installing the system with a worst case
SafeDC voltage (under fault conditions) < 120V.
The worst case voltage is defined as: Voc, max+ (PV string Length-1)*1V, where:
CAUTION!
This unit must be operated according to the technical specification datasheet
provided with the unit.
CAUTION!
HEAVY OBJECT. To avoid muscle strain or back injury, use proper lifting
techniques, and if required - a lifting aid.
NOTE
Use PV modules rated according to IEC 61730 class A.
NOTE
The symbol appears at grounding points on the SolarEdge equipment. This
symbol is also used in this manual.
NOTE
SolarEdge inverters can be installed in sites with an alternative power source
such as a generator. SolarEdge requires installing a physical or electronic
interlock, which will signal to the inverter when the grid has been disconnected.
Interlock procurement, installation, maintenance and support are the
responsibility of the installer. Damage to the inverter due to incorrect interlock
installation or use of an interlock that is incompatible with the SolarEdge
system will render the SolarEdge warranty invalid.
For more information on connecting an alternative power source
to SolarEdge inverter, refer to
https://www.solaredge.com/sites/default/files/se-inverter-
support-of-voltage-sources.pdf.
NOTE
The following warning symbols appear on the inverter warning label:
Power Optimizer
The Power Optimizers are DC-DC converters connected to PV modules to maximize
power harvesting by performing independent Maximum Power Point Tracking (MPPT)
at the module level.
The Power Optimizers regulate the PV string Voltage at a constant level, regardless of
PV string length and environmental conditions.
The Power Optimizers include a safety Voltage mechanism that automatically reduces
the output of each Power Optimizer to 1 Vdc in the following cases:
During fault conditions
The Power Optimizers are disconnected from the inverter
Monitoring Platform
The monitoring platform enables monitoring the technical and financial performance of
one or more SolarEdge sites. It provides past and online information on the system
performance, both at the system and PV module levels.
Designer
Designer recommends inverter and Power Optimizer selection per site size and enables
report generation. You can create a project in Designer and export the site design with
the PV array layout to the monitoring platform.
Supported AC Grids
This section details the AC grids supported by SolarEdge inverters (model dependent).
Ground connection is required for all grids, as described in "Connecting Ground and AC
Wires to the Synergy Manager" on page 40.
For overview of common AC grids and the compatibility of SolarEdge inverters, refer to
Grids Supported by SolarEdge Inverters.
Allen screwdriver for 5mm screw type for the inverter cover, Synergy Manager cover
and inverter side screws
Allen screwdriver for M5/M6/M8 screw types
Standard flat-head screwdrivers set
Non-contact Voltage detector
Cordless drill (with a torque clutch) or screwdriver and bits suitable for the surface
on which the inverter and Power Optimizers will be installed. Use of an impact driver
is not allowed.
MC4 crimping tool
Ring terminals crimping tool
Wire cutters
Wire strippers
Voltmeter
For installing the communication options, you may also need the following:
For Ethernet:
CAT6 twisted pair Ethernet cable with RJ45 connector
If using a CAT6 cable spool: RJ45 plug and RJ45 crimper
For RS485 :
Four- or six-wire shielded twisted pair cable
Watchmaker precision screwdriver set
For secondary grounding:
Ring/lug terminal crimper tool for the Ground wire
Ring/lug terminal
Serrated washer
Grounding screw
Two washers
Installation Procedure
The following procedures, are required for installing and setting up a new SolarEdge
site. Some of these procedures also apply to modification of an existing site.
1. Installing the Power Optimizers
2. Installing the Synergy Manager and Synergy Units
CAUTION!
Power Optimizers are IP68/NEMA6P rated. Choose a mounting location where
optimizers will not be submerged in water.
CAUTION!
This unit must be operated according to the operating specifications provided
with the unit.
CAUTION!
Cutting the Power Optimizer input or output cable connector is prohibited and
will void the warranty.
CAUTION!
All PV modules must be connected to a Power Optimizer.
CAUTION!
If you intend to mount the Power Optimizers directly to the module or module
frame, first consult the module manufacturer for guidance regarding the
mounting location and the impact, if any, on module warranty. Drilling holes in
the module frame should be done according to the module manufacturer
instructions.
IMPORTANT SAFETY FEATURE
Modules with SolarEdge Power Optimizers are safe. They carry only a low safety
voltage before the inverter is turned ON. As long as the Power Optimizers are
not connected to the inverter or the inverter is turned OFF, each Power
Optimizer will output a safe voltage of 1V.
CAUTION!
