2024 Enginerring Survey Notes
2024 Enginerring Survey Notes
Urban and
Regional of
Planning (URP)
School
Environme
ntal of
Plateau
State
Polytechni
c Barkin
ENGINEERI
NG
SURVEY
(SUG 208)
ND11-GCIVIL
ENGINEERIN
April, 2023
ENGINEERING SURVEY-
Engineering survey involved those activities carry out in the planning and execution of surveys for
the location, design, construction, operation and maintenance of civil and other engineering
projects.
It falls under the field of large scale engineering surveys e.g. of engineering surveys are: surveys for
design and location of roads, railways, pipelines, power lines. Micro wave, telephone routes,
bridges, dams, and irrigation works etc.
Moreover, surveying is basic to engineering. Before any engineering work begins there is need for a
prepared plan or map of the area showing the topographical details which involve the horizontal and
vertical measurements.
Stages in engineering survey controls and presentation of data
1) Preliminary investigation surveys- this refers to the collection of data b y the proper
means in order to provide the based map on which the design is carried out his is usually
in a format of a topo. Map.
2) Setting out of the design on the ground and relevant measurements to support the
compliance with the design.
3) Monitoring of construction project.
Engineering survey or common known as construction surveying is sub divided into two classes
namely
a) Route surveying
____________________________________________________________________________
O O
(a) Arc definition (b) chord definition
ARC DEFINITION-
From familiar proportion (fig 3.1(a), we have
100 D 360 100 5729.598
= R= ×
2 πR 360 D 2π = D ft
If 20meres arc (or chord) length is the basis for the degree of the curve, we get.
20 D 20 360 1145.92
=
2 πR 360 from which R= 2 πR D = D metres
If the definition is based on 10m arc length we have
10 D 10× 360 572.958
= from which R= = metres
2 πR 360 2 πD D
ELEMENTS OF SIMPLE CURVE
(P.I) V
(P.C) T 1 T 2 (P.T)
A R R B
O Fig 3.2
Considered fig 3.2
⮚ Length of the curve (l):
πR
L=T 1cT 2=RD where D is in radians = ------------------------- (i)
180 D
Where D, is in degrees
If the curve is designated by is degree of curvature the length of the curve will depend upon
the criteria used for the definition of the degree of the curve.
A. Arc definition: length of arc =100ft.
Since any two central angles of the same circle are proportional to the corresponding intercepted arc
(or chords), we have
∆ l
= ------------------------------------ (iia)
D 100
Or
B. Arc definition: length of arc =20m
2∆
l = D metres ------------------------------ (iib)
πD ° R
⮚ The length of the cure is calculated according to the formula: CL = 180
D
⮚ The length of the long chord (L) is calculate from: L= 2Rsin sin 2
⮚ The long chord is divided into equal halves of the (left haft and the right half). Here the
D
● Oo =DE=versed sin of curve = R(1- cos cos 2 ) ------- (1)
OT 12 = O D2+T 2 D2
2
L
Or R2= (R−Oo)2 + ( )
2
Or R-Oo=√ ❑
Or Oo=R−√ ❑----------------------------- (11)
Thus, the mid-ordinate Oo can be calculated from equ. (1) or (2)
Considering the left half of the long chord, the ordinates O 1, O2, ----- are calculated a distances x 1,
x2------- taken from D towards the tangent point T 1. The formula for the calculation of ordinates is
deduced as follows:
Let P be a point at a distance x from D. then PP 1 (Ox) is the required ordinate. A line P 1 P2 is
drawn parallel to T1 T2. From triangle OP1 P2
Or R Oo Ox = √ ❑
Or O = √ ❑
The ordinates for the right half are similar to these obtained for the left half.
1) Let AB and BC be two tangents meeting at a point B, with deflection angle ( refer to fig3.4)
B
P4 P3 P2 P1 E
T1 T2
A 4 3 2 1 m C
fig3.4
2) The tangent length is calculated from the usual formula, and points T 1 and T2 are marked on
the ground with pegs.
3) The length of the long chord, T 1 T2, is calculated from the usual formula. The long chord is
bisected at point M. the curve will be symmetrical on both sides of M.
4) The ordinates are calculated for the left haft at some regular intervals points, 1, 2, 3, and 4 are
marked with pegs along the long chord as shown in fig3.4.
5) Ordinates O1, O2, O3 and O4 are calculated from the usual formula
6) Perpendiculars are set out at points 1, 2, 3 and 4. The calculated ordinates O 1,O2,O3 and O4
identified along these perpendiculars and pints P1,P2 P3 and P4 are marked with pegs.
7) In the right let point 1’ 2’ 3’ and 4’ are marked who pegs and the corresponding ordinate
(obtained for the left haft) are set out to mark with points P’1, P2’ P3’ and P4’.
8) All these points P1, P2----- and P1’ P2’------- are on the curve. These points are joined by rope or
thread to show the shape of the cure along the alignment (centerline) o the project.
Let AB and BC be two tangents intersecting at B, the deflection angle being (fig3.5). The tangent
length is calculated and tangent points T1 and T2 are marked.
B
T1 T2
A R R C
2∂ T1 P2 =l2 P1 P2=l2
O Fig3.5
Let P1 = first point on the curve
T1 P2 = l1 length of the first chord (initial sub- chord)
∂ 1= deflection angle for first chord
R= radius of the curve
for setting out a circular curve of radius 100m and deflection angle 30 by the method of offsets
from the long chord.
PROBLEM 2
Two tangents intersect at change 1,250m. The angle of intersection is 150 . Calculate all data
necessary for setting out a curve of radius 250m by the deflection angle method. The peg intervals
may be taken as 20m. Prepare a setting out table when the least count of the vernier is 20 .
Calculate the data for field checking.
PROBLEM 3
Two straight roads meet at a deviation angle of 52 30’. If the roads: are to be connected by circular
curve of radius 1500m. Find
a) Tangent distance
b) Length of curve
c) Chainage a the beginning of curve
d) Change at the end of curve. If the chainage of the intersection point is 6344.5m.
Problem 4
The chainage of the intersection point of two strength is 64 93.72 and the intersection angles is 12
48’ 20’’. They are to be joined by a right hand 10 curve. Calculate the data required o set out the
curve by deflection angles in 20m chords, for both steel tape and EDM.
PRACTICAL PROBLEMS ENCOUNTERED IN SETTING OUT CURVE.
1. Intersection point inaccessible
2. Obstruction on the curve
3. Tangent point inaccessible
4. Approximate methods of setting out curve.
WHEN- THE POINT OF INTERSECTION IS INACCESSIBLE
When the point of intersection is inaccessible, a line is run (or traverse if necessary) to connect the
two tangents. In fig 3.6, two points D and E are established on the strengths YX, ZX. If D and E are
intervisible the angle YDE, DEZ and the distance DE are measured. The angle of the triangle XDE
can be calculated, and the sizes of XD and XE are deduced as well. The intersection angle D can be
found likewise. The tangents point can then be established by setting out from D and E respectively.
It the intervisibility position can’t be found for D and E, and then a traverse is run between them
using DY as the initial orientation and closing in the deflection on E
D E
A B
Y Z
O fig 3.6
PROBLEM 5
Two straights of a highway are to be connected by a simple circular curve of 22 . It was found that
the intersection point of these straight is inaccessible and hence the establishment of an auxiliary
angles a U and V of length 289.56m. If the measured auxiliary angles at U and V are 162 50’ 37’’
and 164 53’ 05’’ respectively, and the chainage of U is 2118.18m. Compute the setting out
deflection angles for a left to right setting out using 20m chords through chainage basis.
OBSTRUCTION ON THE CURVE
When the obstruction is on the curve, first and foremost set it as far as possible from the first
tangent point A, an obvious recourse is to set out the remainder of the curves from the second
tangent point. If this is not convenient, the first visible point after the obstruction (e.g. P 4 in fig 3.7)
is fixed from A by turning off the deflection angle δ 1+ 3 δ from AX and setting out the chord
distance.
1
AP4 = 2R sin sin (δ 1+ 3 δ )
2
X
A B
O fig 3.7
The theodolite is moved to P4 set up, sighted on A and transited. Turning the telescope through a
horizontal angle of δ 1+ 3 δ gives the direction of the tangent at P 4 and the remaining points on the
curves, both before and after P4 can be set out from this direction.
TANGENT POINT INACCESSIBLE
When the tangent point is inaccessible the first point is carried round or over the obstruction by
triangulation or traversing, points D and F are fixed on the straights as shown in fig 3.8. The
chainage of A and B are calculated in the usual way and the distance AF. The lengths of the sub
chords are calculated and the curve is set out from B
X
G
A H B
D R R
O fig3.8
T
D C E
A B
∆∆
R R
2 2
O fig 3.9
1
In fig 3.9 CD = DE
2
T XA XC ∆ R × XC
XC = [( XD ¿ ¿2−¿ ( XD ¿ ¿2]1/2 and = = = tan tan , Then T =
R AO CD 2 CD
ASSIGNMENT
1. Distinguish between longitudinal section and cross sections
2. Discuss the term “sectioning” and its requirements.
3. The centre line of two straight of a line is found to intersect at X with a deflection angle of 27
59’ 24’’ If the straights are to be connected with a circular curve of 18. Tabulate all the setting
out data, assuming 25m chords through a chainage basis. The chainage of X being 6259.59m
and setting out would be done using tangential angle and tape only.
