Hydropower Assignment Merged (017-022)
Hydropower Assignment Merged (017-022)
From this DEM file, it is clear that the maximum and minimum elevation of Arghakhachi district is 2259m
and 187m. The catchment area for location 1 of dam almost lie inside Arghakhachi District. So,
𝐴𝑟𝑒𝑎 𝑏𝑒𝑙𝑜𝑤 3000𝑚 𝑒𝑙𝑒𝑣𝑎𝑡𝑖𝑜𝑛 = 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑐𝑎𝑡𝑐ℎ𝑚𝑒𝑛𝑡 = 𝐴𝑟𝑒𝑎 𝑏𝑒𝑙𝑜𝑤 5000𝑚 𝑒𝑙𝑒𝑣𝑎𝑡𝑖𝑜𝑛
𝐶𝑎𝑡𝑐ℎ𝑚𝑒𝑛𝑡 𝐴𝑟𝑒𝑎 (𝐴) = 3.17 𝑠𝑞𝑢𝑎𝑟𝑒 𝑘𝑖𝑙𝑜𝑚𝑒𝑡𝑒𝑟
𝐴3000 = 𝐴5000 = 𝐴 = 3.17 𝑆𝑞. 𝐾𝑚.
Solution:
1) Monthly Average Discharge of Proposed head-works location (Chhedi khola)
Month Discharge (m3/sec)
January 0.09
February 0.08
March 0.30
April 0.13
May 0.06
June 0.22
July 0.65
August 0.97
September 0.72
October 0.35
November 0.16
December 0.11
Annual 0.32
Assignment 3 of Hydropower Engineering Sumit Paudel (017-022)
(NEC)
2) Calculation of total volume of water available in the river annually. (Hint: The area
under hydrograph gives flow volume)
Month Discharge (m3/sec) Volume (Mm3) (Area under curve)
January 0.09
February 0.08 0.224
March 0.30 0.501
April 0.13 0.567
May 0.06 0.250
June 0.22 0.369
July 0.65 1.146
August 0.97 2.135
September 0.72 2.227
October 0.35 1.410
November 0.16 0.672
December 0.11 0.356
Annual 0.32 9.856
Hydrograph
1.20
1.00
Discharge in m3/sec
0.80
0.60
y = 0.0259x + 0.1518
0.40
0.20
0.00
0 2 4 6 8 10 12 14
Month (Jan to Dec)
Assignment 3 of Hydropower Engineering Sumit Paudel (017-022)
(NEC)
Solution:
1) Monthly Average Discharge of Proposed head-works location (Chhedi khola)
Month Discharge (m3/sec)
January 0.09
February 0.08
March 0.30
April 0.13
May 0.06
June 0.22
July 0.65
August 0.97
September 0.72
October 0.35
November 0.16
December 0.11
Annual 0.32
n*Gamma*H = 459719.3293
Assume Generator Efficiency = 0.95
Turbine Efficiency = 0.9
For Conveyance Efficiency
For Canal
Length of Canal = 615 m
Width of Canal = 1.50 m
Assume Rectangular shaped canal
velocity of water in canal (m/s) = 1 m/s
Friction Coefficient (f) = 0.1600
Hydralic Radius (R) = 0.4286 m
Assignment 4 of Hydropower Engineering Sumit Paudel (017-022) (NEC)
0.8
0.6
FDC
0.4 PDC
0.2
0
0.00 20.00 40.00 60.00 80.00 100.00 120.00
Percentage exceedance of time
Assignment 4 of Hydropower Engineering Sumit Paudel (017-022) (NEC)
8) Calculate BC ratio assuming the useful life of the project to be 45 years and interest
rate 7%. Is the project economically feasible?
BC Ratio Calculation
Useful life of project = 45 years
Interest Rate = 7 %
Investment (I) = 65614425.76 NRS
Annual Revenue (A1) = 8002196.975 NRS
Assume, Annual Cost (A2) = 400109.8487 NRS
(5% of Annual Revenue)
Using Conventional B/C Ratio formula
PW (I) = 65614425.76 NRS
PW (B) = 108874063.7 NRS
Taking 5% of Investment as Salvage
= 3280721.288 NRS
Value
PW (S) = 156206.5861 NRS
PW (O & M) = 5443703.185 NRS
Then,
B/C Ratio = 1.8047 >1
𝑃𝑊 (𝐵)
𝐵𝐶 𝑅𝑎𝑡𝑖𝑜 =
𝑃𝑊 (𝐼) − 𝑃𝑊(𝑂 & 𝑀) + 𝑃𝑊 (𝑆)
Since, B/C Ratio >> 1, So, project is economically feasible.