Project Management Overview
Project Management Overview
Table of Contents
Page |1
INMA for Construction & Industrial Development
Page |2
INMA for Construction & Industrial Development
Page |3
INMA for Construction & Industrial Development
1 2 3
Business Preparation for Construction ‘Go’ or
Development
Planning Consultant ‘No-go’ Decision
4 5 6
* Construction Commissioning &
Construction Occupancy
‘Go’ - Decision Completion
Figure 1 - Stages in the Building-Life cycle Before and After Final Construction “Go”, “No-go” Decision
Stage 4: Construction
The project is actually built, involving management and review of construction, and administration
of the related contracts.
This includes proving the building systems, obtaining the occupancy permit, completion
documentation, and turnover of the building to the Owner for occupancy and use.
Page |4
INMA for Construction & Industrial Development
Stage 6: Occupancy
This includes description of initial responsibilities for occupancy period and consideration for
design and warranty requirements. During this period a focus on Management Lessons Learned is
held.
Page | 5 The Building Process follows a relatively fixed sequence of stages between project concept and
completion. Each of these, if properly carried out, is a building block of project success. Each stage
includes its own sequence of management decisions.
Stages Milestones
Project Initiated
1 Business
Planning Development authorized
2 Project
Development Development approved
3 Preparation for
Construction Working drawings &
construction contracts
4 Construction
Ready for commissioning
5 Commissioning
& Completion Substantial completion &
project handover
6 Occupancy
End of warranties
(after project)
The sequence in the above figure represents the project life cycle from concept, through
development, design documentation and construction, to completion, leading to the occupancy
period (after the project completion).
Each stage should be sufficiently complete and, for pre-construction, project viability confirmed
before the Owner authorizes the next stage to proceed. The responsibility assignments and
practices for achieving the results vary with the delivery method.
For some projects, ‘sufficient’ may mean full completion of each stage. For others, significant
overlapping of stages may be acceptable. Especially on a fast-track project, there may be
substantial exceptions to total completion of an intermediate stage when the next one starts.
Page |5
INMA for Construction & Industrial Development
Page |6
INMA for Construction & Industrial Development
A project is considered to start when a prospective Owner recognizes an opportunity or need for a
building, and decides to study its concept. The Owner should make preliminary statements of the
Page | 7 project goal and end product definition. This should include any required building characteristics,
and any identified alternatives whether relating to use, project scope or building location.
Since a good start is the key to a successful project, a management discipline should be put in
place at once and elaborated on as the project team increases in size and diversity. The Project
e Business Plan
f Pre-construction Financing
Stage 2
Stage End: Approval to Develop Project
Project Development
( or not )
Page |7
INMA for Construction & Industrial Development
method. The Project Manager should prepare a preliminary strategy which should influence the
Owner’s organization for the project. The implications of the various delivery options for quality and
risk should be considered. This helps prepare for the project development stage with its increasing
complexity.
There may be alternative business opportunities, project locations, or building characteristics that
need to be considered. Evaluation of these and other business needs may dictate changes to the
preliminary goal and consideration of further project alternatives. The risks include the possibility
that the project will be unsuccessful, and that substantial liabilities may be incurred.
Each Owner needs to tailor risk analysis and the associated benefit-cost evaluation to the specific
business. The Owner may accept, mitigate, and/or assign risks, or spend effort and money to
remove uncertainties and reduce the possibility of problems.
Risk analysis should be a major factor in selecting the preferred project alternative. The Owner’s
tolerance for risk, or even an unfavorable project outcome, may be a crucial aspect of the business
plan and the deciding factor for whether to go after uncertain opportunities. Risk planning interacts
with stipulation of quality requirements which are in addition to those needed for compliance with
regulations. Higher quality is likely to give better performance, but at a cost premium.
2. Identify Risks
Determine Communication Methods with Stakeholders.
3. Analyze Risks
Select Methods for Analyzing Risk.
Determine Likelihood, Consequences.
Estimate Level of Risk.
4. Evaluate Risks
Compare with Criteria
Set Risk Priorities.
5. Treat Risks
Identify Treatment Options.
Evaluate Treatment Options.