A 0 AB=90 45
20
40
60
80
B 100 BC=130 45 BA=270 45
120
WORKING PROFILE
Is the original profile or longitudinal section with the position of the new work levels shown on it,
their relation is to the existing ground level and any other information which may be needed during
the construction.
CROSS SECTIONAL LEVELING
Where profile leveling is in progress, cross sectional leveling should also be done as well. The cross
sections are taken perpendicular to the centre line of alignment at some regular intervals (say 20m,
40m, e.t.c). The main purpose of this is to know the undulations of the ground surface traverse to
the centre of the road. The length of cross section depends upon the nature of the work.
Generally, this type of section provides the most suitable and economic levels to which the ground
is to be worked in the traverse direction e.g. at right angle to its length. It also provides details for
deducing the position, height and slope of any necessary embankments. Finally: the earthwork
quantities for costing purposes and the suitable provision of earth moving plant.
The levels are taken at an interval of 5m on each side; additional readings may be taken if the nature
of the ground surface suddenly changes. The staff readings at a cross section are entered as follows.
Distances BS IS FS Rise Fall RL Remarks
Left centre Right
0 0.760 100
5 1.875 1.115 98.885 R1
10 2.360 0.485 98.400 R2
15 0.985 1.375 99.775 R3
20 0.375 0.610 100.385 R4
5 2.015 1.640 98.745 L1
10 1.550 0.465 99.210 L2
15 0.790 0.760 99.970 L3
20 1.525 0.735 99.235 L4
Summation : 0.760 0.525 3.210 3.975
AREA COMPUTATION
The term ‘area’ in the context of surveying refers to the area of a tract of land projected upon the
horizontal plane, and no to the actual area of the land surface.The following is a hierarchical
representation of the various methods of computation of area.
Area
O1 h1 O2 h2 O3 h3 O4 h4 O5 h5 O6
fig 5.1
O1 O2 O3 O4 O5
Fig 5.2
n= number of divisions
n 1 = number of ordinates
O1+O2 ±−−−−−−−−−−−−−+O n
Area = On +1 l ------------- 5.2
∑ of ordinates
I.e. are = no . of ordinates length of base line.
Consider 5.13
O1 O2 O3 O4 O5
d fig 5.3
d= common distance
O1+O2 O2+O3
1st area = 2 d, 2nd area = 2 d
O3+O 4 On−1+O n
3rd area = 2 d, Last area = 2 d
d
2
Total area = {O1, 2O1 , 2O2 , ---------------- 2On-1, On} ------- (5.3) =
common distance
2
{(1st ordinate last ordinate 2(sum of other ordinate )}
Thus, the trapezoidal rule may be stated as follows: to the sum of the first and the last ordinate,
twice the sum of intermediate ordinate is added. This total sum is multiplied by the common
distance. Half of this product is the required area. Area is equal to product of the common interval d
and sum of intermediate ordinates plus average of the first and last ordinate. If the intervals are not
equal the area of the trapezium has to be computed separately and added together.
LIMITATION: there is no limitation for this rule. This rule can be applied for any number of
ordinates.
SIMPSON’S RULE
In this rule, the boundaries between the ends of ordinates are assumed to form an arc of a parabola.
Hence Simpson’s rule is sometimes called the parabolic rule. Refer to fig 5.4 Let O 1, O2, O3 = three
consecutive ordinates, d = common distance between the ordinate
f e d
F E D
O1 O2 O3
A d B d C
fig 5.4
2
=3 (2d) (Ee)
2 O1+O3
=3 {O2 } 2d
2
So, the area between the first two divisions,
O1+O 3 2 O1+O 3
∆ 1= 2d {O2 } 2d
2 3 2
d
{O1 4O2 O3}
3
d
Total area = 3 {O1 4O2 2O3 4O4--------- On}
d
[(O1 On 4(O2 O4 --------) 2(O3 O5 ----)]
3
commondistance
{(1st ordinate last ordinate) 4(sum of even ordinates) 2(sum of
3
εP
= (y0 x1 y1 x2 ------------------------ O1, O)
Sum of the products along the dotted line,
εQ
= (0 y1 x1 y1 ------------------------ O, y0)
WORK OUT PROBLEM
The following perpendicular offsets were taken from a chain line to a hedge
Chainage (m) 0 5.5 12.7 25.5 40.5
Offsets (m) 5.25 6.50 4.75 5.20 44.20
Calculate the area between the chain line and the hedge by the coordinate method.
