0% found this document useful (0 votes)
127 views8 pages

Concrete Technology and Structural Analysis

Uploaded by

Rajat Sinha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
127 views8 pages

Concrete Technology and Structural Analysis

Uploaded by

Rajat Sinha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

CONCRETE TECHNOLOGY & Structural analysis QUESTIONS:

1- Purpose of concrete curing:


To avoid the evaporation of the water from concrete and to keep moisture inside to
maintain the durability of the concrete
2- What is concrete workability:
The ease of fresh concrete which can be Mixed, placed, and compacted fully over the
formwork
3- What is the core test of concrete and when it is applied?
Core test is a destructive test done for concrete after 28 days usually done if there is
any doubt of the compressive strength of concrete
4- What is the density of water?
1000 kg/m3
5- Why are admixtures added to the concrete?
To increase the durability & strength of concrete and some time for increasing the
workability
6- When we remove the shutter of columns?
After minimum 2 days
7- When we remove the shutter of sides beam or foundation?
It can be removed after 1 day
8- When we remove the shutter of normal slab?
After minimum 14 days
9- How many cubes required for 110 m3 of concrete in one day?
Total of 9 cubes: 3 to do compressive strength after 7 days
3 after 28 days
3 extra cubes
10- Definition of hydration:
It is the reaction between water and cement
11- What is the length of the CG of compression and CG of a tension member?

Effective depth
12- Definition of water cement ratio:
Weight of water over the weight of Cementous components or cement
13- What is the minimum thickness of a structural member?
15 cm
14- Techniques used for beam repair.
Steel plate; carbo fiber cover; fiber road; shipping, cleaning of steel and casting
microconcrete high strength
15- Most used of slabs.
a- Hollow slab
b- Solid slab
c- Post tension slab
d- Flat slab
e- Prestressed slab
16- When is shotcrete used?
a- Difficulty of placing a shutter for members
b- Pool walls
c- Tunnels
d- Curve member
17- When OPC & SRC are used?
OPC for superstructure
SRC for substructure or for member exposed to soil
18- Density of cement.
1440 kg/m3
19- Density of concrete
2500 kg/m3
20- Definition of concrete durability.
Capability of concrete to resist weathering condition like chloride, chemical attack, and
abrasion
21- Till when the curing should continue?
Till minimum 7 days till the concrete reach 70% of its strength

22- Refer to sampling test in BS 12350-1;2009. Standard term “increment” Is


defined as:
Quantity of concrete taken by single operation of a scoop or similar devices
23- After demolding of cubes, cubes shall be cured immediately before testing in
water at temperature of chamber:
20+- 2 at humidity larger than 95%
24- The minimum allowable capacity of the measuring container used in air content
test is:
5 liters
25- Refer to flow table test, leveling each layer by tamping lightly done for how
many times?
10 times
26- The flow table test values results are reported to the nearest.
10 mm
27- Slump test is used to measure.
Consistency of concrete
28- Refer to density test, the standard specifies the method for determining the
density of compacted fresh concrete is.
BS-EN-12350-1;2009
29- For temperature Test, concrete containing aggregate size larger than 75mm may
require how much time for transfer of heat from aggregate to mortar?
20 mins
30- What is the maximum % of reinforcement of beam?
4%
31- What is the minimum % of reinforcement for beam as BS 8110-97?
0.8 %
32-Wind load test taken from wind for regular building if height more than?
120 meters
33- Modification factor of PT Slab:
0.5
34- the deflection for beam span is:
5Wl4/384 EI
35- Nominal tensile strength for post tension tendons is:
1860 MPa
36- Density of light weight concrete:
Between 800 to 1800 kg/m3
37- What is the poison ratio of concrete?
0.2
38- what is the poison ration of steel structure
0.3
39- Es of steel structure is:
205000 MPa
40- Es of concrete
30000 Mpa
41- Minimum vertical reinforcement in walls is:
0.04 %
42- Minimum vertical reinforcement of columns is:
1%
43- Mechanical splice (min 50 diameter) may be used after demonstrating that splice
can develop:
125% of the specified yield strength of the bar
44- the maximum deflection for cantilever beam under uniform load is:
Wl4/ 8 EI

46- As per DIN 1048 Standard, water penetration at 28 days test should not exceed
maximum of:
10 mm
47- As per ASTM C 1202 the rapid chloride penetration test at 28 days for RC pile
should not exceed:
1200 Columbus
48- As per ACI 318-4 the maximum allowable elongation in post tension tendons is:
7%
49- maximum spacing for PT tendons as per ACI 318-05 IS:
8 THICKNESS OF SLAB or 5 ft
50- Maximum acceptable settlement for the piles under working load:
8mm
51- the normal consistency of Portland cement is
25.35 %
52- the Modulus of elasticity of normal concrete is
4700 √f’c N/mm2
53- in post tension the maximum number of strands used per tendons is
5
54- For external walls of building whose U value should be 0.52 w/m2*k, the
thickness of polystyrene should be:
60 mm
55- cover for structural members:
a- Columns & beams 30 mm
b- Foundation 50 mm
c- Pile and exposed to soil 70 mm
56- maximum settlement of raft foundation is
50 mm

57- maximum settlement of isolated footing is


30 mm
58- maximum steel in strap footing is located at?
Top
59- overlap of steel of continues beam done at:
Mid third span at bottom and middle span for top
60- The concrete used for structural purpose shall have compressive strength not
less than:
Minimum Fcu 35 N.mm2 for post tension minimum Fcu 40 N/mm2

61- shear & moment diagram


62- design lifetime of structure:

63- Concrete combination design:


64- Reinforcement details for PT slabs

65- precast slab connection details:


66- deflection of beam and slabs

67- crack width limit:

Wk= Hd/Hw = hydro static pressure of water / wall thickness


For structure exposed to water:
If Hd/Hw> 5 wk= 0.2 mm
If Hd/Hw>35 wk= 0.05 mm
For structure not exposed to water:
Wk= 0.3 mm
For pile
Wk=0.1 mm

68- Combo waterproof detail: