Tang Chung Wak V Grant Thornton International Limited
Tang Chung Wak V Grant Thornton International Limited
Tang Chung Wak V Grant Thornton International Limited
Date: 14/11/2012
Before :
---------------------
John Machell QC and Dan McCourt Fritz (instructed by Locke Lord (UK) LLP) for the
Claimants
Alistair McGregor QC and James Leabeater (instructed by King & Wood Mallesons) for
the 1st – 9th Defendants
The 10th Defendant did not appear and was not represented
1. The Claimants apply for an order under section 67 of the Arbitration Act 1996 (“the
1996 Act”) that the final award (“the Final Award”) of an arbitral tribunal (“the
Tribunal”) appointed by the London Court of International Arbitration (“the LCIA”)
made on 26 March 2012 (reference no. 111853) is of no effect because the Tribunal
did not have substantive jurisdiction.
2. The claim was brought under Part 8 of the Civil Procedure Rules on 23 April 2012
and thus within 28 days of the date of the Final Award. The Claim Form was
amended and re-issued on 13 May 2012.
3. The basis for the claim is the Claimants’ contention that certain provisions of the
relevant agreement pursuant to which the Request for Arbitration was made to the
LCIA on 18 April 2011 stipulated steps to be taken as a condition precedent to any
arbitral process and that such steps were not taken prior to that Request (or at all).
4. The question determinative of the claim is a familiar one but it is not without
difficulty: it is whether the provisions in issue had enforceable contractual effect and
operated as conditions precedent such that the Tribunal cannot have had jurisdiction,
and was wrong in its determination that it had.
5. There have been a number of cases in which the enforceability of clauses providing
for mediation or conciliation prior to arbitration or proceedings in court has been
considered. These suggest, exemplify and explain various requirements to be fulfilled
if such a clause can be given contractual effect; but the essential question is whether
their content is sufficiently precise and certain to be enforced. Like an agreement to
agree, a provision for dispute resolution which lacks sufficient detail as to the process
required to be undertaken cannot be enforced. I return to discuss these authorities
later.
6. The Claimants are two of the partners in a partnership governed by Hong Kong law
called JBPB & Co (“JBPB”). (Strictly, references to JBPB should be taken to be to
all partners in JBPB at the time when the LCIA arbitration commenced.)
8. The claims and counterclaims made in the arbitration to which these proceedings
relate (“the Arbitration”) arose from GTIL’s expulsion of JBPB (then known as Grant
Thornton in Hong Kong (“GTHK”)) from GTIL’s network in late 2010. It is common
ground that the merits of the underlying dispute are not relevant to the issues now
before me, and I say no more in that regard.
9. The Second to Ninth Defendants (“the Majority Partners”), together with the Tenth
Defendant (“Mr Chow”), were at all material times partners in JBPB. They were
represented separately from the Claimants at the Arbitration by the firm of Hart Giles
and were referred to as the Majority Partners in the Final Award.
10. GTIL and the Majority Partners did not contest the Tribunal’s jurisdiction at the
Arbitration and asked that the Tribunal’s decision that it had jurisdiction be affirmed.
The Claimants did contest jurisdiction and now seek to set aside the Award
accordingly.
11. Rosenblatt, who represented the Claimants in the Arbitration, also represented Mr
Chow until September 2011. However, they then ceased to do so: and after
September 2011 Mr Chow has not been represented and he has had no involvement in
the Arbitration. Nor was he represented before me. Indeed, when the matter came on
for hearing it was unclear whether he had been served or what his position was. I
agreed nevertheless to continue with the hearing, subject to Mr Chow being provided
with a transcript and afforded the opportunity at a subsequent date (fixed for 6 August
2012) to make any further submissions he wished. In fact, I subsequently was
informed (and provided with an e-mail from Mr Chow to confirm) that Mr Chow did
not wish to participate and did not intend to acknowledge service, though in the e-
mail he also stated that he agreed with the Claimants that the Tribunal had no
jurisdiction. The further hearing fixed for 6 August 2012 was abandoned as being
unnecessary.
12. To return to the history of the matter, the Majority Partners had, by late October 2011,
and after a mediation attended by all relevant parties, purported to enter into a
settlement agreement with GTIL and others by way of deed (“the Settlement Deed”,
which was stated to be effective as from 28 September 2011). The Settlement Deed,
which is governed by English law, provided for the Arbitration and other proceedings
in the High Court of Hong Kong SAR to be discontinued or withdrawn.
