ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 2 of 17
ETAP Workshop Notes
Here no DC current axis shift. Hence no DC component when fault current at voltage peak point
in inductive circuit.
Short circuit near to generator
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 3 of 17
ETAP Workshop Notes
Fault close to generator, AC component will decay as shown in the below figure:
AC Decay
For fault at grid bus, AC component of fault does not decay since grid bus is considered to be
remote from a generator (i.e. there are many other reactance components of equipment in series
up to grid bus).
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 4 of 17
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 5 of 17
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 6 of 17
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 7 of 17
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 8 of 17
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 9 of 17
ETAP Workshop Notes
Switchgear selection
Switchgear is ok if,
a) Ipm_rtd > Ipm_cal
b) Ib_asymm_rtd > Ib_asymm_cal (at CB opening time)
(CB opening time in second should be entered in CB rating page for the calculation)
c) Ithermal_rtd (at 1 sec) > Ithermal_cal (at 1 sec)
If 3 sec then 3 sec values are compared for calculation. Thermal withstand needs to be
entered in CB rating.
To select CB, use factors from next sheet. These factors are useful to select switchgear rating
require for calculated system.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 10 of 17
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 11 of 17
ETAP Workshop Notes
Procedure
1. Open LF-Example1 OTI file shown below.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 12 of 17
ETAP Workshop Notes
5. Select “Fault 3Phase” from Short Circuit study case and proceed to Edit Study Case
option as shown below.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 13 of 17
ETAP Workshop Notes
8. To study different faults for the selected buses, click “60909” & give name for Output
File Name as shown below.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 14 of 17
ETAP Workshop Notes
10. Go to Display Options to change the type of fault on the selected buses as shown below.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 15 of 17
ETAP Workshop Notes
12. To view the short circuit report, go to Report Manager in Short Circuit Toolbar and
Click on Result & select Short-Circuit Report as shown below. Select the type of file
format to view it.
13. Sizing of HV and LV switchgear can be done from short circuit results obtained from
3-Phase Device Duty (IEC 60909) in Short Circuit toolbar.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 16 of 17
ETAP Workshop Notes
15. Proceed to Alert View in short circuit toolbar for list of alerts for inadequate sizes of
breakers.