Select Treatment Options.
Prepare Treatment Plan.
Implement Treatment Plan.
To identify a best alternative, the Project Manager should carry out the steps below.
Page |8
INMA for Construction & Industrial Development
Specify the characteristics of apparently attractive alternative project concepts, and evaluate
each based on:
Criteria specific to the project and its Owner, applying these to reduce the number of
alternatives needing detailed consideration;
Page | 9 Less tangible benefits and costs, such as reputation and environmental impacts;
Risk analysis that identifies factors which may adversely or favorably affect the project
outcome.
Assess all other project costs, including marketing, off-site services, municipal development
requirements, access, financing, etc.
If the project is straightforward, as for a utility-style building with little fast tracking, the Owner may
emphasize minimum acceptable quality and least cost for all products and services. On the other
hand, if there are high risks, or opportunities for innovative design, it is prudent to invest in
management, design and quality assurance from more experienced people.
Frequently, Owners need the certainty of knowing the project maximum cost; and this may be a
pre-determined amount. Attempting to achieve cost certainty simply by assigning all risks to others
may not be an effective strategy. A more prudent approach is to manage the project so as to
minimize risks and their consequences, and then assign each risk to the party best able to manage
it, and to allow time and cost contingencies for the problems that may occur.
1.2.4 Regulatory Management Strategy
A strategy should be developed by identifying potential conflicts between the project concept and
applicable regulations, and initiating resolution of the conflicts. Replanning may be needed to meet
regulatory conditions or to define project components that do not raise regulatory concerns. The
strategy should recognize that requirements vary between different jurisdictions, and lay out:
the regulations which will be significant to the project,
the responsibilities, including those of the registered coordinating professional, for undertaking
the needed involvement with regulators.
Project scope, quality, cost and schedule can be affected. The Project Manager, with assistance
from design professionals, should:
Identify zoning limitations, development approvals for the jurisdiction in which the project is
located, and other regulatory requirements such as for parking, streets, and major roads, and
external obligations;
Determine regulatory procedures and agency contacts, and give priority to processes with long
lead times for obtaining approvals;
Assign responsibilities for coordinating interaction with the Regulatory Process and determine
the assistance and coordination offered by the municipality.
Direct discussion with municipalities and other regulatory authorities can assist coordination with
the regulatory process. Assigning a consultant familiar with the regularities is a great importance.
Page |9
INMA for Construction & Industrial Development
Market, operation and financial studies differ among sectors of the building industry and among
Owners. These studies are needed for a full evaluation of the project and then for effective
interaction with the Project Team. The Project Manager, through the Owner’s team, summarizes
the project concept, financing, risk, regulatory, schedule and insurance issues, based on the
proposed alternative(s). The business plan should cover the project and the subsequent building
Page | 10 use or sale. A main purpose is to determine the justification for a building-project and often to
enable comparison with competing uses for funds or land. The plan should:
Define the project concept and preliminary objectives, budget and schedule.
Identify the specific needs and constraints that will influence the identification of project
objectives and requirements.
Analyze financing of full costs and benefits, cash flows, uncertainties and financing charges for
the project; full costs should cover marketing and other business support and overhead, even if
not to be accounted for as a project cost; (the analysis is often called a “pro forma”); financial
planning expertise is needed), Define the Owner’s project organization and assignment of
project roles.
Involve the people who could introduce subsequent changes or delays, whether from inside or
outside the Owner’s organization.
Be endorsed by all those who have a business or user interest in the project and whose
acceptance will later be needed for project construction; this reduces the possibility of
omissions in planning, which could lead to disruptive changes and could even jeopardize
project viability. When building users will not be identified until later, someone who is
knowledgeable of typical user requirements should represent their interests at this stage.
P a g e | 10
INMA for Construction & Industrial Development
higher authority should issue the mandate to the Project Manager (who should take part in its
preparation).
This formality reinforces proper business planning and accountability for the decision to continue
with the project, and reduces the potential for costly misunderstanding.
Page | 11 In deciding to proceed with the project, the Owner should give clear instructions for project
development and define the initial project organization. Instructions should:
Be issued to and agreed with the assigned Project Manager, and approved at a senior level
within the Owner’s organization.
