P3 Manual
P3 Manual
Reference Manual
TABLE OF CONTENTS
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 2 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Before you can install P3, Microsoft Windows, Windows 95/98, or Windows NT must be running on
your computer. Because the files on the P3 program CD-ROM are compressed to save space, you
must use the P3 Setup program.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 3 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 4 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
1. Choose File, New and type a unique four-character name in the Project Name field.
2. P3 stores the new project in the current folder. To create the project in a different folder, click
Browse and select a different drive and/or folder.
3. Specify a Number/Version (e.g. Baseline, update 1 etc.), Project Title, and Company Name to
describe the project.
4. The default project-planning unit is day. To change this, click and select Hour, Week, or Month.
5. You can also change the number of workdays per week or the day of the week that work starts.
These fields determine the workweek for Calendar 1.
6. In the Project Start field, click and select a date from the pop-up calendar.
7. Use the mouse or arrow keys to move in the calendar and double-click a date to select it in the
Project Start field. To move month to month, click the up/down scroll arrows (or use PgUp/PgDn
keys). To move year to year, drag the scroll box (or use Ctrl+Pg Up/PgDn keys).
8. To impose an optional project finish date, type a date in the Project Must Finish by field. This
constrains the scheduled project end date.
9. In the Decimal Places field, select the number of decimal places to use for resource and cost
data.
10. If costs in your project exceed Rs.100 million for a summary group, change the decimal-place
configuration to 0.
11. If the project you add will be part of a project group, mark the Add This New Project to a Project
Group checkbox. Click in the Project Group field and select a project group.
12. You can also create a new project group; type a unique four-character project name in the
Project Group field.
13. P3 automatically assigns a two-character project ID to identify a project within a group. The ID
becomes the first two activity ID characters for each activity in the project. Accept the default or
specify a project ID; at least one character must be alphabetic.
14. Click Add to create the new project.
When you add a new project, the default layout appears for the Bar chart; the Activity columns and
Bar chart contain no data. P3 places the cursor in the Edit bar for you to specify the first activity ID.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 5 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 6 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 7 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Defining Calendars
All activities in P3 are assigned to a calendar that defines when work on the activity can occur. Each
project has a global calendar and a standard calendar, called calendar 1.
Every resource has its own calendar. P3 uses an activity calendar as the base, or template, for each
resource calendar. Specify changes to the base calendar to customize each resource calendar.
The global calendar enables you to specify non-work periods, exceptions, and holidays that apply to
all calendars. The changes you make in global calendar will reflect in other base calendars.
Calendar 1 is the default base calendar to which all activities and resources are assigned unless you
specify another calendar. You can change calendar 1, but you cannot delete it.
Add: Opens the Add Calendar dialogs box where you can create a new calendar. P3 will ask you the
Calendar ID and Description. In P3, you can specify 32 Calendars per project
Delete: Deletes the selected calendar from the project. Click yes to confirm. Activities and resources
assigned to the deleted calendar are reassigned to calendar 1.
Transfer: Copies all calendars from another project to the current project, or enables you to transfer
one calendar to another within the same project.
Note: To transfer calendars between projects, both projects must have the same planning unit.
Holidays: Opens the Holidays List dialog box so you can specify non-work time or exceptions to non-
work time not addressed by the Global calendar. You can give the start and finish dates of holidays or
you can specify one holiday by leaving end date empty.
Repeating: Repeat holiday every year.
Standard: When you select the Global Calendar in the Calendar field, clicking Standard opens the
Standard Global Information dialog box where you can define information for all calendars, such as
the Calendar Start Date, Project Start Date, and the Week Starts On day. Here you can specify
working days in a week.
Work/Non work: Use the appropriate button to change the status of the selected date to work or non-
work. A shaded date box indicates non-work time; a UN shaded box indicates work time.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 8 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Adding activities
When adding activities, consider the following:
§ P3 automatically assigns an activity ID.
§ P3 assigns duration of one planning unit, which you can change. P3 automatically sets the
remaining duration equal to the original duration.
§ P3 calculates activity duration based on the type of activity. For some types of activities, you
enter duration; for other types of activities, P3 calculates duration.
§ If your layout is grouped and you add an activity to a group, P3 automatically applies the group
values to the new activity.
Activity IDs can consist of up to 10 characters: letters, numbers, or a combination of both. Each
activity ID must be unique.
Note: When you add a new project, P3 does not automatically assign an ID. Instead, P3 places the
cursor in the edit bar above the Activity columns for you to specify an ID. Once you add the first
activity ID, P3 assigns IDs for each subsequent activity you add, incrementing each ID by 10.
When P3 assigns a new ID, it checks whether the ID already exists in the project. If it exists, P3
searches in increments of 10 until it finds an unused ID. If you delete an activity, that ID becomes
available for a new activity.
You can change the assigned ID at any time, provided you have Exclusive access to the project.
If you add activities to a project that is part of a project group, the project ID automatically appears as
the first two characters in the ID field, followed by the incremented number.
If the selected activity has an ID containing all alphabetic characters, P3 appends the incremented
number to the right of the ID. For example, if activity AAA is selected, the new activity will have an ID
of AAA10. If the activity contains 10 alphabetic characters, such as AAAAAAAAAA, the new activity
will have an ID of 10.
If you want P3 to increment IDs by a value other than 10, choose Tools, Options, and Activity
Inserting. Type a value in the Increment field.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 9 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Activity Types
To open the Activity form
Use any of the following methods to open the Activity form:
• Double-click an activity.
• Select an activity and choose Edit, Edit Activity.
• Choose View, Activity Form, or press F7.
