CBMDM
CBMDM
CBMDM
net/publication/245492083
CITATIONS READS
15 426
2 authors:
All content following this page was uploaded by Jorge de Brito on 16 July 2015.
Abstract: A bridge service life is limited both by its structural deterioration and
upgrade existing bridges, important investments are necessary. Bridge budgets are
always limited, and frequently only a selection of the problems detected can be dealt
INTRODUCTION
The focus of bridge engineering has, in the last few decades, slowly been
changing from the design of new bridges to the maintenance, rehabilitation and
upgrading of existing ones. This is due to the high structural deterioration rates that
have been
_____________________________________________________________________
1
Assistant Professor, Instituto Superior Técnico, Av. Rovisco Pais, 1096 Lisboa Codex, Lisbon,
Portugal
2
Full Professor, Instituto Superior Técnico, Av. Rovisco Pais, 1096 Lisboa Codex, Lisbon,
Portugal
observed in some structures and the functionality loss that has often occurred due to
increasing traffic volumes or axle loads. Causes for structural degradation can be
found in poor durability design, lack of quality control during construction, increasing
levels of pollution and, most importantly, the absence of regular inspection and
maintenance actions.
beyond the minimum acceptable level of safety are not the direct costs of repair, even
though these can amount to a very big investment, but the functional costs due to
Therefore, functional costs should be taken into account in the original design,
encouraging options with longer life between major repairs, even if the minimum
initial cost to achieve the target level of service is increased. Such problems as the
need to properly and easily inspect and maintain the bridge on a regular basis
The functional failure costs mentioned above will also occur due to a deficiency
booms have led to the functional obsolescence of strategic utilities such as bridges,
long before the predicted end of their structural life. When designing a bridge, two
important points must be taken into account: upgrading a bridge a few years after it has
been built can lead to costs higher than the initial construction; the upgrading always
causes very high functional costs concerning the surrounding utilities and it is
Such a wide range of potential problems leads to necessities, that easily become
necessary to rate the potential works in terms of priority, according to several decisive
parameters. In order to rationalize such maintenance / rehabilitation decisions, bridge
management systems have been developed and are being implemented, mostly in
databases. The experience thus gained is presently being used to develop new
replaced by expert knowledge-based criteria fed into computers. In these systems, the
main module contains the decision criteria, that will lead to the optimal repair decision
considering safety, durability, functionality and economy [de Brito et al 1994, de Brito
and Branco1994].
systems can be used to obtain longer service lives and reduce maintenance costs, if the
management system is implemented during the design phase and continued throughout
same design. During the structure life, bridge management is performed through a
inspections, where anomalies are detected possibly resulting in the updating of design
The length of the service life will be defined either by physical deterioration or
occur, service life ends when the benefits obtained from the operation are exceeded by
aspects mentioned before, when setting the service life of a bridge careful
consideration should be given to its eventual cultural, scenic or historical value [AIJ
1993]. Taking into account the disruption caused to society in general whenever an
utility is replaced, the planned service life should be specified, in principle, as long as
possible.
The life cycle of a bridge comprises the stages of planning, design, construction,
operation, maintenance / repair and demolition. During these stages, the bridge
authority, the designer, the contractor and the maintenance authorities will be
responsible for the durability and functional behavior of the bridge, each entity with
At the planning stage, the authorities should define the global service life that is
intended for the structure. This corresponds to the period of time, from its completion
provided. Current concrete bridges are usually designed for lives of 50 - 60 years, and
important ones are sometimes expected to perform its function for 100 - 120 years.
This period of time is adjusted in order to justify, from an economic point of view, the
construction of the bridge, taking into consideration the associated functional benefits.
Such benefits can be quantified in terms of tolls or simply users time / fuel saving,
even though other benefits such as a reduction in the accident rate or the bridge
The prediction of the end of the functional life of a bridge needs specific traffic
impact studies, that should be prepared during the planning stage. For example, in road
bridges the functional obsolescence is mainly related with restrictions to traffic volume
and maximum axle load, whose evolution can be estimated from statistical analyses or
authorities global development plans. Measures to delay obsolescence may be put into
effect at the design stage, through flexibility which allows for a relatively inexpensive
upgrading of the functionality of a bridge during its life (the possibility of increasing
guarantee that the defined global service life will be met. These studies should be
taken into account in the bridge durability design and the resulting requirements
The service life, defined at the planning stage, is expected to be achieved in most
of the construction elements, mainly in the structural ones, with minor repair costs.