Installing a SolarEdge system without ensuring compatibility of the module
connectors with the Power Optimizer connectors may be unsafe and could
cause functionality problems such as ground faults, resulting in inverter shut
down. To ensure mechanical compatibility of the SolarEdge Power Optimizers’
connectors with the PV modules’ connectors to which they are connected:
Use identical connectors from the same manufacturer and of the same type
on both the Power Optimizers and on the modules; or
Verify that the connectors are compatible in the following way:
The module connector manufacturer should explicitly verify compatibility
with the SolarEdge Power Optimizer connector; and the Inverter DC input
connectors.
A third-party test report by one of the listed external labs (TUV, VDE,
Bureau Veritas UL, CSA, InterTek) should be obtained, verifying the
compatibility of the connectors.
Installation Guidelines
For the minimum and maximum number of Power Optimizers in a PV string (PV
string length), see the Power Optimizer datasheets. Refer to the Designer for PV
string length verification. The Designer is available on the SolarEdge website at:
https://www.solaredge.com/products/installer-tools/designer#/.
Do not use extension cables between a module and a Power Optimizer, between
two modules connected to the same Power Optimizer, or between two Power
Optimizers other than in the following cases:
Between a Power Optimizer and a module:
Extension cables of up to 1.8 m are allowed for all Power Optimizers (0.9 m for
DC+, and 0.9 m for DC -).
S-Series Power Optimizers with the 1-type suffix in their part number (Sxxx-
1xxxxxx or Sxxxx-1xxxxxx) - extension cables of up to 16 m can be installed per
Power Optimizer (8 m for DC+, and 8 m for DC-).
SolarEdge Sense Connect technology monitors the S-Series Power Optimizer
cable connectors and the direct connection created between them and another
connector.
P-Series Power Optimizers with the 4-type suffix in their part number (Pxxx-
4xxxxxx) and the Mxxxx-Series - extension cables of up to 16 m can be installed
per Power Optimizer (8 m for DC+, and 8 m for DC-).
Between two Power Optimizers or between a Power Optimizer and the inverter:
Extension cables can be installed between Power Optimizers only from row to
row, around obstacles or pathways within a row and from the end of the PV
string to the inverter. The total length of the extension cables may not exceed
the following values:
3. Attach each Power Optimizer to the rack using M6 or M8 stainless steel bolts, nuts
and washers or other mounting hardware. Apply torque of 9-10 N*m.
4. Verify that each Power Optimizer is securely attached to the module support
structure.
5. Record Power Optimizer serial numbers and locations, as described in Reporting
and Monitoring Installation Data on page 52.
NOTE
The DC bus of each unit is separate and not shared for all units. Therefore, in
addition to following the inverter design rules, each unit should follow the unit
design rules as detailed in the Technical Specifications.
1. Connect the Minus (-) output connector of the PV string’s first Power Optimizer to
the Plus (+) output connector of the PV string’s second Power Optimizer.
2. To minimize electromagnetic interference (EMI), make sure to minimize the distance
between the positive and negative DC cables.
NOTE
Some models Synergy Manager do not include DC Disconnect Switch.
DC Disconnect Switch
The DC Disconnect Switch is a manually operated safety switch for disconnecting the
DC power of the SolarEdge system.
NOTE
When the Synergy Manager is OFF (for example during maintenance) it may
be locked to prevent a safety hazard:
1. Move the switch to the Lock position.
2. Insert the lock through the knob opening
and lock.
ON/OFF/P Switch
Figure 7 shows the ON/OFF/P switch of the Synergy Manager.
ON (1) - Turning this switch ON (after Power Optimizer pairing) starts the operation
of the Power Optimizers, enables power production and allows the inverter to
begin exporting power to the utility grid.
OFF (0) - Turning this switch OFF reduces the Power Optimizer Voltage to a low
safety Voltage and inhibits exportation of power. When this switch is OFF, the
Synergy Manager and Synergy Units control circuitry remains powered up.
P - Holding the switch pressed in P position allows performing the following
functions:
WARNING!
Upon PVRSS, the internal circuitry remains up, therefore the inverter cover
must be opened only after shutting off the inverter ON/OFF/P switch. This
disables the DC Voltage inside the inverter (Synergy Manager). Wait five
minutes before opening the cover. Otherwise, there is a risk of electric
shock from energy stored in the capacitors.
Indication LEDs
(1) (2)
LEDs indication consists on color and state (on/ off/ blinking / flickering /alternating
(3)
). The LEDs indicate different system information, such as errors or performance.
Figure 8 shows the Indication LEDs of the Synergy Manager.
