Nyadi Work Progress Report
Nyadi Work Progress Report
Progress Report
(May 2019)
Kathmandu, Nepal
Nyadi Hydropower Limited (NHL)
Buddha Nagar, Kathmandu, Nepal
Position Date
7. Government Land Leasing and the purchase of the private land ........................................... 26
8. Work Related to Corporate Social Responsibility ..................................................................... 26
9. Initial Public Offer (IPO) of Nyadi Hydropower Limited ......................................................... 28
Annex 1: Salient Features of Project ..................................................................................................... 28
Annex 2: Project Schedule ....................................................................................................................... 30
1. Introduction
1.1. Background
Nyadi Hydropower Project (NHP) was first identified in 1993 during the preparation of the Small
Hydropower Master Plan. The feasibility study of the project (20 MW) was completed by Lamjung
Electricity Development Company (LEDCO) in the year 2000.
In October 2006, Butwal Power Company Limited (BPC) and Lamjung Electricity Development Company
(LEDCO) had an understanding to develop the NHP together. As per agreement made between BPC and
LEDCO, Nyadi Hydropower Limited (NHL) was established on 2063/11/17 (01/03/2007) to undertake the
NHP independently. The project is being developed through a Special Purpose Vehicle (SPV), by Nyadi
Hydropower Limited with BPC as a major stakeholder. Feasibility study of NHP (30 MW) was completed
by NHL in October 2010.
The project has an installed capacity of 30 MW and will generate 168.55GWh of energy annually. The
generated power will be connected to a proposed NEA’s Hub that will be constructed at Marsyangdi
corridor, about 6 km south of the powerhouse. Moreover, about 250 m long adit tunnels which include
Naiche adit, Surge adit and ventilation adit are also proposed to make 4 headings for excavation and
construction of the headrace tunnel. Surge shaft is designed near the end of the headrace tunnel having
diameter of 5.0 m and 35 m height.
An about 14 m diversion dam has been designed to construct across the Nyadi River. The water from
intake is feed to underground settling basin and conveys it through about 3840 m long headrace tunnel and
745 m long penstock pipe. A surface powerhouse has been proposed on the right bank of Nyadi River at
the Thulibesi. The gross head of the project is 334.40 m while design discharge of the project is 11.08 m3/s.
Page 1 of 32
1.3. Completed Milestones
2. Institutional Arrangement
Following entities constitute the whole institutional arrangement of Nyadi Hydropower Project having
Installed Capacity 30 MW
The Employer/Owner : Nyadi Hydropower Limited (NHL)
The Engineer/Consultant : Hydro-Consult Engineering Limited (HCEL)
Financing Institution : Everest Bank Limited as Lead Bank; Nabil Bank Limited and Global IME Bank
Limited as Co-Lead Banks; Himalayan Bank Limited, Sunrise Bank Limited and
Hydroelectricity Investment and Development Company Limited (HIDCL)
Page 3 of 32
11 Total station (TS02 plus) 1 set 35 Pneumatic Pick 5
12 Air drilling (Jackhammer) 20 36 Wheel barrow 25
13 Air storage tank 5 37 Electronic truck scale 1
14 Shotcrete machine 1 38 Electric wire rope hoist 1
Cutting machine (Abrasive
15 18 39 Threading machine 2
cutter)
16 Vibrating screen 2 40 Grouting Machine 1
17 Bar straightening cutter 1 41 Vibrator 2
18 Wheel Loader 2 42 Wheel loader(Small) 3
19 Welding machine 32 43 Concrete pump 3
20 Blower fan 7 44 Submerged water pump 15
21 Air receivers 5 45 Sump pump 20
22 Fuel tank 2 46 Self-priming pump 5
23 Transformers 4 47 Mortar mixture 2
24 Low voltage Distributor 4
Page 4 of 32
Table 1.3: Materials stock at Project site
S.N. Materials Quanti S.N. Materials Quanti
ty ty
1 Drill Rod 400 pcs 16 Engine oil 9 drums
2600
2 Stellidium alloy bit (42*22 mm) 17 Safety belt 42 pcs
pcs
3 Ventilation pipe (45 mm) 6 pcs 18 Mortar spraying pipe 70 rolls
Metal sheet plate 8 mm
4 Hose pipe (25 mm dia.) 120 pcs 19 25 pc
(8"*4")
3000
5 Scaffold couples 20 Jag shakti TMT rebar (16mm) 80 tons
pcs
6 Steel rope 3 roll 21 Jag Shakti TMT rebar (20mm) 60 tons
7 M.S. Sheet (2mm) 1700 kg 22 Jagdamba TMT rebar (25mm) 22 tons
1200
8 M.S. Angle ISA (40x40x5mm) 400 kg 23 Formwork board
pcs
9 M.S. Black pipe (20x20x2mm) 2000 kg 24 Lubricating oil 40 drum
M.S. Black pipe Wood planning machine and
10 45 ton 25 5 boxes
(38x38x2.2mm) its spare parts
37060
11 M.S. Black pipe (2.7mm) 26 Steel plates for Penstock 500 ton
kg
12 M.S. beam ISMB (150*75 mm) 7000 kg 27 Cement 70 ton
13 Channel (125*65 mm) 2375 kg 28 Sand 1200 m3
14 Channel (150*75 mm) 1580 kg 29 Aggregates 1100 m3
15 Hume pipe (75cm dia.) 6 pc 30 Diesel 9000 ltr
6. Project Progress
Page 7 of 32
Project Status of underground Surge Shaft and Ventilation Tunnel
Page 8 of 32
6.1. Distributary Structure
River diversion from the Distributary structure to the Diversion tunnel has been completed on 1st January
2019.