Analysis of durability performed at the design stage considers the service life of
predictable maintenance and repair works throughout the service life. A successful
replaced before the bridge is put out of service with service lives that are sub-multiples
problem undergoing significant research throughout the world [Mangat and Elgarf
1991, Lopes et al 1995]. It includes the definition of the reference limit states
associated with the end of the service life, the environment characterization, the study
of the degradation phenomena of the materials and components and the definition of
- Carbonation;
- Freeze-thaw cycles;
In order to achieve the expected durability for current structures with service
lives of 50 to 60 years, the European standards [CEN 1995] have defined the specific
cement content, maximum water / cement ratio, minimum strength) and reinforcement
cover. For important bridges, where greater service lives are specified (100 to 120
years), there are presently no specific code recommendations. In such cases, the study
[Mangat and Elgarf 1991], based on local environment conditions experience, and the
limit states adopted for design. Presently, these models have been mainly developed
with the Ca(OH)2 of the cement hydration products in the presence of water. The main
proceeds at a rate controlled mainly by the CO2 diffusion coefficient [Mangat and
Elgarf 1991]. The evolution of the depth of the carbonation front "d" (mm) can be
estimated by:
d=K t (1)
where t is the time in years and K is a carbonation constant, which depends on the
effective diffusion coefficient of CO2 through concrete and the concentration of CO2
in the immediate surrounding environment and inside the concrete mass. Based on
experimental data, the parameter K has values around 1.0 - 1.5 (mm / year0.5) for
current situations, but can increase to 7.0 - 8.0 for poor concrete and heavily polluted
For chloride attack, its rate of penetration into concrete can be reasonably
predicted by Fick's law of diffusion. The solution of this differential equation, taking
into account the time dependence of the chloride diffusion coefficient Dc (cm2 / sec),
leads to the following equation, giving the chloride concentration C(x, t) inside the
percentage of the weight of cement), erf is the error function and m an empirical
around C = 0.4 % (of weight of cement), the equation above can be used to estimate
the time for the corrosion initiation for given reinforcement covers (x) and surface
chloride concentration levels (Table 1 [Mangat and Elgarf 1991]), using concrete
Dt = Di - 0,023 t Ic (3)
where Di is the initial bar diameter in mm, t is the time in years, and Ic (µA/cm2) is the
corrosion rate with values varying from 1x10-1 to 1x102 µA / cm2. The scattering of
these values makes the estimation of the corrosion rate difficult, if not based on in-situ
measurements. It must be noted that the corrosion rate is much higher in chloride
initiated than in carbonation initiated processes, resulting in shorter service lives after
initiation for chloride initiated processes (usually not exceeding 5 years [Tuutti 1982]).
achieved for specific concrete characteristics and reinforcement cover. Usually, several
alternatives may be used in the choice of the concrete components and bars cover, and
a cost efficiency analysis performed to reach a decision. It should be noted that for
very long service lives the minimum concrete strength to be adopted is usually
Durability design of concrete bridges may also consider other particular analyses
that affect their service life. These can include, for example, a fatigue analysis of some
components or the study of steel elements corrosion (submerged piles, steel bearings,
Bridge Monitoring
For important bridges and because mathematical models, at the present stage of
knowledge, do not yet give sufficiently accurate results, a monitoring system should
also be planned for at the design stage. Monitoring during construction and service life
(associated with periodic inspections) will provide, for important structural elements,
the main parameters that control the deterioration mechanisms, namely in concrete
structures, the carbonation front depth, the corrosion level, etc., and will allow the
follow their structural behavior in service. This will enable the prevention of major
accidents and the performance of a quick assessment of the structure after an accident
To monitor the functional service life of the bridge, periodic traffic surveys
should also be implemented in order to re-assess the assumptions used in the design
and help in eventual repair decisions, considering the most relevant functional,
Flexibility
Components, such as bearings, joints, rails, pavement, etc., that predictably will
need repair or replacement prior to reaching the defined global service life should be
designed with flexibility, meaning that their replacement / repair can be performed
with minor disruption to the facility’s normal operation [AIJ 1993]. If a later
including the definition of durability tests to be adopted during construction and the
corresponding expected durability parameters for the materials. Based on the design
estimation of the service life of the components, a basic inspection and maintenance
plan for the structure, including the durability and structural monitoring, should be
presented.
should be identified and critical levels defined. The possibility of these levels being
reached during early stages of the service life should trigger off emergency plans in
order to prevent further middle-term effects in terms of both structural and functional
Re-use of materials
In the choice of the materials, the possibility of their re-use at the end of their
service life should also be considered. Guidelines for demolition operations at the end
of the service life may also influence the options at the design stage [AIJ 1993].