13. The Claimants are not parties to the Settlement Deed. On 6 October 2011, they sought
and obtained in Hong Kong an injunction to prevent a meeting being convened of all
JBPB partners to adopt it. The injunction was subsequently lifted and at the meeting
which then took place the Settlement Deed was ratified by the Majority Partners. The
validity of the Settlement Deed is now the subject of proceedings in the High Court of
Hong Kong SAR. Again it is common ground that the merits of those proceedings are
not relevant to my determination.
14. What is relevant is that on 9 November 2011 GTIL and the Majority Partners asked
the Tribunal to terminate the Arbitration, on the basis that the dispute had been
settled. The Claimants contested this. On 18 November 2011 the Tribunal ruled that
the issue whether the dispute had been settled should be decided at a hearing on 2
February 2012.
15. At that hearing the Claimants contended that the Tribunal had no jurisdiction to
determine the issue. The Tribunal thus had to deal with and rule upon the issue of its
own jurisdiction, as it was empowered and required to do by sections 30 and 31 of the
1996 Act.
16. The Tribunal described the issues requiring its decision in the following terms:
(1) Does the Tribunal have jurisdiction to determine this dispute?
(2) If the Tribunal has jurisdiction, does the Settlement Deed preclude the
[Claimants] from continuing their claims against GTIL?
17. The Final Award addresses each in turn, identifying the matter of jurisdiction as the
threshold issue.
(2) the Settlement Deed required the Arbitration to be terminated; the Tribunal
deciding to leave open whether nevertheless the Claimants could pursue
proceedings against the Majority Partners under an agreement called the
Deed of Termination (which is governed by the laws of Hong Kong,
contains no arbitration clause and which could therefore not be the subject
of the Arbitration): (paragraphs 5.14 and 5.16 of the Final Award);
(3) GTIL should be entitled to specified costs against the Claimants but the
Majority Partners should not be entitled to recover their costs from the
Claimants (paragraph 7 of the Final Award).
19. As previously indicated, only the first issue arises for my adjudication, and that issue
is as to the substantive jurisdiction of the Tribunal.
20. There is no dispute that, unlike appeals on a point of law under section 69 of the 1996
Act (where leave of the Court is required), challenges to the substantive jurisdiction of
an arbitral tribunal with a view to declaring any award to be of no effect under section
67 of the 1996 Act may (pursuant to section 67(1)) be made as of right.
21. Sub-section 67(3) of the 1996 Act empowers the Court to (a) confirm or (b) vary or
(c) set aside the award in whole or in part.
22. It is not disputed that, following Dallah Estate & Tourism Holding Co v Ministry of
Religious Affairs, Government of Pakistan [2010] UKSC 46, the proper approach for
the Court is to treat the challenge to an arbitral tribunal’s jurisdiction as a rehearing
rather than a review. Indeed, as Lord Hope put it (at paragraph 30), “The tribunal’s
own view of its jurisdiction has no legal or evidential value…however full was the
evidence before it and however carefully deliberated was its conclusion.”
23. As Lord Hope went on to explain (at paragraph 31), however, that is not to say that a
court seised of the issue “will not examine, both carefully and with interest, the
reasoning of an arbitral tribunal which has undertaken a similar examination. Courts
welcome useful assistance.” It is simply that the court is neither bound nor restricted
by the tribunal’s reasoning and findings.
24. The arbitration clause in issue is contained in an agreement setting out the terms of
membership of the international group of accountancy firms known worldwide as
Grant Thornton and regulated by the international umbrella entity (GTIL). The
agreement is called the Grant Thornton Member Firm Agreement (“the MFA”).
25. The MFA, which is governed by and to be construed in accordance with English law,
excluding its conflict of law rules, also makes provision for the use by member firms
of the intellectual property rights associated with the Grant Thornton name, and for
other matters relating to the conduct of the local firm’s business. The MFA includes
provisions for the expulsion of a local firm from the group.
30. The Claimants contend that unless and until each of the steps specified in section 14.3
of the MFA has taken place none of the parties may invoke the arbitration provision
in section 14.4 and refer the matter to arbitration.
31. As to what was actually done in this regard the relevant facts (which, except where
otherwise stated, I take from the Final Award and which I understand are not in
substance disputed) are as follows.
32. On 4 October 2010, JBPB’s lawyers, Tanner de Witt, recorded the fact that their
clients had and/or wished to “appeal” to the board of governors of GTIL, and sought
to invoke the dispute resolution mechanism under clause 14 of the MFA.