INSTRUMENTAL METHOD
The instrument used for computation of area from a plotted map is from planimeter. The area
obtained by plannimetr is more accurate than that obtained by the graphical method. There are
various types of plannimetter in use. These are:
❖ Roller plannimeter.
However, the amslar is the most commonly used now. The essential parts of the plannimeter are as
follows:
❖ Racing arm
a b
B c A
a+b+ c
Area = √ ❑ where s =
2
AREA FROM CO-ORDINATES
In this method independent co-ordinates of the points are used in the computation of area.
D (XD, YD)
B (XB, YB)
Co-ordinates method
To avoid negative sign, the sign O is chosen the most southerly and westerly point.
Total: area of the traverse.
1 X D+ XC XB+ XC X D+ X A
A= 2 (XC XB) (YC YB) ( 2 ) (YD YC ) ( 2 ) ) (YA YB) ( 2 ) (YB YA)
Or
2A= XA YB XB YC XC YD XD YA XB YA XC YB XD YC XA YD = (XA YB XB YA )
(XB YC XC YB ) ( XC YD XD YC ) ( XD YA XA YD)
The above relation can be expressed as follows for easy remembrance.
YA XA
YB XB
YC XC
YD XD
YA XA
The co-ordinates can be also listed in the following form
X A X B XC X D X A
Y A YB Y C YD Y A
A1 A2 A3 A4 A5 A6 An2 An1 An
D -----------------------------------------------
Fig 5.1
A) TRAPEZOIDAL RULE (AVERAGE END AREA RULE)
D
Volume (cutting or filling), v = {A1 + An + 2(A2 + A3+------- An-1)}
2
commondistance
I.e. volume = {area of 1st section + area of last section +2(sum of area of other
2
sections)}
B) PRISMOIDAL FORMULA
D
Volume (cutting o filling), v = {A1 + An + 4(A2 + A4+ An-1) + 2(A3 +A5 +------- An-2)}
3
commondistance
I.e. volume = {(area of 1st section + area of last section +4(sum of area of even
3
sections) + 2(sum of areas of odd sections)}
The prismoidal formula is applicable when there are an odd number of sections. If the number
section is even, the end strip is treated separately and the area is calculated according to the
trapezoidal rule. The volume of the remaining area is calculated in the usual manner by the
prismoidal formula. Then both the results are added to obtain the total volume.
VOLUME FROM CONTOUR LINE
Volume may be found from contours using either the end area or prismoidal methods. The areas of
the sections are the areas encompassed by the contours; the distance between the sections is the
contour interval.
100
V =volume of water, earth, tipped material etc. Between contour lines x and y
A x + A1
= × D where D is the vertical interval.
2
WORK OUT EXAMPLE
The area within the underwater contour lines of a lake area as follows
Contour (m) AOD 190 188 186 184 182
Area (m2) 3150 2460 1630 840 210
Calculate the volume of water in the lake between the 182 and 190m contours.
VOLUME FROM SPOT HEIGHTS
This method is used for obtaining the volume of large deep excavations such s basements, borrow
pits, underground tanks and is on where the formation level can be sloping, horizontal or traced.
The volume canbe computed by taking levels of number of point along a grid. The difference
between the formation level and the existing level of the ground will give the height of fill or cut at
the corresponding point. The volume of any square says a, b, c, d.
a b f
d c e
Secondary point
For large projects, it is common engineering practice to establish a rectangular grid system. Usually
such a system is based on a local coordinate system. The ends of major x and y grids are fixed by
concrete monument supporting a metal disc. Intermediate points are fixed by wooden sakes 50
100mm.
SETTING OUT OF BUILDING STRUCTURES: The first tasks in setting out a building or
structure is to locate the ownership line. This is required for:
- To provide a baseline for layout
- To check that the pressed building does not encroach on adjoining properties.
When setting out a building by theodolite and ape such as a rectangular structure, the following
stages would occur (fig 6.2)
Profile board /offset detail peg
Theodolite
(a)
9090° °
(b)
Profile /offset
still require here
X X
Check
(c)
Fig 6.2
❖ Set up the theodolite on the line and locate two corners of the building and two
❖ Set up the theodolite at one corner then sight onto the other corner, or the original
❖ Check the length of the furthest side and the diagonals fig6.2©
❖ Set the up the theodolite on the third corner, sight the fourth corner and establish