Installation Manual For Bifacial PV Module - 20230621
Installation Manual For Bifacial PV Module - 20230621
Bifacial PV Module
1
Catalogue
1 Introduction ....................................................................................................................................................... 3
1.1 Purpose .................................................................................................................................................... 3
1.2 Scope of liability ..................................................................................................................................... 3
2 Regulations......................................................................................................................................................... 3
2
1.2 Scope of liability
1 Introduction
We appreciate for your trust and confidence towards No warranty expressed or implied is made with regard
the photovoltaic (PV) module products manufactured to any information in this manual because how this
observed during installation, and the manual shall be without prior notice. In case of any inconsistency
properly kept for further reference. The installer must between the description of different language versions
inform the end customer (or consumer) accordingly. of this manual, the Chinese version shall prevail.
This document provides detailed instructions and The mechanical installation and electrical connection
safety precautions regarding the installation, electrical of PV systems should be performed in accordance with
connection, and maintenance of following PV modules local laws, regulations and corresponding international
CHSM60M(DG)/F-HC CHSM60N(DG)/F-HC
Astronergy’s modules are designed to meet the
requirements of IEC61215 and IEC61730, and they
CHSM66M(DG)/F-BH CHSM72M(DG)/F-BH
have been qualified for Application Class A
CHSM72N(DG)/F-BH CHSM72M(DGT)/F-BH
(equivalent to Safety Class II requirements).
CHSM72N(DGT)/F-BH CHSM78M(DG)/F-BH
Modules can be applied to publicly accessible
CHSM78N(DG)/F-BH
systems operating at greater than 50V DC or 240W.
3
UL61730 standards and meets Class C fire rating days or dewy mornings, take appropriate protective
(IEC61730), type 29 fire rating (UL61730 for US measures to prevent moisture from penetrating the
market) and Class C fire rating (UL61730 for connectors.
Canada market).
Unauthorized personnel are prohibited from
!WARNING approaching the installation area or PV module
storage area.
Read and understand all safety instructions before
installing, wiring, handling, and/or maintaining PV It is forbidden to install or use damaged PV
modules. PV modules generate direct current modules.
electricity when they are exposed to sunlight or other It is forbidden to repair PV modules by
light sources. Whether the module is connected or not, unauthorized personnel, including but not limited
to replacing any part of PV modules (such as
direct contact with the live part of the module such as
diodes, junction boxes, connectors, etc.).
the wiring terminal may cause personal injury or even
death. It is forbidden to plug in connectors of different
types and models.
3.1 General safety
It is forbidden to expose PV modules to the
Before installation, please contact the relevant local
following substances: grease or organic ester
authority to make sure the installation permit and
compounds (e.g. DOP, plasticizers), aromatics,
installation inspection requirements can meet the
phenols, ketones, halogenated substances, mineral
local requirements. The installation process should
oil, alkanes (e.g. gasoline, cleaning lubricants,
comply with the safety rules applicable to all
electronic resurrection agents), alcohol, , adhesive
components in the system, including cables,
sheets that can generate oxime gas and potting glue
terminals, charging monitors, batteries, inverters,
(only for connectors), TBP (plasticizer), detergent,
etc.
etc., to avoid chemical damage and affect the
4
It is forbidden to disassemble and move any part of cases are well ventilated, water-proof and dry.
the PV module; if the connector of the PV module After the arrival, carefully open the outer package
is wet, do not perform any actions to avoid the risk and prevent scratches and bumps of PV modules.
of electric shock. When stacking PV modules, strictly follow the
The cover of the junction box should always be PV module will be affected; standing or walking on
burning the module and causing fire hazard in It is forbidden to pick up, drag, or move PV
Avoid package damaging and falling during modules to prevent current generation.
5
installation surface should be kept to prevent the load-bearing capacity and long-term reliability.
installation surface from touching the junction box.
If the PV module glass or other packaging
When installing on the roof, comply with the fire materials are damaged, please wear personal
protection requirements of the building. It is protective equipment to separate the PV module
recommended to install PV modules on a fireproof from the site or the circuit. It is strictly forbidden to
and insulated roof covering, and ensure adequate touch wet PV modules, unless you are wearing
ventilation between the PV modules and the electric shock protection equipment that meets the
installation surface. In order to ensure the fire requirements.
rating on the roof, the minimum distance between
When professionals replace or repair PV modules,
the frame of the PV module and the roof surface is
do not damage the surrounding PV modules or their
10cm.
support structures.