33. It appears from the correspondence to which I was taken that GTIL’s lawyers, Mayer
Brown JSM, initially contended that the provisions of the MFA relating to expulsion
(section 6.8) are not “within the province of the Dispute Resolution Procedure”; but
that when Tanner de Witt rejected that Mayer Brown JSM (after not a little
equivocation and delay, and still maintaining their position) adopted a different
stance. This was to urge Tanner de Witt either to agree to proceed direct to arbitration
on the basis that since the decision for expulsion was unanimous “there is now a lack
of objectivity and independence” such that “the only option is arbitration”, failing
which to proceed forthwith to invoke formally the dispute resolution procedure.
34. In the event, or so it appears from the correspondence in evidence, it was GTIL
which, by e-mail from Mayer Brown JSM to the Chief Executive dated 24 December
2010, recorded that JBPB had through Tanner de Witt advised them of a dispute, and
whilst “reserving all its rights in terms of alternative methods of determination of this
issue, it being a simple claim “in debt”, expressly submitted the issue to the Chief
Executive “within the meaning of clause 14.3(a) of the MFA.”
35. On 31 December 2010, the Chief Executive of GTIL informed Mayer Brown JSM by
e-mail as follows:
36. Returning to the facts as recorded in the Award, on 1 February 2011, Mr Peter Bodin,
as Chairman of the Board of Governors of GTIL, sent a message asking the Board
whether anyone felt themselves capable of acting on a reconciliation panel.
37. The Award does not record this: but the message from Mr Peter Bodin included the
following passages:
“It is the view of the GTIL legal team (and also external counsel) that
clause 14 does not apply in this scenario but we should go through the
process to avoid protracted legal argument later. The clause 14 process
consists of three steps. The first step, which was taken in December 2010,
was to refer the dispute for conciliation to Ed Nusbaum as CEO. Ed
determined that he could not act as a fully independent and objective
conciliator because of his previous involvement in dealing with the issues
concerning the former firm – including voting as a BoG member to expel
them. He therefore recused himself.
The clause 14 process now goes to a second stage, which is for the Board of
Governors to appoint a panel of three governors to act as
conciliators/mediators in the dispute between GTIL and the former firm.
To sit on the panel, clause 14.3(c) of the MFA provides that none of the
three (3) BoG panel members “shall be associated with or in any other way
related to the Member Firm or Firms who are parties to the dispute or
difference”. Whilst GTIL is not a Member Firm for this purpose, it is of
course a party to the dispute and GTIL acts by the BoG as directors of it.
Further, as a matter of fairness and natural justice it will be necessary for
the panel of three (3) to be fully independent and objective in relation to the
matters in dispute. Should a fully independent and objective panel of three
(3) BoG members not be identified, the dispute will go to third stage of the
process, which is external arbitration in London.”
38. On 14 February 2011, GTIL advised JBPB’s lawyers that no governors had put
themselves forward to serve on a reconciliation panel. As a result, the three-person
panel contemplated by section 14.3(c) of the MFA was never constituted.
Summary of arguments
39. The Claimants allege that the requisite steps to enable a process of pre-arbitration
conciliation were clearly prescribed, and were conditions precedent before an arbitral
reference could be made; as they were not fulfilled, the reference was thus invalid, so
that the Tribunal cannot have had jurisdiction.
40. On the other hand, GTIL and the Majority Partners allege that the steps adumbrated
were not sufficiently precise or certain to be contractually binding; and further or
alternatively, that on the true construction of the MFA, the parties did not intend and
did not agree that if the conciliation process failed, they should not be entitled to refer
the dispute or difference to arbitration.
41. The Tribunal considered that the steps prescribed do not constitute a detailed process
which is sufficiently certain to be legally enforceable (see paragraph 4.17 of the Final
Award).
42. It considered that the provision for the Chief Executive to have one month to attempt
a resolution was, on true construction, “merely a procedure to require that the dispute
be brought to his attention” (see paragraph 4.16): and likewise the provision for
further reference on to the Board of Governors (see paragraph 4.16). It characterised
the provisions together as “only a mechanism to permit the members of the Grant
Thornton group to keep the dispute “in house” for a period of time before it is brought
for binding settlement before objective third parties (in arbitration)”: see paragraph
4.17. It concluded (see paragraph 4.18) that the
43. The Tribunal thus, as I understand the Final Award on the issue of jurisdiction, took
the view that Section 14.3 lacked essential qualities of a binding provision for
mediation or conciliation, which it took to include that the process prescribed should
involve reference to a third party, independent (and possibly also, paid) person.