Definitions:
ID: Activity ID
OD: Original Duration. (Note: This field always defines the planned duration)
Pct: Percent Complete (Note: This field will be zero during planning phase and be filled out
during updating process. 100% means that you have to give EF)
Cal: Calendar (Note: Default calendar is Cal 1, until and unless specified)
ES: Early Start. (Note: This field becomes AS = Actual Start, on checking)
EF: Early Finish. (Note: This field becomes AF = Actual Finish, on checking
Uncheck this field, if the activity is not 100% complete)
RD: Remaining Duration. (Note: You can use either Pct or RD. If you specify Pct, RD will be
calculated automatically and vice versa)
Type: Activity Type. (Note: Details of activity types will be discussed later)
Codes: The last and the very bottom field of Activity form represent the activity codes and WBS
system that you have defined earlier.
Activity Types:
1. Task Driven (Fixed Duration)
2. Resource Driven (Duration dependent on Resources)
3. Hammock (No specific duration, duration is calculated on the basis of relationships)
1. Task: (Fixed duration) P3 schedules a task activity according to the base calendar assigned to
the activity. Designate an activity as a task activity if you aren't assigning resources to the
activity, or if the assigned resources should be scheduled according to the activity's base
calendar; rather than each resource calendar.
For example, several activities must be done in the week before a completion of the building. It
doesn't matter whether the resources are available earlier than that week, or whether they will
otherwise be scheduled for time off during that week--these activities must be scheduled during
a specific time-period, and their scheduling controls the scheduling of their resources.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 10 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
3. Meeting: (Resource Driven) Meeting activities require that all resources work together
simultaneously as a team to complete the work. They are useful for scheduling meetings and
any activities where resources cannot work independently.
For example, in factory relocation project, heavy equipment resources and a crew resource
must be onsite at the same time for one week. Both the equipment and the crew resources are
driving--the activity's duration depends on their work. If you define this activity as a meeting
activity, P3 schedules it only when both the equipment and the crew are available for the same
one-week time period. P3 schedules any non-driving resources, such as an inspector in this
example, according to the combined calendars of the crew and equipment--the conglomerate of
the driving resources' calendars.
4. Milestones/ Flags: (Zero Duration) Use milestones to indicate the beginning or end of a major
event or phase, or any other important point in your project. Use flags to signal the start or finish
of an activity or group of activities. Milestones and flags have no original or remaining duration.
You must assign actual dates to milestones. P3 schedules milestones and flags according to
the activity's base calendar.
In the Bar chart, milestones appear as diamonds in the Bar area, and flags appear as flags. In
PERT, start and finish milestones and flags are represented by an activity with only one end,
depending if the activity is a start or finish milestone or flag.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 11 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
If you enter an activity code value that is not defined in the Activity Codes Dictionary, click yes to add
it and enter a description in the Description field.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 12 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Tips Press ESC to cancel organizing. Press Ctrl+up/down arrow to jump to the next band at the
same level; press Ctrl+Alt+down/up arrow to jump to the next band at any level. When you add an
activity to a group, P3 automatically applies the value of that group to the new activity.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 13 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
View Layouts
Open a Layout:
P3 opens only one layout at a time for each project. If you share projects with other users, P3 can
copy a layout if two or more users need to access it at one time. You must save the copied layout as a
unique layout to save your changes.
P3 remembers the last layout you had open for the last 25 projects. You can change the current
layout while you have a project open.
To open a layout
• Select View, Layout, Open.
• Select a layout and click Open.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 14 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
To
Displays the folder the duplicate project will be copied to. To change the folder or drive, click Browse
and select a different drive or folder.
Project Group: Type the name of the new project. The name can contain letters, numbers, or a
combination of both.
Project Name: If you are copying a project that is part of a project group, type the new project name
here. Then type a two-character project ID to identify the project in the Project ID field.
Planning Unit: P3 uses the planning unit for the project that you are copying by default. You can select
a different planning unit for the new project. See Revise the planning unit for more details.
Project ID: When you copy a project that is associated with a project group; type a two-character
prefix to identify activities in the project. One character must be an alpha character; the other can be
an alpha or a numeric character.
Title: Type a project description (up to 36 characters).
Company: Type a company name (up to 36 characters).
Add the Following Characters to the Left/Right of the Current IDs: Distinguish the activity IDs in the
duplicated project from those in the original project by adding characters to the left or right of the
original activity IDs. Type the characters in the field provided and choose the Left or Right option.
Browse: Click to view or change the location for the copied project.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 15 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 16 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 17 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Early Constraint: Mark this checkbox to assign an early start or early finish constraint. Choose the
Start or Finish option and select the date.
1. Start: An early start constraint affects only the early dates of an activity. Use an early start
constraint to ensure that the start of an activity is not scheduled before a specified date; for
example, use this constraint when the start of an activity depends on the delivery of a piece of
equipment. An early start constraint affects the schedule only if the constraint date is later than
the calculated early start date for the activity.
Note: If an early start constraint date that falls on a non-work period (such as a holiday or weekend) is
imposed on an activity, P3 imposes an early start date that is the first work period after this early start
constraint date. For example, if December 25 is the early start constraint date and December 25 is a
non-work-period, P3 imposes an early start date of December 26.
2. Finish: The early finish constraint functions exactly like an early start constraint, except that it is
applied to the calculated early finish dates for an activity. It changes the schedule only if the
constraint date is later than the calculated early finish date for the activity. This constraint usually
applies only to activities that have few if any predecessors and that must finish before the next
project phase. It can be used to reduce the free float for the activity.
Note: If an early finish constraint date that falls on a non-work period (such as a holiday or weekend)
is imposed on an activity, P3 imposes an early finish date that is the first work period following this
early finish constraint date.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 18 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
3. Start On: Mark this checkbox and then select the date when you want the activity to start.
A start on constraint affects an activity as if both early start and late start constraints are imposed
on it. The early start constraint revises the early dates only if the imposed date is later than the
calculated early start date. The late start constraint revises the late start dates only if the imposed
date is earlier than the calculated late start date.