The connector must be fully mated when wiring. If
When cleaning PV modules, you must follow the
the cable is too long, it is recommended to fix the
cleaning requirements of PV modules.
cable to the rack system with a UV-resistant nylon
cable tie. When fixing the cable to the rack, the The connectors must be kept dry and clean to
bending radius of the cable should be not less than ensure that they are in good working condition. Do
48mm. not insert other metal objects into the connector or
make electrical connections in any other way.
Avoid directly exposing cables and connectors to
sunlight. Please use anti-UV cables. 4 Handling, unloading and unpacking
Do not disconnect the electrical connection when If the PV module is not in use, please do not open
there is a load. the product packaging. The goods should be stored
in a dark, dry and ventilated place. If the PV
It is strictly forbidden to try to disassemble the PV modules are stored in an uncontrollable
module, and it is strictly prohibited to remove the environment, the storage time must be less than 3
nameplate of the PV module or other parts on the months when the outer packaging of the PV
PV module; it is strictly forbidden to paint or apply modules is kept intact.
any adhesive on the surface of the PV module.
It is recommended to unpack an appropriate
It is strictly forbidden to drill holes in the frame of number of PV modules per day according to the
the PV module. project progress, and the unpacked PV modules
should be installed within a day. If unpacking too
It is strictly forbidden to scratch the anodized layer
many PV modules and being stacked on the ground,
on the surface of the aluminum alloy frame, except
in severe weather such as heavy rain and typhoons,
when it is connected to the ground. Scratches may
the PV modules may be immersed in water for a
cause corrosion of the frame, affecting the frame's
long time affecting the reliability of the product or
6
be scraped away. load. Adjust the position of the sling to ensure the
center of gravity is stable and keep moving at a
4.1 Transport and unloading
stable speed. Place the package lightly on a flat
ground and right the package.
During the transportation of the PV modules to the
project site, they must be packed in the packaging box
2. Do not unload the modules under conditions of
provided by Astronergy, and they should be stored in
wind over class 6, rain and snow.
the original packaging box before installation. Please
protect the packaging from damage. 3. For vertical portrait packages, do not lift up more
It is necessary to ensure the safety when unloading PV than 2 pallets of modules at once. For vertical
landscape packages, do not lift up more than 2
modules, especially when hoisting roof projects. The
pallets of modules at once. For lateral unloading ,
PV modules should be placed in a protective device remove the pallet stacking belts before unloading.
and then hoisted to the roof to prevent the packing box
7
1. Unload from both sides of the truck.
!Special instructions
8
Unloading from container
Distance between the upper surface of the forklift tines and the
Packaging turnover points are as follows: ground
strength of ≥ 2000kgf, and place safety prohibited to unload modules under the weather
guardrail on both sides of the forklift.
conditions of wind speed greater than Level 6, heavy
9
1. Prepare the following tools before unpacking: art 3. A fixed support (wall, rack, stable unpacked module
knife (scissors), safety hat, stand supporter, safety pallets, etc.) must be ready for vertical landscape
shoes and anti-cutting gloves. package unpacking, and the steps are as follows
5) Cut off the vertical packing belts excepting two Vertical landscape package unpacking steps
inner belts.
4.3 Stack
6)push the module gently to tilt towards the stand
supporter. When taking out the PV module from the packing box,
put the cardboard on the ground first to prevent the PV
7) Cut the remaining packing belts. module from colliding and scratching with the cement
surface, hard object on the ground, color steel tile,
8) Tear off the anti-fallen tape on the first module in
metal corrugated, etc.
the front, and then take out the modules in order.
When the PV modules are stacked, they must be neatly
and stably stacked on a horizontal surface, and stacked
with the glass side of the bottom module facing up, the
glass side of other modules facing down. At the same
time, there must be cardboard bedding under the PV
modules, the number of piles should not exceed 14. At
Vertical portrait package unpacking steps the same time, avoid installation tools and other
objects on the surface of the PV module.