Page 9 of 32
Figure 3: Excavation Works for Downstream Cut off wall at Headworks
Figure 4: Formworks Placement Level from 1361.50 m at Downstream Cut off Wall
Page 10 of 32
Figure 5: First Lift Concreting Works at Downstream Cut off Wall at Headworks
Page 12 of 32
Figure 7: Shotcrete Lining of Tunnel at the Upstream of Adit 2
6.8. Penstock
The length of penstock alignment is 780 m. 13 nos. of saddle support (40%), 11 nos. of anchor blocks (5%)
and concrete staircase has been constructed at back slope of powerhouse. About 40 % of excavation of
penstock alignment has been finished. Steel plate for the penstock fabrication has arrived at the site and
cutting and rolling of steel plate has been started; welding of the bifurcation has been finished in the month
of January. Concrete casing of Penstock pipe has been started.
Page 13 of 32
Figure 8: Concreting Works at Penstock Alignment between AB 7 to AB 6
Page 14 of 32
6.9.Powerhouse, Tailrace and River training works
Final level of powerhouse excavation is completed and the concreting is ongoing. About 75% of the
concreting has been finished in the month of May. Concreting work at slab of Assembly bay level 1047.00
m has been completed. Concreting of Main Unit Section up to level 1050.845 m and Control room slab
level 1051.10 m has been completed.
Structural concrete of tailrace has been completed. River protection works has been completed in the
powerhouse area. Retaining wall about 153 m has been completed. Storage yard has been established
about 300 m away from the powerhouse towards Naiche.
Figure 10: Reinforcement Works at Main Unit Section up to Level 1050.845 m of Powerhouse
Page 15 of 32
Figure 11: Reinforcement and Formworks Placement at Beam and Column of Control Bay of Powerhouse
Page 16 of 32
Figure 13: Concreting at Main Unit Section up to Level 1050.845 m of Powerhouse
Page 17 of 32
6.12. Quality Control Works
Concrete cube test (7 days and 28 days), tensile strength test and shotcrete test is continued to the period
closing.
Installation
Leaf Installation
superstructure
Fabrication of
Second Stage
Plate Cutting
Plate Cutting
Typical Parts
concreting
Frame Ins.
Welding
Welding
Drilling
A HEADWORKS
1 Under sluice 2 0 0 0 0 0 0 0 0 0 0 - - 0
Radial
2 Under sluice 2 0 0 0 0 0 0 0 0 0 0 0 0 0
stoplog
3 Sewage sluice 1 0 0 0 0 0 0 0 0 0 0 0 0 0
gate
4 Intake gate 1 0 0 0 0 0 0 0 0 0 0 0 0 0
B SUB 6 OTHER GATES 0
TOTAL
1 Bulkhead 1 0 0 0 0 0 0 0 0 0 0 - - 0
gate
NAICHE
2 Bulkhead 2 0 0 0 0 0 0 0 0 0 0 0 0 0
gate adit 1
C SUB 3 0
TOTAL
TOTAL 9
Page 18 of 32
a) Overall Progress in Fabrication of Pipe till May 2019
The following table shows the overall fabrication of penstock pipe for the month April 2019.
Fabrication (length m)
S Thickness Total
length plate NDT Sand Remarks
N (mm)
(m) cutting Rolling welding test blasting Painting
TOTAL
776.56 776.56 657.04 616.31 565.70 565.70 565.70
LENGTH
TOTAL
PROGRESS % 100 84.61 79.36 72.85 72.85 72.85
Page 19 of 32
SN Thickness Total total This This Net Net
(mm) length weight(kg) month month fabricated(kg) remaining
(m) progress progress (kg)
(m) (kg)
Page 20 of 32
c) Progress made in Installation of Penstock Pipe
The following table shows the Progress of installation of Bends of Penstock Pipe for the month of May
This month
Till last
SN Description Diameter(m) Length(m) progress
month
(m)
Page 21 of 32
d) Progress made in Fabrication of Bends
The following table shows the details about fabrication of Bends of Penstock pipe for the month of May
SN Description Total wt.(kg) Fabrication Installation
Underground penstock
1 Not Completed Not Completed
bend 2270
a. Generator Foundation
The placing of form work and rebar for generator foundation at the level of 1050.845 m as per the
drawing was started on May 01, 2019 and the final concreting was done May 28, 2019. The outer
diameter is 7200 mm and the internal diameter of 5480 mm has been constructed as per the design.
