PREPARATION PHASE
1 Created manuscript/initial documentation and brainstormed designs 19-Apr
2 Searched for a suitable machine shop 21-Apr
3 Finalized designs and submitted initial documentation 22-Apr
4 Visited Gayuma Machine Stop and made a partial payment 24-Apr
5 Procured materials and began fabrication 25-Apr
FABRICATION PHASE
1 Completed fabrication of Knight, Rook, and Queen pieces 26-Apr
2 Finished fabrication of all chess pieces 27-Apr
3 Waited for other groups to accomplish their chess pieces fabrication 28-Apr
FINISHING PHASE
1 Conducted search for painting business for metals 1-May
2 Initiated powder coating process 5-May
3 Start of powder coating process 6-May
4 Powder coating finished 7-May
5 Project pickup at Gayuma Machine Shop and submission to professor 8-May
6 Submission 10-May
Submission
END DATE DURATION
7 DAYS
21-Apr 3
21-Apr 1
22-Apr 1
24-Apr 1
25-Apr 1
5 DAYS
26-Apr 1
27-Apr 1
30-Apr 3
8 DAYS
4-May 4
5-May 1
6-May 1
7-May 1
8-May 1
10-May 1