44. The Tribunal relied especially in that regard on the judgment of Ramsey J in
Holloway and another v Chancery Mead Ltd [2007] EWHC 2495 (TCC), [2008] 1 All
ER (Comm) 653, and in particular a passage at paragraph 81 of that judgment which,
after a review of the case law, states as follows:
45. The Tribunal also relied on Halifax Financial Services Ltd v Intuitive Systems Ltd
[1999] 1 All ER (Comm) 303 for the proposition that (as stated in paragraph 4.12 of
the Final Award) that “common provisions such as requiring that the chief executives
of the two companies shall first meet to attempt to resolve the dispute before
commencing arbitration cannot be a condition precedent to one party commencing
arbitration”. I think, however, that this extrapolation may go rather further than the
actual decision in that case, though the more confined proposition that was accepted
by McKinnon J was that “the courts [have] consistently declined to compel parties to
engage in co-operative processes, particularly ‘good faith’ negotiation, because of the
practical and legal impossibility of monitoring and enforcing the process…” (reliance
being placed on Courtney & Fairbairn Ltd v Tolaini Bros. (Hotels) Ltd [1975] 1 WLR
297, Walford v Miles [1992] 2 AC 128, and Paul Smith Ltd v H & S International
Holdings Inc [1991] 2 Lloyd’s Rep 127).
46. The Tribunal referred in addition to the decision of Steyn J (as he then was) in Itex
Shipping PTE Ltd v China Ocean Shipping Co, The “Jing Hong Hai” [1989] 2
Lloyd’s Rep 522 in support of the proposition that a mere agreement that the parties
shall seek to settle their disputes amicably and only refer the matter to arbitration in
the event of being unable to settle is not a legally enforceable obligation constituting a
condition precedent.
47. The case which on behalf of the GTIL and the Majority Partners Mr McGregor QC
presented as being the beginning and end of the matters in dispute, namely,
Sulamérica CIA Nacional de Seguros SA and others v Enesa Engenharia SA – Enesa
and others [2012] EWCA Civ 638, was not cited to the Tribunal, presumably because
no transcript was yet available of Cooke J’s decision at first instance and the Court of
Appeal judgment was published after the date of the Final Award.
48. In that case, the provisions in question (which the claimants contended constituted an
enforceable condition, compliance with which was precedent to the accrual of any
right to refer that dispute to arbitration) stated in material part as follows:
“11. Mediation
If the Dispute has not been resolved to the satisfaction of either party within
90 days of service of the notice initiating mediation, or if either party serves
written notice terminating the mediation under this clause, then either party
may refer the Dispute to arbitration.
In case the Insured and the Insurer(s) shall fail to agree as to the amount to
be paid under this Policy through mediation as above, such dispute shall
then be referred to arbitration under ARIAS Arbitration Rules…”
49. Moore-Bick LJ, with whom the Master of the Rolls and Hallett LJ agreed, upheld the
decision of Cooke J that this provision did not create a binding obligation to
commence or participate in a mediation process before arbitration because it was
insufficiently certain (see paragraphs 35 to 37). At paragraph 35 he cautioned that
each case must be considered on its own terms, and the court should be slow to deny
enforceability, but then at paragraph 36 he said this:
“In the present case, unlike Cable & Wireless Plc v IBM ([2002] EWHC
2059) and Holloway v Chancery Mead, condition 11 does not set out any
defined mediation process, nor does it refer to the procedure of a specific
mediation provider. The first paragraph contains merely an undertaking to
seek to have the dispute resolved amicably by mediation. No provision is
made for the process by which that is to be undertaken and none of the
succeeding paragraphs touches on that question. I agree with the judge,
therefore, that condition 11 is not apt to create an obligation to commence
or participate in a mediation process. The most that might be said is that it
imposes on any party who is contemplating referring a dispute to arbitration
an obligation to invite the other to join in an ad hoc mediation, but the
content of even such a limited obligation is so uncertain as to render it
impossible of enforcement in the absence of some defined mediation
process. I think that the judge was right, therefore, to hold that condition 11
is incapable of giving rise to a binding obligation of any kind.”
“41.1 The parties shall attempt in good faith to resolve any dispute or claim
arising out of or relating to this agreement or any local services agreement
promptly through negotiations between the respective senior executives of
the parties who have authority to settle the same…
41.2 If the matter is not resolved through negotiation, the parties shall
attempt in good faith to resolve the dispute or claim through an alternative
dispute resolution (ADR) procedure as recommended to the parties by the
Centre for Dispute Resolution. However, an ADR procedure which is
being followed shall not prevent any party or local party from issuing
proceedings.”