Identify overall project objectives and needs of the Owner and users (more precise definition of
project objectives and requirements will continue during the project development stage); this
should include a preliminary project budget and master schedule consistent with the business
plan.
Summarize how the Owner’s organization will interface with the project, including specific
practices for decisions, recommendations, approvals and other formal communication involving
the Owner and project team members.
Authorize the Project Manager to assign all project team responsibilities; to proceed with
project development, subject to further approvals of the project, (the next approval may be on
completion of the schematic design); a plan for initiating the project and project team should
already be in place. Assignments may be to existing or newly hired staff, or by contract.
P a g e | 11
INMA for Construction & Industrial Development
The interests of eventual users and any buyer-Owners may not be represented when project
requirements are set. (There is consumer protection law for eventual Owners or lessees from
the open market, mainly for residential buildings).
The user representation problem exists in a different form for a “build-to-suit” project, with a
specific buyer or lessee at pre-determined pricing. A developer may resist user requirements
Page | 12
unless there is a price adjustment. The solution is to negotiate the requirements prior to signing
of the turnkey contract.
The Owner may pre-determine financial, scope, quality, and timing objectives and constraints
for the project, without confirming them to be compatible. This is often the starting point of
projects that get into trouble. The relative priorities of long term building quality, project cost
and project completion date may then be unclear. Cost and schedule may be treated as more
important than quality to the detriment of the end product. , planning is likely to be less
thorough.
First-time Owners and those who build infrequently should especially consider concerns such as
the above.
P a g e | 12
INMA for Construction & Industrial Development
Page | 13 This stage should define the project scope, timing, cost, risks and delivery method, sufficient to
produce a Master Project Plan. The Owner on the recommendation of the Project Manager should
approve these elements, in readiness for the ‘preparation for construction’ stage to proceed. The
Master Project Plan stems from the Project Business and Implementation Plans being elaborated
during the schematic design and design development. The Project Manager should coordinate
with applicable regulatory authorities to facilitate development approvals, re-zoning and
subsequent approvals. The Design Manager typically provides the main input.
The senior manager and Project Manager should define how ongoing requirements and
information will be communicated in a timely manner, to and from the Project Team. Where
changes may be justified, their impacts on the project should be evaluated before specific
P a g e | 13
INMA for Construction & Industrial Development
instructions are issued. The Project Manager will be involved in some external changes, such as in
relation to permit conditions, but others will be the responsibility of the senior manager.
Organize the Project Team for setting Project Objectives, and for development, preliminary
design and preliminary construction planning.
Direct preparation of the initial project plan to cover: project definition; Owner, regulatory and
user requirements; and needs of applicable community and other stakeholders.
Ensure consistency among the preliminary design, the preliminary cost plan and funding plan,
the master schedule and the Owner’s expectations, including required project quality.
Reach agreement with the Design Manager on the process for approving drawings and
specifications, and later the manufacture and construction of the building and its components
and systems. Agree, who will be the registered coordinating professional for the project.
Direct the analysis and assignment of project and business risks.
Guide project definition and requirements for the design, and approve site selection, the facility
program and each phase of the design, but excluding technical approval of the design
(responsibility of the Design Manager).
Oversee interaction with the regulatory authorities to ensure that lines of communication are
established, with a clear mutual understanding of the required approvals and permits and their
timing.
Direct a public involvement process if required by the Owner, or if the need for this is shown by
constraints and influences on the project identified in the municipal approval process.
Oversee the selection of the project delivery method and the preparations for timely and
effective implementation, including the degree of emphasis on quality.
Oversee comprehensive and timely project planning, with all required information and
expertise, for approval by the senior manager before beginning the preparation for construction
stage. As for all Owner involvement, keep the Owner appropriately informed and advised and
ensure that Owner’s decisions are expeditiously made.
Plan the points throughout the project when approval will be required by Owner or Project
Manager, and set the criteria applicable to each.