During the construction stage, effective quality control is the best way to attain
the planned service life. The construction quality control is typically performed by a
supervision team, in contact with the designer, and should include the main activities
described below.
Before any concrete mixing begins, the contractor should study the concrete’s
ability to achieve the durability parameters defined at design stage. This is specially
important because durability tests take time to provide results and, if they are not
performed in advance, the construction may suffer some delays. Besides this initial
study, a control must also be implemented at the reception of all the materials, and in
particular for the structural ones, whose composition needs to be periodically checked
with durability tests to guarantee their behavior [CEN 1995]. Alkali-silica related
specifications. This quality control is one of the most important activities and must be
done in a systematic way during the construction stage, according to the monitoring
The concrete durability properties of the bridge and the environmental parameters
should be controlled, using the in-situ tests results which will also allow the updating
evolution of material properties (in-situ concrete shrinkage and creep, Young modulus,
important bridges or at the authorities request, static and dynamic tests should also be
performed to check the bridge behavior against the design structural models.
durability for the materials [CEN 1995]. Activities such as concrete compacting and
curing, heat of hydration control, etc. are examples of procedures that are important for
concrete durability.
anomalies are detected, the system gives the inspector suggestions concerning the best
defining the "reference state" that will be used for the service life [Andrey 1987]. Later
on, if this information is not available before an inspection of the bridge (because the
have a new reference state. The same should happen, when the bridge is reclassified in
To guarantee a good behavior of the structure during its service life, several
with expert knowledge has been fed into computers leading to knowledge-based
systems.
Within a global strategy for management, these systems should include the basic
maintenance plan and service life estimation, defined at the design stage, and all the
durability and structural performance results obtained from monitoring the bridge
I - Database ;
II - Inspection module;
bridge within the net, the design basic maintenance plan, the durability and structural
tests and inspections results from the construction phase, the defect classification
The inspection module handles the data acquisition at the structure during its
service life at intervals defined by the inspection calendar. The decision module uses
the data and expert knowledge to help in all the decisions that must be made during
that time concerning the maintenance / repair activities. The decision system is divided
III.1 - Maintenance;
III.2 - Repair .
repair work and considers the durability and structural updated information obtained
from the inspections. Its use allows the authorities to choose one of several options
(wait and see, repair, build a new structure [de Brito 1992]), resorting when necessary
Methodology
some flexibility is allowed to take into account a plausible global allocation of the
is detected or suspected.
[Andrey 1987]: current and detailed. It is proposed that current inspections have a
period of around 15 months (in order to check the influence of the weather throughout
the year) and that a detailed inspection replaces a current inspection at 5 year intervals.
In the current inspections, serious defects are not expected to be detected. For this
reason, the inspection will be focused mainly on visual observation of the most
exposed areas and, usually, special means of access and non-portable equipment will
be dispensed with. Results from monitoring equipment should also be obtained. The
defects found are registered, as well as their location, and classified in terms of
division with all the defects that need short or middle-term action.
The detailed inspection differs from the current inspection in that all details that
are susceptible of raising future problems are investigated. Besides visual observation,
durability in-situ tests should be performed to continue the updating of the service life
estimation.
The detailed inspections should also consider the basic maintenance plan defined
at design stage, according to the estimated service life of the bridge components,
checking the need for their replacement / maintenance, and updating that same plan.
The Inspection Interactive Module
help the inspectors with technical information about the defects found, an interactive
knowledge-based system was developed for the inspection module of the bridge
management systems. This module uses a defect classification system considering the
All the possible causes (direct or indirect) of these defects (117 entries) were
diagnosis methods used to detect or analyse the defects (81 entries) were also
classified according to the functioning principle and the type of results provided, in 14
different groups. The repair techniques used to eliminate or prevent the defects listed
above (69 entries) were themselves classified in the same groups as the defects [de
For each of these defects, a defect form [de Brito et al 1994] was prepared in
order to be included in the inspection manual, complementing the system. Each of the
forms includes the following information: short description of the defect, possible
To help the inspector in making decisions at the structure site, the system has had
causes, defects and diagnosis methods as well as defects and repair techniques [de
Brito et al 1994]. Each of these matrices is organized so that each line represents a
defect and each column a possible cause (or diagnosis method, or repair method). In
the intersection of each line and column, representing the correlation between each
defect and the other element, a classification was introduced representing the
knowledge information.
To help the inspector in making decisions concerning the defects detected during
the inspection, the system is then used as a memo aid giving hints as to what should be
done. The inspector selects the defect that has just been detected and has access to the
Using the expert system, the inspector is also able to record the results of the
used to help in the preparation of the definitive inspection report, which is done at the
headquarters.