Note: If a start on constraint date that falls on a non-work period (such as a holiday or weekend) is
imposed on an activity, P3 imposes an early start date that is the first work period following this
imposed date and a late start date that is the first work period prior to this imposed date. For example,
if December 25 is imposed as a start on date, P3 imposes an early start date of December 26 and a
late start date of December 24.
4. Expected Finish: Mark this checkbox and then select the date when you expect this activity to
finish.
Use the expected finish constraint to update the schedule based on an estimate of the expected
finish of an activity. P3 calculates the remaining duration of activities with expected finish
constraints as the work period differences between their calculated early start dates and the
assigned expected finish dates. Ensure that the expected finish date is not earlier than the
scheduled early start, or that the remaining duration for the activity is not set to zero--a value
reserved only for completed and dummy activities.
Float Constraint: Mark this checkbox and then choose Zero total float or Zero free float.
1. Zero Total Float: Use the zero total float constraint to make an activity critical. When you impose
a zero total float constraint, P3 sets the late dates for the activity equal to its early dates, giving it
zero total float. This change of late dates also affects the late dates of other activities that precede
it. If the float for the activity is already zero or a negative value, P3 does not apply this constraint.
2. Zero Free Float: The zero free float constraint (the as-late-as-possible constraint), allows an
activity to start as late as possible without delaying its successors. P3 places the finish of the
activity one work period before the start of the successor activity, assuming a finish to start
relationship. An activity with free float can start as late as possible without delaying its immediate
successors. You may want to impose this constraint on activities involving payments or deliveries.
Late Constraint: Mark this checkbox to assign a late start or late finish constraint. Choose the Start
or Finish option and then select the date.
1. Start: A late start constraint can affect the late dates of an activity if the constraint date is earlier
than the calculated late start date for the activity. This constraint reduces the amount of total float
in successive activities. Usually, it is the result of an agreement among various project
participants that some element of the project will begin on or before a particular date.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 19 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Note: If a late start constraint date falls on a non-work period (such as a holiday or weekend), P3
imposes a late start date that is the first work period prior to this date. For example, if December 25 is
imposed as a late start constraint date, P3 imposes a late start date of December 24.
If a constrained activity has an actual start date, the constraint is treated as a late finish constraint
(actual start + original duration = late finish).
2. Finish: A late finish constraint affects only the late dates. Managers often use it to set
intermediate completion dates or milestones. The assigned constraint date must be earlier than
the scheduled late finish date for the activity.
Note: If a late finish constraint date that falls on a non-work period (such as a holiday or weekend) is
imposed on an activity, P3 imposes a late finish date that is the first work period prior to this late finish
constraint date.
Mandatory: Mark this checkbox to assign a mandatory start or finish constraint to an activity. Choose
the Start or Finish option and then select the date.
1. Start: The mandatory start constraint sets both the early and late start dates equal to a specified
date; P3 does not override the constraint during schedule calculations. Therefore, an imposed
mandatory start constraint sets the early dates for all paths leading from an activity and the late
dates for all paths leading to it. Impose this constraint with caution since it can violate network
logic and cause the dates for an activity to precede those of its predecessor(s).
Note: Avoid imposing a mandatory start constraint date that occurs on a non-work period, such as a
holiday or weekend.
2. Finish: The mandatory finish constraint sets the early and late finish dates equal to the imposed
date. It also sets the late dates of paths leading to the activity and the early dates of paths leading
from it. P3 does not override the mandatory finish constraint during schedule calculations. Impose
this constraint with caution since it can violate network logic by allowing P3 to schedule a
successor activity before its predecessor(s).
Note: Avoid imposing a mandatory finish constraint date that occurs on a nonworkperiod, such as a
holiday or weekend.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 20 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Data Date: Select the date through which you have recorded progress. P3 schedules activities from
the project data date, using the project start date as the initial data date. Be sure to change the data
date each time you record progress for activities. The data date is the beginning of the hour, day,
week, or month, depending on the project's planning unit.
Scheduling report
P3 automatically produces a schedule statistics listing along with the following report listings. Clear
the checkbox besides any listing you do not want to produce.
Activities With Out-Of-Sequence Progress: Produces a listing of activities that have progressed out
of the order specified by the network logic.
Run Report Series: Produces the specified series of reports after calculating the schedule. To define
a series choose Tools, Tabular Reports, Production. An empty field indicates that no report series will
be produced.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 21 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Common Problems:
Loop: If P3 detects a loop in the network logic during scheduling, P3 immediately stops calculating
the schedule and produces a loop report. A loop is circular logic in a network; that is a path of
activities that closes back on itself. P3 sends a loop report to the P3.OUT file. The loop report lists the
activities that form the loop including the activity IDs and descriptions.
Example:
100 Block Masonry
110 Plaster
120 Paint
130 Door
140 Block Masonry
The first and last activities in a loop are the same. To eliminate a loop, delete precedence
relationships.
Negative Float: If you specify the project end date and apply constraints to activities, and the
requirements are not fulfilling, P3 gives you negative floats. The negative floats should be eliminated
or adjusted according to requirement before proceeding further to planning.
Open Ends: Lists activities without predecessor or successor relationships could create problem
scheduling the project in P3. You must check the open-ended activities in report and must connect all
activities.
REMEMBER that a CPM must have one start and one finish. All other activities must be
interconnected.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 22 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Defining Resources
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 23 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 24 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Resources Allocation
Use this command to quickly assign people or equipment resources to activities. You can assign a
resource and corresponding cost code to one or more selected activities.
Specify the budgeted quantity of the resource necessary to complete the activity (ies) and/or how
many units per time period the resource needs to work on the activity (ies). Once the assignments are
made, use the Resources form to view additional resource data automatically calculated by P3.