Generally, the main LED indications are:
COMM. ON - the inverter is communicating with the monitoring platform
POWER ON - the system is producing
POWER blinking - AC is connected but the system is not producing power
FAULT ON - system error
ON/ OFF/
LED
P
Indication Comment
switch
FAULT POWER COMM.
position
S_OK: ON
S_OK: ON communication
Power
with the
Optimizers not OFF Blinking No S_OK:
monitoring
paired OFF
platform is
established
Pairing Blinking Blinking Blinking
ON (1)
Wake-up/ Grid
OFF Blinking Blinking
Monitoring
S_OK: ON
System
OFF ON No S_OK:
Producing
OFF
Night mode
OFF Flickering S_OK: ON
(no production)
No S_OK:
Inverter is OFF
OFF Blinking OFF
(Safe DC)
OFF (0) S_OK: ON
Inverter is OFF
Blinking Blinking No S_OK:
(DC not safe)
OFF
Inverter
configuration ON / P ON ON ON
or reboot
Inverter The upgrade
firmware ON / P Alternating Alternating Alternating process can take
upgrade up to 20 minutes
Refer to Errors
ON/ OFF/ ON/ OFF /
and
Error Any ON Blinking/ Blinking/
Troubleshooting
Flickering Flickering
on page 55
ON/ OFF/
LED color
P
Indication Comment
switch
Red Green Blue
position
Percentage of AC
OFF ON OFF This indicates
Production: 0 - 33 %
power production
Percentage of AC
ON (1) OFF OFF ON as percentage of
Production: 33 - 66 %
rated peak AC
Percentage of AC output power
OFF ON ON
Production: 66 - 100 %
CAUTION!
HEAVY OBJECT. To avoid muscle strain or back injury, use proper lifting
techniques, and if required - a lifting aid.
CAUTION!
SolarEdge inverters and Power Optimizers can be installed at a minimum
distance of 50 m from the shoreline of an ocean or other saline environment, as
long as there are no direct salt water splashes on the inverter or Power
Optimizer.
For SolarEdge inverters installed at a distance of 200 m or closer to the
shoreline, special brackets purchased separately from SolarEdge and SS304
stainless screws are required. For details, please contact your local sales
representative.
2. Allow for proper heat dissipation, follow the guidelines specified in Application Note
- Clearance Guidelines .
NOTE
Some Inverter models are provided with only two Synergy Units.
3. Level the mounting template horizontally against the wall and mark the drilling hole
locations for the bracket of the Synergy Units (see pencil icons in Figure 13).
Lift the Synergy Unit from the sides, or hold it at the top and bottom of the unit
to lift into place.
Align the two indentations in the enclosure with the two triangular mounting
tabs of the bracket, and lower the unit until it rests on the bracket evenly (see
Figure 15).
For the right or left Synergy Units, insert only one screw through the outer
(exposed) side of the unit and into the bracket. Tighten the screws to a torque of
4.0 N*m (see Figure 14 ).
NOTE
For the center Synergy Unit, use both side screws.
Connection Methods
The Synergy Manager connects to the solar panels by the following interface methods:
DC input terminals for three PV arrays inside the Synergy Manager
MC4 input connectors for 12 PV strings located at the bottom of the Synergy
Manager enclosure.
Figure 19 shows the various methods of connection of DC from the PV strings to
Synergy Manager.
NOTE
Functional electrical earthing of DC-side negative or positive poles is
prohibited because the inverter has no transformer. Grounding (earth ground)
of module frames and mounting equipment of the PV array modules is
acceptable.
NOTE
SolarEdge fixed input Voltage architecture enables parallel PV strings to be of
different lengths. Therefore, they do not need to have the same number of
Power Optimizers as long as the length of each PV string is within the
permitted range.
WARNING!
Turn OFF the AC before connecting the AC terminals. If connecting
equipment grounding wire, connect it before connecting the AC Line and
Neutral wires.
NOTE
Functional electrical Earthing of DC-side negative or positive poles is
prohibited because the inverter has no transformer. Grounding (earth
ground) of module frames and mounting equipment of the PV string
modules is acceptable.
4. Insert the DC wires into the DC terminals and fasten the Allen screw to a torque of 5
N*m for 25 mm2 wires or 8 N*m for 35mm2 wires.
CAUTION!
Ensure that each Plus (+) wire is connected with corresponds to its (-) terminal.
5. Fasten the gland nut to a torque of 12 N*m.
6. Close the Synergy Manager cover and secure it by tightening the six screws to a
torque of 3.5 N*m.