The maintenance activity deals with minor repair problems that do not affect the
structural reliability of the structure. It includes also the bridge elements substitution,
defined in the design basic maintenance plan, which is updated during service life as a
planned and performed at least until the next periodic inspection [de Brito 1992].
present value costs are more or less stable and therefore are easy to predict and include
in the next budget. However, some type of criteria must be used in order to define
which defects will have to be eliminated as soon as possible and which can wait until
into account the following three basic aspects [de Brito 1992]:
- Rehabilitation urgency;
- Functionality affected.
in Table 2 [Branco and de Brito 1995] being the corresponding points considered by
the system to obtain a global rating of the defect. The defects will be then included in
assigned to each one. The defects rating allows the system to prepare a list of all the
Fig. 4 [de Brito 1992], associated to the rating of a defect (bar with reduced cross
section).
COST FUNCTION
to quantify the total cost associated with the several stages of the structure life. A
global bridge cost function [de Brito 1992, de Brito and Branco 1994] must include the
structural costs CST and the functional costs and benefits CFU, during the structure life
cycle.
C = C ST + C FU (4)
The structural costs include the initial costs (C0) (design and construction),
inspection (CI), current maintenance (CM), repair (CR) and structural failure costs
(CFSF).
C ST = C 0 + C I + C M + C R + C FSF (5)
The functional costs (CFFF) are associated with reductions in the operation
conditions of a structure, such as speed limitation, live load reduction, etc. The
benefits (B) correspond to negative functional costs as they are associated with an
C FU = C FFF − B (6)
Structural Costs
These costs are mainly associated with the civil engineering works and can be
initial costs (C0) are the ones involved in designing and building the structure. They
can be easily predicted for new structures, based on current construction costs.
The inspection costs CI are the ones involved in inspecting the structure
regularly. They can be estimated based on the structure dimensions and location, the
authorities current costs (labor and equipment) and a pre-fixed calendar of inspections
The maintenance costs CM are the ones involved in keeping the structure at its
design level of service and exclude any main structural work. The yearly maintenance
experience. Typical average annual values of these costs for bridges vary between 1
The repair costs CR are the ones involved in doing main structural work (repair,
strengthening) and include the repair costs themselves and all the costs of the
corresponding structural assessment. In the long-term, these costs can be roughly
predicted using a percentage of the construction costs for each year that tends to grow
with the structure's age [de Brito and Branco 1994]. Typical average annual values for
The structural failure costs (CFSF) include all the costs resulting from a structural
collapse of the structure. Even though collapse will not occur under normal
costs. The cost associated with the structural failure can be obtained from the
C F S F = Pf C F F (7)
The cost CFF is mainly related to the construction of a new structure, but costs
associated with the time in which the existing structure is replaced and the
The functional failure costs (CFFF) are associated with a reduction of the
utility) than the one provided at a certain standard situation (usually the design stage).
They are necessarily associated with functional failure costs (a benefit is equivalent to
a negative functional failure cost) and are therefore measured with the same
a) The costs due to traffic delayed CFFFD that are the ones caused by the slowing
down of the traffic crossing the bridge, specially during rush hours. They are estimated
considering the average delay time and the average user's hour value;
b) The costs due to traffic detoured in terms of volume CFFFV that are the ones
caused by the traffic being detoured from one particular bridge to others nearby
because of the saturation of the bridge in terms of traffic flow. They are estimated in a
similar way considering the costs associated with the additional travel time, the vehicle
running expenditures and traffic accident rate increase [de Brito and Branco 1994];
c) The costs due to heavy traffic detoured in terms of load CFFFL that are the ones
from one particular bridge to others nearby because of its insufficient structural
capacity. They are estimated considering the additional total running costs (including
personnel) and traffic accident costs [de Brito and Branco 1994].
Each of these items can be divided in costs in terms of time wasted by the
drivers, fuel costs, vehicle maintenance costs and traffic accident costs. For an
economic analysis, these costs have to be computed using several data, namely, traffic
surveys (yearly and daily), service design level of the road, future traffic estimates,
existing alternatives to each bridge, its traffic and structural capacity, energy and
vehicle maintenance average costs, etc.. The periodic updating of the traffic results,
obtained from the monitoring plan, are fundamental for this analysis.