10
Astronergy PV modules adopt high and low current 5.1 Environment
bins, and the handlers need to place them separately
Recommended ambient temperature: -20°C to 50°C;
and mark them according to the markings on the
extreme operating ambient temperature for PV
power list on the PV module outer packaging (for
modules: -40 °C to 85°C.
example, 670W-L means low current bin; 670W-H
means high current bin; the current division method Mechanical load on PV modules: under standard
required by other customers is similar); According to installation conditions, the maximum tested
the system design requirements, modules of the same snow/wind load is 5400 Pa/2400 Pa and the design
current bin are usually required to be installed in the load (considering a safety factor of 1.5 times) is
same array. 3600 Pa/1600 Pa. Refer to 5.3 for detailed
installation and mechanical loads.
If the customer requires PV modules to be
distinguished by color, the outer packaging box shall PV modules are strictly forbidden to be installed
be marked accordingly, and the PV modules shall be and used in environments with excessive amounts
marked to prevent confusion when they are taken out of hail, snow, hurricanes, sand, soot, air pollution,
of the packaging box and stacked up. According to the and etc. PV modules are strictly forbidden to be
system design requirements, the color of PV modules installed or used in environments where there are
in the same row or the same array should be the same. strongly corrosive substances (e.g. salt, salt spray,
brine, active chemical vapors, acid rain, strong
Modules should be stored in a dry and ventilated vapor confined environments or any other
environment on a flat ground. Do not place modules substance that will corrode PV modules and affect
on soft ground to avoid damage or dumping of the their safety or performance).
modules due to ground deformation or collapse. Do
not place modules on area with poor water drainage. If the PV modules will be installed in special
environments such as high temperature and high
For long-term storage, it is recommended to store the humidity environments, humid salt-mist
modules in a standard warehouse with regular environments (C3+areas specified in ISO 9223),
inspection, reinforce the package in a timely manner if marine and floating environments and farms, the
any anomalies are found. purchaser or user needs to inform Astronergy in
advance. The types of PV modules, BOM, and
warranty issues will be decided by mutual
agreement between the parties.
11
between the surface of the PV module and the ground and regional regulations or corresponding
surface, as shown in Fig. 1. The power output of a PV international standards.
module is maximized. when it faces the sun directly.
The PV module must be securely fastened to the
mounting system. If the PV module is mounted in a
snowy area, the height of the mounting system
should be designed in a way that the lowest end of
the PV module is not covered by snow. In addition,
it should be ensured that the lowest end of the PV
module is not shaded by surrounding trees or other
Fig. 1 Schematic diagram of tilt angle
vegetation.
For northern hemisphere, PV modules should
When the PV module is mounted on a rack parallel
preferably face south. For southern hemisphere, PV
to the roof, the minimum clearance between the PV
modules should preferably face north. For detailed
module frame and the roof is 10cm, which is
mounting inclination, please follow local regulatory
necessary for air circulation to prevent wiring
guidelines or the recommendations of an experienced
damage of the PV module.
installer. Astronergy recommends an installation tilt
angle of no less than 10°, so that when it rains, the dust
The PV module frame will suffer thermal
on surface is easily carried away by the rainwater, thus
expansion and contraction effect, therefore the
reducing the number of times of clean; at the same
space between two adjacent PV module frames
time, it helps the water on the surface of the PV
should be no less than 10mm when mounted.
module to flow away, avoiding the long-term
accumulation of large amounts of water on the glass For special installation areas (such as high altitude,
surface, which can affect the appearance and mountain tops, coastal areas, wind vents), project
performance of the PV module. sites with frequent strong winds, it is recommended
PV modules connected in series should be installed in to use square gaskets, anti-loosening nuts,
the same orientation and angle. Different orientations anti-loosening gaskets, thickened gaskets, etc.
5.3 Mounting Guide methods are used, the warranty of Astronergy will
be invalid.
PV module mounting system must be composed of
durable, corrosion-resistant and UV-resistant 5.3.1 Bolted mounting
materials, and it must be inspected and tested by a All PV modules must be secured with at least 4
third-party testing organization with static
bolts. The specific corresponding airborne values are
mechanical analysis capabilities meeting national
12
shown in Table 2. 9~12Nm for M6 bolts and 17~23Nm for M8 bolts.
Due to the possible difference of bolt material, the
!ATTENTION specific torque value is subject to the information
confirmed by the bolt supplier.