Assignment
Resource: Specify any resource. Select a resource from the list predefined in the Resource
Dictionary. You can also enter a resource not currently in the dictionary; P3 adds it automatically.
Cost Account/Category: Specify any cost account and optional cost account category to track costs
associated with the assignment. Select a cost account from the list predefined in the Cost Accounts
Dictionary. You can also enter a cost account not currently in the dictionary; P3 adds it automatically.
This Is A Driving Resource: Mark this checkbox to make the selected resource a driving resource. If
the selected resource is marked as driving in the Resource Dictionary, P3 marks the Driving Resource
checkbox automatically.
Budgeted Quantity: Specify a total budgeted quantity required to complete the activity (ies) if the
resource is driving. For non-driving resources, this field is optional. However, if you enter an amount in
this field for a non-driving resource, P3 calculates the number of units per day based on the activity's
remaining duration.
Units Per <time-period>: Specify the number of resource units (such as hours) per day to allocate to
the activity (ies). If you enter both Quantity and Units per Hour amounts, and are assigning a driving
resource, P3 calculates resource duration automatically. This is the only case in which P3 calculates
the resource duration.
Res Lag/ Duration:
Resource lag is the number of work periods from the start of the activity to the start of resource use.
Resource duration is the number of work periods an activity uses a resource. When P3 uses
remaining duration to calculate the quantity to complete, it uses the resource remaining duration. If
you don't specify resource duration, P3 uses the schedule remaining duration.
Resource lag and duration are specified and used together. For example, an activity with duration of
30 days can have a resource with a 15-day duration and a 5-day lag, indicating that use of the
resource begins 5 days after the activity starts, and continues for 15 days.
Note When you specify resource lag and duration, you must reduce the resource duration to show
progress. P3 does not automatically reduce resource duration when you record activity progress.
Insert: Click to add another resource to the activity (ies).
ALL OTHER FIELDS W ILL BE USED AT THE TIME OF UPDATING.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 25 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 26 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Resource Leveling
Resource leveling is a process that helps you assure there are sufficient resources available to
perform the activities in your project as they are planned. While computerized resource leveling
provides you with a valid resolution of resource conflicts, it may not necessarily be the optimal
solution. Through analysis, you may be able to find alternate solutions, such as changing the project
logic to avoid resource conflicts, or reallocating resources.
Once you assign resources to activities, you can produce onscreen profiles to examine resource use.
If a profile indicates that some activities need more resources than are available, use leveling to
redistribute resources.
To level resources
1. Choose Tools, Level.
2. Choose whether to perform forward or backward leveling, and the data date for the leveling run.
3. Choose whether to use resource smoothing, and indicate how P3 should treat your project finish
date: open-ended (non-time constrained smoothing) or fixed (time constrained smoothing)
4. Specify whether you want P3 to automatically produce a series of reports when leveling
completes.
5. In a project group environment, choose whether to level using the project group's resource limits
or net availability
6. Choose whether to level the project through its completion or only up to a date you specify.
7. Indicate how P3 should prioritize activities when they compete for the same resource at the same
time.
8. Click Options to modify the standard scheduling/leveling options.
By default, P3 produces a leveling analysis report.
9. Click Resources to specify the resources you want to level. To specify all resources, click All Res.
You can add or remove individual resources from the list.
10. Click Level Now.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 27 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Choose Tools, Project Utilities, Targets to create a copy of the current project and designate it as a
target. As the project progresses and changes occur, you can globally incorporate these changes into
the target project for an accurate comparison of data. For step-by-step instructions, see Update the
target project globally.
Before you update a schedule the first time, it is suggested that you create a target plan. Follow these
steps to make a complete copy of the original schedule and designate it as a target.
Note: You can create as many target projects as you want, but you can compare only two targets to
the current schedule at any one time.
To create and assign a target project
1. Open the project you want to create a target for.
2. Choose, Tools, Project Utilities, Targets.
3. Click the Target column and type a four-character project name for the target project.
4. Click OK, then click Yes to create the target.
5. Don’t forget to change the Number/ Version after making targets. At the time you are creating
target, you cannot change the Number/ Version. You have to change by open the target file
and change it by checking its overview.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 28 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Most projects progress somewhere between these two situations: some activities are progressing as
planned and some are not. If this is the case, you'll want to combine the two updating methods. Let
P3 calculate your project as if it is progressing exactly as planned, and then individually update those
activities and resources that have deviated from the plan.
Note After recording progress for the current period, always recalculate the schedule by pressing
F9 or choosing Tools, Schedule. Be sure to update the data date--the date from which P3 begins
schedule calculations.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 29 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Updating Resources
You need to update your resources and cost too. Since, things actually going at the field are not
exactly same as we planned earlier. For example, we planned that we need 100 man-hours to
complete the activity. But actually, 70 man-hours have already used and activity is 50% complete. At
this stage, P3 has 30 man-hours left out 100. But actually, we need more than 30, lets say 50 man-
hours. To overcome this flaw, you should update the resources and cost of each completed or started
activity.
Actual This Period: Specify the resources (qty.) used at this period.
Displays costs for a particular resource and cost account for the current period. P3 adds the actual
this period value to the actual to date value for quantities and costs. At the end of each update period,
use the Close Out button in the Resource Dictionary to reset all the values for this period to 0.
Now, other three fields start functioning. Some values are already there. If you are satisfy with the
values, go a head and close the activity form.
But, if the situation is like the above example, you have to update the resources accordingly.
You can fill one of the fields
To Complete
At Completion
To Complete: Displays the number of resource units required to complete the activity. The Quantity
to Complete equals Units Per Timeperiod x Remaining Duration. Autocost Rule 3 determines the
calculation method P3 uses when updating the actual quantity to complete. This field can display up
nine digits.
At Completion: Displays the total amount of resources required at the completion of an activity. This
value always equals the sum of the actual to date and the quantity to complete. The field can display
up to nine digits.