P a g e | 14
INMA for Construction & Industrial Development
complex facility, for which the instructions are often called a “Design Brief”. Design instructions
should be used to initiate the schematic design, design development and construction
documentation phases of the design, and be included in project plans. The Design Manager for
approval by the Project Manager usually prepares them, authorizing the scope of the design
prior to each phase.
Page | 15
Perform or assign and coordinate services, which must under regulations be carried out by
design professionals, including the registered coordinating professional. If there are multiple
consultant assignments directly with the Owner, coordination by the Design Manager is
essential to prevent confusion of the design responsibility chain.
Manage the schematic design and design development, and necessary investigation work.
Oversee optimal and timely site and environmental investigations. Control the project scope in
accordance with the Project Objectives, giving clear instructions to designers to enable the
information required for adequate design to be obtained and utilized.
Approve the technical content of the design drawings and specifications.
Establish and apply quality standards for the design work, and specify or provide advice for the
quality of the end product. Develop and manage the quality assurance program for the design.
It is important that the design reflects available resources and materials, as well as ease of
construction. Construction Methodology, materials storage and delivery, and equipment usage
shall be discussed by the Construction Manager during this phase.
P a g e | 15
INMA for Construction & Industrial Development
time. A Functional Program shall be prepared by the Design Manager based on the information
provided by the Client.
For larger or more complex structures the functional program extends to performance
requirements for systems and equipment. The term “facility program” is often used for such
buildings. Much interaction amongst planners and designers may be needed before all
Page | 16
requirements are agreed. The process will be overseen by:
The Project Manager, particularly if having special expertise of similar special-purpose
buildings from previous projects;
The Design Manager, from the Project Manager’s staff; or,
A consultant specializing in design and construction management for the applicable class of
buildings will be retained by the Project Manager or in some projects, by the prime consultant.
Requirements are typically defined for each system as performance requirements and for each
space as dimensions. These parameters should be used to prepare a corresponding preliminary
target cost estimate. Project scope changes may follow, to respond to evolving Owner or user
needs, to keep actual costs within a budget limit or to fully utilize available funds.
Performance specifications should optimize operation and maintenance costs and risks over the
life of the building.
P a g e | 16
INMA for Construction & Industrial Development
The drawings developed at this stage are used for review with the applicable municipality. This
stage leads directly into the creation and finalization of the Construction Documents. The Design
Development Documents will be reviewed to verify that the entire approved Owner requested
elements are included in the design. For all intents and purpose the design of the structures is
fixed and early procurement and construction services can be released.
Page | 17
2.2.5 Quality Management Planning
The quality management process consists of defining the required end product and then meeting
each of the requirements for achieving it. In each phase of the design there is added definition of
the quality required for the end product. Every party performing work on the project is obligated to
meet design, construction and other service requirements which contribute to the definition and
achievement of the required product quality.
The direct responsibility for producing the required quality of each system and component remains
with the applicable designer, construction contractor or other party doing work. The Owner may
choose to rely on these responsibilities and associated liabilities and may decide not to specify
additional quality assurance.
However, this can be a false economy because the majority of problems develop at the interfaces
between participants, and independent review can identify errors, gaps, and omissions that are
missed by the people doing a particular section of the work. The overall management of the
design is relegated to the senior or lead design firm. Overview of this function must be
accomplished as the design progresses and at each phase of the design completion.
Costs from failure of any party to meet their quality responsibilities may fall to a substantial extent
on the Owner, and project performance and completion objectives may be compromised. There
may be lost opportunities if designers and builders are not motivated to look for best solutions in
the interests of the project. Hence, there is growing understanding in the industry that minimizing of
fees and prices can be counter-productive where expertise is sought.
The project delivery method affects the assignment and timing of design work. For example, if
design-build delivery is selected, the preliminary design should enable drawings to be issued at the
start of the next stage so that selection of the design-build contractor may be expedited and design
documentation can commence.
In the interests of achieving maximum value at minimum cost, the Owner should not assign risks
related to attributes of the land, nor assign any risks to people that cannot control them. However,
the Owner may best carry risks of floods or other extreme occurrences that cannot easily be
P a g e | 17
INMA for Construction & Industrial Development
foreseen. Builder’s All Risk Insurance must be in-place and maintained during the construction
process.
