Name of work : Renovation of Sir Sunder Lal Hospital, BHU, Varanasi under Kayakalp Package-IC (SH: Renovation Main Block building (G+5), OPD Block (G+2),
Radiology (G+2) & Old Emergency Block (G+2) including Internal Electrical installations, Fire Fighting, Fire Alarm System, Air Conditioning System, Public Address
System & Development Works) (Balance Work).
Name of Agency:- M/s Sharma Construction Co.
Agreement no. :- 17/EE/BHUPD-II/2023-24
Date of start:-23.02.2024
Stipulated date of completion:-22.08.2025
TARGET:-24/04/2022
STATUS:-WORK IN PROGRESS
S. No. Activity 21-06-2024 01-07-2024 15-07-2024 31-07-2024 15-08-2024 31-08-2024 15-09-2024 30-09-2024 15-10-2024 31-10-2024
1 Room 105 & 106
Structural repair
Dismentalling Completed
Brickwork Completed
Flooring Work
Electrical Work
HVAC Work
Fire & PA work
2 Room 113
Structural repair
Dismentalling Completed
Brickwork Completed
Flooring Work
Electrical Work
HVAC Work
Fire & PA work
5 Eye OT
Drawing prepration and Completed
designing
Structural repair
Dismentalling
Brickwork
Flooring Work
Electrical Work
HVAC Work
Fire & PA work
7 Surgical Oncology
Structural repair
Dismentalling
Brickwork
Flooring Work
Electrical Work
HVAC Work
Fire & PA work
9 Radiology
Structural repair
Dismentalling
Brickwork
Flooring Work
Electrical Work
HVAC Work
Fire & PA work