Variance (units): Displays the difference between the estimated quantity at completion and the
original budgeted amount. P3 automatically recalculates variance each time you change the At
completion or the Budgeted quantity values.
Don’t forget to
• Reschedule the plan
• Check the Cost/ Resource Plan
• Fix the problems (if any)
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 30 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Organizing:
Already been discussed
You can always reorganize the layout whenever you want.
Format Columns:
Use the Columns dialog box to modify column data, titles, widths, alignments, and fonts for Activity
columns.
Tip To change one or two columns quickly, double-click (or right-click) the column title and make
adjustments.
Column Information
Data: Choose the type of data for each column. Select from the list.
Title: Type a description for each column title (up to 40 characters). To insert a line break, enter a
pipe character where you want the line to break. For example, enter Original Duration as
Original|Duration so the word Duration appears in the second line of the column title.
Width: Enter a width for each column or let P3 calculate an average character width for each
column.
Align: Choose how to align column data: centered, right justified, or left justified.
Data Font: Choose a font for data in each column. Select a different font.
Column Title Font: Select a different font for column titles.
Show Lines Between Rows and Columns: Clear this checkbox if you do not want lines between
activity rows and columns.
Format Bars:
Use the Bars dialog box to add or delete bars, specify which bars show in the layout, the position for
bars, and more.
Defined Bars
Pos (Position): Type a position for each bar (1 through 99). P3 displays bars from lowest position
number to highest, beginning with position 1 at the top of each group of bars. Display multiple
bars in the same position or increase the vertical space between bars by skipping position
numbers.
Bar Description: Type a description for each bar (up to 40 alphanumeric characters). Note that
this field is text field. You can write anything you want
Visible: A marked checkbox indicates that the specified bar will show in the Bars area. Clear this
checkbox beside any bar that you do not want to show in the layout.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 31 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Key: Mark this checkbox to designate a bar as the key bar. Only one bar can be assigned as key.
Progress: A marked checkbox indicates that the bar will show activity progress in the color you
specify in the Color button. Clear this checkbox if you do not want to show activity progress on the
bars in the layout.
Critical: Mark this checkbox to have activity bars show critical highlighting in the color specified in
the Color button. Clear the checkbox if you do not want to show critical highlighting.
Neck: Mark this checkbox to indicate non-work time by indenting or "necking" schedule bars
(Early Start/Early Finish or Late Start/Late Finish) in the current or target projects. P3 indents bars
based on the activity's calendar. Bars also show necking when an activity has defined suspend
and resume dates or when an activity has out of sequence progress and the schedule option
Retained logic is enabled. Clear the checkbox beside any bar where you do not want to show
non-work time on schedule bars.
Display Progress and Criticality On Target Bar Based On: Choose whether target bars display
progress and criticality information from the current project or the target project.
Display Progress On Bars Based On: Choose whether to base progress on Remaining
Duration or Percent Complete, and then select a color to indicate progress on activity bars.
When basing progress on percent complete, the length of the progress indicator equals the
product of percent complete times the overall length of the bar. The length of the bar includes
non-work periods as well as work periods; therefore, the percentage point is not necessarily the
beginning of the remaining duration. This method enables you to show the percentage of the
overall duration and the amount of work completed on an activity, rather than the time remaining.
When basing progress on remaining duration, the progress indicator extends from the actual start
date of the activity to the point at which work on the remaining duration is scheduled to begin.
Show Critical Color On: Choose whether to show critical color on the bar, its endpoints, or both.
Click the Color button to select a different color for critical activities.
Modify: Shows the settings for the selected bar in the Modify Bar Definition dialog box.
Endpoints: Displays the Endpoints dialog box so you can define the shape and color for
endpoints, milestones, flags, and custom data items.
Pattern: Displays the Pattern dialog box so you can highlight bars based on activity codes.
Choose from a variety of colors and patterns for each code value to distinguish groups by code.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 32 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Example: Lets say, you want to show two bars on two rows representing Target Bar on Row 1
(Planned) and Actual Bars on Row 2. You already have a bar named “Early bar”. All you need to show
Actual Bars is to change the Bar Description.
But, to show Target (Planned) bar, you have to add new bar.
How to Add New Bar:
Click (+) and a new op up window will appear.
Description: Planned
Position: 1
Then you have two fields; Structure and Text. Stay in Structure
Start Point: Target 1 early start
Finish Point: Target 1 early finish
Bar: Bar
Now, move to vertical columns of these rows, you will see size, outline, and position, show
Sizeà Size of endpoints or bar
Positionà Above, Center, below. You can change by right click and select.
Outlineà means shadowing of endpoints or bar
Showà Means whether you want to show or not. Sometimes, you don’t like to show end points
and want to see just bars. You can do it easily by unselecting the “show” columns of end points
You can also change the bar color and milestone size.
Note: At this time, you don’t have any targets, but this exercise will help you later when you update
the schedule.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 33 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Format Timescale:
Use this command to control the time span and appearance of the timescale.
Density: Change the density of the timescale by dragging the scroll box. Move it to the left to
compress the timescale; drag it to the right to expand it.
Start Date/End Date: Enter a start and end date to limit the time span shown in the Bar chart layout.
Select a calendar date or click the rolling date button to use a rolling date specification.
Font: Specify the font for the timescale text.
Calendar Dates: Choose hours, days, weeks, months, or years, depending on the available space
and the minimum time unit set.
Minimum Time Unit: Select the smallest division of time to display on the timescale. Choose hours
(in hourly projects), days, weeks, months, quarters, or years, depending on the project's planning unit.
Show Fiscal Years/Start Month: To show the timescale as a fiscal year, mark this checkbox, then
select a start month for the fiscal year.
Show Manufacturing Weeks: To display a number for each week consecutively, beginning with
January, mark this checkbox.
