Chapter 5
Chapter 5
Our focus!!
Traditional Project’s Critical Components (time, cost, & quality); in relation with
sustainable construction concept
Introduction
• Project planning
– Process of identifying all the activities necessary
to successfully complete the project.
– Provides map to guide where to go and focused
on how to get there
– Planned in early stage of Project life Cycle or also
before site activities start.
Introduction
• Importance of planning
– Reduce mistake and rework
– Avoid wastage
– minimize unnecessary in time and cost scheduling
– better quality control
– Effective project progress control
– Effective usage resources
Introduction
• Project scheduling
– Process of determining the sequential order of the
planned activities, assigning realistic durations to
each activity and determining the start and finish
dates for each activities.
– it can be used to manage, coordinate, control and
report.
– Depending on the sophistication of the user, the
schedule can take different forms.
Introduction
• Purpose of project scheduling
– Claim
– Project time and cost control
– Allocate project resources more efficiently
– As a monitoring tool
– Material delivery at site
– Storage – all material cannot put in the site (confined space)
– Avoid delay of the work and activity.
– Minimize the cash flow – as min as possible such as order material
stage by stage depend on the work needed.
– Control human resources and machinery To improve the efficiency
of the operation through the efficient use of resources and cost
control.
• Project planning is prerequisite to project scheduling!
Desired results of planning and
scheduling
• Finish the project on time.
• Continuous (uninterrupted) flow of work (no delays)
• Reduced amount of rework (least amount of changes)
• Minimized confusion on misunderstandings.
• Increase knowledge of status of project by everyone.
• Meaningful and timely reports to management.
• You run the project instead the project running you.
• Knowledge of scheduled times of key parts of the project.
• Knowledge of the distributions of costs of the project
• Accountability of people, define responsibility/authority.
• Clear understanding of who does what, when & how much.
• Integration of all work to ensure a quality project for the owner.
What are the different?
• Planning is more difficult to accomplish than
scheduling.
• The term planning and scheduling are often
used synonymously.
• Planning is first step to project scheduling.
• Tools used for planning and scheduling are
different!
Principles of planning and scheduling
• Begin planning before starting work, rather than after starting
work.
• Involve people who will actually do the work in the planning
and scheduling process.
• Includes all aspects of the project: scope, budget, schedule &
quality.
• Build flexibility into the plan, include allowance for changes and
time for reviews and approvals.
• Remember the schedule is the plan for doing the work, and it
will never be precisely correct.
• Keep the plan simple, eliminate irrelevant details that prevent
the plans from being readable.
• Communicating the plan to all parties; any plan is worthless
unless it is known.
COST
RESOURCES TIME
SCOPE QUALITY
Schedule
development
Create WBS Activity Activity
resource Duration
planning Estimation
Performance
Earthwork
Level 3 bond
Establish and
removal of site Structure Work
office
Architecture
Work
Architecture
Work
M&E work
Work Breakdown Structure (Outline)
• Construction of one – Testing and
block office building Commissioning
– Start Project – Project complete
– Preliminaries
• Performance bond
• Establish and removal
of site office
– Block A
• Earthwork
• Structure Work
• Architecture Work
• M&E work
Work breakdown structure (WBS)
• Importance of WBS
– Overall program can be explain in summary according to
each sub-element divided.
– Planning could execute.
– Cost and budget could estimate more accurately.
– Time, Cost and Performance of each element could be
monitor from time to time.
– Objective could be relate directly with the available
resources in the company.
– Network diagram and control planning could be prepared
in early stages.
– Responsibilities for each parties involve in every element
could be identify and assign.
Work breakdown structure (WBS)
Exercise:
You are the Project Manager for a Construction of
“Cadangan Membina dan Menyiapkan Sebuah
Rumah Banglo 2 Tingkat Serta Kerja-kerja Berkaitan
Untuk Tetuan Dato’ Kamal Jaafar.” Develop a
preliminary graphical work breakdown structure (up
to level 4) for the project given. Your WBS should
complete with all works needs in completing a one
unit bungalow.
Exercise (Suggested Answer-Graphical Method)
Level Cadangan Membina dan Menyiapkan Sebuah Rumah Banglo 2 Tingkat Serta Kerja-
1 kerja Berkaitan Untuk Tetuan Dato’ Kamal Jaafar
Level Performance
Structure Architecture M&E Sewerage
3 bond
Fittings
Ground level Floor Landscape
installation
Level
4
1st floor level Roof
2nd floor
Fittings
level
Exercise (Suggested Answer-Outline Method)
Techniques for scheduling
• Techniques used will vary depending on:
– Project’s size
– Complexity
– Duration
– Personnel
– Owner requirements
• Two general methods commonly used :
Bar chart (Gantt chart)
Critical path method (CPM/ network analysis
system)
Bar chart (Gantt Chart)
• Develop by Henry L.Gantt
• Is a graphical time-scale of the schedule,
length represent the duration of activity.
