WBS Activity Sequencing and Determining Resource Requirements
WBS Activity Sequencing and Determining Resource Requirements
Learning Outcomes
• On completion of this topic you should
The Work Breakdown be able to:
Structure, Activity • to identify all activities necessary to
Sequencing and achieve the goals and objectives of your
Determining Resource project.
Requirements • Display these activities by completion of
a Work Breakdown Structure.
• Schedule the activities
• Apply initial time estimates to the
activities.
1
18/07/2012
Goal
Predecess Duration Cost
Item Activity or (days) Resources $
Milestone 1 Milestone 2 Milestone 3
1 Team Selection
1.1 Draft notice prepared 3 Team members & others: x
WP WP WP WP WP WP WP WP WP 1.2 Final draft approved 1.1 1 Project sponsor -
1.1 1.2 1.3 2.1 2.2 2.3 3.1 3.2 3.3 Notice prepared and
1.3 posted 1.2 2 Clarabelle xx
xxx
2
18/07/2012
3.1 3.2
3
18/07/2012
Start-to-Start. Start-to-Finish.
• This relationship means Task A must • It requires that Task A start so that
start before Task B can start. Task B may finish.
• This relationship allows both activities to • Such relationships may be encountered
happen in tandem. in construction and manufacturing. It is
• The initiation of the successor activity also known as just-in-time (JIT)
depends upon the initiation of the scheduling. The completion of the
predecessor activity. successor activity depends upon the
initiation of the predecessor activity.
• This relationship is unusual and is
rarely used.
4
18/07/2012
5
18/07/2012
B
A C D
8 5 2
4
Finish
H
Start
F 3
9
E
2
G
6
18/07/2012
Page 2 DAY
Mon 10th
TIME DURATION
12 hrs
ACTIVITY
Travel
TRANSPORT
Plane
REQUIRE?
Ticket/visa
CATEGORY