(The Centre for Effective Dispute Resolution (CEDR) model clauses include provisions
preserving the principle of voluntary participation and providing for elective unilateral
withdrawal at any time after the mediator’s appointment, but thereby also envisaging a
“certain minimum participation in the procedure” (for example, cooperation in the
appointment of a mediator and attendance at the first meeting called by him).)
Colman J held that there was an obligation on both parties to participate at least to the extent
of co-operating in the appointment of a mediator and attending at least one meeting (see
paragraphs 34 and 35 of his judgment). He adjourned any further proceedings until after the
parties had taken the prescribed minimum steps, noting (at paragraph 35) that although the
court retained jurisdiction not to enforce such provisions by injunction (since an injunction
was an equitable remedy and always discretionary) “strong cause would have to be shown
before a court would be justified in declining to enforce such an agreement.” He also
suggested (in paragraph 33) that
52. I have puzzled over that last phrase, which was much stressed on behalf of the
Claimants before me. On one reading, it might signify (as the Claimants urged) that
in the case of a unilateral bare commitment to attempt to resolve a dispute all that is
required is that the court should be able to discern what is the minimum that is
required to be done, without necessarily having to be able to go any further in
defining what else is required for the attempt not to be empty of any real content. But
I do not think that such a reading would be correct: and especially where (as here)
although certain steps in the envisaged conciliation process are prescribed, the content
of that process is not defined at all and the commitment is so generally and
equivocally expressed.
53. Further, I do not think the phrase (which is strictly obiter) can have been intended to
signify that the court may, as it were, extrapolate from a clause those parts of it which
it considers are sufficiently certain to be enforceable and treat that as being the
enforceable content of the clause. That would be to re-write the contractual bargain
struck. As it seems to me, and is confirmed by the judgments in Sulamérica, the court
must be satisfied that each part of the clause which was intended to be operative can
be given certain legal content and effect. (There may be an exception in the case of
provisions for machinery which is or has become wholly unnecessary or redundant:
but that is not (on either side's case) the position here.)
54. The last of the numerous cases cited to me which I should specifically mention under
this heading is the decision of the Court of Appeal in Petromec Inc and others v
Petroleo Brasileiro SA Petrobras and others [2005] EWCA Civ 891. In that case, the
Court of Appeal noted that adjudication of the question as to the enforceability of a
provision requiring negotiation in good faith with regard to the cost of a disputed
upgrade of a drilling rig was not essential to the disposition of the appeal; but
Longmore LJ (with whom Mance LJ (as he then was) and Pill LJ agreed) considered
that in the particular circumstances there were no good reasons for saying that the
obligation to negotiate the discrete issue as to the extra cost of the upgrade was
unenforceable: the task was defined and of comparatively narrow scope; the provision
in question was part of a complex agreement drafted by City Solicitors; and whilst
recognising the difficulty of determining when a requirement to negotiate in good
faith has been satisfied (the concept of bringing negotiations to an end in bad faith
being “somewhat elusive”) nevertheless the court should not deny enforcement on
that ground: “the difficulty of a problem should not be an excuse for a court to
withhold relevant assistance from the parties by declaring a blanket enforceability of
the obligation”. Though of course accepting that any review of Walford v Miles was a
matter for the House of Lords/Supreme Court he did not consider it could mandate
“blanket unenforceability” and he concluded as follows (in paragraph 121):
“It would be a strong thing to declare unenforceable a clause into which the
parties have deliberately and expressly entered. I have already observed
that it is of comparatively narrow scope. To decide that it has “no legal
content” to use Lord Ackner’s phrase would be for the law deliberately to
defeat the expectations of honest men, to adopt slightly the title of Lord
Steyn’s Sultan Azlan Shah lecture delivered in Kuala Lumpur on 24 th
October 1996 (113 LQR 433). At page 439 Lord Steyn hoped that the
House of Lords might reconsider Walford v Miles with the benefit of fuller
argument. That is not an option open to this court. I would say only that I
do not consider that Walford v Miles binds us to hold that the express
obligation to negotiate as contained in [the relevant provision] is completely
without legal substance.”
55. However, Longmore LJ’s implicit hope that Walford v Miles might be reviewed at the
highest level has not (yet) been fulfilled. Further, Petromec concerned a commitment
to negotiate in good faith to establish an issue of costing or price. It does seem that the
courts have been more ready to give effect to such commitments, construing them as
in effect stipulations for a reasonable or fair price and treating that as a sufficient
criterion for the courts to act upon. But this is not such a case. I do not think
Petromec really assists in the present context.