The Project Manager should oversee the Master Project Plan and confirm its consistency with the
Project Objectives. Assistance should be obtained from the prime consultant, a representative of
the eventual users, and others responsible for components of the plan. Approval by the Project
Manager of the master schedule confirms the planned project completion date and intermediate
milestones. Approval of the Master Project Plan by the Owner’s Senior Manager should include an
instruction, developed with the Project Manager, to complete the project subject to identified further
approvals.
The budget and schedule prepared for the Implementation Plan should be updated with greater
detail. They may be based partly on summary activities and experience of other projects rather
than on detailed analysis.
P a g e | 18
INMA for Construction & Industrial Development
P a g e | 19
INMA for Construction & Industrial Development
who cannot control the problems, or who are not in a position to manage or carry the
associated risk.
An Owner’s representative may be charged with responsibility to bring the project to completion
on time and within budget, in isolation from the responsibility of the designers for quality and for
compliance with regulations. This may create conflict between Owner and designer by giving
Page | 20
inappropriate priority to savings of cost and time at the expense of meeting quality
requirements.
Design and/or construction work may be fragmented by inappropriate use of multiple contracts
and fast-tracking without the required skilled coordination of a design and management firm.
This may create confusion at interfaces of design or trade specialties and can lead to errors
being undetected or uncorrected.
Confusion over guarantees, liability and insurance may lead to inappropriate responsibility
assignment. There may be an incorrect expectation that project or construction managers, who
provide project direction for a fee, should guarantee performance of designers or construction
and trade contractors.
Master scheduling of the project may inappropriately concentrate on the construction period in
isolation. There may be insufficient attention to the business and design decisions and
approvals which have a substantial influence on total project duration. These determine when
contracts can be tendered and awarded and whether subsequent instructions are timely and
free from changes.
P a g e | 20
INMA for Construction & Industrial Development
In this stage, working drawings and other documents for construction are completed, and
Page | 21 construction plans approved so that all construction may commence.
The Design Manager Role is typically assigned to the prime consultant, while the parts of the
Project Manager and Construction Manager Roles are assigned in ways that depend on the
delivery method.
There may be substantial overlap between this stage and the follow-up construction stage, when a
fast-tracking approach is taken. Approval to commence construction and issue the initial trades
packages for tender is then followed by a sequence of approvals to issue documents for tender
corresponding to the sequence of trades.
P a g e | 21
INMA for Construction & Industrial Development
designers, municipality, contract managers, planners, estimators, bidders, actual contractors and
others use the documents for various purposes.
The Owner, through the Project Manager, should continue to be involved in design choices of
importance to stakeholders. Timing of choices is crucial since even small changes made after
closure dates for drawing approvals can cause substantial redesign, and construction contracts are
Page | 22
adversely affected if already awarded. The prime consultant should reach agreement with the
Project Manager on a document submission schedule covering all design disciplines and Owner’s
approvals.
This schedule should identify reviews and approvals, and letter of assurance and other
submissions to authorities having jurisdiction.
The preparation for construction stage requires design documentation up to and including working
drawings for bid invitations. More detailed parts of design documentation, such as shop drawings,
can be completed during construction.
P a g e | 22
INMA for Construction & Industrial Development
Plan the assignments of all construction responsibilities and risks, partly by reference to the
actual contracts to be used.
Involve the design team and cost, schedule and other specialists.
Be validated or amended by bidders since their bids offer to complete on time.
Page | 23 Planned assignments should anticipate all requirements and potential problems. This includes
schedule management responsibilities, which should be assigned to people able to determine
status in comparison to the project and contract schedules, and to initiate corrective measures
when a schedule slips. Slippage in comparison to key dates needs to be recognized and analyzed
even when detailed activity sequences are rearranged, or when much work is presented as long-
duration activities.
P a g e | 23
INMA for Construction & Industrial Development
STAGE 4: CONSTRUCTION
Through the above practices, construction is carried in accordance with the design requirements,
Page | 24 as detailed by construction, shop drawings, and specifications. Many of the practices in this stage
run concurrently.