Show Day Of Week: Mark this checkbox to show the day of the week in the timescale.
Ordinal Dates/Unit/Ordinal Start: To view the timescale using numbered divisions instead of dates,
mark the Ordinal Dates checkbox, select a unit, and then specify a start date.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 34 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Filters:
Filters control which activities display in the project window. Use this command to apply, view, add,
change, or delete filter specifications. You can also select (highlight) activities based on a filter
specification.
Criteria
ID/Description: Identifies the filter. P3 displays the current filter description in the status bar
of the project window.
Add: Adds a new filter specification to the project. Filter specifications use the prefix FL,
followed by a unique two-character ID.
Modify: Displays selection criteria settings for the selected filter in the Filter Specification
dialog box.
Delete: Removes the selected filter from the project. You cannot, however, remove the All
Activities and No Activities filters from a project.
Filter: Choose Filter to change the set of activities in the current layout, then choose a
method for applying the filter. Choose to replace activities shown in current layout, add
activities to the current layout, or remove activities from the current layout.
Select: Highlight Activities Which Match Criteria: Choose Select to highlight activities in the current
layout based on a filter specification.
Transfer: Enables you to copy all filters from another project to the current project, overwriting the
filters in the current project. To copy one specification from another project to the current one, click
Add, and then click Transfer.
Run: Applies the selected filter to the current layout.
Selection criteria
Select If: Select a data item for filtering activities from the current set.
Define up to seven selection statements per level.
Is: Specify selection criteria.
Low Value/High Value: Enter the data to use for the selection. Enter data in the High Value column
only when you specify WR (Within Range) or NR (Not Within Range) as criteria codes.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 35 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Tabular Reports:
1. Schedule
2. Resource
a. Resource control
b. Resource/cost productivity
c. Earned value [units]
d. Tabular resource
e. Resource loading
3. Cost
a. Cost control
b. Cost, price, and rates
c. Earned value
d. Tabular cost
e. Cost loading
4. Matrix
a. Activity matrix
b. Resource/cost matrix (Very important report for monitoring)
5. Custom report writer
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 36 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Organization
Group Rows By: Click and choose an activity code for grouping the rows of the report. For
example, if you group rows by department, each row lists one department code value.
Subgroup Rows By: Click and select a second activity code to report at a more detailed level.
Skip Lines: Skip from zero to three lines between grouped rows and sub-grouped rows.
Group Columns By: Click and select an activity code for grouping columns of the report. The
values defined for this code provide the choices for grouping column data in the report. This
field is available for Activity Matrix reports only.
Header: Enter a description of the data items chosen for the report, in the order specified, and
the column grouping code. P3 displays this information in the center of the report, just above
the column headings.
Line 1 Title/Line 2 Title: In the first column, enter a description for the codes selected for
grouping rows. Use the Column title cells to enter a title for the code value selected for each
column.
Code value (Activity matrix reports) or
Resource/Cost Account (Resource/cost matrix reports): Click to select values for the columns
of the report. Define up to 25 columns per report. To insert a blank column, type BLNK in this
field.
Insert/Delete: Click Insert to add a new column between existing columns; select the column
you want the new column to precede first. Click Delete to remove a selected column from the
report.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 37 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Format:
Use the Format tab to customize the report. For example, you can set field and page widths,
specify a format for dates or numbers, and display row or column totals. The default settings
in the Format tab place eight columns on each page of a report.
Title: Enter a name for the report specification using up to 48 alphanumeric characters.
Report Font: Displays the report font. Click Font to open the Font dialog box.
Choose Plain Text to generate a plain text report; the remaining options on the dialog box
become unavailable because they are not relevant to ANSI output.
Choose Rich Text to generate output using Rich Text Formatting. Using this option you can
choose any available font, font style, and font size for the body of your report, as well as a
separate style for use in headings and subtotals.
Page Width: Choose 132, 230, or 500 columns per page, depending on your printer's
capabilities. The greater the page width selected, the more columns P3 prints in the report.
When using RTF output the Page Width field is unavailable, since it is irrelevant.
Show Detailed Activities/Number of Skipped Lines (Resource/cost matrix reports only)
Mark this checkbox to show detailed activities for each group or clear it for a one-line
summary. Enter the number of lines to skip (0-9) between each group.
Number presentation
Display Column Totals/Display Row Totals: When you display column totals, P3 prints a totals
line horizontally across the bottom of the report, below each column after each group, and a
grand total appears at the bottom of the report. You can also display row totals to the left or
right of the column data in matrix reports.
Divide Quantities/Costs By/Show Decimal Places: When you report on a quantity or cost data
item, such as budgeted cost; use the Divide Quantities/Costs By and Show Decimal Places
fields to specify the format for displaying numbers. The Divide Quantities/Costs By field
reduces the width of the numbers included in the report by dividing all figures by a common
factor, such as 10 or 1,000. The Show Decimal Places field specifies the number of places
after the decimal to print. Select from 0, 1, or 2 places.
Date format
Calendar Type: Choose a format for dates in the report. Calendar dates appear in
DDMMMYY HH:MM format. Workperiod dates show the workperiod number that corresponds
to the early, late, or actual schedule dates, not including holidays or nonworktime. Ordinal
dates are the same as workperiod dates but include holidays and nonworktime.
Manufacturing dates display a week number from 1 to 52, preceded by the year. For example,
96-15 represents the 15th week of 1996.
Ordinal Units: When using an ordinal calendar, you can choose hours, days, weeks, months,
or years as the units for the calendar.
Ordinal Start Date: When you select Ordinal as the Calendar type, select a start date for the
ordinal calendar.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 38 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Activity codes
Title Length: Determines the number of characters (0-48) of the code description that appears
in the report. Enter a low number to fit more columns on a page and a high number to display
the entire code title.