56. This recitation of authority illustrates the tensions, in the context of provisions for
conciliation or mediation of disputes prior to arbitration or court proceedings, between
the desire to give effect to what the parties agreed and the difficulty in giving what
they have agreed objective and legally controllable substance.
57. Agreements to agree and agreements to negotiate in good faith, without more, must be
taken to be unenforceable: good faith is too open-ended a concept or criterion to
provide a sufficient definition of what such an agreement must as a minimum involve
and when it can objectively be determined to be properly concluded. That appears to
be so even if the provision for agreement is one of many provisions in an otherwise
binding legal contract, with an exception where the provision in question can be
construed as a commitment to agree a fair and reasonable price.
58. However, especially when the relevant provision is but one part of a concluded and
otherwise legally enforceable contract the Court will strain to find a construction
which gives it effect. For that purpose it may imply criteria or supply machinery
sufficient to enable the Court to determine both what process is to be followed and
when and how, without the necessity for further agreement, the process is to be
treated as successful, exhausted or properly terminated. The Court will especially
readily imply criteria or machinery in the context of a stipulation for agreement of a
fair and reasonable price.
59. The Court has been in the past, and will be, astute to consider each case on its own
terms. The test is not whether a clause is a valid provision for a recognised process of
ADR: it is whether the obligations and/or negative injunctions it imposes are
sufficiently clear and certain to be given legal effect.
(1) Section 14.3(a) requires that the dispute or difference should be referred to the
Chief Executive with a view to him attempting amicably to resolve that
dispute or difference by amicable conciliation of an informal nature;
(2) Section 14.3(b) prescribes that the Chief Executive shall attempt to resolve
the dispute or difference in an amicable fashion within one month after receipt
of a request that he should do so;
(3) Section 14.3(c) prescribes that if the dispute or difference is not by then
resolved it should be referred to a three-person Panel selected by the Board
(none of whom is associated with or in any other way related to the member
Firm(s) who are parties to the dispute), it being provided that the Panel is to
have up to one further month to resolve the dispute or difference.
(1) At the first stage all that is required is a reference to the Chief Executive: that
seems to me to be a clear requirement, satisfaction of which is demonstrated by
the objective fact of a reference;
(2) However, no more is said in section 14.3(b) as to (i) what form the process of
conciliation should take (apart from the injunction that it is to be undertaken “in
amicable fashion”); nor as to (ii) who is to be involved in it and what (if
anything) they are required to do by way of participation in the process; nor
indeed as to (iii) what the obligation to attempt to resolve the dispute or
difference requires the Chief Executive to do;
(3) In relation to the next stage, of a reference to the Panel, again no more is said as
to (i) what the form or process of resolution should be; nor (ii) whether it is to
include participation by the parties to the dispute; nor again (iii) what will suffice
in terms of an “attempt to resolve” the dispute or difference, whether on the part
of the Panel or on the part of the other parties to the dispute or difference;
(4) As to the fourth stage, (i) nothing is stated as to whether the Panel must at least
take some step calculated to lead to resolution of the dispute or whether it may
determine that it cannot resolve it without taking any steps at all; but (ii) the
provision for the Panel to have only one month at most to attempt to resolve the
dispute or difference is clear.
64. The Claimants urged on me that none of these omissions deprive Section 14.3 of
enforceable legal effect, and the provision of an end date removes the difficulty there
would otherwise be in determining when and how the process is to be brought to an
end. They submitted, in effect, that the combination of (a) a prescription of the
sequence of steps or events to take place within a defined time-scale; and (b) the clear
purpose of Section 14.3 in providing for a finite period of deferral or cooling off
period; and (c) the certainty which the definition of the time-scale provides in
determining when the period of deferment is complete, is sufficient and certain.
65. Put another way, the Claimants contend that Section 14.3 does not prescribe, and does
not need to prescribe, any standards of compliance nor any basic process for the
exercise of conciliation. The conditions precedent alleged by the Claimants are simple
and absolute, not calling for or requiring any further agreement or (formalistic
compliance being sufficient) subjective judgment: there is nothing deficient or
uncertain in a provision which simply but unequivocally requires formalistic
compliance with prescribed steps in a prescribed sequence with a view to enabling an
opportunity for amicable resolution within a defined and limited time frame before
any party may commence arbitration; and there is no reason not to give effect to such
a provision as a condition precedent, even though no process for ADR, nor any
definition of what as a matter of substance is required of the parties is provided.
