INSPECTION REQUEST FORM

Contractor : Nael Construction and Contracting LLC


Consultant : KHATIB & ALAMI

Project Title : Sewerage & Stormwater Drainage System for Nad Al Shiba 3rd IR Ref. No. : DS-196/2-P4-HC-9222

Project No. : DS-196/2 Date : 24-Jun-24


B.O.Q Items : d/4/3A,d/4/3B Discipline : Civil

Description of Work : Epoxy Painting.


Area 1 ( CH-V-NB-15/1-2 Type A ,CH-V-NB-15/5/1-3 Type A, CH-V-NB-15/9-1 Type B )

Work Location (drawing attached) : Yes Sector : N/A Road, Building etc., N/A

Work to be Inspected :

Work Ready for Inspection at : (Time) : (Date)

Inspection Requested By : Request Received By :


(for CONTRACTOR) (for CONSULTANT)

Date : 24-Jun-24 Time : 12:03:00 PM Date : Time :

SKETCH / NOTES / MEASUREMENTS :

Sketches,Sattached
INSPECTION REPORT :
Inspection of Work Completed : (Time) (Date)
Permission to Proceed with the work : Approved

Approved Subject To (See Comments)


Not Approved (See Comments)

Others (PLS. Specify) (See Comments)


Land Surveyor Comments :

Inspector Comments :

Material Inspector Comments :

Surveyor (Name) : Signature : Date :


Inspector (Name) : Signature : Date :
A. R. E (Name) : Signature : Date :
R. E (Name) : Signature : Date :

Received by Contractor :
Contractor's
: Signature : Date :
Representative
The location of the Chamber
will be approved after
verification of Existing FIC
The location of the Chamber will be approved after verification of Existing FIC

The location of the Chamber will be approved after verification of Existing FIC