Repeat Code Value On All Horizontal Pages: If the report spans more than one page
horizontally, choose whether to reprint the row titles on each page. Mark this checkbox if you
plan to use each page of the report separately. Clear this checkbox if the report contains
many columns and you want to see all columns at once like a spreadsheet.
Selection:
Use the Resource Selection tab to specify resources or cost accounts for reports and
graphics. The resources and cost accounts must be defined in the appropriate dictionaries.
Set up selection statements using criteria codes and then specify a resource or range of
resources in the Resource and Cost columns. Specify up to 40 selection statements.
Title: Displays a description for the specification.
Resource Selection
Profile If: Choose a criteria code to select the resource or cost unless you are generating a
Resource Productivity report; in this case, you can only select a resource with no criteria
code. For all other reports, select a specific resource or cost using the EQ (equal to) criteria
code, or select a range of resources or costs using the WR (within range), NR (not within
range), GT (greater than), or LT (less than) criteria codes. Click to display a list of valid criteria
codes.
Low/High Value Resource: If you specified EQ as a criteria code, enter the specific resource
that you want. If you use LT or GT criteria codes, enter the appropriate resource. If you define
a range of resources using the WR or NR code, enter the resource in the Low Value column.
Display a list of defined resources. Use the High Value Resource column only when you
define a range with the WR or NR criteria.
Low/High Value Cost Account: You can narrow the selection criteria by entering cost
accounts in the Resource selection field. Enter a cost account number in the Low Value Cost
Account column. Use the High Value Cost Account column only when you define a range of
cost accounts using the WR or NR criteria. Click to display a list of defined cost accounts.
You can use a question mark (?) as a wildcard in any position of the cost account number to
select on different levels within the cost account structure. P3 uses cost accounts exactly as
specified, so you must consider the positions of the numbers you enter. For example, if you
leave the cost category position (12th character) blank, P3 includes only cost accounts with a
blank cost category. To consider all cost categories, enter a ? (Question mark) in the 12th
position.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 39 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Note A blank Resource Selection tab produces an individual report for each resource in the
project. To combine these reports into one report, select a range of cost accounts, use the
wildcard option, or select by hierarchical resources.
Run: Click Run to execute the report. To save changes to the specification, click OK. To run a
report with a temporary change to the specification, click Run and do not click OK.
Previous/Next: Click to scroll through the list of report specifications. Previous or Next are not
available when there are no lower or higher numbered report specifications in the list.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 40 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Graphical Reports
THE FIRST THREE GRAPPHIC REPORTS ARE COVERED IN GANT CHART AND PERT CHART.
Content:
Use this tab to design the Resource/cost graphic and define the type of data to include. You can
choose to show the data as a histogram, cumulative curve, or both.
Title: Enter a name for the specification using up to 48 alphanumeric characters.
Schedule: Mark the checkbox for each schedule that you want to show on the graphic. Show up
to two target schedules along with the current project.
Show Data: Choose to display either resource or cost data.
Dates: Specify the schedule dates (early, late, or both) you want to use for the resource/cost
graphic. Click the Pen tab to specify different pen colors and patterns to distinguish between the
early and late date schedules.
Divide By: Determines how resource or cost values are shown. For example, reduce the width of
the numbers shown on the y-axis by dividing the values by 10 or 100.
Curve
Choose Cumulative, Histogram, or Both. Cumulative curves show accumulated use or cost, and
histograms display use or cost per timeperiod. If you show both curves and histograms on the
same drawing, two scales are shown on the y-axis. The left scale is for histograms, and the right
scale is for cumulative curves.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 41 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Cumulative
Display % on Y Axis/Base % On: For cumulative curves, display the percentage of
resources/costs used or spent. The percent scale appears along the y-axis. Specify the schedule
dates on which to base the percentages. For example, create a cost graphic that compares the
current and target plans. By choosing the Target 1 early schedule as the percent scale, you may
find that your current budget has spent 90% of the planned budget.
Note When showing percentages on a graphic that contains both histograms and curves, the
percent value appears in the right y-axis.
Display Labels: P3 prints a label (EARLY and LATE) for the current schedule's early and late date
curves. To show labels for the target curves, use the Pen tab and specify a label for the Target 1
and 2 early and late curves. You can also specify your own labels
for the current schedule curves--P3 uses them instead of the default labels. To mask labels, clear
this checkbox.
Histogram
Format: If you choose Histogram under the Curve option, specify bar or area. Bar drawings show
a single bar per time-period. Area drawings show a profile that spans the defined timeperiod. Area
drawings are useful for comparing profiles such as early and late dates.
Use/Cost: Resource and cost histograms can show total, peak, or average use or cost. Total
use/cost summarizes the use/cost in each time interval, peak use/cost is the highest use/cost in
each time interval, and average use/cost is calculated as the total divided by the number of time
units in the time interval. Cumulative curves always accumulate total use/cost.
Use Calendar: If you are showing average use/cost and the resources/cost accounts are
assigned to activities that use different calendars, click to select a specific calendar to use.
Decimal Places: Specify the number of decimal places to display for values (0, 1, or 2).
Display Data Values: For histograms, mark this checkbox to show use or cost values at the top of
the histogram for each time interval.
Date:
Use the Start Date and End Date fields to control the appearance of the timescale for
resource/cost graphics.
Display dates
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 42 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Calendar/Ordinal: Choose Calendar to show normal calendar dates on the timescale. Choose
Ordinal to show sequential numbers instead of calendar dates. If you choose Ordinal, specify an
Ordinal start date.
Show Fiscal Years/Start Month: To use a fiscal year timescale, mark this checkbox, then specify a
start month for the fiscal year.
Time periods
Start Date/End Date: The start and end dates control the timeperiods that appear on the
timescale. The default start date is the project start date. Change the start and end defaults to
narrow the timescale and focus on activities scheduled in a specific timeframe.