66. The Claimants further contend that Section 14.3 should not be compared with, on the
one hand, agreements to agree or to negotiate, nor, on the other hand, with provisions
(such as in Cable & Wireless) which incorporate CEDR processes by reference: and
the Tribunal was wrong to test the provisions by reference to such an analogy or such
a test (as they suggest it did in paragraph 4.12 of the Final Award). Nor, they
contended, should the obligations be treated as giving rise to a mutual obligation of
uncertain content: the sequential obligations on the Chief Executive and the Panel
should be regarded as purely unilateral and satisfied by any formalistic step towards
conciliation.
67. In summary: the Claimants submit that Section 14.3 must be construed as it is and
without seeking to label or shoe-horn it in to the established requirements for an
enforceable ADR clause as the Tribunal had done. The proper task of the Court is not
to assess whether a recognisable and sufficient process of dispute resolution (with the
ingredients identified by Ramsay J in Holloway v Chancery Mead) is provided for;
rather, it is to assess whether the specific provisions, read sui generis, are singly and
together sufficiently certain to be given legal effect.
68. The Defendants, on the other hand, urged on me the omissions which I have
identified as demonstrating such uncertainty as to render Section 14.3 impossible of
enforcement and thus incapable of constituting a binding condition precedent to the
commencement of arbitration. They submitted that section 14.3 was intended to be
far more than a simple provision for a period of deferment before commencement of
arbitration and for formalistic steps in that period with a view to some form of
resolution emerging. It was intended to provide for, and necessarily envisaged, a
(probably multi-lateral) process of conciliation, and must be judged accordingly in
terms of whether it defined with sufficient objective certainty what is required of the
parties for the purposes of that process.
69. They especially emphasised what they described as the “critical element of
equivocation” inherent in a direction to “attempt to resolve a dispute” and the
“nebulous” nature of the process contemplated. They posed the question in relation to
the obligation thus placed on the Chief Executive as to “what it is precisely that he has
to do to avoid being in breach of the obligation.” They likened the stipulation to the
“ad hoc” process found to be insufficient in Sulamérica and the provisions as a
whole as in substance mere obligations to agree to negotiate which have long been
held to be unenforceable (see Cable & Wireless at [16] and [23]), citing in particular,
Lord Denning MR’s judgment in Courtney and Fairbairn Ltd v Tolaini Brothers
(Hotels) Ltd [1975 1 WLR 297).
70. In summary, the Defendants submit that Section 14.3 provides for a process of
conciliation which, though doubtless intended to be enforceable (as was the provision
in Sulamérica), lacks the certainty to enable the Court to give it legal effect. The
process envisaged was even less certain than an agreement to negotiate, which is
plainly unenforceable.
Adjudication
71. I should admit to at one time having been attracted by Mr Machell’s basic argument
that the Tribunal had quickly and wrongly leaped to the conclusion that the provision
should be tested according to whether the ingredients of a valid ADR clause were
included in it. I have borne very much in mind the injunction in Moore-Bick LJ’s
judgment in Sulamérica (at paragraph 35) that each case must be considered on its
own terms and not by ticking off minimum ingredients for validity in the context of
clauses providing for mediation (or some other form of dispute resolution).
72. However, in line with the submissions of Mr McGregor, I have reached the clear
conclusion that Section 14.3 is too equivocal in terms of the process required and too
nebulous in terms of the content of the parties’ respective obligations to be given legal
effect as an enforceable condition precedent to arbitration. In particular, I accept that
the omission to give any guidance as to the quality or nature of the attempts to be
made to resolve a dispute or difference renders the Court unable to determine or direct
compliance with the provisions of Section 14.3(a), (b) and (c).
73. I have considered whether the negative stipulation or injunction in Section 14.3(d),
which in terms prevents any party commencing any arbitration procedures until the
earlier of (i) a determination by a Panel that it cannot resolve the dispute or difference
or (ii) the date one month after the request for conciliation of the dispute or difference
has been referred to it, may itself be given effect so as to defer any right to commence
any arbitration procedure if the steps set out in the preceding sub-sections have not
been taken.
