Effective depth
12- Definition of water cement ratio:
Weight of water over the weight of Cementous components or cement
13- What is the minimum thickness of a structural member?
15 cm
14- Techniques used for beam repair.
Steel plate; carbo fiber cover; fiber road; shipping, cleaning of steel and casting
microconcrete high strength
15- Most used of slabs.
a- Hollow slab
b- Solid slab
c- Post tension slab
d- Flat slab
e- Prestressed slab
16- When is shotcrete used?
a- Difficulty of placing a shutter for members
b- Pool walls
c- Tunnels
d- Curve member
17- When OPC & SRC are used?
OPC for superstructure
SRC for substructure or for member exposed to soil
18- Density of cement.
1440 kg/m3
19- Density of concrete
2500 kg/m3
20- Definition of concrete durability.
Capability of concrete to resist weathering condition like chloride, chemical attack, and
abrasion
21- Till when the curing should continue?
Till minimum 7 days till the concrete reach 70% of its strength
46- As per DIN 1048 Standard, water penetration at 28 days test should not exceed
maximum of:
10 mm
47- As per ASTM C 1202 the rapid chloride penetration test at 28 days for RC pile
should not exceed:
1200 Columbus
48- As per ACI 318-4 the maximum allowable elongation in post tension tendons is:
7%
49- maximum spacing for PT tendons as per ACI 318-05 IS:
8 THICKNESS OF SLAB or 5 ft
50- Maximum acceptable settlement for the piles under working load:
8mm
51- the normal consistency of Portland cement is
25.35 %
52- the Modulus of elasticity of normal concrete is
4700 √f’c N/mm2
53- in post tension the maximum number of strands used per tendons is
5
54- For external walls of building whose U value should be 0.52 w/m2*k, the
thickness of polystyrene should be:
60 mm
55- cover for structural members:
a- Columns & beams 30 mm
b- Foundation 50 mm
c- Pile and exposed to soil 70 mm
56- maximum settlement of raft foundation is
50 mm