Click the rolling date icon in the Start Date and End Date fields to base the timescale on the
project start date, finish date, or data date, rather than on specific calendar dates. For details, see
Use rolling dates in reports and graphics.
Note If the plotting area is not large enough to fit the number of timescale units based on the
selected time interval and the defined start and end dates, increase the time interval specified and/or
shorten the timescale by respecifying the start or end dates.
Title Each: You can label time intervals with dates. Choose an interval that is the same as or
greater than the timescale interval specified.
Timescale: Choose a time interval that is the same as or greater than the project's planning unit to
use for the x-axis.
Format
Use the Format tab to determine the overall appearance of the resource/cost graphic.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 43 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Major/Minor Scale Values: Major and minor horizontal lines help you trace positions on a bar or
curve horizontally. Specify the y-scale values where you want major and minor grid lines to
appear.
Histogram
Summarize By Resource: Mark this checkbox to produce a summary histogram, which combines
a resource/cost account's use or cost for a defined time-period into one bar.
Stack Resources: Mark this checkbox to produce a stacked histogram, which shows use or cost
for several resources/cost accounts in one bar per time-period, where each resource/cost account
is actually an individual bar "stacked" on top of one another. This format allows you to track both
combined and individual use for several resources on the same graphic. Each resource/cost
account is identified by a color and/or pattern specified in the Res Selection.
Note The Stacked resources option is available for current project data only; target information
does not display in a stacked bar.
Print
Orientation: Choose the direction that the graphic prints on a page, either landscape (horizontal)
or portrait (vertical).
Begin On Sheet/End On Sheet: For multiple-page graphics, specify the begin and end sheet that
you want instead of preparing the entire graphic.
Rows/Columns: You can show many graphs on one page by dividing it into cells, using rows and
columns. For example, specify two rows by three columns to divide the graphic into six cells.
Each cell can contain a graph showing a different resource/cost account. Use the Res Selection
to determine the resources/cost accounts to display in each cell.
Pen
Use this tab to select pen numbers and lettering sizes for the various resource/cost graphic
elements.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 44 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
each item. Change any of these pen numbers, or change the pen on the plotter to the color you
want.
01 Black
02 Red
03 Blue
04 Green
05 DK magenta
06 Cyan
07 Yellow
08 Orange
09 Brown
If you are using a multi-pen plotter, each number corresponds to a color. For single pen
plotters, you are prompted to change pens during the plot process. For histograms, this field
determines the outline color for the bar.
Line Weight: Choose from one to four strikes, where four strikes creates a heavier or darker
line.
Line Type: Specify a line type for each item in the graphic. Choose from solid, dashed, or
dotted lines.
Fill Pen: For histograms, specify a pen color for filling bars.
Fill Pattern: For histograms, specify a pattern for filling each bar. Use different patterns to
distinguish between early and late bars, and current and target bars. Choose Mask if you do
not want the bar filled.
Size
Use this tab to control the point size of the data items listed. Specify a point size between 3 and
60 for most items (except for Title Block text, which cannot exceed 40).
Default point sizes are provided when you add a new specification. The sizes are the best
combination for the page size you selected in the Print Setup dialog box.
If you specify a size for Title Block text that is too large to fit on the page, it is automatically
reduced as necessary. The point size setting for Title Block text applies to the specification title
only. All other text in the title block is automatically adjusted to fit the page size you are using.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 45 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
Selection
Use this tab to select activities. To include all activities in the project, leave this tab empty.
Specify selection criteria by forming a statement with data items, selection criteria, and values.
Right-click in any cell to select from a list of choices for that cell.
Selection Criteria
Resource Selection
Use this tab to specify the resources/cost accounts to include in the graphic. (They must first be
defined in the appropriate dictionaries.) If you are showing multiple graphs in one graphic, use this
tab to specify the cell placement of each resource/cost account within the graphic.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 46 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]
INSTITUTE OF ENGINEERING & MANAGEMENT Primavera Project Planner
lines of selection criteria, the data are consolidated into one graph. If you specify a group number
with no selection criteria or you skip a group number, the corresponding cell is left blank.
The number of cells you specify in the Format tab (rows by columns), along with the criteria
specified using this Resource Selection tab determine how many pages your drawing contains. If
you specify more groups than available cells, additional pages are prepared.
Profile If: Right-click and select a selection criteria.
Low Value/High Value: Specify as many as 24 selections (click to list valid entries). If you select
by resource, you cannot select by the resource designator or curve character. If you select by
cost account, be sure to enter the cost category code, if any. The High Value column is valid only
if you use WR (within range) or NR (not within range).
The output for each line of selection is combined into one graph regardless of the specified
criteria code. For example, if you select WR BOILERMK WELDER, one graph is produced that
consolidates the data for all resources.
You can also use a question mark (?) as a wildcard in the Cost Account fields to select on any
character of the cost account. For example, if you select EQ 31?????????? you get all cost
accounts that begin with 31. All other positions of the cost account can have any value. To report
on all cost categories for an account, specify a wildcard (?) in the last position of the Cost Account
field.
Note When using wildcards, the question marks must occupy the same position in the Low
and High columns.
Pattern: Specify a pattern for each line of selection criteria when producing a summary or stacked
histogram.
Pen: Specify a pen number for each item in the resource/cost graphic. The following picture
shows default pen numbers and colors. Change any of these pen numbers, or change the pen on
the plotter to the color you want.
Enter a zero in the Pen column to mask an item.
If you are using a multipen plotter, each number corresponds to a color. For single pen plotters,
you are prompted to change pens during the plot process. For histograms, this field determines
the outline color for the bar.
A-10, Dashtyar Center, Block-13 A, Gulshan-e-Iqbal. Main University Road. Karachi Page 47 of 47
Ph: 92-21-4993242, 4986752 Email: [email protected]