Gockenbach 2008
Gockenbach 2008
E. Gockenbach*, H. Borsi
Leibniz Universität Hannover, Schering-Institut
Callinstr. 25 A, 30167 Hannover, Germany
* E-mail : [email protected]
Abstract: Power transformers are important determined mainly by two parameters, the faults should
components of all electric networks. They are usually be recognized in a time period, which allows to take
very expensive and therefore diagnosis and monitoring actions to avoid critical conditions, and the request to
systems will be valuable for preventing damages. A do some maintenance work should only take place if the
continuous control of the status of the transformer condition of the plant requires it.
condition is worthwhile and will support the appropriate
decision in case of a problem. The transformers are The advantages of a monitoring system, which should
geographically spread and with the aid of Internet, it is be part of the complete system and therefore very often
possible to collect appropriate information from these a component of the manufacturer service concept, in
transformers to a central node for diagnostic purposes combination with a reasonable diagnosis are:
under the supervision of high voltage engineering
x extension of the remaining life
experts. The aim of this paper is to show the main
problems related to power transformers and to review x improvement of overloading possibility
mitigation methods for the monitoring and diagnosis of x higher availability and service reliability
power transformers. x condition-based maintenance and repair
x prevention of loss and destruction
INTRODUCTION
Diagnosis contains interpretation of data to determine
Power transformers are important equipment in electric the current condition of a transformer based on the
energy networks. The majority of these devices have monitored data. A precise diagnosis is required because
been in service for many years under different a wrong diagnosis costs money in any case, if the
environmental, electrical, and mechanical conditions. diagnosis is to pessimistic the investment for repair
Fig. 1 shows as an example the service years of and/or replacement is actually not necessary. If the
transformers from a large German utility. diagnosis is to optimistic an unexpected failure causes
80 most probably high costs. Therefore numerous research
70
activities are ongoing to use all the available
information form the monitoring systems for a reliable
60
diagnosis. Advanced technologies may have the
potential to reduce time and to increase the reliability of
number of transformers
50
−16−
1000
transformer. In the following the main failure causes of
the insulation system in a transformer should be stressed,
x electrical
x electromagnetic
10
x dielectric
x thermal
x chemical
1
0 1 2 3 [%] 4
These failures may need a certain time until they will
water content in paper
lead to a breakdown in the insulation system. One of the
problems in monitoring and diagnosis is the fact, that in Fig. 3 Relative depolymerisation velocity at different water
content and temperature
the first years of service the failure rate is relatively low
and will not require a monitoring or diagnosis system.
Later the increase of the failure rate may be very strong,
but information from earlier times is necessary to
improve the diagnosis. Fig. 2 shows a general curve electrodes
representing the failure rate of transformers as function
of the service time.
60
50
40
failure rate in %
30
impregated paper
20
10
0 liquid stream
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49
service years
Fig. 4 Sensor for humidity [4]
Fig. 2 Example of failure rate as a function of transformer age [3]
If the system has reached its equilibrium a simple
measurement of the capacitance of the measuring
Electrical causes
electrodes and the conductivity of the liquid will give
information about the humidity content in the paper.
Inside the transformers, insulation systems (made of
insulating oil and cellulose), can be locally overstressed,
whereby the aging process of the insulating system will Electromagnetic causes
be accelerated, leading to acid generation and pollution
in the oil, an increase in the water content, gas and mud High forces can be caused by a short circuit and this
formation. As a consequence, the breakdown voltage will lead to a deformation of the windings within the
will decrease. The increase of the water content will transformer. In consequence the paper insulation may
also accelerate the depolymerisation of the cellulose also be influenced due to mechanical stress. This will be
which leads again to a reduction of the breakdown the initial point for partial discharges which lead after a
voltage, because the paper aging process is primarily certain time to a complete breakdown of the insulation
dependent on the water content and the temperature. system. The evaluation of the mechanical changes in the
Furthermore the existence of oxygen will also transformer is usually difficult, because there is no
remarkably increase the rate of depolymerisation by a direct access to the windings. The measurement of the
factor between 2.5 and 10. Fig. 3 shows the so called Transfer Function is a way to detect
depolymerisation activity as a function of water content mechanical deformation. Fig. 5 shows an example of a
in the paper and the temperature as parameter and it transfer function, measured on a 400 kV transformer.
