Editing Performance Monitoring SEAGS-Final
Editing Performance Monitoring SEAGS-Final
Editing Performance Monitoring SEAGS-Final
ABSTRACT: The Mechanically Stabilized Earth walls (MSE walls) for dam crest rehabilitation was constructed at Mae Suai dam, Thailand.
Welding mesh gabion was used as the facing on both sides, the polymetric geogrid and rebar were used as reinforcements. Furthermore, the
MSE walls was placed on the original earth dam crest, steel sheet pile was installed at upstream and downstream side to prevent leakage and
control the settlement of the new dam crest. The instruments were installed at various test sections to careful field monitoring to obtain high-
quality data. The results obtained from 2D finite element method simulations were in good agreement with the field measurements, the lateral
deformation and settlements were very small. The axial forces in rebar reinforcement were found to be continually changing due to deformation
of foundation, external stimuli and construction factors. Likewise, the strain measured in all positions of geogrid reinforcement was very low.
Combining steel reinforcement (high stiffness) with geogrid reinforcement (low stiffness) was redundant. Most of the lateral stresses are
resisted by the former than the later. It can be concluded that in a reinforced soil wall that uses two or more types of reinforcing materials,
tensile force is developed in higher stiffness material.
KEYWORDS: Dam crest rehabilitation, Dam crest raising, MSE Walls, and Reinforced earth embankment.
performance of back-to-back MSEW for dam crest rehabilitation. dam crest and it will be able to control the normal seepage and prevent
Particular attention was given to the lateral displacements, vertical leakage along the joints.
settlements and axial forces in the reinforcements.
(b)
The RCC section is surrounded by earth zone dam. Core trench of the (c)
earth zone dam was excavated to the foundation rock in the river bed Figure 2 Longitudinal and Cross Section of Mae Suai Dam: (a)
and abutments. Impervious clay consisted of low-plasticity clay (CL) Longitudinal section; (b) Cross section A-A; (c) Cross section B-
and internal filter (sand and gravel) consisted of clayey sand (SC) B (Soralump et al., 2023)
materials to reduce the water pressure and discharge the seepage
water into RCC gallery. Shell zone or random zone is made up of
semi-impervious coarse grain earth (low-plasticity clay (CL), clayey
sand (SC) and silty sand (SM)) with horizontal drain to drain out the
water during drawdown period and maintain the stability of shell
zone. The earth zone extends in both side of the abutment. The 6 m
high RCC retaining block was constructed over the earth filled
material at the downstream of dam crest to reduce the earth fill work
on downstream slope and lower the construction cost.
The transition trapezoidal RCC block (Block D) was constructed
near the joint between RCC spillway section and earth zone dam.
Furthermore, to prevent the erosion at the crest of earth dam during
the overtopping of spillway, RCC blocks A, B and C were constructed
as a water guide wall (wing wall). These blocks were placed directly Figure 3 Removing of the RCC block and dam crest (Soralump
over the earth filled material (Soralump et al., 2023). et al., 2016)
In 2004, after 1 year of operation of Mae Suai Dam, water
overflowed the spillway and leakage was observed at the downstream 3. DESCRIPTION OF THE EMBANKMENT
crest in contact area between earth fill dam and RCC spillway
structure. The water flow was clearly observed behind the RCC block A 6-m-high reinforced earth embankment for dam crest rehabilitation
where differential settlement was also clearly visible. The leakage was designed by Geotechnical Engineering Research and
was observed when reservoir reached a certain elevation near the dam development center (GERD) and constructed by Kanber Geotechnic
crest. The repair work has been done by installing the impervious (Thailand) Company limited with construction supervision by the
membrane over the surface of RCC blocks. The leakage flow was Royal Irrigation Department (Thailand) and Samart Engineering
reduced after the repair of dam but did not disappear completely Consultants Company limited acted as a project consultant. The MSE
(Soralump et al., 2016). wall was 177 m along the dam crest and 10.90 m wide at the top and
Royal irrigation department (Thailand) decided to rehabilitate was prepared by welding the mesh Gabion 1.20x1.20x1.20 m as the
Mae Suai dam and repair works was proposed to solve the leakage facing on both sides and fastened with rebar (DB16 mm) between the
problem and stability of the dam during future earthquake. It has been gabion. The steel plate of dimension 2 0 0 x2 0 0 x9 mm and nut were