In order to achieve maximum safety precautions
against wind and snow loads, it is recommended that ⑤ When using 30mm height frame module, it is
all available mounting holes should be used. The bolt recommended to select fasteners ≤ 20mm length.
installation steps are as follows (Fig. 2).
13
provided by Astronergy) which should be made
with stainless material and treated with an
anti-corrosion process (e.g. hot dipped galvanizing).
Each PV module needs at least four clamps to be
fixed. The module clamps should not come into
contact with the glass and should not deform the
frame, otherwise they may cause module damage.
14
Fig. 10 Installation schematic diagram of mid clamp
Fig. 7 Top view of fringe clamp ⑦ To prevent modules from coming off the fixed
device after installation, it is suggested to choose
fringe and mid clamps and make contact with the A
side of the frame with groove patterns. Suggest to
have 9 patterns with a space between 2 adjecent
patterns of 1.2mm and a depth of 0.6mm, as shown
in figure 7.
15
Table 2 Bolt installation diagram and corresponding mechanical load value
+5400Pa
-2400Pa
CHSM54N(DGT)(BLH)/F-BH
CHSM54M(DG)/F-BH Long side frame with 4 bolts mounting (990mm holes),
CHSM54N(DG)/F-BH guide rails vertical long side frame
CHSM54M(DGT)/F-BH 1722*1134*30
CHSM54N(DGT)/F-BH
CHSM54M(DG)/F-HC
CHSM54N(DG)/F-HC
+5400Pa
-2400Pa
+5400Pa
-2400Pa
CHSM60M(DG)/F-BH
CHSM60N(DG)/F-BH Long side frame with 4 bolts mounting (990mm holes),
CHSM60M(DGT)/F-BH guide rails vertical long side frame
1755*1038*30
CHSM60N(DGT)/F-BH
CHSM60M(DG)/F-HC
CHSM60N(DG)/F-HC
+3600Pa
-2400Pa
16
Table 2 (Renewal)
Module type Module size L*W*H (mm) Installation diagram Load value
+5400Pa
-2400Pa
+3600Pa
-2400Pa
CHSM60M(DG)/F-BH
Long side frame with 4 bolts mounting (1100mm
CHSM60N(DG)/F-BH
holes),guide rail coincides long side frame
CHSM60M(DGT)/F-BH
CHSM60N(DGT)/F-BH
CHSM60N(DG)/F-HC
+5400Pa
-2400Pa
+3600Pa
-2400Pa
17
Table 2 (Renewal)
+5400Pa
-2400Pa
Long side frame with 4 bolts mounting (1400mm holes), guide rails
vertical long side frame
CHSM66M(DG)/F-BH 2384*1303*35
+3600Pa
-2400Pa
+5400Pa
-2400Pa
CHSM48N(DGT)/F-BH
Long side frame with 4 bolts mounting (1300mm holes), guide rails
CHSM72M(DG)/F-BH
2094*1038*30 vertical long side frame
CHSM72N(DG)/F-BH
2094*1038*35
CHSM72M(DGT)/F-BH
CHSM72N(DGT)/F-BH
+3600Pa
-2400Pa
18
Table 2 (Renewal)
Module type Module size L*W*H (mm) Installation diagram Load value
+5400Pa
-2400Pa
CHSM48N(DGT)/F-BH
Long side frame with 4 bolts mounting (1400mm holes),
CHSM72M(DG)/F-BH 2256*1133*35
guide rails vertical long side frame
CHSM72N(DG)/F-BH 2278*1134*30
CHSM72M(DGT)/F-BH 2278*1134*35
CHSM72N(DGT)/F-BH
+3600Pa
-2400Pa
+5400Pa
-2400Pa
+3600Pa
-2400Pa
19
Table 3 Range of clamp mounting and corresponding mechanical load value
Refer to
Refer to
Refer to Figure Figure 6
Module size Refer to Figure 4 for Figure 5 for
Module type 3for installation for
L*W*H (mm) installation method installation