should be noted that the y-axis has a logarithmic scale. The transfer function of the three phases shows some
differences, probably caused due to the non symmetrical
A sensor for detection of humidity in the insulation arrangement in the transformer vessel and some
system is shown in Fig. 4. The main components of the mechanical changes within the windings. It should be
sensor are the paper, the liquid stream and the noted that the measurement of the transfer function is a
measuring electrodes, whereby the paper should be very power tool bur needs some precaution concerning
same material as it used for the other insulation parts. the influence of the measuring circuit on the results.
−17−
available mathematic tools. The well known method of
Dissolved Gas Analysis (DGA) [6] can have some more
reliable result using newly developed software [7].
−18−
Electrical Procedures REFERENCES
[1] M. Stach: Betriebswirtschaftliche Gesichtspunkte im
The electrical procedure is mainly limited to partial Asset-Management im Zeitalter der Fusion, Micafil
discharge (PD) measurement because this method can Symposium, 20-21.März 2002, Stuttgart
be used for non destructive tests and diagnosis [9]. Here [2] CIGRE-WG 12-05: An international survey on
the transfer function can also be use to determine the failures in large power transformers in service, Electra
PD source within the transformer winding. A detailed No.88 (1983), pp. 21-48
description of the method can be found in [10].
[3] C. Bengtsson, J.-O. Persson, M. Svenson:
Dielectric Procedures Replacement and Refurbishment Strategies for
Transformer Populations, CIGRE 2001 Colloquium,
The dielectric methods are used as offline procedure Dublin SC 12.20
and permit a more exact view of the insulating system, [4] E. Gockenbach: A Diagnosis and Condition
if an extended statement about their condition is Monitoring System for the Insulation System of Power
required. The following procedures are mainly used: Transformers, CMD 2006, 2006, Changwon, Korea
x •Recovery Voltage Measurement (RVM) [5] M. Wang, A. J. Vandermaar: Review of condition
x •Polarization and Depolarization Current (PDC) assessment of power transformers in service, IEEE El.
x •Frequency Dielectric Response (FDS) Insul. Magazine, Vol. 18, No. 6, pp. 12-25
[6] Guide for the Sampling of Gases and Oil from
CONCLUSIONS Oil-Filled Electrical Equipment and for the Analysis of
Free and Dissolved Gases,” IEC Publ. 60567, 1992
x Monitoring and diagnosis systems for power
transformers are available. [7] A. Akbari, A. Setayeshmehr, H. Borsi, E.
x The most influencing parameters and the failure Gockenbach: A Software Implementation of the Duval
sources and causes are well known. Triangle Method, International Symposium on
x To monitor the various effects different tools should Electrical Insulation ISEI 2008, p. 124 -127
be used in parallel taking the single advantage of [8] Y. Han, Y.H. Song, Y.H.: Condition monitoring
each tool. techniques for electrical equipment-a literature survey,
x The procedures are mainly on chemical, electrical IEEE Transactions on Power Delivery, Volume: 18,
and dielectric measurements. Issue: 1, Pages:4 - 13, Jan 2003
x The tendency of the different parameters can be [9] A. Akbari, et al.: Transfer Function-Based Partial
recorded however the evaluation of the failure risk Discharge Localization in Power Transformers: A
and the estimation of the residual life time from the Feasibility Study, IEEE Electrical Insulation Magazine,
recorded parameters are not sufficient solved up to
Vol. 18, No. 5, 2002, p 22 – 32
now.
x Using more and more monitoring and diagnosis [10] E. Gockenbach, H. Borsi: Transfer Function as
systems on power transformers like Fig. 6 will Tool for Noise Suppression and Localization of Partial
increase the data base and improve the diagnosis. Discharges in Transformers during On-site
Measurements, ISH 2008, Beijing, China, paper K2-11
Online
& Fuzzy
Voltages, Currents Discrimination
Offline
Sensors CBR
Information
Dissolved Gas in Oil
Fusion MBR
Fig. 6 Block diagram of monitoring and diagnosis system for power transformers
−19−