proposed to remove the RCC blocks A, B, C, D and blocks on the used for the connection joints as shown in Figure 4 and Figure 5. In
crest of the earth dams (Figure 3) and replace RCC block on the addition, the polymetric geogrid reinforcement was added to the MSE
downstream crest by more flexible structure. In this case, MSE Walls wall. The spacing of the rebar reinforcement was 0.60 m. in vertical
(MSEW) will be used (Figure 4), so that there won't be any rigid and and horizontal directions. Likewise, the vertical spacing of the
brittle that crack when subjected to seismic force or differential geogrid reinforcement was 0.30 m. Furthermore, the new MSE walls
settlement. Likewise, no further significant displacement, both will be placed on the original dam crest that consist of 3 materials
vertically and horizontally, will be observed from the load of a new type: 1) Impervious Core 2) Filter and 3) Random Zone. Steel sheet
28
Geotechnical Engineering Journal of the SEAGS & AGSSEA Vol. 54 No. 3 September 2023 ISSN 0046-5828
30
Geotechnical Engineering Journal of the SEAGS & AGSSEA Vol. 54 No. 3 September 2023 ISSN 0046-5828
31
Geotechnical Engineering Journal of the SEAGS & AGSSEA Vol. 54 No. 3 September 2023 ISSN 0046-5828
32
Geotechnical Engineering Journal of the SEAGS & AGSSEA Vol. 54 No. 3 September 2023 ISSN 0046-5828
supported the weight of the old dam crest which was heavier than the
new dam crest. The analytical results are consistent with the measured
results from the settlement plate as shows in Figure 21. The settlement
occurred only at beginning of the wall construction and at the end
when the wall height was 0.90 m. for SP1& SP3 and 1.50 m. for SP4.
Likewise, no settlement was detected in SP2. The maximum
settlement measured at position SP4 was 0.05 m. It can be seen that
the settlement that occurred was an immediate settlement caused by
construction conditions (insufficient preparation of the foundation
surface), especially in the area where the measuring equipment was
installed.
Interaction Rinter
Backfill / Rebar 0.60
Clay / Steel sheet pile 0.50
Backfill / Geogrid 1.00
33
Geotechnical Engineering Journal of the SEAGS & AGSSEA Vol. 54 No. 3 September 2023 ISSN 0046-5828
(a) (b)
Figure 22 Inclinometer reading and FEA results of test section
at the left bank (a) INC-3, Upstream (b) INC-4, Downstream
34
Geotechnical Engineering Journal of the SEAGS & AGSSEA Vol. 54 No. 3 September 2023 ISSN 0046-5828
(a)
(a)
(b)
Figure 26 Total displacement of earth dam from the slope
stability analysis (SRM)
(b)
Figure 24 Axial force in rebar reinforcements with construction
stage (Time, Wall height (H)) (a) downstream side, D1 (b)
upstream side, U1
7. CONCLUSIONS
A 6-m-high reinforced earth embankment for dam crest rehabilitation
was designed and constructed at Mae Suai dam, Chiangrai province,
Thailand. Welding mesh gabion was used as the facing on both sides;
the polymetric geogrid and rebar were used as reinforcements.
Furthermore, the MSE wall was placed on the original earth dam
crest, steel sheet pile was installed at upstream and downstream side
to prevent leakage and control the settlement of the original earth dam
crest. The instruments were installed at various test sections. The field
measurement data was verified with 2D FEM using MIDAS GTS for
Stress-seepage coupled analyses. Furthermore, slope stability
analysis was performed using strength reduction method (SRM) to
determine the F.S. of the dam crest rehabilitation. From the analysis
results, the factor of safety of the new dam crest was 3.10. The
Figure 25 Tensile Strain in Geogrid behavior of restraint back-to-back MSEW for dam crest rehabilitation
is as shown below:
6.4 Stability of MSE Wall for Dam Crest Rehabilitation - Vertical displacement
Stress-seepage coupled analysis in FEM has revealed that the The settlement of the foundation obtained from FEA was very low as
behavior of MSEW and new dam crest during construction and compared with the height of the dam or MSEW because the
operation are consistent with the field measurement data. In this foundation of the MSEW was an earth dam that used to support the
research, slope stability analysis was performed using strength weight of the old dam crest, which was heavier than the new dam
reduction method (SRM) which was the continuation of the Stress- crest. Likewise, the field measurement data also shows the settlement
seepage coupled analysis. Figure 26 shows the total displacement of behavior that was an immediate settlement caused by construction
earth dam from the slope stability analysis (SRM). The failure plane conditions.
occurs on downstream side along the filter passing through the bottom
of the sheet pile, the factors of safety (F.S.) of MSEW for dam crest
35
Geotechnical Engineering Journal of the SEAGS & AGSSEA Vol. 54 No. 3 September 2023 ISSN 0046-5828
37