method installation
method
method
CHSM54N(DGT)(BLH)/F-BH
CHSM54M(DG)/F-BH +1800Pa +1200Pa
+3600Pa +5400Pa
CHSM54N(DG)/F-BH -1800Pa -1200Pa
-2400Pa -2400Pa
CHSM54M(DGT)/F-BH 1722*1134*30 Installation Installation
Installation scope Installation scope
CHSM54N(DGT)/F-BH scope scope
266~466mm 266~466mm
CHSM54M(DG)/F-HC 150~250mm 0~250mm
CHSM54N(DG)/F-HC
+1800Pa
+3600Pa +5400Pa
-1800Pa
CHSM60M(DG)/F-BH -2400Pa -2400Pa
1755*1038*30 Installation ---
CHSM60M(DGT)/F-BH Installation scope Installation scope
scope
1/4L±50mm 1/4L±50mm
150~250mm
CHSM60M(DG)/F-BH +1800Pa +900Pa
+3600Pa +5400Pa
CHSM60N(DG)/F-BH -1800Pa -450Pa
-2400Pa -2400Pa
CHSM60M(DGT)/F-BH 1908*1134*30 Installation Installation
Installation scope Installation scope
CHSM60N(DGT)/F-BH scope scope
320~520mm 320~520mm
CHSM60N(DG)/F-HC 150~250mm 0~250mm
+1800Pa
+3600Pa +5400Pa
-1800Pa
CHSM60M(DG)/F-BH -2400Pa -2400Pa
2172*1303*35 Installation ---
CHSM60M(DGT)/F-BH Installation scope Installation scope
scope
375~425mm 375~425mm
150~250mm
+3600Pa +5400Pa
-2400Pa -2400Pa
CHSM66M(DG)/F-BH 2384*1303*35 --- ---
Installation scope Installation scope
450~550mm 450~550mm
+5400Pa
+3600Pa/-2400Pa
CHSM72M(DG)/F-BH -2400Pa
2094*1038*30 Installation scope --- ---
CHSM72N(DG)/F-BH Installation scope
1/4L±50mm
1/4L±50mm
+5400Pa
CHSM72M(DG)/F-BH +3600Pa/-2400Pa
2256*1133*35 -2400Pa
CHSM72N(DG)/F-BH Installation scope --- ---
2278*1134*35 Installation scope
CHSM72M(DGT)/F-BH 400~500mm
400~500mm
CHSM72N(DGT)/F-BH
2278*1134*30 +3600Pa/-2400Pa +5400Pa --- ---
20
Installation scope -2400Pa
430~530mm Installation scope
430~530mm
+5400Pa
CHSM78M(DG)/F-BH 2465*1134*35 -2400Pa
--- --- ---
CHSM78N(DG)/F-BH 2465*1134*30 Installation scope
480~530mm
(Note: For other installation methods and load capacity not listed in the table, please contact Astronergy for
confirmation.)
The bolts and clamps used for the installation of the tracking bracket shall comply with the requirements of 5.3.1
and 5.3.2
Table 4 Installation diagram of the tracking bracket and corresponding mechanical load values
Location Outer
Mounting
Module size of diameter of Load
Installation method Module type hole spacing
L*W*H (mm) mountin flat gasket value
(mm)
g holes (mm)
A1-A3:400
A1、A2、 +2100Pa
CHSM66M(DG)/F-BH 2384*1303*35 B1-B3:/ 16
A3、A4 -2100Pa
C1-C3:1400
A1、A2、 +2100Pa
A3、A4 -2100Pa
CHSM72M(DG)/F-BH
A1-A3:400
CHSM72N(DG)/F-BH 2278*1134*30
B1-B3:/ 16
CHSM72M(DGT)/F-BH 2278*1134*35
1P Tracking bracket C1-C3:1400
CHSM72N(DGT)/F-BH
C1、C2、 3200Pa
C3、C4 -2400Pa
21
A1-A3:400
CHSM78M(DG)/F-BH 2465*1134*30 A1、A2、 +1800Pa
B1-B3:1200 16
CHSM78N(DG)/F-BH 2465*1134*35 A3、A4 -1800Pa
C1-C3:1500
C1、C2、 +1600pa
A3、A4 -1200pa
CHSM72M(DG)/F-BH
A1-A3:400
CHSM72N(DG)/F-BH 2278*1134*30
B1-B3:无 16
CHSM72M(DGT)/F-BH 2278*1134*35
C1-C3:1400
CHSM72N(DGT)/F-BH
C1、C2、 +2600pa
C3、C4 -2200pa
2P Tracking bracket
(Note: For other installation methods and load capacity not listed in the table, please contact Astronergy for
confirmation.)