Advantages Disadvantages
Act. A 1
Act. B 2
Act. C 3
Act. D 2
Act. E 2
Bar chart (Gantt Chart)-Example 1
Activity A : 1 week, starting from 1 Jun 2014
(1/6-7/6)
Activity B : 2 week, starting from 8 Jun 2014
• Step 3: Draw the (8/6-21/6)
Activity C : 3 week, starting from 15 Jun 2014
activity bars (15/6-5/7)
Activity D : 2 week, starting from 22 Jun 2014
(22/6-5/7)
Activity E : 2 week, starting from 29 Jun 2014
(29/6-12/7)
Activity Duration Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
(week)
1/6 8/6 15/6 22/6 29/6 6/7
Act. A 1
Act. B 2
Act. C 3
Act. D 2
Act. E 2
Bar chart (Gantt Chart)-Example 2
Num. Activity Duration Start Date Cost (RM) Resources
(days) (person)
Activity Duration
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
4/5
5/5
6/5
7/5
8/5
9/5
(days)
Act. A 3
Act. B 5
Act. C 7
Act. D 5
Act. E 4
Act. F 6
Bar chart (Gantt Chart)-Example 2
Activity A : (4/5-6/5)
Activity Duration
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
4/5
5/5
6/5
7/5
8/5
9/5
(days)
Act. A 3
Act. B 5
Act. C 7
Act. D 5
Act. E 4
Act. F 6
S-Curve
• An S-curve is defined as:
"A display of cumulative costs, labor hours or
other quantities plotted against time. The name
derives from the S-like shape of the curve, flatter
at the beginning and end and steeper in the
middle, which is typical of most projects. The
beginning represents a slow, deliberate but
accelerating start, while the end represents a
deceleration as the work runs out."
S-Curve
• Type of S-Curve
– Physical S-Curve
– Financial S-Curve
• Both S-curve can be in Baseline (planned) or
actual S-curve
S-Curve (Example)
Num. Activity Duration Start Date Cost (RM) Resources/
(days) day
(person)
1 Activity A 3 4/5/2014 1,400.00 2
2 Activity B 5 7/5/2014 2,700.00 3
3 Activity C 7 10/5/2014 3,500.00 2
4 Activity D 5 15/5/2014 6,000.00 4
5 Activity E 4 17/5/2014 4,700.00 4
6 Activity F 6 19/5/2014 12,600.00 5
30,900.00
Based on bar chart in Example 2, construct S-curve (daily basis) for this
project:
1. Financial S-Curve
2. Physical S-curve (resources vs time & work vs time)
Planning VS Actual S-curve??
• Before this, we just create a planning bar
chart.
• What if, the real activities has started? How to
create actual S-curve?
• Actually, same process is involve. But it’s ok…
let’s take a look one example.
Planning VS Actual S-curve (Example 2)
Physical S-Curve (work vs time)
Num. Activity Duration Start Date Actual Actual Cost (RM) Resources
(days) Start Date Finish Date (person)
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
(days)
4/5
5/5
6/5
7/5
8/5
9/5
Date Start Finish
Date Date
15/5/14
Act. D 5 17/5/14 21/5/14
Activity A Activity B
Act. A Act. B
Node Node
Network Diagram
Diagram for construction of pad footing
Arrow - Logical
Node - Activity
Logical – Show the relationship
between activities
- Sequences of interrelated
activity
Basic definition in network diagram
• Activity- the performance of a task required to
complete the project. An activity require time,
cost, or both.
• Network- a diagram to represent the
relationship of activities to complete a project.
The network may be drawn as AOA/ADM or
AON/PDM.
• Duration- the estimated time required to
perform an activity.
Basic definition in network diagram
• Early start (ES)- the earliest time an activity can
be started.
• Early finish (EF)- the earliest time an activity can
be finished.
EF = ES + Duration
• Late finish (LF)- the latest time an activity can be
finished.
• Late start (LS)- the latest time an activity can be
started without delaying the completion date of
the project.
LS = LF - D
Basic definition in network diagram
• Total float (TF)- the amount of time an activity
may be delayed without delaying the completion
date of the project.
TF = LF – ES – D
• Free float (FF)- the amount of time an activity
may be delayed without delaying the early start
time of the immediately following activity.
FF(i) = ES(j) –EF(i) ;
i-preceding activity, j-following activity
Basic definition in network diagram
2 E 5 7 G 10
3 3
10 8 13 11 4 14
ES ACT EF
DUR
LS TF LF
Basic definition in network diagram
• Critical path – a series of interconnected activities
through the network diagram, with each activity
having zero total float time. The critical path
determines the minimum time to complete the
project.
• Dummy activity- an activity (represent by a
dotted line) that indicates any activity following
the dummy cannot be started until the
activity(ies) preceding the dummy are
completed. Does not require time. No dummy
activity for AON/PDM.
Activity Sequencing
• Understand the order of how the job to be
accomplished in the field.
• The planner must understand how various
activities of the project related to each other
in term of their logical sequence.
• Example preparing formwork before
reinforcement could be place & than pouring
concrete.
Activity Sequencing
• Predecessor
– A task whose start or finish date determines the
start or finish date of its successor task.
• Successor
– A task whose start or finish date is driven by its
predecessor task.
Link (Relationship)
• Finish to Start (FS) Act. A
– Activity B cannot start until
Activity A finish Act. B
Early Early
Start Finish
Late Late
Start Finish
BACKWARD PASS
Example (ADM)
Activity Duration (day) Predecessor (s)
Act. A 2 -
Act. B 3 -
Act. C 3 A
Act. D 4 B
Act. E 3 C,D
Act. F 2 C,D
Act. G 4 E
Act. H 3 F
Act. B 4
3
7 9
Act. D 5
4 7 7
Critical path
Exercise (PDM)
Activity Duration (day) Predecessor (s)
Act. A 2 -
Act. B 3 A
Act. C 5 A
Act. D 4 A
Act. E 2 B,C
Act. F 3 C
Act. G 4 C,D
Act. H 2 E,F,G
Width of B:
At 40km, the subgrade
works will starts at week
4.4 until week 5.
Height of A:
At week 3, subgrade
works from 13km to
21km.
Distance of C:
It is a time lag / time
float for 10km; between
subgrade works and base
LSM Diagram for highway project (adopted from Nunnally, 2014) course works.
1.4 weeks to be exact.