WARNING!
The inverter must be protected by an over-current protection device (a circuit
breaker or a fuse) with a maximum rating of 250 A. For the exact rating of an
over-current protection device, per model, refer to Application Note:
https://www.solaredge.com/sites/default/files/determining-the-circuit-
breaker-size-for-three-phase-inverters.pdf
In India, use only a circuit breaker device. For selecting a circuit breaker, refer
to https://www.solaredge.com/sites/default/files/se-determining-the-circuit-
breaker-ratings-for-three-phase-inverters-India.pdf
In Israel, use only a circuit breaker device. For selecting a circuit breaker, refer
to https://www.solaredge.com/sites/default/files/se-determining-the-circuit-
breaker-ratings-for-three-phase-inverters-Israel.pdf
For more wiring information, refer to the SolarEdge Recommended AC Wiring
Application Note, available on the SolarEdge website at
http://www.solaredge.com/files/pdfs/application-note-recommended-wiring.pdf.
The following cable and wire configurations can be used to connect the Synergy
Manager:
AC cable with L1, L2, L3, PE wires
AC cable with L1, L2, L3, N, PE wires
AC cable with L1, L2, L3 wires and an external PE (Protective Earth) wire
AC cable with L1, L2, L3, N wires and an external PE wire
WARNING!
To avoid shock hazard conditions, the PE wire must be connected to the
inverter before connecting the AC wires.
Use AC line wires with a maximum of 120 mm2 cross section conductor (For inverter
models SE50K, SE55K, SE66.6K, SE80K use up to 95 mm2)
Use PE wire with a maximum of 70 mm2 cross section conductor (For inverter
models SE50K, SE55K, SE66.6K, SE80K use up to 95 mm2)
For inverter model SE120, use a PE wire with an outer diameter of 12 to 20 mm. For
inverter models SE50K SE55K, SE66.6K, SE80K use 9 to 16 mm
The AC gland supports a cable of 30 - 50 mm in diameter
CAUTION!
Over-current protection for the AC output must be provided by the installer.
Chassis Grounding
If required, ground the Synergy Manager and Synergy units as shown in Figure 22.
Use a grounding cable, a grounding screw, two washers, a ring terminal and a serrated
washer. Connect the grounding cable to the grounding point on the left or right side of
the unit.
Figure 22: Chassis grounding of the Synergy Manager and Synergy Units
3. Open the gland of the AC cable and insert the AC cable through the gland.
4. Strip 10 to 11 mm of insulation from the PE wire.
5. Connect the PE wire to the PE terminal and fasten the Allen screw to a torque of 5
N*m for wires of 16 mm2 to 25 mm2 or 8 N*m for wires of 35 mm2 to 70 mm2.
NOTE
Before connecting lugs to aluminum wires:
a. Remove oxide from the exposed wires with emery paper or a steel-
wire brush
b. Clean dust with a cloth and Isopropyl alcohol (IPA)
c. Coat wires with a designated antioxidant aluminum wire grease
immediately after cleaning
NOTE
Use ferrule when connecting a fine stranded wire of up to 50 mm2.
1. Verify that the main AC circuit breaker is in OFF position at the circuit breakers panel.
2. Remove the upper cover of the AC terminal block.
For downloading SetApp, Internet connection, one-time registration and logging are
required. No registration is required for using the SetApp.
Pairing
1. From the Commissioning menu, select Pairing.
2. Tap Start Pairing.
3. When Pairing Complete is displayed, the system startup process begins:
Since the inverter is ON, the Power Optimizers start producing power and the
inverter starts converting AC.
WARNING!
When you turn ON the ON/OFF/P switch, the DC cables carry a high Voltage
and the Power Optimizers no longer output a safe output.
When the inverter starts converting power after the initial connection to the AC, the
inverter enters Wake up mode until its working voltage is reached. This mode is
indicated by the flickering green inverter LED.
When working voltage is reached, the inverter enters Production mode and
produces power. The steadily lit green inverter LED indicates this mode.
4. Tap OK to return to the Commissioning menu.
Communication
Communication settings can be configured only after communication connections are
complete. Refer to Setting Up Communication to the Monitoring Platform on page 1.
Select Monitoring Communication to configure communication with the
monitoring platform.
Select Site Communication to configure communication between multiple
SolarEdge devices or external non-SolarEdge devices, such as batteries or loggers.
Power Control
Power control options are detailed in the Power Control Application Note, available on
the SolarEdge website at: https://www.solaredge.com/sites/default/files/application_
note_power_control_configuration.pdf.