The Site Supervision Consultant should coordinate the work to meet the time frame of the master
schedule and the details of the approved construction schedule. The prime consultant should
Stage 4: Construction
carry out the construction reviews and resolve all issues of quality and code compliance, enabling
letters of assurance to be signed.
Administration of contracts by or on behalf of the Project Manager is needed to confirm compliance
with requirements. It includes management of changes and payments. This contract administration
role needs to be established at this stage. It is to be noted that contract administration capability
should be a consultant selection criterion.
P a g e | 24
INMA for Construction & Industrial Development
(architectural, structural, electrical, mechanical, plumbing and fire), a design professional must be
appointed “designer of record” with individual responsibility for the integrity of the design.
A schedule for construction drawing issue should have been part of the documents for
construction. The schedule is usually detailed and provided through the Prime Consultant Role and
then used by all parties for coordinating progress of all drawings.
Page | 25
Deviations from the drawing schedule may impact the master schedule and should be monitored
by the Project Manager. Corrective action to make up time or re-negotiate the schedule may be
necessary.
P a g e | 25
INMA for Construction & Industrial Development
Documentation of Quality Control (QC) practices for own work and Quality Assurance (QA)
practices for monitoring subcontractors’ work, including contract requirements.
Sub-trade coordination and safety of all workers
Permit applications for work on public property and for work of various trades.
Page | 26 Purchasing and receiving procedures for contractor’s materials.
P a g e | 26
INMA for Construction & Industrial Development
This is the direct responsibility of the applicable builders and through them their suppliers and
vendors, with additional inspection and testing arranged by the Site Supervision Consultant and
the Design Manager if required for the quality assurance program.
P a g e | 27
INMA for Construction & Industrial Development
require independent checks on progress, retaining a cost consultant. Each party to a contract
contributes to its administration.
A contract administrator originates and manages various documents, such as but not limited to
those listed under 4.1.2 above. Documentation responsibilities should be assigned among
Page | 28 technical, management and administration roles.
Contract Changes
The Owner, Project Manager, designers, or builders may initiate changes in order to improve the
project scope or design. Alternatively, changes may be identified in the site soils, access, services,
or other contract provisions. External factors such as regulations or taxes may cause changes.
Regardless of how a change arises it is processed by the contract administrator in coordination
with others involved in determining the scope of the change. When changes are agreed,
adjustments are usually made to the contract price and the construction schedule.
It is usual for contract changes to affect administration of subcontracts which require similar
change provisions.
Contractual Relations
The way in which the contract is administered may be seen either as fair or as standing in the way
of builders’ entitlements and enforcing contract terms in a biased manner. The contract
administration role is the basis in developing cooperation between Project Manager, prime
consultant, and builders. It is imperative that this basis is unbiased to avoid adversarial relations
which prevent effective teamwork.
P a g e | 28
INMA for Construction & Industrial Development
The Project Manager is involved in administrative decisions. Contract relations may be adversely
affected if construction contractors are reluctant to work towards fair resolution of problems,
especially if an effective dispute resolution process is lacking.
Appropriate solutions are more likely to be reached by those directly involved with the specifics of
a problem, and the need to refer decisions up the organizational hierarchy is limited. Negotiations
Page | 29
are ineffective if someone who is not a party to the discussion can overturn agreements later.
Alternatively, if one party is unable to be objective, or is not negotiating in good faith, then
escalation up the formal dispute resolution process may be necessary. If disputes are prolonged
when equitable solutions are available, they are likely to interfere with effective teamwork.
The best practice is that both parties to a contract should assign decision-making authority for
contractual problems to be resolved at the working level, up to a pre-determined maximum
amount.
P a g e | 29
INMA for Construction & Industrial Development
Problems under the following headings provide further warnings against making choices or
relaxing good practices to obtain short-term advantage, convenience or apparent deflection of risk.
Project success may be threatened as a result. Most of the problems can be minimized if
recommended practices are followed.
Dispute Management
Site coordination meetings may degenerate into ‘blaming’ sessions rather than producing
solutions to day-to-day difficulties in coordinating the work.