Temperature(℃)
Under certain conditions, the output current and/or
voltage of the PV module may be higher than the value 24 ~ 20 1.02
under standard testing conditions. Therefore, the value
22
19 ~ 15 1.04 Where: N is the number of PV modules in a single
string. Voc is the open-circuit voltage of each PV
14 ~ 10 1.06
module (refer to the nameplate or product datasheet).
9~5 1.08
!ATTENTION
4~0 1.10
Depending on the maximum fuse ratings of the PV
-1 ~ -5 1.12
module, and the local electrical installation standards,
-6 ~ -10 1.14
the connection of parallel strings of PV modules needs
-11 ~ -15 1.16 to be equipped with suitable fuses or preventive diodes
for circuit protection purposes.
-16 ~ -20 1.18
is the open-circuit voltage temperature coefficient of from the positive terminal of one module to the
the selected module (refer to corresponding datasheet). negative terminal of the next module. PV modules can
Tmin(°C) is the expected lowest ambient temperature at be wired in parallel to increase the current by
the system installation site. connecting the positive terminal of one module to the
positive terminal of the next module. If a module is not
The string voltage must not be higher than the connected correctly, the bypass diode may be
maximum system voltage, as well as the maximum damaged.
input voltage of the inverter and other electrical
equipment installed in the system. To ensure the above
requirements, the open-circuit voltage of the string
needs to be calculated using the following formula:
23
module. Be aware that if there are two or more
strings parallelly connected, there must be an
overcurrent protection device on each string.
24
prevents module degradation due to shading or The grounding requirements must be checked in
covering. Refer to the junction box diode accordance with the applicable regulations and
specification provided in the relevant product standards before work is started.
datasheet for more details. I When the localized hot
Use the marked 5.5 mm grounding holes to ground
spot phenomenon occurs in the PV module due to
the anodized frame. Use one M5 nut, two M5 cut
partial shading or coverage, the diode in the
washers, one M5 plain washer, one M5 spring
junction box will start to work, so that the module
washer, and one M5 bolt and the copper wire. All
current will no longer flow through the hot spot cell,
nuts, bolts, and washers shall be of type M5 and
so as to limit the heat and loss of the PV module.
made of stainless steel (Fig. 18).
When a diode failure is suspected or found, please
contact Astronergy and do not attempt to open the
Insert the bolt through the cup washer and wrap the
junction box cover.
copper wire around the bolt. (Note that the copper
wire cannot be attached directly to the aluminum.)
6.3 Grounding
25
These holes should be used for grounding purposes electric shock or personal injury.
and should not be used for mounting the modules.
Take routine maintenance to keep PV modules free of
7 Maintenance snow, bird droppings, seeds, pollen, leaves, branches,
dust, stains, etc.
PV modules must be inspected and maintained
regularly, especially during the warranty period, which 7.2 PV module cleaning
is the responsibility of the user. This helps to find and
If the PV module has a sufficient angle of tilt (at least
figure out problems in time and ensure the safe and
15°), it is generally not necessary to clean the PV
effective operation of the PV system.
module (as the rainfall will provide a self-cleaning
7.1 Routine Inspection effect). If there is a large accumulation of dirt on the
PV module surface that has seriously affected the
PV modules in PV arrays should be inspected regularly
power production, the module can be rinsed with water
for damages, such as glass breakage, cable breakage,
without detergent, and use a gentle sponge or brush to
junction box damage, cell cracks, and backsheet
clean the surface during the cooler hours of the day.
breakage and other factors that cause functional and
Dust must not be scraped or wiped off under dry
safety failures of PV modules. If any of the above
conditions as this may result in tiny scuff marks. For
problems occurs, the supplier should be notified to
snow removal, the PV module surface can be cleaned
replace the broken module with a new one of the same
with a brush with soft bristles.
type in time.
For more details on cleaning and maintenance, please
It is recommended to perform preventive inspection refer to the PV Module Cleaning Manual. .
every 6 months and not to replace the components of
PV modules without authorization. When conducting
inspection or maintenance in term of the electrical and
mechanical performance, it is recommended that
qualified professionals perform the work to avoid
26
Modified version and date
·Rev 1.0, released in September 2022.
Add: No. 1 Jisheng Road,Jianshan New Zone Haining 314415 Zhejiang P.R. China
www.astro-energy.com/
27