Pre-commissioning (Off-Grid)
The following items are required for Pre-commissioning:
Mobile device with SolarEdge SetApp application
Power bank: 60W output port, USB-C Power Delivery (PD): 20V 3A (not provided)
USB cable: 3.3 ft (1 meter), USB-C to USB-C (not provided)
IMPORTANT NOTE
Commissioning should be performed in full daylight.
NOTE
When pre-commissioning multiple inverters, each inverter need to be
commission individually.
NOTE
Alternating red / blue LEDs indicate a problem with the power bank.
Designer
Designer recommends inverter and Power Optimizer selection per site size and enables
report generation. You can create a project in Designer and export the site design with
the PV array layout to the monitoring platform.
For more information, refer to https://www.solaredge.com/products/installer-
tools/designer#/.
Signaling Options
Alternative Power Source
Energy-generation systems (such as PV inverters) connected to the grid may consist of
different types of energy generating sources.
In some cases, when grid power is disconnected, PV inverters operate in parallel with
other voltage sources, such as generators.
When inverters operate concurrently with generators, they may be subjected to voltage
and frequency fluctuations that exceed trips, which are preset according to regional
grid connection requirements. To support simultaneous operation of the inverter and a
generator, the inverter extends its Voltage and frequency operating range once it
receives a Power Reduction Interface (PRI) signal indicating that grid power is
unavailable (“Alternative Power Source mode”). When the grid power is restored, the
inverter automatically reverts to its default country setting, which includes the original
Voltage and frequency operating range.
Figure 28 , shows an Example of Alternative Power Source System.
Figure 29: PRI Terminal Block Location on the Communication Board of the Inverter
For detailed connection and configuration of the inverter in alternative power source
mode, refer to: https://www.solaredge.com/sites/default/files/se-inverter-support-of-
voltage-sources.pdf
Identifying Errors
Errors may be indicated in various system interfaces: On the inverter bottom panel, a
red LED indicates an error. In the monitoring platform and SetApp, errors are displayed
with codes.
For more information on the codes displayed for error and warning
messages, refer to http://www.solaredge.com/sites/default/files/se-
inverter-installation-guide-error-codes.pdf. This document describes
errors that appear in SetApp, monitoring platform, and LCD (for inverters
with LCD). To identify the error types, use the methods described below.
Troubleshooting Communication
Troubleshooting Ethernet (LAN) Communication
The possible errors and their troubleshooting are detailed in the following table:
If after follower detection the number of followers displayed for the leader under
RS485-1 > Follower Detect is lower than the actual number of followers, refer to the
following application note to identify missing followers and troubleshoot
connectivity problems:
https://www.solaredge.com/sites/default/files/troubleshooting_undetected_RS485_
devices.pdf
Additional Troubleshooting
1. Check that the modem or hub/router is functioning properly.
2. Check that the connection to the internal connector on the communication board is
properly done.
3. Check that the selected communication option is properly configured.
4. Use a method independent of the SolarEdge device to check whether the network
and modem are operating properly. For example, connect a laptop to the Ethernet
router and connect to the Internet.
5. Check whether a firewall or another type of network filter is blocking
communication.
Wi-Fi Antenna
The Wi-Fi Antenna is provided with a user manual. For more information, refer to:
https://www.solaredge.com/sites/default/files/se-wifi-zigbee-antenna-installation-
guide.pdf
Cellular Plug-in
The cellular plug-in provides wireless communication between the inverter and the
SolarEdge monitoring platform. The Cellular Plug-in kit is provided with an antenna and
user manual. For more information on the Cellular Plug-in, refer to:
https://www.solaredge.com/sites/default/files/cellular_gsm_installation_guide_for_
inverters_with_setapp.pdf
Appendix D: SafeDC™
When AC supply to the inverter is shut off (by shutting off the AC breaker at the site), or
when the inverter ON/OFF/P switch is turned to OFF, the DC Voltage drops to a safe
Voltage of 1V per Power Optimizer.
The SolarEdge inverters are certified for compliance with the following standards as
disconnection devices for PV generators, meaning that they can replace a DC
disconnect:
IEC 60947-3:1999 + Corrigendum: 1999 + A1:2001 + Corrigendum 1:2001 + A2:2005;
DIN EN 60947-3
VDE 0660-107:2006-03
IEC 60364-7-712:2002-05
DIN VDE 0100-712:2006-06.
In compliance with these standards, follow the instructions below to disconnect the DC
power:
1. Move the DC Disconnect Switch to the OFF position, as shown in the following
image.