Type C cable brackets has already been installed on the wall of Pump House and MIV room in the
month of May 2019. It consists of L63x6, L40x4 of Galvanized Angle Steel. The dimension of this type
of cable bracket is 300x300x400 mm height and 400 mm of length. This cable bracket was welded on
th 1047.6 masl of the Powerhouse wall.
Page 22 of 32
c. Earthing Mat
Galvanized MS strip of 0.5 mm thick and 6 mm flat has been lied down for about approximately 1599.5
m2 of switch yard and 893.4 m2 above the tailrace culvert area. The spacing of the earth mat was 4x3.5
m gapping. The earth mat was joined by the thermal welding process. It is to be noted that this Earth
Mat is not the final earth mat for the Powerhouse and Switch Yard as the design is yet to be finalized,
but this is done by the installation team for additional safety only. The switch yard area is not yet
finalized. Thus, Earth mat lying down work might be extended after the final layout of the switch yard
being provided. Similarly, the MS strip also has been lied down along the Bifurcation section of the
Penstock pipe.
d. Transmission System
Walk over survey and desk study was conducted in the month of May for 132 kV transmission system
from Powerhouse at Thulibesi VDC up to Bandre village of Khudi VDC crossing the Marsyangdi River.
Feasibility study was conducted for a new alignment of double circuit transmission line for power
evacuation as NEA proposed Substation at Khudi Hub may not go under construction even at the start
of power generation of Nyadi HEP. Geologist, Environment Engineer and Electrical Engineer were
involved for this purpose. Total of 9.43 km length and 26 nos. of towers were finalized for new
alignment route.
Page 23 of 32
Figure 17: EOT Crane and its Accessories received at Site
Page 24 of 32
Figure 19: Walkover Survey for Transmission Line 132 kV
Page 25 of 32
7. Government Land Leasing and the purchase of the private land
NHL had received letter from Department of Land Management and Archive dated January 17, 2019 on
the waiver of land ceiling limit beyond 75 Ropanis as per the Ministry Level decision. NHL now, can retain
313 Ropanis of land in its ownership as mentioned in project IEE Report irrespective of Land Reform Act
by such relaxation to hydropower projects.
The lease of government land for 132kV transmission line in forest area of Nepal Government has now
been finally approved from the Cabinet of Ministers. The Department of Forest & Soil Conservation has
instructed NHL to sign a tripartite agreement between Department of National Park & Wild Life
Conservation and Department of Forest & Soil Conservation for leasing of forest land to NHL with other
necessary substantiating documents and which shall be executed by the end of June 2019.
Similarly, in respect of private land acquisition, adequate process has already been started and procurement
shall be completed by November 2019.
No. of
Expenses
S.N CSR Program Locals Location Status Remarks
In NPR.
Benefited
Year 2009
Electrical training 10
Mechanical training 10
390 hrs.
Project Affected
1 Plumbing training 5 7,51,000 Completed Training, held at
Areas
CTEVT
Mason training 15
Scaffolding training 15
Year 2017
Project Affected 390 hrs.
1 Electrical training 20 4,43,395 Completed Training, held at
Areas
CTEVT
Year 2018
390 hrs. Training
held at CTEVT.
NHL has
Scaffolding, sponsored 10
Project Affected
1 Welding and Mason 10 1,80,000 Completed out of 65
Areas
training trainees.
Organized by
Marsyangdi Rural
Municipality
Page 26 of 32
No. of
Expenses
S.N CSR Program Locals Location Status Remarks
In NPR.
Benefited
Page 27 of 32
No. of
Expenses
S.N CSR Program Locals Location Status Remarks
In NPR.
Benefited
Public Awareness
Program on World
3 Thulibesi 9 41,106 Completed
Environment Day
2076
4 Hydrology
5 General Hydraulics
Installed Capacity 30 MW
7 Diversion Weir
Crest length 14 m
12 Headrace tunnel
Length 3840 m
14 Surge Shaft
Page 28 of 32
Type Vertical shaft (Underground)
Connecting conduit size Circular with 3.2 m dia. and 2.80 m Height
16 Ventilation Adit
Length 30 m
17 Penstock
Diameter 1750 mm
18 Powerhouse
Type Surface
19 Tailrace Canal
Length 37.0 m
21 Turbines
No of units 2 Nos.
23 Transmission Line
6 km (Nyadi Switchyard to proposed 132 kV NEA Hub at
Length Marsyangdi Corridor)
Voltage 132 kV
25 Energy Generation
26 Access Road
From Marshyangdi Bridge at
Thakanbeshi to Headwork’s site 10.615 km
Page 29 of 32
Annex 2: Project Schedule
Page 30 of 32