74. That raises, as it seems to me, an issue as to whether Section 14.3(d) constitutes, on its
true construction, a permanent bar to any party commencing arbitration if either no
Panel as provided for in Section 14.3(c) is established or no request for conciliation of
the dispute or difference has been referred to it; or whether, rather, the true
construction of the provision is that if for any reason the conciliation process (which,
of course, they intended to be binding and enforceable notwithstanding that I have
held they were not) failed, any restriction on referring the matter to arbitration should
lapse no later than two months after it was first referred to the Chief Executive for
amicable conciliation. (Two months being the aggregate of the one month permitted
at each stage of the two-stage process envisaged by the preceding sub-sections.)
75. The Tribunal addressed this point at paragraph 4.8 of the Final Award as follows:
“It is arguable (as the [Claimants] contend) but by no means clear, that the “it” in
Section 14.3(d) refers only to the reference to a three-person panel of members of
the Board of Governors. However, the word could as easily refer to the date
when it was clear that the panel could not be constituted by reason of the
unanimous refusal of its potential members to serve. This would be a sensible,
commercial reading of the clause. After the failure of the conciliation process, for
whatever reason, a party was permitted (indeed obligated) to seek arbitration if it
wanted redress.”
76. I must confess that I found this approach, and the effort to give alternative meaning to
the word “it”, initially somewhat difficult to follow. However, I have concluded that
the conclusion reached by the Tribunal as to the true effect of the provision is correct.
77. In my view, the purpose of the provision is plain: to reinforce the provisions of the
preceding sub-sections but also to provide an end date after which any restriction on
the right to commence arbitration procedures in accordance with the MFA lapses. The
words need to be construed consistently with that purpose and if possible given
meaning in the context of events that may not have been foreseen.
78. As it seems to me the words “referred to it” in Section 14.3(d)(ii) should be construed
purposively as denoting a reference to the Panel if and when established, and if never
established, to the members of the Board from whom the Panel was to be selected. On
that interpretation, Section 14.3(d)(i) provides for the Panel to bring an end to the
period and Section 14.3(d)(ii) caters for the case where nothing emerges from any
Panel at all.
79. Alternatively, but to the same substantive effect, the words “such date as the Panel
shall determine that it cannot resolve the dispute or difference” in Section 14.3(d)(i)
should be construed as meaning (a) if a Panel is established the date of its
determination that it cannot resolve the dispute or difference but also (b) if a Panel
cannot be established, the date on which it is resolved that that is the position so that
in consequence the dispute or difference cannot be resolved by a Panel and the period
of deferment before commencement of arbitration is thereby terminated.
80. In reaching this conclusion, I am also comforted, as was the Tribunal, by the
unrealistic consequences of the Claimants’ contention that if no panel is established
no arbitration can be commenced, even long after the request for conciliation would
have been required to be referred to the second stage. I do not think it realistic to
suppose the parties to have intended that the Board or panel members could
indefinitely postpone the right to arbitration: but that would be the consequence of the
Claimants’ construction. And if it were to be suggested that the impossibility is self-
induced by the prospective panel members or by the terms of the invitation extended
to them, that would necessitate implying some standard of reasonable excuse for not
agreeing to be part of the panel which again would render the clause uncertain.
81. In that latter context, I should add that the Claimants cited Cipriani v Burnett [1933]
AC 83 (in the Privy Council) in support of the proposition that GTIL should be
precluded from claiming an entitlement to commence arbitration under a contractual
provision by which in other respects it had declined to abide. But all that GTIL and
the Majority Partners have done is to deny (successfully) the legal effectiveness of
Section 14.3 as a condition precedent. The agreement for arbitration under the rules
of the LCIA is comprised in Section 14.4. I do not see there was anything to prevent
or preclude either side from invoking that provision.
Conclusion and result
(1) The provisions of Section 14.3 lack sufficient definition and certainty to
constitute enforceable conditions precedent to the commencement of
arbitration in accordance with the provisions of Section 14.4.
(2) Further or alternatively, on its true construction Section 14.3(d) does not
prevent any party to the MFA from commencing any arbitration procedures
in accordance with its terms after the expiry of two months from the first
reference of a request for conciliation or (if earlier) the failure of the
conciliation process in consequence of (i) it not being possible to establish a
panel because there are no members of the Board willing to serve and/or (ii)
because all such members of the Board take the view that the dispute or
difference cannot not be resolved by such a panel. The arbitration in this
case was commenced well after any such time frame had expired and after it
was clear that no panel could be established because none of the members
of the Board considered that the dispute or difference could be resolved.
(3) On either approach, the Tribunal did have jurisdiction, as it itself concluded.
83. I shall therefore dismiss the claim. I invite counsel to prepare a minute of order
accordingly. That and any other matters can be dealt with when this judgment is
formally handed down.