P a g e | 30
INMA for Construction & Industrial Development
Slow resolution of claims and other disputes may lead to an accumulation of disputes, and
block co-operation and cause delays, cost overruns, and more claims. The easiest solutions
are reached by dealing with problems while they are fresh in people’s minds and the work can
still be observed.
P a g e | 31
INMA for Construction & Industrial Development
P a g e | 32
INMA for Construction & Industrial Development
Contractors are usually required to prepare record drawings as part of their responsibilities. These
are for review by the prime consultant for completeness and then for use during occupancy. As-
built mark-ups of construction, shop and coordination drawings need to be maintained during the
work for record drawings to be complete and accurate. Unless actual locations of items embedded
in concrete or walls are drawn before they are covered up, record drawings will be incomplete.
Page | 33
Some permanent records are needed for the certification of substantial performance, e.g. permits
and certificates these are Design Manager Responsibilities.
Operation and maintenance manuals for equipment and building systems are provided by
suppliers and contractors where specified. Many manuals are documents for equipment or building
components that are provided for many projects, e.g. roofs or boilers, but many must be
customized. The users are best served if the manuals are clear and organized and if special
training is provided for difficult items.
Certificates verifying the operation of various mechanical and electrical systems are required for
operation. Financial, correspondence, as-built progress and other historical records are assembled
per detailed agreements for documentation described in sub-section 4.1.
Requirements for permanent documentation are most effectively addressed during the preparation
for construction stage as part of construction specifications. The accuracy and completeness of
record drawings and documentation cannot be over-emphasized when considering their effect on
the operation and maintenance costs to be incurred during building occupancy.
P a g e | 33
INMA for Construction & Industrial Development
For lessons to be assimilated, a process of record and note-keeping needs to be planned and
monitored. This is only likely to happen if each project participant assigns an individual as
responsible to monitor and compile significant experiences. Design changes, schedule slippage
and cost overruns, records of quality and other problems and their solutions are all possible
documentation with which to facilitate the recognition of the significant variances between plans
Page | 34 and actual should be examined for the lessons they reveal. A formal debriefing is recommended.
Skilled facilitating may be needed to maintain an environment of learning rather than criticism.
However, many lessons will be about good ideas that should be repeated.
P a g e | 34
INMA for Construction & Industrial Development
being expected or planned prior to handover. A solution is to identify handover items in project
and operating plans.
Once holdbacks have been released the incentives to complete remaining deficiencies are
reduced. A holdback may be kept for rectification of deficiencies but this sometimes provides
too little incentive for contractors and their sub-trades to give priority to total completion of their
Page | 35
work. It may be necessary to expedite this work in addition to holding back money until
performance is complete. This can cause project completion to be continually deferred.
The Owner, with due notice, may need to arrange for completion by others and pay for the
work out of the deficiency holdback.
Co-operation between contracting parties over dispute resolution may have broken down,
especially if costly problems occurred during the work that one party claimed should be solved
at the expense of the other. This may have resulted in financial settlement being deferred to
the end of the job. The difficulty of resolution increases as disputes accumulate and interact,
possibly including claims for costs of making up lost time. Formal dispute resolution processes,
whether through the courts or by alternative methods, can be time consuming and expensive.
Marginal performance should be identified as a way of anticipating possible future problems,
and only deferral of only minor deficiencies should be allowed as the work progresses.
Completion on-time and within budget, and acceptance for project handover, do not guarantee
a trouble-free occupancy period.
Formal assimilation of lessons learned is regrettably uncommon. This may be connected to the
absence of a review process during and at the end of the project, because people are too busy
with the current project or in starting the next, or may expect embarrassment from reviewing
problems, or see insufficient value in doing so. The more successful the project, the more
willing people are to review their participation in it.
P a g e | 35
INMA for Construction & Industrial Development
STAGE 6: OCCUPANCY
6.1 Initial Responsibilities for Occupancy Period
Page | 36 During project development, Section 2.2, options should be included for the Owner to occupy the
building or to lease or sell it to others. However, lease or sale is not considered part of the project.
There may be some design modifications needed during the typical one-year warranty period, prior
to total project completion. These could necessitate construction or remedial work and associated
coordination and could involve users as well.
P a g e | 36