Fig. 5 [de Brito 1992] presents the estimation of all functional failure costs
during the life time of a bridge case study. The traffic delayed costs CFFFD are nil until
year 11 (time zero being the year in which the bridge is put in-service) in which the
traffic capacity of the bridge is reached, and these costs start to grow at a rather fast
rate. The traffic detoured costs CFFFV are nil during the whole period of the economic
analysis (up to year 23) because no repair works are planned and the bridge is never
saturated in terms of traffic (even though delays exist). Additionally, the detour length
was too long to compensate for the alternative delay. The exceptionally heavy traffic
detoured costs CFFFL exist every year because of the bridge structural capacity
limitation to very high truck loads. The fact that they decrease in time at present value
prices shows that the discount rate is higher than the detoured traffic annual increase
rate.
REPAIR SUB-MODULE
natural cause or traffic accident (or detected by the structural monitoring) or if the
updating of the durability properties shows that the bridge safety is getting close to
minimum acceptable levels, an important bridge repair may be envisaged. The repair
solution may also include situations where important traffic saturation of the bridge
occurs (obtained from the traffic monitoring), which may lead to a bridge widening or
even substitution.
structural assessment must be performed, providing data to define and quantify the
repair options. For structural anomalies, this assessment should include a comparison
with the bridge behavior obtained in the initial testing of the bridge after construction.
The decision concerning the repair option to be chosen can then be reached using this
sub-module, through rational criteria and based on the above economic analysis [de
Brito 1992].
Using this analysis, the repair decision can be made according to the cost
effectiveness index (CEI) of each option. The CEI coefficient indicates how well the
proposed work-plan compares to the no-action option. The bigger the coefficient for a
particular option, the better investment that option is. In the calculation of CEI, the
repair costs (CR), the failure costs (CF) and the benefits (B), described above, are
considered.
CEI = Erro! (8)
To help in the selection of the best structural repair technique the repair module
can be implemented with expert knowledge (in terms of flowcharts - Fig. 6 [Luikens
1993]) to eliminate the repair techniques that are not appropriate for the structural
defect found. In this system the module will ask a set of parameters that characterize
the defect (for example, its location, the repair area and others) and, with them, the
possible repair methods will be pointed out. Some of these parameters, to be defined
by the inspector, will allow an estimation of the costs of the selected technique. If
more than one technique is considered possible, the system uses an optimization
procedure based on the CEI coefficient. Each technique has an associated cost and
The final economic analysis is then performed, in which all the costs mentioned
before are modelled in order to allow long-term cost prediction. The results can be
very sensitive to some parameters, specially the ones connected with traffic evolution.
are individually made to vary a certain percentage from a medium value, and the
consequences on the final conclusions give the user an approximate idea of the need to
CONCLUSIONS
During the bridge life, the management system can include knowledge-based
including also the structural behavior and the traffic evolution with time. Both at the
inspection level and at the decision level, expert technical information helps the
structure. The use of a global economical analysis is an important tool for repair
decision making.
ACKNOWLEDGEMENTS
Part of the research work presented in this paper was developed at Instituto
Superior Técnico and CMEST - the Structures Research Centre of the Technical
University of Lisboa. This paper also presents results of the EC supported research
for Inspection and Maintenance of Concrete Structures Using Reliability Based Expert
Systems".
REFERENCES
AIJ (Architectural Institute of Japan) “The English Edition of Principal Guide for
Branco, F. and de Brito, J. “Decision Criteria for Concrete Bridge Repair”, Structural
Placing and Compliance Criteria", European Pre-Standard ENV 206 , 7/95, Brussels.
de Brito, J. "Development of a Concrete Bridge Management System" (in Portuguese),
de Brito, J. and Branco, F. "Bridge Management Policy Using Cost Analysis", Civil
de Brito, J.; Branco, F.; Ibañez, M. "A Knowledge-Based System for Concrete Bridge
Lopes, J.; Branco, F.; Bento, J. "Pre-cast Quality Control Software Manual", CRAFT
Luikens, G. "Quantification of and Parameters for Defects, Repairs and Repair Costs
for Implementation", BREU P3091 Report T4-3-21, 1993, CSR (Computational Safety
M AN AG EM EN T PRO C ES S ES
S YS T EM S T AN D ARIZAT IO N
D EC IS IO N -
-M AK IN G
DEC IS IO N
S YS TEM
INS PEC TIO N
S TRATEG Y
REPAIR
REPAIR W O RK
S ELEC TIO N
REHABILITATION URGENCY:
0. Mainly black rust in areas of maximum moments with a local loss over 3%
1. Mainly black rust in areas of maximum moments with a local loss under 3%
2. Predominantly black rust in intermediate areas
3. Predominantly reddish rust
OPTION [0 TO 3]
OPTION [A TO C]
k- degree of obstruction of normal traffic over the bridge caused by the defect
100000
0
1990 2000 2010 2020
YEAR
yes
Bar corroded ? Cross-section loss > 20% ?
no no unknown yes